Agenda WinWin Negotations – What/Why? The ‘science’ of decision making – what, why and how? The role of decision making in Value Based Requirements Engineering & Prioritization (VBRE/RP) Importance of ‘Planning’ VBRP – what, why & how? Practical Example

TRANSCRIPT

Page 1: Stakeholder WinWin And Requirements Prioritization Nupul Kukreja 19 th October 2015 1

1

Stakeholder WinWin And

Requirements Prioritization

Nupul Kukreja19th October 2015

Page 2: Stakeholder WinWin And Requirements Prioritization Nupul Kukreja 19 th October 2015 1
Page 3: Stakeholder WinWin And Requirements Prioritization Nupul Kukreja 19 th October 2015 1

Agenda• WinWin Negotations – What/Why?• The ‘science’ of decision making – what, why

and how?• The role of decision making in Value Based

Requirements Engineering & Prioritization (VBRE/RP)

• Importance of ‘Planning’• VBRP – what, why & how?• Practical Example

Page 4: Stakeholder WinWin And Requirements Prioritization Nupul Kukreja 19 th October 2015 1

Will You Buy The Car?Picture the following dialogue between youand a car salesperson:

You: I’d like to buy the fully loaded Honda Accord, for $25,500. I’ve done my homework. That’s the best price!

Salesperson: You got it! Deal! Let’s finish the paper work.

Page 5: Stakeholder WinWin And Requirements Prioritization Nupul Kukreja 19 th October 2015 1

Negotiation• Negotiation is traditionally viewed as a win-

lose game between two parties• Even if you bought the car on your terms,

you’d still feel you left something on the table• You’d feel it was too easy!• Moral:

– DON’T say “YES” to everything– DON’T say “NO” to everything either

• Than what do you say?

Page 6: Stakeholder WinWin And Requirements Prioritization Nupul Kukreja 19 th October 2015 1

WinWin Negotiations• Negotiation, especially when multiple success

critical stakeholders are involved should never be “Win-Lose”

• There should always be a “WinWin” – even if one party feels they’re losing, they’ll “flip” the winners in their favor over time Lose-Lose

• WinWin != Satisfying Everyone• WinWin == Satisficing Everyone (It’s different)How’s it done?

Page 7: Stakeholder WinWin And Requirements Prioritization Nupul Kukreja 19 th October 2015 1

7

Win ConditionWin Condition

AgreementAgreement OptionOption

I ssueI ssueinvolves

addresses

adopts

covers

WinWin Taxonomy (a.k.a. WIOA Model)

Win-Win Equilibrium:• All win conditions covered

by agreements• No outstanding issues

Win Condition: Stakeholders’ desired objectives stated in a form understandable by users, customers and other stakeholders and formalized only where necessaryIssue: captures conflicts between win conditions and their associated risks and uncertaintiesOption: candidate solutions to resolve an issueAgreement: captures shared commitment of stakeholders with regard to accepted win conditions or adopted options

Page 8: Stakeholder WinWin And Requirements Prioritization Nupul Kukreja 19 th October 2015 1

8

We also capture a 3rd dimension of “Relative Penalty” – Degree of project failure if WC not deilvered

1. Refine and expand negotiation topics2. Collect stakeholders’ win conditions3. Converge on win conditions4. Define glossary of key terms5. Prioritize win conditions on:

Business Value vs. Ease of Realization6. Reveal issues and constraints7. Record issues and options8. Negotiate agreements

WinWin Negotiation Primer

Shared taxonomy of topics to understand project scope

Record first draft of stakeholder’s needs/wants for all to view

Disambiguation and de-duplication

Domain vocabulary to develop mutual understanding

Degree of project success dependent on win condition

Technological, social, political or economic feasibility

Variance in prioritization provokes discussion of issues/constraintsIssues recorded along with possible resolution tactics

Mutually agree to win conditions/optionsAbove steps accelerated by a “Shaper” i.e. a facilitator who guides the negotiation

Page 9: Stakeholder WinWin And Requirements Prioritization Nupul Kukreja 19 th October 2015 1

10

WinWin Equilibrium• The state when:

– All Win Conditions have been covered by agreements – No outstanding issues

• Provides a ‘heat map’ of the current state of negotiations:– RED: Win Conditions (WC)/Options not agreed to or issue not

closed– GREEN: WCs/Options agreed to or issues closed– YELLOW/AMBER: WCs/Options marked as candidates for

‘potential agreement’ further discussion may be required• Winbook provides capability to ‘see’ this heat map!• Every new feature request, expectation, benefit MUST BE

LOGGED into Winbook – helps in having an up to date view of the ‘heat’ map w.r.t., the current state of negotiations

Page 10: Stakeholder WinWin And Requirements Prioritization Nupul Kukreja 19 th October 2015 1

11

Winbook and WinWin Negotiations• Based on the WinWin Negotiation Framework and directly

supports the WIOA Model• Winbook is a tool to ‘log’ the negotiation and show its ‘status’

as function of time• “Functional” Win Conditions to be captured in the user-story

format (As a <role>, I can <activity> so that <business value>)• Dynamic prioritization of win conditions with sensitivity

analysis capability• Winbook Tutorial available on CS577 class-website under

“Tools & Tutorials”• WinWin Sessions are HUMAN centric and highly iterative. A

tool like Winbook only helps ‘document/augment’ the process and not execute it

Page 11: Stakeholder WinWin And Requirements Prioritization Nupul Kukreja 19 th October 2015 1

WHAT NEXT?Negotiations over…

Page 12: Stakeholder WinWin And Requirements Prioritization Nupul Kukreja 19 th October 2015 1

13

Insightful Questions• Given N requirements and budget/schedule

constraints which ones to implement?• Which test cases should I run given time

constraints?• What programming language should I choose?• Which design should I choose?• What framework should I choose?• What architecture should I choose?• Which project(s) should we choose?• Heck! How do I choose anything?

Page 13: Stakeholder WinWin And Requirements Prioritization Nupul Kukreja 19 th October 2015 1

14

Decision Making – What?Definition:*

• Decision making can be regarded as the mental processes (cognitive process) resulting in the selection of a course of action among several alternative scenarios

• Every decision making process produces a final choice

• The output can be an action or an opinion of choice.

*Courtesy: http://en.wikipedia.org/wiki/Decision_making

Page 14: Stakeholder WinWin And Requirements Prioritization Nupul Kukreja 19 th October 2015 1

15

Decision Making – Making a ChoiceWhich apartment do you want to live in?

Page 15: Stakeholder WinWin And Requirements Prioritization Nupul Kukreja 19 th October 2015 1

16

Making a Choice – How?• So, just how did you choose your apartment?• What all did you ‘see’ / evaluate before signing

the lease?• Examples of possible criteria:

– Rent per month– Location i.e., quality of area– Proximity to campus– Presence of a good looking neighbor – …and probably several others

Page 16: Stakeholder WinWin And Requirements Prioritization Nupul Kukreja 19 th October 2015 1

17

Analyzing the ‘Problem’• You have the two key ingredients necessary for a

decision problem:– A list of criteria– A set of alternatives

• Problem: Given a list of criteria AND a set of alternatives select the alternative that best suits the given criteria

Decision Analysis

Criteria

Alternatives

Rank ordered set of alternatives

Apartment Selection

Rank ordered set of apartments

Page 17: Stakeholder WinWin And Requirements Prioritization Nupul Kukreja 19 th October 2015 1

18

Decision Making – Why Bother?• Converts ‘art’ into science

– Adds rigor to the act of decision making• Justification of choice of action i.e., why you

chose what you chose?– Helps decrease legal liability

Ex.: Why did Company A select the bid/tender of Company X over Y? (It’s not only cost )

• Documents the institutional memory that lead to that particular decision (i.e., helps trace back to provide justification of decision)

Page 18: Stakeholder WinWin And Requirements Prioritization Nupul Kukreja 19 th October 2015 1

19

Decision Making – How do you do it?• If it is a well studied science (it is) does anything

exist ‘out there’ to help practice this ‘science’?• There are various techniques that can be

employed:– Multi-attribute utility theory (ISE 562 in Fall)– Analytical Hierarchy Process (AHP)– Simple Additive Weighting (SAW)– TOPSIS (Technique of Ordered Preference by

Similarity to Ideal Solution)– …and many more (http://en.wikipedia.org/wiki/MCDA#MCDM_Methods

)

Page 19: Stakeholder WinWin And Requirements Prioritization Nupul Kukreja 19 th October 2015 1

20

Decision Problem – Look and Feel

Criterion 1

Criterion 2

Criterion 3 … Criterion

N

Alternative 1 S11 S12 S13 … S1N

Alternative 2 S21 S22 S23 … S2N

Alternative 3 S31 S32 S33 … S3N

… … … … … …

Alternative N SN1 SN2 SN3 … SNN

Sij = Measure of how well Alternative ‘i‘ does on Criterion ‘j’

Almost always has a matrix-like representation:

When considering multiple criteria in decision making the problem is often referred to as

“Multiple Criteria Decision Analysis” (MCDA) or “Multiple Criteria Decision Making” (MCDM)

Page 20: Stakeholder WinWin And Requirements Prioritization Nupul Kukreja 19 th October 2015 1

21

Okay, Great! But what has any of it got to do with VBSE?

• Everything!! • How do you decide:

Which requirement to implement first?Which component to design first?Which architectural style/pattern to use?Which requirements to test first?Which test-cases form part of the regression

suite?What all to prototype first?For which component to write the “first line of

code”?

ControlTheory

Page 21: Stakeholder WinWin And Requirements Prioritization Nupul Kukreja 19 th October 2015 1

22

Wait! But I’ve already done all of this before and I got it right too!

• Probably! However…• Were you able to justify your choice i.e., how

you came about choosing a specific option?– Was there ever a need to do so?

• Just “how” did you decide?– Perhaps intuition, gut feel, domain knowledge,

tossing a coin, do as the Romans do…• Yes, a simple 1-10 works or even MoSCoW

(Must, Should, Could, Would – have) but for relatively simple problems

Page 22: Stakeholder WinWin And Requirements Prioritization Nupul Kukreja 19 th October 2015 1

23

PLANNING

Page 23: Stakeholder WinWin And Requirements Prioritization Nupul Kukreja 19 th October 2015 1

24

Planning and Decision Making• What do we work on now?• What do we work on next?• How much money can/should we spend?• How much is being spent?• Are the risks being monitored/mitigated?• How does risk impact the plan?

Important to plan around ‘value’

Page 24: Stakeholder WinWin And Requirements Prioritization Nupul Kukreja 19 th October 2015 1

25

Purpose of ‘Planning’*• Why do we do it?

– Reduce risk & uncertainty– Supporting better decision making– Establishing trust (i.e. frequent delivery)– Conveying expectations

• Planning is a ‘quest for value’– Attempt to find an optimal solution of the overall

product development question: What should be built?

*Agile Estimation & Planning – Mike Cohn

Page 25: Stakeholder WinWin And Requirements Prioritization Nupul Kukreja 19 th October 2015 1

26

A Good Plan• One that stakeholders find sufficiently reliable• One that can be used as basis for decision

making– Approximate time to market– An idea of the set of features

• Made more precise as project moves on• Is a ‘living’ artifact showing the current status

of the project to avoid last minute surprises• Is planned around ‘value’

Page 26: Stakeholder WinWin And Requirements Prioritization Nupul Kukreja 19 th October 2015 1

27

Planning for ‘Value’*• Stakeholders needs must be understood• Just delivering features is not important

– Necessary to balance scope, schedule, cost and value of features comprising the release

• Various factors impacting prioritization– Financial value of having the features– Cost of development– Amount/significance of new knowledge

• Product (what)• Project (how)

– Reducing Risk (Business/Technical)• Schedule• Cost• Functionality

*Agile Estimation & Planning – Mike Cohn

Page 27: Stakeholder WinWin And Requirements Prioritization Nupul Kukreja 19 th October 2015 1

28

Decision Making and Planning for Value• Decision analysis techniques can be ‘overloaded’

to perform requirements prioritization…• …the rank-ordered output of decision making

techniques could also rank-order requirements!• Requirements prioritized against the

goals/needs/values of the stakeholders VBRP

• The prioritized requirements form the basis of the ‘plan’ – what is being delivered, for how much and by when?

Page 28: Stakeholder WinWin And Requirements Prioritization Nupul Kukreja 19 th October 2015 1

29

The ‘Dimensions’ of Value• Value is a multi-dimensional quantity, a simple 1-10 may

not cut it (too many ties – Must have, Must-must haves, must-must-must haves etc.)

• Value lies in the eyes of the beholder…and so does its dimensions!

• Dimensions are ‘hidden’ within the ‘expected benefits’ of the various stakeholders

• The benefits serve as the goals/objectives/criteria on which to prioritize the requirements

• Point to consider: Are all dimensions* equally important?(*dimensions = benefits = criteria = goals = objectives)

Page 29: Stakeholder WinWin And Requirements Prioritization Nupul Kukreja 19 th October 2015 1

30

Prioritizing Criteria/Value Dimensions

• All criteria may NOT be equally important• But just HOW do you prioritize the criteria

themselves?– A simple 1-10 (Yes, it works )– A highly involved process like multi-attribute utility

theory (MAUT) to get the utility functions for each criteria which shows the risk attitude of each criterion

– Or another interesting technique - Project Success Sliders*

* Radical Project Management by Rob Thomsett

Page 30: Stakeholder WinWin And Requirements Prioritization Nupul Kukreja 19 th October 2015 1

31

Project Success Sliders

Image: Radical Project Management by Rob Thomsett

25%

50%

75%

Success Criteria

(defined at start of project)

Page 31: Stakeholder WinWin And Requirements Prioritization Nupul Kukreja 19 th October 2015 1

32

Project Success Sliders

Image: Radical Project Management by Rob Thomsett

25

50

100

75

25

75

50

1

2

4

3

1

3

2

It’s ‘subjective’ but an extremely effective tool to understand the importance of expectations and their relative tradeoffs!

They can be (and are) interpreted on a relative scale i.e., twice as important, half as much etc.,

Page 32: Stakeholder WinWin And Requirements Prioritization Nupul Kukreja 19 th October 2015 1

33

Putting It All TogetherYou have:

1.Relative ranking of all criteria2.List of requirements (or win conditions)

What else do you need?• Scores! How well each requirement/win-

condition does on each criteriaYou STILL need something else…

• The decision analysis ALGORITHM!

Page 33: Stakeholder WinWin And Requirements Prioritization Nupul Kukreja 19 th October 2015 1

34

Overall Score

Criteria

Alternatives

Criterion 1

Criterion 2

Criterion 3 … Criterion

N

W1 W2 W3 … WN

S(A1) Alternative 1 S11 S12 S13 … S1N

S(A2) Alternative 2 S21 S22 S23 … S2N

S(A3) Alternative 3 S31 S32 S33 … S3N

… … … … … … …

S(AN) Alternative N SN1 SN2 SN3 … SNN

Decision Analysis Algorithm: Given a set of criteria with possible weights and the measure of how the alternatives rank on the respective criteria find an optimal alternative

The scale of the scores could be absolute, relative, 1-10 (Likert

Scale), Fibonacci... …must be consistent across

criterion column

Page 34: Stakeholder WinWin And Requirements Prioritization Nupul Kukreja 19 th October 2015 1

35

Algorithms for Practicing VBRP• There are various algorithms in literature to choose

from along with those from MCDA/M:– Kano Analysis– Planning Poker– 100-point assignment technique– Simple Additive Weighting– Quality Function Deployment (House of Quality)– Cost of Delay– Weigers’ Prioritization– Theory-W (Business value vs. Technical Feasibility)– TOPSIS– …and quite a few more

Page 35: Stakeholder WinWin And Requirements Prioritization Nupul Kukreja 19 th October 2015 1

36

A Practical Example• TOPSIS: Technique of Ordered Preference by

Similarity to Ideal Solution (MCDM Technique)• Integrated in Winbook for prioritizing MMFs and

win conditions• We’ll be using Business Value, Technical

Feasibility and Relative Penalty as the criteria against which to rank the requirements

• MMFs Prioritized against stakeholders’ value propositions/goals/objectives

• Success Sliders for prioritizing value propositions

Page 36: Stakeholder WinWin And Requirements Prioritization Nupul Kukreja 19 th October 2015 1

37

Ideal Alternative (S’)

TOPSIS Primer

Criterion 1

Criterion 2

Alternative 1

Alternative 2Non-Ideal Alternative (S*)

Aim: Rank order alternatives by their ‘closeness to ideal’ and ‘distance from non-ideal’Criterion: Has ‘direction of preference’ i.e. more/less of the criterion is preferredIdeal: Best score for each criterion Non-ideal: Worst score for each criterion

Page 37: Stakeholder WinWin And Requirements Prioritization Nupul Kukreja 19 th October 2015 1

38

Page 38: Stakeholder WinWin And Requirements Prioritization Nupul Kukreja 19 th October 2015 1

39

Refinements to TOPSIS/VBRP• Prerequisite Handling (not yet integrated in

Winbook)– Specifying MMF/WC prerequisites and factoring in

prioritization– Simple solution: Priority of item less than all those

in its prerequisite graph • Hierarchical Prioritization (partially integrated)

– Prioritizing high level MMFs w.r.t. project goals– Prioritizing WCs w.r.t. MMFs– Prioritizing test cases w.r.t. WCs and so on

Page 39: Stakeholder WinWin And Requirements Prioritization Nupul Kukreja 19 th October 2015 1

40

Points To Note• TOPSIS is ONE way of practicing VBRP• You could even perform COTS tradeoff analyses

using it. (It’s a decision problem!)• Use the VBRP technique that is best suited to the

situation• Some prioritization techniques do not lend

themselves to a typical spreadsheet like analysis• The output of some techniques could be

bucketed (categorized into the MoSCoW buckets) or ordinal (explicitly rank ordered)

Page 40: Stakeholder WinWin And Requirements Prioritization Nupul Kukreja 19 th October 2015 1

41

Conclusion• Tools and techniques for prioritization are only

one side of the coin…• …negotiations and discussions are the other.

The latter must be held for the former to be of any value. Using the tool will NOT guarantee VBRP

• There “maybe” a Homework on VBRP…keep a watch out for the announcement