status of the harmonic module acc39 - desy - flash · bcp done at argonne 21 activities in a0 at...

10
1 Elmar Vogel DESY Beschleuniger-Betriebs-Seminar, Grömitz, 17-20 November 2008 Status of the Status of the 3 3 rd rd Harmonic Module ACC39 Harmonic Module ACC39 Elmar Vogel for everyone involved in the FLASH 3 rd harmonic system purpose of the system the subsystems and the work distribution survey on all the work done test results actual status what comes next FLASH Seminar at January 26 th 2010 2 Bunch-Compression at FLASH 3 Linearization by 3 rd harmonic Additional effects: space charge, longitudinal wake fields, ... Sum voltage required: ~19 MV Using nine-cell superconducting cavities 4 The geometry of 3.9 GHz cavities follows the one of 1.3 GHz cavities pick up HOM coupler 346 mm 506 mm 38.4 mm power coupler HOM coupler With 14 MV/m we need four cavities … 5 FNAL build 3.9 GHz module ACC39 ACC39 contains four! 3.9 GHz cavities. 6 DESY colleagues are taking care of the power rf (MIN) 7 cavity tuner motor drivers (MCS2) 8 rf-control (MSK) klystron proportional gain DAC ADC set point table feed forward table beam compensation factor beam monitor ADC track back AFF table reset FIR AFF gain several cavities 9 cryogenic integration (MKS1)

Upload: others

Post on 05-Jul-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Status of the Harmonic Module ACC39 - DESY - FLASH · BCP done at Argonne 21 Activities in A0 at Fermilab ... 6/02/2009. 6 Cavity to cavity alignment 46 complete 47 Outer module vessel

1

Elmar VogelDESY Beschleuniger-Betriebs-Seminar, Grömitz, 17-20 November 2008

Status of theStatus of the33rdrd Harmonic Module ACC39Harmonic Module ACC39

Elmar Vogel for everyone involved in the FLASH 3rd harmonic system

• purpose of the system• the subsystems and the work distribution• survey on all the work done• test results• actual status• what comes next

FLASH Seminar at January 26th 2010

2

Bunch-Compression at FLASH3

Linearization by 3rd harmonic

Additional effects: space charge, longitudinal wake fields, ...

Sum voltage required: ~19 MV

Using nine-cell superconducting cavities

4The geometry of 3.9 GHz cavities follows the one of 1.3 GHz cavities

pick up

HOM coupler

346 mm506 mm

38.4 mm

power coupler

HOM coupler

With 14 MV/m we need four cavities …

5

FNAL build 3.9 GHz module ACC39

ACC39contains four!3.9 GHz cavities.

6DESY colleagues are taking careof the power rf (MIN)

7

cavity tuner motor drivers (MCS2)8

rf-control (MSK)

klystron

proportionalgain

DAC ADC

set pointtable

feedforwardtable

beam

compensationfactor

beam monitor

ADC

trackback

AFFtable

reset

FIR AFFgain

several cavities

9

cryogenic integration (MKS1)

Page 2: Status of the Harmonic Module ACC39 - DESY - FLASH · BCP done at Argonne 21 Activities in A0 at Fermilab ... 6/02/2009. 6 Cavity to cavity alignment 46 complete 47 Outer module vessel

2

10

beam and coupler vacuum (MVS)11power coupler assembly and

processing (MHF-sl)

12cavity and module tests(MHF-sl & FNAL colleagues)

13

study of beam dynamics (MPY)

−20 −15 −10 −5 0 5 10 15 20−20

−15

−10

−5

0

5

10

15

20total projected emittance [mm mrad]

H1GUN + H2GUN [A]

V1G

UN

+ V

2GU

N [A

]

1.8

2

2.2

2.4

2.6

2.8

3

3.2

3.4

3.6

3.8

14ACC39 has been inserted in FLASHafter ACC1 and before BC2

15Some time ago,the work started at Fermilab…

16Development, production, and test of the cavities and the module

17

The basic design

pick up

HOM coupler

346 mm506 mm

38.4 mm

power coupler

HOM couplerIdea:

• shape of1.3 GHz cavities

• cells 3x smaller

• beam pipe 2x smaller

• coupler, rf pick-ups und HOM antennas similar to 1.3 GHz

• initial HOM f-part design like at 1.3 GHz, but 3x smaller

18Cavity fabricationin the area of Chicago / Illinois

Page 3: Status of the Harmonic Module ACC39 - DESY - FLASH · BCP done at Argonne 21 Activities in A0 at Fermilab ... 6/02/2009. 6 Cavity to cavity alignment 46 complete 47 Outer module vessel

3

19Mechanical cavity fabrication:Electron beam welding at Sciaky

20Chemical cavity surface treatment:BCP done at Argonne

21

Activities in A0 at Fermilab

‘A0’

22

High pressure rinsing23

Clean rooms for assembly work24

Cavity in vertical insert

25

Vertical test cryostat26

Vertical cavity testing27

Redesign of HOM f-parts

Page 4: Status of the Harmonic Module ACC39 - DESY - FLASH · BCP done at Argonne 21 Activities in A0 at Fermilab ... 6/02/2009. 6 Cavity to cavity alignment 46 complete 47 Outer module vessel

4

28

Typical results of vertical tests

gradient (MV/m) (at 1.8 K)

0 5 10 15 20 25

2E9

4E9

6E9

8E9 un

l oad

edqu

ality

fact

or

1E9

measurements by FNAL

29

Inserting cavities in He vessels30

Helium vessel leak check

31

Preparation for horizontal test32

Meson Hall and MP9 at Fermilab

‘Meson Hall’

‘MP 9’

33

Horizontal cavity test stand

34

Horizontal cavity testing35

Performance of the four cavities

18 MV/m22 MV/mF3A3

18.3 MV/m24 MV/mF3A8

18 MV/m22 MV/mF3A5

26 MV/m

maximum horizontalgradient achieved

21.7 MV/mF3A7

no field emission measured below a

gradient ofcavity

36

Double and one leg HOM f-parts

Page 5: Status of the Harmonic Module ACC39 - DESY - FLASH · BCP done at Argonne 21 Activities in A0 at Fermilab ... 6/02/2009. 6 Cavity to cavity alignment 46 complete 47 Outer module vessel

5

37

Different HOM absorption spectra1st and 2nd dipole path bands for cavities #5 and #7.

2nd dipole path band for cavity #5 is narrower than for cavity #7.

measurements from Timergali Khabiboulline

38Cavity sequence formost ‘optimal’ HOM damping...

Each cavity to cavity beam pipe will have both types of HOM dampers (DLF and SLF) and the cavity adjacent to ACC1 a SLF HOM damper.

(Beam from right to left)

39Clean room for thecavity string assembly

40

Experts discussing the assembly41String of three cavities

(December 2008)

42Leaving the clean room(January 2009)

43

Cold mass assembly44

Cold mass assembly (continued)45Transportation for further

assembly in Technical Division Hall

6/02/2009

Page 6: Status of the Harmonic Module ACC39 - DESY - FLASH · BCP done at Argonne 21 Activities in A0 at Fermilab ... 6/02/2009. 6 Cavity to cavity alignment 46 complete 47 Outer module vessel

6

46Cavity to cavity alignment complete

47

Outer module vessel and cantilever48

Preparation of the transporation

49

The ‘big box’50

Air transport (April 2009)51

Roller floors

52

Charles de Gaulle April 27th 200953Checking shock lock data and the

cavity vacuum

54

Truck transportation

Page 7: Status of the Harmonic Module ACC39 - DESY - FLASH · BCP done at Argonne 21 Activities in A0 at Fermilab ... 6/02/2009. 6 Cavity to cavity alignment 46 complete 47 Outer module vessel

7

55

Arriving Hamburg...56

... and DESY57

Unpacking

58

Everything ok with ACC39?59

Needle bearing revision60

Needle bearings

61

Coupler installation (June 2009)62

Intermediate storage in Hall 163CMTB adaptation 1.3 to 3.9 GHz

August 2009

Page 8: Status of the Harmonic Module ACC39 - DESY - FLASH · BCP done at Argonne 21 Activities in A0 at Fermilab ... 6/02/2009. 6 Cavity to cavity alignment 46 complete 47 Outer module vessel

8

64

ACC39 transport to CMTB65

Installation at CMTB66Connecting feed- and end cap

(September 2009)

67

Wave guides installed 68

Checking the klystron safety69

Checking tuner movements

70Warm coupler processing(October 2009)

71Checks while changing waveguides

72Troubles with the HV connectionto the klystron modulator

Page 9: Status of the Harmonic Module ACC39 - DESY - FLASH · BCP done at Argonne 21 Activities in A0 at Fermilab ... 6/02/2009. 6 Cavity to cavity alignment 46 complete 47 Outer module vessel

9

73Tuning the cavities on resonance after cool down (October 2009)

74

Module & cavity performance

F3A8 F3A3 F3A7 F3A50

5

10

15

20

25

grad

ient

[MV

/m]

cavity

Fermilab tests vertical horizontal start field emission

DESY tests CMTB start field emission

FLASH design value 14 MV/m

75

Cross talk between the cavities

Coupling matrix:

⎟⎟⎟⎟⎟

⎜⎜⎜⎜⎜

1107.0002.0003.0123.01035.0008.0022.0016.01546.0002.0005.0051.01

76Testing the rf control(November 2009)

77

Who ordered this oscillation?78

Is it caused by vibrations?

79

Or by the electronics?80

RF control stability finally achieved

See FLASH Seminar Talk ‘Status of 3.9 GHz LLRF’from Markus Hoffmann given at January 12th 2010

81

Quenching HOM (at cavity #4)

Page 10: Status of the Harmonic Module ACC39 - DESY - FLASH · BCP done at Argonne 21 Activities in A0 at Fermilab ... 6/02/2009. 6 Cavity to cavity alignment 46 complete 47 Outer module vessel

10

82

ACC39 leaving CMTB83

Survey check (December 2009)84

Flying modules (December 2009)

85

Approaching final position86

ACC39 has been inserted in FLASH87

What comes next?

• remaining technical installation

• technical commissioning (start: February)

• cool down (end of March)

• commissioning with beam (start: mid April)

88

Acknowledgements

So many colleagues form different laboratories have been or are contributing to and working on the third harmonic rf system and ACC39 that they do not fit in a readable way into this page.

Thank you very much to all of them!