SPM-UNIT II
ACTIVITY PLANNING
Prof. Kanchana Devi
![Page 2: Spm ap-network model-](https://reader031.vdocument.in/reader031/viewer/2022022202/5882eb151a28ab3f1e8b4691/html5/thumbnails/2.jpg)
Network Planning Models
Prof. Kanchana Devi
2
Scheduling techniques model the project’s activ ities and
their relationships as a “Network”.
In network time flows from left to right
These techniques were developed in 1950’s
There are two best techniques: CPM (Critical Path Method)
PERT (Program Evaluation Review Technique)
Both uses an “activity-on-arrow” approach
Activities are drawn as arrows joining circles, or nodes
Which show the start and completion time of the activities
![Page 3: Spm ap-network model-](https://reader031.vdocument.in/reader031/viewer/2022022202/5882eb151a28ab3f1e8b4691/html5/thumbnails/3.jpg)
Precedence Network
Prof. Kanchana Devi
3
Recently used , Popular one
It uses “activity-on-node” networks
Where activities are represented as nodes
Links between the nodes are represented as
sequencing requirements.
![Page 4: Spm ap-network model-](https://reader031.vdocument.in/reader031/viewer/2022022202/5882eb151a28ab3f1e8b4691/html5/thumbnails/4.jpg)
Formulating a Network Model
Prof. Kanchana Devi
4
First stage:
Representing the activities and their
relationships as graph.
In “Activity-on-node”
Representing the activities as nodes(boxes) and
the lines between nodes represent the
dependencies.
![Page 5: Spm ap-network model-](https://reader031.vdocument.in/reader031/viewer/2022022202/5882eb151a28ab3f1e8b4691/html5/thumbnails/5.jpg)
Rules: Constructing Precedence
Network
Prof. Kanchana Devi
5
A project network should have only one start node
A project network should have only one end node
A node has a duration
Links normally have no duration
Precedents are the immediate preceding activities
Time moves from left to right
A network may not contain loops
A network should not contain dangles
![Page 6: Spm ap-network model-](https://reader031.vdocument.in/reader031/viewer/2022022202/5882eb151a28ab3f1e8b4691/html5/thumbnails/6.jpg)
Fragment of precedence Network
Prof. Kanchana Devi
6
Install Program
Test
Data
Take-on
Code
![Page 7: Spm ap-network model-](https://reader031.vdocument.in/reader031/viewer/2022022202/5882eb151a28ab3f1e8b4691/html5/thumbnails/7.jpg)
A loop represents an impossible
sequence
Prof. Kanchana Devi
7
Code
Program
Release
Program
Test
Program
Diagnose
Errors
Correct
Errors
![Page 8: Spm ap-network model-](https://reader031.vdocument.in/reader031/viewer/2022022202/5882eb151a28ab3f1e8b4691/html5/thumbnails/8.jpg)
A Dangle
Prof. Kanchana Devi
8
Design
Program
Install
Program Test Program
Code
Program
Write User
Manual
![Page 9: Spm ap-network model-](https://reader031.vdocument.in/reader031/viewer/2022022202/5882eb151a28ab3f1e8b4691/html5/thumbnails/9.jpg)
Resolving the Dangle
Prof. Kanchana Devi
9
Design
Program
Install
Program
Test
Program
Code
Program
Write
User
Manual
Sign-Off
![Page 10: Spm ap-network model-](https://reader031.vdocument.in/reader031/viewer/2022022202/5882eb151a28ab3f1e8b4691/html5/thumbnails/10.jpg)
Representing Lagged Activities
Prof. Kanchana Devi
10
Undertake two activities in parallel as there
is a lag between two.
Activities are lagged because a stage in one
activity must be completed before the other
may proceed.
Show each stage as separate activity.
![Page 11: Spm ap-network model-](https://reader031.vdocument.in/reader031/viewer/2022022202/5882eb151a28ab3f1e8b4691/html5/thumbnails/11.jpg)
Adding Time Dimension
Prof. Kanchana Devi
11
Each activity have an estimate of its duration.
Forward pass – Earliest dates at which
activities may commence and project be
completed.
Backward pass – Latest start dates for
activities and critical path.
![Page 12: Spm ap-network model-](https://reader031.vdocument.in/reader031/viewer/2022022202/5882eb151a28ab3f1e8b4691/html5/thumbnails/12.jpg)
Project Specification
Prof. Kanchana Devi
12
![Page 13: Spm ap-network model-](https://reader031.vdocument.in/reader031/viewer/2022022202/5882eb151a28ab3f1e8b4691/html5/thumbnails/13.jpg)
Project Activity Network
Prof. Kanchana Devi
13
![Page 14: Spm ap-network model-](https://reader031.vdocument.in/reader031/viewer/2022022202/5882eb151a28ab3f1e8b4691/html5/thumbnails/14.jpg)
Project Activity Network
represented as CPM Network
Prof. Kanchana Devi
14
![Page 15: Spm ap-network model-](https://reader031.vdocument.in/reader031/viewer/2022022202/5882eb151a28ab3f1e8b4691/html5/thumbnails/15.jpg)
Dummy activities 15
When two paths within a network have a
common event to occur.
It is incorrect to require both hardware
specification and data structure design
![Page 16: Spm ap-network model-](https://reader031.vdocument.in/reader031/viewer/2022022202/5882eb151a28ab3f1e8b4691/html5/thumbnails/16.jpg)
Using Dummy Activities
Prof. Kanchana Devi
16
![Page 17: Spm ap-network model-](https://reader031.vdocument.in/reader031/viewer/2022022202/5882eb151a28ab3f1e8b4691/html5/thumbnails/17.jpg)
…….
Prof. Kanchana Devi
17
Dummy activities shown as dotted lines have
a zero duration and use no resources.
Use of dummy activity where two activities
share the same start and end nodes makes it
easier to distinguish activity end points.
![Page 18: Spm ap-network model-](https://reader031.vdocument.in/reader031/viewer/2022022202/5882eb151a28ab3f1e8b4691/html5/thumbnails/18.jpg)
Forward Pass
Prof. Kanchana Devi
18
Activity Duration
(Weeks)
Earliest Start
Date (Weeks)
Earliest Finish
Date(Weeks)
A 6 0 6
B 4 0 4
C 3 6 9
D 4 4 8
E 3 4 7
F 10 0 10
G 3 10 13
H 2 9 11
![Page 19: Spm ap-network model-](https://reader031.vdocument.in/reader031/viewer/2022022202/5882eb151a28ab3f1e8b4691/html5/thumbnails/19.jpg)
CPM Network
Prof. Kanchana Devi
19
![Page 20: Spm ap-network model-](https://reader031.vdocument.in/reader031/viewer/2022022202/5882eb151a28ab3f1e8b4691/html5/thumbnails/20.jpg)
A CPM Network after forward
pass
Prof. Kanchana Devi
20
![Page 21: Spm ap-network model-](https://reader031.vdocument.in/reader031/viewer/2022022202/5882eb151a28ab3f1e8b4691/html5/thumbnails/21.jpg)
Activity table for forward pass
Prof. Kanchana Devi
21
Activity Duration
(weeks)
Earliest
Start
Date
Latest
Start
Date
Earliest
Finish
Date
Latest
Finish
Date
Total
Float
A 6 0 6
B 4 0 4
C 3 6 9
D 4 4 8
E 3 4 7
F 10 0 10
G 3 10 13
H 2 9 11
![Page 22: Spm ap-network model-](https://reader031.vdocument.in/reader031/viewer/2022022202/5882eb151a28ab3f1e8b4691/html5/thumbnails/22.jpg)
Backward Pass
Prof. Kanchana Devi
22
![Page 23: Spm ap-network model-](https://reader031.vdocument.in/reader031/viewer/2022022202/5882eb151a28ab3f1e8b4691/html5/thumbnails/23.jpg)
CPM Network after the backward
pass
Prof. Kanchana Devi
23
![Page 24: Spm ap-network model-](https://reader031.vdocument.in/reader031/viewer/2022022202/5882eb151a28ab3f1e8b4691/html5/thumbnails/24.jpg)
Identifying the Critical Path
Prof. Kanchana Devi
24
Any delay on the critical path will delay the
project.
Difference between earliest and latest date
for an event is known as slack.
Event with slack of zero is critical as any
delay in achieving that event will delay the
completion date of the project.
![Page 25: Spm ap-network model-](https://reader031.vdocument.in/reader031/viewer/2022022202/5882eb151a28ab3f1e8b4691/html5/thumbnails/25.jpg)
Critical Path
Prof. Kanchana Devi
25
Event
Number
Latest
Date
Earliest
Date
Slack
![Page 26: Spm ap-network model-](https://reader031.vdocument.in/reader031/viewer/2022022202/5882eb151a28ab3f1e8b4691/html5/thumbnails/26.jpg)
Activity Float
Prof. Kanchana Devi
26
As events have slack, activities possess float.
Total float is the difference between earliest
start and latest start ( or difference between
earliest finish and latest finish)
![Page 27: Spm ap-network model-](https://reader031.vdocument.in/reader031/viewer/2022022202/5882eb151a28ab3f1e8b4691/html5/thumbnails/27.jpg)
Activity Schedule showing total
float for each activity
Prof. Kanchana Devi
27
![Page 28: Spm ap-network model-](https://reader031.vdocument.in/reader031/viewer/2022022202/5882eb151a28ab3f1e8b4691/html5/thumbnails/28.jpg)
Activity Schedule
Prof. Kanchana Devi
28
Actvity Name Time Actvity Name Time
1-2 A 4 5-6 G 4
1-3 B 1 5-7 H 8
2-4 C 1 6-8 I 1
3-4 D 1 7-8 J 2
3-5 E 6 8-10 K 5
4-9 F 5 9-10 L 7
![Page 29: Spm ap-network model-](https://reader031.vdocument.in/reader031/viewer/2022022202/5882eb151a28ab3f1e8b4691/html5/thumbnails/29.jpg)
Activity Network Diagram
Prof. Kanchana Devi
29
1
2
3 5
4
7
6
8
10 9
![Page 30: Spm ap-network model-](https://reader031.vdocument.in/reader031/viewer/2022022202/5882eb151a28ab3f1e8b4691/html5/thumbnails/30.jpg)
Solution
Prof. Kanchana Devi
30
Activity Activity
Name
Normal
Time
E.S E.F L.S L.F Total
Float
1-2 A 4 0 4 5 9 5
1-3 B 1 0 1 0 1 0
2-4 C 1 4 5 9 10 5
3-4 D 1 1 2 9 10 8
3-5 E 6 1 7 1 7 0
4-9 F 5 5 10 10 15 5
5-6 G 4 7 11 12 16 5
5-7 H 8 7 15 7 15 0
6-8 I 1 11 12 16 17 5
7-8 J 2 15 17 15 17 0
8-10 K 5 17 22 17 22 0
9-10 L 7 10 17 15 22 5
![Page 31: Spm ap-network model-](https://reader031.vdocument.in/reader031/viewer/2022022202/5882eb151a28ab3f1e8b4691/html5/thumbnails/31.jpg)
Problem 1
Prof. Kanchana Devi
31
Draw activity network of the project.
Find total float of each activity.
Activity Time in Weeks
1-2 20
1-3 25
2-3 10
2-4 12
3-4 5
3-5 10
![Page 32: Spm ap-network model-](https://reader031.vdocument.in/reader031/viewer/2022022202/5882eb151a28ab3f1e8b4691/html5/thumbnails/32.jpg)
Problem 2
Prof. Kanchana Devi
32
Find out the critical path and total float.
Activity Immediate
Predecessor
Time
A 3
B 8
C 5
D A 9
E C 2
F B,E 6
H B,E 12
G D 11