story board -eastside utilities wwtp project (2)
TRANSCRIPT
BUILDING STRONG®
Bagram Airfield Waste Water Treatment Plant
01 OCT 2014
Who: U.S. Army Corps of Engineers, Transatlantic Afghanistan District
What: The Wastewater Treatment Plant (WWTP) is one component of the $26.8M Eastside Utilities Infrastructure Project at Bagram Airfield. The new WWTP, located adjacent to the existing plant, increases the
Where: Bagram Airfield, Afghanistan
When: 01 October 2014
Why: To increase capacity of current wastewater treatment systems and disposal of waste water
Way Ahead: WWTP is 90% complete and scheduled to finish at the end of CY14. Contractor is making significant progress on commissioning the process equipment and continues to complete civil works including site grading & area drainage.
Commissioning of new Equalization Tank #1
Existing WWTP Aeration Tanks (foreground) and new WWTP (background)
New Headworks structure, first stage of processing , exterior equipment designed to screen and direct effluent to either the new or Existing WWTP