status of rex and commissioning with beam dr. jose alberto rodriguez, be-op-psb (167538)
TRANSCRIPT
Status of REXand
Commissioning with Beam
Dr. Jose Alberto Rodriguez, BE-OP-PSB (167538)
Content:
Status of REX• RF Systems
Commissioning with beam• Completed so far• Next steps
Summary
Jose Alberto Rodriguez, BE-OP-PSB (x167538)8th HIE-ISOLDE Physics Coordination Group Meeting - 2015/09/21
RF Systems:
Jose Alberto Rodriguez, BE-OP-PSB (x167538)
Beam from EBIS5 keV/u
Beam to HIE-ISOLDE2.85 MeV/u
Magnets:
Triplets 6
Doublets 1
Steerers 1H, 1V
Trip
let
IHS
RFQ
Bunc
her
7gap
1
7gap
2
7gap
3
9gap
Trip
let
Trip
let
Trip
let
Trip
let
Trip
let
Dou
blet
HV
Stee
rer
Power converters:
200 A, 50 V 20 (1 spare)
bipolar 3.5 A 2
Diagnostics:
REX HIE-ISOLDE
FCMCPCollimator aperturesBeam attenuators
FCSi detectorScanning SlitsCollimator apertures
Dia
gnos
tics
Dia
gnos
tics
Status of REX
Sectors 10
Turbopumps ~20
Cryopumps 3
Gauges ~25
Vacuum (incl. low energy):
8th HIE-ISOLDE Physics Coordination Group Meeting - 2015/09/21
RF Structure
Final Energy [MeV/u]
4-rod RFQ 0.3
Buncher 0.3
IHS 1.2
7gap 1 1.55
7gap 2 1.88
7gap 3 2.2
9gap 2.85
RF Systems:
Jose Alberto Rodriguez, BE-OP-PSB (x167538)
Beam from EBIS5 keV/u
Beam to HIE-ISOLDE2.85 MeV/u
Magnets:
Triplets 6
Doublets 1
Steerers 1H, 1V
Trip
let
IHS
RFQ
Bunc
her
7gap
1
7gap
2
7gap
3
9gap
Trip
let
Trip
let
Trip
let
Trip
let
Trip
let
Dou
blet
HV
Stee
rer
Power converters:
200 A, 50 V 20 (1 spare)
bipolar 3.5 A 2
Diagnostics:
REX HIE-ISOLDE
FCMCPCollimator aperturesBeam attenuators
FCSi detectorScanning SlitsCollimator apertures
Dia
gnos
tics
Dia
gnos
tics
Status of REX
Hardware refurbishment and commissioning for these systems completed and ready for beam commissioning since wk. 25 (HIE-ISOLDE diagnostics box since wk. 27).
Sectors 10
Turbopumps ~20
Cryopumps 3
Gauges ~25
Vacuum (incl. low energy):
8th HIE-ISOLDE Physics Coordination Group Meeting - 2015/09/21
RF Structure
Final Energy [MeV/u]
4-rod RFQ 0.3
Buncher 0.3
IHS 1.2
7gap 1 1.55
7gap 2 1.88
7gap 3 2.2
9gap 2.85
RF Systems:
Jose Alberto Rodriguez, BE-OP-PSB (x167538)
Beam from EBIS5 keV/u
RF Structure
Final Energy [MeV/u]
4-rod RFQ 0.3
Buncher 0.3
IHS 1.2
7gap 1 1.55
7gap 2 1.88
7gap 3 2.2
9gap 2.85
Beam to HIE-ISOLDE2.85 MeV/u
Trip
let
IHS
RFQ
Bunc
her
7gap
1
7gap
2
7gap
3
9gap
Trip
let
Trip
let
Trip
let
Trip
let
Trip
let
Dou
blet
HV
Stee
rer
Dia
gnos
tics
Dia
gnos
tics
Status of REX
8th HIE-ISOLDE Physics Coordination Group Meeting - 2015/09/21
4-rod RFQ: Functional since wk. 25 (10 Hz, 1ms, power levels up to A/Q = 4.0) Ready for commissioning with beam and physics program New steeper motor for one of the tuners will be installed this week Broken cooling fan will be repaired during the winter shutdown Duty cycle and peak power requirements will be significantly higher next
year (this applies to all the RF systems)
Buncher: Functional since wk. 25 Ready for commissioning with beam and physics program Phase shifter in the LLRF replaced on wk. 32
IHS structure: Powered on wk. 29, ramped up in wk. 30, functional since wk. 35 Ready for commissioning with beam and physics program Problem with LLRF’s control PLC solved on wk. 31 Amplifier disassembled, RF tube replaced on wk. 34
RF Systems:
Jose Alberto Rodriguez, BE-OP-PSB (x167538)
Beam from EBIS5 keV/u
RF Structure
Final Energy [MeV/u]
4-rod RFQ 0.3
Buncher 0.3
IHS 1.2
7gap 1 1.55
7gap 2 1.88
7gap 3 2.2
9gap 2.85
Beam to HIE-ISOLDE2.85 MeV/u
Trip
let
IHS
RFQ
Bunc
her
7gap
1
7gap
2
7gap
3
9gap
Trip
let
Trip
let
Trip
let
Trip
let
Trip
let
Dou
blet
HV
Stee
rer
Dia
gnos
tics
Dia
gnos
tics
Status of REX
8th HIE-ISOLDE Physics Coordination Group Meeting - 2015/09/21
7 gap structures: Functional since wk. 32 Ready for commissioning with beam and physics program Problem with tuner of 7gap3 solved on wk. 32 Problem with reachable range of phases of 7gap1 solved on wk. 36 Possible problem stability of 7gap1 observed (gone, but may reappear)
9 gap structure: Temporary amplifier functional since wk. 25 Ready for commissioning with beam Final amplifier delayed. Will not available this year (implications in the
maximum A/Q (<3.6) and the time structure) Peak power and duty cycle increased on wk. 36 (52 kW, 0.2%: 10 Hz, 200 us) New RF line will be install on wk. 39 to minimize RF losses Problem with remote phase acquisition solved on wk. 36
Commissioning with beamStage 1: REX diagnostics box: Commissioning with beam started on wk. 25 (June 16th) Beam with an A/Q=4.0 was accelerated to 0.3 MeV/u (RFQ output energy) We reached the first diagnostic box and re-commissioned the FC, MCP and collimator wheel on wk. 25 Beam transmission through RFQ for different power levels on wk. 26
Beam in FC after RFQ for different collimator aperture sizes (15, 5, 3 and 1 mm)
MCP image of the beam after the RFQ
Diagnostic box: FC, MCP, Collimator Wheel, Beam attenuators
Jose Alberto Rodriguez, BE-OP-PSB (x167538)
wk. 25 // 0.3 MeV/u
IHS
RFQ
Bunc
her
7gap
1
7gap
2
7gap
3
9gap
Dia
gnos
tics
Dia
gnos
tics
Beam transmission thru the RFQ vs RF power for A/Q=4.0
8th HIE-ISOLDE Physics Coordination Group Meeting - 2015/09/21
Already reported in previous meeting
Stage 2: First HIE-ISOLDE diagnostics box: First diagnostics box of HIE-ISOLDE installed at the end of wk. 27 First beam in FC and to the Si detector with 0.3 MeV/u energy on wk. 28 Systematic characterization by E. D. Cantero and S. Sadovich on wk. 33 and after More details in the next presentation by S. Sadovich
Commissioning with beam
Jose Alberto Rodriguez, BE-OP-PSB (x167538)
wk. 28 // 0.3 MeV/u
IHS
RFQ
Bunc
her
7gap
1
7gap
2
7gap
3
9gap
Dia
gnos
tics
Dia
gnos
tics
Screen shot of BI expert applicationBeam in Faraday Cup
8th HIE-ISOLDE Physics Coordination Group Meeting - 2015/09/21
Beam signal in Si detector after pre-amplifier in “oscilloscope” mode
Diagnostic box: FC, Si detector, Scanning slit, Collimator slit
Quad scan using scanning slits (I = 15 pA)
Commissioning with beam
Jose Alberto Rodriguez, BE-OP-PSB (x167538)
IHS
RFQ
Bunc
her
7gap
1
7gap
2
7gap
3
9gap
Dia
gnos
tics
Dia
gnos
tics
Stage 3: Commissioning and phasing of RF Structures in REX: Cavities and their amplifiers were commissioned after they were turned on by the RF team Many of the problems listed in previous slides were discovered at this time Finally, operational settings (phases and amplitudes) for all RF cavities were determined
8th HIE-ISOLDE Physics Coordination Group Meeting - 2015/09/21
Energy spectrum around zero-crossing phase of the buncher
Phasing of the first 7gap structure
Energy of the beam for different phases and amplitudes out of the 9gap
wk. 28 - 36 @ 1.2 – 2.85 MeV/u
Commissioning with beam
Jose Alberto Rodriguez, BE-OP-PSB (x167538)CM1
XLN
2.03
00
Stage 4: Commissioning the High Energy Beam Transfer (HEBT) line: First attempt to drift beam passed the cryomodule on wk. 33 Second attempt on wk. 38 (rupture disk incident and work related to the SRF tuners) Beam all the way to the last diagnostics box of XT01 at the end of wk. 38
8th HIE-ISOLDE Physics Coordination Group Meeting - 2015/09/21CM2 (2016) wk. 38 @ 2.85 MeV/u
XLN
3.03
00
XLN
4.03
00
XT00
.040
0
XT00
.070
0
XT00
.100
0
XT00
.130
0
XT01.0400
XT01.0900
FC name Measurement(1) BI expert app.
I [epA] (2) calibration for XT01.0900 Transmission
XRFQ.FC20 11.2 pA 10.6 pA (used external Keithley) 1.00
XIHS.FC10 9.3 pA Reading affected by buncher
XLN2.0300 0.47 (1) 9.3 pA (2) 0.88
XLN3.0300 1.09 (1) e - suppressor problem
XLN4.0300 0.48 (1) 9.5 pA (2) 0.90
XT00.0400 0.47 (1) 9.3 pA (2) 0.88
XT00.0700 0.45 (1) 8.9 pA (2) 0.84
XT00.1000 0.45 (1) 8.9 pA (2) 0.84
XT00.1300 0.79 (1) e - suppressor problem
XT01.0400 0.41 (1) 8.1 pA (2) 0.76XT01.0900 0.41 (1) 8.1 pA (used external Keithley) 0.76
End
Tunn
el
SC S
olen
oid
Qua
d
H/V
Ste
erer
s
Overall transmission ~75% Transmission through REX ~88% No mayor problems found (two
electron suppressors don’t work) Optics model seem to work pretty
well, but systematic measurements of beam properties still need to be done
Commissioning with beam
Jose Alberto Rodriguez, BE-OP-PSB (x167538)CM1
Next steps (high priority): Deliver beam from the pilot source before the trap to the end of XT01 Finalize the commissioning of the new TRAP/EBIS/RF timing system and the high level control application Phase SC cavities and measure the energy gain of the beam (benchmark their performance) Test machine scalability in A/Q and in energy
8th HIE-ISOLDE Physics Coordination Group Meeting - 2015/09/21CM2 (2016) wk. 38 @ 2.85 MeV/u
Next steps (lower priority): Systematic measurements of beam properties (e.g. emittance, Courant-Snyder parameters…) Benchmarking optics model and implement modifications if necessary Finalize and commission the field regulation of the power converters for the dipole magnets
Next steps (medium priority): Improve beam transmission Individual calibration of each Faraday cup Cross calibration of the two Si detectors and the dipole magnets and determine error bars in beam
energy measurements Check calibrations / phases after installation of new RF line for 9gap and steeper motor for tuner of RFQ Systematic commissioning of all the devices in the beam diagnostics boxes Systematic checks with beam of polarities of all optics magnetic elements Finalize and commission the beam diagnostics high level control application
Summary
Jose Alberto Rodriguez, BE-OP-PSB (x167538)
Status of REX: Hardware refurbishment and commissioning of power converters, magnets, diagnostics
and vacuum systems completed before wk. 25 All RF systems operational at the same time since wk. 35 (some of them since wk. 25) Due to delay in delivery of the final 9gap amplifier, we will need to use the temporary
amplifier (constrains in maximum A/Q and time structure deliver to users)
Commissioning with Beam: Commissioning started in wk. 25 and progressed as hardware was ready 12C4+ beam produced in the charge breeder has been accelerated to 2.85 MeV/u (REX
nominal final energy) and transported to the end of the XT01 experimental line A lot of work still needs to be completed before the start of the physics program
8th HIE-ISOLDE Physics Coordination Group Meeting - 2015/09/21
Additional Slides
Jose Alberto Rodriguez, BE-OP-PSB (x167538)8th HIE-ISOLDE Physics Coordination Group Meeting - 2015/09/21
Constrains imposed by the temporary amplifier
Jose Alberto Rodriguez, BE-OP-PSB (x167538)
Limits on peak power
translate into
Limits on the repetition rate translate into
Limits on the maximum A/Q
of the beam
Possible beam contamination
Limits on the maximum A of the beam
Stripper foils for light ions
Longer breeding time
Lower breeding efficiency
Lower beam current
Non-usable or lower quality experimental data for heavy ions
Force to operate in non-optimal of the CSD
Constrains on the time structure
delivered to users
Limits on duty cycle
translate into
Unable to stretch
beam pulse
Lower beam current
Increase operational complexity (set-up time, risk,
reduces beam quality…)
Limits on half-life of the beam
Fortunately, only a few of these affect the experiments planned for 2015 Having the amplifier for the 2016 experimental campaign is an absolute must!
Increased pile-up
Lower effective beam current
Fewer and longer experiments (ie.
reduced physics output)
8th HIE-ISOLDE Physics Coordination Group Meeting - 2015/09/21