strategic level management and project success increase
TRANSCRIPT
-
7/30/2019 Strategic Level Management and Project Success Increase
1/62
Strategic level management and
project success increase
KONSTANTINOS KONSTANTINIDIS
A dissertation submitted in partial fulfillment of the requirements forthe degree of MSc Construction Project Management
Supervisor: Dr. Graeme Bowles
Heriot- Watt University
School of the Built Environment
March 2012
-
7/30/2019 Strategic Level Management and Project Success Increase
2/62
ii
DECLARATION
I Konstantinos Konstantinidis, confirm that this work submitted for assessment is my
own and is expressed in my own words. Any uses made within it of the works of other
authors in any form (e.g. ideas, equations, figures, text, tables, programmes) are
properly acknowledged at the point of their use. A full list of the references employed
has been included.
Signed: .
Date: ..
-
7/30/2019 Strategic Level Management and Project Success Increase
3/62
iii
Contents
1. Introduction ............................................................................................................... 1
1.1 Background discussion ......................................................................................... 1
1.2 Research Aim ........................................................................................................ 2
1.3 Groundwork Questions ......................................................................................... 2
1.4 Subsidiary questions or objectives........................................................................ 2
1.5 Research Methodology ......................................................................................... 2
1.6 Anticipated findings.............................................................................................. 3
1.7 Time scale and work program .............................................................................. 3
1.8 Research structure ................................................................................................ 3
2. Literature Review ....................................................................................................... 4
2.1 Introduction .......................................................................................................... 4
2.2 Research structure ................................................................................................ 4
2.3 What is Project Strategy? ..................................................................................... 5
2.4 Defining Project Strategy ..................................................................................... 6
2.5 What does Project Strategy contain? ................................................................... 9
2.6 Towards a strategy definition ............................................................................ 12
2.7 Why is strategy important? ................................................................................ 14
2.7.1 Causes of failure .......................................................................................... 14
2.7.2 Success factors ............................................................................................. 15
2.8 The situation in Greece ....................................................................................... 16
2.9 Theoretical Framework ...................................................................................... 18
2.9.1 About success .............................................................................................. 18
2.9.2 Requirements for a successful strategy ...................................................... 20
2.9.3 Why fail the organisations to develop successful strategies?..................... 21
2.10 Conclusion ........................................................................................................ 22
2.10.1 General findings ......................................................................................... 22
2.10.2 Research questions .................................................................................... 23
3. Research Method ..................................................................................................... 25
3.1 Introduction ........................................................................................................ 25
3.2 Aim Hypothesis ................................................................................................ 25
3.3 Research Approach ............................................................................................. 26
-
7/30/2019 Strategic Level Management and Project Success Increase
4/62
iv
3.3.1 Quantitative Research Approach ................................................................ 26
3.3.2 Qualitative Research Approach ................................................................... 28
3.3.3. Mixed Research Approach .......................................................................... 29
3.4 Research Method selection ................................................................................ 30
3.4.1 Quantitative vs Qualitative Research .......................................................... 30
3.4.2 Method Selection ........................................................................................ 31
3.4.3 Research style and considerations .............................................................. 31
3.5 Sample selection ................................................................................................. 33
3.6 Questionnaire Design ......................................................................................... 34
3.7 Limitations .......................................................................................................... 36
3.8 Ethical issues....................................................................................................... 37
4. Data analysis and discussion .................................................................................... 38
4.1 Introduction ........................................................................................................ 38
4.2 The situation in Greek construction sector ......................................................... 38
4.3 Result overview .................................................................................................. 39
4.3.1 General Information .................................................................................... 39
4.3.2 Results of Questionnaire Section B ............................................................. 40
4.3.3 Results of Questionnaire Section C ............................................................. 43
4.4 Result discussion ................................................................................................. 46
5. Conclusions, limitations and further studies ........................................................... 47
5.1 Review and Conclusions ..................................................................................... 47
5.2 Limitations .......................................................................................................... 48
5.3 Future Studies ..................................................................................................... 48
References ................................................................................................................... 49
Appendix ...................................................................................................................... 53
Appendix 1 Cover Letter ........................................................................................... 53
Appendix 2 Questionnaire ........................................................................................ 54
-
7/30/2019 Strategic Level Management and Project Success Increase
5/62
v
List of Figures
Figure 1: Strategy approaches by different authors 6
Figure 2: Strategy formulation and implementation 13
Figure 3: Project/Product lifecycle stages and milestones 18
Figure 4: Measuring project success 19
Figure 5: main differences between quantitative and qualitative research 30
Figure 6: advantages and disadvantages of interview technique 32
Figure 7: advantages and disadvantages of questionnaire technique 32
Figure 8: Questionnaire promotion timeline 35
Figure 9: questionnaire construction and administration 36
Figure 10: Questionnaire return rate 39
Figure 11: Business Sectors (company activities) 40
Figure 12: Project strategy use 41
Figure 13: Percentage of feature use in project strategy 42
Figure 14: Project time decrease 44Figure 15: Project cost reduction 44
Figure 16: Predictability increase in projects 45
Figure 17: Productivity increase in projects 45
-
7/30/2019 Strategic Level Management and Project Success Increase
6/62
vi
Acknowledgement
I would like to thank all the people that have contributed both directly and indirectly
to the success of this research work. My sincere thanks go to all the respondent
Companies who have given their time and their significant answers on the research
questions and made the completion of the research possible. My special gratitude goes
to my supervisor, Dr. Graeme Bowles for his general guiding and his directions and
supports during the whole research. Also, my thanks go to the Heriot-watt University
for giving me the opportunity, the knowledge and the support to undertake a research
on this high level. Finally, my thanks go to my family and friends for their support.
-
7/30/2019 Strategic Level Management and Project Success Increase
7/62
vii
Abstract
The topic comes from the discussion about the project management effectiveness.
While PM has two equally important levels (strategic and operational), attention is
paid mainly (almost exclusively) to the operational level, aka the PM tools. This is a
misunderstanding of the very nature of Project Management and leads inevitably to a
misapplication of PM practice. The research highlights the importance of strategic
level PM and examines how much a well planned and performed PM strategy can
contribute to project success increase. The research is based on two levels, literature
review (theory) and practical research. Through the theoretical research, the
dissertation presents the function of strategy in management of projects; what exactly
is project strategy, what is its role in a project, which are the most important strategy
features. The practical part is based on a quantitative research method and shows the
level on which the construction companies are aware of this discipline, how they
implement strategy and most importantly if their planning and implementation is
bringing results. The study confirms that there is an average time and cost excess in
projects, that the majority of the construction companies are aware of the project
strategy in project management and that they use it in almost all of their projects. The
initial hypothesis that a well performed strategic level project management cancontribute decisively in project success and increase the predictability of the projects
is also confirmed. The answer to project success increase and to more successful
project management lies in project strategy, which is not something vague, but a
process / practice explicitly specified, with specific features and contents.
Keywords: Project strategy, project success increase, strategic level project
management, project strategy contents, strategy features
Konstantinos Konstantinidis
Construction Project Management
March 2012
-
7/30/2019 Strategic Level Management and Project Success Increase
8/62
1
1. Introduction
1.1 Background discussion
The topic comes from the discussion about the project management effectiveness.
More specifically, it has been proved that the majority of the projects is delivered later
than initially planned and (or) over the pre-estimated budget. Why is this happening?
Seeking for the causes of project failure, the reader will realise that the problem is not
at PM itself, but in the way of its implementation.
While PM has two equally important levels (strategic and operational), attention is
paid mainly (almost exclusively) to the operational level, aka the PM tools. This is a
misunderstanding of the very nature of Project Management and leads inevitably to a
misapplication of PM practice. The result of project failure should be therefore rather
expected. Attention should be paid at strategic level. Evans (2005) supports that
according to the Project Management Institute; there are five distinct phases in every
project: initiation; planning; execution; control; and closure. Problems take place
most frequently when initiation gets separated from execution. Shi (2011) states that
there areorganizations which have gained little value from project management and
the reason is that they have not introduced and applied project management correctly.
The operational aspects of PM process are well defined and they work (Heriot
Watt 2011, 8-3). There is a lot of discussion about the reasons of project failure and
many factors are related to strategy. According to Anderson and Merna (387393)
Creating a strategy is therefore a primary action in two ways, it is both the first step
and also the most important action since it provides the overarching plan and
objectives. The discussion has been going for many years, having a historical
perspective. Avots (1969) is referring to inadequate basis for project and inadequately
defined tasks, while Munns and Bjeirmi (1996) support that successful project
management requires among other actions spending time to define the project
adequately, correctly planning the activities in the project and ensuring correct and
adequate information flows. Dietrich (2005) also believes that high quality
information in decision making is a factor that affects successful implementation.
-
7/30/2019 Strategic Level Management and Project Success Increase
9/62
2
1.2 Research Aim
The purpose of the research is to highlight the importance of strategic level PM and to
examine how much a well planned and performed PM strategy can contribute to
project success increase.
1.3 Groundwork Questions
Based on those previously presented, the research will try to answer to three main
questions:
Why do projects fail? Which strategy factors are the most important? How can a better strategy contribute to improved project success?
1.4 Subsidiary questions or objectives
The dissertation will try to examine and present the importance of a number of topics
such as strategy factors, initial planning, taking strategic decisions, etc. The purpose is
to discover the level of their contribution to project success in terms of time and cost
reduction and predictability & success increase. Bibliography can confirm the
significance of those factors; Assaf and Al-Hejji (2006) and Al-Barak (1993)
underline the importance of early planning and project estimation practices, while
Chan (1997) supports that slow decision making and poor risk management are
among the factors that cause failure.
1.5 Research Methodology
The research will be based on two levels, literature review (theory) and practical
research. Through the theoretical research, the dissertation will present the function of
strategy in management of projects; what exactly are strategy and its role in a project
and why is it so important? After the general verging, the study will focus on the
location of the major aspects of the strategic level PM. According to the theory those
aspects influence the project success.
-
7/30/2019 Strategic Level Management and Project Success Increase
10/62
3
The practical (field) research will be developed a way that will allow conclusions
about the importance of those factors in PM to be carried out. Are the contractors
aware of the value of strategic level PM? Do they use those strategies to improve their
performance? Is that working? The sample will be the construction companies that
are working in the private sector and more specifically those that undertake mall
logistic and complex constructions in Greece. This sector is chosen for several
reasons. Those projects have an adequate level of complexity (comparing to the main
construction sector in Greece which is private housebuilding), involve contractors and
sub-contractors, and are common projects in the last twenty years (adequate number
and mature discipline). Therefore the sample is representative and suitable for the
research.
1.6 Anticipated findings
By focusing on that specific construction sector, research will confirm the high
importance of strategic level PM in project success and will also show the level at
which every strategic aspect contributes to the increase of project effectiveness.
1.7 Time scale and work program
The time scale is planned as follows:
Literature research and intro development: 1 month
Bibliography based part development: 2 months
Questionnaire based part development: 1.5 month
Analysis, Conclusion and finishing tasks: 1.5 month
1.8 Research structure
The Dissertation will have 5 main chapters, namely:
1. Introduction
2. Literature Survey
3. Methodology
4. Analysis
5. Conclusion
The study contains a reference list as well as the required appendices.
-
7/30/2019 Strategic Level Management and Project Success Increase
11/62
4
2. Literature Review
2.1 Introduction
The following section will present the theoretical background and discussion about
project strategy. The purpose is to define project strategy, identify its importance to
project management and its relation to project success. Therefore the section will be
divided into three main chapters. The first part is going to approach different views
about strategy in order to structure a theoretical framework. The second part will
proceed to the formulation of a comprehensive definition of project strategy that will
include also more practical parts, like the contents of strategy. This is important
because there is a need in project management of an applied strategy. This part will
be partially based on existing references, which will be used in a targeted way to
assist the new theoretical formulation of strategy. The third parts aim is to present the
importance of strategy in project management and its correlation with project success
and project failure. There is a specific logic around this: if we can locate the reasons
of project success or project failure; that are related to strategy, we can formulate and
use strategy in a way that can increase the success of the projects. That is after all the
basic aim of the project management discipline.
2.2 Research structure
The literature survey has two main targets. The first one is, as written above, the
formulation of a complete theory about project strategy. The second one is to generate
broad conclusions about the role of project strategy in project management. The logic
behind this is specific. The opinion of the writer is that some strategy related issues
are more or less universal and therefore need to be addressed. After reaching to the
theory building and the conclusions, the aim is to test them. The purpose is to test the
validity of both the theory and the findings related to strategy use in a more specific
area. Therefore the data research will be narrowed down to a more specific sample,
namely in Greece (for more details see Sampling part in Research Method
section).
-
7/30/2019 Strategic Level Management and Project Success Increase
12/62
5
2.3 What is Project Strategy?
The definition of Project Strategy is the first step that has to be taken in order to
explore Project Management at the strategic level. There are several opinions about
the definition and the scope of project strategy and its relation to project and Project
Management. However there is a common belief that should be highlighted: since
every project is unique as it includes unique characteristics, objectives, etc every
project strategy should be unique for every single project respectively. Shenhar et al.
(2000) clearly underlines that for each project a distinct and unique process of doing
things has to be developed in order to succeed in the specific situation. Project
strategy is that explicit process. Artto et al. (2008) provides a similar approach by
underlining that the projects unique environment is to be taken under consideration
when formulating the project strategy, which is a dynamic direction that contributes to
its success. Project strategy is therefore the strategy of a single project.
A different view is provided by Naaranoja et al. (2007), who distinguishes project
strategy from project management strategy. According to the writer project strategy
refers to a high level plan for achieving the projects certain objectives and it is
related to strategic decisions during the project life-cycle. On the other hand, aspects
like team building; project flexibility; risk management avoidance; contract strategy
and alliances are part of the project management strategy, which is the strategy for the
management of the project. This point of view separates project strategy and project
management strategy by presenting them as two different disciplines.
Another important addition to the theory provided by Shenhar et al. (2000) is the
differentiation between a strategy and a plan. According to the writer plans include in
general decisions about the operational aspect of a project, such as activities
scheduling, resources allocation and use, timelines, and deliverables. Strategy on the
contrary is one level above those activities. This is a significant clarification, since
very often project managers and organisations tend to focus only on those operational
level features, without the formulation of a general strategy to drive them. A plan
should be part of a broader strategy if it is to be adequately effective and successful.
The following figure shows the general views about strategy that are presented by
different authors in the last decade. This is only indicative and its role is to highlightsome important project strategy features.
-
7/30/2019 Strategic Level Management and Project Success Increase
13/62
6
Figure 1: Strategy approaches by different authors
Author Approach Year
Shenhar et al. Project uniqueness, strategy according to project 2000
Kerzner Strategy has to be objective - driven 2001
Anderson and Merna Strategy provides the overarching plan and objectives 2003
Naaranoja et al. Project strategy different from project management strategy 2007
Artto et al. Project uniqueness, strategy should lead to success 2008
Source: own processing
2.4 Defining Project Strategy
As presented above, there are different views about what exactly project strategy is.
However a proper definition is the first step for actual successful development and
implementation. Therefore the basic characteristics and a specific definition will be
presented below.
Project strategy or project management strategy
Is project strategy something that has to be distinguished from project managementstrategy? This is the first and maybe fundamental question someone has to answer in
order to proceed to the rest theoretical formulation. As presented above there are
different views about the theory. For Naaranoja et al. (2007) those two are referring to
different aspects and strategy levels, while Artto et al. (2008) does not separating
them. Since it is rather a matter of theoretical view than a fixed theory / definition,
every aspect has its arguments. Project strategy is the generic strategy of the project. It
has to drive the complete project and define all of its features. It defines the way to
achieve the projects objectives, the direction and the philosophy of the strategic
decisions and handling of the project. However the project strategy should also clearly
define project flexibility, contract strategy, risk management, cost management, etc.
Those are not to be excluded from the project strategy. They should not be defined on
another (latter) stage of the planning, or independently from other strategic decisions.
The way a project is going to be managed has to be defined by the project strategy.
Therefore, project management strategy is not to be distinguished from project
strategy. It can be said that they are in essence the same thing.
-
7/30/2019 Strategic Level Management and Project Success Increase
14/62
7
Uniqueness / adopted to project
Every project is unique. There are of course some characteristics that are common for
all projects. Every project has objectives; there can be no project without them. On the
other hand, the objectives of every project are particular and specific, giving to the
project a unique nature (since projects are objective driven). In addition, every
project has stakeholders, but at the same time, the number, the composition and the
importance of every stakeholder differ from project to project. Furthermore, resources
of all kinds are an exclusive (but always present) part of every project. It is obvious
that the same thing applies for all project features (constrains, etc). That fact leads to
the conclusion that, since every project is unique, every project strategy has also to be
unique. In other words the project strategy has to be adapted to the specific project;
hence it must be developed exclusively for it. Like projects, all project strategies have
to contain both common and unique features.
Process leading to project success
A project strategy has to be interconnected to project success. After all, project
success is one of the main reasons for project management development. The role of
project strategy is to drive the project from the early (before initiation) phase through
all the stages, to prepare the key participants for any potential issues, to set up the
management plan, to contribute to control, general operation, project administration,
etc. All those will be defined on a level from the strategy formulation. A well planned
and integrating developed strategy is of key importance for a successful project.
Therefore one of its tasks is to lead to project success.
Organisingplanning the project
Driving from above, the project strategy has to lead to the project plan. The general
setting up, the way the progress will be monitored and controlled, the operational
plan, the administrational style, in other words every general (or even some more
specific) aspect and direction that will affect the whole progress has to be a direct
result of the formulated strategy. Strategy has limited use and effectiveness if the
-
7/30/2019 Strategic Level Management and Project Success Increase
15/62
8
planning of the project is independent from it. Moreover a project plan that is based
on ad hoc decisions with no association with each other and a general project strategy
will be not able to drive the project successfully and solve any possible problems
whatsoever.
Justification
The four main issues presented above create the basic characteristics of project
strategy. It is expected that authors or organisations will have differences in their
views of strategy. It can be said that a view is accepted if it can be justified. Examples
often help that process. If a project strategy sets only a broad generic framework of
the project, without dealing with project management issues like project flexibility,
cost / risk management, etc it will not be able to assist the managers taking strategic
decisions during the project. The managers that will be responsible for the project
should define for example the number and the kind of subcontractors that will be
appointed and the work that they will undertake. In case of underachieving, or if
problems arise strategic decisions (changes, tradeoff, etc) must be taken. Project
uniqueness is also a key factor, since special features of the project play a main role.Different stakeholders create different environment of the project. The same thing
applies in a number of other factors such as location of the project. A different project
organisation is required for example at a project in an urban area, a suburban area, a
rural area or an island. Transportation, infrastructure, prefabricated parts, even
weather and site conditions and many more are factors that combined create the
uniqueness of the project. Therefore the formulation project strategy has to be based
upon those factors. Project planning and organising should also be clearly defined. It
should be clear and predefined who is responsible of what, what should be the work
structure and progress, how are those to be monitored and measured, who will take
the decisions in every case. Projects that do not solve those issues tend to deal with
organisational problems that lead to failure. Tools like Work Breakdown Structure
(WBS), Organisation Breakdown Structure (OBS), Statement of Work (SOW), Task
Responsibility Matrix, etc have been created to assist those procedures. All the above
mentioned lead as expected to project success. It is already mentioned that project
success is the main aim of project management. Therefore, project strategy which can
-
7/30/2019 Strategic Level Management and Project Success Increase
16/62
9
be defined as the initial process in project management should at all case drive to and
maximise the project and product success.
2.5 What does Project Strategy contain?
After an initial approach of project strategy the next step in order to come up with an
integrated definition is to locate the main contents of it. In other words, what should a
comprehensive and successful strategy take under consideration and thus include.
This is an important section because it particularises the general view and theory and
shows how it can be useful on a more practical level. In other words, what should
every project team incorporate and take under consideration during the formulation
and implementation of a project strategy.
Scope management
Scope management should be the beginning of project strategy. It includes all the
aspects of the project; quality, performance, specifications and properties of the
project product. There are in fact the quantitative and qualitative deliverables of the
project, thus the work that needs to be done in order the project to be completed
successfully. Taking this under consideration, scope management has to be the
initiation of the project strategy, since all the project objectives will be come from it.
S.W.O.T. analysis
This is basically a mapping process. It locates, defines and assesses strengths,
weaknesses, opportunities and threats of the project. It is a valuable procedure that
provides a representative image of the project and its issues and characteristics.
Kerzner (2001) states that identifying opportunities and threats allows us to spot what
we want to do, but recognising our strengths and weaknesses lets us be aware of what
we can do. Therefore, strategy should be formed by taking under consideration those
matters in order to be effective and in response to the unique characteristics of the
project.
-
7/30/2019 Strategic Level Management and Project Success Increase
17/62
10
Correlation with the project objectives
It is well known and widely adopted that the projects are on a high level objective
driven. According to HeriotWatt (2009) thesuccess of a project can be measured in
terms of how closely it has met its prearranged objectives. The objectives of a project
show in a way the project direction. Site set up plans, resources allocation and
mobilisation, time sheets and many more project features are mainly dependent from
the objectives of the project. Furthermore, every projects milestones are utterly
related to the project objectives. Therefore also project progress; performance
measurement and benchmarking are reliant on the project objectives. The formulation
of the strategy has to be based upon the specific objectives of the project. The
management and the achievement of the objectives should be the main guidelines.
Kerzner (2001) supports that the process of the objectivesetting and the integration
of the implementation through methodology assure that all of the parts of an
organisation are moving toward the same common goal. A careful mapping and
assessment of the objectives have to be of the main drivers of the strategy creation
and development.
Work Management Plan
After defining the projects objectives the next step is to define the work that needs to
be done in order to achieve them. The project strategy has to classify the amount and
type of work that needs to be done for the project completion. A comprehensive
analysis of the project works is of main importance in project planning. This process
contains an analysis of the amount, the type and the sequence of the project works.
Those have to be planned early and carefully and in detail because they are practically
the core of each project. Through this plan will be also decided and formed the time
of each work units completion and most important the allocation and utilisation o f
the available resources. In other words, the Work Management Plan is the framework
that drives the planning and the organising processes of the project. An organisational
structure of the project that includes also specific responsibilities can be formed either
separately, or as part of this plan with each group of activities assigned to specific
people.
-
7/30/2019 Strategic Level Management and Project Success Increase
18/62
11
Criteria to assess success
Driving from above, every strategy has to enclose criteria to assess the project
progress and success. Performance measurement is a procedure of main importance
during a project lifecycle. It is for that reason essential for a project strategy to plan
and formulate carefully on that direction specific criteria. Those will make available a
measurement which will reflect the real project progress. What strategy needs to set is
specific goals and standards. These have to be both quantitative and qualitative and
cover all the aspects of the project and the product. In addition to those an integrated
strategic planning should also provide possible measures that should be taken if
performance is bellow the expected and planned levels. That naturally leads to the
next topic bellow.
Risk Management Plan
Risk management is a valuable procedure in every project. Raz et al. (2001) describes
it as one of the key processes in project management. Poor risk management can lead
to project delay, cost increase, scope affection, or even cancellation of the project
(failure in general). The plan should map and locate possible risks, their probability,
the effect they might have on the project progress and of course ways to solve any
upcoming problems. Strategy planning that does not contain a full risk management
plan cannot be complete effective at the time when problems arrive. According to the
Project Management Body of Knowledge (PMBOK) of the Project Management
Institute (2004), in order to be successful, an organisation should be committed to
addressing the management of risk proactively and at all times throughout the project
lifecycle. Kerzner (2001) also supports this view. He believes that a reaction to a
crisis of the moment may lead to a choice that is not linked to, and maybe also
conflicting with, the choice made in an earlier moment of crisis. Discontinuous and
contradictory choices are causing problems to the organization and might well be the
reason of its failure.
-
7/30/2019 Strategic Level Management and Project Success Increase
19/62
12
Cost Estimation
Egan (1998) supports that some of the construction industry problems are competitive
tendering and low profit margins. According to Doloi (2011) cost overrun is a
constant problem across most projects and the accuracy of cost estimation is affected
by the experiences of the bidding team and project managers as well. One of the main
results of project failure is cost overruns. For those reasons precise cost estimation is
of key importance in a project. A comprehensive and integrated strategy has to
carefully estimate every aspect of the project that can affect (either in a positive or in
a negative way) the cost of the project. That way it is possible to define which the cost
parameters of the project are, what are the profit margins and whether or not it is
possible for the organisation to undertake the project. A strategy with poor or
inaccurate cost estimation is likely to lead to project failure or cancelation.
2.6 Towards a strategy definition
Giving a specific definition to the term of project strategy is not only a theoretical
matter. The way someone defines projects strategy affects also the approach of the
implementation. Drawing from the topics presented above, the definition can be
formed as follows:
Project strategy is a comprehensive direction plan that defines the way a project will
be successfully managed, taking under consideration its unique characteristics.
That definition includes more or less elements from the topics presented above both
from the general and the specific ones (see those referring to the strategy contents and
Figure 1). It is clear that there is no single definition of strategy and each writer can
give a different perspective of that, although some issues remain always common.
This happens because independently of the personal view, everyone will agree on the
strategys main aim which is successful management, in other words achieving
projects objectives working with high productivity on time and scope, not above
predefined cost and with the product on the specified quality standards. Project
strategy in order to lead to a successful project has to be seen as the vehicle to manage
the project and not as a standardised and typical procedure that is identical in everysingle project. Furthermore strategy, as a continuously applied process, has to be
-
7/30/2019 Strategic Level Management and Project Success Increase
20/62
13
flexible and able to change and become adapted to project changes and alterations.
The proposal about strategy formulation and application during a project is presented
bellow in the following figure:
Figure 2: Strategy formulation and implementation
Source: own processing
The figure shows clearly the issues mentioned above. Project strategy can be divided
into three main sections (or stages); analysis and plan formulation, decision and
implementation and control. Feedback and revision processes are playing a very
important role in this procedure, since they drive the improvement and adaptation of
the project strategy. It should be noticed however that the first step is extremely
important in this procedure. A comprehensive analysis that includes and takes under
consideration all the critical factors (see strategy contents) will not only require fewer
and small scale revisions, but will be also much more adjustable and alteration
friendly.
-
7/30/2019 Strategic Level Management and Project Success Increase
21/62
14
Although there is a multiannual literature about project strategy it remains a question
whether project managers and companies today know about the importance and the
role of project strategy. This is in fact one of the main questions of this paper.
However before proceeding to this section it is of key importance to answer to another
question. That question is why is strategy important? Where and how can strategy
contribute to project success, or otherwise can a strategy absence or misapplication
lead to project failure?
2.7 Why is strategy important?
In order to answer to this fundamental question the theoretical approach has to cover
two views. Therefore the following chapter will be divided in two sections. The first
part will approach the causes of failure and underachieving in projects and locate
strategy related factors. The section should reveal that lack of strategy leads to project
failure. The second part will present the factors of the projects that lead to success and
the role that strategy plays in those factors. A strong correlation between strategy and
success is expected to be found.
2.7.1 Causes of failure
There are several studies that try to locate the reasons of project failure. Strategy
related reason can easily be found on them. Assaf (2006) states, that the completion of
a project within the specified time is a rare occurrence. Among the reasons of delay
are also early planning and design of the project. He adds that planning and
scheduling are ongoing procedures during projects and equal to the resources and time
to develop the work that is essential in order to avoid cost overrun and disputes. This
means basically that inadequate early planning (strategy formulation) leads to time
overrun. Al-Barak (1993) studies the main causes of failure in Saudi Arabia
construction industry. He surveyed 68 contractors and 34 different causes of failure.
The study concluded that lack poor estimation practices and bad decisions in
regulating companys policy are among the critical factors . Those are parts of strategy
as it is developed above (see previous part). Chan and Kumaraswamy (1997)performed a survey to evaluate the relative importance of 83 potential delay factors of
-
7/30/2019 Strategic Level Management and Project Success Increase
22/62
15
construction projects constructed in Hong Kong. They found five principal causes,
which were poor risk management and supervision, unforeseen site conditions, slow
decision making, client-initiated variations, and work variations. All of them (except
maybe supervision) are related to project strategy as presented in previous chapters.
Kaming (1997) et al. located among others in cost overrun factors inaccurate material
estimation and degree of complexity, while time overrun reasons include inadequate
planning. Those factors show that it is impossible to have a clear view of the project
special features without the formulation of an integrated strategy. Shenhar et al.
(2000) suggests that there is a strict difference between operationally managed and
strategically managed projects and that traditional project management focus is on
operational performance. The article adds that there is a need for a new, more
strategic way of thinking in project management. All those studies show that
inadequate strategy formulation equals to project failure. Having a wrong idea about
the project leads to incorrect planning; wrong decisions in project management and
poor responses to problems that may occur. Due to these projects exceed time and
cost limits and can end up with an altered scope.
2.7.2 Success factors
By precisely locating the reasons of failure, it becomes easier to define and formulate
success factors of projects. From the information presented above is clear that project
strategy has a key role in projects. Since a misunderstanding, an inadequate or
inaccurate formulation or a misapplication of strategy can cause failure of a project, it
is only logical that a highquality strategy can be a driver of project success. This is
an idea that has been presented several times. Munns and Bjeirmi (1996) in their
article discuss the role of project management in achieving project success. They
suggest that a successful project management requires also among other factors:
planning with a commitment to complete the project, spending time to define the
project adequately, correctly planning the activities in the project, ensuring correct
and adequate information flows and changing activities to accommodate frequent
changes on dynamic. All those are factors that are directly related to strategy as it has
been presented above. It is even more accurate to say that they are an integral part of
strategy. Moreover, Cooke (2002) released a research from more than 70 large multi-
-
7/30/2019 Strategic Level Management and Project Success Increase
23/62
16
national or national organizations on the success factors of the projects. Four out of
five factors related to time success and one out of two factors related to cost success
(ontime performance and oncost performance respectively) are directly related to
project strategy. More specifically the strategy related time factors are adequacy of
company wide education on the concepts of risk management, sufficiency on
maintenance of a visible risk register, capability of having an up-to-date risk
management plan, and a sufficient documentation of organisational responsibilities on
the project. Furthermore, one of the two on cost performance factors is to maintain
the integrity of the performance measurement guideline. All those factors that lead to
time and cost success of a project are explicitly related to project strategy and confirm
that a well planned and carefully formulated strategy can increase the success of a
project. Kerzner (2001) also confirms that statement by supporting that when the
implementation process is made precise, objectives, missions, and policies become
visible guidelines that create logically consistent decisions. On cost estimating he
adds that strategic planning can include provisions in the methodology for better
estimating techniques, such as the creation of lessons learned files on previous costing
and the purchasing of historical databases. He concludes supporting that effective
strategic planning can mean the difference between long-term success and failure
(Kerzner 2001, p9).
2.8 The situation in Greece
The research sample will be the construction companies in Greece (for more details
see Sample selection in Research Method part). It is therefore important to set up
a framework view about the topic in the country. There is however a fundamental
problem in this process, mainly because of the lack of bibliography and references
about the Project Management discipline (Pantouvakis, 2003).
It is nevertheless a fact that like in all other countries, projects in Greece often exceed
time and budget limit and are completed bellow the specified quality standards
(Pantouvakis, 2003). Inadequate project planning leads to a result where strategically
important actions remain unexecuted while the whole organisation structure and
culture are being lead by ad hoc processes (Kourounakis, 2010). According toChazapis (2010) the most efficient way to achieve project success is to ensure that the
-
7/30/2019 Strategic Level Management and Project Success Increase
24/62
17
project team will be well prepared for any potential problems that might occur. That
view underlines and highlights the importance of strategic planning. Furthermore,
Bafas (2007) underlines the importance of a various features in project management
planning. The features (scope management, risk management, cost estimation, project
objectives mapping, Work Breakdown Structure, etc) are identical to those presented
above during the Literature review and the formulation of the theory.
It can be realised that in general terms the situation in Greece regarding project
management and its practices does not differ from the general findings that this
specific research underlines. In any case, the questionnaire results will be able to
provide a more specific and detailed aspect about this matter (see Questionnaire
Design in Research Method part).
-
7/30/2019 Strategic Level Management and Project Success Increase
25/62
18
2.9 Theoretical Framework
2.9.1 About success
There is a very long discussion about project success. What is considered to be project
success and how it can be measured is a matter that allows many different views.
Although it is not directly the topic of this research, a compact discussion about this is
necessary. First of all we have to underline that success in a project has different
views. A project that ended for example on time, on budget and according to the
quality standards is successful for the owner, but can be unsuccessful for the
contractor if he had no profit or if he lost money. There is even the possibility that
both the owner and the contractor consider the project as successful but the final users
believe that the product does not cover their needs. Project success and product
success have are of course interrelated but at the same time they are two different
matters. If it is viewed completely isolated, a project can be successful even by
creating an unsuccessful product and on the other hand a successful product can be a
result of an unsuccessful project. Angus et al. (2005) present very comprehensible
examination regarding the matters of project, product and view of stakeholders in the
following figure:
Figure 3: Project/Product lifecycle stages and milestones
Project lifecycle Product lifecycle Owner/ActionsStage 1 Project
conception
Product feasibility The client organisation, assisted by specialists
Milestone
1
Project
commitment
High level product requirement
produced
The client commits to the project and appoints a
project team
Stage 2 Project
execution
Design, development or
acquisition
The project team (the prime contractor assisted by
subcontractors)
Milestone
2
Project closure Product created The project team delivers the created product to the
clientStage 3 N/A Product operation The client organisation, possibly transferred to a
customer/user
Source: Angus et al. (2005 p. 429)
It can be clearly seen that project and product are separated from each other and also
that there are different owners in each phase. The main purpose however of a
successful strategy is to lead to a successful project. If the final product is created
according to the initial specifications and does not meet the final users needs, that is
not a question or a problem of project management and hence of the project
-
7/30/2019 Strategic Level Management and Project Success Increase
26/62
19
management strategy. It should be noticed that the present research focuses on the
strategy related to project management. It is however helpful to see a holistic view of
success that includes the success of all factors of a project (project management,
product, market, etc) and highlights the initial argument, provided by AlTmeemy et
al. (2011):
Figure 4: Measuring project success
Source: AlTmeemy et al. (2011, p. 339)
As written above the discussion about success can be approached in many different
ways. Regarding project (management) success there is also a relativity issue. If for
example there is a need for changes to some of the technical specifications due to
external reasons; that could alter the whole project scope. A solution however that can
approach the initial planning can easily be considered as a success even if for example
raises the total cost of the project. There are numerous tradeoffs like that to be
considered regarding time, cost, quality, scope, efficiency, value etc.
Furthermore this view can be expanded. In a hostile environment for example, with
several different problems and issues, even the survival of the project can be
-
7/30/2019 Strategic Level Management and Project Success Increase
27/62
20
considered as success. There is clearly not a single approach to the matter. This is also
one of the reasons why this research is about increase project success. In every case
nevertheless it is clear that a wellestablished and wellapplied strategy is required
to achieve project success.
2.9.2 Requirements for a successful strategy
It is important to notice that in order the strategy process to be successful, there must
be followed some principles. First of all the whole project has to be very specific and
not to contain any kind of vagueness. The people inside the company who are taking
the decisions should be aware of all the aspects of the strategy. Secondly, the internal
and the external assessment must be integrated. A good analysis will provide the right
information that will allow the company to set up a realistic mission and the
appropriate goals to achieve it. An analysis that does not reflect the real situation and
does not take under consideration all the important factors may lead to an
unsuccessful strategy and even to company failure.
There must also be a clear correlation between the mission, the goals and the actions.
Every goal decided has to contribute to the achievement of the mission. Goals should
not be set if they are not related to the mission of the project. Likewise, the
determined actions should reflect the projects goals (objectives). It is also important
to notice that mission should not be changing according to goals and goals should not
be changing according to actions. This is a mistake that many organisations use to
make. Those steps must be interlinked with a very specific way.
Great attention should be given also to implementation process. It is common the
actions finally taken to differ from those initially decided. A good strategy is of no
use, if it is not applied the way it was planned. That underlines the importance of the
third stage (see Figure 2). The performance should be measured in order to note if
everything goes according to the planned strategy. An integrated control and
evaluation system is key factor for a successful strategy. Feedback is of great
importance for the control system. Any conclusions made after evaluation should be
used to change the strategy process, if necessary. It should of course be noticed that
-
7/30/2019 Strategic Level Management and Project Success Increase
28/62
21
the reliability of the feedback depends very much on the quality of the evaluation
process.
Finally, like mentioned above, it is important for the strategy to be flexible. It must be
capable to be adjusted to any unexpected changes that may occur. The strategy should
not be followed blindly, because it reflects reality. If the reality changes the same
thing must happen to the strategy, too.
2.9.3 Why fail the organisations to develop successful strategies?
As analysed before, the strategy in general and the strategy process are meanings that
are in general known and surely easily available to the organisations. However it is
common that the organisations fail to develop successful strategies. As Whittington
says, the average book on strategic planning [management] is pretty cheap. So, how
come, if the secrets of strategic management are so cheaply and easily available,
many organizations fail to develop successful strategies? Is there something wrong
with the literatureor maybe even the concept itself? (Clegg et al. 2005, p410).
The answer to that is not so difficult, as it appears to be. If there was a problem withthe literature, there would not be any organisations that have developed successful
strategies based on the literature. Moreover, if there was something wrong with the
concept itself, there would be not organisations that have developed successful
strategies at all. So we can say that it is more a rhetorical question. The problem is not
in the theory; it is when the theory is applied.
As written before, strategy and the strategy process contain many factors that have to
be fully understood. Sometimes the organisations set up their strategies, but they dont
give attention to all of the requirements presented before. Those requirements are
relevant with the implementation of strategy. It is logical, that if something goes
wrong during the implementation process, the theory will not be of any use. All stages
and steps of the strategy process are connected with each other; the process is like a
chain. That means that one mistake or omission during the process can affect the
whole performance. Organisations that fail to develop successful strategies often are
those which did not take under consideration all the factors. A reason for that is thatmany times, those who are supposed to plan the strategy and monitor the strategy
-
7/30/2019 Strategic Level Management and Project Success Increase
29/62
22
process, are not well trained to do so. Managers must have advanced studies in order
to correspond to the corporate requirements; otherwise failure is possible to happen.
2.10 Conclusion
2.10.1 General findings
The review developed and presented the nature, the role and the importance of project
strategy in project management. Project strategy is not an abstract concept. It is a
specific and explicit process that is strongly correlated to the project itself; a
procedure that it is central and must not be seen as typical. Project strategy has to be
uniquely developed for each project and must respond to each projects special nature
and characteristics. It has to lead to project success and help the administration team
to successfully manage the project. It is a dynamic process that can be changed and
corrected during its implementation as long as it is wellplanned at first place.
Underestimation of the role and the importance of project strategy can increase the
completion time or total cost of the project, change its scope, decrease the quality of
the product, and lead to project failure in general or even to project cancellation. Onthe other hand, a well planned and successfully implemented strategy can lead to
problem overcoming, effective management, effective response and project success in
general. A strategic level project management that is performing well can only lead to
an effective operational level. Tools do not manage projects by themselves but can be
a crucial factor of successful management if they are utilised as part of a broadly
applied strategic planning.
To sum up with, this part explicitly highlighted what is project strategy about and
what is its essence in general terms. Specific strategy features and contents of strategy
have been addressed in this part. Those are important not only on a theoretical basis,
but also on a practical level. They should be included in every project strategy.
Moreover the importance of strategy regarding project success and project failure (as
a result of inadequately planned or miss applied strategy) has been stressed,
confirming the initial research hypothesis.
-
7/30/2019 Strategic Level Management and Project Success Increase
30/62
23
2.10.2 Research questions
The importance of project strategy is proved on the theoretical basis, but it is still a
question whether contractors share the same view about this process and use it in the
right way during the projects they undertake. Is it possible to increase project success
and if so, what do we have to change? There are issues that need to be addressed in
order to answer to this fundamental question. The literature review showed the role
that the project strategy should have in order to contribute to project success increase.
There is a need to test whether the construction companies are aware of this role, how
they implement strategy and most importantly if their planning and implementation is
bringing results. Therefore, the main research questions that are created are the
following:
o Do the contractors plan and implement project strategy in their projects?This question is based on the causes of failure and success factors topics that
structure the importance of strategy (see Why is strategy important?). Since the
importance is proven, there is a need to examine, whether or not the contractors
act accordingly.
o Is project strategy a common practice?This is practically the second part of the previous question. It particularises the in
fact the first question: If the contractors do plan and implement project strategy, at
what amount do they do that? Is it a broad discipline?
o Which strategy features are known and used?During the theory building, specific features (contents) of strategy were proposed
and presented (see related part, What does Project Strategy contain?) Theamount and the frequency of their use have to be tested. Moreover any additional
features can accrue from this question.
o How successful are their projects in terms of time, cost, effectiveness, etc?According to the theory, projects in Greece and in general (see The situation in
Greece and causes of failure parts) often exceed the pre -defined limits and
constraints. The research will try through this question to define an average time
-
7/30/2019 Strategic Level Management and Project Success Increase
31/62
24
and cost excess in the projects in Greece. This is a very important fact for the
study.
o Do the contractors notice project success and predictability increase due to theuse of strategy?
This is maybe the most important question of the research. It is a question that can
mainly prove the theory formulated by this study. There is a simple sequence of
thoughts: Projects are underachieving, a main reason for that is the inadequate
planning and implementation of strategy, a better planning and implementation
can increase project success. If the contractors can validate a success increase due
to strategy, the theory is proven.
Those five are the main research questions that need to be answered. They represent
not only the initial aim of the research (The operational aspects of PM process are
well defined and they work (Heriot Watt 2011, 8-3), but also the issues that have
been developed in the literature survey part. Through those questions a data research
can be undertaken in order to provide specific statistical answers about the strategy
related issues. The questionnaire questions will be based upon those five main
research questions (see Questionnaire Design).
-
7/30/2019 Strategic Level Management and Project Success Increase
32/62
25
3. Research Method
3.1 Introduction
As mentioned above, the general theory is confirming the role and the importance of
the strategic level project management. It is however important to look at the applied
practices in the construction sector in order to find out the relationship between theory
and practice. In order to proceed to the research, a decision about the method to be
followed is needed. The selection of the method that will be suitable for the desired
research is something that requires consideration. It depends mostly on the research
topic, the research type and the research area. The purpose of the following chapter is
to examine and contribute to the decision about the research approach that will be
adopted to undertake the necessary research. Therefore the chapter will present all the
necessary facts and features of the subject and investigate the methods in order to
highlight the one that is appropriate for the case.
3.2 AimHypothesis
Creswell (2009); states that the role of the purpose statement is to set the objectives,the target, or the major idea of a proposal or a study. In this case the aim of the data
collection is to test the theory formed at the previous chapters. Previous chapters
proved the importance of the strategy in project management, found the correlation
between strategy application and project success or project failure and showed clearly
that this level of management is a key factor for improving project success and project
management effectiveness and efficiency. Moreover a definition of strategy has been
established along with strategic features and specific contents which are aiming to
applied strategy or simply strategy implementation. It is therefore important at this
point to undertake a research in the construction sector and find out what is the
approach of the construction companies regarding strategy matters. This is about both
formulation and use of strategy in projects. Moreover the purpose is to find after the
research ways to increase project success.
-
7/30/2019 Strategic Level Management and Project Success Increase
33/62
26
3.3 Research Approach
Fellows and Liu (2008); support that it is a frequent occurrence for people to believe
that research has not really started before the initiation of the data collection, which is
not valid. A commonly occurring issue is that the data collection is begun too early
before the theory and literature review and, in some extreme cases, even before the
finalisation of the research proposal. It is therefore of high importance to notice and
define the role of the data collection during a research.
The essence of a research is to collect information and data about a particular subject
area that is to be examined with a view of critically analysing, assessing and
understanding the information. That information is going to lead to a conclusion. For
this purpose to be achieved there is the need to create a specific and appropriate way
of questioning the research objectives in other to assure a constructive result. This
questioning type refers to the strategy that will be adopted in the data collection and
the result analysis.
There are three main research approaches, namely the quantitative research approach,
the qualitative research approach and the mixed method approach. According to
Naoum (2007) deciding on the type of research to be adopted, depends on three mainissues, namely the purpose of the study, the type and the availability of the
information which is required. The main and key difference is located between the
quantitative and the qualitative research method. They represent two different
research approaches and philosophies. Each one is used under different
circumstances. Mixed method uses tools and procedures from both quantitative and
qualitative approaches. The amount and the type of each approachs participation may
vary since they are depending on the research type and subject.
3.3.1 Quantitative Research Approach
Quantitative research is objective in nature and is thought of as a strategy that
places emphasis on quantity of data. It is defined as an investigation into a problem
(of social or human nature). This investigation is based on testing a hypothesis or a
theory that is consisting of variables, measured with numbers, and analysed withstatistical procedures. Therefore, the aim is to investigate, study and determine
-
7/30/2019 Strategic Level Management and Project Success Increase
34/62
27
whether the hypothesis or the theory hold true (Creswell, 1994). Bouma and
Atkinson, (1995) support that quantitative data is not abstract, they are hard and
reliable since they are measurements of substantial, countable, sensate features of the
world. Quantitative research is therefore solid, specific and contains fixed variables,
calculations and results.
When is quantitative research selected?
Fellows and Liu, (2008) suggest that quantitative research is about making
measurements in collecting data. According to Naoum (2007) quantitative research is
to be selected under two specific conditions:
1. When a survey is required to investigate and discover facts about a concept, a
question or a feature.
2. When there is a need to collect factual verification and examine the relationship
between those facts in order to test a specific theory or hypothesis that has been
expressed or developed.
Fellows and Liu (2008); support thatthis approach is based on previous work which
has already developed specific principles, laws and theories. The purpose of thismethods use is to contribute to the decision of the data requirements arising in a
particular research project.
Furthermore they add there are two major questions regarding the quantitative
research procedure: firstly what is to be measured and secondly how should those
measurements be made. Moreover an aspect that may be unnoticed is the scale of
measurement. There should be paid great attention, since the nature of the scale
selected is of high importance. The research should identify clearly and carefully the
unit of analysis (Fellows and Liu 2008).
The use of literature
Quantitative research incorporates an extensive amount of literature at the beginning
of a study. In those cases the function of literature is to introduce a theory, an
explanation for expected relationships, or to provide direction for the main questionsor hypotheses of the research. It plays also a second role, which is to present a
-
7/30/2019 Strategic Level Management and Project Success Increase
35/62
28
problem or to describe in depth the existing literature related to the subject. That part
of the study will be separated from the others, usually under the title Related
Literature or Literature Review, or some other analogous phrase. At the closing
stages of the study, the literature is revisited by the researcher; who proceeds to a
comparison between the data results and the previous findings in the literature. In this
type of research, the researcher utilises the literature in a deductive way, as a
framework for the research questions or hypotheses (Creswell, 2009).
3.3.2 Qualitative Research Approach
Naoum (2007) provides an accurate definition about qualitative research. He states
that is an approach subjective in nature, which emphasises concepts, experiences
(which often are described in a verbal way), explanation and so on. The data collected
in this procedure can be divided in two research categories which are exploratory and
attitudinal.
When is qualitative research selected?
Exploratory research is used when there is a partial amount of knowledge about theinvestigated topic, while attitudinal research is used to evaluate the opinion,
estimation, or the belief of a person in a subjective way, towards a particular object,
Naoum (2007). Fellows and Liu (2008) add that qualitative research is the appropriate
research method in cases of theory building research, which is a research which seeks
to build a theory around the collected data. Grounding theory is a representative
example of that.
They also add that this kind of procedure (developing theory from data) needs a great
amount of a continuous, over a relatively long period and comprehensive interaction
between the researcher and the observed, (Fellows and Liu, 2008). Therefore
qualitative research method is not ideal in cases where there is a narrow time limit for
the data collection.
Since the information generated from this research method represents in general terms
what have been said by people either by interview or what was observed, it is a
-
7/30/2019 Strategic Level Management and Project Success Increase
36/62
29
method that is mostly used along with tools like interview or open ended questions in
questionnaires.
To sum up, qualitative research is the appropriate method when there is a need to
develop a new theory, to explore personal (subjective) views about a specific topic
or an issue, or when there is a lack of information related to the research area.
The use of Literature
In theory-oriented qualitative studies, such as critical theory, or an advocacy or
emancipatory aim, the researcher can locate the theory discussion and literature in a
separate section, typically toward the beginning of the write up. However, in
qualitative research, the researcher can also include the literature part in the final
section. The literatures role in that case is to be compared and contrasted with the
results that came out from the data collection based study. It is a model that is, as
written above, mainly popular in grounded theory studies (Creswell, 2009).
3.3.3. Mixed Research Approach
As written above, this is an approach that utilises methods and tools from both
approaches (quantitative and qualitative). The logic behind this is that there are cases
where the features of a single method are not enough to support the type of research
that is required to be undertaken. Creswell (2009) describes the way of using the two
different approaches during literature review and data research. He states that if for
example the study initiates with a quantitative phase, then the researcher is likely to
embrace a substantial literature review that facilitates to set up a justification for the
research questions or hypotheses. If on the other hand the study starts with a
qualitative phase, then the literature will be considerably less, and thus, the researcher
may include it more into the end of the study, leading to an inductive approach. In the
case where the researcher advances a concurrent study that contains an equal amount
and weight on both qualitative and quantitative data, then the literature part may take
either qualitative or quantitative forms, (Creswell, 2009).
It is clear that the nature of the mixed approach does indeed allow flexibility during
the research, since it allows the researcher to alter or adjust the research style
-
7/30/2019 Strategic Level Management and Project Success Increase
37/62
30
according to the type or the environment of the study. However due to that reason it
can only be used on specific situations, when no other approach can generate the
expected results, or drive the research towards completion.
3.4 Research Method selection
As already mentioned the selection of the appropriate research method is critical for
the successful completion of the research. Since mixed method is considered to be
unsuited due to its characteristics (see above), the following chapter will summarise
and present the main features of the two major approaches (quantitative and
qualitative) in order to define the most suitable method for this particular study.
3.4.1 Quantitative vs Qualitative Research
The two different approaches have their own specific characteristics and elements.
Therefore they each one of them is suitable for a different kind of research, topic and
environment. Naoum (2007), states that the difference between quantitative and
qualitative research is rather like the difference between counting the shape and
types of design of a sample of green houses as opposed to living in them and feeling
the environment, (Naoum 2007, p.42). The following figure shows the main
differences between the two research philosophies.
Figure 5: main differences between quantitative and qualitative research
Quantitative Qualitative
1 RoleFact-finding based on
evidence or records
Attitude measurementbased on
opinions, views and
perceptionsmeasurement
2 Nature of research Objective Subjective
3Relationship between
researcher and subjectDistant Close
4 Scope of findings Nomothetic Idiographic
5
Relationship between
theory/ concepts and
research
Testing/confirmation Emergent/development
6 Nature of data Hard and reliable Rich and deep
Source: Bryman 1988, cited in Naoum (2007, p. 43) and own processing
-
7/30/2019 Strategic Level Management and Project Success Increase
38/62
31
3.4.2 Method Selection
The nature of this research, the role of the literature and theory review, as well as the
aim of the study are showing that the appropriate research method to be followed is
the quantitative research method. In this case the theoretical framework leads to
specific findings and to an explicit theory. Project strategy is not been planned and
implemented in an effective way, it has not the role it is supposed to have and that
situation is leading to low performance in projects. Through a well performed
strategic level project management, the project success can be increased. Those
theoretical perspectives need to be tested, in order to be confirmed. The point of the
research is to exclude findings that will have a broad validity (facts) and for that
reason it has to be objective. Moreover, in this study, the researcher will have a
distant relationship with the subject during data collection. For all the reasons
mentioned above, quantitative research is the most suitable method to be followed.
3.4.3 Research style and considerations
As mentioned above, the purpose of the data gathering is to test the theory that is
formed during the review of the literature. A consideration about the appropriate
method for data collection is needed. This has to be selected according to the selected
research approach (quantitative). Under this condition, a case study would not be
fitting and therefore has to be rejected. The reason for that is first of all the nature of
the research which has not been structured in an inductive way. It does not focus at a
specific case or situation in order to generate wider conclusions. Furthermore there is
no single case, which can broadly represent an entire sector in this specific subject.
Consequently the selection is going to be made between two different research tools,
namely the interview and the questionnaire. A briefdevelopment of each techniques
characteristics and a comparison between them will be presented in the figures
bellow.
-
7/30/2019 Strategic Level Management and Project Success Increase
39/62
32
Figure 6: advantages and disadvantages of interview technique
Advantages Disadvantages
Information is available in a direct way Extra planning is required, increasing research time
Answers can be more specific Generally small sample
Interviewees may be questioned in more depth Sample may not be representativeAdditional information can easily be acquired Answers may have prejudice
Initial topic may be expanded Data may be subjective
Interviewees may be more dedicated to the
research
Information may not be revealed due to a sensitive
topic area
Source: own processing
Figure 7: advantages and disadvantages of questionnaire technique
Advantages Disadvantages
Speed Generally low rate of participation
Broad sample Little depth of data
Great amounts of information for little effort Respondents assign low priority to questionnaires
Known and specific structure May not be answered by the appropriate person
Results can produce statistical data Additional information requires a lot of time
Generally more objective methodQuestions need to be well structured to generate
useful data
Source: own processing
It is clear that both techniques have their advantages and disadvantages. There is no
question about which method is better. Each one is respectively appropriate
according to the type and nature of the followed research. However, a quick view in
their features can reveal that in general, interview technique is more suitable for a
qualitative research approach, while questionnaire technique fits more to a
quantitative method of research. For that reason the technique that will be adopted inthis case is the research through questionnaires. Details about the architecture of the
questionnaires will be presented in the following chapter.
-
7/30/2019 Strategic Level Management and Project Success Increase
40/62
33
3.5 Sample selection
The sample of the research will be selected according to the type of research. This
means that there are several subjects that have to be taken under consideration. Those
are related to the broad research questions (see Conclusion part in Literature
review chapter) but also to the structure of the research (research structure in
Literature review chapter). According to FrankfortNachmias et al. (2000:167), a
sample is considered representative if the analyses made using the sampling units
produce results similar to those that would be obtained had the entire population
been analyzed. In this case there are findings and conclusions that are considered to
have a general validity. There is a need those findings to be related in a particular
area, namely a specific construction sector and a specified location.
The selected research location is Greece. As a member of the European Union it has
an environment that is typical of the so called West world. The recent economic
recession does not; at this point and type of research; affect the core of the studied
subject, but reduces however the size of the sample. Before the recession there was a
well developed construction sector and thus a satisfying amount of data. At this
point, due to the crisis and the measures taken by the Government, the construction
sector (along with many others) has been broadly affected in a very negative way. As
a result, the companies left are enough to provide the necessary data, but the data
gathering process is much more difficult.
There is a question about the construction sector (public, private, or PPP / PFI) that
will be selected for the research, since all of them contain large projects. The research
will focus on private sector projects because of one main reason. Some of the main
research factors are project completion time, total project cost, effectiveness, etc. In
public or PPP / PFI projects, where the state is involved there has been noticed during
the decades that exist problems related to legal issues, responsibility matters, property
issues, bureaucracy, etc that can significantly affect the project time, the total cost, the
predictability, the scope and cause alterations, cancellations and changes in general.
For all those reasons the research would not be accurate and the sample would not be
representative.
Moreover, private contractors in Greece undertake mainly two types of projects,which are housing and shopping / business centers or industrial / logistics projects.
-
7/30/2019 Strategic Level Management and Project Success Increase
41/62
34
Since housing projects are considered to be (mainly due to their size) smaller and
much simpler, the role of project management in those projects is narrow. Therefore it
would not be possible to study the role of project strategy in its full extent. For all
those reasons mentioned above the study will focus on companies affiliated to those
project types.
3.6 Questionnaire Design
The questionnaire survey seeks Greece contractors view on the implementation of the
concept of project strategy in construction industry. The design of the questionnaire
was shaped based the background information gathered from the literature review of
journals and papers, on the theory formed during the literature survey and on the five
(5) main research questions (see Research Questions chapter in Literature Review
part).
A two page questionnaire, escorted by a covering letter was sent to managing
directors and managers of sample construction companies. The covering letter
explained the purpose of the research and its relevance to construction firms. It
explained also that the questionnaire is meant to be completed only by the senior
members of the staff on a managerial position. The questionnaire tried to deal with thefears of privacy of information by assuring the respondents that its confidentiality
would be kept and that the information provided shall not be used for any purpose
other than the dissertation. It also offered the organisations the possibility to receive
the research results if they wish. This offer is thought as an extra motivation for the
firms to participate in the research.
The construction of the questionnaire was of such that is devoid of any ambiguou