straw manufacturing current status t.enik, s.shkarovskiy, i.polenkevich,yu.potrebenikov 07.02.2011
TRANSCRIPT
Straw manufacturing current Straw manufacturing current statusstatus
T.Enik, S.Shkarovskiy, I.Polenkevich,Yu.PotrebenikovT.Enik, S.Shkarovskiy, I.Polenkevich,Yu.Potrebenikov07.02.201107.02.2011
““Raw” strawRaw” straw139 straws (2700 mm) are ready.
46 ring samples from the beginning of straws (5 mm width) and 22 ones from the end of straws were broken off on base material
~ 70 straws from one tape roll
20 - 30 “raw” straws per day
Example ofa bar code
07/02/11 Yu.Potrebenikov 2
““Raw” straw qualityRaw” straw quality
A piece of the straw #3 remain alive at 7 Atm overpressure more then 10 days(end plug is formed by thermo glue)
Blue – start of the straw; Red – end of the straw
A piece of the straw #14 (~40 cm) remainAlive at 9 Atm overpressure more than 1 min; 1,5 mm elongation after break
07/02/11 Yu.Potrebenikov 3
We proposemin=3 mm
““Raw” straw qualityRaw” straw quality
Blue – start of the straw; Red – end of the straw07/02/11 Yu.Potrebenikov 4
Min=4 kg
Min=3 mm
Last configuration of the welding Last configuration of the welding machinemachine
Thermo stabilization zone near welding point
New visualization: 2 microscope
Visual control
Frequency control
Automatic (computer)
control
07/02/11 Yu.Potrebenikov 5
Thermo stabilization of the welding Thermo stabilization of the welding areaarea
General cooling
Local sonotrode cooling(air blowing by thin injector)
Small air overpressure into straw
(diameter stabilization) 07/02/11 Yu.Potrebenikov 6
Straw quality before and after Straw quality before and after modification of the welding machine modification of the welding machine
Straw #83: only 5 rings from 26 broken along the seam
07/02/11 Yu.Potrebenikov 7
Straw diameter distributionStraw diameter distribution
Blue – star of the straw; Red – end of the strawMore than 95% straws have the same diameter
9.77 mm (20 microns precision)
07/02/11 Yu.Potrebenikov 8
Straw leakage Straw leakage
Straw and PVC tube with 4 Atm He overpressure in cooled boiled water
07/02/11 Yu.Potrebenikov 9
Straw plugging and connection for long Straw plugging and connection for long term overpressure testterm overpressure test
07/02/11 Yu.Potrebenikov 10
Conclusion and plansConclusion and plans
1. After modification of the welding machine straw quality seams good
2. Long term overpressure test and leakage test are under preparation
3. It is necessary to produce more than 500 straw till the end of February to deliver their to CERN at the beginning of March
4. It is necessary to define minimal straw quality test before sending straws to CERN and minimal straw quality test at CERN before their installation into Module-0
07/02/11 Yu.Potrebenikov 11