study of open access and cost benefit analysis of open ... · study of open access and cost benefit...

88
i Summer Internship Report on Study of Open Access and Cost Benefit Analysis of Open Access over Grid Power Under the guidance of Dr. Rohit Verma, Deputy Director, CAMPS, NPTI & Mr.Dipanshu Gupta, Senior Manager, Global Energy Pvt.Ltd. At Submitted by: Himanshu Arora Roll No : 35 MBA Power Management (Under Ministry of Power , Govt. of India) Affiliated to August 2013

Upload: dangnhi

Post on 06-May-2018

232 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

i

Summer Internship Report on

Study of Open Access and Cost Benefit Analysis of Open

Access over Grid Power

Under the guidance of

Dr. Rohit Verma, Deputy Director, CAMPS, NPTI

&

Mr.Dipanshu Gupta, Senior Manager, Global Energy Pvt.Ltd.

At

Submitted by:

Himanshu Arora

Roll No : 35

MBA – Power Management

(Under Ministry of Power , Govt. of India)

Affiliated to

August 2013

Page 2: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

ii

Certificate

Page 3: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

iii

Declaration

I, Himanshu Arora, Roll no:, student of MBA – Power Management (2012-14) at National Power

Training Institute, Faridabad hereby declare that the Summer Training Report entitled ―Study of

Open Access and Cost Benefit Analysis of Open Access over Grid Power‖ is an original work and

the same has not been submitted to any other institute for the award of any other degree.

A Seminar presentation of the Training Report was made on __________________________

And the suggestions as approved by the faculty were duly incorporated.

Presentation in-charge Signature of Candidate

Countersigned

Director / Principal of the Institute

Page 4: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

iv

Acknowledgement

Apart from the efforts of the person doing the project, the success of any project largely depends on

the encouragements and guidelines of many others. I take this opportunity to express my gratitude to

the people who have been instrumental in the successful completion of this project.

I would like to thank Mr. Amit Kumar, Sr.Vice President, and Global Energy Pvt.Ltd for giving me

this opportunity to execute my Summer Internship project. I would like to extend my thanks to my

guide, Mr.Dipanshu Gupta, Sr.Manager, Global Energy for showing me the right path and approach

towards the project. I would also like to thank Mr.Niraj Kumar, VP, Global Energy and Mr.

Himanshu Chandrakar, VP, Global Energy for their support during my project.

I feel deep sense of gratitude towards Mr. J.S.S.Rao, Principal Director , Corporate Planning , NPTI ,

Mr.S.K. Chaudhary , Principal Director , CAMPS , Mrs.Manju Mam , Director , NPTI and Mrs.Indu

Maheshwari , Dy. Director , NPTI for arranging my internship at Global Energy Private Limited,

New Delhi and being a constant source of motivation and guidance throughout the course of my

internship.

A special thanks to my Project-in-charge, Dr. Rohit Verma, Dy.Director, NPTI for his support and

guidance throughout the summer internship.

I also record my sincere thanks to Mr. Rahul Sharma (Jay Pee Group) and Mr. Rohit Bhutani (TCS)

for their support during my project and showing me right path and approach towards the project.

I also extend my thanks to all my faculties and my batch mates in CAMPS, NPTI for their support

and guidance.

Himanshu Arora

(MBA – Power Management)

Page 5: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

v

Table of Contents Certificate ............................................................................................................................................. ii

Declaration ........................................................................................................................................... iii

Acknowledgement ............................................................................................................................... iv

Executive Summary .......................................................................................................................... viii

Abbreviations ....................................................................................................................................... x

List of Table ........................................................................................................................................ xii

List of Figures .................................................................................................................................... xiii

Chapter 1: Introduction ...................................................................................................................... 1

1.2 Problem Statement ...................................................................................................................................... 3

1.3 Scope of the project .................................................................................................................................... 3

1.4 Objective of the project .............................................................................................................................. 3

1.5 Significance of the project .......................................................................................................................... 4

1.6 Organizational Profile: ............................................................................................................................... 5

1.6.1 About the Organization ....................................................................................................................... 5

1.6.2 Services ................................................................................................................................................ 5

Chapter 2: Literature Review and Research Methodology ............................................................. 7

2.1 Literature Review ....................................................................................................................................... 7

2.2 Research Methodology ............................................................................................................................. 10

Chapter 3: Open Access ....................................................................................................................... 10

3.1 Introduction to Open Access .................................................................................................................... 11

3.2 Legal Framework ...................................................................................................................................... 12

3.3 Distribution Open Access ......................................................................................................................... 15

3.3.1Eligibility to seek Open Access: ......................................................................................................... 15

3.4 Category of Open Access consumers as per CERC regulations 2011 ...................................................... 16

3.5. Transmission Open Access ...................................................................................................................... 16

3.5.1.Eligibility to seek OA ........................................................................................................................ 16

3.5.2Grant of connectivity .......................................................................................................................... 17

3.5.3Grant of connectivity to STU ............................................................................................................. 17

3.6 PROCEDURE FOR ALLOTMENT OF OPEN ACCESS ....................................................................... 18

3.6.1 Long Term Open Access ................................................................................................................... 18

3.6.2 Short Term Open Access ................................................................................................................... 19

3.6.3 Allotment Priority .............................................................................................................................. 19

3.7 ROLE OF DIFFERENT AGENCIES IN OPEN ACCESS ...................................................................... 20

3.7.1 NLDC (National Load Dispatch Centre) ........................................................................................... 20

Page 6: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

vi

3.7.2 RLDC (Regional Load Dispatch Centre) .......................................................................................... 20

3.7.3 SLDC (State Load Dispatch Centre) ................................................................................................. 20

3.7.4 CTU (Central Transmission Utility) .................................................................................................. 21

3.7.5 STU (State Transmission Utility) ...................................................................................................... 21

3.8 Understanding Open Access charges ....................................................................................................... 22

1.Wheeling Charges or Distribution Charges ................................................................................................. 22

2.Wheeling Loss or Distribution Loss ............................................................................................................ 22

3.Transmission Charges or STU Charges ....................................................................................................... 22

4.Transmission Loss or STU Loss .................................................................................................................. 23

5 PoC Charge & PoC Losses .......................................................................................................................... 23

6. Cross Subsidy Surcharge ............................................................................................................................ 23

7. Application Fees ......................................................................................................................................... 24

8. SLDC Charge ............................................................................................................................................. 24

9. RLDC Charge ............................................................................................................................................. 24

3.9 Unscheduled Interchange Charges (UI Charges) ..................................................................................... 25

Chapter 4: COST BENEFIT ANALYSIS for Intra State OA ............................................................. 26

4.1 Assumptions ............................................................................................................................................. 26

4.2 Selection of States for Intra State OA ...................................................................................................... 27

4.3 Punjab ....................................................................................................................................................... 27

4.3.1 Charges applicable ............................................................................................................................. 28

4.4 Gujarat ...................................................................................................................................................... 29

4.4.1 Charges Applicable............................................................................................................................ 30

4.5 Uttar Pradesh ............................................................................................................................................ 32

4.5.1 PuVVNL - Purvanchal Vidyut Vitran Nigam Limited ...................................................................... 33

4.5.2 MVVNL - Madhyanchal Vidyut Vitran Nigam Limited ................................................................... 33

4.5.3 PVVNL - Paschimanchal Vidyut Vitran Nigam Limited .................................................................. 34

4.5.4 DVVNL - Dakshinanchal Vidyut Vitran Nigam Limited ................................................................. 34

4.5.5 KESCoL - Kanpur Electricity Supply Company Limited ................................................................. 35

4.5.6 NPCL - Noida Power Company Limited........................................................................................... 35

4.6 Maharashtra .............................................................................................................................................. 36

4.6.1 MSEDCL ........................................................................................................................................... 36

4.6.2 R-Infra D ........................................................................................................................................... 37

4.6.3 Tata Power: TPC-D ........................................................................................................................... 37

4.7 Andhra Pradesh ........................................................................................................................................ 38

4.7.1 NPDCL .............................................................................................................................................. 38

4.7.2 SPDCL ............................................................................................................................................... 39

Page 7: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

vii

4.7.3 EPDCL .............................................................................................................................................. 39

4.7.4 CPDCL .............................................................................................................................................. 40

4.8 Analysis for the States (Intra State OA) ................................................................................................... 41

4.8.1. Punjab ............................................................................................................................................... 41

4.8.2 Gujarat ............................................................................................................................................... 42

4.8.3 Uttar Pradesh ..................................................................................................................................... 43

4.8.4 Maharashtra ....................................................................................................................................... 44

4.8.5. Andhra Pradesh................................................................................................................................. 45

CHAPTER 5: ISSUES WITH OPEN ACCESS .................................................................................. 47

5.1 Implementation of Open Access ............................................................................................................... 47

5.1.1Determination of Cross Subsidy ......................................................................................................... 47

5.1.2 Phasing out of cross-subsidies ........................................................................................................... 48

5.1.3Transmission charges for short-term Open Access within the region (Inter-state Intra Regional) .... 49

5.1.4 Regulatory approach to Open Access ................................................................................................ 50

5.2 MANAGEMENT OF AGRICULTURE SUPPLY AND SUBSIDY ...................................................... 51

5.2.1Metering Agriculture Supply .............................................................................................................. 51

5.2.2 Separating Agriculture Supply .......................................................................................................... 53

5.3 OA in Andhra Pradesh - case ................................................................................................................... 55

5.4 Intra State Open access issues .................................................................................................................. 57

5.5 Open Access in Uttar Pradesh .................................................................................................................. 60

5.5.1 Open Access for industries key to UP‘s Economic growth ............................................................... 60

5.5.2. Lack of Implementation of OA regulations ...................................................................................... 61

5.5.3. Affordable and reliable power through the IEX ............................................................................... 62

5.5.4. OA as a panacea to power woes ....................................................................................................... 63

Chapter 6: SUMMARY ....................................................................................................................... 64

6.1 CONCLUSION ........................................................................................................................................ 64

6.2 RECOMMONDATION ........................................................................................................................... 66

6.3 LIMITATIONS OF THE PROJECT ........................................................................................................ 68

6.4 RESULT & DISCUSSION ...................................................................................................................... 68

6.5 FUTURE SCOPE OF THE PROJECT .................................................................................................... 69

6.6 BIBLIOGRAPHY .................................................................................................................................... 69

Page 8: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

viii

Executive Summary

Power is a critical infrastructure component for the country‘s economic development. The Ministry

of Power has given a major thrust to speed up the development and reforms of the power sector. It

has set an agenda of providing power to all by 2012. The Ministry seeks to achieve this objective

through a comprehensive and holistic approach to power sector development at the national, state,

SEB, distribution, feeder and consumer levels.

The Electricity Act, 2003 provides for Open Access for private generators and bulk consumers. Open

Access is a mechanism that allows generator to sell power to the highest bidder while consumers can

source their needs from the most economic seller. One of the greatest achievements of this over haul

in the power industry can be considered – is the freedom to buy and the freedom to sell the

electricity

As mentioned above, the freedom to buy and sell the electricity thereby creating or tending towards a

perfect market in the sector , which was previously almost a monopoly market run and maintained by

SEBs , is now widely opened up for a greater private participation. Trading is now considered as a

distinct activity. Open Access thus finds its own niche in supporting this activity. . However, even

nine years of the Act coming into force, the issue still evokes strong reactions from all the stake

holders with some resisting the idea while others welcoming it.

Open access transactions of energy should be promoted. Some of the high potential states have been

reluctant to allow open access to consumers and third party sales by captive generators because of

concerns of losing large high-paying consumers and the resultant impact on utility finances. The

high incidence of cross-subsidy surcharges and wheeling charges imposed on the direct sale of

power to consumers, reduces the competitiveness of energy in an otherwise potentially high-demand

market. It would also put competitive pressure on utilities to improve the quality of supply. Central

Transmission Utility (CTU) and State Transmission Utility (STU) are obliged to allow their facilities

for the purpose. Thus the timing of allotment , charges to be taken from users , amount of capacity to

be allotted like cross subsidy, extent of subsidy, method of calculation of surcharge, etc. are to be

addressed by the quasi judiciary entities.

This report gives a clear insight about the concept of Open Access and regulations issued by CERC

and various SERCs. Also, the detailed procedure laid out for grant of connectivity, Long-term,

medium-term and short-term Open Access by the CTU is studied.

Page 9: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

ix

This report highlights the cost benefit analysis of using Open Access against Grid power for

consumers with demand above 1MW for states such as, Andhra Pradesh, Gujarat, Maharashtra,

Punjab and Uttar Pradesh having high potential for Open Access. It would help in understanding the

benefit one can get by availing the facility of OA and explains various charges levied on Open

Access.

As a student of MBA in Power Management from National Power Training Institute (NPTI),

Faridabad, I had this opportunity to work as a summer intern with Global Energy Private Limited. It

lasted for 8 weeks and I was assigned a project to work on it.

This report includes study of existing CERC regulations for Inter State Open Access, 2008 for

eligible consumers. It also highlights the issues and recommendations highlighted by Forum of

Regulators (FOR) for successful implementation of Open Access. This report will help in

understanding the power market regulations. This project would help the eligible consumers

(demand above 1MW) in these states to decide upon their electricity provider and hence help them

in making substantial benefits out of the same. The vital information helps consumer to understand

the cost implications of OA in the state.

Page 10: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

x

Abbreviations

1. APCPDCL Central Power Distribution Company of Andhra Pradesh

Limited

2. APEPDCL Eastern Power Distribution Company of Andhra Pradesh

Limited

3. APERC Andhra Pradesh Electricity Regulatory Commission

4. APNPDCL Northern Power Distribution Company of Andhra Pradesh

Limited

5. APPC Average Power Purchase Cost

6. APSEB Andhra Pradesh State Electricity Board

7. APSPDCL Southern Power Distribution Company of Andhra Pradesh

Limited

8. APTRANSCO Transmission Company of Andhra Pradesh Limited

9. ARR Average Revenue Requirement

10. AT&C Aggregate Technical & Commercial Losses

12. CEA Central Electricity Authority

13. CERC Central Electricity Regulatory Commission

14. CSS Cross Subsidy Surcharge

15. CTU Central Transmission Utility

16. Discom Distribution Company

17. EA Electricity Act

18. EHT Extra High Tension

19. FOR Forum of Regulators

20. HT High Tension

21. IEX India Energy Exchange

22. kWh Kilo Watt Hour

23. LT Low Tension

Page 11: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

xi

24. LTOA Long Term Open Access

25. MAHADISCOM Maharashtra State Electricity Distribution Company

26. MERC Maharashtra Electricity Regulatory Commission

27. MSEDCL Maharashtra State Electricity Distribution Company

Limited

28. MSETCL Maharashtra State Electricity Transmission Company

Limited

29. MTOA Medium Term Open Access

30. MU/MUs Million Units

31. MYT Multi Year tariff

32. NLDC National Load Despatch Centre

33. OA Open Access

34. PGCIL Power Grid Corporation on India Limited

35. PLF Plant Load Factor

36. PSEB Punjab State Electricity Board

37. PSERC Punjab State Electricity Regulatory Commission

38. PXIL Power Exchange India Limited

39. RLDC Regional Load Despatch Centre

40. SLDC State Load Despatch Centre

41. STOA Short Term Open Access

42. STU State Transmission Utility

43. ATC Available Transfer Capacity

44. TTC Total Transfer Capacity

45. TOA Transmission OA

46. DOA Distribution OA

Page 12: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

xii

List of Table

Table 1- Open Access Provision ........................................................................................................................ 12

Table 2- Stages of Evolution of OA ................................................................................................................... 15

Table 3- UI Rates for Average Frequency of Time Block (Hz) ......................................................................... 25

Table 4- Assumptions for OA analysis ............................................................................................................... 26

Table 5- OA consumers in Punjab ...................................................................................................................... 28

Table 6- PSPCL analysis .................................................................................................................................... 28

Table 7- STOA in Gujarat .................................................................................................................................. 29

Table 8- STOA network in Gujarat .................................................................................................................... 29

Table 9- MTOA in Gujarat ................................................................................................................................. 29

Table 10: UGVCL Analysis ............................................................................................................................... 30

Table 11: PGVCL Analysis ................................................................................................................................ 30

Table 12: MGVCL Analysis .............................................................................................................................. 31

Table 13: DGVCL Analysis ............................................................................................................................... 31

Table 14: Torrent Power Analysis ...................................................................................................................... 32

Table 15: PuVVNL Analysis .............................................................................................................................. 33

Table 16: MVVNL Analysis .............................................................................................................................. 33

Table 17: PVVNL Analysis ................................................................................................................................ 34

Table 18: DVVNL Analysis ............................................................................................................................... 34

Table 19: KESCoL Analysis .............................................................................................................................. 35

Table 20: NPCL Analysis ................................................................................................................................... 35

Table 21: MSEDCL Analysis ............................................................................................................................. 36

Table 22: Rinfra Analysis ................................................................................................................................... 37

Table 23: TPC Analysis ...................................................................................................................................... 37

Table 24: NPDCL Analysis ................................................................................................................................ 38

Table 25: SPDCL Analysis ................................................................................................................................ 39

Table 26: EPDCL Analysis ................................................................................................................................ 39

Table 27: CPDCL Analysis ................................................................................................................................ 40

Table 28: Energy Shortage in UP ....................................................................................................................... 60

Table 29: Peak shortage in UP ........................................................................................................................... 61

Table 30: OA at IEX ........................................................................................................................................... 62

Page 13: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

xiii

List of Figures

Figure 1-Services of Global Energy....................................................................................................... 5

Figure 2-Research Methodology .......................................................................................................... 10

Figure 3 : Category of OA ................................................................................................................... 16

Figure 4- Allotment Priority ................................................................................................................ 19

Figure 5- Volume traded at IEX .......................................................................................................... 56

Page 14: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

1

Chapter 1: Introduction

The Indian power sector has made significant progress over the years. The installed capacity of the

industry grew manifold from 1,361 MW in 1947 to 225 GW till July 2013. The sector has also

undergone substantial structural changes. Regulatory policies have played a predominant role in

changing the landscape of the Indian power sector. Though the sector has come a long way from its

humble beginnings, it is still lagging on several fronts, such as power shortages, T&D losses, and

Grid instability among others, and has a long way to go.

The Electricity Act, 2003 aims at bringing about competitions with the ultimate objective of

ensuring efficiency gains from competition for the consumers. Competition with regulatory

oversight is the hallmark of the legislations and it recognises the important role of the regulatory

commissions in the wake of the challenges that opening of the sector poses for consumers and other

stake holders.

In the context of competition, Open Access is the corner-stone of the Act. OA has been conceived as

an important tool of introducing competition in the electricity industry and ensuring choice to buyers

and suppliers of electricity.

The Act envisages OA in Transmission and distribution network. OA in transmission has been

allowed from the very beginning and without any fetter, however in so far as OA in distribution is

concerned, the law envisages introduction of such OA in phases with due consideration of the

operational constraints and existence of cross subsidy between consumer categories . This

responsibility of phased introduction of OA in distribution has been bestowed on SERCs. Though an

amendment in the Act, it has, however been provided that the state commissions shall provide by

January, 2009 OA to all consumers with load exceeding 1MW.

The issue of OA for consumers with load exceeding 1 MW has been under discussion in recent past

in view of the various interpretations floated in the context. The Govt.of India( Ministry of Power

and Ministry of Law) in its latest interpretation on 31.11.2011 has been anticipated that section 42 of

the act makes it mandatory for all consumers with load exceeding 1 MW to be OA consumers and

that the tariffs for such consumers shall not be regulated by SERCs.

Even as the Central Government is pushing states for mandatory implementation of OA for bulk

Page 15: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

2

power consumers, an analysis by a regulators body has revealed that contrary to expectations, the

consumers in 12 states have had to pay more for power under the new regime.

OA at various levels is the hallmark of electricity reforms and the regime has been effective in 20

states since Jan‘09 on an optional basis. Under the OA regime, bulk consumers enter into bilateral

deals with discoms and stay outside the ambit of the regulated tariff system.

The Electricity Act defines ―Open Access‖ as non-discriminatory provision for the use of

transmission lines or distriburion system or associated facilities with such lines or system by any

licensee or consumer or a person engaged in generation in accordance with the regulation specified

by the appropriate Commission. As compared to the earlier legal and regulatory regime, the strategic

intent of the act is to promote competition by freeing up possible avaenues of procurement and sale

of power. The provisions of the act relating to delicensing of generation, open access, elimination of

cross-subsidy, dedicated tranmsission lines and definition of captive generating stations are desinged

to allow the freedom to purchase and sell electricity. However, this freedom has little meaning

without the capabitlity to carry the energy from the generating plant to the point of consumption.

This makes the entire arrangements reliant on the transmission and the distribution companies to

transmit the energy, and on regulatory commissions to facilitata the process through adequate

regulations and mechanism to enable non-discriminatoy open access.

In general, cross-subsidies cannot be sustained in the presence of OA and competition, because of

the problems of ―cherry picking‖. Regulators will have to phase our cross-subsidies in order to

introduce competition. However, a phase out of cross-subsidies require an alternative mechanism to

provide for the minimum needs of those with inadequate capacity to pay and those living in areas

with high cost of network extension.

Page 16: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

3

1.2 Problem Statement

Due to continuous shifting of bulk consumers, distribution licensee and losing their paying

consumers and if the process will continue, then the time will reach when distribution licensee will

remain only with subsidised of non-paying consumers. Under the Electricity Act, OA consumers

have to pay charges including wheeling and standby charges and CSS, besides the cost of electricity.

But these charges are not up to the mark and to minimise the loss of distribution licensee, following

things should be considered:

Ideally, the net effect of subsidy and cross subsidy should need to be zero but in reality, it is

not zero due to AT&C losses and theft has not been considered in case of CSS formula.

Need to define, who will pay the cross subsidy of renewable? If its obligation has been

removed from paying CSS for its promotion.

1.3 Scope of the project

The scope of the project is as follows:

1. The report aims at respecting the end consumer‘s interest because electricity gets associated

with a social aspect as well. It is a basic necessity and any development should aim at

providing more reliable and quality power at reasonable rates.

2. In accordance with the eligibility conditions that OA to consumers of loads greater than or

equal to 1MW. Till date, almost 22 SERCs have granted OA. Further reduction in eligibility

conditions in terms of load will enhance the development of retail market in India.

This project will help to highlight the problem which Discom are facing & also help in minimising

their losses by their different initiatives. Customer interaction and analysis of consumer view will

help the licensee to understand the ground realities in OA and also help to know the consumer

expectation and suggestion to improve the process. The reasons of shifting of bulk consumer when

there is already a reliable power available in the state for them.

To develop financial model to compute the OA charges and landed cost of electricity for various

states by assuming a typical 5MW capacity project.

1.4 Objective of the project

To study and analyse the present scenario of OA in the county.

To determine open access charges based on economic principles and methodologies adopted

Page 17: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

4

by various SERCs.

To understand the billing procedure in OA.

Understand the role of RLDC, SLDC in OA.

Find out that whether the customers would really be benefitted through OA or they have

more benefit by retaining with existing licensees.

To understand OA provision outlined in EA 2003 for wheeling of electricity for captive use

and third-party sale.

1.5 Significance of the project

Enactment of the EA, 2003 has forced for promotion of OA to develop competition in the

market but actual competition is possible only when there is perfect market available like

number of buyers and sellers and most importantly surplus of commodity. When we are

deficit in power and talk about competition, then it creates number of flaws which affects the

interest of consumers.

While implementation of OA, the loss of Discom has not been taken into consideration

though there may be number of surcharge available like CSS to compensate the loss of

Discom but it is not up to the mark to recover the full loss. Due to improper implementation

of OA under the name of ―Promotion to Competition‖, now almost all discoms are in losses,

hence it is very important to look into this matter and take some revolutionary steps to

recover the losses of discoms.

Also the theft of Power has not been taken into consideration into CSS which Discom has to

bear although they have taken number of steps to stop theft of electricity.

Besides, DE licensing generation and removing controls on captive generation, the provision

regarding availability of non-discriminatory OA in transmission from the very beginning and

distribution in phased manner is the core of the act.

However, a full fledged competitive electricity structure at distribution side with the quality

and reliable supply at competitive price and choice to consumer to select his supplier is yet to

take off.

The project assumes greater significance to bridge the gap between existing vertically

centralized monopoly system in power sector to a more market oriented decentralized and

competitive system and beneficial to enter into a more globalized and market oriented

economy.

Page 18: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

5

1.6 Organizational Profile: Global Energy Private Limited

1.6.1 About the Organization

Global Energy Pvt Ltd is an ISO 9001:2008 certified Energy Company like no other, which is

committed towards honouring the trust invested in it by its clients, by providing uninterrupted power

supply and commitments made to its employees by delivering them a steady growth path. They are

committed to achieving success in accordance with our company‘s high business ethics and values

with a focus on green and renewable energy. Every member of GEPL has imbibed this commitment

and purpose.

Global Energy Pvt Ltd focus is to efficiently operate our renewable facilities in order to provide our

customers with a reliable, low-cost source of power. GE is an ISO 9001:2008 Certified Company for

generation of Power from Agro waste.

As a power trader, Global Energy supports their esteemed clients with data driven power market

analysis to help them get best returns. Global Energy has till date, transacted almost 3 billion units of

Energy. Global Specializes in renewable energy trading, especially wind and Hydro.

They understand the dynamics of the various energy markets and maintains effective relationships

with stakeholders by using extensive knowledge to benefit clients through advisory services.

1.6.2 Services

Figure 1-Services of Global Energy

Power Trading

Power Generation

Power Advisory

Certificate Trading

Clean Energy

Page 19: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

6

Power Trading: Power Trading powered by analytics directed towards equitable growth.

o Analytics driven methodology

o Renewable power transactions and Non Renewable power transactions

o Power supply via OA

Power Generation: Generating energy through renewable sources for a cleaner and greener

tomorrow.

Clean Energy Initiatives: Helping provide for India's burgeoning energy needs.

Energy Certificate trading: Contribution towards the above effort lies in helping clients build their

RE Certificates sales portfolio at the optimum price range through:

Renewable Energy Certificate

Verified Emission Reduction Certificates, and

Certified Emission Reduction Certificates.

Power Advisory: Share knowledge and expertise in the energy sector for a brighter future.

o Capacity Design for Public and Private Enterprises

o Infrastructure and Logistics Planning

o Turnkey Advisory Services

o Regulatory Advisory.

Page 20: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

7

Chapter 2: Literature Review and Research Methodology

2.1 Literature Review

CERC Concept paper on [Open Access in Inter-state Transmission] [August 2003] highlights the

issues associated with OA and frame regulations as the outcome of the exercise. It also describes the

transmission pricing schemes designed to promote efficient day to day operation of bulk power

market including power trading. It gives economic signals for efficient use of transmission

resources, investment in transmission, location of new generation and loads, compensating owner of

transmission system. It also describes energy accounting, e.g. Active Energy, Reactive Energy, etc.

The paper concluded that:

The existing long-term transmission agreements should be honoured until modified; else the

issue of stranded assets would arise.

To begin with only spare transmission capacity can be made available for OA.

Since, RLDCs will have a key role to play in the OA related issues; neutrality in their

functioning is expected.

In the new scenario, original beneficiaries will also be treated as OA customers at par, for the

purpose of power trading and bilateral exchanges. However, the original beneficiaries shall

continue to pay transmission charges for transmission of allocated power from the ISGS.

Contract Path Method and Incremental Postage Stamp Method have been suggested for OA

pricing.

The Transmission Service Providers in the country (CTU, STU, Licensees, etc.) will have to

declare rates for various types of services within the ceiling price as described by the

Commission.

Special Energy Meters will be installed by the OA customers as and when required.

S.K.Chatterjee, Deputy Chief (RA), CERC [7th

July, 2009] [Open Access – Challenges & Way

Forward] describes application procedures and approval for consumers connected to distribution

system, Intra-state transmission system. It describes eligibility conditions and provisions under

‗FOR‘ model regulations. It also describes the provision for imbalance settlements and various

charges payable by OA Consumers.

Planning Commission, Government of India (2009) [Report of the Task Force on Measures for

Operationalizing Open Access in the Power Sector] confirmed that no consumer in any state has

availed OA under Section 42 of the act so far and in fact in many states the provisions of the Act

Page 21: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

8

have not been operationalized so far. The facility has been availed of only by captive producers and

that too marginally. The Task Force noted that the surplus states were extracting undue rent from

their surplus supplies, some of which actually came from the Central Public Sector Units (CPSUs).

The Task Force concluded that it would be in public interest to amend Section 21(1)(a) to make it

explicit that supply of electricity by a generating company to as distribution licensee includes

through an electricity trader. The Task Force also recommended that since no case of OA under

Section 42 of the Act had been reported so far, the Regulators should meet with the stakeholders to

address their concerns with a view to operationalizing the scheme f the Act. It further recommended

that consumer education and pro-active action by the electricity regulators both at the centre and in

the states was vital for encouraging OA to consumers.

In 2005, Mr.Nayak, R.N. (PGCIL, Gurgaon) etal describes Indian Power system and the reforms

being undertaken to restructure it. Introduction of OA in transmission has been deliberated in detail.

Various issues arising due to liberalized electricity market and the need of change in power system

planning methods has been mentioned. Need of suitable mechanism for sharing of transmission

charges in the de regulated regime is also deliberated.

Shafqat Mughal [2010] in National Power Engineering Conference presented a paper on ―The

Changing Scenario of Electricity Trading and Power Market Mechanism in India‖ described

the significance of OA in the power market. He describes OA as the key to a free and fair electricity

market. Power producers (sellers) and dealers/customers (buyers) have to share a common

transmission network for wheeling the power from the point of generation to point of consumption.

The OA provided non-discriminatory use of the inter state and intra state transmission system,

facilitating the trading of power from one utility to other. It also facilitates setting up of Independent

Power Producers (IPPs), Captive Power Producers (CPPs) and merchant power plants. After

implementation of OA, the experience gained has been providing signals for identification of

congested corridors and expansion planning.

S.K. Soonee (C.E.O. POSCO) in his paper [Open Access in Inter-state Transmission] cites the

significance of OA in Trading Market Evolution. It describes various products of Trading, accounts

the short trade in various financial periods.

Tushar Giri Nath in his paper [―OPEN ACCESS: UNFINISHED AGENDA OF POWER SECTOR

REFORMS IN INDIA”] described Open Access Regulations in transmission and distribution as a

must for the development of private sector power generation and in the development of market for

Page 22: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

9

distribution entities. The charges payable by the generator for using the network should be reasonable

and access should be non-discriminatory. This will not only ensure the power flow to the deficit areas

but also facilitate optimal use of the network and investment in the network by the distribution and

transmission utilities based on the actual demand of the region rather than on their capacity to procure

and distribute power. This paper attempts to find out the limiting factors in the success of open access

regulations in India.

N. Balavenkata Muni et al in journal [ADVANCED OPEN ACCESS PRICING

METHODOLOGIES IN ECONOMICALLY ADAPTED ELECTRIC POWER SYSTEM]

[IJART, Vol.2 Issue 2, 2012, 33– 42] describe Open Access as the key to free and fair electricity

market. Under Open Access, transmission acts as a Gate Keeper. It can be closed in defence of

regulated market place or opened to support a greater number of participants.

Ravinder, Talegaonkar Ajay in his journal [Developing Power Exchanges in India : Issues and

challenges] [2008, Vol. 65, Issue 3] discussed the introduction of open access for inter-state

transmission as per the new electricity legislation in India has facilitated bilateral trading resulting in

better resource optimization within an overall deficit scenario. While the volume of traded electricity

is tiny compared to the total consumption, nonetheless it has electrified an otherwise grim scenario.

As a result, the Indian power sector has started at tracing private investment in hydro and thermal

generation at an unprecedented scale.

K. Sarkar S. in his journal [Competition in the electricity sector: tracing recent developments]

[2006, Vol. 12, Issue: 23] described that the Electricity Act 2003 is bold enough to set its objectives

to promote competition in the electricity sector. It has obligated the distribution licensee to allow

non-discriminatory

‗Open access‘ to various consumers subject to technical requirements and payment of certain

charges. The National Electricity Policy 2005 and the NTP (National Tariff Policy) 2006 have

contained elaborate provisions to meet these objectives. The electricity regulators at the central level

and in more than 12 states have framed the ‗open access‘ regulations. These enabling frameworks are

supposed to bring in many players seeking open access to the distribution and transmission electricity

system. Unfortunately, this has not happened. The often quoted reason is that the ‗surcharge

formula‘, as stipulated under the NTP 2006 gives rise to an amount, which, in many cases, is more

than the cross subsidy amount. Even in the remaining cases, the number of players seeking for open

access is almost nil. This calls for a closer look at the ‗open access‘ regulation.

Page 23: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

10

2.2 Research Methodology

Figure 2-Research Methodology

Chapter 3: Open Access

Study of CERC Open Access Regulations

Study of detailed procedures of CTU for Open

Access

Study of FOR Model Intra State OA

Regulations

Study of Issues related to OA

Study of Open Access charges applicable

Selection of states for Cost Benefit Analysis

Determination of Charges applicable through

Tariff Order

Comparison of Tariff through Open Access and

Grid Power (Discom)

Detailed Analysis of OA in states

Page 24: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

11

3.1 Introduction to Open Access According to section 2 (47) of the “Electricity Act 2003” Open Access is defined as “A non-discriminatory provision for the use of transmission lines or distribution system or

associated facilities with such lines or system by any licensee or consumer or a person engaged in

generation in accordance with the regulations specified by the Appropriate Commission”

To interpret it in a more understandable way the above can be put as follows:

Enabling of non-discriminatory sale/ purchase of electric power/energy between two parties utilizing

the system of an in-between (third party), and not blocking it on unreasonable grounds.

Open access allows large users of power — typically having connected load of 1 megawatt (MW)

and above — to buy cheaper power from the open market. The idea is that the customers should be

able to choose among a large number of competing power companies–instead of being forced to buy

electricity from their existing electric utility monopoly. It helps large consumers particularly the sick

textile, cement and steel industrial units by ensuring regular supply of electricity at competitive rates

and boost business of power bourses.

Open Access on Transmission and Distribution on payment of charges to the Utility will enable

number of players utilizing these capacities and transmit power from generation to the load centre.

This will mean utilization of existing infrastructure and easing of power shortage. Trading, now a

licensed activity and regulated will also help in innovative pricing which will lead to competition

resulting in lowering of tariffs.

The Electricity Act, 2003 aims at bringing about competition with the ultimate objective of ensuring

efficiency gains resulting from competition for the consumers. Competition with regulatory oversight

is the hallmark of the legislation - and it recognises the important role of the regulatory commissions

in the wake of the challenges that opening of the sector poses for consumers and other stakeholders.

In the context of competition, open access is the corner-stone of the Act. Open Access has been

conceived as an important tool of introducing competition in the electricity industry and ensuring

choice to buyers and suppliers of electricity.

The Act envisages Open Access in transmission and distribution network. Open Access in

transmission has been allowed from the very beginning and without any fetter. However, in so far as

Open Access in distribution is concerned, the law envisages introduction of such Open Access in

Page 25: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

12

phases with due consideration of the operational constraints and existence of cross subsidy between

consumer categories. This responsibility of phased introduction of open access in distribution has

been bestowed on State Electricity Regulatory Commissions. Through an amendment in the Act, it

has, however been provided that the State Commissions shall provide by January, 2009 open access

to all consumers with load exceeding 1 MW.

The issue of open access for consumers with load exceeding 1 MW has been under discussion in

recent past in view of the various interpretations floated in the context. The Government of India

(Ministry of Power and Ministry of Law) in its latest interpretation on 30.11.2011 has articulated that

Section 42 of the Act makes it mandatory for all consumers with load exceeding 1 MW to be open

access consumers and that the tariffs for such consumers shall not be regulated by SERCs.

Open access enables consumers to obtain their supply of electricity from a generating company or

any licensee, other than the distribution licensee for the area. The distribution licensee will be paid a

wheeling charge; a surcharge to meet the current level of cross-subsidy within the area of supply; and

an additional surcharge to meet the fixed costs of the distribution licensee arising out of his obligation

to supply. The regulator will determine only the wheeling charges and surcharge, not the tariff. The

surcharge is not payable by a captive generation plant.

3.2 Legal Framework Provisions on Open Access in the Electricity Act, 2003

Section 2(47) of the act defines ―Open Access‖ to mean

“Non-discriminatory provision for the use of transmission lines or distribution system or

associated facilities with such lines or system by any licensee or consumer or a person

engaged in generation in accordance with the regulations specified by the Appropriate

Commission”.

Table 1- Open Access Provision

SECTION 9 (2) CAPTIVE GENERATION

SECTION 38 (2) (D) FUNCTIONS OF CTU

SECTION 39 (2) (D) FUNCTIONS OF STU

SECTION 42 DISTRIBUTION LICENSEE & OPEN ACCESS

SECTION 43 SUPPLY ON REQUEST

SECTION 86 (1) (C) FUNCTIONS OF STATE COMMISSION

Source: ElectricityAct2003

Page 26: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

13

SECTION 9(2) (CAPTIVE GENERATION)

Every person, who has constructed a captive generating plant and maintains and operates such plant,

shall have the right to Open Access for the purposes of carrying electricity from his captive

generating plant to the destination of his use. Provided that such Open Access shall be subject to the

Central Transmission Utility or the State Transmission shall determine availability of adequate

transmission facility and such availability of transmission facility.

Utility, as the case may be: Provided further that the Appropriate Commission shall adjudicate upon

any dispute regarding the availability o transmission facility.

SECTION 38(2)(D) FUNCTIONS OF CTU

To provide non-discriminatory Open Access to its transmission system for use by-

Any licensee or generating company on payment of the transmission charges can avail

open access.

Any consumer as and when such Open Access is provided by the State Commission

under sub-section (2) of section 42 on payment of the transmission charges and a surcharge

thereon. As may be specified by the Central Commission: Provided that such surcharge shall

be utilised for the purpose of meeting the requirement of current level cross-subsidy: Provided

further that such surcharge and cross subsidies shall be progressively reduced in the manner

as may be specified by the Central Commission.

Provided also that the manner of payment and utilisation of the surcharge shall be specified

by the Central Commission: Provided also that such surcharge shall not be leviable in case

Open Access is provided to a person who has established a captive generating plant for

carrying the electricity to the destination of his own use.

Section 39(2)(d)Functions of State Transmission Utility

(d) To provide non-discriminatory Open Access to its transmission system for use by:

(i) Any licensee or generating company on payment of the transmission charges.

(ii) Any consumer as and when such Open Access is provided by the State Commission under sub-

section (2) of section 42, on payment of the transmission charges and a surcharge thereon, as may be

specified by the State Commission. Provided that such surcharge shall be utilised for the purpose of

meeting the requirement of current level cross-subsidy. Provided further that such surcharge and

Page 27: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

14

cross subsidies shall be progressively reduced in the manner as may be specified by the State

Commission.

Provided also that the manner of payment and utilisation of the surcharge shall be specified by the

State Commission. Provided also that such surcharge shall not be leviable in case Open Access is

provided to a person who has established a captive generating plant for carrying the electricity to the

destination of his own use.

SECTION 42(DUTIES OF DISTRIBUTION LICENSEE AND OPEN ACCESS)

(1) It shall be the duty of a distribution licensee to develop and maintain an efficient, co-ordinated

and economical distribution system in his area of supply and to supply electricity in accordance with

the provisions contained in this Act.

(2) The State Commission shall introduce Open Access in such phases and subject to such conditions,

(including the cross subsidies, and other operational constraints) as may be specified within one year

of the appointed date by it and in specifying the extent of Open Access in successive phases and in

determining the charges for wheeling. It shall have due regard to all relevant factors including such

cross subsidies and other operational constraints. Provided that such Open Access shall be allowed on

payment of a surcharge in addition to the charges for wheeling as may be determined by the State

Commission. Provided further that such surcharge shall be utilised to meet the requirements of

current level of cross subsidy within the area of supply of the distribution licensee. Provided also that

such surcharge and cross subsidies shall be progressively reduced in the manner as may be specified

by the State.

SECTION 43(DUTY TO SUPPLY ON REQUEST)

(1) 1[Save as otherwise provided in this Act, every distribution] licensee, shall, on an application by

the owner or occupier of any premises, give supply of electricity to such premises, within one month

after receipt of the application requiring such supply: Provided that where such supply requires

extension of distribution mains,

Or commissioning of new sub-stations, the distribution licensee shall supply the electricity to such

premises immediately after such extension or commissioning or within such period as may be

specified by the Appropriate Commission:

Page 28: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

15

SECTION 49(AGREEMENT WITH RESPECT TO SUPPLY OR PURCHASE

OF ELECTRICITY)

Where the Appropriate Commission has allowed Open Access to certain consumers under

section 42, such consumers, notwithstanding the provisions contained in clause (d) of sub-

section (1) of section 62, may enter into an agreement with any person for supply or purchase of

electricity on such terms and conditions (including tariff) as may be agreed upon by them.

Table 2- Stages of Evolution of OA

Stage of evolution Description

Electricity Act 2003 Introduction of Competition in Power Sector and Open

Access in Inter-State transmission.

2004: First CERC Regulation (Issued Introduced LTOA (>25 yrs.) and STOA (<1 yr.) products.

on 30-1-04) Congestion Management through fax/e-mail.

Open Access 2005 (First Amendment Introduction of new products under STOA: Advance

issued on 21-2-05) Scheduling, First come First Serve Basis (FCFS), Day

Ahead, Same Day. E-bidding invited for STOA.

Open Access 2006-2007 (Second Developing a common platform for Electricity Trading,

Amendment) Grant of permission for setting up and operation of Power

Exchange.

Open Access Regulation 2008 (Issued Exit option provided with payment of up to 5 days open

on 25-1-08 Access charges.

Amendment 2009 (Issued on 20-5-09) Exit option provided with payment of up to 2 days open

Access charges.

CERC Power Market Regulation, Introduction of REC contracts.

2010 \

3.3 Distribution Open Access

3.3.1Eligibility to seek Open Access: Regulation 2011 allows a contract demand of more than

1 MVA from the date of notification of these regulations subjected to approval from commission.

3.3.2 Rules for grant of connectivity as per 2011 regulations:

1. A generating station having installed capacity less than 5 MW shall be eligible to obtain

connectivity to the distribution system.

2. A generating station having capacity more than 5 MW may also get connectivity provided

Page 29: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

16

such connectivity is technically feasible

3. Application shall be accompanied by a non- refundable fees of 2 Lakh

4. On receipt of application, the Distribution Licensee should process application in

consultation with STU when required.

3.4 Category of Open Access consumers as per CERC regulations 2011

Figure 3 : Category of OA

Long Term Open Access Customers: Period exceeding 12 yrs. but less than 25 yrs.

Medium Term Open Access Customers: Period between 3 months and 3 yrs.

Short Term Open Access Customers: Period not exceeding 30 days

Day Ahead Open Access Customers: It is permitted on availability of surplus capacity in

distribution Licensee‘s system. The application will be received within 2 days prior to date of

scheduling but not later than 1500 hrs. Of day immediately proceeding the day of scheduling

for day ahead transaction.

Scheduling

Inter-State: Intra-State Open Access transactions shall be specified by CERC

Intra-State: Intra-State Open Access transactions in respect of load 5MW and above and all

generating stations irrespective of the capacity shall be scheduled by SLDC in accordance with the

provisions of State Grid Code. No scheduling required in respect of open access consumer having load of less than 5MW and

Captive Power Plants.

3.5. Transmission Open Access

3.5.1. Eligibility to seek OA

1. Generating company which own or operates or intends to operate a generating station in the

state.

Page 30: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

17

2. Person who constructed, maintained, operates or intends to in the state for its own use

3. Distribution Licensee or a person who has applied for a licensee to distribute electricity

Trading Licensee or a person applied for trading in electricity shall be eligible for open access to

intra-state transmission system in accordance with these regulations.

3.5.2 Grant of connectivity:

A consumer having load of 5MW and above or a generating station having installed capacity of

5MW and above shall be eligible to obtain connectivity to Intra-State Transmission system.

Application shall be accompanied by a non-refundable fee of Rs. 2 lakh. The application shall

contain details such as proposed geographical location, quantum of power to be interchanged and

such other details as may be laid down by STU.

3.5.3 Grant of connectivity to STU

On receipt of application, the STU shall, in consultation and through coordination with other

agencies involved in Intra-State transmission system to be used, process the application and carry out

the necessary interconnection in compliance with CTU.

While granting connectivity, the STU shall specify the name of the sub-station or pooling station or

switchyard where connectivity is to be granted.

The applicant or inter-State transmission licensee shall sign a connection agreement with the CTU or

IST licensee owning the sub-station or pooling station or switchyard or the transmission line as

identified by the nodal agency where connectivity is being granted.

A generating station, including captive generating plant which has been granted connectivity to

the grid shall be allowed to undertake testing including full load testing by injecting its infirm

power into the grid before being put into commercial operation .Even before availing any type of

open access, after obtaining permission of the concerned Regional Load Despatch Centre, which

shall keep grid security in view while granting such permission.

This infirm power from a generating station or a unit thereof (except those based on non-

conventional energy sources) will be governed by the Central Electricity Regulatory Commission

(Terms and Conditions of Tariff) Regulations, 2009. The power injected into the grid from other

generating stations as a result of this testing shall also be charged at UI rates. An applicant may be

required by the Central Transmission Utility to construct a dedicated line to the point of connection

to enable connectivity to the grid except if it is:

Page 31: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

18

A Thermal generating station of 500 MW and above.

A Hydro generating station of 250 MW and above.

Not a captive generating plant.

3.6 PROCEDURE FOR ALLOTMENT OF OPEN ACCESS

3.6.1 Long Term Open Access

i) An application for long-term access shall be submitted to the nodal agency;

ii) The application shall contain the details, such as capacity needed, point(s) of injection, point(s)

of drawl, duration of availing open access, peak load, average load and such other additional

information that may be specified by the nodal agency: Provided that the nodal agency shall

issue necessary guidelines, procedure and application forms within 30 days of commencement of

these regulations.

iii) The application shall be accompanied by a non-refundable application fee of Rs one lakh payable

in the name and in the manner to be decided by the nodal agency;

iv) Based on system studies conducted in consultation with other agencies involved including other

transmission licensees, the nodal agency shall, within 30 days of receipt of the application,

intimate to the applicant whether or not the long-term access can be allowed without further

system strengthening:

v) Provided that where the long-term access can be allowed without further system strengthening,

this shall be allowed immediately after entering into commercial agreements.

vi) If, in the opinion of the nodal agency, further system strengthening is essential before providing

the long-term access, the applicant may request the nodal agency to carry out the system studies

and preliminary investigation for the purpose of cost estimates and completion schedule for

system strengthening;

vii) The nodal agency shall carry out the studies immediately on receipt of request from the applicant

under clause (v) above and intimate results of the studies within 90 days of receipt of request

from the Central / State transmission Unit.

viii) The applicant shall reimburse the actual expenditure incurred by the nodal agency for system

strengthening studies:

Page 32: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

19

Provided that the fee of ` 1 lakh paid by the applicant shall be adjusted against the actual expenditure

to be reimbursed.

3.6.2 Short Term Open Access

i) A short-term customer shall submit an application for transmission access to the nodal Regional

Load Despatch Centre.

ii) The application shall contain the details, such as capacity needed, point or points of injection,

point or points of drawl, duration for availing of open access, peak load, average load and such

other additional information that may be laid down by the Regional / State Load Dispatch

Centre.

iii) The application shall be accompanied by a non-refundable application fee of Rupees five

thousand only; Provided that in case of application for access on the date of the application or on

the following day, the application fee may be deposited within next three working days of

making of application.

iv) The reserved transmission capacity shall not be transferred by a short-term customer to any other

customer.

3.6.3 Allotment Priority

Figure 4- Allotment Priority

Distribution

Licensee

STOA

MTOA

LTOA

Existing OA Customer New OA Customer

Page 33: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

20

3.7 ROLE OF DIFFERENT AGENCIES IN OPEN ACCESS

3.7.1 NLDC (National Load Dispatch Centre)

Section 26. (National Load Dispatch Centre) of the Act stipulates that: (1) The Central Government may establish a centre at the national level, to be known as the National

Load Dispatch Centre for optimum scheduling and dispatch of electricity among the Regional

Load Dispatch Centres.

(2) The constitution and functions of the National Load Dispatch Centre shall be such as may be

prescribed by the Central Government.

Note: Provided that the National Load Dispatch Centre shall not engage in the business of

trading in electricity.

3.7.2 RLDC (Regional Load Dispatch Centre)

Section 27. (Constitution of Regional Load Dispatch Centre) of the Act stipulates that:

(1) The Central Government shall establish a centre for each region to be known as the Regional

Load Dispatch Centre having territorial jurisdiction as determined by the Central Government in

accordance with section 25 for the purposes of exercising the powers and discharging the functions

under this Part.

(2) The Regional Load Dispatch Centre shall be operated by a Government company or any

authority or corporation established or constituted by or under any Central Act, as may be

notified by the Central Government. Provided that until a Government company or authority or

corporation referred to in this sub-section is notified by the Central Government, the Central

Transmission Utility shall operate the Regional Load Dispatch Centre.

Note: Provided further that no Regional Load Dispatch Centre shall engage in the business of

generation of electricity or trading in electricity.

3.7.3 SLDC (State Load Dispatch Centre)

Section 31 (Constitution of State Load Dispatch Centre) of the Act stipulates that: --

(1) The State Government shall establish a Centre to be known as the State Load Dispatch Centre

Page 34: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

21

for the purposes of exercising the powers and discharging the functions under this Part.

(2) The State Load Dispatch Centre shall be operated by a Government company or any authority

or corporation established or constituted by or under any State Act, as may be notified by the

State Government. Provided that until a Government company or any authority or corporation

is notified by the State Government, the State Transmission Utility shall operate the State

Load Dispatch Centre.

Note: Provided further that no State Load Dispatch Centre shall engage in the business of

trading in electricity.

3.7.4 CTU (Central Transmission Utility)

Section 38. (Central Transmission Utility and functions) of the Act stipulates that:

(1) The Central Government may notify any Government company as the Central Transmission

Utility.

Note: Provided that the Central Transmission Utility shall not engage in the business of

generation of electricity or trading in electricity.

One of the functions of Central Transmission Utility is to provide non-discriminatory Open Access

to its transmission system for use by –

(i) any licensee or generating company on payment of the transmission charges; or

(ii) any consumer as and when such open access is provided by the State Commission under sub-

section (2) of section 42, on payment of the transmission charges and a surcharge thereon, as

may be specified by the Central Commission.

3.7.5 STU (State Transmission Utility)

Section 39. (State Transmission Utility and functions) of the Act stipulates that:

(1) The State Government may notify the Board or a Government company as the State

Transmission Utility.

Note: Provided that the State Transmission Utility shall not engage in the business of trading in

electricity.

One of the functions of State Transmission Utility is to provide non-discriminatory open access to its

transmission system for use by

(i) any licensee or generating company on payment of the transmission charges ; or

(ii) any consumer as and when such open access is provided by the State Commission under sub-

Page 35: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

22

section (2) of section 42, on payment of the transmission charges and a surcharge thereon, as

may be specified by the State Commission. The Load Dispatch Centres, transmission utilities are

barred from trading n power in order to ensure non-discriminatory open access to all the

generators/ consumers.

3.8 Understanding Open Access charges

There are major charges to be paid by open access consumers to distribution licensee, transmission

licensees and other related entities, other than the power purchase cost paid to the generator or

supplying entity. These charges include:

1. Wheeling Charges or Distribution Charges

Distribution charges are those charges which are paid to distribution licensee for the use of

distribution system and associated facilities by another person for the conveyance of electricity.

The licensees, generating stations, captive generating plants and consumers shall be eligible for open

access to distribution system of a distribution licensee on payment of the wheeling charges as may be

determined by the Commission

Applicability: These charges are applicable to generating stations, captive generating plants and

consumers who are connected to Discom network i.e., at 11 and 33 kV.

2. Wheeling Loss or Distribution Loss

Distribution losses are the technical losses for the distribution system. It is determined by the

Commission for various voltage levels for the applicable year, based on prudence check of the

submissions of the Distribution Licensee during their Tariff determination process and shall be

apportioned in proportion to the actual energy drawl by the Open Access consumers and shall be

payable in kind at relevant voltage level.

Applicability: This loss is applicable to generating stations, captive generating plants and consumers

who are connected to Discom network i.e., at 11 and 33 kV.

3. Transmission Charges or STU Charges

Transmission charges are those charges which are paid to transmission licensee for the use of

transmission system and associated facilities by another person for the conveyance of electricity.

Page 36: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

23

Applicability: These charges are applicable to generating stations, captive generating plants and

consumers who are connected to state transmission network i.e., at 66 or 132 kV and Discom

network i.e., at 11 and 33 kV.

4. Transmission Loss or STU Loss

Transmission losses are those losses which are there in the transmission system. The buyers and

sellers shall absorb apportioned energy losses in the transmission system in accordance with the

provisions specified by the Central Commission.

Applicability: This loss is applicable to generating stations, captive generating plants and consumers

who are connected to state transmission network i.e., at 66 or 132 kV and Discom network i.e., at 11

and 33 kV.

5. PoC Charge & PoC Losses

It is a transmission charge pricing methodology introduced for sharing of Inter State Transmission

Systems (ISTS) charges and Losses among the Designated ISTS Customers (DICs) depending on

their location and sensitive to their distances from load centres (generators) and generation

(customers) and the direction of the node in the grid.

Applicability: This charges and losses are applicable to generating stations, captive generating plants

and consumers who are connected to central transmission network or to state transmission network

i.e., at 66 or 132 kV and Discom network i.e., at 11 and 33 kV.

6. Cross Subsidy Surcharge

If open access facility is availed of by a subsidising consumer of a distribution licensee of the State,

then such consumer, in addition to transmission and/or wheeling charges, shall pay cross subsidy

surcharge determined by the Commission. Cross subsidy surcharge determined on Per Unit basis

shall be payable, on monthly basis, by the open access customers based on the actual energy drawn

during the month through open access. The amount of surcharge shall be paid to the distribution

licensee of the area of supply from whom the consumer was availing supply before seeking open

access.

Applicability: This charge is paid by open access consumers irrespective of voltage or connectivity

level.

Page 37: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

24

Cross Subsidy Mechanism as per NTP

S = T - [C (1+ L / 100) + D], Where,

O S is the surcharge

O T is the Tariff payable by the relevant category of consumers;

o C is the weighted average cost of power purchase of top 5% at the margin excluding

renewable power and liquid fuel based generation

O D is the Wheeling charge

o L is the system loss for the applicable voltage level, expressed as a %age

7. Application Fees

A person seeking Open Access shall make an application in the prescribed format to the Distribution

Licensee to which it is connected. The application fees in general for short term open access

consumer is ` 5000/application.

8. SLDC Charge

A composite operating charge @ ` 2, 000/- per day in general or part of the day shall be payable by a

short-term open access customer for each transaction to the SLDC or as determined by the

Commission from time to time. The operating charge includes fee for scheduling and system

operation, energy accounting, fee for affecting revisions in schedule on bonafide grounds and

collection and disbursement of charges.

Applicability: This charge is payable to both injecting and drawing SLDC.

9. RLDC Charge

A composite operating charge @ ` 2,000/day/RLDC is payable by a short-term open access customer

for each transaction to the RLDC or as determined by the Commission from time to time.

10. Other Charges

In addition to above mentioned charges there are some other charges which have a very small impact

on the final landed cost of electricity through open access, these charges are:

Page 38: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

25

1. NLDC Application Fees: ` 5000/ (No. of Successful bidders), applicable for power

exchange transactions.

2. NLDC Scheduling and Operating Charges: ` 5,000.00 x (Regional Entity Buyers +

Regional Entity Sellers) / (No. of Successful Portfolios), applicable for power exchange

transactions.

3. Trading Margin: trading margin exceeding seven (7.0) paisa/kWh in case the sale price is

exceeding Rupees three (3.0)/kWh and four (4.0) paisa/kWh where the sale price is less than

or equal to Rupees three (3.0)/kWh.

4. Exchange Charges: Rs 20/Mwh, applicable for power exchange transactions.

5. Service Tax: 12.36% of Exchange Charges (`/Mwh), applicable for power exchange

transactions.

3.9 Unscheduled Interchange Charges (UI Charges)

The mismatch between the scheduled and the actual drawl/ scheduled and the actual injection

at the interface points may be met from the grid, which shall be governed by UI pricing

mechanism.

Unless specified otherwise by the State Commission concerned, the UI rate for intra-State

entity shall be 105% (for over-drawls or under generation) and 95% (for under-drawls or over

generation) of the UI rate at the periphery of regional entity.

Table 3- UI Rates for Average Frequency of Time Block (Hz)

Each 0.02 Hz step is equivalent to 16.50 Paisa/KWh in 50.2-50.00 Hz frequency range, 28.50

Paisa/KWh in 50 Hz to 49.80 Hz and 28.12 Paisa/KWh in frequency in the below 49.8 Hz to 49.5 Hz

range.

Page 39: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

26

Chapter 4: COST BENEFIT ANALYSIS for Intra State OA

Open access allows large users of power — typically having connected load of 1 megawatt

(MW) and above — to buy cheaper power from the open market. The idea is that the

customers should be able to choose among a large number of competing power companies–

instead of being forced to buy electricity from their existing electric utility monopoly. It helps

large consumers particularly the sick textile, cement and steel industrial units by ensuring

regular supply of electricity at competitive rates and boost business of power bourses.

THE ELECTRICITY Act 2003 is a landmark legislation in that it opens the power sector to

a number of players by laying down provisions for a power market and competition. As per

Electricity Act 2003 Open Access is

“Non-discriminatory provision for the use of transmission lines or distribution system or

associated facilities with such lines or system by any licensee or consumer or a person

engaged in generation in accordance with the regulations specified by the Appropriate

Commission”.

4.1 Assumptions

Voltage at Generation End – Injection Point 132 kV

Voltage at Consumer End – Drawl Point 132 kV, 33 kV, 11kV and LT

Open Access load 5 MW

Load Factor 80% (CERC Guidelines)

Nature of Open Access Short Term (1 month)

Charges and Losses Considered as per respective SERC’s

tariff orders for the year 2013-14.

Cost of Generation APPC method

Usage (Time of Day) Uniform throughout the day

Type of Consumer Industrial Consumer

Table 4- Assumptions for OA analysis

Page 40: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

27

The format used by MERC for calculation of OA charges has been considered for the ease of

analysis.

4.2 Selection of States for Intra State OA

The states were selected on the basis of their provisions for Open Access. OA has been

granted in these states in all formats viz LTOA , MTOA and STOA. The guidelines are

issued by their respective ERCs and SLDCs are responsible for congestion management in

case of Intra State OA. The detailed procedure for OA has been set by CERC which is

followed by every state.

The states with high potential for OA are being considered for Cost Benefit Analysis which

would clearly reflect benefits that an Industrial Consumer would get by getting electricity

through OA when compared with Grid Power i.e. through Discom. Various charges

applicable are considered for the analysis based on the tariff orders issued by the respective

SERCs for the particular state.

Punjab – Northern Region

Gujarat - Western Region

Uttar Pradesh – Northern Region

Maharashtra – Western Region

Andhra Pradesh – Southern Region

4.3 Punjab

PSPCL – Punjab State Power Corporation Limited

PSERC – Punjab State Electricity Regulatory Commission

PSTCL – Punjab State Transmission Corporation Limited

Open Access office under Chief Engineer/SLDC, PSTCL, and Patiala is a nodal agency in

state power utilities for grant of short term open access to all eligible customers & consumers

of PSPCL. Open Access is being granted in discriminatorily by PSTCL to all the eligible

open access customers embedded in Transmission and Distribution system of PSTCL &

PSPCL as per provisions of Electricity Act-2003 and Open Access Regulations issued by

Punjab State Electricity Regulatory Commission (PSERC) and Central Electricity Regulatory

Page 41: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

28

Commission (CERC) from time to time. Presently Open Access for interstate sale of power

has been granted to three embedded power plants for third party sale of power through power

exchange/bi-lateral agreements. (Total 59.8 MW approx.)

Open Access has already been granted to 316 no. Large supply consumers of PSPCL

(Powercom) for purchase of power through power exchange. (Total 1360 MW approx.) 293

no. consumers are presently purchasing power through power exchange as per their

requirement against a total permission of purchase granted for 1287 MW. Open Access

office also deals with the energy accounting of UI based energy of Open Access customers

and reactive energy accounts and records are maintained for UI, reactive energy and

assessment of open access charges.

There are 373 OA consumers in Punjab with a combined load of 1569.26 MW.

No. of OA

customers

132 KV 66KV 33 KV 11 KV

5 104 3 261 373

No. of OA

customers

CBC Ludhiana CBC Jalandhar CBC Patiala CBC Bathinda

283 35 32 23 373

Table 5- OA consumers in Punjab

4.3.1 Charges applicable

The Tariff Order for the year 2013-14 is issued by PSERC based on the ARR petition filed by

PSPCL and PSTCL, in exercise of powers vested in it under EA‘03.

Injection Point – 132 kV

Table 6- PSPCL analysis

Parameter Case 1 Case 2 Case 3

Drawl Point 132 kV 33kV 11kV

Energy Injected (MUs) 2.88 2.88 2.88

Cost of Generation ` 3.67 ` 3.67 ` 3.67

Transmission Losses 2.50 % 2.50 % 2.50 %

Transmission Charge ` 0.27 / unit ` 0.27 / unit ` 0.27 / unit

Wheeling Losses N.A. 4.76% 8.53%

Wheeling Charges N.A. ` 1.19 / unit ` 1.19 / unit

Cross Subsidy Surcharge ` 1.14/unit ` 1.14/unit ` 1.14/unit

Additional Surcharge N.A. N.A. N.A.

Effective Rate ` 5.18 / unit ` 6.57 / unit ` 6.75 / unit Tariff through Discom ` 6.38/unit ` 6.38 / unit ` 6.38 / unit Cost Benefit ` 1.2/ unit ` - 0.19/ unit ` - 0.37/ unit

Page 42: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

29

4.4 Gujarat

GERC– Gujarat Electricity Regulatory Commission

GETCO – Gujarat Energy Transmission Corporation Limited (Transco)

UGVCL – Uttar Gujarat Vij Company Ltd.

MGVCL–Madhya Gujarat Vij Company Ltd.

PGVCL – Paschim Gujarat Vij Company Ltd.

DGVCL – Dakshin Gujarat Vij Company Ltd.

Torrent Power - Ahmedabad

The GERC notified MYT Regulations 2011 on 22nd

March, 2011. All Discoms submitted the

True up of FY 2011-12 and calculation of revenue estimates for FY 2013-14.

STOA consumers in Gujarat for the month of August, 2013 are:

No.of

STOA

consumers

UGVCL PGVCL MGVCL DGVCL Torrent Total

63 92 40 97 29 321

Table 7- STOA in Gujarat

STOA consumers connection

network

STU Discom

118 203 Table 8- STOA network in Gujarat

MTOA consumers in Gujarat as in August, 2013 are:

MTOA consumers

connection network

STU Discom

14 1 (MGVCL) Table 9- MTOA in Gujarat

Page 43: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

30

4.4.1 Charges Applicable

4.4.1.1 UGVCL – Uttar Gujarat Vij Corporation Limited

Injection Point – 132 kV

Table 10: UGVCL Analysis

Parameter Case 1 Case 2 Case 3

Drawl Point 132 kV 11 kV LT

Energy Injected (MUs) 2.88 2.88 2.88

Cost of Generation ` 4.49 ` 4.49 ` 4.49

Transmission Losses 4.81 % 4.81 % 4.81%

Transmission Charge ` 0.13 / unit ` 0.13 / unit ` 0.13 / unit

Wheeling Losses N.A. 10 % 10.82 %

Wheeling Charges N.A. ` 0.3 / unit ` 1.15 / unit

Cross Subsidy Surcharge ` 0.45 /unit ` 0.45 /unit ` 0.45 /unit

Additional Surcharge N.A. N.A. N.A.

Effective Rate ` 5.35 / unit ` 6.01 / unit ` 6.37 / unit

Tariff through Discom ` 5.27/unit ` 5.27 / unit ` 5.27 / unit Time of use Charges ` 0.25 / unit ` 0.25 / unit ` 0 / unit

Final Tariff ` 5.52 / unit ` 5.52 / unit ` 5.27 / unit

Cost Benefit ` 0.17/ unit ` - 0.49/ unit ` - 1.1/ unit

4.4.1.2 PGVCL – Paschim Gujarat Vij Corporation Limited

Injection Point – 132 kV

Table 11: PGVCL Analysis

Parameter Case 1 Case 2 Case 3

Drawl Point 132 kV 11 kV LT

Energy Injected (MUs) 2.88 2.88 2.88

Cost of Generation ` 4.54 ` 4.54 ` 4.54

Transmission Losses 4.81 % 4.81 % 4.81%

Transmission Charge ` 0.13 / unit ` 0.13 / unit ` 0.13 / unit

Wheeling Losses N.A. 10 % 10.82 %

Wheeling Charges N.A. ` 0.3 / unit ` 1.15 / unit

Cross Subsidy Surcharge ` 0.45 /unit ` 0.45 /unit ` 0.45 /unit

Additional Surcharge N.A. N.A. N.A.

Effective Rate ` 5.35 / unit ` 6.01 / unit ` 6.37 / unit Tariff through Discom ` 5.48/unit ` 5.48 / unit ` 5.48 / unit Time of use Charges ` 0.25 / unit ` 0.25 / unit ` 0 / unit

Final Tariff ` 5.73 / unit ` 5.73 / unit ` 5.48 / unit

Cost Benefit ` 0.38/ unit ` - 0.28/ unit ` - 0.89/ unit

Page 44: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

31

4.4.1.3 MGVC L – Madhya Gujarat Vij Corporation Limited

Injection Point – 132 kV

Table 12: MGVCL Analysis

Parameter Case 1 Case 2 Case 3

Drawl Point 132 kV 11 kV LT

Energy Injected (MUs) 2.88 2.88 2.88

Cost of Generation ` 4.54 ` 4.54 ` 4.54

Transmission Losses 4.81 % 4.81 % 4.81%

Transmission Charge ` 0.13 / unit ` 0.13 / unit ` 0.13 / unit

Wheeling Losses N.A. 10 % 10.82 %

Wheeling Charges N.A. ` 0.3 / unit ` 1.15 / unit

Cross Subsidy Surcharge ` 0.45 /unit ` 0.45 /unit ` 0.45 /unit

Additional Surcharge N.A. N.A. N.A.

Effective Rate ` 5.35 / unit ` 6.01 / unit ` 6.37 / unit Tariff through Discom ` 5.67/unit ` 5.67/unit ` 5.67/unit

Time of use Charges ` 0.25 / unit ` 0.25 / unit ` 0 / unit

Final Tariff ` 5.92 / unit ` 5.92 / unit ` 5.67 / unit

Cost Benefit ` 0.57/ unit ` - 0.09/ unit ` - 0.7/ unit

4.4.1.4 DGVC L – Dakshin Gujarat Vij Corporation Limited

Injection Point – 132 kV

Table 13: DGVCL Analysis

Parameter Case 1 Case 2 Case 3

Drawl Point 132 kV 11 kV LT

Energy Injected (MUs) 2.88 2.88 2.88

Cost of Generation ` 4.54 ` 4.54 ` 4.54

Transmission Losses 4.81 % 4.81 % 4.81%

Transmission Charge ` 0.13 / unit ` 0.13 / unit ` 0.13 / unit

Wheeling Losses N.A. 10 % 10.82 %

Wheeling Charges N.A. ` 0.3 / unit ` 1.15 / unit

Cross Subsidy Surcharge ` 0.45 /unit ` 0.45 /unit ` 0.45 /unit

Additional Surcharge N.A. N.A. N.A.

Effective Rate ` 5.35 / unit ` 6.01 / unit ` 6.37 / unit

Tariff through Discom ` 5.86/unit ` 5.86/unit ` 5.86/unit

Time of use Charges ` 0.25 / unit ` 0.25 / unit ` 0 / unit

Final Tariff ` 6.11 / unit ` 6.11 / unit ` 5.86 / unit

Cost Benefit ` 0.76/ unit ` 0.10/ unit ` - 0.51/ unit

Page 45: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

32

4.4.1.5 Torrent Power - Ahmedabad

Injection Point – 132 kV

Parameter Case 1 Case 2 Case 3

Drawl Point 132 kV 11 kV LT

Energy Injected (MUs) 2.88 2.88 2.88

Cost of Generation ` 4.49 ` 4.49 ` 4.49

Transmission Losses 4.81 % 4.81 % 4.81%

Transmission Charge ` 0.13 / unit ` 0.13 / unit ` 0.13 / unit

Wheeling Losses N.A. 3 % 3 %

Wheeling Charges N.A. ` 0.28 / unit ` 0.28 / unit

Cross Subsidy Surcharge ` 0.29 /unit ` 0.29 /unit ` 0.29 /unit

Additional Surcharge N.A. N.A. N.A.

Effective Rate ` 5.14 / unit ` 5.57 / unit ` 5.57 / unit Tariff through Discom ` 6.39 /unit ` 6.39 /unit ` 4.39 /unit

Time of use Charges ` 0.25 / unit ` 0.25 / unit ` 0 / unit

Final Tariff ` 6.64 /unit ` 6.64 /unit ` 4.39 /unit

Cost Benefit ` 1.50/ unit ` 1.07/ unit ` - 1.18 / unit

Table 14: Torrent Power Analysis

4.5 Uttar Pradesh

The Electricity structure in UP is governed by Regulatory commission along with Discoms.

UPERC (Uttar Pradesh Electricity Regulatory Commission)

PVVNL ( Paschimanchal Vidyut Vitran Nigam Limited) – Meerut Discom

PuVVNL (Purvanchal Vidyut Vitran Nigam Limited) – Varanasi Discom

MVVNL ( Madhyanchal Vidyut Vitran Nigam Limited) – Lucknow Discom

DVVNL ( Dakshinanchal Vidyut Vitran Nigam Limited) – Agra Discom

KESCoL (Kanpur Electricity Supply Company Limited) – Kanpur Discom

NPCL ( Noida Power Company Limited) – Noida Discom

The Commission has issued UPERC Open Access Regulation, 2004 to operationalize long

term and short term OA in the state. The regulations also provide that effective from April 1,

2008 any consumer with demand above 1 MW can avail OA of T&D systems.

There was no authentic data available for OA consumers in the state. According to IEX

source there were no industrial participants for OA at IEX.

Page 46: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

33

4.5.1. PuVVNL - Purvanchal Vidyut Vitran Nigam Limited

Injection Point – 132 kV

Parameter Case 1 Case 2 Case 3

Drawl Point 132 kV > 11 kV 11 kV

Energy Injected (MUs) 2.88 2.88 2.88

Cost of Generation ` 3.56 ` 3.56 ` 3.56

Transmission Losses 3.67 % 3.67 % 3.67 %

Transmission Charge ` 0.034 / unit ` 0.034 / unit ` 0.034 / unit

Wheeling Losses N.A. 7 % 8 %

Wheeling Charges N.A. ` 0.078 / unit ` 0.124 / unit

Cross Subsidy Surcharge Nil Nil Nil

Additional Surcharge N.A. N.A. N.A.

Effective Rate ` 3.73 / unit ` 4.09 / unit ` 4.18 / unit Tariff through Discom ` 6.05/unit ` 6.05/unit ` 6.16 unit Cost Benefit ` 2.32/ unit ` 1.96/ unit ` 1.98/ unit

Table 15: PuVVNL Analysis

4.5.2 MVVNL - Madhyanchal Vidyut Vitran Nigam Limited

Injection Point – 132 kV

Table 16: MVVNL Analysis

Parameter Case 1 Case 2 Case 3

Drawl Point 132 kV > 11 kV 11 kV

Energy Injected (MUs) 2.88 2.88 2.88

Cost of Generation ` 3.56 ` 3.56 ` 3.56

Transmission Losses 3.67 % 3.67 % 3.67 %

Transmission Charge ` 0.034 / unit ` 0.034 / unit ` 0.034 / unit

Wheeling Losses N.A. 7 % 8 %

Wheeling Charges N.A. ` 0.078 / unit ` 0.124 / unit

Cross Subsidy Surcharge Nil Nil Nil

Additional Surcharge N.A. N.A. N.A.

Effective Rate ` 3.73 / unit ` 4.09 / unit ` 4.18 / unit Tariff through Discom ` 6.05/unit ` 6.05/unit ` 6.16 unit Cost Benefit ` 2.32/ unit ` 1.96/ unit ` 1.98/ unit

Page 47: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

34

4.5.3 PVVNL - Paschimanchal Vidyut Vitran Nigam Limited

Injection Point – 132 kV

Parameter Case 1 Case 2 Case 3

Drawl Point 132 kV > 11 kV 11 kV

Energy Injected (MUs) 2.88 2.88 2.88

Cost of Generation ` 3.56 ` 3.56 ` 3.56

Transmission Losses 3.67 % 3.67 % 3.67 %

Transmission Charge ` 0.034 / unit ` 0.034 / unit ` 0.034 / unit

Wheeling Losses N.A. 7 % 8 %

Wheeling Charges N.A. ` 0.078 / unit ` 0.124 / unit

Cross Subsidy Surcharge Nil Nil Nil

Additional Surcharge N.A. N.A. N.A.

Effective Rate ` 3.73 / unit ` 4.09 / unit ` 4.18 / unit

Tariff through Discom ` 6.05/unit ` 6.05/unit ` 6.16 unit Cost Benefit ` 2.32/ unit ` 1.96/ unit ` 1.98/ unit

Table 17: PVVNL Analysis

4.5.4 DVVNL - Dakshinanchal Vidyut Vitran Nigam Limited

Injection Point – 132 kV

Table 18: DVVNL Analysis

Parameter Case 1 Case 2 Case 3

Drawl Point 132 kV > 11 kV 11 kV

Energy Injected (MUs) 2.88 2.88 2.88

Cost of Generation ` 3.56 ` 3.56 ` 3.56

Transmission Losses 3.67 % 3.67 % 3.67 %

Transmission Charge ` 0.034 / unit ` 0.034 / unit ` 0.034 / unit

Wheeling Losses N.A. 7 % 8 %

Wheeling Charges N.A. ` 0.078 / unit ` 0.124 / unit

Cross Subsidy Surcharge Nil Nil Nil

Additional Surcharge N.A. N.A. N.A.

Effective Rate ` 3.73 / unit ` 4.09 / unit ` 4.18 / unit Tariff through Discom ` 6.05/unit ` 6.05/unit ` 6.16 unit

Cost Benefit ` 2.32/ unit ` 1.96/ unit ` 1.98/ unit

Page 48: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

35

4.5.5 KESCoL - Kanpur Electricity Supply Company Limited

Injection Point – 132 kV

Parameter Case 1 Case 2 Case 3

Drawl Point 132 kV > 11 kV 11 kV

Energy Injected (MUs) 2.88 2.88 2.88

Cost of Generation ` 3.56 ` 3.56 ` 3.56

Transmission Losses 3.67 % 3.67 % 3.67 %

Transmission Charge ` 0.034 / unit ` 0.034 / unit ` 0.034 / unit

Wheeling Losses N.A. 7 % 8 %

Wheeling Charges N.A. ` 0.078 / unit ` 0.124 / unit

Cross Subsidy Surcharge Nil Nil Nil

Additional Surcharge N.A. N.A. N.A.

Effective Rate ` 3.73 / unit ` 4.09 / unit ` 4.18 / unit

Tariff through Discom ` 6.05/unit ` 6.05/unit ` 6.16 unit Cost Benefit ` 2.32/ unit ` 1.96/ unit ` 1.98/ unit

Table 19: KESCoL Analysis

4.5.6 NPCL - Noida Power Company Limited

Injection Point – 132 kV

Table 20: NPCL Analysis

Parameter Case 1 Case 2 Case 3

Drawl Point 132 kV > 11 kV 11 kV

Energy Injected (MUs) 2.88 2.88 2.88

Cost of Generation ` 3.56 ` 3.56 ` 3.56

Transmission Losses 3.67 % 3.67 % 3.67 %

Transmission Charge ` 0.034 / unit ` 0.034 / unit ` 0.034 / unit

Wheeling Losses N.A. 2 % 3 %

Wheeling Charges N.A. ` 0.08 / unit ` 0.13 / unit

Cross Subsidy Surcharge Nil Nil Nil

Additional Surcharge N.A. N.A. N.A.

Effective Rate ` 3.73 / unit ` 3.90 / unit ` 3.97 / unit

Tariff through Discom ` 6.05/unit ` 6.05/unit ` 6.16 unit

Cost Benefit ` 2.32/ unit ` 2.15/ unit ` 2.19/ unit

Page 49: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

36

4.6 Maharashtra

In Maharashtra, OA started in 2005 with the guideline of MERC‘s regulations 2005. In

Maharashtra, there are four Discoms namely:

Maharashtra State Electricity Distribution Co. limited (MSEDCL) (Except for

Mumbai, Rest of Maharashtra)

Tata Power (Mumbai Region)

Reliance Power – RinfraD (Mumbai Region)

Brihanmumbai Electric Supply & Transport (BEST) (Mumbai Region)

There are 87 STOA consumers in the state as of Jul, 2013 with major consumers being

CPP/IPP consumers.

4.6.1 MSEDCL

Injection Point – 132 kV

Parameter Case 1 Case 2 Case 3 Case 4

Drawl Point 132 kV 33 kV 11 kV LT

Energy Injected

(MUs)

2.88 2.88 2.88 2.88

Cost of Generation ` 4.48 ` 4.48 ` 4.48 ` 4.48

Transmission Losses 4.19 % 4.19 % 4.19 % 4.19 %

Transmission

Charge

` 0.43 / unit ` 0.43 / unit ` 0.43 / unit ` 0.43 / unit

Wheeling Losses N.A. 6 % 9 % 12.50 %

Wheeling Charges N.A. ` 0.11 / unit ` 0.60 / unit ` 1.03 / unit

Cross Subsidy

Surcharge

` 1.20 / unit ` 0.76 / unit ` 0.10 / unit ` 0.73 / unit

Additional

Surcharge

N.A. N.A. N.A. N.A.

Effective Rate ` 6.31 / unit ` 6.31 / unit ` 6.32 / unit ` 7.60 / unit

Tariff through

Discom

` 7.43/unit ` 7.43/unit ` 7.43/unit ` 7.04 / unit

Time of use Charges ` -0.08 / unit ` -0.08 / unit ` -0.08 / unit ` -0.08 /unit Final Tariff ` 7.35 / unit ` 7.35/ unit ` 7.35 / unit ` 6.96 / unit Cost Benefit ` 1.04/ unit ` 1.04/ unit ` 1.03/ unit `-0.64/unit

Table 21: MSEDCL Analysis

Page 50: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

37

4.6.2 R-Infra D

Injection Point – 132 kV

Parameter Case 1 Case 2 Case 3 Case 4

Drawl Point 132 kV 33 kV 11 kV LT

Energy Injected (MUs) 2.88 2.88 2.88 2.88

Cost of Generation ` 4.48 ` 4.48 ` 4.48 ` 4.48

Transmission Losses 4.19 % 4.19 % 4.19 % 4.19 %

Transmission Charge ` 0.43 / unit ` 0.43 / unit ` 0.43 / unit ` 0.43 / unit

Wheeling Losses N.A. 1.94 % 1.94 % 9%

Wheeling Charges N.A. ` 0.76 / unit ` 0.76 / unit ` 1.46 / unit

Cross Subsidy

Surcharge

` 2.36 / unit ` 1.80 / unit ` 1.80 / unit ` 1.00 / unit

Additional Surcharge N.A. N.A. N.A. N.A.

Effective Rate ` 7.47 / unit ` 7.77 / unit ` 7.77 / unit ` 8.08 / unit Tariff through Discom ` 7.60/unit ` 7.60/unit ` 7.60/unit ` 7.58 / unit Time of use Charges ` -0.50 / unit ` -0.50 / unit ` -0.50 / unit ` -0.50 /unit

Final Tariff ` 7.10 / unit ` 7.10 / unit ` 7.10 / unit ` 6.94 / unit Cost Benefit ` -0.37/ unit ` - 0.67/ unit ` -0.67/ unit `-1.14/unit

Table 22: Rinfra Analysis

4.6.3 Tata Power: TPC-D

Injection Point – 132 kV

Table 23: TPC Analysis

Parameter Case 1 Case 2 Case 3 Case 4

Drawl Point 132 kV 33 kV 11 kV LT

Energy Injected (MUs) 2.88 2.88 2.88 2.88

Cost of Generation ` 4.48 ` 4.48 ` 4.48 ` 4.48

Transmission Losses 4.19 % 4.19 % 4.19 % 4.19 %

Transmission Charge ` 0.43 / unit ` 0.43 / unit ` 0.43 / unit ` 0.43 / unit

Wheeling Losses N.A. 1.12 % 1.12 % 1.12%

Wheeling Charges N.A. ` 0.89 / unit ` 0.89/ unit ` 1.87 / unit

Cross Subsidy Surcharge Nil Nil Nil Nil

Additional Surcharge N.A. N.A. N.A. N.A.

Effective Rate ` 5.11 / unit ` 6.06 / unit ` 6.06 / unit ` 7.04 / unit Tariff through Discom ` 6.24/unit ` 6.24/unit ` 6.24/unit ` 5.56 / unit

Time of use Charges ` -0.50 / unit ` -0.50 / unit ` -0.50 / unit ` -0.50 /unit Final Tariff ` 5.74 / unit ` 5.74 / unit ` 5.74 / unit ` 5.06 / unit

Cost Benefit ` 0.63/ unit ` - 0.32/ unit ` -0.32/ unit `-1.98/unit

Page 51: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

38

4.7 Andhra Pradesh

The APERC notified MYT Regulations 2009 and is following the same for the 5th

control

period, 2013-14. All Discoms submitted the True up of FY 2011-12 and calculation of

revenue estimates for FY 2013-14, there are four Discoms namely:

NPDCL - Northern Power Distribution Company of AP Limited

SPDCL - Southern Power Distribution Company of AP Limited

EPDCL - Eastern Power Distribution Company of AP Limited

SPDCL - Southern Power Distribution Company of AP Limited

There is no official data available on the number of OA consumers in the state.

4.7.1 NPDCL

Injection Point – 132 kV

Parameter Case 1 Case 2 Case 3 Case 4

Drawl Point 132 kV 33 kV 11 kV LT

Energy Injected

(MUs)

2.88 2.88 2.88 2.88

Cost of Generation ` 3.60 ` 3.60 ` 3.60 ` 3.60

Transmission Losses 4.02 % 4.02 % 4.02 % 4.02 %

Transmission

Charge

` 0.08 / unit ` 0.08 / unit ` 0.08 / unit ` 0.08 / unit

Wheeling Losses N.A. 3.90 % 8.08 % 13.14%

Wheeling Charges N.A. ` 0.046 / unit ` 0.50/ unit ` 1.15 / unit

Cross Subsidy

Surcharge

Nil Nil Nil Nil

Additional

Surcharge

N.A. N.A. N.A. N.A.

Effective Rate ` 3.84 / unit ` 4.01 / unit ` 4.37 / unit ` 4.90 / unit

Tariff through

Discom

` 5.04/unit ` 5.44/unit ` 5.87/unit ` 6.18 / unit

Cost Benefit ` 1.20/ unit ` 1.43/ unit ` 1.50/ unit ` 1.28/unit Table 24: NPDCL Analysis

Page 52: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

39

4.7.2 SPDCL

Injection Point – 132 kV

Parameter Case 1 Case 2 Case 3 Case 4

Drawl Point 132 kV 33 kV 11 kV LT

Energy Injected (MUs) 2.88 2.88 2.88 2.88

Cost of Generation ` 3.79 ` 3.79 ` 3.79 ` 3.79

Transmission Losses 4.02 % 4.02 % 4.02 % 4.02 %

Transmission Charge ` 0.08 / unit ` 0.08 / unit ` 0.08 / unit ` 0.08 / unit

Wheeling Losses N.A. 3.40 % 7.51 % 12.22%

Wheeling Charges N.A. ` 0.10 / unit ` 0.64/ unit ` 1.22 / unit

Cross Subsidy

Surcharge

Nil Nil Nil Nil

Additional Surcharge N.A. N.A. N.A. N.A.

Effective Rate ` 4.04 / unit ` 4.22 / unit ` 4.62 / unit ` 5.11 / unit Tariff through Discom ` 5.04/unit ` 5.44/unit ` 5.87/unit ` 6.18 / unit Cost Benefit ` 1.00/ unit ` 1.22/ unit ` 1.25/ unit ` 1.07/unit

Table 25: SPDCL Analysis

4.7.3 EPDCL

Injection Point – 132 kV

Table 26: EPDCL Analysis

Parameter Case 1 Case 2 Case 3 Case 4

Drawl Point 132 kV 33 kV 11 kV LT

Energy Injected

(MUs)

2.88 2.88 2.88 2.88

Cost of Generation ` 3.75 ` 3.75 ` 3.75 ` 3.75

Transmission Losses 4.02 % 4.02 % 4.02 % 4.02 %

Transmission

Charge

` 0.08 / unit ` 0.08 / unit ` 0.08 / unit ` 0.08 / unit

Wheeling Losses N.A. 3.39 % 7.47 % 12.10%

Wheeling Charges N.A. ` 0.03 / unit ` 0.27/ unit ` 0.91 / unit

Cross Subsidy

Surcharge

Nil Nil Nil Nil

Additional

Surcharge

N.A. N.A. N.A. N.A.

Effective Rate ` 4.00 / unit ` 4.17 / unit ` 4.59 / unit ` 5.46 / unit Tariff through

Discom

` 5.04/unit ` 5.44/unit ` 5.87/unit ` 6.18 / unit

Cost Benefit ` 1.04/ unit ` 1.27/ unit ` 1.28/ unit ` 0.72/unit

Page 53: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

40

4.7.4 CPDCL

Injection Point – 132 kV

Parameter Case 1 Case 2 Case 3 Case 4

Drawl Point 132 kV 33 kV 11 kV LT

Energy Injected

(MUs)

2.88 2.88 2.88 2.88

Cost of Generation ` 3.74 ` 3.74 ` 3.74 ` 3.74

Transmission Losses 4.02 % 4.02 % 4.02 % 4.02 %

Transmission

Charge

` 0.08 / unit ` 0.08 / unit ` 0.08 / unit ` 0.08 / unit

Wheeling Losses N.A. 3.96 % 7.80 % 12.50%

Wheeling Charges N.A. ` 0.04 / unit ` 0.28/ unit ` 0.90 / unit

Cross Subsidy

Surcharge

Nil Nil Nil Nil

Additional

Surcharge

N.A. N.A. N.A. N.A.

Effective Rate ` 3.99 / unit ` 4.20 / unit ` 4.61 / unit ` 5.46 / unit Tariff through

Discom

` 5.04/unit ` 5.44/unit ` 5.87/unit ` 6.18 / unit

Cost Benefit ` 1.05/ unit ` 1.24/ unit ` 1.26/ unit ` 0.72/unit Table 27: CPDCL Analysis

Page 54: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

41

4.8 Analysis for the States (Intra State OA)

4.8.1. Punjab

The Electricity Distribution system in Punjab vests with PSPCL. In the case with load of

5MW for STOA industrial consumers, with current power crisis in the state, it is highly

preferable for Industrial Consumers connected to Discom network to shift for Open Access in

Punjab at 132 kV network. For better and reliable power supply, Industrial Consumers

connected at 33kV and 11kV network can also shift for OA provided their willingness to

accommodate higher tariff rates compared with Discom.

The CSS component is levied on all consumers which help PSPCL in reducing losses caused

by consumers moving towards OA. Drawing power at 132kV at STU network helps the

consumers and making substantial gain through OA with savings of almost 18 % (` 1.2)

every unit purchased when compared with PSPCL network. While consumers connected to

33kV or 11kV has to use Discom network and thus liable to pay wheeling charges which

makes it costlier than Discom network.

Thus Industrial consumers can switch to OA from existing network considering the amount

they have to pay for the new service provider. With recent tariff hike of almost 13% for

industrial consumers and considering TOD tariff brought into effect for Large industrial

consumers @ ` 1/unit for usage during off peak hours i.e. 10p.m. to 6 a.m., this would help

them bring down their cost and thus assure reliable and continuous power supply.

PSERC’s Initiatives

With 373 OA consumers, Punjab is one of the leading states in terms of implementing the

OA mechanism. The volume of electricity transacted through OA increased considerably

between 2009-10 and 2011-12 from 131 MUs to 2,512 MUs. With introduction of CSS,

power traded through OA during 2012-13 declined significantly to 1,881 MUs. For 2013-14,

the CSS notified by the commission for various consumer categories are - ` 1.07 per unit for

large supply, ` 1 per unit for domestic supply and ` 1.14 per unit for non residential supply.

In October 2012, PSERC opposed the Ministry of Power‘s directive of mandating OA for

industrial consumers with a connected load of 1MW and above. The regulator stated that the

Page 55: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

42

directive does not conform with the provisions of the EA 2003 as it overlaps with the

universal obligation of a distribution licensee to supply power under Section 43 with the

rights of a consumer, licensees or generators under Section 42.

4.8.2 Gujarat

The Electricity network in Gujarat is managed by five Discom, 4 of them are owned by

Government (UGVCL, MGVCL, PGVCL and DGVCL) while 1 is a private entity (Torrent

Power). The Average Power Purchase Cost (APPC) method is considered for computation of

effective rate of power supply through OA. Owning to low losses in the states, consumers get

reliable power supply. Transmission charges for using STU network have been kept at

minimal amount. CSS for the 4 Govt. owned Discom is kept high above `1 per unit owning

to increase in tariff rate for OA consumers. While for Torrent Power, Commission has fixed

combined component of Wheeling charge and CSS at ` 0.57 per unit, thus making CSS at `

0.29 per unit in the area.

Considering different voltage level at drawl point, getting supply through STU network at

132 kV proves out to be most economical with saving of varying per unit for the 4 discoms

while this has substantial gain in region of Torrent power with ` 1.50 per unit, thus

favouring usage of OA at this network. While for lower voltage network involving Discom

network, OA proves to be a costly affair owning to wheeling losses and charges in the

network. In case of Torrent Power, it still helps the industrial consumers at 11 kV network

with advantage of ` 1 per unit through OA when compared with Discom. At LT network,

OA for industrial consumers is not beneficial due to high difference in tariff when compared

with Discom tariff.

GERC initiatives

GERC notified OA regulations in 2005. State has implemented intra-state ABT w.e.f.

05.04.2010 which is pre-requisite for implementation of OA. Subsequently GERC OA

Regulation 2011 notified as per model regulation of FOR. Gujarat has also been providing

adequate infrastructure support to OA consumers in the state.

Page 56: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

43

4.8.3 Uttar Pradesh

Uttar Pradesh electricity network has 6 discoms which supplies power to the every corner of

the state. 5 of them are govt. owned, NPCL is a privately managed Discom. With no CSS

being introduced in the tariff order for 2013-14, the effective rate for OA has reduced

considerably. All the charges and losses have been kept same for all the govt. owned

discoms, it varies for NPCL. Considering Point of withdrawal to be 132kV, OA consumers

can save as much as ` 2.32 per unit which would help them in reducing their overall cost for

the purpose. While OA consumers using Discom network and operating at voltage greater

then 11 kV can also benefit from OA by saving almost equivalent amount of ` 1.96 per unit.

In case of OA at 11 kV, consumers are still benefitted with ` 1.98 per unit when compared

with local Discom network. The situation is advantageous in case of NPCL where an

industrial consumer saves ` 2.32 per unit at 132kV STU network, ` 2.15 per unit at Discom

network with voltage above 11kV and ` 2.19 per unit with 11kV network. These owes to low

transmission and wheeling charges & losses and also high tariff with discoms that help OA

consumers in getting better and reliable energy.

UPERC initiatives

UPERC was one of the first state regulators to notify them under the terms and conditions of

OA regulations in June 2005. Moreover, amendments to these regulations were released in

June 2009. As per the regulations, any consumer with a load of 1 MW and above with a

minimum connectivity level of 11kV can avail OA. The SLDC is designated as the nodal

agency for STOA. Despite the enabling legislative and regulatory provisions, applications for

OA are yet to be approved. In fact, the UPSLDC was established in January 2011, almost six

years after the notification of OA regulations. It is under resourced and therefore, carrying out

operations to a limited extent.

Page 57: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

44

4.8.4 Maharashtra

Maharashtra electricity distribution network is managed by four discoms, with MSEDCL

covering the major portion of the state. With Tata Power, Reliance Infra and BEST covering

the Mumbai region. All charges levied on the discoms are based on their ARR petition and

thus approval from MERC. Time of Day (TOD) usage is effectively implemented in the state

with provision for incentives for usage during the day. MERC implemented MYT regulations

and thus are followed in the second control period as well in 2013-14.

Considering the area under MSEDCL, OA consumers have significant advantage of using

OA over Discom power due to charges levied on the consumers in form of Wheeling and

CSS in the area and also high energy charges in Discom network. This helps OA consumers

using STU network at 132kV can save almost ` 1 per unit and also in case of network at

33kV and 11kV. While drawing power at LT is not favourable due to high cost through OA.

In case of Tata Power, there is No CSS being levied on the users which immensely helps the

OA consumers in reducing their tariff to be charged. While Energy charge in the region is

low, thus advantage of OA over Discom power is reduced. Connectivity at STU network

helps with a gain of ` 0.63 per unit for OA consumers, it is not advantageous at other voltage

levels. At LT level, Discom power is preferable as OA proves costly by almost ` 2 per unit.

In region of Reliance Infra, OA is not at all preferable due to high CSS and thus makes OA

power expensive with loss ranging from ` 0.37 per unit to ` 1.14 per unit w.r.t 132kV to LT

network. Thus, OA doesn‘t hold significant advantage in this region.

MERC initiatives

The Maharashtra state energy department‘s principal secretary Mr. Mehta has in a letter dated

31.07.2013, written to MERC (Maharashtra Electricity Regulatory Commission) asking the

regulator to review relevant policies/regulations in context of granting open-access, which

supposedly is impacting the tariff for low-end consumers of the state.

The govt. expressed its concern over the methodology and operationalization of open-access

regulations which as per the govt. is going to jeopardize the financial conditions of low-end

Page 58: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

45

consumers in state. The govt. has explicitly mentioned that it wants the chief regulator to

check the grants of OA through exchanges and that to renewable energy generators.

Power guzzlers may now be allowed to buy power directly from any other source, but they

cannot force their previous distribution utility to bail them out in case of non-availability of

power from the new supplier. This has been ruled by the Supreme Court in the special leave

petition moved by the state-owned power distribution company, Mahavitaran.

The utility had moved the Supreme Court after the Bombay high court refused to grant

interim relief to it against the Maharashtra Electricity Regulatory Commission‘s (MERC)

directive to allow open access — a procedure in which a consumer can buy power directly

from other supplier across the country by paying carrying charges to distribution and

transmission companies. At present, open access proposals of 500MW are pending for

approval before the MERC. Of this, Ispat Industries alone wants 300MW from a source other

than the state-owned power distribution company.

4.8.5. Andhra Pradesh

AP state Electricity distribution network vests with four Govt. owned Discom namely,

NPDCL, SPDCL, CPDCL and EPDCL responsible for northern, southern, central and eastern

region of the state respectively. The Commission issued Regulation 4 of 2005 on 14-11-2005

laying down terms and conditions for determination of tariff for Wheeling and Retail supply

of electricity. This regulation introduced Multi year Tariff (MYT) framework and

accordingly, each distribution licensee has to make the filings for ARR along with its

Proposals for Tariff (PFT) with the commission for determination of tariffs for (a) Wheeling

and (b) Retail supply of electricity for a period of 5 years (called Control Period). The second

control period covers the year 2009-10 to 2013-14. The Wheeling tariffs were determined for

the control period of 5 years, namely 2009 to 2014.

A big relief for OA consumers came through exemption from paying CSS till the next order

for the year 2013-14. In case of NPDCL, owning to CSS being waived off , the effective rate

at 132kV, directly through STU network costs ` 3.84 and saves ` 1.2 per unit at this voltage

level. While at 33kV, due to high energy charges, Discom power is costlier and thus with a

rate of ` 5.43, it gives clear advantage to OA consumers of ` 1.43 per unit. At 11kV network,

Page 59: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

46

this difference is widened and saves ` 1.50 per unit to OA consumers at this voltage. Even at

LT network, Discom power comes up at ` 6.18 per unit when compared OA power at ` 4.90,

thus giving away benefit of ` 1.28 per unit to OA consumers.

For OA consumers in SPDCL region, getting power at 132kV network directly helps them

save ` 1.00 per unit over grid power. At 33kV network, owning to energy charge, ` 1.22 per

unit advantage of OA can be seen over Discom. While at 11kV network, OA is still beneficial

with ` 1.25 per unit saving and at LT network, ` 1.07 per unit can be saved using OA.

In case of EPDCL, similar trend can be observed and in all four networks, OA is

advantageous over Discom power with savings of ` 1.04, ` 1.27, ` 1.28 and ` 0.72 per unit

at 132kV, 33kV, and 11kV and LT network respectively.

CPDCL is now far behind and this also supports OA over Discom. While getting power at

132kV network helps in saving ` 1.05 per unit, ` 1.24 per unit can be saved at 33kV

network. At 11kV network, OA power is cheaper as compared to Discom power by ` 1.26

per unit and at LT network, it is advantageous by ` 0.72 per unit over Discom.

APERC initiatives

CSS has been waived on OA transactions by the commission vide R&C order issued 01-11-

12. This has been done in view of R&C measures taken by the commission. All the Discom

are directed to take into account 90% of scheduled energy and corresponding demand ,

procured by the consumers through inter-state OA (bi-lateral or through exchange), for the

purpose of provisional monthly settlement for the sake of billed energy/demand from the

discoms ‘side. Even by the erratic power supply standards that Indian industry has had to bear

with for years, factories in Andhra Pradesh have had an unusually tough 2012. Power

shortages in the state had been acute for well over a year and a half, but in August last year,

the state government began implementing a "power holiday" for industrial consumers three

days a week. This has triggered demand for OA in the state thus providing them round the

clock power supply at an affordable cost.

Page 60: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

47

CHAPTER 5: ISSUES WITH OPEN ACCESS

5.1 Implementation of Open Access

The main issue in implementing the open access provision is the determination and phasing

out of the cross subsidy surcharge for open access. A related issue is the determination of the

license area for new distribution licensees.

5.1.1Determination of Cross Subsidy

All regulatory commissions provide for a cross-subsidy in tariffs. Cross-subsidy is usually

defined as ―The difference between the cost to serve and the tariff charged‖. Given the lack of adequate

data, even after several years of reform in many states, regulators have adopted relatively

unsophisticated methodologies for estimating cost of service. Most regulators use a uniform

average cost of supply and distribution for all categories of consumers.

The Andhra Pradesh regulator uses one of the most sophisticated methodologies to estimate

cost of service. Consumers are differentiated on the basis of different critical aspects of

electricity consumption such as voltage levels, time of consumption, patterns of usage,

number of consumers, etc. all costs are classified under three expense heads: energy, demand

and consumer.

Energy Consumption: This denotes the amount of energy consumed at a specified voltage

level. Voltage level determines the extent of T & D losses and the cost of equipment etc. to

provide power at a particular voltage level. The only element of cost under this category is

the variable cost of generation or power purchase

Demand: This represents the contribution of a consumer category towards the peak demand

on the system. In Andhra Pradesh, the system peak occurs between 6 pm and 9 pm. The two

categories that contribute most to this evening peak are domestic and commercial.

Customer: The servicing costs, such as the costs of the meter reading, billing and collection,

are influenced by the number of consumers in a category. Most other state regulators have used the average cost of supply to calculate cross-subsidies.

Cross-subsidy calculated in this manner will be lower than that obtained by using the cost of

Page 61: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

48

service model. For example, in the case of AP, using the average Fully Allocated Costs

(FAC) will the increase the gap from `1434 crores to ` 2718 crores.

The main problem with the cost of service estimation is the non-availability of reliable

consumer category wise consumption data. All agriculture consumption is unmetered. Some

proportion of other consumption is assessed because of non-existent or faulty meters. In some

states, rural domestic consumption is also charged at a flat rate with no incentive for accurate

metering. In Andhra Pradesh, where about 3.5 million new meters have been installed and

about 4 million defective meters replaced during the four years 2000-04, in one of the

DISCOMS almost 20% of the billed units were on assessed basis.

5.1.2 Phasing out of cross-subsidies

The Electricity Act requires the phasing out of cross-subsidy and the associated surcharge for

open access. So far regulators have taken an ad hoc approach to reduction in cross-subsidy,

with no specified time frame. Reduction in cross-subsidies can be achieved by increasing

subsidized tariffs, increasing efficiency and reducing distribution losses. Increasing tariffs for

subsidized categories is likely to be politically difficult. Increasing government subsidy is

constrained by the poor financial situation of most state governments. The only alternative

for regulators is to seek improvements in efficiency, especially by reduction of thefts and

losses. In the case of Andhra Pradesh T & D loss reduction seems to have become harder to

achieve. T & D losses have stagnated at about 28-30 %.

Similarly, the cross-subsidy has remained around ` 2000 crores and government subsidy at

` 1500 crores over the last four years.

The AP regulator expressed concerns in their tariff order (2004-05). Allowing captive generation and multiple licensees, without cross subsidization surcharge

will have an adverse effect on the existing distribution licensees who have a universal service

obligation for the entire area of supply. If the captive generation and the second licensee take

away the subsidizing consumers and the paying areas, the finances of the existing licensees

will get affected without any fault of the existing licensees. This is particularly so during the

transition period envisaged under Section 61(g) of the Electricity Act, for progressive

reduction and elimination of cross-subsidy prevalent in the system. In the transition period,

the subsidizing consumers will move out of the existing distribution licensees making the

above reduction and elimination of cross-subsidy more difficult.

Page 62: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

49

5.1.3Transmission charges for short-term Open Access within the region

(Inter-state Intra Regional)

At present, the transmission charges for the network belonging to CTU/POWERGRID in a

region are shared by the beneficiaries/long-term customers pro rata to their share in central

generation and contracted power evacuated by CTU/POWERGRID network. The revenue

realized from short-term customers is adjusted in accordance with the regulations against the

total transmission charges payable by the beneficiaries/long-term customers. The short-term

customers are charged a minimum rate corresponding to 25% of the regional transmission

charges for the previous year calculated in terms of `/MW/day. This is because of the reasons

that the short-term customers are served only to the extent of available surplus capacity on

the existing transmission network built for the beneficiaries who have the obligation to pay

full transmission charges and the short-term customers are to be curtailed first in case of

transmission constraints. The economic rationale was to have some charges corresponding to

usage to avoid conflict of interest between those using the network frequently for short term

transactions and others. The transmission charges for short-term customers come to a few

paisa per kWh for each region. The charges applicable to the short term customers are also

applicable for the long-term customers, if they enter into transactions of short-term nature. In

the event of congestion, RLDCs conduct electronic-bidding to decide who should be given

the short-term reservation. As far as POWERGRID is concerned, it is in any case assured of

recovery of full transmission charges even if no charges are levied for short-term open

access.

Some of the stakeholders feel that existing beneficiaries/long-term customers should not be

required to pay transmission charges within the region for short term open access. It has been

contended by them that beneficiaries/long-term customers have obligation to pay full

transmission charges applicable for the region and, therefore, should have the flexibility to

make use of spare capacity for short-term open access, without paying any extra charges.

a) The implications of making short-term open access free for beneficiaries/long-term

customers are:

b) The Independent Power Producers (IPPs), Captive Power Plants (CPPs) may raise

demand for free open access on the POWERGRID network in the region so that they

can trade their power on equal footing, since otherwise IPPs and CPPs would be

forced to sell their surplus generation to the state utilities, who in turn would be able

Page 63: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

50

to trade it with other state utilities by availing of open access without payment of the

transmission charges. In this manner, the market for short-term trading in power

would get monopolized by the state utilities.

c) 'Early birds' would take advantage and others would not get open access due to

congestion. Thus, it may result in heart-burning among the long-term open access

customers due to disproportionate usage of the network.

d) Free usage might result in what is referred to as 'tragedy of the commons'. No one

values and cares for a service available free of charge, and this may ultimately result

in slackening of investment in transmission sector.

e) On the same reasoning, any embedded customer while availing of such inter-state

open access would also not be required to pay for using the network of the state utility

in which it is embedded.

f) Similar treatment would be expected for intra-state transactions, more so because the

procedure and methodology adopted by the Central Commission, serves as a guide for

the State Commissions.

The existing methodology for treatment of transmission losses will also call for a review

simultaneously. At present, average losses are being apportioned in kind to the short-term

open access customers, irrespective of the fact whether they are causing or relieving

congestion. It will be fair that short-term customers are levied incremental transmission

losses if they are causing congestion and are not apportioned any transmission losses in

case they are relieving congestion. Such a differential treatment of transmission losses

will also help in optimal utilization of the transmission network by creating incentive for

relieving congestion.

5.1.4 Regulatory approach to Open Access

Only a few regulators have notified the terms and conditions of open access. Even these

regulators have not clarified their position on the cross-subsidy surcharge and phasing out of

cross-subsidies. Most of them appear to be waiting for the National Tariff Policy which the

central government is required to issue under the Electricity Act 2003. However, a few

regulators have taken open access decisions which provide some indication of their approach

in future.

The National Electricity Policy lays special emphasis on time bound reduction of

Page 64: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

51

transmission and distribution losses and advocates promotion of competition aimed at

consumer benefits.

Open access in transmission will promote competition and in turn lead to availability

of cheaper power. The policy emphasizes that the Regulatory Commissions need to

provide facilitative framework for non-discriminatory open access at the earliest

including technological up gradation of the State Load Dispatch Centres to ensure

data acquisition capability on a real time basis.

Open access in distribution networks, initially for bulk consumers, would increase the

availability of cheaper and reliable power supply. State Regulatory Commissions have

been mandated to notify regulations by June 2005 for laying down the road map for

introducing open access in distribution. It has also been envisaged that amount of

cross-subsidy surcharge and additional surcharge to be levied from consumers who

are permitted open access should not become so onerous that it eliminates

competition.

5.2 MANAGEMENT OF AGRICULTURE SUPPLY AND SUBSIDY

In India, agriculture accounts for the bulk of the power subsidy and cross-subsidy. In the

absence of agricultural metering there is significant disagreement over the exact amount of

subsidy. Any attempt at subsidy reform must address the issue of power supply to agriculture.

So far power subsidy has been a general input subsidy, not targeted at any particular group of

farmers. Given the limitations on pump ownership by small and marginal farmers a

disproportionate amount of the subsidies has gone to the wealthier farmers. Current levels of

power subsidy are not only unsustainable, given the condition of state government finances,

but also undesirable, given its impact on groundwater extraction. In future, subsidies will

have to reduced and targeted.

5.2.1Metering Agriculture Supply

Appropriate metering is an essential prerequisite for controlling and targeting the subsidy and

cross-subsidy. However, there is likely to be serious resistance by farmers to the transition to

metered tariffs and progressive reduction in subsidies. In the case of Haryana, according to a

World Bank study ―about 69% of the farmers surveyed favoured metered supply‖.

Page 65: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

52

According to Haryana Vidyut Parishad Nigam (HVPN), these statements by farmers are not

confirmed by the reality on the ground. In spite of significant increase in unmetered tariff and

attractive metered tariffs, farmers still prefer to take unmetered connection. According to

them there are several difficulties encountered in the installation of meters.

i. It is necessary to house the meter in a safe weather proof place, and farmers are not

ready to construct the room or shed for the meters.

ii. Farmers apprehend that once the meter is installed they would be questioned for the

extra-consumption for other purpose for the pumping load and their unauthorized load

would be detected; iii. Farmers do not own the responsibility of the safe custody of the meters, as these are

not covered under their power supply contract for unmetered connections; iv. The utility is neither able to recover the cost of the meter nor charge any meter rental

or maintenance charges;

v. The cost of reading the meters would be an extra financial burden to the utility; vi. There are reports of the meters having been removed by the farmers and damage to

the meters. According to the HVPN the metering program will be successful only if the unmetered tariff

is totally withdrawn and there is no option for farmers other than to have a metered

connection.

Most farmers‘ organizations have justified resistance to metering and tariff increases given

the poor quality of power supply. Several studies have concluded that farmers are willing to

pay more for power if the supply is reliable and of better quality. Of course, there is no

guarantee that farmers will actually pay more once the supply has improved. Studies have

also found that farmers are unwilling to pay more if the quality of supply is already good. In

any case, it will be easier for politicians to justify and utilities to implement installation of

meters and increase in tariffs if it is accompanied by improvements in quality and reliability.

Elimination of power subsidies for agriculture appears infeasible in the short term given the

critical role of groundwater irrigation in agriculture. The poor condition of canal irrigation

along with flat rate subsidized power tariffs has led to increasing reliance on pumped ground

water. Ground water provides a more flexible and reliable source of irrigation than surface

Page 66: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

53

water, in spite of the poor quality of power supply. The increasing reliance on ground water

for irrigation is reflected in the fact that during the period 1990-99 the area under canal

irrigation remained virtually constant at 17-18 million hectares. The share of land under canal

irrigation dropped from 37% to 31% while the share irrigated by wells increased from 51 to

58%. More specifically, the share irrigated by tube wells increased from 30 to 36%.

Given these factors regulators have been largely unsuccessful in dealing with the problems of

power supply to agriculture. Attempts at metering of pump-sets and quantitative restrictions

on the overall supply of power to agriculture have not worked. Farmers have been ignored

attractive metered tariffs and continue to prefer flat rate supply. Hence there is need to work

out structural solutions to the problem.

5.2.2 Separating Agriculture Supply

Given the specific characteristics of power supply to agriculture, it is not surprising that there

is broad consensus on the need for a separate organization for delivering power to agriculture.

This is necessary not only from the perspective of meeting the agriculture demand more

efficiently but also to separate the problems of rationing and subsidy in the case of power

supply to agriculture, from other parts of the organization. This will make reforms, including

privatization, of other parts feasible.

As early as 1980, the Rajadhyaksha Committee considered the question of the appropriate

organization structure for the rural electrification programme and concluded that, ― SEBs

should progressively extricate themselves from operating and servicing the RE (Rural

Electrification) system‖, and consider, ―other alternatives to the SEB staff undertaking

maintenance, repair, servicing, billing and collection‖. According to the committee, operating the RE system solely through expanding the staff of

SEBs, on account of their high costs and lack of close involvement with the village

community, will make the programme increasing unviable and retard its progress. Many of

these recommendations have appeared in modified forms in recent reports of the Ministry of

Power.

The March 2002 report of the Distribution Policy Committee recommends, ―The insulation of

the main stream operations from rural operations and adopting a specific plan of action for

rural operations is an approach, which has some merit‖. Even after separation of rural supply,

Page 67: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

54

a social charge to be levied upon non-rural consumers for subsidizing the rural supplies,

whether serviced by a private or a state entity is an option that could be considered along with

budgetary support from the government.

The Expert Committee on State-specific reforms (MoP September2002) recommends a

carving out of the states into concentrated and other zones. The main rationale for

concentrated zoning is to eliminate or at least minimize the problem of misreporting T & D

losses as subsidized agriculture consumption. It is also expected to make the remaining

distribution business attractive for private investors. Considering the distinct characteristics

of electricity supply to rural areas and the international experience the committee

recommends that,

The government would ring-fence the subsidy that is targeted towards the rural zones and

deploys it diligently through a combination of innovative solutions such as minimum subsidy

bidding and involving user cooperatives and local franchisees, and fostering of institutions to

provide quality advice to these franchisees on financial, technical and managerial matters.

Several issues will need to be sorted out in creating a separate organization for supplying

power to agriculture:

i. Organization form:

This is likely to be a government organization, carved out of the existing SEBs. However, it

would need to use appropriate local organization form such as co-operatives, village

committees and franchisees to perform most of its tasks of routine maintenance and billing

and collection. There is some experience with village committees in Orissa.

ii. Physical separation of the agriculture/rural network:

Agriculture metering is likely to be a long drawn out process for rural areas in general, and

agriculture in particular, in the face of resistance of farmers. Therefore, the only way to

determine the exact amount of supply to agriculture is to physically separate the network and

measure the input into the system. Separation of the network is also necessary for controlling

the quality and timing of power supply to agriculture.

iii. Delivery of subsidies: Mechanisms for delivering subsidies are possible only with

Page 68: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

55

comprehensive metering. Moreover, non-pump-owning farmers would not be able to

directly benefit from power. Therefore, without comprehensive metering the current

system of untargeted subsidies is likely to continue.

Maharashtra appears to be the first state to actively consider a separation of rural agriculture

power supply. According to the Maharashtra Electricity Regulatory Commission (MERC) the

Maharashtra state government has outlined three options on distribution company formation

and requested the Commission to indicate its preference. The options are:

I. Extension of existing structure through a single distribution company being vested

with the distribution business of MSEB.

II. A traditional or balanced distribution company structure featuring three distribution

companies having comparable urban and rural consumer mix. III. Urban-rural structure featuring two urban and four rural distribution

companies

5.3 OA in Andhra Pradesh - case

Power purchases by consumers directly from the open market - instead of relying on local

power utilities - now account for well over 40% of total power traded on India's biggest

energy exchange. But serious issues remain in providing such 'open access' to industries.

Even by the erratic power supply standards that Indian industry has had to bear with for

years, factories in Andhra Pradesh have had an unusually tough 2012. Power shortages in the

state had been acute for well over a year and a half, but in August last year, the state

government began implementing a "power holiday" for industrial consumers three days a

week.

According to K Karunakara Rao, Executive Director of the Kurnool-based Sree Rayalaseema

Alkalies and Allied Chemicals, there are now peak hour restrictions in place, between 6 pm

and 10 pm, during which power supply is heavily rationed. According to news reports, small

and medium industry in the state, reeling from the cuts, has resorted to heavy layoffs to stay

afloat. "Power supply has been difficult for the last year, but in September it started becoming

severe," says Rao.

Page 69: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

56

So at that time, Rao's company decided to obtain clearances from its power distribution

company (Discom), which allowed the company to buy power through "open access". Simply

put, the company could now buy power from any power plant in the country either directly,

or by placing bids on a power exchange, rather than relying on its local Discom. The power

would be routed to the factory through the existing network of lines and feeders. "We buy up

to 2 lakh units a day," says Rao.

In the wake of Andhra's power crisis, scores of other industries have gone down the open

access path. "We have seen many customers from Andhra Pradesh join us over the last year

or so," says Rajesh Mediratta, director of business development at Indian Energy Exchange

(IEX), India's largest power exchange, which has a 27% share of the market for "short-term"

power.

Figure 5- Volume traded at IEX

In Rajasthan, it is a similar story. "Open access provides a transparent system of price

discovery," says NK Bahedia, senior general manager (commercial) at RSWM, a textile

company. "Companies can save as much as 50 paisa per unit of power, sometimes more,

through it."

Open access, a cornerstone of power reforms for almost 10 years, has also remained a largely

unfulfilled aspiration across the country. The state electricity boards (SEBs) have for long

been painted as the villains of the piece, unwilling to let their most lucrative customers

bypass them and buy power from elsewhere, thus condemning factories to endless power

cuts, and lost output. The reality, however, is more complex.

Page 70: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

57

NAVIGATING THE MIDDLEMEN While the short-term power market is officially used

to describe transactions where power is supplied for periods of less than a year, in actual

practice the bulk of deals on the IEX is for literally the next day. A power consumer in

Andhra will, for instance, bid to buy power for 11 am to 5 pm the following day. That power

could be supplied by a plant in Chhattisgarh, and routed through a series of lines in the

national grid, and the Andhra state grid, to the consumer's doorstep. But it's along that path

that all the problems and intermediaries lie.

The biggest of them is, of course, the SEBs. Towards the end of last year, the government

proposed yet another package of reforms to bail out SEBs, reeling under hundreds of

thousands of crores of losses accumulated over the years from selling power below cost, or

even free, to domestic consumers and farmers. For an SEB, charging high rates of power to

industries is a quick, politically easy way to offset low rates charged to farmers. Allowing

those consumers to buy power from elsewhere seems tantamount to economic suicide; even if

the SEB gets compensated by charges paid to it, and mandated by the government, to

essentially soften the blow.

"Only if the problem of losses of SEBs, and of cross subsidies (whereby farmers and retail

consumers are effectively subsidised by higher rates charged to industrial consumers) are

removed, will open access become a reality," says SK Chatterjee, deputy chief, regulatory

affairs, Central Electricity Regulatory Commission (CERC), the apex regulator for the sector.

The issue facing most industries (all consumers with a load of more than 1 megawatt are

eligible for open access) was not that they were being charged high rates by their Discom, but

that the power supply was erratic. "To me the issue is not of price but availability," says Rao.

"The price we pay on power exchanges, when adjusted for all the other charges are about the

same as we pay to the Discom."

5.4 Intra State Open access issues Open access transaction has been primarily used by SEBs / distribution licensees to sell

surpluses or to meet the short – term power requirements in their respective regions. The

industrial customers still face problems pertaining to accessing their choice of suppliers due

to the restrictions (such as invoking Section 11/108 of Electricity Act 2003) imposed by

Page 71: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

58

several state governments / SLDCs citing shortages or non – availability of transmission

infrastructure. According to Central Electricity Regulatory Commission (CERC), up to May

2010, applications seeking open for over 18000 MW have been submitted, but

implementation has been quite low at about 2,000 MW (mainly for captive power).

While the inter State open access market has progressed due to regulatory initiatives taken by

CERC, (on going development of national grid by Power Grid (although congestion is

currently taking place during peak times) and support from NLDC / RLDCs), the intra state

open access is facing constraints on account of delays in implementation of Intra – State ABT

by several states. The sources of concern for implementation of Intra State ABT are

assessment / augmentation of intra – state transfer capability, advanced infrastructure at State

Load Despatch Centre (SLDC), real time communication and special metering at consumer

level. The progress of reforms at state level, with less intervention by respective State

government, will continue to remain crucial for penetration of such transactions across the

States, to facilitate the development of full – fledged short term market.

Open access to the distribution network owned by Discom, however, was to be implemented

in phases on payment of open access charges and charges for cross-subsidy and additional

subsidy if any, which were to be progressively reduced to within 20 per cent of the average

cost of power by 2010-11. Open access is available for power purchase or sale by utilities or

distribution licensees.

However, when it relates to generators and consumers, only some of the States have

permitted limited open access. Some are permitting open access to generators if they are

connected to central transmission network.

Lack of open access in intra-State transmission has affected the development of the power

market, jeopardizing competition. The competition is only feasible if players in the power

market are per-mitted access to both intra and inter-state transmission networks on payment

of reasonable charges. While inter-state open access within the limitation of adequate

‗available transfer capability‘ (ATC) has been operational, intra-State open access has not

progressed because of slow implementation of certain pre-requisites. Lack of open access has

also restricted transfer of power from surplus to deficit regions and failed to optimize

Page 72: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

59

procurement costs.

The irony is that open access has not been allowed to succeed for various reasons, such as

apprehension of the State utilities about flight of industrial consumers from their net; non-

availability of surplus power at reasonable rates; irrational open access charges; non-

availability of open access infrastructure of metering; and segregation of consumers‘ lines,

among other factors.

Even though the cross-subsidy surcharge on open access transactions is mandated under

Section 39 and 42 of the Act, erecting a high tariff barrier deters customers from purchasing

supplies from outside the jurisdiction of Discoms and runs counter to the tariff envisaged in

the National Electricity Policy and Tariff Policy. For meeting the demand during acute power

shortage, it is observed that some States have misused their powers to block the sale of

surplus capacity of captive generators to other States, by inappropriately invoking Section 11

of the Act. This de-motivates the generators to sell power through the power trading

mechanism, and forces some of them to sell power be-low market rates. It defeats the very

spirit of the Act. It has forced the Union Minis-try of Power to issue direction to Central /

State Regulatory Commissions to allow industrial consumers to buy cheaper power from the

open market under Section 107 of the Electricity Act.

A standard, consumer-friendly open access regulation with balanced cross-subsidy

computation should be formulated through a forum of regulators and adopted uniformly by

all states regulators. Taking the holistic view of the various pro-visions of the Act, open

access cannot be legally denied, if requested by consumers. Open access, industries are either

forced to opt for captive generation or depend on unreliable power supply from Discoms.

Some States like Punjab, Rajasthan and Gujarat, on a non-sustainable basis, have started

allowing open access to the consumers for procuring power for meeting their requirements.

Some States like Tamil Nadu are not allowing captive generators to sell power through open

access, even though it allows importation of power during peak hours.

With increasing size and depth of the market, new products are bound to hedge the risks for

the buyers and suppliers, and these could be in the form of options and futures. Also, for

making transparent open access regulations, there is a need for segregating the wires and

Page 73: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

60

content business in the distribution segment too. To help facilitate a successful open-access

regime, Discom has to create infrastructure and last mile connectivity.

5.5 Open Access in Uttar Pradesh

5.5.1 Open Access for industries key to UP’s Economic growth

The Industrial sector in UP, one of the largest states in northern India, has been facing several

challenges due to unreliable and expensive power supply. Once considered the hub of Small

and Medium Enterprises (SMEs), the state is now witnessing a slowdown with many such

players either shutting down operations or shifting to other states with better infrastructural

facilities, primarily electricity. This is acting as an impediment to the state‘s industrial and

economic growth. The industries are bearing the brunt of load shedding for several hours a

day. Even though industrial tariffs for electricity have increased over the years, industries

continue to be deprived of reliable power.

Meanwhile, the state‘s electricity demand is increasing with rising temperatures. The Central

Electricity Authority (CEA) data for January-March 2013 shows that the peak demand rose to

12,696 MW in March 2013. However, only 9,949 MW of this demand was met through self-

generation and allocation from central generation plants. In 2012-13, the energy shorted stood

at 16.6%, among the highest in the country.

Table 28: Energy Shortage in UP

January February March

Requirement 7709 6441 8087

Availability 6388 5366 6387

0

1000

2000

3000

4000

5000

6000

7000

8000

9000

En

ergy (

MU

s)

Energy Requirement in Uttar Pradesh (2013) Source : CEA

Page 74: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

61

With the state being unable to meet the energy demand, several industries – many with a

contracted demand of 1 MW and above- have sought OA in distribution to procure power

from the open market, primarily energy exchanges such as IEX . However, this has not been

allowed, and, as a consequence, the industries continue to face load shedding. The

fundamental right to avail OA has not been implemented even 10 years after the enactment of

the EA 2003.

Table 29: Peak shortage in UP

Other northern states like Punjab, Haryana Rajasthan and Uttarakhand have allowed

consumers with a demand of 1 MW and above to leverage the IEX platform to purchase

power through OA. This has not only facilitated the development of industries in these states,

but has also helped them to reduce energy costs significantly, thereby improving their

profitability and overall competitiveness.

5.5.2. Lack of Implementation of OA regulations

The regulations for OA are already in place in UP. In fact, the UPERC was one of the first

state regulators to notify them under the terms and conditions of OA regulations in June

2005. Moreover, amendments to these regulations were released in June 2009. As per the

regulations, any consumer with a load of 1MW and above a minimum connectivity level of

11kV can avail OA. The SLDC is designated as the nodal agency for STOA.

The regulations also specify the procedure for availing of OA. Any consumer wanting to

avail of OA should submit an application to the SLDC with a copy each to the STU and the

Discom in its area. The application should provide details such as the capacity requirement,

January February March

Demand 12665 12278 12696

Peak met 10745 9363 9949

0

2000

4000

6000

8000

10000

12000

14000

Cap

aci

ty (

MW

)

Peak demand in UP (2013) Source :CEA

Page 75: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

62

the point of injection/drawl, duration of availing of OA and any additional information as

specified by the SLDC. Based on consultations with the STU and the Discom, the SLDC will

take a decision on the application.

Despite the enabling legislative and regulatory provisions, applications for OA are yet to be

approved. In fact, the UPSLDC was established in January, 2011 almost six years after the

notification of OA regulations.

In its order dated January 7, 2013, the CERC directed UPSLDC to consider the applications

for OA filed by Noida Power Company Limited (NPCL), the Discom responsible for

supplying electricity in Noida and Greater Noida, or any other individual in the future for

issuing No-objection certificate (NOC), a mandatory requirement for purchasing power

through the energy exchanges. NPCL had filed a petition with the CERC as UPSLDC did not

respond to its NOC application after several attempts over three years (2008, 2009 and 2010).

Prior to the CERC‘s directive, UPERC had also asked UPSLDC to grant OA to NPCL.

However, the state has yet to respond to OA applications submitted by NPCL.

5.5.3. Affordable and reliable power through the IEX

At the IEX, the average price for 2012-13 for the N2 region (the bid area for UP at the IEX)

was ` 3.13 per unit. This means that an industry connected at 11kV will have to pay around

` 4.05 per unit including the applicable losses and charges and the IEX fees. The energy

charge for an industry connected at 11kV in UP, including the recently imposed regulatory

surcharge is ` 6.16 per unit. This implies that the industries could save more than ` 2 per unit

by procuring electricity through the IEX.

State Chhattisgarh Himachal

Pradesh

Punjab Haryana Delhi Uttar

Pradesh

Uttarakhand Rajasthan

OA for

industries

Industrial

Participants

at IEX

Nil (not

many

industries)

Nil( tariffs

are low and

no

shortage)

287

125

Nil (No

shortage)

Nil( high

tariffs and

industrial

loads)

41

121

Source: IEX Table 30: OA at IEX

Page 76: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

63

Similarly, the average peak hour price at the IEX for 2013-13 for the N2 region was ` 3.50

per unit. This implies a cost of ` 4.47 per unit (including the applicable losses and charges)

for an industry. Therefore, an industry can save more than ` 2.50 per unit during peak hours

by sourcing electricity from the IEX through OA. According to UPERC‘s latest tariff order,

the discom‘s tariff for industries at the 11kV level during peak hours including the regulatory

surcharge is ` 7.03 per unit.

5.5.4. OA as a panacea to power woes

OA has been a key enabler in introducing competition in the power sector. Consumers across

the country are benefitting from this provision under the Electricity Act. The IEX has over

1,800 OA consumers who are using the exchange platform to meet their electricity needs in a

cost-effective and reliable manner.

Since electricity costs account for a significant part of the expenditure for industries, any

reduction in this cost component adds to an industry‘s profitability and enhances its overall

competitiveness.

The CERC‘s recent directive allowing NPCL to purchase power through OA is expected to

expedite the implementation of OA in the state. The state‘s reluctance to allow OA to

industries comes at the cost of limiting its own industrial and economic growth, and

therefore, it will be prudent to provide OA to these units.

With industrial growth in the state staggering due to worsening power supply, OA is indeed a

panacea for the industry to procure power from the energy exchanges and for the state

government to drive its economic growth.

Source: Power Line June, 2013.

Page 77: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

64

Chapter 6: SUMMARY

6.1 CONCLUSION

Making the distribution segment of the power industry efficient and solvent is the key to

success of power sector reforms. Implementation of open access in distribution with

proper market condition by studying its feasibility is the only solution. Though it has

been widely says that Open access in distribution will create a competitive environment

but its improper introduction may create huge losses to distribution and also to consumer.

Subsidy to different segment of consumer is the most challenging part of Open Access

hence it needs to tackle in proper manner because this is the only reason because of

which most of the distribution company are resisting for implementation of Open Access.

However, there are some roadblocks in the successful implementation of open access in

distribution in India.

There are some of positive point which encourage for implementation of Open Access

Some of the benefit of Open Access are :

i) As mentioned above the freedom to buy and sell electricity thereby creating or

tending towards a perfect market in this sector.

ii) It allows the generator with an excess capacity to sell and take part in the trading of

electricity.

As there are some benefit of Open Access, but its improper implementation may lead to

huge hotchpotch so it need to be handle properly.

o Cross Subsidy Surcharge is not adequate to compensate subsidy :-

Present Cross Subsidy surcharge formula is not compatible to balance the subsidy

with cross subsidy because it will not considered AT & C loss and theft. So finally it

has negative impact but as per the concept of cross subsidy it should neutralize the

effect of subsidy but in actual practice it is not happening. So in present case licensee

Page 78: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

65

is bearing all this loss and state government has given assurance of payment.

o Distribution of subsidy is also not proportionate because location has not considered

due to which those who are economically strong are getting same subsidy as that of

economically weak consumer.

o In Open Access there is no surety for all time power availability or backup because

if Open Access seller power plant has gone for shut down then ideally consumer has

also shut down its activity but in actual practice as they are connected with grid they

are consuming power from grid and create power shortage for licensee. In that case

either licensee has to make load shedding or else they have to purchase costlier

power if available. This also one of the major reasons because of which consumer

doesn’t want to move in Open Access.

o Renewable generator has exempted from cross subsidy and wheeling charge under

the name of renewable promotion but then who will pay on behalf of renewable is

not clear. Also if renewable energy producer sells powers in Open Access and as we

already know that renewable is not firm power so only because of their grid

connectivity they start consuming power from grid and create power shortage for

licensee. In that case either licensee has to make load shedding or else they have to

purchase costlier power.

o Lot of consumer are also resisting for implementation of Open Access because of

unreliability of generating unit because due to Open Access it has become their

headache for getting continuous power from generating unit.

o Charges for the open access levied by different SERCs are variable in nature.

o Apart from few states, many states are still incorporating and facing problem of

cross subsidy surcharge which finally increases the net cost of power from open

access.

o Net cost of power from open access is more as compared to the tariff which

discourages the buyers and sellers.

o SERC’s has to use different methodologies for the calculation of surcharge because

of complexity of consumer even though there is common formula for calculation of

surcharge given by National Tariff Policy 2005.

o Distribution companies in India are not financially very sound and Distribution

network in India is not strong.

Page 79: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

66

6.2 RECOMMONDATION a) In present scenario of Indian Electricity Sector which is power deficit the

implementation of Open Access are creating huge problems which are given below :

Forecasting of Distribution Company for future requirement of power is adversely

affected because of consumer uncertainty in Open Access.

Gaming in Electricity Market which is altogether is not acceptable as per Electricity

Act 2003.

Sudden drawl of power from grid by Open Access consumer when there are

shutdown at seller side those who are selling power to consumer through Open

Access.

So for proper implementation of Open Access electricity market should be power

Surplus.

b) Central and State ERCs should be advised by the appropriate governments to comply

with the statutory requirements relating to open access in a time bound manner. There is

challenge for calculation of open access surcharge because of complexity of consumer

even though there is provision in Tariff Policy notified by the Central Government under

Sec. 3 of the Act but states are using their own method to calculate which need to be

standardized. c) Subsidy are not reaching to right consumer hence it is advisable to have consideration of

location during calculation of subsidy because the needy consumer like consumer from

Vidharbh region of Maharashtra which actually required the subsidy are getting same

subsidy as that of other region which is economically reach. But when load shedding has

to do then first consideration has given to Vidharbh region saying the reason that they

are not paying consumer though this region has less availability of water and has to go

more deep into the soil to get the water hence requirement of electricity is most

important. Interesting part is that most of powers generating units are there in this region

only but still they are not getting enough power for agriculture and industrial sector

because of this there is instability in the state. Cross subsidy is levied equal in all regions

hence it is important for all state holders to consider this issues.

Page 80: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

67

d) Promotion of renewable energy altogether is considerable but it needs to be taken care

that no one should get its undue advantage by using Open Access. Because many

companies have formed their subsidiary and generated renewable power and showed that

company as loss making company. By doing this they are taking all type of benefits like

Tax Exemption for renewable power generation & loss making company, meeting RPO e) The question of “Who will pay the remaining part (comes under AT & C Loss and Theft)

of subsidy?” is still unanswered because present Cross Subsidy pattern is not able to

balance the subsidy with cross subsidy and distribution companies are bearing this loss

and continuously coming in loss making company. f) The theft loss is still present even though Distribution has taken lot of measure to reduce

it like metering and it is counted in subsidised section and all other paying consumer like

domestic and industrial consumer are bearing it. If paying or reach consume are moved

in Open Access then rest of the consumer which is not economically strong has to bear

this loss because there is no provision for this in Cross subsidy surcharge (Even though

State Government has given assurance to pay it but it is uncertain). g) State Governments and States’ ERCs should be suitably advised to enable

operationalization of open access to promote a healthy development of the market where

private investment can be attracted. Where the State Governments or the respective

SERCs do not conform to the Act or the Tariff Policy there under, the State Governments

should be advised and the matter be discussed in the appropriate inter- and intra-State

forum of Power Secretaries/Ministers. h) IPPs, captive and small generators shall be educated for their responsibility and future

condition if they are bringing power into the market. i) Need to take regular customer feedback to understand their difficulties so that consumer

satisfaction can be achieved. j) Regulators should meet with the bulk consumers and other stakeholders to address their

concerns with a view to operationalizing the scheme of open access as provided in the

Act. k) Consumer education and pro-active action by Regulators, both at the Centre and in the

States, is considered vital for encouraging open access to consumers.

Page 81: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

68

6.3 LIMITATIONS OF THE PROJECT

a) First of all the time duration of 8 weeks was a major constraint in going through the

project completely.

b) Getting tariff orders for year 2013-14 of some of the states was not possible as they were

not notified on respective SERC’s website.

c) Tried to reach various SLDCs and SERCs but no one actually replied.

d) States like UP did not share much of information about their OA consumers (if any), thus

accurate analysis could not be made.

e) Assumptions, such as uniform usage of electricity through out day for TOD metering

may not be applicable to every consumer.

f) Data collection for all the calculations has been done from regulations and orders of

respective states. There is always a risk of update of tariff during preparation of report.

g) No interaction with the open access consumers. The interaction could have helped to

understand the real time problems faced by them.

6.4 RESULT & DISCUSSION In present scenario of Indian Electricity Sector which is power deficit market the improper

implementation of Open Access are creating huge problems which are listed below:

Forecasting of Distribution Company for future requirement of power is adversely

affected because of consumer uncertainty in Open Access. Sudden drawl of power from grid by Open Access consumer when there are shutdown at

seller side those who are selling power to consumer through Open Access. SERCs to calculate Cross-Subsidy Surcharge based on the assumptions that the power

available as a result of exit of open access consumer will be sold at the average revenue

realization rate. This is the most practical scenario in a situation of shortage of power

supply. The SERCs may assume certain percentage (say, 10%) of the total consumption

by eligible open access consumers for the purpose of estimation of power available for

sale at average realization rate. The wheeling charge (grossed up by the system loss at

appropriate level) to be recovered from the open access consumers should also be

factored into computation of surcharge.

For a situation where there is no power cut, SERCs may calculate Cross-Subsidy

Page 82: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

69

Surcharge based on the estimation that the DISCOM will avoid purchase of the quantum

of power for which open access has been sought.

6.5 FUTURE SCOPE OF THE PROJECT To bring the competition in the electricity market it very important to implement Open

Access and Indian Power Sector has already taken shining steps towards it. But its proper

implementation is also equally important to avoid gaming and mismatch. This report will

help to take proper step toward implementation of Open Access also help to put the

difficulties of Distribution Companies.

This report gives eligible OA consumers to choose their supply through it at desired voltage

level and thus can save substantial cost of electricity. This would also help industries to

choose their transaction method so that they can get reliable and efficient supply.

Everyone is expecting retail competition in Electricity Market and this report highlight the

points of its improper implementation which guide during its implementation.

6.6 BIBLIOGRAPHY

List of Documents

– Central Electricity Regulatory Commission (Grant of Connectivity, Long-term

Access and Medium-term Open Access in inter-State Transmission and related

matters) Regulations, 2009

– Central Electricity Regulatory Commission (Open Access in inter-State

Transmission) Regulations, 2008.

– Central Electricity Regulatory Commission (Grant of Connectivity, Long-Term

Access and Medium-Term Open Access in Inter-State Transmission and related

matters) (Second Amendment) Regulations, 2012.

–– Forum of Regulators‘ Model Regulations on Terms and Conditions of intra-State

Open Access.

– Paper on ―Open Access-Challenges and way forward‖ by SK Chatterji Deputy

Chief CERC, 2009.

– Task Force Report on ―Measures of operationalizing Open Access in Power

Sector‖, by Planning Commission.

Page 83: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

70

– Paper on ―Issues on Distribution Open Access and Retail competition‖ by SK

Chatterji.

– Paper on ―Open Access in Inter State Transmission‖ by SK Soonee.

– Forum of Regulators’ Model Regulations on Terms and Conditions of intra-State

Open Access.

– Tariff Order for States – Maharashtra, Gujarat, Andhra Pradesh, Punjab and Uttar

Pradesh.

– Position Paper on Open Access by FOR.

– FOR Report on Open Access-Theory and Practices-08-04-2009.

– Open Access case by MERC.

Websites

http://www.cea.nic.in/

http://www.cercind.gov.in/

http://www.powermin.nic.in/

http://www.forumofregulators.gov.in/

http://www.iexindia.com/

https://www.sldcguj.com/

http://www.gercin.org/

http://www.gseb.com/guvnl/index.aspx

http://getco.co.in/getco_new/

http://www.mgvcl.com/

http://www.ugvcl.com/

http://www.pgvcl.com/

http://www.dgvcl.com/dgvclweb/index.php

http://www.pspcl.in/

http://www.pserc.nic.in/

http://www.pstcl.org/

http://www.punjabsldc.org/

http://www.uperc.org/Default2.aspx

http://www.aptransco.gov.in/

http://mahasldc.in/

http://www.mahadiscom.in/

http://www.tatapower.com/

http://www.rinfra.com/

http://www.mahasldc.in/

http://www.mercindia.org.in/

http://www.nldc.in/

http://www.thehindubusinessline.com/

http://www.mahatransco.in/

Page 84: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

71

Annexure

1. Charges for Maharashtra

1) Charges for MSEDCL

Page 85: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

72

2) Charges for R-InfraD

3) Charges for TPC

2. Charges for Gujarat

I. MGVCL, PGVCL, UGVCL, DGVCL

Page 86: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

73

II. Torrent Power

3. Charges for Uttar Pradesh

Page 87: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

74

PuVVNL, MVVNL, PVVNL, DVVNL

KESCoL

NPCL

Page 88: Study of Open Access and Cost Benefit Analysis of Open ... · Study of Open Access and Cost Benefit Analysis of Open ... Open Access and Cost Benefit Analysis of Open Access over

75

4. Charges for Punjab