    STATUTORYREQUIREMENTS /

    CLEARANCESWELCOME TO ALL

  • 7/31/2019 Statutory Clearances

    2/16

    STATUTORY REQUIREMENTS /CLEARANCES

    WHY ?

    TO INSURE HEALTHY ENVIRONMENT

    TO TAKE CARE OF SAFETY ANDWELFARE OF WORKMEN

    TO INSURE SAFETY OF MACHINES

  • 7/31/2019 Statutory Clearances

    3/16

    STATUTORY REQUIREMENTS /CLEARANCES

    WHAT ARE THE AREAS ?

    CLEARANCES BEFORE AWARD OF PROJECT SITING CRITERIA & RELATED CLEARANCES

    EIA STUDY SOCIO-ECONOMIC STUDY

    CLEARANCES AFTER AWARD OF PROJECT CLEARANCE FROM BOILER INSPECTOR

    CEA CLEARANCES EXPLOSIVE CLEARANCE LPA CLEARANCE MISC. CLEARANCES

  • 7/31/2019 Statutory Clearances

    4/16

    CLEARANCES BEFORE AWARD

    Should be avoided within 25 kms of theouter peripheries of Metropolitan cities

    National Park and Wildlife sanctuaries

    Ecologically sensitive areas like tropicalforests, biosphere reserves, National Parks &Sanctuaries, important lakes and coastalareas rich in coral formations.

    500 m of HTL, a buffer zone of 500 mts shouldbe kept free

  • 7/31/2019 Statutory Clearances

    5/16

    CLEARANCES BEFORE AWARD

    Chimney should not fall within the approachfunnel of the runway.

    500 mts. Away from National Highway, Railway

    and Flood Plains of the Riverine Systems 10 kms away from archaeological, historical,

    cultural, religious or tourist importance anddefense installations

    No forest or prime agricultural land should beutilized for setting up of TPS, or for ash disposal. Should not be on coal bearing area.

  • 7/31/2019 Statutory Clearances

    6/16

    EIA STUDY

    Environmental Impact Assessment (EIA ) StudyBroad scope includes: Field studies Impact assessment

    Preparation of the EIA document covering Land Use, Water Use,Soils, Geology, Hydrology, Sediments, Water Quality, Meteorology,Air Quality, Terrestrial Ecology, Aquatic Ecology, Noise, RiskAssessment, Ash Utilization and Occupational Health and Safety.Services (based on 12 months data).

    EIA report covers the existing environmental baseline conditions,impacts due to operation of the power plant, EnvironmentalManagement Plan, post study-monitoring programme, OccupationSafety & Health and Risk Assessment.

  • 7/31/2019 Statutory Clearances

    7/16

    SOCIO-ECONOMIC STUDY

    Socio-economic StudyBroad scope includes : Assessing the number of Project Affected Persons (PAPs), overall

    impact due to land acquisition and establishment of the project on theaffected villages and its populace in general and the PAPs , whose

    livelihood is affected (directly or indirectly) in particular. To establish base line condition, assess the social-economic impacts

    and to what extent, analyse the impoverishment risk to find out themost vulnerable section of the society and to suggest the initiativesto address these issues.

    To establish social inventory of affected villages covering the social,cultural, economic, historical, political and environmental aspects.

    To identify indicators for monitoring the standards of living of PAPsin future.

  • 7/31/2019 Statutory Clearances

    8/16

    CLEARANCES REQUIRED

    Input AgencyLand Availability State Government

    Water Availability State Irrigation Deptt.CWC / MOWR

    Coal Linkage Dept. of Coal (SLC)

    Gas/Liquid Fuel

    Availability

    Ministry of Petroleum &

    Natural GasFuel Transportation Railways /

    GAIL/Oil Companies

  • 7/31/2019 Statutory Clearances

    9/16

    CLEARANCES REQUIRED

    Clearance Agency

    Clearance for Chimneyheight

    Airports Authority of

    India

    Defence Clearance Ministry of Defence

    Public Hearing SPCB

    Environment Clearance MOEF

    Forest Clearance State Forest Department/ MOEF

    R&R of displaced family Concerned State Govts

  • 7/31/2019 Statutory Clearances

    10/16

    CLEARANCES AFTER AWARD

    CLEARANCES FROM CHIEF BOILER INSPECTOR ASPER IBR-1950

    1. MANUFACTURING

    Submission of drawings before fabrication

    Test certificates of materials used

    Testing of High Pressure Welder

    Inspection at every stage of fabrication

    Hydro testing and stamping

  • 7/31/2019 Statutory Clearances

    11/16

    CLEARANCE FROM BOILERINSPECTOR

    2. INSTALLATION Submission of all clearances from inspector in the state of

    manufacture to the inspector in the state of installation Registration of agency for the start of work

    Test of welder for site welding Offering all pr. Parts for inspection Submitting all the documents for welding checks at site Witnessing of hydro test Clearance for charging of boiler Witnessing of safety valve floating

    BOLER OPERATING CERTIFICATE IS OBTAINED BY INSPECTORWHICH IS RENEWED EVERY YEAR AFTER SPECIFIED CHECKESUNDER INDIAN BOILER ACT-1923

  • 7/31/2019 Statutory Clearances

    12/16

    CEA CLEARANCE

    APPROVAL TO ENERGISE THE HV/EHV OVERHEAD

    TRANSMISSION LINES & UNDERGROUND CABLES

    APPROVAL TO ENERGISE THE HV/EHV

    APPARATUS/INSTALLATIONS

  • 7/31/2019 Statutory Clearances

    13/16

    EXPLOSIVE CLEARANCE

    TO REGULATE THE MANFACTURE, POSSESSION, USE,SALE & TRANSPORT OF EXPLOSIVES, CLEARANCEUNDER INDIAN EXPLOSIVE ACT IS REQUIRED FOR

    HYDROGEN GENERATION PLANT

    LDO, HFO OR ANY OTHER FUEL TANKCHLORINATION SYSTEM

  • 7/31/2019 Statutory Clearances

    14/16

    LPA CLEARANCE

    FIRE FIGHTING SYSTEM SHOULD BE INSTALLED AS

    PER THE GUIDELINES OF LPA

    -Insurance of the equipments and systems installed

    in project can only be obtained after installation of

    fire fighting system

  • 7/31/2019 Statutory Clearances

    15/16

    MISCELLANEOUSCLEARANCES/REQUIREMENTS

    LABOUR LICENCE

    PF CLEARANCE

    LOAD TEST OF LIFTING TOOLS AND TACKLES

    ENFORCEMENT OF SAFETY RULES AND

    APPOINTMENT OF SAFETY OFFICER UNDER

    FACTORIES ACT-1948