staj gardaşım (5)
TRANSCRIPT
7/29/2019 staj gardaşım (5)
http://slidepdf.com/reader/full/staj-gardasim-5 1/19
1
SUMMER TRAINING
NAME : SEMİH TUNÇ
ID :21003139
DEPARTMANT : ELECTRIC- ELECTRONIK ENG
CAMPANY : EUAŞ (BURSA DOĞAL GAZ ELEKTRİK ÇEVRİM)
ADRESS : Pc.41 16105 Gençosman - Osmangazi, Bursa
DATES OF PRACTİSE : 18.07.2011 – 12.08.2011
7/29/2019 staj gardaşım (5)
http://slidepdf.com/reader/full/staj-gardasim-5 2/19
2
TABLE OF CONTENTS
1.INTRODUCTION
1.1.PURPOSE OF THE POWER PLANT
1.2.LOCATİON
1.3.GENERAL INFORMATION ABOUT THE POWER PLANT
1.4.ORGANIZATION CHART
2.PRODUCTION
2.1 PRODUCTION SYSTEM
2.1.1 Gas Turbines
2.1.2 Steam Turbines
2.2 ANNUAL GENERATION
3.WORK DONE
3.1 RESEARCH
3.1.1 SCADA SYSTEM
3.1.1.2 PID CONTROLLER
3.1.2 SWITCHYARD
3.2 TEST AND CONTROL
3.2.1 DIESEL GENERATOR
3.2.2 OIL PUMP
3.2.3WATER PUMP
3.2.4 AUXILERY ENERGY UNIT
4. CONCLUSION
5.REFRENCES
7/29/2019 staj gardaşım (5)
http://slidepdf.com/reader/full/staj-gardasim-5 3/19
3
1. INTRDUCTION
This report contain 3 main part first introduction where I am going to give some
fundamental information about the power plant. Then in the second part which is production
I am going to give some significant information about how they produce the electric. Finally
at the last part I am going to tell what I have done in power plant in my working days.
Before all I want to do my internship program in energy sector because it is a rapidly
increasing sector in Turkey .İt is increasing due to technological improvements and increasing
population. Since the population and technology increase companies are run up their
investment on energy sector. In parallel with this, I apply Electricity Generation Incorporated
Company Bursa Natural Gas Fired Combined Cycle Power Plant Operational Management
for an internship position. Then, I have been accepted for an internship position. Then I have
successfully finished my summer practice in two different departments. First electric
maintance then test and control department.
7/29/2019 staj gardaşım (5)
http://slidepdf.com/reader/full/staj-gardasim-5 4/19
4
1.1 . Purpose of the Power Plant
a) Meeting of electric energy demand of Bursa region and South Marmara in economical
ways with minimum electrical loss and minimum cost.Due to the increasing number of
people and growing industry in Marmara region and especially in Bursa city
government had to do something and they decide to establish the natural gas fired
combined cycle power plant operational management to correspond the energy
demand .
b) Provide with uninterrupted electricity to the industrial enterprises.
There are 3 industrial regions in Bursa and thus they haven’t got a bility to produce
their own energy they need to be provided by a uninterrupted electricity. The
industrial regions are DOSAB (demirtaşsanayibölegesi ) which is the nearest place to
power plant. BOSB (BURSA ORGANİZE SANAYİ BÖLGESİ) küçüksanayi(
bursabeşevlersanayisitesi)
c) Reduction of electric loss due to the power transmission lines.
d) Meeting of predicted electric energy deficit for following years.
e )Employment opportunities for increasing population growth.
7/29/2019 staj gardaşım (5)
http://slidepdf.com/reader/full/staj-gardasim-5 5/19
5
1.2 Location
There were 16 possible areas were determined in Bursa to establish the power plant
respect to following criteria and after 1 year research Bursa commission select the Ovaakça
plain.
a) Geological conditions
b) Close to natural pipe line
c) Close to consumption area ( ındustrial regions)
d) Transportation state
e) Soil and agricultural features
f) Cooling water conditions
g)
Topographical state
h) Closeness to 154 kV transformer station
7/29/2019 staj gardaşım (5)
http://slidepdf.com/reader/full/staj-gardasim-5 6/19
6
1.3 General Information about Power Plant
Bursa Natural Gas Cycles Main Units
Gas turbines (2 for each block)
Heat recovery boilers
Steam turbine (1 for each block)
Cooling water and steam condensation system
Water demineralization system
Switchyard and electric systems
Control and command systems
Bursa natural gas cycle power plant contain two symmetric block and each blocks are
consisted of two gas turbines and a steam turbine and each block produces 705 MW/h and
there are two cooling towers which are working for cooling the circulation water. They are
cooled water naturally due to the hyperbolic shape.
7/29/2019 staj gardaşım (5)
http://slidepdf.com/reader/full/staj-gardasim-5 7/19
7
Gas turbines use natural gas to generate electricity and at the end of the burning session
steam comes out with 1350 C’ and this steam use for again generating electricity from steam
turbine.
A gas turbine consumes 68.000 Sm³ / h natural gas so four units consume 270 000 Sm³ / h
natural gas. At maximum load two gas turbines + one steam turbine which has 8100 kCal /
Sm³ heat value, work with 1564 kCal / kWh. Its efficiency is %55.
1.4 ORGANIZATION CHART
7/29/2019 staj gardaşım (5)
http://slidepdf.com/reader/full/staj-gardasim-5 8/19
8
7/29/2019 staj gardaşım (5)
http://slidepdf.com/reader/full/staj-gardasim-5 9/19
9
2.PRODUCTION
2.1 Production System
2.1.1. Gas Turbines
Bursa Natural Gas Combined Cycle contain two symmetric blocks. Each has two gas
turbines and generator units and one steam turbine and its generator unit. Gas turbines can
generate 239 MWh and its worked with 50 hz which means 3000 revolution per minute. After
this air combines with natural gas which is 200c and 40 bars, it goes to combustor. Then a
combustion gas which is 1.350C goes to four level gas turbine blades thus turbine rotor is
rotated. The turbine rotor is coupled with generator rotor so at the same time also generator
rotor is rotated.
At each block there are two heat recovery boilers. They have three phases which are low
pressure , medium pressure and high pressure . They use 3 phase because they want to
increase the efficiency of the power plant with using all phase of steam. Heat recovery boilers
consist of deaeratordom super-heater and cold-heater and economizer.
COLD-
HEATER
DEAERATOR ECONOMIZER DOM
SUPER HEATER
EVAPORATOR
Steam Turbine
7/29/2019 staj gardaşım (5)
http://slidepdf.com/reader/full/staj-gardasim-5 10/19
10
2.1.2. Steam Turbine
After gas turbines done their jobs. They obtain air which is at 1350 C and ıf they let it
go to the nature we might face with lots of natural problem. They don’t let it go and moreover
they use this air to obtain some new electricity from steam turbine. Steam turbine can
generate 237 MW/h of electricity with 50 hz revolution. Steam turbine has three pressure
phase high pressure medium pressure and low pressure.They use this three phase to use the
potential energy more efficiently. At the end of the gas turbines work the air reduces its heat
to 100C. There are 2 steam turbine they obtain 237*2 MW/h =474MW/h which corresponds
to %33 energy of total power plant .They don’t waste any energy however efficiency is not
more than %55.
2.2 ANNUAL GENERATION
As I have already mentioned in Bursa power plant there are 2 symetric block and each
block has two gas turbines and one steam turbine. Gas turbines generate 232 MW/h each and
steam turbine 237MW/h totally one block can generate 704MW/h and since there are two
blocks the power plant can generate 704*2=1408 MW/h. When Bursa Power Plant
established it can provided %8 energy of Turkey however now it can only provide %3.5
nearly %4.That means energy sector growing significantly fast.
7/29/2019 staj gardaşım (5)
http://slidepdf.com/reader/full/staj-gardasim-5 11/19
11
Voltage output of the power plant is 13.08 KV and there are two types of transmition
line one is 154 kV which they use this line to transfer energy to a closer place like Gemlik,
Göktaş, Demirtaş and other is 380kV which they use for far centers like
Adapazarı,Tepeören(Istanbul) and İçtaş (Çanakkale).They use 380kV for far centers because
since the Voltage is high current will small and if current small energy loss will be smaller.
Gemlik, Göktaş, Demirtaş, AsılÇelik, Otosansit 1 ve 2 and Bursa SanayiSitesi are
supplied by 154 kV’s bus and Adapazarı, Bursa SanayiSitesi, Tepeören and İçtaş (Çanakkale)
are supplied by 380 kV’s bus.
Energy production in natural gas power plants can change regarding to other types of
power plants energy production to illustrate this in summer you may not find water to
produce energy in hydro-electric power plants and you need to fill this gap with other types
of power plant so you need to use natural gas power plant and in the winter citizens demand
more natural gas due to that natural gas power plants doesn’t produce a lot energy . As you
can observe from the generation chart energy production showing big differences year to year
because government does not want to use natural gas power plant because natural gas is
coming from other countries like Russia and Iran. theYEARS PRODUCTION(MWh)
1999 4.769.421
2000 9.149.350
2001 10.654.140
2002 8.589.123
2003 3.097.4402004 764.917
2005 2.384.187
2006 5.008.734
2007 8.110.871
2008 8.956.289
2009 8.478.411
2010 7.097.587
7/29/2019 staj gardaşım (5)
http://slidepdf.com/reader/full/staj-gardasim-5 12/19
12
3.Work Done
3.1 RESEARCH
3.1.1 SCADA SYSTEM
Scada control system is the most significant thing in Bursa Power Plant it is a data
acquisition system. By using this system without human hand you can control the
following things.
a) Monitoring generated energy
b) Control cooling towers and cooling water
c) Control gas turbine and steam turbine energy generation
d) Control substance they add to obtain pure water
e) Control water pumps and oil pumps
f) Control transformers
g) Finally works done in real time without any significant delay
Scada system done all these jobs with the help of sensors and PID system
which I m going to explain below.
Part of Scada System
3.1.1.1 PID System
A proportional – integral – derivative controller (PID controller) is a generic control
loop feedback mechanism (controller) widely used in industrial control systems – a PID is the
most commonly used feedback controller. A PID controller calculates an "error" value as the
difference between a measured process variable and a desired setpoint. The controller
attempts to minimize the error by adjusting the process control inputs.The PID controller
calculation (algorithm) involves three separate constant parameters, and is accordingly
7/29/2019 staj gardaşım (5)
http://slidepdf.com/reader/full/staj-gardasim-5 13/19
13
sometimes called three-term control: the proportional, the integral and derivative values,
denoted P, I, and D. Heuristically, these values can be interpreted in terms of time: P depends
on the present error, I on the accumulation of past errors, and D is a prediction
of future errors, based on current rate of change.[1] The weighted sum of these three actions is
used to adjust the process via a control element such as the position of a control valve, or the
power supplied to a heating element.
In the absence of knowledge of the underlying process, a PID controller has historically been
considered to be the best controller .[2] By tuning the three parameters in the PID controller
algorithm, the controller can provide control action designed for specific process
requirements. The response of the controller can be described in terms of the responsiveness
of the controller to an error, the degree to which the controller overshoots the setpoint and the
degree of system oscillation. Note that the use of the PID algorithm for control does not
guarantee optimal control of the system or system stability.Some applications may require
using only one or two actions to provide the appropriate system control. This is achieved by
setting the other parameters to zero. A PID controller will be called a PI, PD, P or I controller
in the absence of the respective control actions. PI controllers are fairly common, since
derivative action is sensitive to measurement noise, whereas the absence of an integral term
may prevent the system from reaching its target value due to the control action
7/29/2019 staj gardaşım (5)
http://slidepdf.com/reader/full/staj-gardasim-5 14/19
14
Physical systems
Scada system physical events are temperature ,pressure and velocity . At this part
simply sensors convert analog data that they ve taken and convert in to digital data and finally
these data are computerized.
Signal Processing
This system is used to increase the quality of signals which are made by sensors.
Some way of this processing is scaling, linearization, filtering and amplification. The systems
which are based on PC generally use amplification in order to make signal clear.
Data Collection and Control Equipment
Control equipment has some units and cards which is placed on PC bearing element.
Some of the units are CPU, operating system, analog input and output, counter and timer,
programmable amplifier, memory and buffer memory.
In order to evaluate, screen and save the data which are collected, they should be
transferred to PC. The crucial point is that if we assume that our card is programmed for
converting every second, when card makes analog to digital conversion, it should transfer the
data immediately.
7/29/2019 staj gardaşım (5)
http://slidepdf.com/reader/full/staj-gardasim-5 15/19
15
3.1.2 Research Switchyard
Although we are not allowed to get in to switchyard without any engineer it is one of
the most significant part of the power plant. Thus I haven’t taken any lesson about power
electric devices I didn’t know anything about switchyard .
Switchyards consist of of selectors, breakers(Even if there is a short circuit condition,
it interrupts circuit under load condition), busbars(is a conductor and it is used to
communication of equipments which control and conduct electrical energy.) and auxiliary
accoutrements that I am going to explain below. Bursa power plants switchyard consist of two blocks 154 Kv and 380 Kv First part is fed by first block of the plant which has gas turbine
11-12 and steam turbine 1. Second part is fed by second block of the plant which has gas
turbine 21-22, steam turbine 2. Maneuver is done by order of dispatching center. There are
current and voltage transformers (decreases high voltage and phase difference is close to zero.
AC voltage leads to current on primary winding. This current triggers magnetic flux and with
the effect of this flux, voltage is occurred on secondary winding), surge arresters, insulators
and conservation wires in the first and second parts.
Output of the plant is 13.8 kV and by using transformers it converts to 154 kV and 380
kV and in order to make 154 kV / 380 kV and 380 kV / 154 .
.
7/29/2019 staj gardaşım (5)
http://slidepdf.com/reader/full/staj-gardasim-5 16/19
16
3.2 TEST AND CONTROL
3.2.1 Diesel Generator Test
Diesel generator is working for to generate 14MW .It is tested twice in a month. Its
purpose is when 154 kV and 380 kV transmission lines are disabled diesel generator
supplies electricity in order to feed where it need.
In this test we focus on the electrical values and mechanical values. Electrical values
are AC voltages , current , power , and power factor. Mechanicals are oil temperature
water temperature.
Test includes two parts with load and without load. In load part excessive vibration is
occurred due to incompatibility of freq. Load part takes 4 minutes and other part takes 10
minutes and after 5 minutes test is terminated then engineers decided to order new
governor card which adjust controlling of the primary frequency automatically.
3.2.2Control Oil Pump
Oil pump has one significant purpose in the power plant. It cools the mechanical
devices running part. Like transformers or gas turbine . Controlling oil pump system
contain two important main and auxiliary oil pump .For controlling oil pump fault signal
is warned because of excessive vibration. Engineers deactivate this unit and activate
auxiliary oil pump.
7/29/2019 staj gardaşım (5)
http://slidepdf.com/reader/full/staj-gardasim-5 17/19
17
We have made some test like temperature control with thermal cameras and current
test after those test we have noticed that oil temperature is too high . So device is need to
maintenance immediately.
3.2.3Water Pump Test
We can split the water pumps in to two main and auxiliary water pumps. Main water
pump can be splited in to three low pressure high pressure and medium pressure . Simply
they are working for to use the 3 phase of the steam and increase the efficiency of the
energy. If there is a problem on main water pumps auxiliary pumps starts to work .
The water pumps should be tested twice in a month. Test is splited in to two first main
pump test second auxiliary pump test. In this test engineers measure the pressure level of
each different pressure level and decide if they make pressure enough or not. While they
were making the test they got help from scada system for measuring the pressure levels.
Finally they decide that there is no problem on water pumps.
3.2.4 AUXILIARY ENERGY UNIT
Normally the energy that power plant produces feed the facilities of the Bursa Power
Plant and as you can guess there are some places which need energy without any
corruption like first aid room or fire department. For this purpose there is a energy unit
which is consisted of batteries. There always 1MW energy store in this unit. Energy unit
is charged by the power plant when plant is online and it is simply feed the power plants
significant places The energy unit is tested frequently once in a month.
7/29/2019 staj gardaşım (5)
http://slidepdf.com/reader/full/staj-gardasim-5 18/19
18
Test contain just one part, engineers corrupt the energy which feed the facilities of the
power plant than they will test if auxiliary unit feed the significant rooms or not. Finally
they observe that there is no problem with auxiliary unit.
4. CONCLUSION
First of all ıt was my first experience on real engineering working area. I was very curious
about electric and electronic engineering applications. I have learned lots of things about how
a natural gas power plants works and how energy is transmitted to us.
In my first ten days I read manual of the power plant however it was too complicated and
too advance for me. So I started to search what I had wanted to learn, from internet and I
asked lots of question to my supervisor engineer OrhanKüçük. Thus they are not in revision
he had many time to explain how power plant works. Every day we went some part of power
plant and he explained how things work. Mostly I have worked on how gas turbines and
steam turbines works. I haven’t tak en power electronic and power electronic devices lessons
in Bilkent University so I need to study some lessons which I have never seen before. I guess
it has been beneficial for me. After that my supervisor took me to the switchyard and explain
which device work for what .
In my last ten days I changed my department and I transferred to testing and
controlling department. In this department I spent most of my time with technicians and I
tried to learn technical parts. I have learned how scada system works and I have worked on
PID systems.
To sum up I have done my summer practice frankly I has been beneficial for me in
terms of engineering knowledge. I had a change to experiment what I have learned in my
lessons.
7/29/2019 staj gardaşım (5)
http://slidepdf.com/reader/full/staj-gardasim-5 19/19
19
5. References
[1] This graph is taken from EVD Energy Efficiency Consulting
[2]This graph is taken from EVD Energy Efficiency Consulting
[3] This flow diagram is taken from information notes about the power plant
[4]This flow diagram is taken from information notes about the power plant
[5] http://en.wikipedia.org/wiki/File:Pid-feedback-nct-int-correct.png
[6] This graph is taken from EVD Energy Efficiency Consulting
Sources which I used indicated below;
a) Electricity Generation Incorporated Company Bursa Natural Gas Fired CombinedCycle Power Plant Operational Management sources especially General Information
Notes.
b) J.Kuffel, E.Kuffel, W. Zaengl, High Voltage Engineering Fundamentals