Strategic Sourcing Guidelines for Capital Improvement Projects The University of Kansas Office of Design and Construction Management July 20, 2016 Background The University of Kansas (KU) Changing for Excellence (CFE) initiative included an analysis of KU’s business practices and recommendations from the Huron Consulting Group on ways to potentially improve efficiency in a number of business operations, including construction. Huron’s “Phase II Business Case Executive Summary: Construction All Campuses” (dated November 4, 2011), available online at http://cfe.ku.edu/documents/phase2-Construction.pdf provides additional background on projected cost savings and improved business practice recommendations. A key component of this initiative is to implement a strategic sourcing program which will leverage KU’s purchasing power across projects, departments and campuses, and will take advantage of aggressively negotiated discount pricing for the procurement of goods and services for KU construction projects. The Office of Design and Construction Management (DCM) has been tasked with implementing this element of the KU strategic sourcing initiative. The strategic sourcing initiative seeks to achieve maximum cost effectiveness and other long-term benefits to KU in the procurement of materials and equipment for construction projects. Preferred or Required Manufacturers and Vendors The University of Kansas has identified manufacturers and vendors for specific goods and services that are to be used as standard components in KU construction projects. This will result in a number of benefits to KU, including: More efficient and cost-effective operation, maintenance, repairs and replacement. Improved operation and reliability of campus-wide networks and control systems. Enhanced public safety and emergency responses. Consistent and enhanced campus aesthetics. Support of KU standards based on performance, initial cost and life cycle cost, and other factors. The University has negotiated contracts with preferred manufacturers and vendors, or has identified other State of Kansas, cooperative or institutional contracts which provide discount pricing and other benefits to the University, as identified in the attached table. Preferred Manufacturers: KU prefers that materials from the indicated manufacturers be specified as the basis of design and utilized on all KU construction projects. Project designers and contractors are to incorporate them to the greatest extent possible in each capital improvement project.

Upload: others

Post on 29-Jul-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Strategic Sourcing Guidelines for Capital Improvement Projects · 7/20/2016  · taylor@encompaskc.com 816-300-1122 Stacy Roth StacyR@scottrice.com 913-227-7727 Derek Majors Derek.Majors@Staples.com

Strategic Sourcing Guidelines for

Capital Improvement Projects

The University of Kansas

Office of Design and Construction Management

July 20, 2016

Background

The University of Kansas (KU) Changing for Excellence (CFE) initiative included an analysis of KU’s

business practices and recommendations from the Huron Consulting Group on ways to potentially

improve efficiency in a number of business operations, including construction. Huron’s “Phase II

Business Case Executive Summary: Construction – All Campuses” (dated November 4, 2011),

available online at http://cfe.ku.edu/documents/phase2-Construction.pdf provides additional

background on projected cost savings and improved business practice recommendations.

A key component of this initiative is to implement a strategic sourcing program which will leverage

KU’s purchasing power across projects, departments and campuses, and will take advantage of

aggressively negotiated discount pricing for the procurement of goods and services for KU

construction projects. The Office of Design and Construction Management (DCM) has been tasked

with implementing this element of the KU strategic sourcing initiative.

The strategic sourcing initiative seeks to achieve maximum cost effectiveness and other long-term

benefits to KU in the procurement of materials and equipment for construction projects.

Preferred or Required Manufacturers and Vendors

The University of Kansas has identified manufacturers and vendors for specific goods and services

that are to be used as standard components in KU construction projects. This will result in a number

of benefits to KU, including:

More efficient and cost-effective operation, maintenance, repairs and replacement.

Improved operation and reliability of campus-wide networks and control systems.

Enhanced public safety and emergency responses.

Consistent and enhanced campus aesthetics.

Support of KU standards based on performance, initial cost and life cycle cost, and other

factors.

The University has negotiated contracts with preferred manufacturers and vendors, or has identified

other State of Kansas, cooperative or institutional contracts which provide discount pricing and other

benefits to the University, as identified in the attached table.

Preferred Manufacturers: KU prefers that materials from the indicated manufacturers be specified as

the basis of design and utilized on all KU construction projects. Project designers and contractors are

to incorporate them to the greatest extent possible in each capital improvement project.

Page 2: Strategic Sourcing Guidelines for Capital Improvement Projects · 7/20/2016  · taylor@encompaskc.com 816-300-1122 Stacy Roth StacyR@scottrice.com 913-227-7727 Derek Majors Derek.Majors@Staples.com

Strategic Sourcing Guidelines for KU Capital Improvement Projects July 20, 2016

Page 2 of 13

Required Manufacturers: Materials identified with an “RM” abbreviation in the “Required Mfr.” column

shall be specified and bid as no-substitution components from the indicated manufacturers only,

unless otherwise approved in writing by KU, strictly on a per-project basis.

Required Vendors: Materials and services that are available from a KU, state or institutional contract

shall be bid and procured solely from that source. The exception to this is if an alternate bid is taken

for procuring an item from a different source and it is determined during a review and comparison of

those competitively-bid alternates to KU’s contract prices included in the base bid, that it is in KU’s

best interests to accept that alternate bid.

Vendors identified with an “RV” abbreviation in the “Required Vendor” column are the only source that

the indicated materials can be purchased from for all KU projects.

Project Designer and Contractor Guidelines

Preconstruction / Design Phase:

The Architect/Engineer (A/E) serving as the project designer and, on CM At-Risk projects, the

Construction Manager (CM) shall review KU’s list of preferred manufacturers and vendors and shall

develop the design to include those components to the greatest extent possible and beneficial to KU.

If the A/E feels that materials from other manufacturers offer greater value to the University for the

Project, the A/E shall submit a written recommendation to utilize components from other

manufacturers or vendors, and shall review them with KU as early as possible during the design

phase, for written response and direction from the University.

Bidding Phase:

The A/E shall develop construction documents which clearly indicate items which are required/no-

substitution materials and services, and if applicable, required vendors for those materials and

services. The A/E shall assist KU and, on CM At-Risk projects, the CM in developing bidding

documents and bid forms which include provisions for bidders to submit alternate bids for materials

and services from vendors not on KU’s preferred vendors list.

The bid documents shall reference the KU, state, cooperative or institutional contract numbers, which

bidders shall provide to vendors, along with the specific KU project name and project number, when

requesting pricing utilizing the terms of those contracts; example project: School of Business – New

Building, KU #234-8585. Vendors shall provide pricing which is more competitive than KU’s standard

contract terms, if available at the time of bidding due to prevailing market conditions, vendor incentive

programs or other factors.

The A/E and, on CM At-Risk projects, the CM shall review and evaluate the competitively-bid

alternate pricing with KU’s vendor contract pricing included in the base bid and shall recommend an

award of bid based on whichever appears to be in KU’s best interests. This evaluation shall include

consideration of lowest initial cost, as well as life cycle costs, operating costs, ease of maintenance,

contractual incentives, delivery time and other relevant issues.

DCM shall track cost savings from strategic sourcing and other cost reductions/costs avoided for each

project.

Page 3: Strategic Sourcing Guidelines for Capital Improvement Projects · 7/20/2016  · taylor@encompaskc.com 816-300-1122 Stacy Roth StacyR@scottrice.com 913-227-7727 Derek Majors Derek.Majors@Staples.com

Strategic Sourcing Guidelines for KU Capital Improvement Projects July 20, 2016

Page 3 of 13

KU Preferred or Required Manufacturers and Vendors List

(Organized by CSI specification section numbers; required manufacturers & vendors are indicated by an “RM or RV” abbreviation)

Materials /Services Description

Acceptable Manufacturers

Req’d Mfr. Vendor

Under Contract Req’d

Vendor Contract Type /

Contract Number Vendor Contact Person (Name, Email, Phone)

Notes

Div. 2 – Existing Conditions

Abatement Services Associated Insulation

RV 15010429 Ron Tacha

800-748-2428 [email protected]

15

Div. 4 - Masonry

Masonry restoration products

Prosoco -- NA -- NA

Restoration mortars Hahn RM NA -- NA

Installation/Maintenance See above See above

Mid-Continental Restoration Restoration

Waterproofing Contractors

Western Waterproofing

KU #15010313

Paul Underwood [email protected]

620-223-3700 David Falley

[email protected] 785-478-9538

Eric Birch [email protected]

816-241-0424

Div. 7 – Thermal and Moisture Protection

Roofing -- --

Centimark or

Diamond Everley Or

Kaw Roofing & Sheet Metal

RV KU # 14010121

Don Fazio [email protected]

913-693-4130

Mark Gwaltney [email protected]

785-843-3433

John Daly [email protected]

913-371-6100

8

Div. 8 - Openings

Door closers LCN -- NA -- NA

Page 4: Strategic Sourcing Guidelines for Capital Improvement Projects · 7/20/2016  · taylor@encompaskc.com 816-300-1122 Stacy Roth StacyR@scottrice.com 913-227-7727 Derek Majors Derek.Majors@Staples.com

Strategic Sourcing Guidelines for KU Capital Improvement Projects July 20, 2016

Page 4 of 13

Materials /Services Description

Acceptable Manufacturers

Req’d Mfr. Vendor

Under Contract Req’d

Vendor Contract Type /

Contract Number Vendor Contact Person (Name, Email, Phone)

Notes

Geared hinges Select NA -- NA

Doors/Frames/Hardware Various

D.H. Pace dba Overhead Door

Co of KC Dorma USA dba

Montgomery Door Controls

RV KU #14010200

Steve Whitfield [email protected]

816-918-6100 Michael Honeyman

[email protected] 785-234-4242

Keys and cylinders Medeco (KU)

RM

Intermountain Lock &

Supply/CBS Manhattan

RV KU # 14010105

Brent Bown [email protected] 1-800-453-5386

Mike Waggoner [email protected] 913-845-3345

Keys and cylinders BEST (Housing) RM

Intermountain Lock &

Supply/CBS Manhattan

RV KU #– 14010105

Brent Bown [email protected] 1-800-453-5386

Mike Waggoner [email protected] 913-845-3345

Mortise locksets Corbin, Sargent,

or Schlage -- NA -- NA

Panic hardware Von Duprin, or Sargent

RM NA -- NA

Div. 9 - Finishes

Carpet/VCT/wall base/moldings and

installation Various National Flooring RV KU #36951130

Kamela Compton [email protected]

316-263-0038 5

Carpet Various

Interface Americas, Inc

Mohawk Carpet Distribution, Inc. Shaw Industries,

Inc.

RV KU #14010189

Katie Sweetin [email protected]

816-673-5771 Roy Glazer

[email protected] 913-486-4863

Michelle Masters [email protected]

785-806-3894

13

Page 5: Strategic Sourcing Guidelines for Capital Improvement Projects · 7/20/2016  · taylor@encompaskc.com 816-300-1122 Stacy Roth StacyR@scottrice.com 913-227-7727 Derek Majors Derek.Majors@Staples.com

Strategic Sourcing Guidelines for KU Capital Improvement Projects July 20, 2016

Page 5 of 13

Materials /Services Description

Acceptable Manufacturers

Req’d Mfr. Vendor

Under Contract Req’d

Vendor Contract Type /

Contract Number Vendor Contact Person (Name, Email, Phone)

Notes

Fluid Applied Flooring Various --

Epoxy Coating Specialists

Desco Coatings, Inc

15010391

Brent Moroney 913-362-4141

[email protected] Blake Wood

913-782-3330 [email protected]

Painting Various -- Brotherton

Painting LLC, Blue Bear Inc.

-- KU #15010280

Daryl Brotherton [email protected]

785-979-3450 Lotus Millin

[email protected] 913-441-1717

Resilient Flooring Armstrong

ISC Surfaces Tandus Centiva

-RM- NA KU #14010243

Sarah Anning [email protected]

1-816-604-8532 Kristan Kettering

[email protected] Jenny Wolff

[email protected] 1-913-558-8531

14

Div. 10 - Specialties

Toilet partitions (resin) Santana -- NA -- NA

White/Chalk boards Claridge,

or Magnatag -- Claridge -- KU #13030012

Kristi Popin 972-247-8075

[email protected] E&I

Div. 11 - Equipment

Fume hoods Labconco RM Fisher Scientific RV KU #23316997 Rich Grabbe

913-314-4425 1

Parking access control gates

T2 RM T2 RV KU #130100687 1-800-434-1502

Div. 12 - Furnishings

Countertops and sinks (epoxy resin)

Durcon RM Fisher

Scientific RV KU #23316997

Rich Grabbe 913-314-4425

1

Page 6: Strategic Sourcing Guidelines for Capital Improvement Projects · 7/20/2016  · taylor@encompaskc.com 816-300-1122 Stacy Roth StacyR@scottrice.com 913-227-7727 Derek Majors Derek.Majors@Staples.com

Strategic Sourcing Guidelines for KU Capital Improvement Projects July 20, 2016

Page 6 of 13

Materials /Services Description

Acceptable Manufacturers

Req’d Mfr. Vendor

Under Contract Req’d

Vendor Contract Type /

Contract Number Vendor Contact Person (Name, Email, Phone)

Notes

Furnishings TBD -- TBD -- TBD

Furniture (classroom and educational)

Various -- Kruger

International RV KU #14050001

Craig Karges [email protected]

913-239-9439 6

Furniture (Lounge, Library, Dining

Various --

BA Designs, LLC Contract

Furnishings, Inc. Scott Rice Office

Works Spaces, Inc

Business Interiors by Staples

RV KU #14010194

Lee Kimsey [email protected]

785-267-8100 Charles Johnson

[email protected] 816-931-0900

Stacy Roth [email protected] 913-227-7727Lene Yeo [email protected]

913-894-8900 Derek Majors

[email protected] 816-504-2514

12

Furniture (Office Systems, Task/Guest

Chairs, Case goods, Filing & Storage)

Various --

BA Designs, LLC Contract

Furnishings, Inc. Designed Business

Interiors, Inc Encompas

Scott Rice Office Works

Business Interiors by Staples

RV KU #14010182

Lee Kimsey [email protected]

785-267-8100 Charles Johnson

[email protected] 816-931-0900

Mark Fraser [email protected]

785-233-2078

Taylor Stucky [email protected]

816-300-1122 Stacy Roth

[email protected] 913-227-7727 Derek Majors

[email protected] 816-504-2514

11

Laboratory shelving materials

Trespa RM Fisher

Scientific RV KU #23316997

Rich Grabbe 913-314-4425

1

Page 7: Strategic Sourcing Guidelines for Capital Improvement Projects · 7/20/2016  · taylor@encompaskc.com 816-300-1122 Stacy Roth StacyR@scottrice.com 913-227-7727 Derek Majors Derek.Majors@Staples.com

Strategic Sourcing Guidelines for KU Capital Improvement Projects July 20, 2016

Page 7 of 13

Materials /Services Description

Acceptable Manufacturers

Req’d Mfr. Vendor

Under Contract Req’d

Vendor Contract Type /

Contract Number Vendor Contact Person (Name, Email, Phone)

Notes

Partition systems (full height demountable)

DIRTT RM SPACES RV KU # 14010161 Vicki Allenbrand

[email protected] 913-894-8900

4

Div. 14 – Conveying Equipment

Elevators

Otis, Schindler, Thyssen-Krupp,

Dynatron/Minnesota Elevator

--

Vendors must provide non-proprietary systems &

components

-- NA --

Div. 21 -Fire Suppression

Fire alarm systems SimplexGrinnell RM SimplexGrinnell RV KU #13010066 Cliff Price

[email protected] 785-217-1200

3

Fire hydrants Waterous Pacer,

or Mueller RM NA -- NA --

Fire sprinklers SimplexGrinnell -- SimplexGrinnell -- KU #13010066 Cliff Price

[email protected] 785-217-1200

--

Div. 22 - Plumbing

Backflow preventers Watts RM Reeves-

Wiedeman RV Kansas #36105

Ted Wiedeman [email protected]

816-423-4820 --

Drinking fountains, bottle fill stations

Elkay -- -- -- -- -- --

Faucets, lab service valves

Chicago Faucets -- VWR -- E&I #01163 1

Page 8: Strategic Sourcing Guidelines for Capital Improvement Projects · 7/20/2016  · taylor@encompaskc.com 816-300-1122 Stacy Roth StacyR@scottrice.com 913-227-7727 Derek Majors Derek.Majors@Staples.com

Strategic Sourcing Guidelines for KU Capital Improvement Projects July 20, 2016

Page 8 of 13

Materials /Services Description

Acceptable Manufacturers

Req’d Mfr. Vendor

Under Contract Req’d

Vendor Contract Type /

Contract Number Vendor Contact Person (Name, Email, Phone)

Notes

Mechanical, Electrical, Plumbing

-- --

Central Mechanical

Construction

Or

McElroy’s, Inc

Or

P1Group

RV KU #14010155

Mike Pearson [email protected]

785-537-2437

Wade Jueneman [email protected]

785-266-4870

Chris Champagne [email protected]

785-843-2910

10

Pumps Bell & Gossett -- Blackmore &

Glunt -- TBD

Jeff Slaven 913-469-5715

Sinks, urinals, water closets

Kohler -- Grainger -- KU #28655755 Zack Barron

[email protected] 816-489-3023

1

Water heaters Aerco -- Blackmore &

Glunt -- TBD

Jeff Slaven 913-469-5715

--

Div. 23 – Heating, Ventilation & Air Cond.

Air handling units Trane/York RM Trane/JCI RV Trane - TCPN

#5045 York – #87057

Trane-Greg Schnakenberg [email protected]

913-599-4664 JCI-Tim Swope

[email protected] 785-267-0801

--

Air separators Spirotherm Summers &

Assocs. --

Kansas (ESU) #36100

--

Building Automation Controls

Johnson Controls, or Automated Logic

RM

Johnson Controls, or Control Services

Company

RV KU #87057(JCI),

or KU #29064170 (AL)

JCI-Tim Swope [email protected]

785-267-0801 Control Serv – Matt Adamson

[email protected] 816-600-5807

3

Page 9: Strategic Sourcing Guidelines for Capital Improvement Projects · 7/20/2016  · taylor@encompaskc.com 816-300-1122 Stacy Roth StacyR@scottrice.com 913-227-7727 Derek Majors Derek.Majors@Staples.com

Strategic Sourcing Guidelines for KU Capital Improvement Projects July 20, 2016

Page 9 of 13

Materials /Services Description

Acceptable Manufacturers

Req’d Mfr. Vendor

Under Contract Req’d

Vendor Contract Type /

Contract Number Vendor Contact Person (Name, Email, Phone)

Notes

Chillers Trane/York RM Trane/JCI RV Trane - TCPN

#5045 York – #87057

Trane-Greg Schnakenberg [email protected]

913-599-4664 JCI-Tim Swope

[email protected] 785-267-0801

--

Cooling towers Marley

/McQuay

RM Midwest

Machinery/SPX Technologies

RV 14010268 Jerry Robison

[email protected] 913-438-1919

--

Fume hood variable air volume control systems

Phoenix Controls RM Associated Air

Products RV KU #13010034

Dan Bukovaz [email protected]

913-207-5684 --

Mechanical, Electrical, Plumbing

-- --

Central Mechanical

Construction

Or

McElroy’s, Inc

Or

P1Group

RV KU #14010155

Mike Pearson [email protected]

785-537-2437

Wade Jueneman [email protected]

785-266-4870

Chris Champagne [email protected]

785-843-2910

10

Terminal boxes, diffusers, grilles

Titus -- Triangle Sales -- NA --

Water chemical treatment

Nalco RM Nalco RV KU #14010113 Michael Mixon

[email protected] 816-214-1783

--

Div. 26 - Electrical

Ballasts Advance Transformer -- Stanion

Wholesale Electric

-- KU #28655755 Janice McNabb, 785-841-8420,

[email protected] 2

Page 10: Strategic Sourcing Guidelines for Capital Improvement Projects · 7/20/2016  · taylor@encompaskc.com 816-300-1122 Stacy Roth StacyR@scottrice.com 913-227-7727 Derek Majors Derek.Majors@Staples.com

Strategic Sourcing Guidelines for KU Capital Improvement Projects July 20, 2016

Page 10 of 13

Materials /Services Description

Acceptable Manufacturers

Req’d Mfr. Vendor

Under Contract Req’d

Vendor Contract Type /

Contract Number Vendor Contact Person (Name, Email, Phone)

Notes

BTU meters Onicon RM Johnson Controls -- TBD JCI-Tim Swope

[email protected] 785-267-0801

--

Emergency generators Generac -- Stanion -- KU #28655755 Janice McNabb, 785-841-8420,

[email protected] 2

Exit signs, emergency light fixtures

Dual Light -- Stanion -- KU #28655755 Janice McNabb, 785-841-8420,

[email protected] 2

Exterior light poles Valmont-Lexington RM Stanion RV KU #28655755 Janice McNabb, 785-841-8420,

[email protected] 2

Exterior lighting fixtures (metal halide)

KIM Lighting RM Stanion RV KU #28655755 Janice McNabb, 785-841-8420,

[email protected] 2

Exterior lighting fixtures (LED)

McGraw-Edison/ Cooper Lighting

RM Stanion RV KU #13010009 Janice McNabb, 785-841-8420,

[email protected] 2

Interior light bulbs Phillips Lighting -- Stanion -- KU #28655755 Janice McNabb, 785-841-8420,

[email protected] 2

Interior light fixtures H.E. Williams -- Stanion -- KU #28655755 Janice McNabb, 785-841-8420,

[email protected] 2

Mechanical, Electrical Plumbing

-- --

Central Mechanical

Construction

Or

McElroy’s, Inc

Or

P1Group

RV KU #14010155

Mike Pearson [email protected]

785-537-2437

Wade Jueneman [email protected]

785-266-4870

Chris Champagne [email protected]

785-843-2910

10

Medium voltage switchgear

S&C Electric Co. RM Stanion -- KU #28655755 Janice McNabb, 785-841-8420,

[email protected] 2

Occupancy sensors Wattstopper,

or Hubbell -- Stanion -- KU #28655755

Janice McNabb, 785-841-8420, [email protected]

2

Page 11: Strategic Sourcing Guidelines for Capital Improvement Projects · 7/20/2016  · taylor@encompaskc.com 816-300-1122 Stacy Roth StacyR@scottrice.com 913-227-7727 Derek Majors Derek.Majors@Staples.com

Strategic Sourcing Guidelines for KU Capital Improvement Projects July 20, 2016

Page 11 of 13

Materials /Services Description

Acceptable Manufacturers

Req’d Mfr. Vendor

Under Contract Req’d

Vendor Contract Type /

Contract Number Vendor Contact Person (Name, Email, Phone)

Notes

Panel boards, PowerLogic meters

Square D RM Stanion -- KU #28655755 Janice McNabb, 785-841-8420,

[email protected] 2

Switchboards Square D RM Stanion -- KU #28655755 Janice McNabb, 785-841-8420,

[email protected] 2

Photocells Tork -- Stanion -- KU #28655755 Janice McNabb, 785-841-8420,

[email protected] 2

Timers Intermatic -- NA -- NA

Track lighting Juno -- Stanion -- KU #28655755 Janice McNabb, 785-841-8420,

[email protected] 2

Wiring devices Leviton,

or Hubbell -- Stanion -- KU #28655755

Janice McNabb, 785-841-8420, [email protected]

2

Div. 28 – Electronic Safety & Security

Access control & card swipe systems

CBORD RM Capital

Electric/KU Construction

RV KU #23662373

Ron Kneib [email protected]

816-329-8340 Tim Browder

[email protected] 785-864-4981

--

Closed-circuit TV cameras

Pelco RM Capital Electric RV KU #23662373 Ron Kneib

[email protected] 816-329-8340

--

Div. 32 – Exterior Improvements

Accessible detectable warning pavers

Endicott Clay Products

RM NA -- NA --

Page 12: Strategic Sourcing Guidelines for Capital Improvement Projects · 7/20/2016  · taylor@encompaskc.com 816-300-1122 Stacy Roth StacyR@scottrice.com 913-227-7727 Derek Majors Derek.Majors@Staples.com

Strategic Sourcing Guidelines for KU Capital Improvement Projects July 20, 2016

Page 12 of 13

Materials /Services Description

Acceptable Manufacturers

Req’d Mfr. Vendor

Under Contract Req’d

Vendor Contract Type /

Contract Number Vendor Contact Person (Name, Email, Phone)

Notes

Landscaping Services -- --

Hermes

Landscaping

Or

Lawrence

Landscape

Or

Turf Design

RV KU # 13010046

Eric Soriano [email protected]

913-888-2400

Leonard Bremenkamp [email protected]

785-843-4370

Lindsey Richardson [email protected]

913-764-6531

9

Outdoor Benches Dumor RM Dumor RV TBD --

Outdoor Tables Landscape Forms RM Landscape Forms RV 15010332 Carrie Miles

[email protected]

800-430-6206 x1206

Paving, utilities -- --

King’s

Construction

or

Kissick

Construction

or

RD Johnson

Excavating

RV KU #13010075

Dale Ping

[email protected]

785-863-2534

Jim Kissick

[email protected]

816-363-5530

Roger Johnson

[email protected]

785-842-9100

7

Trash/recycle

receptacles,

ash urns

Petersen

Manufacturing

RM

Petersen

Manufacturing

RV KU #14010132 Rick Carstensen

[email protected]

--

Page 13: Strategic Sourcing Guidelines for Capital Improvement Projects · 7/20/2016  · taylor@encompaskc.com 816-300-1122 Stacy Roth StacyR@scottrice.com 913-227-7727 Derek Majors Derek.Majors@Staples.com

Strategic Sourcing Guidelines for KU Capital Improvement Projects July 20, 2016

Page 13 of 13

Notes:

1) 3% rebate to KU on total annual sales.

2) 0.5% rebate to KU on total annual sales made directly to KU.

3) KU/state contract which includes installation by the vendor or by the vendor’s pre-approved, pre-qualified subcontractors.

4) Other landscape partition systems can be used if more appropriate for a particular project, but preference shall be given to using DIRTT systems if

suitable for a project and if specified, DIRTT shall be a sole-source manufacturer and vendor. 1% quick pay discount (15 days); 2% rebate on total

annual material sales of $250,001-$750,000; 3% if $750,001-$1,500,000; 5% if $1,500,001 and over.

5) National Flooring: 1% rebate on total annual material sales if $200,000 and over.

6) Kruger International: 1% rebate on total annual material sales if $100,000-$199,999; 2% if $200,000-$299,999; 3% if $300,000 and over.

7) King’s Construction: 2% quick pay discount (15 days); 1% rebate on total annual sales if $750,001-$1,500,000; 2% if $1,500,001 and over. Kissick

Construction: 2% quick pay discount (20 days); $20,000 scholarship contribution for every $2,000,000 awarded. RD Johnson excavating: 1% quick

pay discount (10 days); 1% rebate on total sales if $500,001-$1,000,000; 1.5% if $1,000,001-$2,000,000; 2% if $2,000,001 and over.

8) Centimark: 2% back on all purchase. Diamond Everley: 1% quick pay discount (20 days); ½ % rebate on sales $500,001-$1,000,000; 1% if

1,000,001 and over.

9) Lawrence Landscape: 1% rebate on annual volume $50,001-100,000; 2% on $100,001-150,000; 3% on $150,001-200,000; 4% on $200,001-

250,000; 5% on volume $250,001 and above. Turf Design: additional discount by project amount, 2% on projects up to $50,000; 3% on $50,001-

200,000; 4% on $200,001-500,000; 5% on $500,001-1,000,000; 6% on $1,000,001 – 2,500,000; 7% on projects $2,500,001 and above.

10) Central Mechanical: 2% quick pay discount (20 days); ½ % rebate on sales $500,000-999,999; 1% on $1,000,000-1,499,999; 1.5% on $1,500,000-

1,999,999; 2% on $2,000,000-2,999,999.

11) Rebates vary based on vendor and product line purchased.

12) Rebates vary based on vendor and product line purchased.

13) Interface Americas: 3% rebate on product quarterly; Mohawk Industries: 2% rebate on product quarterly; Shaw Inc: 3% rebate after $100K in

product.

14) Armstrong must be purchased through local distributor. Pricing is guaranteed by manufacturer, but is subject to markup and delivery by

installer/contractor.

15) Abatement Services must be coordinated through KU Environmental Health and Safety (EHS), and will be contracted and managed through EHS.