Page 1: Statewide Financial System (Internal Use Only) Agency Task List Kickoff Meeting June 9, 2010 Presented by: Mary Acquaviva Org Readiness

Statewide Financial System (Internal Use Only)

Agency Task List Agency Task List Kickoff MeetingKickoff MeetingAgency Task List Agency Task List Kickoff MeetingKickoff Meeting

June 9, 2010June 9, 2010

Presented by:

Mary Acquaviva

Org Readiness

Page 2: Statewide Financial System (Internal Use Only) Agency Task List Kickoff Meeting June 9, 2010 Presented by: Mary Acquaviva Org Readiness

Statewide Financial System (Internal Use Only)2

Stakeholder Delivery Map

Overview of Task List Tools

Agency Task List

Agency Monthly Reporting Scorecard

Statewide Dashboard

Task List Walkthrough

Agency Next Steps

Agency Support

Questions

Stakeholder Delivery Map

Overview of Task List Tools

Agency Task List

Agency Monthly Reporting Scorecard

Statewide Dashboard

Task List Walkthrough

Agency Next Steps

Agency Support

Questions

Meeting AgendaMeeting Agenda

Page 3: Statewide Financial System (Internal Use Only) Agency Task List Kickoff Meeting June 9, 2010 Presented by: Mary Acquaviva Org Readiness

Statewide Financial System (Internal Use Only)3

ImplementationImplementation

OSC and Agency ReadinessOSC and Agency Readiness

Agency LOE Forms and Plan to Procure Due

Agency Interface Project Plans

Certification Pilot Begins

Bulkload Certification Begins

OSC Change Impact Due OSC Change Action Plans Begin

Agency Specific Scorecards Created Agency Checkpoint Meetings

Bulkload Certification Ends

Trainers Identified

Final Layouts to Agencies

Services AcquisitionServices Acquisition Interface Design/BuildInterface Design/Build

Certif PilotCertif Pilot

Formal CertificationFormal Certification

Agency Implementation GuideAgency Implementation GuideRelease Guide

with File Layouts

Conversion Mock TestsConversion Mock Tests

Data Cleansing at 70%Data Cleansing Complete

Vendor File Live

Execute ConversionExecute Conversion

Go-Live

Production SupportProduction Support

OSC Oracle GLS used for 2010-11 CAFR

OSC Oracle GLS used for 2010-11 CAFR

Operations Information

Agency Executes Change Actions and Provides Scorecard UpdatesAgency Executes Change Actions and Provides Scorecard Updates

Final Agency Vendor File

Agency Impacts/ActionsAgency Impacts/Actions

Training DesignTraining Design Training DevelopmentTraining Development Training DeliveryTraining DeliveryTrain TrainersTrain Trainers

OSC Action Plan DevelopmentOSC Action Plan DevelopmentCollect OSC ImpactsCollect OSC ImpactsOSC Executes Change ActionsOSC Executes Change Actions CutoverCutover

CutoverCutover

OSC/AgencyOSC/Agency

SFS Team SFS Team

Stakeholder Delivery Map

Page 4: Statewide Financial System (Internal Use Only) Agency Task List Kickoff Meeting June 9, 2010 Presented by: Mary Acquaviva Org Readiness

Statewide Financial System (Internal Use Only)4

Task List Tools

Agency Task List

Agency-specific tasks that need to be completed prior to Go-Live. Three-month rolling task list created and distributed by SFS

Organizational Readiness Team on a monthly basis. Updated by agencies to indicate status of completion and

returned to SFS monthly. Agency Monthly Reporting Scorecard

Based on Agency’s status of task completion. Created and distributed by the Agency’s Organizational

Readiness Liaison monthly. Statewide Dashboard

Global view of all agencies’ organizational readiness. Created, maintained, and used internally by SFS.

Page 5: Statewide Financial System (Internal Use Only) Agency Task List Kickoff Meeting June 9, 2010 Presented by: Mary Acquaviva Org Readiness

Statewide Financial System (Internal Use Only)5

Task List Tools: How They are Related

Agency task lists are distributed to agencies at the beginning of the month.

Agencies return task lists by the last business day of the month.

SFS uses agency task lists to update and distribute each agency’s monthly reporting scorecard.

SFS uses agency monthly reporting scorecards as input to the statewide dashboard.

Agency A Task List Agency A Scorecard

•A•B

•C •D

Agency B Task ListAgency C Task List

Agency D Task List

Agency B Scorecard Agency C Scorecard

Agency D Scorecard

DASHBOARDSCORECARDSTASKLISTS

Page 6: Statewide Financial System (Internal Use Only) Agency Task List Kickoff Meeting June 9, 2010 Presented by: Mary Acquaviva Org Readiness

Statewide Financial System (Internal Use Only)6

Agency Task List Kickoff Meeting

Agency Task List Agency Task List OverviewOverview

Agency Task List Agency Task List OverviewOverview

Presented by:

Divya Chadalavada

Org Readiness

Page 7: Statewide Financial System (Internal Use Only) Agency Task List Kickoff Meeting June 9, 2010 Presented by: Mary Acquaviva Org Readiness

Statewide Financial System (Internal Use Only)7

Agency Task List: What is it?

Agency-specific listing of all tasks that need to be completed in preparation for Go-Live.

Task lists cover all aspects of organizational readiness:

Process Readiness – New tools in place; new / modified business processes documented.

People Readiness – Open intra-agency communications; successful training delivery; user roles / provisioning.

Support Readiness – Provision of user support; Super User preparation.

System Readiness – Systems are configured / converted / interfaced / tested.

Infrastructure Readiness – Desktops / workstations are prepared.

Page 8: Statewide Financial System (Internal Use Only) Agency Task List Kickoff Meeting June 9, 2010 Presented by: Mary Acquaviva Org Readiness

Statewide Financial System (Internal Use Only)8

Agency Task List: What is it?

Task lists contain all tasks that are due within the next three months and any incomplete tasks from the previous task list.

Distributed to Agency Coordinators monthly.

Page 9: Statewide Financial System (Internal Use Only) Agency Task List Kickoff Meeting June 9, 2010 Presented by: Mary Acquaviva Org Readiness

Statewide Financial System (Internal Use Only)9

Agency Task List Snapshot: As Sent to Agencies

Task ID No.

High-Level Task Category

Task Description Reference MaterialTask

Start DateTargeted

Completion

Task Status (Agency to Complete)

Info. Req'd from SFS

Entity Impacted

2 Business Process Determine agency use of requisitioning in FMS Not Applicable 1-Jul-2010 31-Aug-2010    Phase I

6 Business Process Identify change to internal business processes and procedures

Not Applicable 1-Jul-2010 31-Aug-2010    Phase I

8 Communications Create communication distribution channels (i.e. email distribution list) for end users

Not Applicable 10-Jun-2010 30-Jul-2010    All agencies

12 Configuration (COA) Complete Cost Center Mappings - Round 1 Section 8.0 Agency Implementation Guide

1-Dec-2009 30-Apr-2010    All agencies

18 Conversion Identify agency systems that require conversion (Consider AR billing systems that are to be replaced by SFS)

Not Applicable 10-Jun-2010 30-Jul-2010    Phase I

17 Conversion Identify data conversion requirements for disposed systems (Consider AR billing systems that are to be replaced by SFS)

Not Applicable 10-Jun-2010 30-Jul-2010    Phase I

16 Conversion Identify conversion data owners   10-Jun-2010 30-Jul-2010    Phase I54 Interface

DevelopmentComplete and return Level of Effort form for Interface Development to SFS

Section 2.5 and Appendix J Agency Implementation Guide

23-Oct-2009 26-Mar-2010    Interface Agency

55 Interface Development

Complete and submit to SFS a Project Plan for Interface Development to SFS

Section 2.5.2 Agency Implementation Guide

23-Oct-2009 26-Mar-2010    Interface Agency

24 Interface Development

Determine finalized dispositions for feeder systems Not Applicable 1-Apr-2010 30-May-2010    Phase I

25 Interface Development

Complete and submit the Agency Interface Profile template to SFS

Section 4.0 and Appendix G Agency Implementation Guide

24-May-2010 18-Jun-2010    Interface Agency

27 Interface Development

Complete conversion to Tumbleweed Appendix F Agency Implementation Guide

16-Feb-2010 31-Aug-2010    Interface Agency

31 Security Confirm Security Coordinator has been designated Section 3.2 Agency Implementation Guide

24-May-2010 30-Jun-2010    All agencies

41 Training Complete training survey and submit to SFS Section 10.5 Agency Implementation Guide

1-Mar-2010 1-May-2010    Phase I

49 Training Ensure all agency end-users are registered in NYS-Learn Section 10.5 Agency Implementation Guide

24-May-2010 31-Aug-2010    Phase I

48 Training Confirm end user prerequisite training gaps Section 10.5 Agency Implementation Guide

1-Jul-2010 31-Aug-2010    Phase I

Page 10: Statewide Financial System (Internal Use Only) Agency Task List Kickoff Meeting June 9, 2010 Presented by: Mary Acquaviva Org Readiness

Statewide Financial System (Internal Use Only)10

Task ID No.

High-Level Task Category

Task Description Reference MaterialTask

Start DateTargeted

Completion

Task Status (Agency to Complete)

Info. Req'd from SFS

Entity Impacted

2 Business Process Determine agency use of requisitioning in FMS Not Applicable 1-Jul-2010 31-Aug-2010 2 - 25% Complete  Phase I

6 Business Process Identify change to internal business processes and procedures

Not Applicable 1-Jul-2010 31-Aug-2010 3 - 50% Complete Awaiting Information from SFS

Phase I

8 Communications Create communication distribution channels (i.e. email distribution list) for end users

Not Applicable 10-Jun-2010 30-Jul-2010 4 - 75% Complete  All agencies

12 Configuration (COA) Complete Cost Center Mappings - Round 1 Section 8.0 Agency Implementation Guide

1-Dec-2009 30-Apr-2010 5 – Complete   All agencies

18 Conversion Identify agency systems that require conversion (Consider AR billing systems that are to be replaced by SFS)

Not Applicable 10-Jun-2010 30-Jul-2010 6 - Not Applicable   Phase I

17 Conversion Identify data conversion requirements for disposed systems (Consider AR billing systems that are to be replaced by SFS)

Not Applicable 10-Jun-2010 30-Jul-2010 6 - Not Applicable   Phase I

16 Conversion Identify conversion data owners   10-Jun-2010 30-Jul-2010 3 - 50% Complete  Phase I54 Interface

DevelopmentComplete and return Level of Effort form for Interface Development to SFS

Section 2.5 and Appendix J Agency Implementation Guide

23-Oct-2009 26-Mar-2010 5 – Complete   Interface Agency

55 Interface Development

Complete and submit to SFS a Project Plan for Interface Development to SFS

Section 2.5.2 Agency Implementation Guide

23-Oct-2009 26-Mar-2010 5 – Complete   Interface Agency

24 Interface Development

Determine finalized dispositions for feeder systems Not Applicable 1-Apr-2010 30-May-2010 5 – Complete   Phase I

25 Interface Development

Complete and submit the Agency Interface Profile template to SFS

Section 4.0 and Appendix G Agency Implementation Guide

24-May-2010 18-Jun-2010 5 – Complete   Interface Agency

27 Interface Development

Complete conversion to Tumbleweed Appendix F Agency Implementation Guide

16-Feb-2010 31-Aug-2010 4 - 75% Complete  Interface Agency

31 Security Confirm Security Coordinator has been designated Section 3.2 Agency Implementation Guide

24-May-2010 30-Jun-2010 1 - Not Started   All agencies

41 Training Complete training survey and submit to SFS Section 10.5 Agency Implementation Guide

1-Mar-2010 1-May-2010 1 - Not Started   Phase I

49 Training Ensure all agency end-users are registered in NYS-Learn Section 10.5 Agency Implementation Guide

24-May-2010 31-Aug-2010 2 - 25% Complete  Phase I

48 Training Confirm end user prerequisite training gaps Section 10.5 Agency Implementation Guide

1-Jul-2010 31-Aug-2010 2 - 25% Complete  Phase I

Agency Task List Snapshot: Statuses Updated by Agencies

Page 11: Statewide Financial System (Internal Use Only) Agency Task List Kickoff Meeting June 9, 2010 Presented by: Mary Acquaviva Org Readiness

Statewide Financial System (Internal Use Only)11

Agency Task List Support

Agencies should contact their Organizational Readiness Liaison with any questions regarding the task list/scorecard.

http://www.nyfms.state.ny.us/assets/Docs/ Organizational_Readiness_Agency_Assignments.doc

Page 12: Statewide Financial System (Internal Use Only) Agency Task List Kickoff Meeting June 9, 2010 Presented by: Mary Acquaviva Org Readiness

Statewide Financial System (Internal Use Only)12

Agency Task List Considerations

Status updates on task lists are due to the SFS Organizational Readiness Liaison by the last business day of each month.

If agencies do not submit a task list by the due date, SFS will assume that no progress was made.

SFS will not adjust published reports to accommodate late agency task list submissions.

Page 13: Statewide Financial System (Internal Use Only) Agency Task List Kickoff Meeting June 9, 2010 Presented by: Mary Acquaviva Org Readiness

Statewide Financial System (Internal Use Only)13

Agency Task List Kickoff Meeting

Agency Monthly Agency Monthly Reporting ScorecardReporting Scorecard

Agency Monthly Agency Monthly Reporting ScorecardReporting Scorecard

Presented by:

John Libutti

Org Readiness

Page 14: Statewide Financial System (Internal Use Only) Agency Task List Kickoff Meeting June 9, 2010 Presented by: Mary Acquaviva Org Readiness

Statewide Financial System (Internal Use Only)14

Agency Monthly Reporting Scorecard: What is it? Agency’s status of task list completion.

Identifies issues and highlights areas, by category, that may be at-risk for Go-Live.

Metrics are based off completion of tasks from the agency’s task list.

Agency scorecards are updated monthly by SFS and distributed to the Agency Coordinator.

Dependent upon agencies submitting task lists by the end of each month.

Page 15: Statewide Financial System (Internal Use Only) Agency Task List Kickoff Meeting June 9, 2010 Presented by: Mary Acquaviva Org Readiness

Statewide Financial System (Internal Use Only)15

Agency Readiness Scorecard  

Agency Name New York State Agency A

  Total Number of Tasks Due this Month

23 Checkpoint Date (Monthly)        Readiness Metric Categories:      

Process Readiness -New tools are in place and processes have been documented  People Readiness - The organization can successfully operate in the new environmentSystem Readiness - The system is ready to operate as designedSupport Readiness- The processes are in place to successfully support the system on Go-Live

Infrastructure Readiness- Technical components have been completed to ensure users are ready for the transition to SFS

Category Planned Tasks Complete Actual Tasks Complete Variance Comments / Includes Mitigation Approach Agency Specific 10.0 7.0 70%  

Process Readiness 3.0 2.0 67%  Business Process 3.0 2.0 67%  

People Readiness 5.0 3.0 60%  Communications 1.0 1.0 100%  Training 1.0 0.0 0%  User Roles/Provisioning 3.0 2.0 67%  

System Readiness 5.0 4.0 80%     Variance Legend In Good Shape    Some Concerns    Urgent Attention    Unable to Assess           

Agency Monthly Reporting Scorecard Snapshot

Page 16: Statewide Financial System (Internal Use Only) Agency Task List Kickoff Meeting June 9, 2010 Presented by: Mary Acquaviva Org Readiness

Statewide Financial System (Internal Use Only)16

Agency Task List Kickoff Meeting

Statewide DashboardStatewide DashboardStatewide DashboardStatewide Dashboard

Presented by:

John Libutti

Org Readiness

Page 17: Statewide Financial System (Internal Use Only) Agency Task List Kickoff Meeting June 9, 2010 Presented by: Mary Acquaviva Org Readiness

Statewide Financial System (Internal Use Only)17

Statewide Dashboard: What is it?

Global view of all agencies’ organizational readiness and task list completion.

Agencies are given scores based on two factors:

Readiness – based on task list completion Complexity – based on several factors, such as:

Number of source system interfacesNumber of cost centersScale of workforce training effortScale and complexity of security rolesTransaction volumeScale and complexity of conversion effortIdentification of host agency

Page 18: Statewide Financial System (Internal Use Only) Agency Task List Kickoff Meeting June 9, 2010 Presented by: Mary Acquaviva Org Readiness

Statewide Financial System (Internal Use Only)18

Statewide Dashboard: What is it?

Readiness and Complexity scores combine to place an agency in one of four quadrants:

High

Low

Hig

h

Low

Complexity

Rea

dine

ss

•Agency B

•Agency C

•Agency D

•Agency E

•Agency F

•Agency G

•Agency H

•Agency J

Page 19: Statewide Financial System (Internal Use Only) Agency Task List Kickoff Meeting June 9, 2010 Presented by: Mary Acquaviva Org Readiness

Statewide Financial System (Internal Use Only)19

Statewide Dashboard: What is it?

An agency’s placement in the matrix guides SFS interaction to those agencies in need of the greatest support.

High

Low

Hig

h

Low

Complexity

Rea

dine

ss

•Caution

•Agency At Risk

•All systems go!

•Caution

Page 20: Statewide Financial System (Internal Use Only) Agency Task List Kickoff Meeting June 9, 2010 Presented by: Mary Acquaviva Org Readiness

Statewide Financial System (Internal Use Only)20

Agency Task List Kickoff Meeting

Review June Agency Review June Agency Task ListTask List

Review June Agency Review June Agency Task ListTask List

Presented by:

Ted Paniccia III

Org Readiness

Page 21: Statewide Financial System (Internal Use Only) Agency Task List Kickoff Meeting June 9, 2010 Presented by: Mary Acquaviva Org Readiness

Statewide Financial System (Internal Use Only)21

Agency Task List Timeline

Page 22: Statewide Financial System (Internal Use Only) Agency Task List Kickoff Meeting June 9, 2010 Presented by: Mary Acquaviva Org Readiness

Statewide Financial System (Internal Use Only)22

Next Steps/Significant Dates

June 7th: Agency task lists were distributed to Agency Coordinators.

June 9th: Agency Task List Kickoff Meeting.

June: SFS will be scheduling working sessions with agencies to walkthrough the task lists and review agency-specific tasks.

June 30th: Agency task lists are due to SFS.

July – Go-Live:

SFS distributes agency task lists and scorecards monthly to Agency Coordinators.

Agencies return task lists to SFS by last business day of each month.

Page 23: Statewide Financial System (Internal Use Only) Agency Task List Kickoff Meeting June 9, 2010 Presented by: Mary Acquaviva Org Readiness

Statewide Financial System (Internal Use Only)23

Questions?