SRNS-MS-2014-00020 SRS Waste Program Update EFCOG WM Working Group Director, Solid Waste & F Area Operations John C. Gilmour Phoenix, AZ Waste Management Symposium Savannah River Nuclear Solutions, LLC March 6, 2014

Upload: dangmien

Post on 25-Mar-2018

221 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: SRS Waste Program Update EFCOG WM Working · PDF fileSRNS-MS-2014-00020 SRS Waste Program Update . EFCOG WM Working Group . Director, ... – Relocation of LCNDA system to reclaim

SRNS-MS-2014-00020

SRS Waste Program Update EFCOG WM Working Group

Director, Solid Waste & F Area Operations John C. Gilmour

Phoenix, AZ

Waste Management Symposium

Savannah River Nuclear Solutions, LLC March 6, 2014

Page 2: SRS Waste Program Update EFCOG WM Working · PDF fileSRNS-MS-2014-00020 SRS Waste Program Update . EFCOG WM Working Group . Director, ... – Relocation of LCNDA system to reclaim

SRNS-MS-2014-00020

E Area Solid Waste Management Facility

2

Page 3: SRS Waste Program Update EFCOG WM Working · PDF fileSRNS-MS-2014-00020 SRS Waste Program Update . EFCOG WM Working Group . Director, ... – Relocation of LCNDA system to reclaim

SRNS-MS-2014-00020

Accomplishments

• Remediation activities on legacy TRU complete • Made 159 legacy TRU shipments to WIPP • Disposed ~100 m3 of MLLW • Disposed ~5,000 m3 of LLW • Started disposal operations in new Engineered Trench

3

Page 4: SRS Waste Program Update EFCOG WM Working · PDF fileSRNS-MS-2014-00020 SRS Waste Program Update . EFCOG WM Working Group . Director, ... – Relocation of LCNDA system to reclaim

SRNS-MS-2014-00020

FY14 Outlook

4

• Expected budget for year is $47M • Complete certification of remaining legacy TRU waste • Complete shipment of mixed waste from legacy TRU • Initiate RCRA closure of TRU Pad 16 • Continue shipping legacy TRU once WIPP reopens

~10 TRUPACT-III shipments needed ~60 TRUPACT-II shipments needed ~55 Remote Handled 72-B shipments needed

Page 5: SRS Waste Program Update EFCOG WM Working · PDF fileSRNS-MS-2014-00020 SRS Waste Program Update . EFCOG WM Working Group . Director, ... – Relocation of LCNDA system to reclaim

SRNS-MS-2014-00020

FY14 Challenges

• Competing with Site Infrastructure for limited funds – Disposition of excess chemical backlog – Relocation of LCNDA system to reclaim HW/MW storage pad – D&R of legacy TRU processing equipment in E Area

• Maintaining qualified shipping resources during WIPP outage

5

Page 6: SRS Waste Program Update EFCOG WM Working · PDF fileSRNS-MS-2014-00020 SRS Waste Program Update . EFCOG WM Working Group . Director, ... – Relocation of LCNDA system to reclaim

SRNS-MS-2014-00020

FY15 Outlook

• Expected budget is $43M • Complete RCRA Closure of TRU Pad 16 • Complete legacy TRU shipments to WIPP • Continue to compete with Infrastructure for funding

6