strategic level management and project success increase

Upload: konstantinosk

Post on 04-Apr-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/30/2019 Strategic Level Management and Project Success Increase

    1/62

    Strategic level management and

    project success increase

    KONSTANTINOS KONSTANTINIDIS

    A dissertation submitted in partial fulfillment of the requirements forthe degree of MSc Construction Project Management

    Supervisor: Dr. Graeme Bowles

    Heriot- Watt University

    School of the Built Environment

    March 2012

  • 7/30/2019 Strategic Level Management and Project Success Increase

    2/62

    ii

    DECLARATION

    I Konstantinos Konstantinidis, confirm that this work submitted for assessment is my

    own and is expressed in my own words. Any uses made within it of the works of other

    authors in any form (e.g. ideas, equations, figures, text, tables, programmes) are

    properly acknowledged at the point of their use. A full list of the references employed

    has been included.

    Signed: .

    Date: ..

  • 7/30/2019 Strategic Level Management and Project Success Increase

    3/62

    iii

    Contents

    1. Introduction ............................................................................................................... 1

    1.1 Background discussion ......................................................................................... 1

    1.2 Research Aim ........................................................................................................ 2

    1.3 Groundwork Questions ......................................................................................... 2

    1.4 Subsidiary questions or objectives........................................................................ 2

    1.5 Research Methodology ......................................................................................... 2

    1.6 Anticipated findings.............................................................................................. 3

    1.7 Time scale and work program .............................................................................. 3

    1.8 Research structure ................................................................................................ 3

    2. Literature Review ....................................................................................................... 4

    2.1 Introduction .......................................................................................................... 4

    2.2 Research structure ................................................................................................ 4

    2.3 What is Project Strategy? ..................................................................................... 5

    2.4 Defining Project Strategy ..................................................................................... 6

    2.5 What does Project Strategy contain? ................................................................... 9

    2.6 Towards a strategy definition ............................................................................ 12

    2.7 Why is strategy important? ................................................................................ 14

    2.7.1 Causes of failure .......................................................................................... 14

    2.7.2 Success factors ............................................................................................. 15

    2.8 The situation in Greece ....................................................................................... 16

    2.9 Theoretical Framework ...................................................................................... 18

    2.9.1 About success .............................................................................................. 18

    2.9.2 Requirements for a successful strategy ...................................................... 20

    2.9.3 Why fail the organisations to develop successful strategies?..................... 21

    2.10 Conclusion ........................................................................................................ 22

    2.10.1 General findings ......................................................................................... 22

    2.10.2 Research questions .................................................................................... 23

    3. Research Method ..................................................................................................... 25

    3.1 Introduction ........................................................................................................ 25

    3.2 Aim Hypothesis ................................................................................................ 25

    3.3 Research Approach ............................................................................................. 26

  • 7/30/2019 Strategic Level Management and Project Success Increase

    4/62

    iv

    3.3.1 Quantitative Research Approach ................................................................ 26

    3.3.2 Qualitative Research Approach ................................................................... 28

    3.3.3. Mixed Research Approach .......................................................................... 29

    3.4 Research Method selection ................................................................................ 30

    3.4.1 Quantitative vs Qualitative Research .......................................................... 30

    3.4.2 Method Selection ........................................................................................ 31

    3.4.3 Research style and considerations .............................................................. 31

    3.5 Sample selection ................................................................................................. 33

    3.6 Questionnaire Design ......................................................................................... 34

    3.7 Limitations .......................................................................................................... 36

    3.8 Ethical issues....................................................................................................... 37

    4. Data analysis and discussion .................................................................................... 38

    4.1 Introduction ........................................................................................................ 38

    4.2 The situation in Greek construction sector ......................................................... 38

    4.3 Result overview .................................................................................................. 39

    4.3.1 General Information .................................................................................... 39

    4.3.2 Results of Questionnaire Section B ............................................................. 40

    4.3.3 Results of Questionnaire Section C ............................................................. 43

    4.4 Result discussion ................................................................................................. 46

    5. Conclusions, limitations and further studies ........................................................... 47

    5.1 Review and Conclusions ..................................................................................... 47

    5.2 Limitations .......................................................................................................... 48

    5.3 Future Studies ..................................................................................................... 48

    References ................................................................................................................... 49

    Appendix ...................................................................................................................... 53

    Appendix 1 Cover Letter ........................................................................................... 53

    Appendix 2 Questionnaire ........................................................................................ 54

  • 7/30/2019 Strategic Level Management and Project Success Increase

    5/62

    v

    List of Figures

    Figure 1: Strategy approaches by different authors 6

    Figure 2: Strategy formulation and implementation 13

    Figure 3: Project/Product lifecycle stages and milestones 18

    Figure 4: Measuring project success 19

    Figure 5: main differences between quantitative and qualitative research 30

    Figure 6: advantages and disadvantages of interview technique 32

    Figure 7: advantages and disadvantages of questionnaire technique 32

    Figure 8: Questionnaire promotion timeline 35

    Figure 9: questionnaire construction and administration 36

    Figure 10: Questionnaire return rate 39

    Figure 11: Business Sectors (company activities) 40

    Figure 12: Project strategy use 41

    Figure 13: Percentage of feature use in project strategy 42

    Figure 14: Project time decrease 44Figure 15: Project cost reduction 44

    Figure 16: Predictability increase in projects 45

    Figure 17: Productivity increase in projects 45

  • 7/30/2019 Strategic Level Management and Project Success Increase

    6/62

    vi

    Acknowledgement

    I would like to thank all the people that have contributed both directly and indirectly

    to the success of this research work. My sincere thanks go to all the respondent

    Companies who have given their time and their significant answers on the research

    questions and made the completion of the research possible. My special gratitude goes

    to my supervisor, Dr. Graeme Bowles for his general guiding and his directions and

    supports during the whole research. Also, my thanks go to the Heriot-watt University

    for giving me the opportunity, the knowledge and the support to undertake a research

    on this high level. Finally, my thanks go to my family and friends for their support.

  • 7/30/2019 Strategic Level Management and Project Success Increase

    7/62

    vii

    Abstract

    The topic comes from the discussion about the project management effectiveness.

    While PM has two equally important levels (strategic and operational), attention is

    paid mainly (almost exclusively) to the operational level, aka the PM tools. This is a

    misunderstanding of the very nature of Project Management and leads inevitably to a

    misapplication of PM practice. The research highlights the importance of strategic

    level PM and examines how much a well planned and performed PM strategy can

    contribute to project success increase. The research is based on two levels, literature

    review (theory) and practical research. Through the theoretical research, the

    dissertation presents the function of strategy in management of projects; what exactly

    is project strategy, what is its role in a project, which are the most important strategy

    features. The practical part is based on a quantitative research method and shows the

    level on which the construction companies are aware of this discipline, how they

    implement strategy and most importantly if their planning and implementation is

    bringing results. The study confirms that there is an average time and cost excess in

    projects, that the majority of the construction companies are aware of the project

    strategy in project management and that they use it in almost all of their projects. The

    initial hypothesis that a well performed strategic level project management cancontribute decisively in project success and increase the predictability of the projects

    is also confirmed. The answer to project success increase and to more successful

    project management lies in project strategy, which is not something vague, but a

    process / practice explicitly specified, with specific features and contents.

    Keywords: Project strategy, project success increase, strategic level project

    management, project strategy contents, strategy features

    Konstantinos Konstantinidis

    Construction Project Management

    March 2012

  • 7/30/2019 Strategic Level Management and Project Success Increase

    8/62

    1

    1. Introduction

    1.1 Background discussion

    The topic comes from the discussion about the project management effectiveness.

    More specifically, it has been proved that the majority of the projects is delivered later

    than initially planned and (or) over the pre-estimated budget. Why is this happening?

    Seeking for the causes of project failure, the reader will realise that the problem is not

    at PM itself, but in the way of its implementation.

    While PM has two equally important levels (strategic and operational), attention is

    paid mainly (almost exclusively) to the operational level, aka the PM tools. This is a

    misunderstanding of the very nature of Project Management and leads inevitably to a

    misapplication of PM practice. The result of project failure should be therefore rather

    expected. Attention should be paid at strategic level. Evans (2005) supports that

    according to the Project Management Institute; there are five distinct phases in every

    project: initiation; planning; execution; control; and closure. Problems take place

    most frequently when initiation gets separated from execution. Shi (2011) states that

    there areorganizations which have gained little value from project management and

    the reason is that they have not introduced and applied project management correctly.

    The operational aspects of PM process are well defined and they work (Heriot

    Watt 2011, 8-3). There is a lot of discussion about the reasons of project failure and

    many factors are related to strategy. According to Anderson and Merna (387393)

    Creating a strategy is therefore a primary action in two ways, it is both the first step

    and also the most important action since it provides the overarching plan and

    objectives. The discussion has been going for many years, having a historical

    perspective. Avots (1969) is referring to inadequate basis for project and inadequately

    defined tasks, while Munns and Bjeirmi (1996) support that successful project

    management requires among other actions spending time to define the project

    adequately, correctly planning the activities in the project and ensuring correct and

    adequate information flows. Dietrich (2005) also believes that high quality

    information in decision making is a factor that affects successful implementation.

  • 7/30/2019 Strategic Level Management and Project Success Increase

    9/62

    2

    1.2 Research Aim

    The purpose of the research is to highlight the importance of strategic level PM and to

    examine how much a well planned and performed PM strategy can contribute to

    project success increase.

    1.3 Groundwork Questions

    Based on those previously presented, the research will try to answer to three main

    questions:

    Why do projects fail? Which strategy factors are the most important? How can a better strategy contribute to improved project success?

    1.4 Subsidiary questions or objectives

    The dissertation will try to examine and present the importance of a number of topics

    such as strategy factors, initial planning, taking strategic decisions, etc. The purpose is

    to discover the level of their contribution to project success in terms of time and cost

    reduction and predictability & success increase. Bibliography can confirm the

    significance of those factors; Assaf and Al-Hejji (2006) and Al-Barak (1993)

    underline the importance of early planning and project estimation practices, while

    Chan (1997) supports that slow decision making and poor risk management are

    among the factors that cause failure.

    1.5 Research Methodology

    The research will be based on two levels, literature review (theory) and practical

    research. Through the theoretical research, the dissertation will present the function of

    strategy in management of projects; what exactly are strategy and its role in a project

    and why is it so important? After the general verging, the study will focus on the

    location of the major aspects of the strategic level PM. According to the theory those

    aspects influence the project success.

  • 7/30/2019 Strategic Level Management and Project Success Increase

    10/62

    3

    The practical (field) research will be developed a way that will allow conclusions

    about the importance of those factors in PM to be carried out. Are the contractors

    aware of the value of strategic level PM? Do they use those strategies to improve their

    performance? Is that working? The sample will be the construction companies that

    are working in the private sector and more specifically those that undertake mall

    logistic and complex constructions in Greece. This sector is chosen for several

    reasons. Those projects have an adequate level of complexity (comparing to the main

    construction sector in Greece which is private housebuilding), involve contractors and

    sub-contractors, and are common projects in the last twenty years (adequate number

    and mature discipline). Therefore the sample is representative and suitable for the

    research.

    1.6 Anticipated findings

    By focusing on that specific construction sector, research will confirm the high

    importance of strategic level PM in project success and will also show the level at

    which every strategic aspect contributes to the increase of project effectiveness.

    1.7 Time scale and work program

    The time scale is planned as follows:

    Literature research and intro development: 1 month

    Bibliography based part development: 2 months

    Questionnaire based part development: 1.5 month

    Analysis, Conclusion and finishing tasks: 1.5 month

    1.8 Research structure

    The Dissertation will have 5 main chapters, namely:

    1. Introduction

    2. Literature Survey

    3. Methodology

    4. Analysis

    5. Conclusion

    The study contains a reference list as well as the required appendices.

  • 7/30/2019 Strategic Level Management and Project Success Increase

    11/62

    4

    2. Literature Review

    2.1 Introduction

    The following section will present the theoretical background and discussion about

    project strategy. The purpose is to define project strategy, identify its importance to

    project management and its relation to project success. Therefore the section will be

    divided into three main chapters. The first part is going to approach different views

    about strategy in order to structure a theoretical framework. The second part will

    proceed to the formulation of a comprehensive definition of project strategy that will

    include also more practical parts, like the contents of strategy. This is important

    because there is a need in project management of an applied strategy. This part will

    be partially based on existing references, which will be used in a targeted way to

    assist the new theoretical formulation of strategy. The third parts aim is to present the

    importance of strategy in project management and its correlation with project success

    and project failure. There is a specific logic around this: if we can locate the reasons

    of project success or project failure; that are related to strategy, we can formulate and

    use strategy in a way that can increase the success of the projects. That is after all the

    basic aim of the project management discipline.

    2.2 Research structure

    The literature survey has two main targets. The first one is, as written above, the

    formulation of a complete theory about project strategy. The second one is to generate

    broad conclusions about the role of project strategy in project management. The logic

    behind this is specific. The opinion of the writer is that some strategy related issues

    are more or less universal and therefore need to be addressed. After reaching to the

    theory building and the conclusions, the aim is to test them. The purpose is to test the

    validity of both the theory and the findings related to strategy use in a more specific

    area. Therefore the data research will be narrowed down to a more specific sample,

    namely in Greece (for more details see Sampling part in Research Method

    section).

  • 7/30/2019 Strategic Level Management and Project Success Increase

    12/62

    5

    2.3 What is Project Strategy?

    The definition of Project Strategy is the first step that has to be taken in order to

    explore Project Management at the strategic level. There are several opinions about

    the definition and the scope of project strategy and its relation to project and Project

    Management. However there is a common belief that should be highlighted: since

    every project is unique as it includes unique characteristics, objectives, etc every

    project strategy should be unique for every single project respectively. Shenhar et al.

    (2000) clearly underlines that for each project a distinct and unique process of doing

    things has to be developed in order to succeed in the specific situation. Project

    strategy is that explicit process. Artto et al. (2008) provides a similar approach by

    underlining that the projects unique environment is to be taken under consideration

    when formulating the project strategy, which is a dynamic direction that contributes to

    its success. Project strategy is therefore the strategy of a single project.

    A different view is provided by Naaranoja et al. (2007), who distinguishes project

    strategy from project management strategy. According to the writer project strategy

    refers to a high level plan for achieving the projects certain objectives and it is

    related to strategic decisions during the project life-cycle. On the other hand, aspects

    like team building; project flexibility; risk management avoidance; contract strategy

    and alliances are part of the project management strategy, which is the strategy for the

    management of the project. This point of view separates project strategy and project

    management strategy by presenting them as two different disciplines.

    Another important addition to the theory provided by Shenhar et al. (2000) is the

    differentiation between a strategy and a plan. According to the writer plans include in

    general decisions about the operational aspect of a project, such as activities

    scheduling, resources allocation and use, timelines, and deliverables. Strategy on the

    contrary is one level above those activities. This is a significant clarification, since

    very often project managers and organisations tend to focus only on those operational

    level features, without the formulation of a general strategy to drive them. A plan

    should be part of a broader strategy if it is to be adequately effective and successful.

    The following figure shows the general views about strategy that are presented by

    different authors in the last decade. This is only indicative and its role is to highlightsome important project strategy features.

  • 7/30/2019 Strategic Level Management and Project Success Increase

    13/62

    6

    Figure 1: Strategy approaches by different authors

    Author Approach Year

    Shenhar et al. Project uniqueness, strategy according to project 2000

    Kerzner Strategy has to be objective - driven 2001

    Anderson and Merna Strategy provides the overarching plan and objectives 2003

    Naaranoja et al. Project strategy different from project management strategy 2007

    Artto et al. Project uniqueness, strategy should lead to success 2008

    Source: own processing

    2.4 Defining Project Strategy

    As presented above, there are different views about what exactly project strategy is.

    However a proper definition is the first step for actual successful development and

    implementation. Therefore the basic characteristics and a specific definition will be

    presented below.

    Project strategy or project management strategy

    Is project strategy something that has to be distinguished from project managementstrategy? This is the first and maybe fundamental question someone has to answer in

    order to proceed to the rest theoretical formulation. As presented above there are

    different views about the theory. For Naaranoja et al. (2007) those two are referring to

    different aspects and strategy levels, while Artto et al. (2008) does not separating

    them. Since it is rather a matter of theoretical view than a fixed theory / definition,

    every aspect has its arguments. Project strategy is the generic strategy of the project. It

    has to drive the complete project and define all of its features. It defines the way to

    achieve the projects objectives, the direction and the philosophy of the strategic

    decisions and handling of the project. However the project strategy should also clearly

    define project flexibility, contract strategy, risk management, cost management, etc.

    Those are not to be excluded from the project strategy. They should not be defined on

    another (latter) stage of the planning, or independently from other strategic decisions.

    The way a project is going to be managed has to be defined by the project strategy.

    Therefore, project management strategy is not to be distinguished from project

    strategy. It can be said that they are in essence the same thing.

  • 7/30/2019 Strategic Level Management and Project Success Increase

    14/62

    7

    Uniqueness / adopted to project

    Every project is unique. There are of course some characteristics that are common for

    all projects. Every project has objectives; there can be no project without them. On the

    other hand, the objectives of every project are particular and specific, giving to the

    project a unique nature (since projects are objective driven). In addition, every

    project has stakeholders, but at the same time, the number, the composition and the

    importance of every stakeholder differ from project to project. Furthermore, resources

    of all kinds are an exclusive (but always present) part of every project. It is obvious

    that the same thing applies for all project features (constrains, etc). That fact leads to

    the conclusion that, since every project is unique, every project strategy has also to be

    unique. In other words the project strategy has to be adapted to the specific project;

    hence it must be developed exclusively for it. Like projects, all project strategies have

    to contain both common and unique features.

    Process leading to project success

    A project strategy has to be interconnected to project success. After all, project

    success is one of the main reasons for project management development. The role of

    project strategy is to drive the project from the early (before initiation) phase through

    all the stages, to prepare the key participants for any potential issues, to set up the

    management plan, to contribute to control, general operation, project administration,

    etc. All those will be defined on a level from the strategy formulation. A well planned

    and integrating developed strategy is of key importance for a successful project.

    Therefore one of its tasks is to lead to project success.

    Organisingplanning the project

    Driving from above, the project strategy has to lead to the project plan. The general

    setting up, the way the progress will be monitored and controlled, the operational

    plan, the administrational style, in other words every general (or even some more

    specific) aspect and direction that will affect the whole progress has to be a direct

    result of the formulated strategy. Strategy has limited use and effectiveness if the

  • 7/30/2019 Strategic Level Management and Project Success Increase

    15/62

    8

    planning of the project is independent from it. Moreover a project plan that is based

    on ad hoc decisions with no association with each other and a general project strategy

    will be not able to drive the project successfully and solve any possible problems

    whatsoever.

    Justification

    The four main issues presented above create the basic characteristics of project

    strategy. It is expected that authors or organisations will have differences in their

    views of strategy. It can be said that a view is accepted if it can be justified. Examples

    often help that process. If a project strategy sets only a broad generic framework of

    the project, without dealing with project management issues like project flexibility,

    cost / risk management, etc it will not be able to assist the managers taking strategic

    decisions during the project. The managers that will be responsible for the project

    should define for example the number and the kind of subcontractors that will be

    appointed and the work that they will undertake. In case of underachieving, or if

    problems arise strategic decisions (changes, tradeoff, etc) must be taken. Project

    uniqueness is also a key factor, since special features of the project play a main role.Different stakeholders create different environment of the project. The same thing

    applies in a number of other factors such as location of the project. A different project

    organisation is required for example at a project in an urban area, a suburban area, a

    rural area or an island. Transportation, infrastructure, prefabricated parts, even

    weather and site conditions and many more are factors that combined create the

    uniqueness of the project. Therefore the formulation project strategy has to be based

    upon those factors. Project planning and organising should also be clearly defined. It

    should be clear and predefined who is responsible of what, what should be the work

    structure and progress, how are those to be monitored and measured, who will take

    the decisions in every case. Projects that do not solve those issues tend to deal with

    organisational problems that lead to failure. Tools like Work Breakdown Structure

    (WBS), Organisation Breakdown Structure (OBS), Statement of Work (SOW), Task

    Responsibility Matrix, etc have been created to assist those procedures. All the above

    mentioned lead as expected to project success. It is already mentioned that project

    success is the main aim of project management. Therefore, project strategy which can

  • 7/30/2019 Strategic Level Management and Project Success Increase

    16/62

    9

    be defined as the initial process in project management should at all case drive to and

    maximise the project and product success.

    2.5 What does Project Strategy contain?

    After an initial approach of project strategy the next step in order to come up with an

    integrated definition is to locate the main contents of it. In other words, what should a

    comprehensive and successful strategy take under consideration and thus include.

    This is an important section because it particularises the general view and theory and

    shows how it can be useful on a more practical level. In other words, what should

    every project team incorporate and take under consideration during the formulation

    and implementation of a project strategy.

    Scope management

    Scope management should be the beginning of project strategy. It includes all the

    aspects of the project; quality, performance, specifications and properties of the

    project product. There are in fact the quantitative and qualitative deliverables of the

    project, thus the work that needs to be done in order the project to be completed

    successfully. Taking this under consideration, scope management has to be the

    initiation of the project strategy, since all the project objectives will be come from it.

    S.W.O.T. analysis

    This is basically a mapping process. It locates, defines and assesses strengths,

    weaknesses, opportunities and threats of the project. It is a valuable procedure that

    provides a representative image of the project and its issues and characteristics.

    Kerzner (2001) states that identifying opportunities and threats allows us to spot what

    we want to do, but recognising our strengths and weaknesses lets us be aware of what

    we can do. Therefore, strategy should be formed by taking under consideration those

    matters in order to be effective and in response to the unique characteristics of the

    project.

  • 7/30/2019 Strategic Level Management and Project Success Increase

    17/62

    10

    Correlation with the project objectives

    It is well known and widely adopted that the projects are on a high level objective

    driven. According to HeriotWatt (2009) thesuccess of a project can be measured in

    terms of how closely it has met its prearranged objectives. The objectives of a project

    show in a way the project direction. Site set up plans, resources allocation and

    mobilisation, time sheets and many more project features are mainly dependent from

    the objectives of the project. Furthermore, every projects milestones are utterly

    related to the project objectives. Therefore also project progress; performance

    measurement and benchmarking are reliant on the project objectives. The formulation

    of the strategy has to be based upon the specific objectives of the project. The

    management and the achievement of the objectives should be the main guidelines.

    Kerzner (2001) supports that the process of the objectivesetting and the integration

    of the implementation through methodology assure that all of the parts of an

    organisation are moving toward the same common goal. A careful mapping and

    assessment of the objectives have to be of the main drivers of the strategy creation

    and development.

    Work Management Plan

    After defining the projects objectives the next step is to define the work that needs to

    be done in order to achieve them. The project strategy has to classify the amount and

    type of work that needs to be done for the project completion. A comprehensive

    analysis of the project works is of main importance in project planning. This process

    contains an analysis of the amount, the type and the sequence of the project works.

    Those have to be planned early and carefully and in detail because they are practically

    the core of each project. Through this plan will be also decided and formed the time

    of each work units completion and most important the allocation and utilisation o f

    the available resources. In other words, the Work Management Plan is the framework

    that drives the planning and the organising processes of the project. An organisational

    structure of the project that includes also specific responsibilities can be formed either

    separately, or as part of this plan with each group of activities assigned to specific

    people.

  • 7/30/2019 Strategic Level Management and Project Success Increase

    18/62

    11

    Criteria to assess success

    Driving from above, every strategy has to enclose criteria to assess the project

    progress and success. Performance measurement is a procedure of main importance

    during a project lifecycle. It is for that reason essential for a project strategy to plan

    and formulate carefully on that direction specific criteria. Those will make available a

    measurement which will reflect the real project progress. What strategy needs to set is

    specific goals and standards. These have to be both quantitative and qualitative and

    cover all the aspects of the project and the product. In addition to those an integrated

    strategic planning should also provide possible measures that should be taken if

    performance is bellow the expected and planned levels. That naturally leads to the

    next topic bellow.

    Risk Management Plan

    Risk management is a valuable procedure in every project. Raz et al. (2001) describes

    it as one of the key processes in project management. Poor risk management can lead

    to project delay, cost increase, scope affection, or even cancellation of the project

    (failure in general). The plan should map and locate possible risks, their probability,

    the effect they might have on the project progress and of course ways to solve any

    upcoming problems. Strategy planning that does not contain a full risk management

    plan cannot be complete effective at the time when problems arrive. According to the

    Project Management Body of Knowledge (PMBOK) of the Project Management

    Institute (2004), in order to be successful, an organisation should be committed to

    addressing the management of risk proactively and at all times throughout the project

    lifecycle. Kerzner (2001) also supports this view. He believes that a reaction to a

    crisis of the moment may lead to a choice that is not linked to, and maybe also

    conflicting with, the choice made in an earlier moment of crisis. Discontinuous and

    contradictory choices are causing problems to the organization and might well be the

    reason of its failure.

  • 7/30/2019 Strategic Level Management and Project Success Increase

    19/62

    12

    Cost Estimation

    Egan (1998) supports that some of the construction industry problems are competitive

    tendering and low profit margins. According to Doloi (2011) cost overrun is a

    constant problem across most projects and the accuracy of cost estimation is affected

    by the experiences of the bidding team and project managers as well. One of the main

    results of project failure is cost overruns. For those reasons precise cost estimation is

    of key importance in a project. A comprehensive and integrated strategy has to

    carefully estimate every aspect of the project that can affect (either in a positive or in

    a negative way) the cost of the project. That way it is possible to define which the cost

    parameters of the project are, what are the profit margins and whether or not it is

    possible for the organisation to undertake the project. A strategy with poor or

    inaccurate cost estimation is likely to lead to project failure or cancelation.

    2.6 Towards a strategy definition

    Giving a specific definition to the term of project strategy is not only a theoretical

    matter. The way someone defines projects strategy affects also the approach of the

    implementation. Drawing from the topics presented above, the definition can be

    formed as follows:

    Project strategy is a comprehensive direction plan that defines the way a project will

    be successfully managed, taking under consideration its unique characteristics.

    That definition includes more or less elements from the topics presented above both

    from the general and the specific ones (see those referring to the strategy contents and

    Figure 1). It is clear that there is no single definition of strategy and each writer can

    give a different perspective of that, although some issues remain always common.

    This happens because independently of the personal view, everyone will agree on the

    strategys main aim which is successful management, in other words achieving

    projects objectives working with high productivity on time and scope, not above

    predefined cost and with the product on the specified quality standards. Project

    strategy in order to lead to a successful project has to be seen as the vehicle to manage

    the project and not as a standardised and typical procedure that is identical in everysingle project. Furthermore strategy, as a continuously applied process, has to be

  • 7/30/2019 Strategic Level Management and Project Success Increase

    20/62

    13

    flexible and able to change and become adapted to project changes and alterations.

    The proposal about strategy formulation and application during a project is presented

    bellow in the following figure:

    Figure 2: Strategy formulation and implementation

    Source: own processing

    The figure shows clearly the issues mentioned above. Project strategy can be divided

    into three main sections (or stages); analysis and plan formulation, decision and

    implementation and control. Feedback and revision processes are playing a very

    important role in this procedure, since they drive the improvement and adaptation of

    the project strategy. It should be noticed however that the first step is extremely

    important in this procedure. A comprehensive analysis that includes and takes under

    consideration all the critical factors (see strategy contents) will not only require fewer

    and small scale revisions, but will be also much more adjustable and alteration

    friendly.

  • 7/30/2019 Strategic Level Management and Project Success Increase

    21/62

    14

    Although there is a multiannual literature about project strategy it remains a question

    whether project managers and companies today know about the importance and the

    role of project strategy. This is in fact one of the main questions of this paper.

    However before proceeding to this section it is of key importance to answer to another

    question. That question is why is strategy important? Where and how can strategy

    contribute to project success, or otherwise can a strategy absence or misapplication

    lead to project failure?

    2.7 Why is strategy important?

    In order to answer to this fundamental question the theoretical approach has to cover

    two views. Therefore the following chapter will be divided in two sections. The first

    part will approach the causes of failure and underachieving in projects and locate

    strategy related factors. The section should reveal that lack of strategy leads to project

    failure. The second part will present the factors of the projects that lead to success and

    the role that strategy plays in those factors. A strong correlation between strategy and

    success is expected to be found.

    2.7.1 Causes of failure

    There are several studies that try to locate the reasons of project failure. Strategy

    related reason can easily be found on them. Assaf (2006) states, that the completion of

    a project within the specified time is a rare occurrence. Among the reasons of delay

    are also early planning and design of the project. He adds that planning and

    scheduling are ongoing procedures during projects and equal to the resources and time

    to develop the work that is essential in order to avoid cost overrun and disputes. This

    means basically that inadequate early planning (strategy formulation) leads to time

    overrun. Al-Barak (1993) studies the main causes of failure in Saudi Arabia

    construction industry. He surveyed 68 contractors and 34 different causes of failure.

    The study concluded that lack poor estimation practices and bad decisions in

    regulating companys policy are among the critical factors . Those are parts of strategy

    as it is developed above (see previous part). Chan and Kumaraswamy (1997)performed a survey to evaluate the relative importance of 83 potential delay factors of

  • 7/30/2019 Strategic Level Management and Project Success Increase

    22/62

    15

    construction projects constructed in Hong Kong. They found five principal causes,

    which were poor risk management and supervision, unforeseen site conditions, slow

    decision making, client-initiated variations, and work variations. All of them (except

    maybe supervision) are related to project strategy as presented in previous chapters.

    Kaming (1997) et al. located among others in cost overrun factors inaccurate material

    estimation and degree of complexity, while time overrun reasons include inadequate

    planning. Those factors show that it is impossible to have a clear view of the project

    special features without the formulation of an integrated strategy. Shenhar et al.

    (2000) suggests that there is a strict difference between operationally managed and

    strategically managed projects and that traditional project management focus is on

    operational performance. The article adds that there is a need for a new, more

    strategic way of thinking in project management. All those studies show that

    inadequate strategy formulation equals to project failure. Having a wrong idea about

    the project leads to incorrect planning; wrong decisions in project management and

    poor responses to problems that may occur. Due to these projects exceed time and

    cost limits and can end up with an altered scope.

    2.7.2 Success factors

    By precisely locating the reasons of failure, it becomes easier to define and formulate

    success factors of projects. From the information presented above is clear that project

    strategy has a key role in projects. Since a misunderstanding, an inadequate or

    inaccurate formulation or a misapplication of strategy can cause failure of a project, it

    is only logical that a highquality strategy can be a driver of project success. This is

    an idea that has been presented several times. Munns and Bjeirmi (1996) in their

    article discuss the role of project management in achieving project success. They

    suggest that a successful project management requires also among other factors:

    planning with a commitment to complete the project, spending time to define the

    project adequately, correctly planning the activities in the project, ensuring correct

    and adequate information flows and changing activities to accommodate frequent

    changes on dynamic. All those are factors that are directly related to strategy as it has

    been presented above. It is even more accurate to say that they are an integral part of

    strategy. Moreover, Cooke (2002) released a research from more than 70 large multi-

  • 7/30/2019 Strategic Level Management and Project Success Increase

    23/62

    16

    national or national organizations on the success factors of the projects. Four out of

    five factors related to time success and one out of two factors related to cost success

    (ontime performance and oncost performance respectively) are directly related to

    project strategy. More specifically the strategy related time factors are adequacy of

    company wide education on the concepts of risk management, sufficiency on

    maintenance of a visible risk register, capability of having an up-to-date risk

    management plan, and a sufficient documentation of organisational responsibilities on

    the project. Furthermore, one of the two on cost performance factors is to maintain

    the integrity of the performance measurement guideline. All those factors that lead to

    time and cost success of a project are explicitly related to project strategy and confirm

    that a well planned and carefully formulated strategy can increase the success of a

    project. Kerzner (2001) also confirms that statement by supporting that when the

    implementation process is made precise, objectives, missions, and policies become

    visible guidelines that create logically consistent decisions. On cost estimating he

    adds that strategic planning can include provisions in the methodology for better

    estimating techniques, such as the creation of lessons learned files on previous costing

    and the purchasing of historical databases. He concludes supporting that effective

    strategic planning can mean the difference between long-term success and failure

    (Kerzner 2001, p9).

    2.8 The situation in Greece

    The research sample will be the construction companies in Greece (for more details

    see Sample selection in Research Method part). It is therefore important to set up

    a framework view about the topic in the country. There is however a fundamental

    problem in this process, mainly because of the lack of bibliography and references

    about the Project Management discipline (Pantouvakis, 2003).

    It is nevertheless a fact that like in all other countries, projects in Greece often exceed

    time and budget limit and are completed bellow the specified quality standards

    (Pantouvakis, 2003). Inadequate project planning leads to a result where strategically

    important actions remain unexecuted while the whole organisation structure and

    culture are being lead by ad hoc processes (Kourounakis, 2010). According toChazapis (2010) the most efficient way to achieve project success is to ensure that the

  • 7/30/2019 Strategic Level Management and Project Success Increase

    24/62

    17

    project team will be well prepared for any potential problems that might occur. That

    view underlines and highlights the importance of strategic planning. Furthermore,

    Bafas (2007) underlines the importance of a various features in project management

    planning. The features (scope management, risk management, cost estimation, project

    objectives mapping, Work Breakdown Structure, etc) are identical to those presented

    above during the Literature review and the formulation of the theory.

    It can be realised that in general terms the situation in Greece regarding project

    management and its practices does not differ from the general findings that this

    specific research underlines. In any case, the questionnaire results will be able to

    provide a more specific and detailed aspect about this matter (see Questionnaire

    Design in Research Method part).

  • 7/30/2019 Strategic Level Management and Project Success Increase

    25/62

    18

    2.9 Theoretical Framework

    2.9.1 About success

    There is a very long discussion about project success. What is considered to be project

    success and how it can be measured is a matter that allows many different views.

    Although it is not directly the topic of this research, a compact discussion about this is

    necessary. First of all we have to underline that success in a project has different

    views. A project that ended for example on time, on budget and according to the

    quality standards is successful for the owner, but can be unsuccessful for the

    contractor if he had no profit or if he lost money. There is even the possibility that

    both the owner and the contractor consider the project as successful but the final users

    believe that the product does not cover their needs. Project success and product

    success have are of course interrelated but at the same time they are two different

    matters. If it is viewed completely isolated, a project can be successful even by

    creating an unsuccessful product and on the other hand a successful product can be a

    result of an unsuccessful project. Angus et al. (2005) present very comprehensible

    examination regarding the matters of project, product and view of stakeholders in the

    following figure:

    Figure 3: Project/Product lifecycle stages and milestones

    Project lifecycle Product lifecycle Owner/ActionsStage 1 Project

    conception

    Product feasibility The client organisation, assisted by specialists

    Milestone

    1

    Project

    commitment

    High level product requirement

    produced

    The client commits to the project and appoints a

    project team

    Stage 2 Project

    execution

    Design, development or

    acquisition

    The project team (the prime contractor assisted by

    subcontractors)

    Milestone

    2

    Project closure Product created The project team delivers the created product to the

    clientStage 3 N/A Product operation The client organisation, possibly transferred to a

    customer/user

    Source: Angus et al. (2005 p. 429)

    It can be clearly seen that project and product are separated from each other and also

    that there are different owners in each phase. The main purpose however of a

    successful strategy is to lead to a successful project. If the final product is created

    according to the initial specifications and does not meet the final users needs, that is

    not a question or a problem of project management and hence of the project

  • 7/30/2019 Strategic Level Management and Project Success Increase

    26/62

    19

    management strategy. It should be noticed that the present research focuses on the

    strategy related to project management. It is however helpful to see a holistic view of

    success that includes the success of all factors of a project (project management,

    product, market, etc) and highlights the initial argument, provided by AlTmeemy et

    al. (2011):

    Figure 4: Measuring project success

    Source: AlTmeemy et al. (2011, p. 339)

    As written above the discussion about success can be approached in many different

    ways. Regarding project (management) success there is also a relativity issue. If for

    example there is a need for changes to some of the technical specifications due to

    external reasons; that could alter the whole project scope. A solution however that can

    approach the initial planning can easily be considered as a success even if for example

    raises the total cost of the project. There are numerous tradeoffs like that to be

    considered regarding time, cost, quality, scope, efficiency, value etc.

    Furthermore this view can be expanded. In a hostile environment for example, with

    several different problems and issues, even the survival of the project can be

  • 7/30/2019 Strategic Level Management and Project Success Increase

    27/62

    20

    considered as success. There is clearly not a single approach to the matter. This is also

    one of the reasons why this research is about increase project success. In every case

    nevertheless it is clear that a wellestablished and wellapplied strategy is required

    to achieve project success.

    2.9.2 Requirements for a successful strategy

    It is important to notice that in order the strategy process to be successful, there must

    be followed some principles. First of all the whole project has to be very specific and

    not to contain any kind of vagueness. The people inside the company who are taking

    the decisions should be aware of all the aspects of the strategy. Secondly, the internal

    and the external assessment must be integrated. A good analysis will provide the right

    information that will allow the company to set up a realistic mission and the

    appropriate goals to achieve it. An analysis that does not reflect the real situation and

    does not take under consideration all the important factors may lead to an

    unsuccessful strategy and even to company failure.

    There must also be a clear correlation between the mission, the goals and the actions.

    Every goal decided has to contribute to the achievement of the mission. Goals should

    not be set if they are not related to the mission of the project. Likewise, the

    determined actions should reflect the projects goals (objectives). It is also important

    to notice that mission should not be changing according to goals and goals should not

    be changing according to actions. This is a mistake that many organisations use to

    make. Those steps must be interlinked with a very specific way.

    Great attention should be given also to implementation process. It is common the

    actions finally taken to differ from those initially decided. A good strategy is of no

    use, if it is not applied the way it was planned. That underlines the importance of the

    third stage (see Figure 2). The performance should be measured in order to note if

    everything goes according to the planned strategy. An integrated control and

    evaluation system is key factor for a successful strategy. Feedback is of great

    importance for the control system. Any conclusions made after evaluation should be

    used to change the strategy process, if necessary. It should of course be noticed that

  • 7/30/2019 Strategic Level Management and Project Success Increase

    28/62

    21

    the reliability of the feedback depends very much on the quality of the evaluation

    process.

    Finally, like mentioned above, it is important for the strategy to be flexible. It must be

    capable to be adjusted to any unexpected changes that may occur. The strategy should

    not be followed blindly, because it reflects reality. If the reality changes the same

    thing must happen to the strategy, too.

    2.9.3 Why fail the organisations to develop successful strategies?

    As analysed before, the strategy in general and the strategy process are meanings that

    are in general known and surely easily available to the organisations. However it is

    common that the organisations fail to develop successful strategies. As Whittington

    says, the average book on strategic planning [management] is pretty cheap. So, how

    come, if the secrets of strategic management are so cheaply and easily available,

    many organizations fail to develop successful strategies? Is there something wrong

    with the literatureor maybe even the concept itself? (Clegg et al. 2005, p410).

    The answer to that is not so difficult, as it appears to be. If there was a problem withthe literature, there would not be any organisations that have developed successful

    strategies based on the literature. Moreover, if there was something wrong with the

    concept itself, there would be not organisations that have developed successful

    strategies at all. So we can say that it is more a rhetorical question. The problem is not

    in the theory; it is when the theory is applied.

    As written before, strategy and the strategy process contain many factors that have to

    be fully understood. Sometimes the organisations set up their strategies, but they dont

    give attention to all of the requirements presented before. Those requirements are

    relevant with the implementation of strategy. It is logical, that if something goes

    wrong during the implementation process, the theory will not be of any use. All stages

    and steps of the strategy process are connected with each other; the process is like a

    chain. That means that one mistake or omission during the process can affect the

    whole performance. Organisations that fail to develop successful strategies often are

    those which did not take under consideration all the factors. A reason for that is thatmany times, those who are supposed to plan the strategy and monitor the strategy

  • 7/30/2019 Strategic Level Management and Project Success Increase

    29/62

    22

    process, are not well trained to do so. Managers must have advanced studies in order

    to correspond to the corporate requirements; otherwise failure is possible to happen.

    2.10 Conclusion

    2.10.1 General findings

    The review developed and presented the nature, the role and the importance of project

    strategy in project management. Project strategy is not an abstract concept. It is a

    specific and explicit process that is strongly correlated to the project itself; a

    procedure that it is central and must not be seen as typical. Project strategy has to be

    uniquely developed for each project and must respond to each projects special nature

    and characteristics. It has to lead to project success and help the administration team

    to successfully manage the project. It is a dynamic process that can be changed and

    corrected during its implementation as long as it is wellplanned at first place.

    Underestimation of the role and the importance of project strategy can increase the

    completion time or total cost of the project, change its scope, decrease the quality of

    the product, and lead to project failure in general or even to project cancellation. Onthe other hand, a well planned and successfully implemented strategy can lead to

    problem overcoming, effective management, effective response and project success in

    general. A strategic level project management that is performing well can only lead to

    an effective operational level. Tools do not manage projects by themselves but can be

    a crucial factor of successful management if they are utilised as part of a broadly

    applied strategic planning.

    To sum up with, this part explicitly highlighted what is project strategy about and

    what is its essence in general terms. Specific strategy features and contents of strategy

    have been addressed in this part. Those are important not only on a theoretical basis,

    but also on a practical level. They should be included in every project strategy.

    Moreover the importance of strategy regarding project success and project failure (as

    a result of inadequately planned or miss applied strategy) has been stressed,

    confirming the initial research hypothesis.

  • 7/30/2019 Strategic Level Management and Project Success Increase

    30/62

    23

    2.10.2 Research questions

    The importance of project strategy is proved on the theoretical basis, but it is still a

    question whether contractors share the same view about this process and use it in the

    right way during the projects they undertake. Is it possible to increase project success

    and if so, what do we have to change? There are issues that need to be addressed in

    order to answer to this fundamental question. The literature review showed the role

    that the project strategy should have in order to contribute to project success increase.

    There is a need to test whether the construction companies are aware of this role, how

    they implement strategy and most importantly if their planning and implementation is

    bringing results. Therefore, the main research questions that are created are the

    following:

    o Do the contractors plan and implement project strategy in their projects?This question is based on the causes of failure and success factors topics that

    structure the importance of strategy (see Why is strategy important?). Since the

    importance is proven, there is a need to examine, whether or not the contractors

    act accordingly.

    o Is project strategy a common practice?This is practically the second part of the previous question. It particularises the in

    fact the first question: If the contractors do plan and implement project strategy, at

    what amount do they do that? Is it a broad discipline?

    o Which strategy features are known and used?During the theory building, specific features (contents) of strategy were proposed

    and presented (see related part, What does Project Strategy contain?) Theamount and the frequency of their use have to be tested. Moreover any additional

    features can accrue from this question.

    o How successful are their projects in terms of time, cost, effectiveness, etc?According to the theory, projects in Greece and in general (see The situation in

    Greece and causes of failure parts) often exceed the pre -defined limits and

    constraints. The research will try through this question to define an average time

  • 7/30/2019 Strategic Level Management and Project Success Increase

    31/62

    24

    and cost excess in the projects in Greece. This is a very important fact for the

    study.

    o Do the contractors notice project success and predictability increase due to theuse of strategy?

    This is maybe the most important question of the research. It is a question that can

    mainly prove the theory formulated by this study. There is a simple sequence of

    thoughts: Projects are underachieving, a main reason for that is the inadequate

    planning and implementation of strategy, a better planning and implementation

    can increase project success. If the contractors can validate a success increase due

    to strategy, the theory is proven.

    Those five are the main research questions that need to be answered. They represent

    not only the initial aim of the research (The operational aspects of PM process are

    well defined and they work (Heriot Watt 2011, 8-3), but also the issues that have

    been developed in the literature survey part. Through those questions a data research

    can be undertaken in order to provide specific statistical answers about the strategy

    related issues. The questionnaire questions will be based upon those five main

    research questions (see Questionnaire Design).

  • 7/30/2019 Strategic Level Management and Project Success Increase

    32/62

    25

    3. Research Method

    3.1 Introduction

    As mentioned above, the general theory is confirming the role and the importance of

    the strategic level project management. It is however important to look at the applied

    practices in the construction sector in order to find out the relationship between theory

    and practice. In order to proceed to the research, a decision about the method to be

    followed is needed. The selection of the method that will be suitable for the desired

    research is something that requires consideration. It depends mostly on the research

    topic, the research type and the research area. The purpose of the following chapter is

    to examine and contribute to the decision about the research approach that will be

    adopted to undertake the necessary research. Therefore the chapter will present all the

    necessary facts and features of the subject and investigate the methods in order to

    highlight the one that is appropriate for the case.

    3.2 AimHypothesis

    Creswell (2009); states that the role of the purpose statement is to set the objectives,the target, or the major idea of a proposal or a study. In this case the aim of the data

    collection is to test the theory formed at the previous chapters. Previous chapters

    proved the importance of the strategy in project management, found the correlation

    between strategy application and project success or project failure and showed clearly

    that this level of management is a key factor for improving project success and project

    management effectiveness and efficiency. Moreover a definition of strategy has been

    established along with strategic features and specific contents which are aiming to

    applied strategy or simply strategy implementation. It is therefore important at this

    point to undertake a research in the construction sector and find out what is the

    approach of the construction companies regarding strategy matters. This is about both

    formulation and use of strategy in projects. Moreover the purpose is to find after the

    research ways to increase project success.

  • 7/30/2019 Strategic Level Management and Project Success Increase

    33/62

    26

    3.3 Research Approach

    Fellows and Liu (2008); support that it is a frequent occurrence for people to believe

    that research has not really started before the initiation of the data collection, which is

    not valid. A commonly occurring issue is that the data collection is begun too early

    before the theory and literature review and, in some extreme cases, even before the

    finalisation of the research proposal. It is therefore of high importance to notice and

    define the role of the data collection during a research.

    The essence of a research is to collect information and data about a particular subject

    area that is to be examined with a view of critically analysing, assessing and

    understanding the information. That information is going to lead to a conclusion. For

    this purpose to be achieved there is the need to create a specific and appropriate way

    of questioning the research objectives in other to assure a constructive result. This

    questioning type refers to the strategy that will be adopted in the data collection and

    the result analysis.

    There are three main research approaches, namely the quantitative research approach,

    the qualitative research approach and the mixed method approach. According to

    Naoum (2007) deciding on the type of research to be adopted, depends on three mainissues, namely the purpose of the study, the type and the availability of the

    information which is required. The main and key difference is located between the

    quantitative and the qualitative research method. They represent two different

    research approaches and philosophies. Each one is used under different

    circumstances. Mixed method uses tools and procedures from both quantitative and

    qualitative approaches. The amount and the type of each approachs participation may

    vary since they are depending on the research type and subject.

    3.3.1 Quantitative Research Approach

    Quantitative research is objective in nature and is thought of as a strategy that

    places emphasis on quantity of data. It is defined as an investigation into a problem

    (of social or human nature). This investigation is based on testing a hypothesis or a

    theory that is consisting of variables, measured with numbers, and analysed withstatistical procedures. Therefore, the aim is to investigate, study and determine

  • 7/30/2019 Strategic Level Management and Project Success Increase

    34/62

    27

    whether the hypothesis or the theory hold true (Creswell, 1994). Bouma and

    Atkinson, (1995) support that quantitative data is not abstract, they are hard and

    reliable since they are measurements of substantial, countable, sensate features of the

    world. Quantitative research is therefore solid, specific and contains fixed variables,

    calculations and results.

    When is quantitative research selected?

    Fellows and Liu, (2008) suggest that quantitative research is about making

    measurements in collecting data. According to Naoum (2007) quantitative research is

    to be selected under two specific conditions:

    1. When a survey is required to investigate and discover facts about a concept, a

    question or a feature.

    2. When there is a need to collect factual verification and examine the relationship

    between those facts in order to test a specific theory or hypothesis that has been

    expressed or developed.

    Fellows and Liu (2008); support thatthis approach is based on previous work which

    has already developed specific principles, laws and theories. The purpose of thismethods use is to contribute to the decision of the data requirements arising in a

    particular research project.

    Furthermore they add there are two major questions regarding the quantitative

    research procedure: firstly what is to be measured and secondly how should those

    measurements be made. Moreover an aspect that may be unnoticed is the scale of

    measurement. There should be paid great attention, since the nature of the scale

    selected is of high importance. The research should identify clearly and carefully the

    unit of analysis (Fellows and Liu 2008).

    The use of literature

    Quantitative research incorporates an extensive amount of literature at the beginning

    of a study. In those cases the function of literature is to introduce a theory, an

    explanation for expected relationships, or to provide direction for the main questionsor hypotheses of the research. It plays also a second role, which is to present a

  • 7/30/2019 Strategic Level Management and Project Success Increase

    35/62

    28

    problem or to describe in depth the existing literature related to the subject. That part

    of the study will be separated from the others, usually under the title Related

    Literature or Literature Review, or some other analogous phrase. At the closing

    stages of the study, the literature is revisited by the researcher; who proceeds to a

    comparison between the data results and the previous findings in the literature. In this

    type of research, the researcher utilises the literature in a deductive way, as a

    framework for the research questions or hypotheses (Creswell, 2009).

    3.3.2 Qualitative Research Approach

    Naoum (2007) provides an accurate definition about qualitative research. He states

    that is an approach subjective in nature, which emphasises concepts, experiences

    (which often are described in a verbal way), explanation and so on. The data collected

    in this procedure can be divided in two research categories which are exploratory and

    attitudinal.

    When is qualitative research selected?

    Exploratory research is used when there is a partial amount of knowledge about theinvestigated topic, while attitudinal research is used to evaluate the opinion,

    estimation, or the belief of a person in a subjective way, towards a particular object,

    Naoum (2007). Fellows and Liu (2008) add that qualitative research is the appropriate

    research method in cases of theory building research, which is a research which seeks

    to build a theory around the collected data. Grounding theory is a representative

    example of that.

    They also add that this kind of procedure (developing theory from data) needs a great

    amount of a continuous, over a relatively long period and comprehensive interaction

    between the researcher and the observed, (Fellows and Liu, 2008). Therefore

    qualitative research method is not ideal in cases where there is a narrow time limit for

    the data collection.

    Since the information generated from this research method represents in general terms

    what have been said by people either by interview or what was observed, it is a

  • 7/30/2019 Strategic Level Management and Project Success Increase

    36/62

    29

    method that is mostly used along with tools like interview or open ended questions in

    questionnaires.

    To sum up, qualitative research is the appropriate method when there is a need to

    develop a new theory, to explore personal (subjective) views about a specific topic

    or an issue, or when there is a lack of information related to the research area.

    The use of Literature

    In theory-oriented qualitative studies, such as critical theory, or an advocacy or

    emancipatory aim, the researcher can locate the theory discussion and literature in a

    separate section, typically toward the beginning of the write up. However, in

    qualitative research, the researcher can also include the literature part in the final

    section. The literatures role in that case is to be compared and contrasted with the

    results that came out from the data collection based study. It is a model that is, as

    written above, mainly popular in grounded theory studies (Creswell, 2009).

    3.3.3. Mixed Research Approach

    As written above, this is an approach that utilises methods and tools from both

    approaches (quantitative and qualitative). The logic behind this is that there are cases

    where the features of a single method are not enough to support the type of research

    that is required to be undertaken. Creswell (2009) describes the way of using the two

    different approaches during literature review and data research. He states that if for

    example the study initiates with a quantitative phase, then the researcher is likely to

    embrace a substantial literature review that facilitates to set up a justification for the

    research questions or hypotheses. If on the other hand the study starts with a

    qualitative phase, then the literature will be considerably less, and thus, the researcher

    may include it more into the end of the study, leading to an inductive approach. In the

    case where the researcher advances a concurrent study that contains an equal amount

    and weight on both qualitative and quantitative data, then the literature part may take

    either qualitative or quantitative forms, (Creswell, 2009).

    It is clear that the nature of the mixed approach does indeed allow flexibility during

    the research, since it allows the researcher to alter or adjust the research style

  • 7/30/2019 Strategic Level Management and Project Success Increase

    37/62

    30

    according to the type or the environment of the study. However due to that reason it

    can only be used on specific situations, when no other approach can generate the

    expected results, or drive the research towards completion.

    3.4 Research Method selection

    As already mentioned the selection of the appropriate research method is critical for

    the successful completion of the research. Since mixed method is considered to be

    unsuited due to its characteristics (see above), the following chapter will summarise

    and present the main features of the two major approaches (quantitative and

    qualitative) in order to define the most suitable method for this particular study.

    3.4.1 Quantitative vs Qualitative Research

    The two different approaches have their own specific characteristics and elements.

    Therefore they each one of them is suitable for a different kind of research, topic and

    environment. Naoum (2007), states that the difference between quantitative and

    qualitative research is rather like the difference between counting the shape and

    types of design of a sample of green houses as opposed to living in them and feeling

    the environment, (Naoum 2007, p.42). The following figure shows the main

    differences between the two research philosophies.

    Figure 5: main differences between quantitative and qualitative research

    Quantitative Qualitative

    1 RoleFact-finding based on

    evidence or records

    Attitude measurementbased on

    opinions, views and

    perceptionsmeasurement

    2 Nature of research Objective Subjective

    3Relationship between

    researcher and subjectDistant Close

    4 Scope of findings Nomothetic Idiographic

    5

    Relationship between

    theory/ concepts and

    research

    Testing/confirmation Emergent/development

    6 Nature of data Hard and reliable Rich and deep

    Source: Bryman 1988, cited in Naoum (2007, p. 43) and own processing

  • 7/30/2019 Strategic Level Management and Project Success Increase

    38/62

    31

    3.4.2 Method Selection

    The nature of this research, the role of the literature and theory review, as well as the

    aim of the study are showing that the appropriate research method to be followed is

    the quantitative research method. In this case the theoretical framework leads to

    specific findings and to an explicit theory. Project strategy is not been planned and

    implemented in an effective way, it has not the role it is supposed to have and that

    situation is leading to low performance in projects. Through a well performed

    strategic level project management, the project success can be increased. Those

    theoretical perspectives need to be tested, in order to be confirmed. The point of the

    research is to exclude findings that will have a broad validity (facts) and for that

    reason it has to be objective. Moreover, in this study, the researcher will have a

    distant relationship with the subject during data collection. For all the reasons

    mentioned above, quantitative research is the most suitable method to be followed.

    3.4.3 Research style and considerations

    As mentioned above, the purpose of the data gathering is to test the theory that is

    formed during the review of the literature. A consideration about the appropriate

    method for data collection is needed. This has to be selected according to the selected

    research approach (quantitative). Under this condition, a case study would not be

    fitting and therefore has to be rejected. The reason for that is first of all the nature of

    the research which has not been structured in an inductive way. It does not focus at a

    specific case or situation in order to generate wider conclusions. Furthermore there is

    no single case, which can broadly represent an entire sector in this specific subject.

    Consequently the selection is going to be made between two different research tools,

    namely the interview and the questionnaire. A briefdevelopment of each techniques

    characteristics and a comparison between them will be presented in the figures

    bellow.

  • 7/30/2019 Strategic Level Management and Project Success Increase

    39/62

    32

    Figure 6: advantages and disadvantages of interview technique

    Advantages Disadvantages

    Information is available in a direct way Extra planning is required, increasing research time

    Answers can be more specific Generally small sample

    Interviewees may be questioned in more depth Sample may not be representativeAdditional information can easily be acquired Answers may have prejudice

    Initial topic may be expanded Data may be subjective

    Interviewees may be more dedicated to the

    research

    Information may not be revealed due to a sensitive

    topic area

    Source: own processing

    Figure 7: advantages and disadvantages of questionnaire technique

    Advantages Disadvantages

    Speed Generally low rate of participation

    Broad sample Little depth of data

    Great amounts of information for little effort Respondents assign low priority to questionnaires

    Known and specific structure May not be answered by the appropriate person

    Results can produce statistical data Additional information requires a lot of time

    Generally more objective methodQuestions need to be well structured to generate

    useful data

    Source: own processing

    It is clear that both techniques have their advantages and disadvantages. There is no

    question about which method is better. Each one is respectively appropriate

    according to the type and nature of the followed research. However, a quick view in

    their features can reveal that in general, interview technique is more suitable for a

    qualitative research approach, while questionnaire technique fits more to a

    quantitative method of research. For that reason the technique that will be adopted inthis case is the research through questionnaires. Details about the architecture of the

    questionnaires will be presented in the following chapter.

  • 7/30/2019 Strategic Level Management and Project Success Increase

    40/62

    33

    3.5 Sample selection

    The sample of the research will be selected according to the type of research. This

    means that there are several subjects that have to be taken under consideration. Those

    are related to the broad research questions (see Conclusion part in Literature

    review chapter) but also to the structure of the research (research structure in

    Literature review chapter). According to FrankfortNachmias et al. (2000:167), a

    sample is considered representative if the analyses made using the sampling units

    produce results similar to those that would be obtained had the entire population

    been analyzed. In this case there are findings and conclusions that are considered to

    have a general validity. There is a need those findings to be related in a particular

    area, namely a specific construction sector and a specified location.

    The selected research location is Greece. As a member of the European Union it has

    an environment that is typical of the so called West world. The recent economic

    recession does not; at this point and type of research; affect the core of the studied

    subject, but reduces however the size of the sample. Before the recession there was a

    well developed construction sector and thus a satisfying amount of data. At this

    point, due to the crisis and the measures taken by the Government, the construction

    sector (along with many others) has been broadly affected in a very negative way. As

    a result, the companies left are enough to provide the necessary data, but the data

    gathering process is much more difficult.

    There is a question about the construction sector (public, private, or PPP / PFI) that

    will be selected for the research, since all of them contain large projects. The research

    will focus on private sector projects because of one main reason. Some of the main

    research factors are project completion time, total project cost, effectiveness, etc. In

    public or PPP / PFI projects, where the state is involved there has been noticed during

    the decades that exist problems related to legal issues, responsibility matters, property

    issues, bureaucracy, etc that can significantly affect the project time, the total cost, the

    predictability, the scope and cause alterations, cancellations and changes in general.

    For all those reasons the research would not be accurate and the sample would not be

    representative.

    Moreover, private contractors in Greece undertake mainly two types of projects,which are housing and shopping / business centers or industrial / logistics projects.

  • 7/30/2019 Strategic Level Management and Project Success Increase

    41/62

    34

    Since housing projects are considered to be (mainly due to their size) smaller and

    much simpler, the role of project management in those projects is narrow. Therefore it

    would not be possible to study the role of project strategy in its full extent. For all

    those reasons mentioned above the study will focus on companies affiliated to those

    project types.

    3.6 Questionnaire Design

    The questionnaire survey seeks Greece contractors view on the implementation of the

    concept of project strategy in construction industry. The design of the questionnaire

    was shaped based the background information gathered from the literature review of

    journals and papers, on the theory formed during the literature survey and on the five

    (5) main research questions (see Research Questions chapter in Literature Review

    part).

    A two page questionnaire, escorted by a covering letter was sent to managing

    directors and managers of sample construction companies. The covering letter

    explained the purpose of the research and its relevance to construction firms. It

    explained also that the questionnaire is meant to be completed only by the senior

    members of the staff on a managerial position. The questionnaire tried to deal with thefears of privacy of information by assuring the respondents that its confidentiality

    would be kept and that the information provided shall not be used for any purpose

    other than the dissertation. It also offered the organisations the possibility to receive

    the research results if they wish. This offer is thought as an extra motivation for the

    firms to participate in the research.

    The construction of the questionnaire was of such that is devoid of any ambiguou