Page 1: Steve Craker K-12 Team Lead Geoff Overland IT and Data Center Focus on Energy Increase IT Budgets with Energy Efficiency

Steve CrakerK-12 Team Lead

Geoff OverlandIT and Data Center

Focus on Energy

Increase IT Budgets with

Energy Efficiency

Page 2: Steve Craker K-12 Team Lead Geoff Overland IT and Data Center Focus on Energy Increase IT Budgets with Energy Efficiency

Agenda• Focus on Energy overview• IT and data center energy growth• Demand and supply energy• Energy-efficient computing• School and government IT project results

Page 3: Steve Craker K-12 Team Lead Geoff Overland IT and Data Center Focus on Energy Increase IT Budgets with Energy Efficiency

Benefits of Energy Efficiency

• Save money• Protect the environment• Increase reliability of energy resources

by controlling Wisconsin’s growing demand

• Promote in-state economic development

Page 4: Steve Craker K-12 Team Lead Geoff Overland IT and Data Center Focus on Energy Increase IT Budgets with Energy Efficiency

• Wisconsin’s statewide program for energy efficiency and renewable energy

• Legislature created in 1999; expanded in 2005

• Helps implement projects that would not occur otherwise

• Customer eligibility based on electric and/or natural gas utilities

What Is Focus on Energy?

Page 5: Steve Craker K-12 Team Lead Geoff Overland IT and Data Center Focus on Energy Increase IT Budgets with Energy Efficiency

• More than 91,000 businesses and 1.7 million residents have participated in Focus

• More than 3,000 Wisconsin businesses partner with Focus to sell energy related goods and/or services

• Since 2001, Focus has helped Wisconsin residents and businesses save more than $319 million in annual energy costs

Focus Accomplishments

Page 6: Steve Craker K-12 Team Lead Geoff Overland IT and Data Center Focus on Energy Increase IT Budgets with Energy Efficiency

• Technical expertise• Education and training• Financial assistance• Services are available for energy efficiency

and renewable energy projects for businesses and residences– Single and multifamily homes– Commercial, industrial, agribusiness, and

school/government buildings

Focus on Energy Services

Page 7: Steve Craker K-12 Team Lead Geoff Overland IT and Data Center Focus on Energy Increase IT Budgets with Energy Efficiency

Focus for Businesses

• Standard “prescriptive” incentives on lighting, HVAC equipment, solar hot-water systems <8 panels: can be submitted by the customer

• Incentives on custom projects are calculated by estimated energy savings; up to 30% of project’s cost and max of $250,000– Must work with a Focus Energy Advisor on custom

projects

Page 8: Steve Craker K-12 Team Lead Geoff Overland IT and Data Center Focus on Energy Increase IT Budgets with Energy Efficiency
Page 9: Steve Craker K-12 Team Lead Geoff Overland IT and Data Center Focus on Energy Increase IT Budgets with Energy Efficiency

Efficient IT Opportunities• 2011 prescriptive incentives

– PC network power management– Server virtualization– Thin client conversion

• Custom incentives– Energy-efficient cooling, airflow management– Multi-user computing– Energy-efficient UPS– Others…

Page 10: Steve Craker K-12 Team Lead Geoff Overland IT and Data Center Focus on Energy Increase IT Budgets with Energy Efficiency

Data Centers are Information Factories

• Data centers are energy intensive facilities– Server racks now designed for >25+ kW

– Surging demand for data storage

– Typical facility ~1MW (can be >20 MW)

– Nationally 1.5% of U.S. electricity consumption in 2006– EPA Report to Congress (Public Law 109-431)

• Growing faster than any other electric load• Significant data center building boom

– Power, cooling constraints in existing facilities

Page 11: Steve Craker K-12 Team Lead Geoff Overland IT and Data Center Focus on Energy Increase IT Budgets with Energy Efficiency

Energy Issues Abound

“Over the next five years, power failures and limits on power availability will halt data center operations at

more than 90% of all companies.”AFCOM Data Center Institute’s Five Bold Predictions, 2006

“By 2008, 50% of current data centers will have insufficient power and cooling capacity to meet the

demands of high density equipment.” Gartner press release, 2006

“Survey of 100 data center operators: 40% reported running out of power, cooling capacity and, to a lesser extent, space without sufficient notice.”

Aperture Research Institute

Page 12: Steve Craker K-12 Team Lead Geoff Overland IT and Data Center Focus on Energy Increase IT Budgets with Energy Efficiency

The Rising Cost Of IT Ownership

• 2000-2006—computing performance increased 25x, energy efficiency only 8x

• Cost of electricity, supporting infrastructure surpassing capital cost of IT equipment over its useful life

• Split incentives—IT and facility costs are responsibility of different parts of organization

Source: The Uptime Institute, 2007

Page 13: Steve Craker K-12 Team Lead Geoff Overland IT and Data Center Focus on Energy Increase IT Budgets with Energy Efficiency

EPA Projected Energy Use

Source: EPA Report to Congress, U.S. DoE, Office of Energy Efficiency & Renewable Energy

Page 14: Steve Craker K-12 Team Lead Geoff Overland IT and Data Center Focus on Energy Increase IT Budgets with Energy Efficiency

Supply and Demand Energy

Source: Emerson Network Power

Page 15: Steve Craker K-12 Team Lead Geoff Overland IT and Data Center Focus on Energy Increase IT Budgets with Energy Efficiency

IT Energy Supply Side

Source: Emerson Network Power

Page 16: Steve Craker K-12 Team Lead Geoff Overland IT and Data Center Focus on Energy Increase IT Budgets with Energy Efficiency

2010 School and Government Results on IT Projects

• 69 completed projects across 36 districts and agencies

• Peak demand reduction of 198 kW• Energy reduction of 2,589,597 kWh• Annual savings of $207,000• $135,754 in cash incentives

Page 17: Steve Craker K-12 Team Lead Geoff Overland IT and Data Center Focus on Energy Increase IT Budgets with Energy Efficiency

Potential was Greater in 2010

• Offered $243,000 for virtualization projects• Server virtualization ($280 + $150 = $430)

– Anticipated savings 3,500 kWh per server– At $0.08 /kWh, annual savings of $280

• Thin client conversion ($32 + $60 = $92)– Anticipated savings of 400 kWh per PC replaced– At $0.08 /kWh, annual savings of $32 per PC

Page 18: Steve Craker K-12 Team Lead Geoff Overland IT and Data Center Focus on Energy Increase IT Budgets with Energy Efficiency

Improvement Areas

• Air management• Free cooling – air or water• Environmental conditions• Centralized air handlers• Low pressure drop

systems• Fan efficiency• Cooling plant optimization• Direct liquid cooling• Right sizing/redundancy• Heat recovery• Building envelope

• UPS, transformer efficiency

• High voltage distribution

• Premium efficiency motors

• DC power use• Standby generation• Right sizing/

redundancy• Lighting – efficiency

and controls• On-site generation

Electrical• Power supply• Standby/sleep

power modes• IT equipment fans• Virtualization• Thin client &

Multiuser PCs• Load shifting• Storage• ENERGY STAR• CRT Replacement• PC Refresh• 1:1 Initiative

IT Cooling

Page 19: Steve Craker K-12 Team Lead Geoff Overland IT and Data Center Focus on Energy Increase IT Budgets with Energy Efficiency

Financial Analysis

• Annual savings in dollars• Simple payback calculation

net investment /annual savings = payback period

• Lifecycle costs and savings

Page 20: Steve Craker K-12 Team Lead Geoff Overland IT and Data Center Focus on Energy Increase IT Budgets with Energy Efficiency

Selling a Facility Project

• Example—lighting – Old technology vs. new technology

• Cost for repair or replacement

– Old energy vs. new energy• Difference in operating costs

– Old maintenance cost vs. new maintenance cost

– Life of equipment

Page 21: Steve Craker K-12 Team Lead Geoff Overland IT and Data Center Focus on Energy Increase IT Budgets with Energy Efficiency

Selling IT Projects

• Exactly the same– Technology improvement

• Repair or replace

– Energy savings• Operating costs

– Process efficiency• Improvement in work being completed

– Life of equipment

Page 22: Steve Craker K-12 Team Lead Geoff Overland IT and Data Center Focus on Energy Increase IT Budgets with Energy Efficiency

Thank you!Stop by booth 614

Focus on Energy

Phone 800.762.7077

Email [email protected]

Web focusonenergy.com