Statewide Financial System (Internal Use Only)
Agency Task List Agency Task List Kickoff MeetingKickoff MeetingAgency Task List Agency Task List Kickoff MeetingKickoff Meeting
June 9, 2010June 9, 2010
Presented by:
Mary Acquaviva
Org Readiness
Statewide Financial System (Internal Use Only)2
Stakeholder Delivery Map
Overview of Task List Tools
Agency Task List
Agency Monthly Reporting Scorecard
Statewide Dashboard
Task List Walkthrough
Agency Next Steps
Agency Support
Questions
Stakeholder Delivery Map
Overview of Task List Tools
Agency Task List
Agency Monthly Reporting Scorecard
Statewide Dashboard
Task List Walkthrough
Agency Next Steps
Agency Support
Questions
Meeting AgendaMeeting Agenda
Statewide Financial System (Internal Use Only)3
ImplementationImplementation
OSC and Agency ReadinessOSC and Agency Readiness
Agency LOE Forms and Plan to Procure Due
Agency Interface Project Plans
Certification Pilot Begins
Bulkload Certification Begins
OSC Change Impact Due OSC Change Action Plans Begin
Agency Specific Scorecards Created Agency Checkpoint Meetings
Bulkload Certification Ends
Trainers Identified
Final Layouts to Agencies
Services AcquisitionServices Acquisition Interface Design/BuildInterface Design/Build
Certif PilotCertif Pilot
Formal CertificationFormal Certification
Agency Implementation GuideAgency Implementation GuideRelease Guide
with File Layouts
Conversion Mock TestsConversion Mock Tests
Data Cleansing at 70%Data Cleansing Complete
Vendor File Live
Execute ConversionExecute Conversion
Go-Live
Production SupportProduction Support
OSC Oracle GLS used for 2010-11 CAFR
OSC Oracle GLS used for 2010-11 CAFR
Operations Information
Agency Executes Change Actions and Provides Scorecard UpdatesAgency Executes Change Actions and Provides Scorecard Updates
Final Agency Vendor File
Agency Impacts/ActionsAgency Impacts/Actions
Training DesignTraining Design Training DevelopmentTraining Development Training DeliveryTraining DeliveryTrain TrainersTrain Trainers
OSC Action Plan DevelopmentOSC Action Plan DevelopmentCollect OSC ImpactsCollect OSC ImpactsOSC Executes Change ActionsOSC Executes Change Actions CutoverCutover
CutoverCutover
OSC/AgencyOSC/Agency
SFS Team SFS Team
Stakeholder Delivery Map
Statewide Financial System (Internal Use Only)4
Task List Tools
Agency Task List
Agency-specific tasks that need to be completed prior to Go-Live. Three-month rolling task list created and distributed by SFS
Organizational Readiness Team on a monthly basis. Updated by agencies to indicate status of completion and
returned to SFS monthly. Agency Monthly Reporting Scorecard
Based on Agency’s status of task completion. Created and distributed by the Agency’s Organizational
Readiness Liaison monthly. Statewide Dashboard
Global view of all agencies’ organizational readiness. Created, maintained, and used internally by SFS.
Statewide Financial System (Internal Use Only)5
Task List Tools: How They are Related
Agency task lists are distributed to agencies at the beginning of the month.
Agencies return task lists by the last business day of the month.
SFS uses agency task lists to update and distribute each agency’s monthly reporting scorecard.
SFS uses agency monthly reporting scorecards as input to the statewide dashboard.
Agency A Task List Agency A Scorecard
•A•B
•C •D
Agency B Task ListAgency C Task List
Agency D Task List
Agency B Scorecard Agency C Scorecard
Agency D Scorecard
DASHBOARDSCORECARDSTASKLISTS
Statewide Financial System (Internal Use Only)6
Agency Task List Kickoff Meeting
Agency Task List Agency Task List OverviewOverview
Agency Task List Agency Task List OverviewOverview
Presented by:
Divya Chadalavada
Org Readiness
Statewide Financial System (Internal Use Only)7
Agency Task List: What is it?
Agency-specific listing of all tasks that need to be completed in preparation for Go-Live.
Task lists cover all aspects of organizational readiness:
Process Readiness – New tools in place; new / modified business processes documented.
People Readiness – Open intra-agency communications; successful training delivery; user roles / provisioning.
Support Readiness – Provision of user support; Super User preparation.
System Readiness – Systems are configured / converted / interfaced / tested.
Infrastructure Readiness – Desktops / workstations are prepared.
Statewide Financial System (Internal Use Only)8
Agency Task List: What is it?
Task lists contain all tasks that are due within the next three months and any incomplete tasks from the previous task list.
Distributed to Agency Coordinators monthly.
Statewide Financial System (Internal Use Only)9
Agency Task List Snapshot: As Sent to Agencies
Task ID No.
High-Level Task Category
Task Description Reference MaterialTask
Start DateTargeted
Completion
Task Status (Agency to Complete)
Info. Req'd from SFS
Entity Impacted
2 Business Process Determine agency use of requisitioning in FMS Not Applicable 1-Jul-2010 31-Aug-2010 Phase I
6 Business Process Identify change to internal business processes and procedures
Not Applicable 1-Jul-2010 31-Aug-2010 Phase I
8 Communications Create communication distribution channels (i.e. email distribution list) for end users
Not Applicable 10-Jun-2010 30-Jul-2010 All agencies
12 Configuration (COA) Complete Cost Center Mappings - Round 1 Section 8.0 Agency Implementation Guide
1-Dec-2009 30-Apr-2010 All agencies
18 Conversion Identify agency systems that require conversion (Consider AR billing systems that are to be replaced by SFS)
Not Applicable 10-Jun-2010 30-Jul-2010 Phase I
17 Conversion Identify data conversion requirements for disposed systems (Consider AR billing systems that are to be replaced by SFS)
Not Applicable 10-Jun-2010 30-Jul-2010 Phase I
16 Conversion Identify conversion data owners 10-Jun-2010 30-Jul-2010 Phase I54 Interface
DevelopmentComplete and return Level of Effort form for Interface Development to SFS
Section 2.5 and Appendix J Agency Implementation Guide
23-Oct-2009 26-Mar-2010 Interface Agency
55 Interface Development
Complete and submit to SFS a Project Plan for Interface Development to SFS
Section 2.5.2 Agency Implementation Guide
23-Oct-2009 26-Mar-2010 Interface Agency
24 Interface Development
Determine finalized dispositions for feeder systems Not Applicable 1-Apr-2010 30-May-2010 Phase I
25 Interface Development
Complete and submit the Agency Interface Profile template to SFS
Section 4.0 and Appendix G Agency Implementation Guide
24-May-2010 18-Jun-2010 Interface Agency
27 Interface Development
Complete conversion to Tumbleweed Appendix F Agency Implementation Guide
16-Feb-2010 31-Aug-2010 Interface Agency
31 Security Confirm Security Coordinator has been designated Section 3.2 Agency Implementation Guide
24-May-2010 30-Jun-2010 All agencies
41 Training Complete training survey and submit to SFS Section 10.5 Agency Implementation Guide
1-Mar-2010 1-May-2010 Phase I
49 Training Ensure all agency end-users are registered in NYS-Learn Section 10.5 Agency Implementation Guide
24-May-2010 31-Aug-2010 Phase I
48 Training Confirm end user prerequisite training gaps Section 10.5 Agency Implementation Guide
1-Jul-2010 31-Aug-2010 Phase I
Statewide Financial System (Internal Use Only)10
Task ID No.
High-Level Task Category
Task Description Reference MaterialTask
Start DateTargeted
Completion
Task Status (Agency to Complete)
Info. Req'd from SFS
Entity Impacted
2 Business Process Determine agency use of requisitioning in FMS Not Applicable 1-Jul-2010 31-Aug-2010 2 - 25% Complete Phase I
6 Business Process Identify change to internal business processes and procedures
Not Applicable 1-Jul-2010 31-Aug-2010 3 - 50% Complete Awaiting Information from SFS
Phase I
8 Communications Create communication distribution channels (i.e. email distribution list) for end users
Not Applicable 10-Jun-2010 30-Jul-2010 4 - 75% Complete All agencies
12 Configuration (COA) Complete Cost Center Mappings - Round 1 Section 8.0 Agency Implementation Guide
1-Dec-2009 30-Apr-2010 5 – Complete All agencies
18 Conversion Identify agency systems that require conversion (Consider AR billing systems that are to be replaced by SFS)
Not Applicable 10-Jun-2010 30-Jul-2010 6 - Not Applicable Phase I
17 Conversion Identify data conversion requirements for disposed systems (Consider AR billing systems that are to be replaced by SFS)
Not Applicable 10-Jun-2010 30-Jul-2010 6 - Not Applicable Phase I
16 Conversion Identify conversion data owners 10-Jun-2010 30-Jul-2010 3 - 50% Complete Phase I54 Interface
DevelopmentComplete and return Level of Effort form for Interface Development to SFS
Section 2.5 and Appendix J Agency Implementation Guide
23-Oct-2009 26-Mar-2010 5 – Complete Interface Agency
55 Interface Development
Complete and submit to SFS a Project Plan for Interface Development to SFS
Section 2.5.2 Agency Implementation Guide
23-Oct-2009 26-Mar-2010 5 – Complete Interface Agency
24 Interface Development
Determine finalized dispositions for feeder systems Not Applicable 1-Apr-2010 30-May-2010 5 – Complete Phase I
25 Interface Development
Complete and submit the Agency Interface Profile template to SFS
Section 4.0 and Appendix G Agency Implementation Guide
24-May-2010 18-Jun-2010 5 – Complete Interface Agency
27 Interface Development
Complete conversion to Tumbleweed Appendix F Agency Implementation Guide
16-Feb-2010 31-Aug-2010 4 - 75% Complete Interface Agency
31 Security Confirm Security Coordinator has been designated Section 3.2 Agency Implementation Guide
24-May-2010 30-Jun-2010 1 - Not Started All agencies
41 Training Complete training survey and submit to SFS Section 10.5 Agency Implementation Guide
1-Mar-2010 1-May-2010 1 - Not Started Phase I
49 Training Ensure all agency end-users are registered in NYS-Learn Section 10.5 Agency Implementation Guide
24-May-2010 31-Aug-2010 2 - 25% Complete Phase I
48 Training Confirm end user prerequisite training gaps Section 10.5 Agency Implementation Guide
1-Jul-2010 31-Aug-2010 2 - 25% Complete Phase I
Agency Task List Snapshot: Statuses Updated by Agencies
Statewide Financial System (Internal Use Only)11
Agency Task List Support
Agencies should contact their Organizational Readiness Liaison with any questions regarding the task list/scorecard.
http://www.nyfms.state.ny.us/assets/Docs/ Organizational_Readiness_Agency_Assignments.doc
Statewide Financial System (Internal Use Only)12
Agency Task List Considerations
Status updates on task lists are due to the SFS Organizational Readiness Liaison by the last business day of each month.
If agencies do not submit a task list by the due date, SFS will assume that no progress was made.
SFS will not adjust published reports to accommodate late agency task list submissions.
Statewide Financial System (Internal Use Only)13
Agency Task List Kickoff Meeting
Agency Monthly Agency Monthly Reporting ScorecardReporting Scorecard
Agency Monthly Agency Monthly Reporting ScorecardReporting Scorecard
Presented by:
John Libutti
Org Readiness
Statewide Financial System (Internal Use Only)14
Agency Monthly Reporting Scorecard: What is it? Agency’s status of task list completion.
Identifies issues and highlights areas, by category, that may be at-risk for Go-Live.
Metrics are based off completion of tasks from the agency’s task list.
Agency scorecards are updated monthly by SFS and distributed to the Agency Coordinator.
Dependent upon agencies submitting task lists by the end of each month.
Statewide Financial System (Internal Use Only)15
Agency Readiness Scorecard
Agency Name New York State Agency A
Total Number of Tasks Due this Month
23 Checkpoint Date (Monthly) Readiness Metric Categories:
Process Readiness -New tools are in place and processes have been documented People Readiness - The organization can successfully operate in the new environmentSystem Readiness - The system is ready to operate as designedSupport Readiness- The processes are in place to successfully support the system on Go-Live
Infrastructure Readiness- Technical components have been completed to ensure users are ready for the transition to SFS
Category Planned Tasks Complete Actual Tasks Complete Variance Comments / Includes Mitigation Approach Agency Specific 10.0 7.0 70%
Process Readiness 3.0 2.0 67% Business Process 3.0 2.0 67%
People Readiness 5.0 3.0 60% Communications 1.0 1.0 100% Training 1.0 0.0 0% User Roles/Provisioning 3.0 2.0 67%
System Readiness 5.0 4.0 80% Variance Legend In Good Shape Some Concerns Urgent Attention Unable to Assess
Agency Monthly Reporting Scorecard Snapshot
Statewide Financial System (Internal Use Only)16
Agency Task List Kickoff Meeting
Statewide DashboardStatewide DashboardStatewide DashboardStatewide Dashboard
Presented by:
John Libutti
Org Readiness
Statewide Financial System (Internal Use Only)17
Statewide Dashboard: What is it?
Global view of all agencies’ organizational readiness and task list completion.
Agencies are given scores based on two factors:
Readiness – based on task list completion Complexity – based on several factors, such as:
Number of source system interfacesNumber of cost centersScale of workforce training effortScale and complexity of security rolesTransaction volumeScale and complexity of conversion effortIdentification of host agency
Statewide Financial System (Internal Use Only)18
Statewide Dashboard: What is it?
Readiness and Complexity scores combine to place an agency in one of four quadrants:
High
Low
Hig
h
Low
Complexity
Rea
dine
ss
•Agency B
•Agency C
•Agency D
•Agency E
•Agency F
•Agency G
•Agency H
•Agency J
Statewide Financial System (Internal Use Only)19
Statewide Dashboard: What is it?
An agency’s placement in the matrix guides SFS interaction to those agencies in need of the greatest support.
High
Low
Hig
h
Low
Complexity
Rea
dine
ss
•Caution
•Agency At Risk
•All systems go!
•Caution
Statewide Financial System (Internal Use Only)20
Agency Task List Kickoff Meeting
Review June Agency Review June Agency Task ListTask List
Review June Agency Review June Agency Task ListTask List
Presented by:
Ted Paniccia III
Org Readiness
Statewide Financial System (Internal Use Only)21
Agency Task List Timeline
Statewide Financial System (Internal Use Only)22
Next Steps/Significant Dates
June 7th: Agency task lists were distributed to Agency Coordinators.
June 9th: Agency Task List Kickoff Meeting.
June: SFS will be scheduling working sessions with agencies to walkthrough the task lists and review agency-specific tasks.
June 30th: Agency task lists are due to SFS.
July – Go-Live:
SFS distributes agency task lists and scorecards monthly to Agency Coordinators.
Agencies return task lists to SFS by last business day of each month.
Statewide Financial System (Internal Use Only)23
Questions?