Page 1: Static Process Schedule

1

Static Process Schedule

Csc8320 Chapter 5.2

Yunmei Lu

2011-10-03

Page 2: Static Process Schedule

2

OutlineDefinition and GoalModels

Precedence process modelCommunication system model

Future workReference

Page 3: Static Process Schedule

3

What is Static Process Schedule?(SPS)

Scheduling a set of partially ordered tasks on a non-preemptive multiprocessor system of identical processors to minimize the overall finishing time (makespan)[1]

Page 4: Static Process Schedule

4

Implications ?

Mapping of processes to processors is determined before execution of a process.

Process behavior, process execution time, precedence relationships, and communication patterns need to be known before execution

Non-preemptive, once started, process stays on processor until completed.

Page 5: Static Process Schedule

5

Goal ?

Minimize the overall finish time (makespan) on a non-preemptive multiprocessor system (of identical processors)

Scheduling algorithm that can best balance and overlap computation and communication

Page 6: Static Process Schedule

6

Other Characteristics?Optimize makespan NP-completeNeed approximate or heuristic algorithms…For classical definition, inter-processor

communication is considered to be negligible, but for distributed system, it is non-negligible.

Page 7: Static Process Schedule

7

Models?

Precedence Process Model(PPM)Communication Process

Model(CPM)

Page 8: Static Process Schedule

8

Precedence Process Model(PPM)Program is represented by a directed acyclic

graph (DAG) (Figure a in following slide). Precedence constraints among tasks in a program are

explicitly specified. It can be characterized by a communication system

model showing unit communication delays between processors (Figure b in follow slide).

The communication cost between two tasks = unit communication cost in the communication system graph multiply the message units in the DAG.

Page 9: Static Process Schedule

9

Example of DAG

In figure a, each node denotes a task with a known execution timeAn edge represents a precedence relationship between two tasks, arrow represents the priority of execution; The label show message units to be transferred

[Chow and Johnson 1997]

Page 10: Static Process Schedule

10

Precedence process and communication system models

Figure b is an example of a communication system model with three processors(p1,p2,p3), the unit communication costs are non-negligible for inter-processor communication and negligible (zero weight on the internal edge) for intra-processor communication.

Communication cost between A(on p1) and E(on p3) is: 4*2=8

[Chow and Johnson 1997]

Page 11: Static Process Schedule

11

Precedence Process ModelAlgorithms:

List Scheduling (LS): A simple greedy heuristic: no processor remains idle if there are some tasks available that it could process. Without considering communication.

Extended List Scheduling (ELS): the actual scheduling results of LS with communication consideration.

Earliest Task First scheduling (ETF): the earliest schedulable task (with communication delay considered) is scheduled first.

[Chow and Johnson 1997]

Page 12: Static Process Schedule

12

(critical path): is the longest execution path in the DAG

Dashed-lines represent waiting for communication

Algorithms

[Chow and Johnson 1997]

Page 13: Static Process Schedule

13

Communication Process Model(CPM)

Modeled by a undirected graph G, nodes represent processes and weight on the edge is the amount of communication messages between two connected processes.

There are no precedence constrains among processes

Processors are not identical(different in speed and hardware)

Scheduling goal: maximize the resource utilization and minimize inter-process communication.

[Chow and Johnson 1997]

Page 14: Static Process Schedule

14

Communication Process Model

The problem is to find an optimal assignment of m processes to P processors with respect to the target function(called Module Allocation problem):

P: a set of processors. ej(pi): computation cost of execution process pj in processor Pi. ci,j(pi,pj): communication overhead between processes pi and pj. Assume a uniform communicating speed between processors.

GEji

jijiGVj

ij ppcpePGCost,

, ,),(

[Chow and Johnson 1997]

Page 15: Static Process Schedule

15

Communication Process Model Stone’s two processors model to achieve minimum total

execution and communication cost:

Process Cost on A Cost on B1 5 10

2 2 infinity

3 4 4

4 6 3

5 5 2

6 infinity 1

(a) Computation cost

Figure (a) shows execution time of each process on either processor, (b) shows inter-process communication [Chow and Johnson 1997]

Page 16: Static Process Schedule

16

How to map processes to processors? Partition the graph by drawing a line cutting through

some edges Result in two disjoint graphs, one for each process Set of removed edges cut set

Cost of cut set sum of weights of the edges, which represents the total inter-process communication cost between processors

The cost of cut sets is 0 if all processes are assigned to the same node, but it makes no senseComputation constraints (no more k, distribute

evenly…)

[Chow and Johnson 1997]

Page 17: Static Process Schedule

17

How to map process to processors?

The weight assigned to an edge between A and process i is the cost to execute process i on B. [Chow and Johnson 1997]

Minimum-cost cut

Page 18: Static Process Schedule

18

Extend of stone’s two processors model

To generalize the problem beyond two processors, Stone uses a repetitive approach based on two-processor algorithm to solve n-processor problems.

Treat (n-1) processors as one super processor The processors in the super-processor are

further broken down based on the results from previous step.

[Chow and Johnson 1997]

Page 19: Static Process Schedule

19

Problems?Too complexThe optimization objectives of minimizing

computation and communication costs are often conflicting

Therefore, we use some other heuristic solutions

Page 20: Static Process Schedule

20

Some heuristic solutions

Separate the optimization of computation and communication into two independent phases

Merge processes with higher inter-process interaction into clusters of processes

Processes in each cluster are then assigned to the processor that minimizes the computation cost

[Chow and Johnson 1997]

Page 21: Static Process Schedule

21

Problem and Solution Merging processes eliminates inter-processor

communication but may impose a higher computation burden on the processor and thus reduce concurrency.

Solution Merge only processes with communication costs

higher than a certain threshold C Constrain the number of processes in a cluster, like

that total execution cost of the processes in a single cluster cannot exceed another threshold X

[Chow and Johnson 1997]

Page 22: Static Process Schedule

22

Cluster of processes For C = 9, We get three clusters (2,4), (1,6 )and (3,5) Clusters (2,4) and (1,6) must be mapped to processors A and B. Cluster (3,5) can be assigned to A 0r B, according to the goal of

minimizing of computation cost or communication cost Assigning (3,5) to A has a lower communication cost but higher

computation cost If we assign (3,5) to A, the total Cost = 41 ( Computation cost = 17 on

A and 14 on B Communication cost = 6+4= 10)

(2,4))

(1,6))

(3,5))

6

84

[Chow and Johnson 1997]

Page 23: Static Process Schedule

23

Summary of static process schedule Non-preemptive, once a process is assigned to a

processor, it remain there until its execution has been completed

Need prior knowledge of execution time and communication behavior

Scheduling decision is centralized and non-adaptive Not effective Not realistic To find the optimal solution is NP-hard, so always use

heuristic algorithms.

Page 24: Static Process Schedule

24

Future work With the advancements in processors and networking

hardware technologies, parallel processing can be accomplished in a wide spectrum of platforms. Designing diverse platforms makes the scheduling problem even more complex and challenging.

Designing scheduling algorithms for efficient parallel processing, should consider the following aspects:

Page 25: Static Process Schedule

25

CONT… Performance: Scheduling algorithm should produce high

quality solution Time-complexity: It is an important factor insofar as the

quality of solution is compromised. A fast algorithm is necessary for finding good solutions efficiently.

Scalability: Have to consistently give good performance even for large input. Given more processors for a problem, the algorithm should produce solutions with comparable quality in a shorter period of time.

Applicability: Must be applicable in practical environments, so it should take into account realistic assumptions about the program and multiprocessor models such as arbitrary computation and communication weights…

Page 26: Static Process Schedule

26

CONT…

The above mentioned goals are conflicting and thus pose a number of challenges to researchers.

To combat these challenges, several new ideas are: Genetic algorithms Randomization approaches Parallelization techniques Extend DAG scheduling to heterogeneous computing

platforms

Page 27: Static Process Schedule

27

Reference1. Randy Chow, Theodore Johnson, “Distributed Operating

Systems & Algorithms”, Addison Wesley, pp.156-163.2. Yu-Kwong Kwok, Ishfaq Ahmad; Static scheduling algorithms

for allocating directed task graphs to multiprocessors; ACM Computing Surveys; December 1999

3. Sachi Gupta, Gaurav Agarwal, Vikas Kumar “Task Scheduling in Multiprocessor System Using Genetic Algorithm”,10.1109/ICMLC.2010.50

4. Hongze Qiu, Wanli Zhou, Hailong Wang. “A Genetic Algorithm-based Approach to Flexible Job-shop Scheduling Problem” . DOI 10.1109/ICNC.2009.609 

5. Xueyan Tang & Samuel T. Chanson. “ Optimizing Static Job Scheduling in a Network of Heterogeneous Computers”. pp 373- 382, icpp, IEEE 2000