spiral wall system.pdf

Upload: somdeb-banerjee

Post on 01-Mar-2016

35 views

Category:

Documents


0 download

TRANSCRIPT

  • SPIRAL WALL SYSTEM OF 2 X 660 MW

    1 | P a g e B y R o h i t

    A

    REPORT

    ON

    SPIRAL WALL SYSTEM OF 2 X 660 MW

    (BARH STPP STAGE-II)

    AT

    BHEL :PSER:BARH SITE

    Prepared By: Guided By:

    RohitManjhi Mr. S Chatterjee Engineer SDGM BHEL PSER Barh site BHEL PSER Barh site

  • SPIRAL WALL SYSTEM OF 2 X 660 MW

    2 | P a g e B y R o h i t

    Acknowledgement

    First and foremost, I would like to thank my guide for this report, Mr. Sumanta Chatterjee,

    Senior. Deputy General Manager, BHEL:PSER:BARH Site for his valuable guidance and

    wholehearted support in completing my report as well as enriching my knowledge. His advice

    from time to time has been very helpful; without which this report would not have been

    possible.

    Besides, I would like to thank my esteemed organization , BHEL for providing me with a good

    environment and facilities to complete this report. It was am opportunity to study and learn

    about various welding & NDE work , which are inevitable while erecting spiral wall system.

    Finally, I am grateful for the support which I have received from Mr. D Guha GM

    /Projects(Barh), Mr. M Prasad AGM, Our Technical associate ASTOM India Barh site &

    colleagues during this total exercise.

    Rohit Manjhi

  • SPIRAL WALL SYSTEM OF 2 X 660 MW

    3 | P a g e B y R o h i t

    Contents

    SL NO DESCRIPTION PAGE NO.

    1. Introduction 1-3

    2. Why do we use Spiral wall system 4- 4

    3. Detail of spiral-wall system 4-10

    4. Critical checks on spiral wall system 11-18

    5. References 19-19

  • SPIRAL WALL SYSTEM OF 2 X 660 MW

    1 | P a g e B y R o h i t

    1. Introduction Supercritical Boiler technology is gaining acceptance worldwide as Clean Coal Technology

    due to its significant advantages like higher overall plant efficiency, reduced coal

    consumption, reduced gaseous emissions like SO2, NO2 and CO2 and particulate

    emission. Large capacity units of size 600 to 1000 MW are now built up with supercritical

    parameters. In India, the trend is clearly towards large capacity Mega / Ultra Mega Power

    Projects based on supercritical technology. Evaporators of once through supercritical

    boilers are designed with either high mass flux spiral/vertical wall or low mass flux vertical

    wall.

    The major difference between a drum type boiler and once through supercritical boiler is the

    furnace wall design. An once through furnace wall design needs to take care of the

    temperature difference between tube-to-tube at furnace wall outlet due to the variation in

    furnace heat absorption. Also the occurrence of boiling crisis, associated metal

    temperatures need to be critically analyzed and taken care in the furnace wall design. There

    are basically two types of furnace wall designs used namely helically wound spiral wall and

    vertical wall. The design aspects of these two types of furnace wall are discussed in this

    paper.

    TEMPERATURE ENTROPY DIAGRAM OF SUPERCRITICAL RANKINE CYCLE

  • SPIRAL WALL SYSTEM OF 2 X 660 MW

    2 | P a g e B y R o h i t

    Key parameters of Super Critical Boiler at Barh

    Main steam flow 2120 T/hr

    SH steam pressure 255 kg/cm2

    SH steam temp. 568 deg centigrade

    Feedwater temp. 294 deg centigrade

    RH steam flow 1708 T/hr

    RH steam pressure 54.7 kg/cm2

    RH steam temp. 596 deg centigrade

    What are the key differences between the subcritical units and the Supercritical units?

    Efficiency

    The main advantage and the reason for a higher pressure operation is the increase in the

    thermodynamic efficiency of the Rankine cycle.

    Large Subcritical thermal power plants with 170 bar and 540 / 540 C (SH / RH) operate at

    an efficiency of 38 %. Supercritical units operating at approx 250 bar and 600/610 C can

    have efficiencies in the range of 42 %.

    Ultra supercritical units at 300 bar and 615 / 630 C will still increase the efficiency up to 44

    %.

    Increase in efficiency directly lead to reductions in unit cost of power and CO2 emissions.

  • SPIRAL WALL SYSTEM OF 2 X 660 MW

    3 | P a g e B y R o h i t

    Operational Flexibility

    Most of the Supercritical units use the once-through technology. This is ideal for sliding

    pressure operation which has much more flexibility in load changes and controlling the

    power grid.

    However this also requires more sensitive and quick responding control systems.

    Evaporation End Point

    In subcritical units the drum acts as a fixed evaporation end point. The furnace water walls

    act as the evaporator. Not so, in the case of a supercritical unit. The evaporation end point

    can occur in various levels of the furnace depending on the boiler load. The percentage of

    Superheat in supercritical units is higher than subcritical units. Because of this the furnace

    tubes act more as superheaters than waterwalls. This necessitates the use of higher grade

    of materials like alloy steels in the furnace.

    Heat transfer Area

    Higher steam temperatures in supercritical units results in a lesser differential temperature

    for heat transfer. Because of this, heat transfer areas required are higher than subcritical

    units.

    Higher Superheat steam temperatures entering the HP turbine also mean higher reheater

    inlet temperatures which again results in a higher heat transfer areas.

    Materials

    Supercritical power plants use special high grade materials for the boiler tubes. The turbine

    blades are also of improved design and materials. In fact, the very increase in higher

    pressure and temperature designs are dependent on the development of newer and newer

    alloys and tube materials.

    The aim of the industry is to achieve power plant efficiencies in the range of 50 %.

  • SPIRAL WALL SYSTEM OF 2 X 660 MW

    4 | P a g e B y R o h i t

    2. Why do we use spiral wall system:- i) Smaller OD tubes.

    ii) Helically wound spiral wall construction in which the tubes are inclined (15 to

    25 deg.) and furnace tubes pass through the circumference of the furnace

    more than one time and connected to a transition header above the burner

    zone. Above the transition header the furnace enclosure is made up of

    vertical water wall tubes. The spiral wall concept reduces the number of

    parallel tubes and hence increases the mass flux through the tubes. As all

    tubes pass through all the furnace walls, any variation in heat absorption is

    applicable to all these tubes and hence the temperature difference between

    these tubes is minimized.

    iii) To achieve reliable cooling, the mass flux generally adopted is around 2000

    kg/(m2s) at full load. It may be chosen higher for other reasons, e.g. to lower

    the minimum load for once through operation.

    iv) Smooth tubes are adequate, as the mass flux is high.

    v) By using spiral wall system total height of the boiler get reduced.

    3. Details of spiral wall system in 660 MW Barh stage II project:-

    Joints detail of spiral wall system as per FWS:-

    SL NO.

    MATERIAL SPEC.

    DIM(mm) PROCESS OF WELD

    NO. OF JOINTS

    ELECTRODE WPS NO.

    TIG ARC

    1 SA213 T22 + SA 213 T22

    Dia 41.3 + 41.3

    TIG & ARC 9498 ER90S B3

    E 9018-B3

    1031/01

    2 SA213 T22+ SA182 F12 CL2

    Dia 38.1 + 38.1

    TIG & ARC 1032 ER80S B2

    E 8018-B2

    1011/01

    3 SA106 GR.C+SA234 WPC

    Dia 406.4+ 406.4

    TIG & ARC 4 ER70S A1

    E 7018-A1

    1005/05

  • SPIRAL WALL SYSTEM OF 2 X 660 MW

    5 | P a g e B y R o h i t

    Sequence wise snapshot of spiral wall system at 2X660 MW Barh stage-II project.

    Assembly of transition header with terminal tubes at pre-assembly area

    Pre-assembly/Fit-up of spiral wall panel for matching confirmation

    Transition

    Header

    Term-Tube

  • SPIRAL WALL SYSTEM OF 2 X 660 MW

    6 | P a g e B y R o h i t

    Tube welding of transition header term tube with vertical water wall panel

    Pre-assembly of tension bar with spiral wall panel

  • SPIRAL WALL SYSTEM OF 2 X 660 MW

    7 | P a g e B y R o h i t

    Pre-assembled spiral wall panel ready for lifting after DP & sponge test

    Lifting of assembled right side spiral wall panel

    Tension Bar,

    Material-

    SA387 Gr 22

    Cl 2

    Thickness-

    30mm

    Scallop

    Bar,

    Material-

    SA387 Gr

    22 Cl 2

    Thickness-

    12 mm

  • SPIRAL WALL SYSTEM OF 2 X 660 MW

    8 | P a g e B y R o h i t

    Corner tube joints

    Assembly of sofa panel

    Buck stay

    fitted with

    stir-up

    system &

    spiral panel

    Tension bar

  • SPIRAL WALL SYSTEM OF 2 X 660 MW

    9 | P a g e B y R o h i t

    Burner panel fit-up at boiler-IV corner-1

    A view of bottom side Spiral wall system

  • SPIRAL WALL SYSTEM OF 2 X 660 MW

    10 | P a g e B y R o h i t

    Assembled bottom ring header with term tube

    Assembled bottom ring header with term tube

  • SPIRAL WALL SYSTEM OF 2 X 660 MW

    11 | P a g e B y R o h i t

    4. Critical checking of spiral wall panel SL

    NO.

    CHECKING DESCRIPTION CLASS OF

    CHECK

    TOLERENCE

    i Physical verification of header, panels,

    Tension bar, scallop bar etc.

    A As per FQP/Drawing

    Ii Measurement of materials as per

    FQP/drawing

    B Header(1mm/M),

    Panel(+2mm or -5mm)

    Iii Fit-up checking of tube joints, panel fin to

    fin joints, tension bar, Scallop bar.

    B Mismatch(2.5 mm)

    Iv Root gap checking of tube joints, panel fin

    to fin joints, TB & SB .

    B Tube(2 to 5mm),fin(3 mm),

    TB(3 to 4 mm)

    V Visual inspection of weld joints A As per ASME code & FQP,

    Reinforcement(0.5 to 4 mm)

    , weave(3X dia of electrode)

    Vi Nomenclature of weld joints. A As per FQP/drawing

    Vii DP test of weld joints as per FWS &FQP B As per FWS/FQP, 10% for

    TB,SB & fin (T-22 & T-12 )

    Viii Radiography test of weld joints as per FWS &FQP

    A Asper FQP/FWS, 20% RT

    Ix If found some discrepancy in the weld segment in RT/DP Test, required to do repair for the same & take RT/DP (as per requirement) for confirmation

    A As per ASME code & NDE MANUAL

    x PWHT/SR of applicable weld joints as per FWS

    A As per WPS (+ or 15 deg centigrade)

    Material Test Report of Tension Bar, Scallop Bar & Fins,

    Nomenclature of weld joints and Protocols of

    Radiography Test, Dye Penetration Test & Post Weld

    Heat Treatment are attached below:-

  • SPIRAL WALL SYSTEM OF 2 X 660 MW

    12 | P a g e B y R o h i t

  • SPIRAL WALL SYSTEM OF 2 X 660 MW

    13 | P a g e B y R o h i t

  • SPIRAL WALL SYSTEM OF 2 X 660 MW

    14 | P a g e B y R o h i t

    Nomenclature of weld joints

  • SPIRAL WALL SYSTEM OF 2 X 660 MW

    15 | P a g e B y R o h i t

  • SPIRAL WALL SYSTEM OF 2 X 660 MW

    16 | P a g e B y R o h i t

  • SPIRAL WALL SYSTEM OF 2 X 660 MW

    17 | P a g e B y R o h i t

  • SPIRAL WALL SYSTEM OF 2 X 660 MW

    18 | P a g e B y R o h i t

  • SPIRAL WALL SYSTEM OF 2 X 660 MW

    19 | P a g e B y R o h i t

    5. References:

    FWS of 2X660 MW Barh stage-II

    Approved drawing of Barh stage-II , Boiler unit-IV