strategic planning for nablus power system

49
Strategic planning for Nablus power system Prepared by: Aya Kamal Alawneh Amal Nazzeh Allan Presented to: Dr. MAHER KHAMMASH

Upload: ilar

Post on 13-Feb-2016

25 views

Category:

Documents


0 download

DESCRIPTION

Strategic planning for Nablus power system. Prepared by: Aya Kamal Alawneh Amal Nazzeh Allan Presented to : Dr. MAHER KHAMMASH. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Strategic planning for Nablus power system

Strategic planning for Nablus power

system

Prepared by: Aya Kamal Alawneh Amal Nazzeh Allan

Presented to: Dr. MAHER KHAMMASH

Page 2: Strategic planning for Nablus power system

• Our project is to make a load flow study and analysis for MojeerAldeen& Aljam3a and Kamal jomblat (Nablus) Electrical Network using ETAP software

- to improve the power factor- to reduce the electrical losses in the network- to increase the capability of the transformers and

the transmission lines

Page 3: Strategic planning for Nablus power system

Outlines

Page 4: Strategic planning for Nablus power system

Nablus electrical network

Page 5: Strategic planning for Nablus power system

Electrical Network Improvements

1.1 Simulation For Mojeer Al deen Network fed from Quseen

1.1.1 FOR MAXIMUM CASE

Max. load case results with improvement

MW Mvar MVA % PF

Swing

Bus(es):

7.597 2.616

8.03 94.55Lag

Apparent

Losses:

0.098 0.631

∆P% 1.29

Max. load case results without improvement

MW Mvar MVA % PF

Swing

Bus(es):7.8 2.8 8.2 88.8 lag

Apparent

Losses:0.122 0.71

∆P% 1.56

Page 6: Strategic planning for Nablus power system

Electrical Network Improvements

V% Mojeer Al deen Network from Quseen(max)

1.05 Vnominal <V<1.1 Vnominal

Page 7: Strategic planning for Nablus power system

Electrical Network Improvements

PF for Mojeer al deen from QuseenMax case

Page 8: Strategic planning for Nablus power system

Electrical Network Improvements

• 1.1.2 FOR MINIMUM CASE• we reduce the loads to 40% from the original case

Min. load case results without improvement

MW Mvar MVA % PF

Swing

Bus(es):2.902 1.476 3.255 89.14 lag

Apparent

Losses:0.017 0.058

∆P% 0.586

Min. load case results with improvement

MW Mvar MVA % PF

Swing

Bus(es):2.8 1.015 3.131 94.59 lag

Apparent

Losses:0.015 0.054

∆P% .541

Page 9: Strategic planning for Nablus power system

Electrical Network Improvements

• 1.1.3 The economical study

• ∆∆P=∆Pbefore,cap - ∆Pafter,cap∆∆P:saving in real power losses∆Pbefore,cap : real power losses before adding capacitor ∆Pafter,cap : real power losses after adding capacitor

Z∆p=∆∆p*T*100Z∆p : annual saving in real power cost

• T max =the time of max loss = 3800 h 100:cost per MWh($/MWh)

Kc=C*QcKc :cost of capacitorC: cost of capacitor per KVAr($/KVAr)Qc: capacitor KVAr

Page 10: Strategic planning for Nablus power system

Electrical Network Improvements

• Fixed Cap=4000($/MVAr). Regulated Cap= 10000 ($/MVAr)

Zc =0.22*KcZc :annual capacitor running cost0 .22: maintenance & life time of capacitor (depreciation factor)

∆Z=Z∆p-Zc∆Z: annual saving

S.P.B.P=investment(capacitors initial cost)/ total annual savingS.P.B.P < 2year →→→project is visible S.P.B.P > 2year →→→project is not visible

Page 11: Strategic planning for Nablus power system

Electrical Network Improvements

• ∆∆P=saving in real power losses ==∆Pbefore-∆Pafter=0.024

Z∆p= annual saving in real power cost ==∆∆p*T*100== T=the time of max loss $/MWH=100• Kc=cost of capacitor= cost of capacitor per KVAr * capacitor KVAr

Kc=0 .55*4000 + 0.59*10000 =8100$Zc= annual capacitor running cost ==0.22*Kc=1782 $/ year

• ∆Z= annual saving =Z∆p-Zc=9120 - 1782==7338 Which is > 0 good design • S.P.B.P =Kc/∆Z =8100/7338=1.1 year which is feasible

Economical for Mojeer al deen from QuseenMax case

Page 12: Strategic planning for Nablus power system

Electrical Network Improvements

1.2 Simulation For Mojeer Al deen Network Fed from Sara

1.2.1 FOR MAXIMUM CASE

Max. load case results with improvement

MW Mvar MVA % PF

Swing

Bus(es):

8.200

2.3988.544 95.98Lag

Apparent

Losses:

0.110 0.398

∆P% 1.34

Max. load case results without improvement

MW Mvar MVA % PF

Swing

Bus(es):8.3 2.49 8.211

95.94

Lag

Apparent

Losses:0.18 0.4

∆P% 2.1

Page 13: Strategic planning for Nablus power system

Electrical Network Improvements

V% Mojeer Al deen Network from Sara(max)

Page 14: Strategic planning for Nablus power system

Electrical Network Improvements

PF for Mojeer al deen from SaraMax case

Page 15: Strategic planning for Nablus power system

Electrical Network Improvements

• 1.2.2 FOR MINIMUM CASE

M. load case results without improvement

MW Mvar MVA % PF

Swing

Bus(es):

3.227 0.857 3.33896.66 lag

Apparent

Losses:0.018 .061

∆P% 0.558

Min. load case results with improvement

MW Mvar MVA % PF

Swing

Bus(es):3.163 0.839 3.272 96.67Lag

Apparent

Losses:0.016 0.059

∆P% .506

Page 16: Strategic planning for Nablus power system

Electrical Network Improvements

1.3 Simulation For Aljam3a and Kamal jomblat Network fed from Quseen

1.3.1 FOR MAXIMUM CASE

Max. load case results with improvement

MW Mvar MVA % PF

Swing

Bus(es):5.38 2.38 6.397 92.82La

g

Apparen

t Losses:

0.290 0.478

∆P% 5.4

Max. load case results without improvement

MW Mvar MVA % PF

Swing

Bus(es):

5.747 3.082 6.521 88.12Lag

Apparent

Losses:0.333 0.528

∆P% 5.8

Page 17: Strategic planning for Nablus power system

Electrical Network Improvements

V% V% Aljam3a and Kamal jomblat Network in Quseen (max)

1.05 Vnominal <V<1.1 Vnominal

Page 18: Strategic planning for Nablus power system

Electrical Network Improvements

P.F Aljam3a and Kamal jomblat NetworkFrom quseen

Page 19: Strategic planning for Nablus power system

Electrical Network Improvements

• ∆∆P=saving in real power losses ==∆Pbefore-∆Pafter=0.043

Z∆p= annual saving in real power cost T=the time of max loss $/MWH=100 ==∆∆p*T*100=

• Kc=cost of capacitor= cost of capacitor per KVAr * capacitor KVAr Kc= 0 .135*4000 + 0.55*10000= =6040$ Zc= annual capacitor running cost ==0.22*Kc= 1329 $/ year

• ∆Z= annual saving =16340 - 1329==15011 Which is > 0 good design • S.P.B.P =Kc/∆Z = = 4.8 months which is feasible

Economical for Aljam3a and Kamal jomblat from QuseenMax case

Page 20: Strategic planning for Nablus power system

Electrical Network Improvements

• 1.3.2 FOR MINIMUM CASE

Min. load case results without improvement

MW Mvar MVA % PF

Swing

Bus(es):2.902 1.476 3.255 89.14 lag

Apparent

Losses:0.089 .098

∆P% 3%

Min. load case results with improvement

MW Mvar MVA % PF

Swing

Bus(es):2.593 0.955 2.763

93.83Lag

Apparent

Losses:0.057 0.091

∆P% .2.1%

Page 21: Strategic planning for Nablus power system

Chapter(1) :Electrical Network Improvements

1.4 Simulation For Aljam3a and Kamal jomblat Network FED from Sara case

1.4.1 FOR MAXIMUM CASE

Max. load case results with improvement

MW Mvar MVA % PF

Swing

Bus(es):6.063 1.042 6.447

98.69

Lag

Apparent

Losses:0.296 0.488

∆P% 4.6

Max. load case results without improvement

MW Mvar MVA % PF

Swing

Bus(es):

6.2451.776 6.493

96.19

Lag

Apparen

t Losses:0.330 0.524

∆P% 5.2

Page 22: Strategic planning for Nablus power system

Electrical Network Improvements

V% V% Aljam3a and Kamal jomblat Network in Sara (max)

Page 23: Strategic planning for Nablus power system

Electrical Network Improvements

P.F Aljam3a and Kamal jomblat NetworkFrom Sara

Page 24: Strategic planning for Nablus power system

Electrical Network Improvements

• 1.4.2 FOR MINIMUM CASE

MIN. load case results without improvement

MW Mvar MVA % PF

Swing

Bus(es):

2.90.87 3

96.19

Lag

Apparent

Losses:0.055 0.087

∆P% 1.89

Min. load case results with improvement

MW Mvar MVA % PF

Swing

Bus(es):2.504 0.595 2.574 97.29

Lag

Apparen

t Losses:0.047 0.075

∆P% 1.87

Page 25: Strategic planning for Nablus power system

For mojeer al deen

Quseennetwork

Saranetwork

Max. load case results with improvement

MW Mvar MVA % PF

Swing

Bus(es):

7.597

2.6168.03 94.55Lag

Apparent

Losses:

0.110 0.398

∆P%

1.34

Max. load case results with improvement

MW Mvar MVA % PF

Swing

Bus(es):

8.200

2.3988.544 95.98Lag

Apparent

Losses:

0.098 0.231

∆P%

1.29

Page 26: Strategic planning for Nablus power system

For Aljam3a and Kamal jomblatQuseennetwork

Sara network

Max. load case results with improvement

MW Mvar MVA % PF

Swing

Bus(es):5.38 2.38 6.397 92.82La

g

Apparen

t Losses:0.296 0.488

∆P%

5.4

Max. load case results with improvement

MW Mvar MVA % PF

Swing

Bus(es):6.063 1.042 6.447

98.69

Lag

Apparent

Losses:

0.290 0.478

∆P%

4.6

Page 27: Strategic planning for Nablus power system

Comparison between the Quseen

and Sara networks

Quseen network

Sara network

-Its fed from Quseen connection point

-It has low P.F& higher Losses

- Its fed from Sara connection

- Its has a high p.f due to transfer loads from Quseen to Sara connection point

- So the p.f increase and lower losses than the Quseen network

Page 28: Strategic planning for Nablus power system

Optimization of the electrical network

2.1 Replacing transformers

The table below shows the values

of apparent power

and the load factor before and after the replacing:

Summary

Apparent Losses for mojeer al deen

Page 29: Strategic planning for Nablus power system

2.2 : Operation mode of medium voltage distribution feeders:

Medium voltages (MV) are radialy..

We construct ring network to insure back-up connections to improve the reliability of the system. .

In MOJEER ALDEEN network we should construct rings for all four main feeders (on 6.6kv) after the switch gear ,between every two adjacent feeders

The main transmission line is ACSR ( cross sectional area120) Carries an electric current up to 395A.

Optimization electrical network

Page 30: Strategic planning for Nablus power system

• But at worst condition they carry currents as the following

Optimization electrical network

Page 31: Strategic planning for Nablus power system

Optimization electrical network

• Ring between ALENJELE and ALITHAD feeder:

• Ring between ALM3AJEN and ALDARDOK feeder:

Page 32: Strategic planning for Nablus power system

Ring between ALMAHKAMA and ALENJELE feeder

Summary

Page 33: Strategic planning for Nablus power system

Optimization electrical network

Suggestion for Location of substation

2.3 Design substation

Page 34: Strategic planning for Nablus power system

Optimization electrical network

The main purpose of substation mainly feds hospitals and north region (Aseera Al Shmalia) and it is near the loads and it decreases losses so the current reach the customer in good quality also to improve ring system

Page 35: Strategic planning for Nablus power system

• This figure shows the configuration of substation

Optimization electrical network

Page 36: Strategic planning for Nablus power system

• Electrical Network Supply• Nablus are fed from 4 connection point by Israel Electrical Company (IEC),

At 33KV as following:

Future planning for connection point

Nablus

1.Asker

(odeleh & Almeslekh)

30MVA 2.Sa

ra 40MV

A

3 .Innab 7MVA

4 .Howwara 20

MVA

Sara

Carraco

n

Transformer(33-11KV) 10MVA

Transformer(33-11KV) 10MVA

Al jam3a

Mojeer Al

deen

Transformer(33-11KV) 10MVA

Transformer(33-11KV)

10MVA

Transformer(33-11KV)

5MVA

Page 37: Strategic planning for Nablus power system

Element of sara connection point

• Transmission Line • There are two type of conductor:1.ACSR 150mm22.XLPE cables 240mm2 • The resistance and reactance of XLPE and ACSR in table below

(A) Transmission Line DataMV Cable XLPEResistance (Ω/Km) 0.0975 Reactance (Ω/Km) 0.11486Length (Km) 3.7 Length (Km) 3.7Resistance (Ω) 0.36075 Reactance (Ω) 0.424982

MV overhead line ACSRResistance (Ω/Km) 0.223 Reactance (Ω/Km) 0.257Length (Km) 4.7 Length (Km) 4.7Resistance (Ω) 1.0481 Reactance (Ω) 1.2079

Page 38: Strategic planning for Nablus power system

Future planning for connection point

4.1 Strategic planning for the network

.Power (W)consumption in last ten year

Page 39: Strategic planning for Nablus power system

Future planning for connection point

Load Flow Results

• we can summarize the forecasted results, total generation, demand , loading., percentage of losses, and the total power factor for the maximum case in future ten years in Nablus network as in tables below:

Page 40: Strategic planning for Nablus power system

Future planning for connection point

Page 41: Strategic planning for Nablus power system

Future planning for connection point

4.2 Recommended and solution

Page 42: Strategic planning for Nablus power system

Future planning for connection point

Page 43: Strategic planning for Nablus power system

Protection Analysis

Why protection system is needed• Personnel saifty against electrical hazards .• Avoid equipment stress(thermal,electrical,mechanical damages) .• make network stability .• Clear electrical faults and maintain service continuity

• Short cct calculation :

In our project we use Etap program to calculate the maximum currents for three regions East , MEDIUM and WEST loads .and we get the required short cct current from NEDCO

Page 44: Strategic planning for Nablus power system

Protection Analysis

• Selection of circuit breaker :

• I C.B ≥ K safty*Imax load K safty=1.3• V C.B ≥ Vsystem• I breaking capacity ≥ 1.2 Is.c

• Selection of instrument transformer :• Potential transformer : Vs= 110v but V p≥ V source

• Current transformer : Is=5 A but I p≥ 1.1Imaxload

Page 45: Strategic planning for Nablus power system

Protection Analysis and Design

• To make differential protection for the power transformer as the following figure:

Page 46: Strategic planning for Nablus power system

Protection Analysis and Design

• The relay which we used is (inverse time relay )• The aim of the protection in our project is how to achive selectivity

between cct breakers

• The following eqn is to calculate the setting (T)time of each relay

T=t0/K• T: setting time • t0 :operating time • K: factor depend on the type of the relay curves

Page 47: Strategic planning for Nablus power system

Protection Analysis and Design

t0 :operating time

Page 48: Strategic planning for Nablus power system

Thank

• We thanks Dr.maher khammash

• We thanks NEDECO for cooperation with us especially for :

Eng. Shadia QamheyeEng.Allam Abd AlfattahEng.Samah Alnamer

Page 49: Strategic planning for Nablus power system