status of fast reactor development in india: april …. puthiyavinayagam associate director, core...
TRANSCRIPT
P. Puthiyavinayagam
Associate Director, Core Design Group
Indira Gandhi Centre for Atomic Research
Kalpakkam, India
Status of Fast Reactor Development in India:
April 2012 – March 2013
46th Annual Meeting of TWGFR, IAEA
IAEA Headquarters, Vienna, May 21-24, 2013
Energy Source
Installed
Capacity
(MWe)
Capacity
(%)
Generation
Apr12-Mar13
(BU)
Generation
Apr12-Mar13
(%)
Thermal (Coal,
Oil & Gas)151530 67.8 760.4 83.9
Hydro 39491 17.7 113.6 12.5
Nuclear 4780 2.2 32.9 3.6
Renewables 27542 12.3 -- --
Total 223343 100.0 906.9 100.0
Current Electricity Scenario
2012-13
Planned capacity addition:17,956 MWe Achieved: 20,623 MWe
Planned Generation: 930 BU Achieved: 912 BU
20 NPP in operation : Capacity factor - 80%, Availability factor - 90%
7 reactors under construction:
2 PWRs expected this year; PFBR under construction)
Strategy for Nuclear Power Growth
Results of a typical case study
1980 1995 2010 2025 2040 2055 2070
0
100
200
300
400
500
600Installed capacity (GWe)
Year
Power profile of PHWR programme
Growth with Pu-U FBRs
Further growth with thorium
FBR Program in India
• Indigenous Design & Construction
• Comprehensiveness in development of
Design, R&D and Construction
• Synthesis of Operating Experiences
• Focus on National & International
Collaborations
• Emphasis on sustaining quality human
resources
• Concepts and innovations to enhance safety
of SFRs
PFBR• 1250 MWt • 500 MWe• Pool Type• UO2-PuO2• Indigenous • From 2014
10 09
07 08
06
04 05
03
02 01
11
12
Ø11950
CFBR• 500 MWe• Pool Type• UO2-PuO2• Twin units• Indigenous • From 2023…
Future FBR• 1000 MWe• Pool Type• Metallic fuel • Serial constr.• Indegenous• Beyond 2025
FBTR• 40 MWt • 13.5 MWe • Loop type • PuC – UC• Design: CEA• Since 1985
Metallic Fuel Development
Activities
FBR-1&2�Design finalisation of reactor
assembly comp.�Component level technology
development�Safety systems design &
development� Integrated RA technology
demonstration (reactor grade)�Capacity expansion – through
EU based SFR as an option
PFBR�Construction�Commissioning �Component testing
& qualification�Design of special
devices for tests�Demonstration of
higher safety margins
�Operation strategy
FBTR�Operation�Fuel & Material Irradiation and Data generation (PIE)�Testing of PFBR devices�Life Extension
SFR & Fuel Cycle Activities - In a Nutshell
Metal Fuel Program� Test pin irradiation (Nat U-Zr; EU-Zr, U-Pu-Zr)� Plan for irradiation in PFBR to test design & safety aspects � Reference core and fuel pin design for test reactor (320
and 115 MWt)� Strategy for MFBR
R & D • Component development &
testing• Testing for demonstration of
safety margins• Clad Materials development• Sensors - Development • Safety engineering
SFR & Fuel Cycle Activities - In a Nutshell
Fuel Cycle• FRFCF awaiting
Govt sanction• Reprocessing –
DFRP• Pyro-processing
development
Human Resources Development & Collaborations
� Reactor Power:20.3 MWt; High power operationfor 1678 h with TG (1406 h)
� Electrical power generated 4.0 MWe
� Energy produced: 32.5 GWh thermal (3.3 BU)
FBTR Operation Highlights
AERB has, in principle,
agreed for extension of
operating license up to
31st March 2018
• Testing of Prototypes of High Temperature
Fission Counters for PFBR
• Irradiation of three pins of sodium-bonded
EU-6%Zr metal fuel started
• Irradiation of structural materials for FR
• Yttria capsule Irradiation - discharged for
separation of 89Sr
• Irradiation of ferro-boron
• Scram drop time measurement and testing
the industrial version of KALMAN filter for
reactivity
20th Campaign Core
FBTR Future Activities & MOX Fuel Irradiation Performance
(a) Fission gas release and
gas composition
(b) Pellet central hole
(C) Fuel pin temperature 0
10
20
30
40
50
60
70
80
90
100
0 4 8 12
Ga
s c
on
ce
ntr
ati
on
(%
)
BU (atom %)
%He %Ar %Kr %Xe % release
MOX Fuel Performance• A 37 pins SA with PFBR type MOX fuel
irradiated in FBTR up to 112 GWd/t• Fuel performance analysis carried out
and compared with PIE results• Important parameters, like fission gas
pressure, clad strains, pellettemperature distribution, central holediameter comapred which isreasonably satisfactory
• Results indicate that good marginexists between the analysis and thedesign safety limits for the target burn-up of 100 GWd/t
Future Activities
• Effect of bowing on core reactivity – experiments
• Irradiation of sodium bonded ternary (U-Pu-Zr) metal fuel pins
• Other irradiations planned : TRISO coated particle type of fuel for CHTR, sol-gel fuel and structural materials for fast reactors.
• Post Fukushima retro-fits have been identified and action will be initiated shortly.
1.6
1.8
2
2.2
2.4
0 50 100 150 200 250
Axial distance from active core bottom (mm)
Fu
el
pe
lle
t ID
(m
m)
at
EO
L
0
500
1000
1500
2000
2500
0 1 2 3 4Tem
pe
ratu
re d
istr
ibu
tio
n a
t P
PL
(d
eg
C)
Fuel pin radius (mm)
BOL
EOL
a b c
PFBR Project – Current Status
Turbine FloorReactor Vault TopDummy CoreOverall Project
� Civil work for NICB, service water pump house, Horton sphere, ventilation stack, DG building and service building completed.
� Erection of major large diameter critical reactor components including rotating plugs completed
� Primary tilting mechanism and primary ramp has been fixed to grid plate. � Erection of fuel handling equipment in fuel building is nearing completion. � Pre-commissioning activities in progress for the completed systems. � All eight SG and four DHX erected. � Commissioning of all 4 emergency DG completed. � Outgoing transmission lines from switchyard have been charged and
connected to southern India grid. � Erection of turbine equipments are nearing completion� Commissioning of DM water, raw water, normal service water and emergency
service water systems have been completed.
PFBR - Major Activities
• Analysis towards demonstration of higher safety margins in design
• Design of special components for tests after criticality and designconfirmation
• Review of commissioning procedures (~ 60nos.) in progress by AERB SG
• Adequacy, appropriateness & format of the details provided for SafetyLimits, Limiting Safety System Settings (LSSS) and Limiting Conditionsfor Operation (LCO) for ‘Protective Instrumentation’ and ‘ReactivityControl & Shutdown Systems’ review by SG-Tech Spec
• Philosophy and Scheme of PSI & ISI Inspection for Components –Review by SG-ISI in progress
• Observations given by the PDSC – Action Taken Reports submitted
• Performance testing and qualification of major components such asInclined Fuel Transfer Machine, Transfer Arm, Absorber rod drivemechanisms and seismic qualification of many systems undertaken
• Lessons gained from PFBR - broad categories (i) material,(ii) fabrication,(iii) welding & (iv) inspection&testing –for future FBR design improvement
Methodology for Isothermal Testing of Sodium Systems During Commissioning Stage
Heat inputs & losses from Primary &
Secondary Systems
� Liquid sodium would be preheated to200°C and filled in primary andsecondary sodium systems. Afterinitial filling, it is essential to maintainthe sodium temperature above 150°Cto avoid freezing at any location.
� Before fuel loading, isothermal testingof primary & secondary systems at450°C planned
� Time required to bring the sodiumsystems to isothermal condition withthe only available heat source viz.operation of sodium pumps.
� Various heat losses from primary andsecondary sodium systems areconsidered during the heatingoperation and the scheme is finalised Evolution of temperature in primary and
secondary sodium during heating
Strategy for Criticality and Operation
� Currently, a strategy for criticality and operation of the reactor in stages is being evolved
� Initial test program, low power physics measurements, physics experiments at various power levels, engineering tests for design confirmation will be carried out.
� Two options are under discussion:
(i) Full core configuration with testing at various subset of power levels
(ii) Progressive core configuration with tests at every stage (30%, 50% and 100%)
� The reactor is scheduled to go critical in Sep 2014 and full power operation will be reached by April 2015.
� A comprehensive and detailed operation strategy and test programme is under discussion.
Design of DND & Sodium Void Special Assemblies
DND & Na void SA
• After commissioning, it is essential to testthe fuel failure detection system & todetermine sodium void worth
• DND system functioning & Calibration :Delayed Neutron Detector SA is designed.DND pin contains natural U+6%Zr metalslug in the place of actual fuel enclosed in aperforated clad. Rest of the pins are dummysteel pins.
• To validate the sodium void worth estimatedby theoretical codes, special SA for sodiumvoid measurement is designed. Twoassemblies are designed - one with sodiumfilled and the other with argon filled. Thevoid is simulated for 1000 mm of active fuelregion and can be loaded in any location inthe core.
Results of Few Studies
• Seismic qualification ofControl & Safety Rod DriveMechanism was furthercontinued to demonstratethe insertability of CSRduring seismic events.
• Fast drop tests wereperformed in water with andwithout seismic excitationunder OBE and SSE.
Drop Time for CSRDM (Without &
With Seismic Excitation) in Water
• Insertability of the control rod into the control subassemblywas demonstrated in all cases.
• Drop time, strain and acceleration were measured atimportant locations.
• Measured increase in drop time is 255 ms / 180ms underOBE/SSE respectively
Test facility
Seismic Qualification of CSRDM in Water
ISI System for Main Vessel & Safety Vessel - Testing
ISI vehicle being manoeuvred
through the knuckle-crown
transition during the trialsMock-up test facility
ISI vehicle into the inter-
space during the trials
ISI Vehicle
ISI Vehicle
MV & SV Sectors
Air Lock Chamber
Plug Handling
Chamber
� System integration completed.� Testing of modules at 150 °°°°C� Comprehensive mockup test
facility with 1/13th of MV and SV sectors
� Trials on the deployment conducted
� ISI vehicle lowered up to crown region with all designed motions including the cable-take up system
� Extensive functional testing and validation of the system in the mock-up facility is underway
Assessment of Core Stability with Reactivity Perturbations
• Stability of core with small and largereactivity pulse perturbations (step andsinusoidal)
• Reactivity pulses of 0.1$, 0.3$ and 0.5$ forone second duration considered - for fullpower operation and part load operation(40% & 20%). Sinusoidal reactivityperturbations of amplitude 0.5 $ andfrequencies 10 Hz, 1 Hz, 0.1 HZ and 0.01Hz – all reactivity feedbacks considered
• Range of reactivity values consideredenvelopes the entire possible range.
• The power does not show any oscillatorybehavior and stabilised in few secondsconfirming reactor stability in all cases
Analysis Towards Higher Safety Margins
Net Reactivity and Normalised Power with
Time (Power =100%,
Flow=100%, Perturbation = 0.1$
Analysis of UTOPA at Low Power Conditions
• UTOPA analysis was carried out at low power to check ifthe reactor comes to another steady state ultimately.
• The analysis was carried out for conditions
(a) at criticality with 50% primary flow through the core
(b) at criticality with 100% primary flow through the core
(c) at 20% electrical power operation (26.4% thermalpower and 50% primary sodium flow).
• From the study, it is concluded that for UTOPA initiated atlow power, the reactor ultimately goes to a steady statewith fuel, clad and coolant temperatures stabilising atlower values than that in case of UTOPA happening atfull power conditions.
• There is no fuel melting in this case.
Integrated Seismic Analysis of SGDHR
• To study the effect of equipment and vesselsconnected to SGDHR lines under seismicexcitation for both OBE and SSE.
• SGDHR main line, Dump line, DHX-A, AHX-A,Storage tank, and expansion tank are modeled
• Envelop response spectrum method is used
• The analyses considered both coupling anduncoupling the equipment and vessels from thelines
• The maximum stress intensity is 169.4 MPa
• The comparison between the coupled anduncoupled analysis reveal that the componentsmainly DHX and storage tank affected theresponse of the loop by affecting its modeshapes, while the other components did notaffect the line or had negligible effect.
Location of Maximum stress intensity
Fig.6:Von Mises Plot
Primary Containment Capacity against CDA
� Higher mechanical energy release during asevere CDA investigated from the structuralintegrity of primary containment and postaccident cooling aspects.
� Parametric study - range of work potentials100-1000 MJ - indicates that primarycontainment has high potential to withstandthe transient forces generated by energyrelease even more than 1000 MJ.
� The sodium level fall due to main vesselexpansion (large permanent deformation) isfound to be acceptable.
� Hence, high uncertainties in the energyrelease assessment are not of greatconcern.
� However the deformations of DHXimmersed in the sodium pool could limit theacceptable work potential - found to be 500MJ from the simulated experimental study
Decay Heat Removal Capacity
of SGDHR after CDA.
Vessel Deformation
Evolution of hot pool and AHX sodium outlet temperatures during prolonged station blackout
REACTOR
M
DUMP TANK
STEEL STACK
SODIUM-AIR HEAT EXCHANGER(AHX)
ARGON
EXPANSION TANK
AIR
NITROGEN
AIR
DAMPERS
Fig. 1: SAFETY GRADE DECAY HEAT REMOVAL CIRCUIT
AIR
T
ARGON
DHX
STEEL CASING
T
MHot pool
T
C
D
� It is essential to ensure that sodium does not freeze during a prolonged SBO.
�Two different SGDHRS operating strategies, viz., (i) controlled manipulation of sodium-to-air heat exchanger dampers of all the 4 AHX and (ii) sequential closing of AHX dampers one after the other
�Sequential closing of AHX dampers is found to be better, because of the number of damper operations required is less.
�By this strategy, with the available battery power and pneumatic power, each of the dampers can be operated 2-3 times and the decay heat removal operation can be continued for more than 10 days without any risk of sodium freezing.
Sodium Freezing during Prolonged Station Blackout
Evolution of neighboring SA thermocouple reading during TIB in a single fuel SA
0
2
4
6
8
10
0 10 20 30 40 50 60
Time (s)
Nei
gh
bo
rin
g S
A T
her
mo
cou
ple
Rea
din
g (
K)
1 2 3
4
5 SCRAM Limit
1 - End of sodium boiling in blocked SA
2 - End of clad melting in blocked SA
3 - End of fuel melting in blocked SA
4 - End of blocked SA hexcan melting
5 - Neighboring hexcan with 55 %
…..residual thickness
Subassembly power (P) = 8 MW
Hexcan thickness (δ) =3.4 mm
Investigation of Total Instantaneous Blockage in a Fuel SA
� During a TIB event, the clad, fuel and hexcan of the affected SA melt –damage radially propagates to other SA
� Knowledge of the number of SA that would get affected by this event (before automatic reactor shut down takes place by core temperature monitoring system) is essential to decide the thermal load on core-catcher.
� Various thermal hydraulic phenomena taking place during this process are complex, involving phase-change heat transfer, moving solid-liquid interfaces and progressive changes in the geometrical configurations of the affected SA.
� A robust one-dimensional thermal hydraulic model has been developed to understand the sequence of various events and the response of the core monitoring thermocouples.
It is established that detection of this event is possible at ~55 s after TIB and the residual thickness of neighbouring hexcan is 55% at that instant suggesting damage is contained within 7 SA.
Investigations of PSP Under Large Suction Re-circulation
Inlet
Outlet
Impeller
Diffuser
Axial velocity (m/s) at impeller eye
100 % speed & 100 % flow
(Negative velocity indicates flow is
downwards without recirculation)
Axial velocity (m/s) at impeller eye
100 % speed & 20 % flow (Positive
velocity around periphery indicates
flow is upwards with recirculation)
� Two primary sodium pumps operating in parallel supply sodium to coreat 7000 kg/s (head - 75 mlc)
� At the end of 50 hrs testing, erosion marks have been observed on thepressure side of all the 5 blades – possible reasons could be eitherrecirculation or non-uniform flow distribution at the impeller eye.
� Detailed CFD studies on (i) suction passage hydraulics, (ii) impeller-diffuser hydraulics and (iii) sump hydraulics, are carried out
� Suction passage renders a non-uniform velocity field at the exit- no.ofwebs has to be increased from 4 to 8 - Extra 4 webs are welded
� Further testing revealed that the performance is smooth.
700
800
900
1000
1100
1200
1300
1400
0 1 2 3 4 5 6 7 8 9 10
Time, s
Cla
d h
ots
pot te
mpera
ture
, K
8 pipe layout
8 pipe layout
SCRAM initiation time = 0.93 s (8 pipe layout)
SCRAM initiation time = 1.22 s (4 pipe layout)
4
Clad hotspot temperature (K) under a pipe rupture event
Finalization of Mechanical Design of Reactor Assembly Components of FBR1&2
• Thermal Hydraulic Analysis: Detailed multi-dimensional thermalhydraulic investigations for design verification:
• Pool mixing
• Gross temperature gradients across components
• Free surface sodium velocity & Gas entrainment
• Main vessel cooling
• Baffle configuration inside the header
• Integrataed thermal analysis of top shield and reactor vault
Temp. distribution on MV during normal operation
Stress distribution in inner vessel under normal condition
403525201596
-3-6
Von mises stress intensity of grid plate top plate under
mechanical loading
Structural Mechanics Analysis:
• Carried out for various loading levelconditions
• Design verification as per RCC-MR code
• Stress analysis of welded grid plate formechanical load
• Stress analysis of primary pipes with pumpheader and grid plate for the mechanicalloading and various thermal transients(slope in absorber location and max slopeof SA)
• Design satisfies RCC-MR code
• Effective damage due to creep-fatigueinteraction has been determined to be< 0.3.
• Design optimization studies of inner vessel
Finalization of Mechanical Design of Reactor Assembly Components of FBR1&2 …
Seismic Analysis:
• Integrated seismic analysis considers main vessel, inner vesseland top shield while the core subassemblies, core supportstructure and grid plate are incorporated by appropriate dynamicequivalent models.
• Analysis was done by response spectrum method to determinerelative displacement between vessels and stresses on thevessel. It is seen that the relative vertical displacements betweencore and absorber rods are acceptable with respect to reactivityvariations.
• The maximum vertical acceleration of core subassemblies is lessthan 0.9 g and hence there is no concern of detachment of wholecore.
• Also, the stress limits are respected at all the critical locations withcomfortable margin for OBE as well as SSE.
Finalization of Mechanical Design of Reactor Assembly Components of FBR1&2 …
Technology Development of Critical RA Components
• Technology development exercises have beencompleted for the key components of reactorassembly which have a bearing on themanufacturing time and in turn on the constructiontime.
• The tri-junction forging for dome shaped roof slab,large diameter bearing, thick plate welding forrotatable plugs and welded grid plate werecompleted in the last year.
• Inner vessel with redan of large single torus and30 m long tubes of steam generator have beensuccessfully completed in the current year.
• Successful completion of technology developmenthas demonstrated the manufacturing feasibilitiesand given confidence for the design improvementsincorporated in the reactor assembly componentsof future FBRs.
Optimised IV Shape
Die & Punch
Profile Check
Design of Ultimate Shutdown System
Ultimate shutdown system (USS) isenvisaged to meet the followingobjectives :
(i) to ensure shutdown of the reactorunder Anticipated Transients WithoutScram (ATWS) events, which in theabsence of shutdown will lead toCDA.
(ii) to limit the consequences followingATWS to Cat IV design safety limit
• Enriched lithium liquid / B4C granules is provided within a pressurizedchamber separated by a fuse plug. During reactor operation, the poisonmaterial is kept above active core.
• Under ATWS, the temperature of the coolant rises and melts the fuse plugonce the temperature exceeds the melting point of fuse plug. Six such SAcan achieve cold shutdown with (n-1) criteria.
• With B4C granules, the worth is more; experiment was conducted tounderstand the flow behaviour of the granules.
I & C Devices Development
Advantages: Less head space required for the removal of the transmitter and
Commercially available.
Radar Type Level Probes
Tests were carried out at different temperature.
Errors are with +/- 10 mm.
Endurance test was carried out at 550 °°°°C for 600 hrs.
Effect of sodium vapour deposit on antenna was observed to be
insignificant
Use of Wireless Technology
Advantages: (i) Avoid congestion in roof slab (ii) Avoid trailing
cable system (iii) Reduction in cable and connector box
Areas identified for deployment : (i) Reactor Assembly
Instrumentation (ii) Mobile fuel handling machines (iii) Trailing
cable system
Tests were carried out to establish its suitability with
commercially available products.
Metallic Fuel Development
• Three sodium bonded metal fuel pins of natural U- 6% Zr undergoingirradiation
• Testing of mechanically bonded natural U/ U- Pu fuel with Zr liner planned
• Need for data from fuel, subassembly behavior and fuel cycle relatedaspects
• Utility of existing facilities like FBTR and PFBR to address the needs
• Smaller dedicated test reactor for the development of total technologiesassociated with metallic fuel including reprocessing facilities may beconsidered.
• Design for reference cores of different power capacity done
• Engineering scale studies on pyroprocessing of irradiated metallic alloyfuels is in progress. U-Zr fuel pins were chopped and processed in anelectorefiner on 1 kg scale.
• An ambient temperature electrorefiner on 10 kg scale has beencommissioned.
• A plant for large scale fabrication of metallic fuel is being set up at IGCARfor partial conversion of FBTR core with metallic fuel SA
Reference Core Physics Design
Preliminary physics design ofreference cores
i. Sodium bonded pin designii. Relatively low critical massiii. Peak LHR close to 450 W/cmiv. Peak burnup of 150 GWd/tv. Single enrichment zonevi. Marginal breedervii. 3-4 experimental locationsviii. U-21%Pu-6% Zr for 320 MWtix. 15.5%Eu-23%Pu-6%Zr for115
MWt
Reactor Power: 320 MWt
: Core (30)
: RB (126)
: Reflector (102)
: CSR (6)
: DSR (3)
: Exp. SA (3)
: Exp. Special SA (1)
Reactor Power: 115 MWt
A. Performance Testing of Transfer Arm in Sodium
Tested at different conditions viz. air at room
temperature, hot air, hot argon and sodium at 200oC.
B. Sodium calibration of all PFBR probes – mutual inductance type (continuous and discreet type)
C. Fabrication and qualification of high temperature ultrasonic transducers for the Ultrasonic Under Sodium Viewer
D. Pin-on-disc type (rotary type) tribometer – To conduct tribology tests
E. Eddy current position sensor for DSR testing
F. Eddy current flow meter testing
G. Studies in Steam Generator Test facility
(test with plugged tube, heat transfer expt, flow instability tests)
H. Multi-purpose loop for testing of sodium components for future FBRs
Component & Device Development and Testing
A
C
D
E
IFTM Chain Test
Qualification of IFTM Chain:
• Two specimen - fatigue and break load testing -cyclic load 0.2 t to 1.5 t
• 97000 cycles completed (ASME, MandatoryAppendix:6) without failure
• Functionality not affected; After fatigue loadtesting, break load test carried out; lowest breakload is 27.1 t
• Accidental conditions – load may go up to 5 t –Large margin exists
Structural Mechanics R&D
Pressure Carrying Capacity of SGDHR Piping after SSE
• A typical pipe bend of the SGDHR piping systemwas tested to quantify the net margin availablein the design beyond SSE limits
• The pipe bend could withstand bending momentof 2.9 times the SSE without any leak in the pipebend.
• Subjected to 180 bars internal pressure –structural integrity reatined
Seismic Qualification of PFBR Components
• A number of components, I&C systemsand sensors have been seismicallyqualified in the shake table facility.
• Few major tests: IFTM gate valves, Fieldinstruments – pressure,flow, tempearture,level measurement
• Shake table test was carried out - 5 OBEfollowed by 1 SSE
• All components qualified
• Experiments were carried out with FerroBoron slabs having 10% and 5% naturalboron in KAMINI
• The foils used are Gold, Rhodium, Indium,Platinum, Copper, Hafnium, Cadmium andManganese.
• Fast, thermal and epi-thermal neutronattenuation pattern
Neutron Attenuation Experiments
Validation of Thermal Design of Top Shield
90
100
110
120
130
140
150
0 50 100 150 200 250 300 350 400
Circumferential Location (Angles in Deg.)
Tem
pera
ture
(oC
)
Roof Slab Inner Shell EL28300
Roof Slab Inner Shell EL28600
Circumferential Temp.
Distribution in Roof Slab-SRP
Annulus
• The Integrated Top Shield Test Facility whichsimulates reactor vault, reactor assembly andassociated cooling systems, was successfullyoperated continuously and the intendedobjectives have been fulfilled. (jet coolingsystem, effectiveness of wire mesh insulation,,tem. Evolution during loss of power, cellularconvection in narrow annulus etc.)
• Sodium aerosols will be released in to the atmosphere in case of Sodium leak from pipes of PFBR
• A test facility was constructed to study the atmospheric dispersion characteristics of sodium aerosols in open atmosphere
• Various sampling techniques used for characterization of the dispersed sodium aerosols
Test facility for Atmospheric Dispersion Studies of Sodium Aerosols during Sodium Fire
Sodium Fire Studies in SOCA facility
Objectives of SOCA facility
Evaluation of different scenarios of sodium firesresultant to CDAEffect of sodium fire on the integrity of importantsafety grade components like Decay HeatExchanger and its piping held in the TSP of PFBREffect sodium fire on the cable materials, and theevaluation resultant secondary fire consequencesDesign optimization of TSP with polar table likestructure for the future fast reactorsGeneration of benchmark data for the validation ofnumerical models developed
Salient features
Experimental Chamber to withstand hightemperature and pressure (500°°°°C and 10 bar)High Pressure Sodium Ejection System with 81nozzles to release sodium in few secondsIntegrated instrumentation system to monitor thetemperature and pressure rise during theexperimentHigh Speed Video Camera system to capture theevents for analysisEfficient Exhaust Gas Treatment System toremove the sodium aerosols from the exit air andrelease clean air into the atmospherePurging systems to conduct the experiments atdifferent oxygen concentrations
Argon Buffer Tank
Experimental Chamber Scrubber system
3D VIEW OF SOCA FACILITY
SOCA chamber Sodium release system
Performance Evaluation of Scrubber unit
Sodium aerosol inlet concentration = 945 mg/m3
Sodium aerosol outlet concentration = 1.3 mg/m3
Scrubber efficiency in removing sodium aerosol=99.9%
Sodium Spray fire Scenario Temperature and Pressure rise
Investigation on structural integrity of DHX
Experimental Results - SOCA facility
Peak temperature of air = 78oCPeak pressure of air = 1.07 bar
Time (s)
Co
nc. (m
g/c
u.m
)before after
Settling behaviour of sodium aerosol
Time (Days)
Co
nc
. (m
g/c
u.m
)
SOFISOFI Facility Facility –– Experimental Program Experimental Program
� Phase – I (Induction heating of notional mass)
� (U metal + SS) – Sodium system using melt mass ~ 1 kg
� (U oxide + SS) – Sodium system using melt mass ~ 1 kg
�Phase – II (Induction heating of small mass)
� (U metal + SS) – Sodium system using melt mass < 20 kg
� (U oxide + SS) – Sodium system using melt mass < 20 kg
�Phase – III (Plasma heating of large mass)
� (U metal + SS) – Sodium system using melt mass > 20 kg
� (U oxide + SS) – Sodium system using melt mass > 20 kg
Crucible, coil and release valve Crucible top assembly Facility view from control room
Sodium Safety Experimental Facilities Sodium Lab-View School
• Controlled & remotelyoperated water injection
• Hydrogen gas analysis
• Transient pressure andtemperature measurement
• SS vessel with toughenedglass viewing windows
• High speed opticalimaging
• SS steam vessel with 20 bar
design pressure at 200oC
• Remotely operated steaminjection
• Hydrogen gas analysis
• Transient pressure andtemperature measurement
• High speed optical imaging
• Ignition of sodium at
controlled atmosphere
• Leak proof Quartz chamber
• Gas analysis, Pressureand temperaturemeasurement
• High speed optical andthermal imaging
• Temperature and pressure
monitoring
• Controlled spraying ofsodium at 500oC
• Robust & compact sodiumsystem with Innovativesodium release valve
• Gas analysis, aerosol,temperature and pressuremeasurement
• High speed optical andthermal imaging
Sodium Pool Fire Sodium Spray Fire Sodium-Water reaction Sodium-Steam reaction
� Two sphere-pac test fuel pinsfabricated and qualified
� These pins contain coarser fractionof (U,Pu) MOX microspheres (780±70 µm) and fine fraction of UO2
microspheres (115 ± 10 µm)vibrocompacted into D-9 clad tube
� Six numbers of test fuels containingsodium bonded enriched U-6 wt.%Zr and alloy slugs were fabricatedas part of development of metallicfuels
Chemistry - Fabrication of Test Fuel Pins
Glove boxes for sphere-pac test pin fabrication
X-ray radiograph of sphere – pac test pins
Facility used for fabrication of sodium bonded test fuel pins with U-Zr and U-Pu-Zr alloy slugs
Set up used for top end plug welding in test fuel pins with metal fuels
� Spot technique equipment housed an argon atmosphere glove box and also qualified for radioactive material handling
� Solidus temperature of Mark-I carbide fuel containing 70% PuCmeasured
� Solidus temperature determined to be 2161 ± 4 K which is in agreement with the value ( 2148 ± 25 K) determined earlier at BARC, Mumbai by incipient melting technique. The present value is more accurate
Solidus-liquidus measurements on U-Zr alloys
Lid and orifice
Equipment used for solidus measurement on Mark-I carbide fuel of FBTR
� Chopping of sodium bonded test fuel pinscontaining natural U-6 wt.% Zr alloy slug in T-91clad tubes and Electrorefining of sodium bonded1 kg of U-6wt% Zr alloy carried out in thedemonstration facility
� U consolidated from the cathode deposit by distillation of salt and melting
� Lab. scale facility for studies on actinide draw down process commissioned in argon atmosphereglove box
� Equilibrations runs between LiCl-KCl-UCl3 and Cd-1 wt.% Li alloy at 500 deg. C being carried out
� Studies on equilibration of halide salts with zeoliteat 1 kg scale at 500 deg. C in a V mixer carried out
Studies related to Pyroprocessing of Alloy Fuels
Chopped pieces of sodium bonded U-Zr pins
Chopped pins loaded in anode basket
Expt. Set up for studies on Actinide draw down process
V- mixer used for studies on equilibration of salt and zeolite
• To recover 10B from nuclear grade boron carbide: Electroextractionmethod
• Process parameters were optimized and product was characterized forchemical purity, specific surface area, size distribution of particles andX-ray crystallite size
• Boron was recovered from boron carbide scrap (rejected pellets), Purityobtained: 92 wt. %.
Chemistry Studies on Boron Extraction
� Regeneration of cold trap by thermaldecomposition of sodium hydride
� Method based on monitoring H2 releasedduring thermal decomposition using a polymermembrane hydrogen sensor (PEMHS)explored
� Tin oxide based trace level hydrogen sensorfor monitoring hydrogen in argon cover gaswas demonstrated
Chemical Sensors
Materials & Metallurgy
� Ion Irradiation studies on ODS alloys
� Integrity Assessment of the Ferritic / Austenitic Dissimilar Weld Jointbetween Intermediate Heat Exchanger and Steam Generator
� Effect of Nitrogen Alloying on Low Cycle Fatigue and Creep-fatigueInteraction of 316LN SS
� Microstructural Analysis of 20% CW Alloy D9after Irradiation in FBTR
� Creep Crack Growth Characterisation of SS 316(N) and P91 welds
� Wall Thickness Loss in 316LN SS Due to Exposure to Sodium
� Long Term Corrosion Evaluation of Candidate Materials in SimulatedFBR Dissolver Solution using Mockup Zircaloy dissolver
� High Nitrogen 304L Stainless steels for Nuclear Waste Storage
� Thermal cycling studies on 9Cr-1Mo steel, 316LSS and Inconel 600
� Studies on Materials & Coatings for Pyrochemical Reprocessing
� Fabrication of irradiation capsules
• Several campaigns for reprocessing ofspent fuel of FBTR with a burnup of 155GWd/t were completed in CORAL
• An empirical model for Pu(VI)distribution coefficients in 30% TBP andits temperature dependency wereformulated. Comparison with literaturedata revealed a reasonably goodagreement between the reportedexperimental and model predictedvalues.
• For dissolution experiments in rotarycontinuous dissolver were carried outwith unirradiated UO2 pellets. Theresults were compared with batchdissolution data.
Comparison of Modeling results
with reported experimental Pu(VI)
distribution coefficients in PUREX
conditions
A view of 150mm 2-stage Rotary
dissolver inside fume hood
Reprocessing Studies
� CEA-IGCAR Collaboration on LMFBR Safety :
� Several collaborative projects undertaken
� Training in Phenix
� ERANOS 2.1, CAST2M, PLEXUS, TRIO-U – Access
� Implementing Agreements
International CollaborationInternational CollaborationInternational CollaborationInternational Collaboration
� AFCEN : RCC-MR codes
� India has adopted RCC-MR for PFBR
� Proposed few revisions based on PFBR experience
� CRP on Passive system reliability
� Control rod withdrawal test during Phenix EOL
� Participation in JHR
Participation in JHRParticipation in JHR
� Development of In-CoreSodium Loop for Irradiation ofMultiple Samples at hightemperature to generate datatowards numerical simulationof fuel pin behaviour(Advanced AusteniticStainless Steels& ODS andOxide fuel) for understandingof fuel safety issues
� Use in FBTR till JHR is readyto receive
� Performance tests at adedicated test sodium facilitydeveloped at JHR
In core sodium loop test facility
� Activities on development of science and technology forSFR and fuel cycle have been continued in an intensemanner.
� PFBR operation strategy is under evolution and supportfor commissioning, safety review, Tech.specs, ISI reviewactivities
� PFBR component testing completed� Analysis for establishing higher margin in design� CFBR design in progress – Mechanical design of RA
completed� Metal fuel program actively pursued� Fuel cycle activities catering to MOX and metal fuel are
in progress� Advanced material development studies� International collaboration in the domain of safety –
bilateral and through IAEA
SummarySummarySummarySummary
Thank youThank you