stakeholder workshop on tariff aspects of the draft cam network code
DESCRIPTION
Stakeholder workshop on tariff aspects of the draft CAM network code. Introduction. Brussels – 19 July 2011. Stakeholder workshop on tariff aspects of the draft CAM network code. CAM and tariffs are closely related… …reserve prices, bundling, over/under recovery. - PowerPoint PPT PresentationTRANSCRIPT
Stakeholder workshop on tariff aspects of the draft CAM network code
Brussels – 19 July 2011
Introduction
Stakeholder workshop on tariff aspects of the draft CAM network code
2
CAM and tariffs are closely related…
…reserve prices, bundling, over/under recovery.
CAM network code needs to be implemented upon entry into force…
….regulated tariff arrangements on national level will need adjustment to new regime.
Essentials need to be codified at an EU level at this stage through the CAM network code, to enable a workable CAM regime.
Stakeholder workshop on tariff aspects of the draft CAM network code
3
Aims of this workshop:
•Foster common understanding of issues at hand
•Get support for quality network code rules
For the avoidance of doubt: Neither the draft network code nor this workshop including the practical exercises intends to encroach upon NRA and TSO
prerogatives in determining specific tariffs.
It is however important to point to the policy decisions that have to be taken in tariff calculation
Tariff arrangements need to suit the proposed CAM measures to enable the functioning of the regime, therefore essentials have to be set on EU level.
Stakeholder workshop on tariff aspects of the draft CAM network code
4
No. Description Time
1. Introduction and Agenda 14:00-14:05
2. Tariff provisions in the draft CAM network code 14:05-14:20
3. Reserve prices throughout Standard Capacity Products 14:20-14:50
4. Hands-on exercise 1: Revenue equality between users 14:50-15:20
Coffee Break 15:20-15:30
5. Exercise 1 outcomes and discussion 15:30-16:00
6. Issues with over and under recovery 16:00-16:30
7. Hands-on exercise 2: Oops! there is too much cash (or too little) 16:30-17:00
Coffee Break 17:00-17:10
8. Exercise 2 outcomes and discussion 17:10-17:40
9. Wrap up 17:40-18:00
Tariff provisions in the draft CAM network code
Johannes Heidelberger
Brussels – 19 July 2011
Stakeholder workshop on tariff aspects of the draft CAM
network code
Tariff provisions in the draft CAM network code7. Tariffs
1) If not further or otherwise specified in the network code on tariffs, the following shall apply for the determination of specific tariffs for the application of this Network Code.2) The Regulated Tariff shall be used as the Reserve Price in all auctions for all Standard Capacity Products for firm and interruptible capacity.
1.2 Definitions
(s) ‘Regulated Tariff’ means either the tariff as calculated using the methodology set and/or approved by the national regulatory authority, or the tariff set and/or approved by the national regulatory authority, or both.
6
Tariff provisions in the draft CAM network code7. Tariffs
3) The regulated prices as Reserve Prices for firm Standard Capacity Products shall be set such that bookings of a profiled set of products to meet the actual flow requirements throughout the year yield revenues which are, as far as reasonably possible, equivalent to the revenues from non-profiled longer capacity bookings to meet annual peak flow requirements. In order to achieve such equivalence, Standard Capacity Products shall be offered at regulated prices as Reserve Prices, which are derived per Interconnection Point and per direction by applying multipliers higher than one to a tariff determined from an annual accounting basis.
7
Tariff provisions in the draft CAM network code7. Tariffs4) Auction revenues from Bundled Capacity need to be split between the transmission system operators placing capacity elements in a Bundled Capacity. The Reserve Price of the Bundled Capacity shall be the sum of Reserve Prices of the capacity elements in the bundle. All revenues from sales of Bundled Capacity shall be attributed to the contributing transmission system operators in relation to each capacity transaction.
5) Any revenue from an auction of Bundled Capacity shall be split between the transmission system operators placing capacity elements in the bundle according to a pro-rata rule, based on the proportions of the Reserve Prices of the capacity elements placed in the bundle at the time of the auction. By way of derogation, transmission system operators placing capacity in a Bundled Capacity can agree on a different split of the revenue from an auction of bundled products.
8
Tariff provisions in the draft CAM network code
7. Tariffs
6) Auction revenues exceeding the allowed revenue (or under a price cap, auction revenues arising from capacity prices above the regulated tariff) shall be used for different aims, subject to approval by the national regulatory authority.
7) In the event of revenue under-recovery (or under a price cap, capacity prices falling short of later regulated prices after the auction), national regulatory authorities shall allow transmission system operators to collect the revenue shortfall in a timely manner by adjusting tariffs accordingly.
9
Regulated reserve prices throughout Standard Capacity Products
Adriaan de Bakker
Brussels – 19 July 2011
stakeholder workshop on tariff aspects of the draft CAM
network code
Regulated reserve prices throughout Standard Capacity Products
• To enable the offer of Standard Capacity Products (SCP) as proposed in the draft CAM NC, TSOs need assurance on revenue recovery
• Reserve price design needs to be based on booking forecast:• Profiling of capacity, e.g. seasonal quarters• Substitution of products – long vs. short term
11
Regulated reserve prices throughout Standard Capacity Products
Revenue of long term booking approximately equal to revenue of profiled booking along actual flows
12
Principle in draft CAM network code:
Aim: Equity for all system users and avoidance of cross-subsidisation
Not foreseen in draft CAM NC
Achieving equity between long and short product users
• Reserve prices enabling profiling of quarters should therefore be:(annual accounting tariff/4) x (appropriate multiplier)
• Users who book longer term shall be put on equal footing with those who can book close to time of flow – no undue cross-subsidisation:
Reserve prices for short term SCP (monthly and shorter) to reflect further profiling opportunity closer to flow
13
14
… substitutability between long and short term capacity is observed and this may create material distortions and inefficiencies in regime functioning
Source: National Grid Sep 2009
Migration from long term
booking. Not even zero firm day ahead reserve
price! (but discount; and zero
within day / interruptible)
Low short term prices may lead to non-optimal charging
Regulated reserve prices throughout Standard Capacity Products - Conclusion
Finally: KEMA (2009) identified high tariffs for short term capacity as market barrier
Regulation 715 calls for tariffs not “arbitrarily” higher or lower than the standard annual tariff (Art. 14 (2))
15
With the principle of revenue equivalence of profiled vs. longer term bookings, a reasoned, non-arbitrary
approach is introduced.
Exercise 1: revenue equality between users
Quarter 1 Quarter 2 Quarter 3 Quarter 4 Total YearAnnual bookingannual accounting based reserve price 1.00
Profiled booking forecastQ capacity sales forecast 90% 40% 40% 90% 65%M capacity sales forecast 5% 5% 5% 5% 5%D capacity sales forecast 5% 5% 5% 5% 5%Total capacity sales forecast 100% 50% 50% 100% 75%
Possible non-seasonal reserve pricesQ reserve price 1.30 1.30 1.30 1.30 M reserve price 1.40 1.40 1.40 1.40 D reserve price 1.70 1.70 1.70 1.70 Capacity revenue forecast 0.33 0.17 0.17 0.33 1.00
Possible seasonal reserve pricesQ reserve price M reserve price D reserve price Capacity revenue forecast 1.00
To do: fill red box with seasonal reserve pricing, such that total revenue is 1.00
Figures are only to illustrate reserve price principles and do not constitute concrete TSO positions.NB: Regulated reserve prices may be subject to changes over the years – with changes in tariffs for products already auctioned (cf. “German model” with auction premium above regulated price). Distinction of annual monthly and rolling monthly is conceivable. Within-day needs to fit in revenue equality principle as well.
Issues with over and under recovery
Eddie Blackburn
Brussels – 19 July 2011
Stakeholder workshop on tariff aspects of the draft CAM
network code
Issues with over and under recovery Under recovery; contributing factors are:
– Aggregate level of capacity sold being less than forecast– Greater than expected profiling of capacity to meet flow
requirements– Target (allowed) revenue increasing following the auction
Over recovery; contributing factors are:– Aggregate level of capacity sold being greater than forecast– Less than expected profiling of capacity to meet flow requirements– Target (allowed) revenue reducing following the auction– Capacity sold at prices in excess of the reserve price
The method of managing under/over recovery might depend on the contributing factors
18
Issues with over and under recovery
Examples of current, quite different ways of dealing with over and under recovery
Commodity charge (GB)– Under recovery is charged to all users flowing gas (including “flat”
users)
“floating” regulated price under an auction premium (DE) – System wide smearing of over recovery to all capacity tariffs– Regulated “reserve” price of products, already auctioned, may
change over time, as the TSO cost basis changes.
Regulatory account– Under/over recovery is passed through to the next year
19
Issues with over and under recovery
General options for dealing with over and under recovery:
• Retrospective v current year v future year
• Capacity v commodity
• Locational v entry/exit side only v system wide
20
Issues with over and under recovery
Potential effects of different over and under recovery mechanisms and issues involved (1):• Users who bid high at a location get money back:
– perverse incentive to excessively outbid competitors
• Tariff adjustments to or from other users:– may create cross-subsidies
• Dedicated commodity charge may hamper trade:– acts as a tax on allocated gas quantities
21
Issues with over and under recovery
Potential effects of different over and under recovery mechanisms and issues involved (2):
• Tariff volatility may become substantial, depending on e.g. number of points in system
• Ex-post over or under recovery mechanisms may involve cash and interest rate issues:– How are network users or TSOs treated in terms of the time value of
money?
22
Issues with over and under recoveryConclusion
Ex post over and under recovery correction will always have the potential to create cross-subsidisation and distortions, between users
– at different locations, or– of different products, or– at different times.
23
It is therefore vital to ex-ante design tariffs such that ex-post correction need is minimised
Entry-Exit zoneAllowed revenue: 400
Domestic Exits
Revenue: 100
Revenue Entry: 100Actual auction revenue: 200
Revenue Entry: 50Revenue Exit: 50
Revenue Entry: 50Revenue Exit: 50
Auction revenue exceeding allowed revenue: 100To do: Where, when, and with what charge (capacity/commodity) to be returned to system users?
Exercise 2 (1): over recovery
Entry-Exit zoneAllowed revenue: 400
Domestic Exits
Revenue: 100
Revenue Entry: 100Actual auction revenue: 40
Revenue Entry: 50Revenue Exit: 50
Revenue Entry: 50Revenue Exit: 50
Revenue falling short of allowed revenue: 60To do: Where, when, and with what charge (capacity/commodity) to be recovered from system users?
Exercise 2 (2): under recovery
Wrap up
Brussels – 19 July 2011
Stakeholder workshop on tariff aspects of the draft CAM
network code
Wrap up
27