strategicplanning long term.ppt
TRANSCRIPT
-
7/22/2019 StrategicPlanning LONG TERM.ppt
1/19
Strategic Planning Solutions
Mine SiteLocal AreaEnterprise Wide
confidential customer briefing
-
7/22/2019 StrategicPlanning LONG TERM.ppt
2/19
1 NPV Scheduler(metals)
NPV Scheduler v3.1 Lerchs Grossman pit optimization
NPV optimal extraction sequencing
Multi grade, multi ore type, multi process Pushback generator
Multi target scheduler
NPV optimal stockpiling
Cutoff grade optimization (MFO option)
Export schedule surfaces and models to Datamine
Used in: iron ore, gold, platinum, copper, nickel, base metals,diamonds
Used by: Rio Tinto, BHP, CVRD, Phelps Dodge, Ashanti, DeBeers, Barrick, Anglo American, Codelco, Vulcon,
-
7/22/2019 StrategicPlanning LONG TERM.ppt
3/19
Economic Model
InputBlock modelDetailed mining andprocessing costsExtraction factorsCut off factors
OutputEconomic model- revenue per block
Resource model
Economic model
-
7/22/2019 StrategicPlanning LONG TERM.ppt
4/19
SequenceInputEconomic ModelMining ratesFinancial constraintsSlope Defn.Pit Outline
OutputLerchs Grossman(undiscounted) shellAnoptimised pit(discounted)Reports-block sequence
Resource model
Economic model
Sequence
-
7/22/2019 StrategicPlanning LONG TERM.ppt
5/19
Pushback
Input Sequence model Ultimate PitA mining rate Pushback Defn
OutputReports per pushbackExport into DM for pit design
Resource model
Economic model
Sequence
Pushback
-
7/22/2019 StrategicPlanning LONG TERM.ppt
6/19
Schedule
InputPushback ModelPit RateDetailed Targets
OutputCompleted Optimised Practical ScheduleReports per period
Resource model
Economic model
Sequence
Pushback
Schedule
-
7/22/2019 StrategicPlanning LONG TERM.ppt
7/19
Stockpiles
InputPit Schedule(Rates)Define StockpilesPlant CapacitiesGrade ConstraintsPrice/Cost variations
OutputPlant Input ScheduleCalculate NPV s/p
Resource model
Economic model
Sequence
Pushback
Schedule
Stockplies
-
7/22/2019 StrategicPlanning LONG TERM.ppt
8/19
Tonnage
NPV
NPV Scheduling
Head Grade
-
7/22/2019 StrategicPlanning LONG TERM.ppt
9/19
2 Haulage Simulation(Truck Optimisation)
Truck requirements over the life of
the mine based on
Truck capacities
Haulage routes
Optimised Pit Schedule
-
7/22/2019 StrategicPlanning LONG TERM.ppt
10/19Haulage Opimiser
Annual Haul Hours
0
50000
100000
150000
200000
250000
300000
350000
400000
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29
Period
HaulHours
Annual Haul HoursAnnual Haul Hours
0
50000
100000
150000
200000
250000
300000
350000
400000
1 2 3 4 5 6 7 8 9 10 11 12 1 3 14 1 5 16 17 18 19 20 21 22 23 2 4 25 26 27 28 29
Period
HaulHours
Annual Haul HoursAnnual Haul Hours
0
50000
100000
150000
200000
250000
300000
350000
400000
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29
Period
HaulHours
Annual Haul Hours
-
7/22/2019 StrategicPlanning LONG TERM.ppt
11/19
3 RM Scheduler v3.1(raw materials)
RM Scheduler v3.1 Resource maximizationor Lerchs Grossman
Blended or NPV optimal extraction sequencing
Locate optimal blended pit at any point in time
Multi quality, multi rock type, multi process
Multi target scheduler
Haulage simulation and truck hours scheduling
Blend with stockpiles and external additives
Export optimal blended pits and models to Datamine
Used in: limestone, aggregates, phosphates, coal, gypsum, borax,kaolin, sand,
Used by: Cemex, Soeicom, ISCOR, National Power, ,
-
7/22/2019 StrategicPlanning LONG TERM.ppt
12/19
Cement plant sources raw materials from local limestone quarry, andsupplements kiln feed with sand and clay purchased from independentsupplier.
What is the best mix of quarried and imported materials which, whilemeeting the silica and lime modulus targets, also minimizes the cost ofproduction and maximizes the operational life of the quarries and kiln?
What is the optimal extraction sequence in the limestone quarry (theoptimal blended pit)?
Cement Solution
RM Scheduler
Lime Saturation Factor(LSF)
___________%CaO 0.7 %SO3__________
2.8 %SiO2+ 1.2 %Al2O3+ 0.65 %Fe2O3
-
7/22/2019 StrategicPlanning LONG TERM.ppt
13/19
Linking together open pit planning systems to create strategicplanning tools
Corporate Planning Solutions
-
7/22/2019 StrategicPlanning LONG TERM.ppt
14/19
1. MultiMine
Single blended product from multiple pits.
2. Mining Enterprise PlanMultiple blended products and commodities from
multiple pits.
Corporate Planning Tools
-
7/22/2019 StrategicPlanning LONG TERM.ppt
15/19
1. MultiMine
Multiple, geographically independent ore reserve models
Separate economic modeling of individual minesincorporating additional haulage costs
Attach NPVS and RMS project resources
Generate combined schedule for all mines Export local area plan (LAP) back to NPVS at individual
mines
Report combined and individual production data
Single Product
-
7/22/2019 StrategicPlanning LONG TERM.ppt
16/19
Multiple Operations-One Product
-
7/22/2019 StrategicPlanning LONG TERM.ppt
17/19
MultipleProducts
2. Enterprise Mine Planning
Include all functions of MultiMine
Multiple products and commodities from multiple pits.
Market Driven
Includes capital expenditure
-
7/22/2019 StrategicPlanning LONG TERM.ppt
18/19
Market Driven Plans
Mine plans derived from central marketing plans
Best utilization of available resources to meet corporatesales and financial objectives
Decision support system for strategic planners Rapid assessment of alternative market scenarios
-
7/22/2019 StrategicPlanning LONG TERM.ppt
19/19
Financial CAPEX Investments
Truck Fleet AdditionalTrucks
Shovels
Fleet
Additional
Shovel
Plant Plant
Extension
Pit 1 No 27 +1 4 +1 1 +1
Capacity 120000 5000 14000 20000 1400000 40000
CAPEX $.5M $2M $5m
Pit 2 No 12 +1 4 +1 1 +1Capacity 70000 5000 14000 20000 40000 40000
CAPEX $.5M $2M $3m
Enterprise-wide approach to NPV maximization
Optimum allocation and timing of capital expenditure atmines based on corporate, not local, benefit
Optimum utilization of global ore resources