status of production at lnf e. dane, c. forti, d. pinci, a. sarti – lhcb muon cern 25-may-04...
TRANSCRIPT
Status of production at LNF
E. Dane, C. Forti, D. Pinci, A. Sarti – LHCb Muon CERN 25-may-04
31-Jan10-Feb20-Feb1-Mar
11-Mar21-Mar31-Mar10-Apr20-Apr30-Apr10-May20-May30-May
6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
Chamber
Clo
sing
dat
e
Monday 24-may: closed chamber 30. Will close 2 more this week.
Chamber differential closing rate
0.0
1.0
2.0
3.0
4.0
5.0
6.0
6 8 10 12 14 16 18 20 22 24 26 28 30 32
Chamber number
Rat
e (c
h/w
eek)
5/(work days required) 7/(all days required)
Chamber integral closing rate
Average production rate (ch.14-23)
0.90
1.10
1.30
1.50
1.70
1.90
2.10
2.30
13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
Chamber number
cham
bers
/wee
k
5/(work days required) 7/(all days required)
Panel differential winding rate
2.00
4.00
6.00
8.00
10.00
12.00
14.00
16.00
29-Jan 13-Feb 28-Feb 14-Mar 29-Mar 13-Apr 28-Apr 13-May 28-May
pan
els/
wee
k
7/all days 5/work days
Panel differential winding rate
0.0
2.0
4.0
6.0
8.0
10.0
12.0
14.0
16.0
14-Jan 29-Jan 13-Feb 28-Feb 14-Mar 29-Mar 13-Apr 28-Apr 13-May 28-May
Dif
fere
ntia
l win
ding
rat
e (p
an/w
eek)
N*5/(work-days required) N*7(all days required)
Panel average winding rate
2.00
3.00
4.00
5.00
6.00
7.00
8.00
15-Jan 30-Jan 14-Feb 29-Feb 15-Mar 30-Mar 14-Apr 29-Apr 14-May 29-May
winding date
aver
age
win
din
g ra
te (
pan
/wee
k) N*5/work-days from 23-jan N*7/all days from 23-jan
Reasons of delay
For some time the company producing the cathodes did not send the FR4 foils with cathode pads to the Internormal. In 2 periods: 7-16 Apr. and 27 Apr. 5-May we winded only ground panels (layers L1 and L3) and could not close chambers.
HV-bars drawing current: from 15-Apr we found panels drawingcurrent during the HV test. The possible cause was a set of HV-barswith much humidity in their plastic bag. They were cured by heating(under infrared lights) and, if needed, removing the conformal coatingand cleaning them.Then we started a systematic check of all HV-bars.
We found a panel with tested HV-bars drawing current:we investigated the wire under the microscope but did not find a systematic difference between samples from good vs. bad panels.
Observation of wire from one panel drawing current
We found a panel with tested HV-bars drawing current: we investigated the wire under the microscope but did not understand much.
gold removed
Observation of last 6 spools received
All samples seem OK
Average tension (± sigma) 113 panels of chambers 6-35
55.0
60.0
65.0
70.0
75.0
80.0
85.0
0 20 40 60 80 100 120A
vera
ge t
ensi
on (
g)Wire tensionIn panels with smaller <T> : wires have beenglued at smaller tempe-rature and/or wireshave been cut too soon ( after ~12 hrs)
We reached the
goal < 2 g
0.0
1.0
2.0
3.0
4.0
5.0
6.0
7.0
8.0
9.0
0 20 40 60 80 100 120
Wired panel (C6L1=1)
Sigm
a of
ten
sion
(g)
We have increased thepower of heating lights and fresh gas was put in the clean room conditioning system
Fraction of substituted wires
0.0
1.0
2.0
3.0
4.0
5.0
6.0
7.0
8.0
9.0
10.0
0 20 40 60 80 100
Wired Panel (C6L1=1)
Inte
gral
Fra
ctio
n (
per
mil)
113 panels of chambers 6-35
< 1 per mil
HV test
0
10
20
30
40
50
60
70
20 25 30 35 40 45 50
Humidity (%)
Las
t cu
rren
t (n
A)
100 panels of chambers 6-30
0
100
200
300
400
500
600
700
0 2 4 6 8 10 12 14 16 18 20 22 24 26
ChamberI(
nA
)
A B C D
Uniformity test: currents in gaps and
bi-gaps
B higher
The uniformity betweendifferent gaps of a samechamber and of differentchambers is improvingcompared to cham 1-10
In chamber 22, gap B draws ~ 50% more current320 vs. 220 nA
0
100
200
300
400
500
600
700
0 2 4 6 8 10 12 14 16 18 20 22 24 26
Chamber
I(n
A)
AB CD
C>>D
CD OK
Currents in chamber 24
Currents in chamber 22
Effect of brass bars ch 22 (C,D) C
D
Chamber 22 gaps C,D
The 3 brass bars putbelow the chamberas support,produce a visibleeffect on gap currents
N. of goodgaps in each chamber (1-25)
>95% in range(0.8 – 1.25) G0
14 chambers rejectedless than 4 gaps OK
>90% in range(0.8 – 1.25) G0
8 chambers rejectedless than 4 gaps OK
0
1
2
3
4
5
0 2 4 6 8 10 12 14 16 18 20 22 24 26
ChamberN
. of
good
gap
s
0
1
2
3
4
5
0 2 4 6 8 10 12 14 16 18 20 22 24 26
Chamber
N. o
f go
od g
aps
N. of goodbi-gaps in each chamber (1-25)
>95% in range(0.8 – 1.25) G0
4 chambers rejected:1,2,4,5less than 2 bigaps OK
>90% in range(0.8 – 1.25) G0
2 chambers rejected:4 and 5less than 2 bigaps OK
0
1
2
3
0 2 4 6 8 10 12 14 16 18 20 22 24 26
ChamberN
. of
good
bi-
gap
s
0
1
2
3
0 2 4 6 8 10 12 14 16 18 20 22 24 26
Chamber
N. o
f go
od b
i-ga
ps
End of M3R3 production (52+2 chambers)
End M3R3: 30-jul / 16-aug Start M5R3 in September
23-May-04
22-Jun-04
22-Jul-04
21-Aug-04
8-Feb 23-Feb 9-Mar 24-Mar 8-Apr 23-Apr 8-May 23-May
Chamber closing date
En
d o
f M
3R3
pro
du
ctio
n
2 ch/w 2.5 ch/w
End of M3R3 production (216 wired panels=54 chambers)
2-Jul
12-Jul
22-Jul
1-Aug
11-Aug
21-Aug
31-Aug
10-Sep
14-Jan 3-Feb 23-Feb 14-Mar 3-Apr 23-Apr 13-May 2-Jun
En
d o
f 20
8 p
anel
s w
ind
ing
6 panels/week 8 panels/week
End M3R3 calculated from winding rate: 30-jul / 21-aug
LNF production schedule (updated 24-may-04, ch. 30)
(52+2) M3R3 + 52 M5R3 + 52 M1R4 + 125 M1R3 = 283
0
50
100
150
200
250
300
1-Sep-03
1-Dec-03
1-Mar-04
31-May-04
30-Aug-04
29-Nov-04
28-Feb-05
30-May-05
29-Aug-05
28-Nov-05
27-Feb-06
29-May-06
28-Aug-06
Cha
mbe
rs
Plan Actual M3-M5R3 2/w M1 3/w
Holidays: 2 weeks (Christmas) + 1w Easter + 4w August = 7wEnd prod. = Plan: 15-mar-06 Extrapolation: 26-jun-06
Conclusions
Wire tension:
1. reached the goal < 2 g
2. <T> smaller in 4 panels temperature in winding machine increased.
Wire pitch: never found a wire out of specs (<1.9 or >2.1 mm)
Other procedures are stable and OK: wire soldering machine, panel
preparation, WTM, HV test, chamber assembly.
We are investigating the cause of some panels drawing current even if
HV-bars. May be the wire is dirty ? It gets dirty during soldering procedure ?
Chambers produced up to now: one chamber (N.3) leaks.
Uniformity test: 4 chambers (1,2,4,5) with bi-gaps area < 95% in range
(0.8 – 1.25) G0 we will build 2-4 more M3R3 chambers.
Cosmic ray stand, nearly ready, will allow soon to switch on 6 chambers
together for a ~2 weeks conditioning
HV test
0
10
20
30
40
50
60
70
0 20 40 60 80 100 120
Panel (C6L1=1)
Las
t I
(nA
)
100 panels of chambers 6-30
HV and ground connections check
A wire pad (13 wires x 2 mm pitch) disconnected from HV
A 2.75 cm pad disconnected from ground
Altough the beam flux has a 15 cm diameter, the system can give very precise information
Chamber 12
Gap C
Gap D
... while the gain of the Bi-Gap CD is rather flat.
A bent panel between gaps C and D provides this situation: the gain in the gap C and D not uniform...
What about efficiency, time resolution and cluster size?
... to be investigated with test beam or cosmic rays...
Bi-gap CD