stripping pipes in azerbaijan - hydronindustrial.comhydronindustrial.com/pipelines/indan case study...

5
www.rpr.indan.es www.indan.es STRIPPING PIPES IN AZERBAIJAN Introduction Project target: CPC (Caspian Pipe Coating) managed by Bredero Shaw has the necessity to remove the coating on more than 700 pipes which have been stocked during the last Project. The company can not stop its production because of tight schedule. As a result, Bredero seeks alternative methods to solve the problem. Finally the meeting among Indan, RPR and Bredero was carried out in early summer. People Involved RPR: Dag Rune Wiksten (Technical Sales Manager). Indan: Patxi Anza (Manager) Sergio Lebrero (Project Manager) Bredero Shaw: Peter Steel (Maintenance Manager) Farzad Zaeem (Engineering and Mobilisation Manager) Jamila Jabbarli (Procurement and Contracts Manager) Scope of the Project Place: Azerbaijan (BP Project) Date: 1 September 2015 Duration: 3,5 month Features: Bredero Shaw Company got removed the coating on 776 pipes with 12,3 meters of length and 0,8 metres of diameter. Steel thickness between 21 and 24 mm. Removed area 25475 m 2 , Coating of the pipes (70% = PE + Adhesive + FBE / 20% = FBE + adhesive / 10% = PE + adhesive). Thickness PE= 6-8 mm.

Upload: others

Post on 04-Jul-2020

5 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: STRIPPING PIPES IN AZERBAIJAN - hydronindustrial.comhydronindustrial.com/pipelines/Indan Case Study Azerbaijan.pdf · Azerbaijan (BP Project) Date: 1 September 2015 . Duration: 3,5

www.rpr.indan.es www.indan.es

STRIPPING PIPES IN AZERBAIJAN

Introduction

Project target: CPC (Caspian Pipe Coating) managed by Bredero Shaw has the necessity

to remove the coating on more than 700 pipes which have been stocked during the last

Project. The company can not stop its production because of tight schedule. As a result,

Bredero seeks alternative methods to solve the problem.

Finally the meeting among Indan, RPR and Bredero was carried out in early summer.

People Involved

RPR: Dag Rune Wiksten (Technical Sales Manager).

Indan: Patxi Anza (Manager)

Sergio Lebrero (Project Manager)

Bredero Shaw: Peter Steel (Maintenance Manager)

Farzad Zaeem (Engineering and Mobilisation Manager)

Jamila Jabbarli (Procurement and Contracts Manager)

Scope of the Project

Place: Azerbaijan (BP Project)

Date: 1 September 2015

Duration: 3,5 month

Features: Bredero Shaw Company got removed the coating on 776 pipes with 12,3

meters of length and 0,8 metres of diameter. Steel thickness between 21 and 24 mm.

Removed area 25475 m2, Coating of the pipes (70% = PE + Adhesive + FBE / 20% = FBE

+ adhesive / 10% = PE + adhesive).

Thickness PE= 6-8 mm.

Page 2: STRIPPING PIPES IN AZERBAIJAN - hydronindustrial.comhydronindustrial.com/pipelines/Indan Case Study Azerbaijan.pdf · Azerbaijan (BP Project) Date: 1 September 2015 . Duration: 3,5

www.rpr.indan.es www.indan.es

Implementation

Equipment: Induction Generator of 400 V, Induction Head 10 cm x 10 cm, Transformer

3:1 XL and Chiller.

Special request: 4 electricity filters placed between generator and power plant to avoid the problems with the high frequencies.

Auxiliaries: Bogey to semi-automate stripping process.

Page 3: STRIPPING PIPES IN AZERBAIJAN - hydronindustrial.comhydronindustrial.com/pipelines/Indan Case Study Azerbaijan.pdf · Azerbaijan (BP Project) Date: 1 September 2015 . Duration: 3,5

www.rpr.indan.es www.indan.es

Experience

Description: Stripping rejected pipes executed during the production and daily pipes

generated in the starting up of the plant, which are used every day like a test at start up. Duration of the removing process for a pipe with 3 Layer: PE + Adh. + FBE = 2 hours.

Stripping Speeds

Stripping in one time (3 Layer)

Rotation: 5 - 7 Hz

Travel: 2 - 2.4 Hz

Stripping in two times (1º PE and Adhesive /2º FBE)

Rotation: 8.5 - 10 Hz

Travel: 2.5 – 3 Hz

Page 4: STRIPPING PIPES IN AZERBAIJAN - hydronindustrial.comhydronindustrial.com/pipelines/Indan Case Study Azerbaijan.pdf · Azerbaijan (BP Project) Date: 1 September 2015 . Duration: 3,5

www.rpr.indan.es www.indan.es

Page 5: STRIPPING PIPES IN AZERBAIJAN - hydronindustrial.comhydronindustrial.com/pipelines/Indan Case Study Azerbaijan.pdf · Azerbaijan (BP Project) Date: 1 September 2015 . Duration: 3,5

www.rpr.indan.es www.indan.es

Relevant problems

1. Chiller: Without enough power to work continuously

2. Generator: Trip Fault

3. Supply: Power unit

4. Performance: Environmental Conditions

5. Bogey: guidance system

6. Cables damaged because of stress and friction

Solutions

1. Chiller AX5 was changed by new model: AX10

2. 4 filters were installed to remove earth faults

3. The equipment was plugged in to power plant

4. Stripping method was modified to increase the performance

5. New guidance system where the forces are distributed 6. The cable was cut and spliced.

Conclusions

Process carried out to remove the accumulation of stock occurred during a project of

more than 2 years of duration, completed successfully and replacing a system of waterjet of 1000 bar of pressure.

www.rpr.indan.es