    Strategic Planning Solutions

    Mine SiteLocal AreaEnterprise Wide

    confidential customer briefing

  • 7/22/2019 StrategicPlanning LONG TERM.ppt

    2/19

    1 NPV Scheduler(metals)

    NPV Scheduler v3.1 Lerchs Grossman pit optimization

    NPV optimal extraction sequencing

    Multi grade, multi ore type, multi process Pushback generator

    Multi target scheduler

    NPV optimal stockpiling

    Cutoff grade optimization (MFO option)

    Export schedule surfaces and models to Datamine

    Used in: iron ore, gold, platinum, copper, nickel, base metals,diamonds

    Used by: Rio Tinto, BHP, CVRD, Phelps Dodge, Ashanti, DeBeers, Barrick, Anglo American, Codelco, Vulcon,

  • 7/22/2019 StrategicPlanning LONG TERM.ppt

    3/19

    Economic Model

    InputBlock modelDetailed mining andprocessing costsExtraction factorsCut off factors

    OutputEconomic model- revenue per block

    Resource model

    Economic model

  • 7/22/2019 StrategicPlanning LONG TERM.ppt

    4/19

    SequenceInputEconomic ModelMining ratesFinancial constraintsSlope Defn.Pit Outline

    OutputLerchs Grossman(undiscounted) shellAnoptimised pit(discounted)Reports-block sequence

    Resource model

    Economic model

    Sequence

  • 7/22/2019 StrategicPlanning LONG TERM.ppt

    5/19

    Pushback

    Input Sequence model Ultimate PitA mining rate Pushback Defn

    OutputReports per pushbackExport into DM for pit design

    Resource model

    Economic model

    Sequence

    Pushback

  • 7/22/2019 StrategicPlanning LONG TERM.ppt

    6/19

    Schedule

    InputPushback ModelPit RateDetailed Targets

    OutputCompleted Optimised Practical ScheduleReports per period

    Resource model

    Economic model

    Sequence

    Pushback

    Schedule

  • 7/22/2019 StrategicPlanning LONG TERM.ppt

    7/19

    Stockpiles

    InputPit Schedule(Rates)Define StockpilesPlant CapacitiesGrade ConstraintsPrice/Cost variations

    OutputPlant Input ScheduleCalculate NPV s/p

    Resource model

    Economic model

    Sequence

    Pushback

    Schedule

    Stockplies

  • 7/22/2019 StrategicPlanning LONG TERM.ppt

    8/19

    Tonnage

    NPV

    NPV Scheduling

    Head Grade

  • 7/22/2019 StrategicPlanning LONG TERM.ppt

    9/19

    2 Haulage Simulation(Truck Optimisation)

    Truck requirements over the life of

    the mine based on

    Truck capacities

    Haulage routes

    Optimised Pit Schedule

  • 7/22/2019 StrategicPlanning LONG TERM.ppt

    10/19Haulage Opimiser

    Annual Haul Hours

    0

    50000

    100000

    150000

    200000

    250000

    300000

    350000

    400000

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29

    Period

    HaulHours

    Annual Haul HoursAnnual Haul Hours

    0

    50000

    100000

    150000

    200000

    250000

    300000

    350000

    400000

    1 2 3 4 5 6 7 8 9 10 11 12 1 3 14 1 5 16 17 18 19 20 21 22 23 2 4 25 26 27 28 29

    Period

    HaulHours

    Annual Haul HoursAnnual Haul Hours

    0

    50000

    100000

    150000

    200000

    250000

    300000

    350000

    400000

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29

    Period

    HaulHours

    Annual Haul Hours

  • 7/22/2019 StrategicPlanning LONG TERM.ppt

    11/19

    3 RM Scheduler v3.1(raw materials)

    RM Scheduler v3.1 Resource maximizationor Lerchs Grossman

    Blended or NPV optimal extraction sequencing

    Locate optimal blended pit at any point in time

    Multi quality, multi rock type, multi process

    Multi target scheduler

    Haulage simulation and truck hours scheduling

    Blend with stockpiles and external additives

    Export optimal blended pits and models to Datamine

    Used in: limestone, aggregates, phosphates, coal, gypsum, borax,kaolin, sand,

    Used by: Cemex, Soeicom, ISCOR, National Power, ,

  • 7/22/2019 StrategicPlanning LONG TERM.ppt

    12/19

    Cement plant sources raw materials from local limestone quarry, andsupplements kiln feed with sand and clay purchased from independentsupplier.

    What is the best mix of quarried and imported materials which, whilemeeting the silica and lime modulus targets, also minimizes the cost ofproduction and maximizes the operational life of the quarries and kiln?

    What is the optimal extraction sequence in the limestone quarry (theoptimal blended pit)?

    Cement Solution

    RM Scheduler

    Lime Saturation Factor(LSF)

    ___________%CaO 0.7 %SO3__________

    2.8 %SiO2+ 1.2 %Al2O3+ 0.65 %Fe2O3

  • 7/22/2019 StrategicPlanning LONG TERM.ppt

    13/19

    Linking together open pit planning systems to create strategicplanning tools

    Corporate Planning Solutions

  • 7/22/2019 StrategicPlanning LONG TERM.ppt

    14/19

    1. MultiMine

    Single blended product from multiple pits.

    2. Mining Enterprise PlanMultiple blended products and commodities from

    multiple pits.

    Corporate Planning Tools

  • 7/22/2019 StrategicPlanning LONG TERM.ppt

    15/19

    1. MultiMine

    Multiple, geographically independent ore reserve models

    Separate economic modeling of individual minesincorporating additional haulage costs

    Attach NPVS and RMS project resources

    Generate combined schedule for all mines Export local area plan (LAP) back to NPVS at individual

    mines

    Report combined and individual production data

    Single Product

  • 7/22/2019 StrategicPlanning LONG TERM.ppt

    16/19

    Multiple Operations-One Product

  • 7/22/2019 StrategicPlanning LONG TERM.ppt

    17/19

    MultipleProducts

    2. Enterprise Mine Planning

    Include all functions of MultiMine

    Multiple products and commodities from multiple pits.

    Market Driven

    Includes capital expenditure

  • 7/22/2019 StrategicPlanning LONG TERM.ppt

    18/19

    Market Driven Plans

    Mine plans derived from central marketing plans

    Best utilization of available resources to meet corporatesales and financial objectives

    Decision support system for strategic planners Rapid assessment of alternative market scenarios

  • 7/22/2019 StrategicPlanning LONG TERM.ppt

    19/19

    Financial CAPEX Investments

    Truck Fleet AdditionalTrucks

    Shovels

    Fleet

    Additional

    Shovel

    Plant Plant

    Extension

    Pit 1 No 27 +1 4 +1 1 +1

    Capacity 120000 5000 14000 20000 1400000 40000

    CAPEX $.5M $2M $5m

    Pit 2 No 12 +1 4 +1 1 +1Capacity 70000 5000 14000 20000 40000 40000

    CAPEX $.5M $2M $3m

    Enterprise-wide approach to NPV maximization

    Optimum allocation and timing of capital expenditure atmines based on corporate, not local, benefit

    Optimum utilization of global ore resources