stu/trans-plan/doc-4 /wef 01/04/10 - · pdf filesubstations nomenclature used in plan 1 400 kv...

191
STU/TRANS-PLAN/DOC-4 /WEF 01/04/10

Upload: haquynh

Post on 28-Mar-2018

254 views

Category:

Documents


4 download

TRANSCRIPT

Page 1: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS-PLAN/DOC-4 /WEF 01/04/10

Page 2: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

CO�TE�TS

S�O PARTICULARS PAGE

�O.

1 INTRODUCTION 1-74

2 MSETCL PLAN FOR THE YEAR 2010-11 TO 2014-15 75-173

i) Evacuation Schemes 77-78

ii) Washi EHV Construction Cum O& M Zone 79-90

iii) Pune EHV Construction Cum O& M Zone 91-101

iv) Karad EHV Construction Cum O& M Zone 102-113

v) Nasik EHV Construction Cum O& M Zone 114-130

vi) Aurangabad EHV Construction Cum O& M Zone 131-148

vii) Amravati EHV Construction Cum O& M Zone 149-157

viii) Nagpur EHV Construction Cum O& M Zone 158-171

ix) Capacitor and Reactor requirement 172-173

3 R-INFRA PLAN FOR THE YEAR 2010-11 TO 2014-15 174-178

4 TPC PLAN FOR THE YEAR 2010-11 TO 2014-15 179-185

5 756 KV & 400 KV TRANSMISSION NETWORK OF

MAHARASHTRA STATE INCLUDING INTERSTATE LINES

186-188

Page 3: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

�omenclatures for substation

Sr.

No. Substations

Nomenclature used in

plan

1 400 kV Akola (existing) 400 kV Akola-I

2 765 kV Akola (proposed) 765 kV Akola-II

3 400 kV Koradi (existing) 400 kV Koradi-I

4 400 kV Koradi (proposed) 400 kV Koradi-II

5 765 kV Koradi (proposed) 765 kV Koradi-III

6 400 kV Lonikand (existing) 400 kV Lonikand-I

7 400 kV Lonikand (proposed) 400 kV Lonikand-II

8 400 kV Bhusawal (existing) 400 kV Bhusawal-I

9 400 kV Bhusawal (proposed) 400 kV Bhusawal-II

10 400 kV Karad (existing) 400 kV Karad-I

11 400 kV Karad (proposed at Malharpeth) 400 kV Karad-II (Malharpeth)

12 400 kV Padghe (existing) 400 kV Padghe-I

13 400 kV Padghe (proposed at Kudus) 400 kV Padghe-II (Kudus)

14 400 kV Dhule (existing) 400 kV Dhule-I

15 400 kV Dhule (proposed at Dondaicha) 400 kV Dhule-II (Dondaicha)

16 400 kV Aurangabad (existing at Waluj) 400 kV Aurangabad-I

17 400 kV Aurangabad

(proposed at Pandhari Pimpalgaon)

400 kV Aurangabad-II

(Pandhari Pimpalgaon)

Page 4: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

INTRODUCTION

1

A-PDF Watermark DEMO: Purchase from www.A-PDF.com to remove the watermark

Page 5: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15

STU/TRA�S-PLA�/DOC-4 /WEF 01/04/10

‘‘We as a State Transmission Utility (STU) dedicate ourselves to plan, develop, operate

and maintain the State Transmission System to facilitate transmission of electricity from its

source to load centres in a secure, reliable and economic manner for the best services to

the consumers.’’

‘‘We aim to provide an effective transmission services’’ Table – 1 - The network of Transmission System of MSETCL as on 31-03-2010

Sr. No. Voltage Level

(KV) No. of EHV S/s

Trans. Capacity (MVA)

EHV Lines Ckt (KM)

1 500 2 3582 1504

2 400 21 13270 6562

3 220 149 31161 12357

4 132 246 19517 11063

5 110 33 2080 1691

6 100 35 2323 678

7 66 34 1139 3270

Total 520 73072 37125

Table – 1.1 - The network of Transmission System of TATA as on 31-03-2010

Sr No.

Voltage Level

(KV)

No. of EHV S/S

Trans Capacity

(MVA)

EHV Lines Ckt

(KM)

1 220 7 3120 364.86

2 110 11 4272 713.06

Total 18 7392 1077.92

Table – 1.2 - The network of Transmission System of REL as on 31-03-2010

Sr No.

Voltage Level

(KV)

No. of EHV S/S Trans Capacity

(MVA) EHV Lines Ckt

(KM)

1 220 3 1475 484.59

2 110 0 0 0

Total 3 1475 484.59

2

Page 6: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15

STU/TRA�S-PLA�/DOC-4 /WEF 01/04/10

Table – 2 - Previous Power scenario in Maharashtra

Year Peak Demand (MW) Availability

(MW)

Peak Shortfall(-) /Surplus(+)

(MW) State MSEDCL Mumbai

2001-02 11895 10119 1776 10879 -1016

2002-03 13418 11425 1993 10997 -2421

2003-04 13692 11357 2335 11650 -2042

2004-05 14822 12749 2073 11777 -3045

2005-06 16049 14016 2033 11889 -4160

2006-07 17161 14825 2336 13027 -4134

2007-08 18390 15946 2444 12522 -5868

2008-09 18072 15630 2442 13189 -4883

2009-10 19120 16582 2538 14952 -4168

Table - 3 MSPGCL(Mahagenco) Generation

Table – 3.1 - Available Generation by MSPGCL

Sr. No.

Generating Station MW

1 Nasik ( 2x125MW+ 3x210MW ) 792

2 Koradi (4X105MW +2X210MW+1X200MW) 936

3 Khaperkheda (4X210MW ) 756

4 Parli (2X20MW+3X210MW+2X250) 1053

5 Paras ( 1X55 MW + 2X250MW) 500

6 Chandarpur (4X 210MW + 3X500MW) 2106

7 Bhusawal ( 1X55MW+2X210MW) 428

8 Uran ( 612 MW +240 MW (WHR )) 767

9 Koyna (4X70MW+4X80MW+4X250MW+4X80MW+2X18MW)

440

10 Other Hydro Generations (388MW) As per Table 3.2 97

Total MAHAGENCO Generation 7875

3

Page 7: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15

STU/TRA�S-PLA�/DOC-4 /WEF 01/04/10

Table- 3.2 - MSPGCL Installed Capacity of Other Hydro Generations

Sr. No. Power Stations Unit Capacity (MW)

1 Bhatghar(IP) 1x16 16

2 Bhatsa (DW) 1x15 15

3 Bhira Tail Race (PP) 2x40 80

4 Dhom (IP) 2x1 2

5 Dimbhe (IP) 1x5 5

6 Dhudhganga (IP) 2x12 24

7 Eldari (IP) 3x7.5 22.5

8 Kanher (IP) 1x4 4

9 Manikdoh (IP) 1x6 6

10 Paithan PSS (DW) 1x12 12

11 Panshet (DW) 1x8 8

12 Pawna (IP) 1x10 10

13 Radhanagari (IP) 4x1.2 4.8

14 Surya (DW & IP) 1x6 6

15 Terwanmedhe(IP) 1x0.2 0.2

16 Tillari (PP) 1x66 66

17 Ujani PSS (DW&IP) 1x12 12

18 Vaitrna (DW &PP) 1x60 60

19 Vaitarna Dam Toe (DW) 1x1.5 1.5

20 Varasgaon (DW) 1x8 8

21 Veer (IP) 2x4.5 9

22 Warna (IP) 2x8 16

TOTAL 388

4

Page 8: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15

STU/TRA�S-PLA�/DOC-4 /WEF 01/04/10

Table – 3.3 – Proposed Year wise Generation addition (in MW Ex-Bus) by MSPGCL

MAHAGENCO Projects 2010-11 2011-12 2012-13 2013-14 2014-15

Uran Unit-9 (1x814) - - 789 - -

Uran Unit-10 (1x406) - - 394 - -

Bhusawal E Unit-4 (1 x 500) 450 - - - -

Bhusawal E Unit -5 (1x500) - 450 - - -

Khaparkheda Unit-5 (1x500) 450 - - - -

Parli Rep. Unit-8 (1x250) - 189 - - -

Bhusawal Unit 6 (1x660) - - - 400 -

Chandrapur Unit -8 (1x500) - - 450 - -

Chandrapur Unit -9 (1x500) - - 450 - -

Koradi Rep. Unit 8 (1x660) - - - 216 -

Koradi Unit 9 (1x660) - - - - 594

Koradi Unit 10 (1x660) - - - - 594

Total 900 639 2083 616 1188

Existing Generation 7875 8775 9414 11497 12113

Yearwise Generation Availability

8775 9414 11497 12113 13301

Table – 4 STATE GOVERNMENT & INTER STATE GENERATION Table – 4.1 Existing State Government & Inter state Generation as on 31-03-10

Existing(State Government, MAHADISCOM) Capacity (MW)

Ghatghar (2x125MW) 225

RGPPL 1862

Total 2087

5

Page 9: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15

STU/TRA�S-PLA�/DOC-4 /WEF 01/04/10

Table – 4 .2 – Proposed Generation by State Government & MAHADISCOM

Proposed (State Govt., MAHADISCOM) 2010-11 2011-12 2012-13 2013-14 2014-15

LEPL (Lanco Energy Pvt. Ltd.) (500MW & 680MW)

- - 1062 - -

M/s Maharashtra Water Resourse Dept.Koyna (2 x 80 MW)

79

Total 0 79 1062 0 0

Existing Allocation 2087 2087 2166 3228 3228

Yearwise Allocation Availability 2087 2166 3228 3228 3228

Table- 5 Central Sector Power Allocation Table – 5.1 Available Allocation of Power by Central Sector as on 31-03-10

Name of Generating Station Installed Capacity

Available at MSETCL N/W

KSTPS (Korba) 2100 608

Vindhyachal STPS Stage -I 1260 412

Vindhyachal STPS Stage -II 1000 322

Vindhyachal STPS Stage -III 1000 268

KGPS (Kawas) 658 180

GGPP (Gandhar) 657 177

SIPAT Stage – II (2 x 500MW) 1000 268

KAPS (Kakrapar) 440 134

TAPS (Tarapur 3 & 4) 1080 391

TAPS (Tarapur 1 & 2) 324 161

SSP (Sardar Sarowar) 1450 354

NTPC ER to MSEDCL 4940 137

Total 15910 3412

6

Page 10: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15

STU/TRA�S-PLA�/DOC-4 /WEF 01/04/10

Table – 5 .2 – Proposed Year wise Allocation of power by Central Sector

Name of Generating Station 2010-11 2011-12 2012-13 2013-14 2014-15

Sipat 170 - - - -

Sipat - 170 - - -

Mundra UMPP - 320 - - -

Mauda - 350 - - -

Mundra UMPP - - 480 - -

Sipat - - 170 - -

Vindhyachal - - 300 - -

Krishnapattanam UMPP - - - 400 -

North Karnapura - - - 33 -

Barh - - - 33 -

Total Allocation 170 840 950 466 0

Existing Allocation 3412 3582 4422 5372 5838

Yearwise Allocation Availability

3582 4422 5372 5838 5838

Table – 6 Proposed Year wise total generation available in Mumbai (TATA/REL) as on 31-03-10

Generation 2010-11 2011-12 2012-13 2013-14 2014-15

TPC - - - - -

REL - - - - -

Existing Generation Availability (TPC + REL)

(1924 + 459) =

2383 2383 2383 2383 2383

Table – 7 - Power scenario in Mumbai (TATA/REL)

Year

Expected Demand in Mumbai Generation capacity in

Mumbai

Peak Shortfall (-) / Surplus (+)

(MW) TPC + BEST

R-Infra Total

2010-11 976 2154 3130 2383 -747

2011-12 1109 2233 3342 2383 -959

2012-13 1221 2350 3571 2383 -1188

2013-14 1343 2474 3817 2383 -1434

2014-15 1468 2706 4174 2383 -1791

* Shortfall of Mumbai would be met from the bilateral power purchase.

7

Page 11: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15

STU/TRA�S-PLA�/DOC-4 /WEF 01/04/10

Table - 8 IPP Plants Table- 8.1 Existing Generation from IPP/CPP/Biomass/Bagasse/Biogas based Plants

Sr. No.

NAME OF APPLICANT Location of the

Plant CAPACITY

APPLIED (MW)

EX - Bus Generation

(MW)

1 M/s Indrajit Infrastructure Pvt.Ltd. Modern Centre,'B' Wing, 2nd Floor, Sane Guruji Marg, Mahalaxmi, Mumbai-400011.

Bhugaon (Wardha-II)

2 x 40 = 80 72

2 M/s. Purty Sakhar Karkhana, Dist. Wardha. Wardha. 1 x 24 = 24 22

3 M/s Ind-barath Engineers (Maharashtra) Ltd.Plot No.30-A,Road No.1, Film Nagar,Jubillee Hills, Hyderabad-500 033.

Village Kharab Khandgaon,,Dist.

Nanded 20 18

4

M/s Lokmangal Sugar Ethanol & Co-Generation Industries Ltd, 33/A, Sahyadri Nagar,Hotgi Road, Solapur -413 003.

Bhandarkavathe, Tal. South Solapur, Dist.

Solapur. 1 X 15 = 15 13.5

5 M/s M/s Hotel Leelaventure Ltd, The Leela Kempinski, Sahar, Andheri (E), Mumbai 400 059.

Village Khaparale,Tal. Sinnar dist Nasik.

4.5 4.05

6 M/s Hotel ITC the Maratha, Near Blue Dart Office,Sahar Airport Road, Mumabi -400 099.

Village Khaprale (Sinnar),Dist. Nasik

6 5.4

7

M/s Renuka Sugars Ltd.at Deshbakta Ratnnappanna Kumbhar Panchaganga Sahakari Sakhar Karkhana, Ganga Nagar, Ichalkarangi.

Ganga Nagar, Dist.Ichalkarangi

1 X 30 = 30 27

8 M/s Daund Sugar Ltd, ICC Trade Tower, B-Wing 201,Senapati Bapat Road, Pune-411 016.

Village Alegaon, Tal.

Daund, Dist. Pune. 18 16.2

9 M/s Baramati Agro Ltd, Pimpli, Baramati, Dist. Pune, Maharashtra - 413 102.

At Pimpli, Tal. Baramati, Dist. Pune.

22 19.8

10 M/s Finolex Industries Ltd. Project Office,26/27, Mumbai -Pune Road,Pimpri,Pune-411 018.

At Ranpar-Golap,dist. Ratnagiri

22 19.8

11 M/s Kranti Sahakari Sakhar Karkhana,Kundal,Tal. Palus, Dist.sangli-416 309.

Kundal, Tal. Palus, Dist. Sangli.

6.65 (8.85) 6

Total EX Bus Generation ( MW ) 224

8

Page 12: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15

STU/TRA�S-PLA�/DOC-4 /WEF 01/04/10

Table – 8.2.1 Proposed Year wise Generation Addition by IPP/CPP/Biomass/Bagasse/ Biogas based Plants

SR. NO.

NAME OF APPLICANT Location of the Plant

Capacity Applied (MW)

MW ( EX - BUS GENERATION )

2010-11 2011-12 2012-13 2013-14 2014-15

1

M/s JSW Energy Ltd. Jindal Mansion, 5A.Dr.G.Deshmukh Marg. Mumbai 400 026.

Jaigad 4 X 300 = 1200

1080 -- -- -- --

2

M/s M/s Gupta Energy Pvt. Ltd.(Formerly Gupta Coal Fields and Washaries Ltd.) 7th Floor,Shriram Towers, Kingsway, Nagpur 440 001Tal. Ghugus, Dist.Chandrapur.

Usegaon, Dist.

Chandrapur

2 X 60 = 120

108 -- -- -- --

3

M/s Nagpur Energy Infrastructure Ltd.(Formerly Baidyanath Power &Mining), 5, Temple Road,Civil Lines, Nagpur-440 001.

Near Bhadravati,Di

st. Chandrapur.

250 + 250 + 500 = 1000

-- -- 450 450 --

4

M/s Patni Energy Ltd. 302-304, Regent Chembers,Nariman Point, Mumbai 400021.

Medhekar, Tal.Alibag.

2 x 135 = 270

-- -- 243 -- --

5

M/s Emco Energy Ltd.Warora, Plot No.F-5, Road No.28, wagle industrial Estate,Thane-400 604.

Warora 2 x 135 =

270 -- 243 -- -- --

6 M/s Sun-Flag Iron and Steel Co.Ltd. Bhandara Road, Bhandara-441 905

At Warthi, Dist.

Bhandara

2 x 15 = 30

27 -- -- -- --

7

M/s Wardha Power Company Pvt.Ltd, 8-2-293/82/A/431/A, Road No.22, Jubilee Hills, Hyderabad -500033.

Warora,Dist. Chandrapur

2 x 135 = 270

(Phase -I) 243 -- -- -- --

8 M/s Ultra Tech Cement Ltd. Awapur Cement works, tal. Korpana, Dist. Chandrapur.

Awapur, Tal. Korpana,Dist. Chandrapur.

12 10.8 -- -- -- --

9

M/s Finolex Industries Ltd. Project Office,26/27, Mumbai -Pune Road,Pimpri,Pune-411 018.

At Ranpar-Golap,dist. Ratnagiri

22 19.8 -- -- -- --

10

M/s Reliance Industries Ltd, Maker Chanbers IV,3rd Floor,222,Nariman Point,Mumbai 400 021.

Nagothane 345 -- -- -- -- --

11

M/s Ind-Barath Power (Konkan) Ltd. Plot No.321, Br. Nath Pai Road,RamtirthNagar, Belgaum-590016.

At Village Aonda,Dist. Sawanwadi.

300 -- 270 -- -- --

9

Page 13: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15

STU/TRA�S-PLA�/DOC-4 /WEF 01/04/10

SR. NO.

NAME OF APPLICANT Location of the Plant

Capacity Applied (MW)

MW ( EX - BUS GENERATION )

2010-11 2011-12 2012-13 2013-14 2014-15

12

M/s Wardha Power Company Pvt.Ltd, 8-2-293/82/A/431/A, Road No.22, Jubilee Hills, Hyderabad -500033.

Warora,Dist. Chandrapur

2 x 135 = 270

(Phase -II) 121.5 121.5 -- -- --

13

M/s Finolex Infrastructure Ltd. 26-27,Mumbai -Pune Road, Pimpri, Pune-411 018

At Ranpar-Golap,dist. Ratnagiri

1000 -- -- 450 450 --

14

M/s Indiabulls Real Tech Limited. Indiabulls House, 448-451, Udyog Vihar, Phase, Gurgaon -122 001.

Sinnar 2 X 660 = 1320

-- -- 1188 -- --

15 M/s Sophia Power Company Limited.At Nandgaon pet Ind.Area.Amravati

Nandgaon Peth

Amravati

4 X 660 = 2640

-- -- 1215 -- --

16 M/s Abhijit MADC Nagpur Energy Pvt.Ltd.39, Ambazari Layout, Nagpur-440 033.

At Gumgaon MIHAN SEZ, Dist. Nagpur

4 X 50 = 200

90 -- -- 90 --

17

M/s Maharashtra Vidyut Nigam Ltd. 7th Floor,Shriram Towers, Kingsway, S.V.Patel Marg, Sadar,Nagpur.Nagpur

MIDC Deoli. Dist. Wardha

10 9 -- -- -- --

18

M/s Lloyds Metals & Engineers Ltd, Modern Mills Compound,101, Keshavrao Khade Marg, Jacob circle,Mumbai 400 011.

Ghugus, Dist.

Chandrapur.

4 X30 = 12

27 -- -- -- --

19

M/s IDEAL Energy Projects Ltd, IRB Complex, 2nd Floor, Chandivili Village, Andheri (E), Mumbai -400 072

Near Bela, tal. Umred, Dist.Nagpur

2 X 135 = 270

-- 243 -- -- --

20

M/s JSW Steel Ltd. B-6,Tarapur MIDC Industrial Area, Navapur road, Boiser -401 506.

Tarapur. 30 27 -- -- -- --

21

Uttam Galva Steels Ltd, Donavat Complex,Village Donavat, Tal. Khalapur, Dist. Raigad.

Narangi,Dist. Raigad.

2 X 30 = 60

54 -- -- -- --

22 M/s Jay Mahesh Sugar Industries Ltd, Off. Pawarwadi, tal. Majalgaon, Dist. Beed.

Parewadi,Dist. Beed.

1 X 30 = 30

27 -- -- -- --

10

Page 14: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15

STU/TRA�S-PLA�/DOC-4 /WEF 01/04/10

SR. NO.

NAME OF APPLICANT Location of the Plant

Capacity Applied (MW)

MW ( EX - BUS GENERATION )

2010-11 2011-12 2012-13 2013-14 2014-15

23

M/s Renuka Sugars Ltd.at Deshbakta Ratnnappanna Kumbhar Panchaganga Sahakari Sakhar Karkhana, Ganga Nagar, Ichalkarangi.

Ganga Nagar,

Dist.Ichalkarangi

1 X 30 = 30 27 -- -- -- --

24

M/s Birla carban, Patalganga Project, Village Lohop, Patalganga, Tal.Khalapur, Dist.Raigad

Patalganga,Dist. Raigad.

2 x 15 = 30 27 -- -- -- --

25

M/s Gangakhed Sugar and Energy Pvt. Ltd. C/O Sunil Hitech Engineers Ltd,97, East High Court Road, Ramdaspeth

Gangakhed, Dist.

Parbhani 1 X 30 = 30 27 -- -- -- --

26

M/s Tembhu Power Private Limited, Krishnangan C-7, karad Wakhan Road, Karad Gramin, Tal. Karad, Dist. Satara.

Koregaon, Tal.Karad, Dist. Satara.

3 X 1.5 = 4.5

4.455 -- -- -- --

27

M/s Saikrupa Sakhar Karkhana Ltd, A/P Hiradgaon, Tal.Shigonda,Dist. Kolhapur.

Village Takaliwadi, Tal. Shirol,Dist. Kolhapur.

35 31 -- -- -- --

28 M/s ISMT Ltd. At Lunkad Towers, Viman Nagar, Pune 411 014.

Kurla, Dist. Chandrapur.

40 36 -- -- -- --

29

M/s Urjankur Shree Datta Power Company Ltd.at Datta Nagar, Taluka Shirol, Dist. Kolhapur.

Datta Nagar, Tal.Shirol,

Dist. Kolhapur.

36 32.4 -- -- -- --

30

M/s Urjankur Shree Datta Power Company Ltd.at Shree Tatyasaheb Kore Warna SSKL, Warnanagar, Tal. Panhala, Dist. Kolhapur.

Warnanagar, Tal.

Panhala,Dist. Kolhapur.

44 39.6 -- -- -- --

31 M/s Purna Sahakari Sahkar Karkhana Ltd,At Basmatnagar Dist. Hingoli.

Basmat nagar Dist. Hingoli

18 -- -- 594 -- --

32

M/s Shree Someshwar Sahakari Sakhar Sakhar Karkhana Ltd.,Someshwarnagar, Taluka- Baramati, Dist. Pune

Someshwarnagar, Tal. Baramati, Dist.Pune.

18 16.2 -- -- -- --

11

Page 15: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15

STU/TRA�S-PLA�/DOC-4 /WEF 01/04/10

SR. NO.

NAME OF APPLICANT Location of the Plant

Capacity Applied (MW)

MW ( EX - BUS GENERATION )

2010-11 2011-12 2012-13 2013-14 2014-15

33

M/s Daund Sugar Ltd, ICC Trade Tower, B-Wing 201,Senapati Bapat Road, Pune-411 016.

Village Alegaon, Tal. Daund, Dist. Pune.

18 16.2 -- -- -- --

34

M/s Samarth Sahakari Sakhar Karkhana Ltd, Post. Ankushnagar, Tal. Ambad, Dist. Jalna.

Ankush nagar, Tal.Ambad, Dist. Jalna.

18 16.2 -- -- -- --

35

M/s Vighnahar Sahakari Sakhar Karkhana Ltd, At Nivrutinagar(Dhalewadi),P.O. Shiroli, Tal. Junnar, Dist. Pune.

Nivrutinagar (Dhalewadi)

Tal. Junnar,Dist.

Pune

12 10.8 -- -- -- --

36 M/s Baramati Agro Ltd, Pimpli, Baramati, Dist. Pune, Maharashtra - 413 102.

Pimpli, Tal. Baramati, Dist. Pune.

22 19.8 -- -- -- --

37

M/s Sonhira Sahakari Sakhar Karkhana Ltd, At Mohanrao Kadamnagar, Wangi, Tal. Kadegaon,Dist. Sangli.

Mohanrao Kadam Nagar,

Wangi. Tal. Kadegaon Dist.Sangli.

22 19.8 -- -- -- --

38

M/s Adani Power Maharashtra Ltd, Adani House (Power Division),Plot No.83, Industrial area,Sector-32,Gurgaon-122001

Tiroda,Dist. Gondia

5 X 660 = 3300

-- 1782 1188 -- --

39

M/s Vidarbha Industries Power Ltd, Dhirubai Ambani Knoledge City,I, Block,2nd Floor, Noth Wing, tane Belapur Road, Koperkhiirne- New Mumbai

MIDC Butibori, Nagpur

50 (300) -- 45 -- -- --

40

M/s Bhaurao Chavan Sahakari Sakhar Karkhana Ltd,Laxminagar, Degaon-Yelegaon,Post. Laxminagar, Tal. Ardhapur, Dist. Nanded.

Laxminagar, Tal.Ardhapur

, Dist.Nanded

16.2 14.58 -- -- -- --

41 M/s Gurudatt Sugars Ltd, A/P Takaliwadi, Tal. Shirol,Dist. Kolhapur.

Village Takaliwadi,

Tal. Shirol,Dist. Kolhapur.

15 13.5 -- -- -- --

42

M/s Spark Green energy (Satara), Ltd,"Link Side" 50, Carter Road, Bandra (West), Mumbai -400 050

MIDC Lonand

25 22.5 -- -- -- --

12

Page 16: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15

STU/TRA�S-PLA�/DOC-4 /WEF 01/04/10

SR. NO.

NAME OF APPLICANT Location of the Plant

Capacity Applied (MW)

MW ( EX - BUS GENERATION )

2010-11 2011-12 2012-13 2013-14 2014-15

43

M/s Spark Green energy (Satara), Ltd,"Link Side" 50, Carter Road, Bandra (West),Mumbai -400050

MIDC Newasa

25 22.5 -- -- -- --

44

M/s Yashvantrao Mohite Krishna Sahakari Sakhar Karkhana Ltd, Rehthare Budruk,Tal. Karad, Dist. Satara, P.P.Shivajinagar -415 108.

Rehthare BK., P.O.

Shivajinagar, Tal. Karad, Dist. Satara

16 14 -- -- -- --

45

M/s A.A. Energy Ltd, 101, Nikalas Tower, Central Bazar Road, Ramdaspeth, Nagpur-440 010.

Kh. No.324, Mauza Wadsa,

Desaiganj, Dist.

Gadchiroli

10 9 -- -- -- --

46 M/s Ballarpur Industries Ltd. P.O.Ballarpur Paper Mills, Dist. Chandrapur-4420901

At Ballarpur, Dist.

Chandrapur 10 (40) 9 -- -- -- --

47

M/s Mahati Hydro Power Projects Pvt. Ltd.32-33, Shankarshet Road,Behind S.T.Workshop, Pune

Veer NLBC Small HEP,

Tal. Purandar,Dist. Pune

4.8 4.752 -- -- -- --

48

M/s Mahati Hydro Power Projects Pvt. Ltd.32-33, Shankarshet Road,Behind S.T.Workshop, Pune

Sonwade (Chandoli),Tal. Shirala, Dist.Sangli.

5 4.95 -- -- -- --

49 M/s Dudhaganga Vedganga SSK.Ltd. Mouninagar,Tal. Kagal ,Dist. Kolhapur-416 208.

At Mouninagar

(Bidri) Dist.Klhapur.

20 18 -- -- -- --

50

M/s Technocraft Industries Ltd.A-25. MIDC, Street No.3, Marol Indusrial Area, Andheri (E),Mumbai-400 093.

At Village Dahivali, Murbad.

15 13.5 -- -- -- --

51

M/s R.M Mohite Textile Ltd, R.S.347, Ambapwadi Phata,Off NH4, P.O.1 Wadgaon, Tal. Hatkanagle, Dist.Kolhapur

At Radhanagari Dam Dist. Kolhapur

10 9 -- -- -- --

13

Page 17: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15

STU/TRA�S-PLA�/DOC-4 /WEF 01/04/10

SR. NO.

NAME OF APPLICANT Location of the Plant

Capacity Applied (MW)

MW ( EX - BUS GENERATION )

2010-11 2011-12 2012-13 2013-14 2014-15

52 M/s Dhariwal Infrastructure(P)Ltd.At Tadali, Dist.Chandrapur.

Tadali(Chandrapur

MIDC),Dist. Chandrapur.

300 MW -- -- 270 -- --

53

M/s Shri Vasant Dada Sahakari Sakhar Karkhana Ltd Vithewadi (Lohoner) Tal. Deola, Dist. Nasik

Vithewadi (Lohoner) Tal. Deola, Dist. Nasik.

17 MW 15.3 -- -- -- --

54

M/s ACI Infotech Ltd, A division of Infocom Ltd, 278, Vasan Udyog Bhawan, Opp. Highstreet Phoenix Mill, Lowar Parel(W), Mumbai-400 013

At Bhigwan, Tal. Indapur, Dist. Pune.

15 MW 13.5 -- -- -- --

55 M/s Gopani Iron &Power (India) P.Ltd.A-22 MIDC Growth Centre, Post Tadali-442 406.

MIDC Growth Centre Tadali

8MW(15 MW)

7.2 -- -- -- --

56 M/s Uttam Galva Metallics Ltd,Bhugaon Link Road,Wardha -442001.

At Bhugaon Link Road, Wardha.

10 MW (15 MW)

9 -- -- -- --

57 M/s Grace Industries Ltd, A-23, MIDC Estate, Tadali Growth Centre, Chandrapur

At MIDC Estate Tadali.

28 MW(33 MW)

25.2 -- -- -- --

58

M/s Shree Virangana Steels Pvt. Ltd. 126-128, 1st Floor, Shriram Tower, Kingswamy Sadar, near NIT office ,Nagpur-440001

At Mauja Ukerwahi, Village Heti, Umrer Road, Nagpur.

22 MW(30 MW)

19.8 -- -- -- --

59

M/s RPL URJA (Division of Rasoya Protiens Ltd), Village Kalmana, Tal.Wani, Dist.Yavatmal.

Village Kalmana, Tal. Wani,

Dist. Yavatmal

8.5MW (10 MW)

7.65 -- -- -- --

60 M/s B.S.Ispat Ltd.Survey No.97, Village Salori, Yensa, Tal. Warora, dist. Chandrapur.

Village Salori,

Yensa, Tal. Warora

15 MW 13.5 -- -- -- --

61 M/sVikas SSK. Ltd, Vaishali Nagar, Tal. Nivali, Dist. Latur.

At Vaishli Nagar, tal. Nivali. Dist.

Latur

18 MW 16.2 -- -- -- --

62 M/s Shankar Sahakari Sakhar Karkhana Ltd. -Kaulage, Tal.Kagal Dist.Kolahapur.

At Sadashivnag

ar, Tal. Malshiras,

Dist.Solapur.

17.5MW (20 MW)

15.75 -- -- -- --

14

Page 18: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15

STU/TRA�S-PLA�/DOC-4 /WEF 01/04/10

SR. NO.

NAME OF APPLICANT Location of the Plant

Capacity Applied (MW)

MW ( EX - BUS GENERATION )

2010-11 2011-12 2012-13 2013-14 2014-15

63

M/s Sadashivrao Mandalik Kagal Taluka SSK.Ltd, Sadashiv Nagar, Hamidwada -Kaulage, Tal.Kagal Dist.Kolahapur.

At Sadashivnag

ar, Hamidwada,

Tal. Kagal,Dist. Kolhapur.

12 MW 10.8 -- -- -- --

64

M/s Vayunandana Power Ltd, 12-2-460,Plot No.2, New Huda layout, Gudimalkapur, Mahadipatnam, Hyderabad-500 028.

At Village Kaneri,Dist. Gadchiroli.

10MW(12 MW)

9 -- -- -- --

65

M/s M/s Bombay Rayon Fashions Ltd,Plot No.C-7, Tarapur MIDC, Near Tarapur Vidya Mandir, Boisar, Tal. Palghar, Dist. Thane.

At Tarapur MIDC

6MW(8 MW)

5.4 -- -- -- --

66

M/s Shri Shankar Maharshi Shankarrao Mohite-Patil SSK Ltd, Shankarnagar, Akluj Tal. Malshiras, Dist. Solapur.

At Akluj,Tal. Malshiras, Solapur

33 MW 29.7 -- -- -- --

67

M/s Pepsico India Holdings Pvt. Ltd, L.U.Gadkari Marg, Village Anik,Mahul, Chembur,Mumbai 400 074.

Sadawaghapur, Dist. Satara

1.85 MW -- 1.665 -- -- --

68

M/s Shree Renuka Sugars Ltd,7th floor, Devchand House, Shiv sagar Estate, Dr.Annie Beasant Road, Worli, Mumbai-400 018.

At Ajinkyatara SSK,Shahun

agar, Shendre, Satara

22 MW(24 MW)

20 -- -- -- --

69

M/s Dwarkadhish SSSK Ltd, KarkhanaShalivahana Projects Ltd,1582,7th Floor, Minerva Complex, S.D. Road, Secunderabad.

At Village Seware,

Taharabad, tal.Satana,Dist. Nasik

10MW 9 -- -- -- --

70

M/s Mahalaxmi Vidyut Private Ltd, 363/11, Balaji Niwas,Deep Bangalow Chowk, Shiwaji Nagar, Pune-411 016.

At Konal, Sindhudurg

2 X 5 MW 9 -- -- -- --

71

M/s Kalyani Renewable

Energy India Ltd,D.No.5-

6,Prathipadu Village,

Tadepalligudem, west

Godavari, Dist. A.P.534 146.

At Balapur MIDC, Dist.

Akola

13.8 MW

(15 MW) 12.42 -- -- -- --

15

Page 19: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15

STU/TRA�S-PLA�/DOC-4 /WEF 01/04/10

SR. NO.

NAME OF APPLICANT Location of the Plant

Capacity Applied (MW)

MW ( EX - BUS GENERATION )

2010-11 2011-12 2012-13 2013-14 2014-15

72

M/s The Sanjivani (Takli)

Sahakari Sakhar Karkhana

Ltd.Sahajanandnagar,

P.O.Shinganapur - 423 603,

Tal. Kopargaon, Dist.

Ahmednagar

Sahajanandnagar, Tal. Kopargaon,

Dist. Ahmednagar

.

6.6

MW(15.9

MW)

-- 5.94 -- -- --

73

M/s Kisanveer Satara Sahakari

Sakhar Karkhana Ltd,

Kianveer Nagar, Tal. Wai,

dist.Satara.

At Kisan Veer Nagar,

Tal. Wai.Dist. Satara

19.56MW

(22 MW) 17.604 -- -- -- --

74

M/s Ideal Energy Projects

Ltd,122, 2nd Floor, Telecom

Nagar, Near Ranta Pratap

square, Nagpur-440 022.

Kundal, Tal.

Palus, Dist.

Sangli.

Addil.1 X

270 -- -- 243 -- --

75

M/s Shriram Jawahar

Shetkari Sahakari Sakhar

Udyog,Phaltan,

Tal.Phaltan,Dist.Satara

Phaltan,

Tal.Satara

1.2 MW

(1.5 MW) 1.08 -- -- -- --

76

M/s Hindustan Electricity

Generation Company Pvt.

Ltd.Olympia, Central

Avenue, Hiranandani

Business Park.

At Navlakhumbre, pune

350 MW 339.5 -- -- -- --

77

M/s Vidarbha Energy and

Infrastructure P.Ltd, 4th Floor,

MG House, R.T. Road, Civil

Lines, Nagpur.

Village Choramba,

Tal. Ghatangi,

Dist. Yeotmal.

10 MW 9 -- -- -- --

78

M/s Malegaon Sahakari

Sakhar Karkhana Ltd.At Post.

Shivajinagar,Tal. Baramati,

Dist. Pune.

Village Shivajinagar,

tal. Baramati, Dist.Pune

14MW(2

1 MW) 12.6 -- -- -- --

79

M/s M/s Greta Energy Ltd,

Station Road, Brahampuri-

441206.

Dist. Chandrapur.

Mul

MIDC,Tal

Mul, Dist.

Chandrapur

15 MW 13 -- -- -- --

80

M/s Shree Sidhabali Ispat Ltd,

Plot No.C-2, MIDC Area,

Tadali, Dist. Chandrapur-

442406.

C-2 MIDC

Area

Tadali,Dist.

Chandrapur.

10MW(2

0 MW) 9 -- -- -- --

16

Page 20: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15

STU/TRA�S-PLA�/DOC-4 /WEF 01/04/10

SR. NO.

NAME OF APPLICANT Location of the Plant

Capacity Applied (MW)

MW ( EX - BUS GENERATION )

2010-11 2011-12 2012-13 2013-14 2014-15

81

M/s Renuka Sugar Ltd,

7th Floor, Devchand House,

Shiv Sagar Estate,

Dr. Annie Besant Road,

Worli, Mumbai-400 018.

Balaji

nagar,

Nandur,

Tal.

Mangalwed

a Dist.

Solapur

26 MW

(30 MW) 23 -- -- -- --

82

M/s Kukadi Sahakari Sakhar

Karkhana Ltd,

At Pimpalgaon Pisa, Tal.

Shrigonda, Dist.Ahmednagar.

Pimpalgaon

Pisa, Tal.

Shrigonda,

Dist.Ahmed

nagar

10MW(1

6 MW) 9 -- -- -- --

Total 3021 2712 5841 990 0

Existing EX BUS Generation 224 3245 5957 11798 12788

Year Wise EX - BUS Availability 3245 5957 11798 12788 12788

Note :1. The year wise date of commissioning is considered as per the dates indicated in application forms. 2. ( ) The figures indicated in the brackets are Installed capacities of Generating Plant

17

Page 21: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15

STU/TRA�S-PLA�/DOC-4 /WEF 01/04/10

Table – 8.2.2 Proposed Yearwise Generation Addition by IPPs'/ Biogas/Bagasse/Biomass Plants etc. for which PPA signed with Various Distribution Companies in State

SR. NO.

NAME OF APPLICANT Location of the Plant

CapacityApplied (MW)

Available Generation in MW (PPA Signed )

2010-11 2011-12 2012-13 2013-14 2014-15

1

M/s JSW Energy Ltd. Jindal Mansion, 5A.Dr.G.Deshmukh Marg. Mumbai 400 026.

Jaigad 4 X 300= 1200MW

1080 -- -- -- --

2

M/s M/s Gupta Energy Pvt. Ltd7th Floor,Shriram Towers, Kingsway, Tal. Ghugus, Dist.Chandrapur.

Usegaon, Dist.

Chandrapur

2 X 60 MW = 120

MW 108 -- -- -- --

3

M/s Emco Energy Ltd.Warora, Plot No.F-5, Road No.28, wagle industrial Estate,Thane-400 604.

Warora 2 x 135

MW = 270 MW

-- 200 -- -- --

4

M/s Wardha Power Company Pvt.Ltd, 8-2-293/82/A/431/A, Road No.22, Jubilee Hills, Hyderabad -500033.

Warora,Dist. Chandrapur

2 x 135 MW = 270

MW (Phase -I)

50 100 -- -- --

5 M/s Ultra Tech Cement Ltd. Awapur Cement works, tal. Korpana, Dist. Chandrapur.

Awapur, Tal. Korpana,Dist. Chandrapur.

12 MW 10.8 -- -- -- --

6

M/s Finolex Industries Ltd. Project Office,26/27, Mumbai -Pune Road,Pimpri,Pune-411 018.

At Ranpar-Golap,dist. Ratnagiri

22 MW 19.8 -- -- -- --

7

M/s Wardha Power Company Pvt.Ltd, 8-2-293/82/A/431/A, Road No.22, Jubilee Hills, Hyderabad -500033.

Warora,Dist. Chandrapur

2 x 135 MW = 270

MW (Phase -II)

-- 150 -- -- --

8

M/s Finolex Infrastructure Ltd. 26-27,Mumbai -Pune Road, Pimpri, Pune-411 018

At Ranpar-Golap,dist. Ratnagiri

1000MW -- -- 450 -- --

9

M/s Indiabulls Real Tech Limited. Indiabulls House, 448-451, Udyog Vihar, Phase, Gurgaon -122 001.

Sinnar 2 X 660 MW

-- -- 450 -- --

10 M/s Sophia Power Company Limited.At Nandgaon pet Ind.Area.Amravati

Nandgaon Peth

Amravati

5 X 270 MW

-- -- 750 -- --

11 M/s Abhijit MADC Nagpur Energy Pvt.Ltd.39, Ambazari Layout, Nagpur-440 033.

At Gumgaon MIHAN SEZ, Dist. Nagpur

4 X 50 MW

90 -- -- 90 --

18

Page 22: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15

STU/TRA�S-PLA�/DOC-4 /WEF 01/04/10

SR. NO.

NAME OF APPLICANT Location of the Plant

CapacityApplied (MW)

Available Generation in MW (PPA Signed )

2010-11 2011-12 2012-13 2013-14 2014-15

12

M/s Maharashtra Vidyut Nigam Ltd. 7th Floor,Shriram Towers, Kingsway, S.V.Patel Marg, Sadar,Nagpur.Nagpur

MIDC Deoli. Dist. Wardha

10 MW 9 -- -- -- --

13

M/s IDEAL Energy Projects Ltd, IRB Complex, 2nd Floor, Chandivili Village, Andheri (E), Mumbai -400 072

Near Bela, tal. Umred, Dist.Nagpur

2 X 135 MW

-- 200 -- -- --

14

M/s JSW Steel Ltd. B-6,Tarapur MIDC Industrial Area, Navapur road, Boiser -401 506.

Tarapur. 30 MW 27 -- -- -- --

15

Uttam Galva Steels Ltd, Donavat Complex,Village Donavat, Tal. Khalapur, Dist. Raigad.

Narangi,Dist. Raigad.

2 X 30 MW

54 -- -- -- --

16

M/s Jay Mahesh Sugar Industries Ltd, Off. Pawarwadi, tal. Majalgaon, Dist. Beed.

Parewadi,Dist. Beed.

1 X 30 MW

27 -- -- -- --

17

M/s Renuka Sugars Ltd.at Deshbakta Ratnnappanna Kumbhar Panchaganga Sahakari Sakhar Karkhana, Ganga Nagar, Ichalkarangi.

Ganga Nagar,

Dist.Ichalkarangi

1 X 30 MW

27 -- -- -- --

18

M/s Gangakhed Sugar and Energy Pvt. Ltd. C/O Sunil Hitech Engineers Ltd,97, East High Court Road, Ramdaspeth

Gangakhed, Dist.

Parbhani

1 X 30 MW

27 -- -- -- --

19

M/s Tembhu Power Private Limited, Krishnangan C-7, karad Wakhan Road, Karad Gramin, Tal. Karad, Dist. Satara.

Koregaon, Tal.Karad, Dist. Satara.

3 X 1.5 MW

4.455 -- -- -- --

20 M/s Saikrupa Sakhar Karkhana Ltd, A/P Hiradgaon, Tal.Shigonda,Dist. Kolhapur.

Village Takaliwadi,

Tal. Shirol,Dist.

Kolhapur.

35 MW 31 -- -- -- --

21 M/s ISMT Ltd. At Lunkad Towers, Viman Nagar, Pune 411 014.

Kurla, Dist. Chandrapur.

40 MW 36 -- -- -- --

22

M/s Urjankur Shree Datta Power Company Ltd.at Datta Nagar, Taluka Shirol, Dist. Kolhapur.

Datta Nagar, Tal.Shirol,

Dist.Kolhapur.

36 MW 32.4 -- -- -- --

19

Page 23: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15

STU/TRA�S-PLA�/DOC-4 /WEF 01/04/10

SR. NO.

NAME OF APPLICANT Location of the Plant

Capacity Applied (MW)

Available Generation in MW (PPA Signed )

2010-11 2011-12 2012-13 2013-14 2014-15

23

M/s Urjankur Shree Datta Power Company Ltd.at Shree Tatyasaheb Kore Warna SSKL, Warnanagar, Tal. Panhala, Dist. Kolhapur.

Warnanagar, Tal.

Panhala,Dist. Kolhapur.

44 MW 39.6 -- -- -- --

24 M/s Purna Sahakari Sahkar Karkhana Ltd,At Basmatnagar Dist. Hingoli.

At Basmatnaga

r Dist. Hingoli

18 MW 16.2 -- -- -- --

25

M/s Shree Someshwar Sahakari Sakhar Sakhar Karkhana Ltd.,Someshwarnagar, Taluka- Baramati, Dist. Pune

At Someshwarnagar, Tal. Baramati, Dist.Pune.

18MW 16.2 -- -- -- --

26

M/s Daund Sugar Ltd, ICC Trade Tower, B-Wing 201,Senapati Bapat Road, Pune-411 016.

Village Alegaon,

Tal. Daund, Dist. Pune.

18 MW 16.2 -- -- -- --

27

M/s Samarth Sahakari Sakhar Karkhana Ltd, Post. Ankushnagar, Tal. Ambad, Dist. Jalna.

At Ankushnaga

r, Tal.Ambad, Dist. Jalna.

18 MW 16.2 -- -- -- --

28

M/s Vighnahar Sahakari Sakhar Karkhana Ltd, At Nivrutinagar(Dhalewadi),P.O. Shiroli, Tal. Junnar, Dist. Pune.

At Nivrutinagar(Dhalewadi)

Tal. Junnar,Dist.

Pune

12 MW 10.8 -- -- -- --

29 M/s Baramati Agro Ltd, Pimpli, Baramati, Dist. Pune, Maharashtra - 413 102.

At Pimpli, Tal.

Baramati, Dist. Pune.

22 MW 19.8 -- -- -- --

30

M/s Sonhira Sahakari Sakhar Karkhana Ltd, At Mohanrao Kadamnagar, Wangi, Tal. Kadegaon,Dist. Sangli.

Wangi. Tal. Kadegaon Dist.Sangli.

22 MW 19.8 -- -- -- --

31

M/s Adani Power Maharashtra Ltd, Adani House (Power Division),Plot No.83, Industrial area,Sector-32,Gurgaon

Tiroda,Dist. Gondia

5 X 660 MW -- 1320 1200 -- --

32

M/s Vidarbha Industries Power Ltd, Dhirubai Ambani Knoledge City,I, Block,2nd Floor, Noth Wing, tane Belapur Road, Koperkhiirne- New Mumbai

MIDC Butibori, Nagpur

1 X 50 MW out of 300

MW -- 45 -- -- --

20

Page 24: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15

STU/TRA�S-PLA�/DOC-4 /WEF 01/04/10

SR. NO.

NAME OF APPLICANT Location of the Plant

Capacity Applied (MW)

Available Generation in MW (PPA Signed )

2010-11 2011-12 2012-13 2013-14 2014-15

33

M/s Spark Green energy (Satara), Ltd,"Link Side" 50, Carter Road, Bandra (West), Mumbai -400 050

MIDC Lonand

25 MW 22.5 -- -- -- --

34

M/s Spark Green energy (Satara), Ltd,"Link Side" 50, Carter Road, Bandra (West), Mumbai -400 050

MIDC Newasa

25 MW 22.5 -- -- -- --

35

M/s Yashvantrao Mohite Krishna Sahakari Sakhar Karkhana Ltd, Rehthare Budruk,Tal. Karad, Dist. Satara, P.P.Shivajinagar -415 108.

Rehthare BK., P.O.

Shivajinagar, Tal. Karad, Dist. Satara

16 MW 14 -- -- -- --

36

M/s A.A. Energy Ltd, 101, Nikalas Tower, Central Bazar Road, Ramdaspeth, Nagpur-440 010.

Kh. No.324, Mauza Wadsa,

Desaiganj, Dist.

Gadchiroli

10 MW 9 -- -- -- --

37 M/s Ballarpur Industries Ltd. P.O.Ballarpur Paper Mills, Dist. Chandrapur-4420901

At Ballarpur, Dist.

Chandrapur

10 MW (40 MW)

9 -- -- -- --

38

M/s Mahati Hydro Power Projects Pvt. Ltd.32-33, Shankarshet Road,Behind S.T.Workshop, Pune

Veer NLBC Small HEP,

Tal. Purandar,Dist. Pune

4.8 MW 4.752 -- -- -- --

39

M/s Mahati Hydro Power Projects Pvt. Ltd.32-33, Shankarshet Road,Behind S.T.Workshop, Pune

Sonwade (Chandoli),Tal. Shirala, Dist.Sangli.

5 MW 4.95 -- -- -- --

40

M/s Dudhaganga Vedganga SSK.Ltd. Mouninagar,Tal. Kagal ,Dist. Kolhapur-416 208.

At Mouninagar

(Bidri) Dist.Klhapur.

20 MW 18 -- -- -- --

41

M/s R.M Mohite Textile Ltd, R.S.347, Ambapwadi Phata,Off NH4, P.O.1 Wadgaon, Tal. Hatkanagle, Dist.Kolhapur

At Radhanagari Dam Dist. Kolhapur

10 MW 9 -- -- -- --

42

M/s Shri Vasant Dada Sahakari Sakhar Karkhana Ltd Vithewadi (Lohoner) Tal. Deola, Dist. Nasik

Vithewadi (Lohoner) Tal. Deola, Dist. Nasik.

17 MW 15.3 -- -- -- --

21

Page 25: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15

STU/TRA�S-PLA�/DOC-4 /WEF 01/04/10

SR. NO.

NAME OF APPLICANT Location of the Plant

CapacityApplied (MW)

Available Generation in MW (PPA Signed )

2010-11 2011-12 2012-13 2013-14 2014-15

43

M/s Gopani Iron &Power (India) P.Ltd.A-22 MIDC Growth Centre, Post Tadali-442 406.

MIDC Growth Centre Tadali

8MW (15 MW)

7.2 -- -- -- --

44 M/s Uttam Galva Metallics Ltd,Bhugaon Link Road,Wardha -442001.

At Bhugaon Link Road, Wardha.

10 MW (15 MW)

9 -- -- -- --

45

M/s Shree Virangana Steels Pvt. Ltd. 126-128, 1st Floor, Shriram Tower, Kingswamy Sadar, near NIT office ,Nagpur-440001

At Mauja Ukerwahi, Village Heti, Umrer Road, Nagpur.

22 MW (30 MW)

19.8 -- -- -- --

46

M/s RPL URJA (Division of Rasoya Protiens Ltd), Village Kalmana, Tal.Wani, Dist.Yavatmal.

Village Kalmana, Tal. Wani,

Dist. Yavatmal

8.5MW (10 MW)

7.65 -- -- -- --

47 M/s Shankar Sahakari Sakhar Karkhana Ltd. -Kaulage, Tal.Kagal Dist.Kolahapur.

Tal. Malshiras,

Dist.Solapur.

17.5MW (20 MW)

15.75 -- -- -- --

48

M/s Vayunandana Power Ltd, 12-2-460,Plot No.2, New Huda layout, Gudimalkapur, Mahadipatnam, Hyderabad-500 028.

At Village Kaneri,Dist. Gadchiroli.

10MW (12 MW)

9 -- -- -- --

49

M/s Pepsico India Holdings Pvt. Ltd, L.U.Gadkari Marg, Village Anik,Mahul, Chembur,Mumbai 400 074.

Sadawaghapur, Dist. Satara

1.85 MW -- 1.665 -- -- --

50

M/s Shree Renuka Sugars Ltd,7th floor, Devchand House, Shiv sagar Estate, Dr.Annie Beasant Road, Worli, Mumbai-400 018.

Shahunagar, Shendre,Sat

ara

22 MW (24 MW)

20 -- -- -- --

51

M/s Kalyani Renewable Energy India Ltd,D.No.5-6,Prathipadu Village, Tadepalligudem, west Godavari, Dist. A.P.534 146.

At Balapur MIDC, Dist.

Akola

13.8 MW

(15 MW) 12.42 -- -- -- --

52

M/s The Sanjivani (Takli) Sahakari Sakhar Karkhana Ltd.Sahajanandnagar, P.O.Shinganapur - 423 603, Tal. Kopargaon, Dist. Ahmednagar

Tal. Kopargaon,

Dist. Ahmednagar

6.6 MW

(15.9 MW) -- 5.94 -- -- --

22

Page 26: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15

STU/TRA�S-PLA�/DOC-4 /WEF 01/04/10

SR. NO.

NAME OF APPLICANT Location of the Plant

CAPACITY APPLIED (MW)

Available Generation in MW (PPA Signed )

2010-11 2011-12 2012-13 2013-14 2014-15

53

M/s Kisanveer Satara Sahakari Sakhar Karkhana

Ltd, Kianveer Nagar, Tal. Wai, dist.Satara.

At Kisan Veer Nagar,

Tal. Wai.Dist. Satara

19.56MW (22 MW)

17.604 -- -- -- --

54

M/s Malegaon Sahakari Sakhar Karkhana Ltd.At Post. Shivajinagar,Tal. Baramati,

Dist. Pune.

Village Shivajinagar

,tal. Baramati,Dis

t.Pune

14MW (21 MW)

12.6 -- -- -- --

55

M/s Kukadi Sahakari Sakhar Karkhana Ltd,

At Pimpalgaon Pisa, Tal. Shrigonda, Dist.Ahmednagar.

Tal. Shrigonda,

Dist. Ahmednagar

10MW (16 MW)

9 -- -- -- --

Total 2057 2023 2850 90 0

Existing EX BUS Generation 224 2281 4304 7154 7244

Year Wise EX - BUS Availability 2281 4304 7154 7244 7244

23

Page 27: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15

STU/TRA�S-PLA�/DOC-4 /WEF 01/04/10

Table – 8.4 – Evacuation Arrangement for existing IPP /CPP/Biomass/Bagasse/Biogas

based Plants

SR. NO.

NAME OF APPLICANT Location of the

Plant

CAPACITY APPLIED (MW)

Evacuation Arrangement

1 M/s Indrajit Infrastructure Pvt.Ltd. Modern Centre,'B' Wing, 2nd Floor, Sane Guruji Marg, Mahalaxmi, Mumbai-400011.

Bhugaon (Wardha-II)

2 x 40 MW = 80 MW

220kV line from their plant upto 220 kV Bhugaon S/S.

2 M/s. Purty Sakhar Karkhana, Dist. Wardha.

Wardha. 1 x 24 = 24 MW

LILO on 220 kV Khaparkheda – Wardha S/c at 220 kV Purty S/s

3 M/s Ind-barath Engineers (Maharashtra ) Ltd.Plot No.30-A,Road No.1, Film Nagar,Jubillee Hills, Hyderabad-500 033.

Village Kharab Khandgaon,,Dist.

Nanded

20MW 132 kV line from their plant upto 132 kV Mukhed S/S.

4 M/s Lokmangal Sugar Ethanol & Co-Generation Industries Ltd, 33/A, Sahyadri Nagar,Hotgi Road, Solapur -413 003.

Bhandarkavathe, Tal. South Solapur, Dist. Solapur.

1 X 15 MW 132 kV line from their plant upto 132 kV Mandrup S/S

5 M/s M/s Hotel Leelaventure Ltd, The Leela Kempinski, Sahar, Andheri (E), Mumbai 400 059.

Village

Khaparale,Tal.

Sinnar dist Nasik.

4.5 MW 33 kV line from their plant at Khaprale, upto MSETCL 132 /33 kV Khaprale S/S-

6 M/s Hotel ITC the Maratha, Near Blue Dart Office,Sahar Airport Road, Mumabi -400 099.

Village Khaprale (Sinnar),Dist.

Nasik

6 MW 33 kV line from there proposed plant at Khaprale, Sinnar upto MSETCL 132/33 kV Khaprale S/S,

7 M/s Renuka Sugars Ltd.at Deshbakta Ratnnappanna Kumbhar Panchaganga Sahakari Sakhar Karkhana, Ganga Nagar, Ichalkarangi.

Ganga Nagar, Dist.Ichalkarangi

1 X 30 MW LILO on 110 kV Kolhapur-II -Ichalkarangi Line.

8 M/s Daund Sugar Ltd, ICC Trade Tower, B-Wing 201,Senapati Bapat Road, Pune-411 016.

Village Alegaon,

Tal. Daund, Dist.

Pune.

18 MW LILO on 132 kV Daund -Shrigonda Line.

9 M/s Baramati Agro Ltd, Pimpli, Baramati, Dist. Pune

At Pimpli, Tal. Baramati, Dist.

Pune.

22 MW 220 kV lines from their plant to Bhigwan S/S.

10 M/s Finolex Industries Ltd. Project Office,26/27, Pimpri,Pune

At Ranpar-Golap,dist. Ratnagiri

22 MW 220 kV line from their plant upto 220 kV Pawas S/S.

11 M/s Kranti Sahakari

Sakhar Karkhana, Kundal,

Dist.sangli

Kundal, Tal.

Palus, Dist.

Sangli.

6.65 MW

(8.85 MW)

33 kV lines from your plant at Kundal, Tal. Palus,Dist Sangli upto MSETCL 110/33 kV Kundal S/S

24

Page 28: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15

STU/TRA�S-PLA�/DOC-4 /WEF 01/04/10

Table – 8.5 – Evacuation Arrangement for proposed IPP /CPP/Biomass/Bagasse/Biogas based Plants

SR. NO.

NAME OF APPLICANT Location of the Plant

CAPACITY APPLIED (MW)

Proposed Evacuation Arrangement

1 M/s JSW Energy Ltd. Jindal Mansion, 5A.Dr.G.Deshmukh Marg. Mumbai 400 026.

Jaigad 4 X 300 = 1200

1) 400 kV Jaigad-New Koyna D/C with Quad Cond. 2) 400 kV Jaigad-Karad D/C with quad cond.

2 M/s M/s Gupta Energy Pvt. Ltd.(Formerly Gupta Coal Fields and Washaries Ltd.) 7th Floor,Shriram Towers, Kingsway, Nagpur 440 001Tal. Ghugus, Dist.Chandrapur.

Usegaon, Dist.

Chandrapur

2 X 60 = 120 1) 220 kV Ghugus -Chandrapur MIDC D/C line.

3 M/s Nagpur Energy Infrastructure Ltd.(Formerly Baidyanath Power &Mining), 5, Temple Road,Civil Lines, Nagpur-440 001.

Near Bhadravati,Dist. Chandrapur.

250 + 250 + 500 = 1000

1) 400 kV Bhadravati Plant-Chandrapur-II D/C line with quad. Cond.

4 M/s Patni Energy Ltd. 302-304, Regent Chembers,Nariman Point, Mumbai 400021.

Medhekar, Tal.Alibag.

2 x 135 = 270 1) 220 kV Patni Plant -Wadkhal D/C line.

5 M/s Emco Energy Ltd.Warora, Plot No.F-5, Road No.28, wagle industrial Estate,Thane-400 604.

Warora 2 x 135 = 270 1) 220 kV Emco Plant -Warora D/C line

6 M/s Sun-Flag Iron and Steel Co.Ltd. Bhandara Road, Bhandara-441 905

At Warthi, Dist. Bhandara

2 x 15 = 30 1) 220 kV Lines from the plant to 220 kV Bhandara S/S

7 M/s Wardha Power Company Pvt.Ltd, 8-2-293/82/A/431/A, Road No.22, Jubilee Hills, Hyderabad -500033.

Warora,Dist. Chandrapur

2 x 135 = 270 (Phase -I)

1) 220 kV Warora plant - Warora D/C line

8 M/s Ultra Tech Cement Ltd. Awapur Cement works, tal. Korpana, Dist. Chandrapur.

Awapur, Tal. Korpana,Dist. Chandrapur.

12 1) 220 kV line from their Plant at Awapur upto 220 kV Gadchandur

9 M/s Finolex Industries Ltd. Project Office,26/27, Mumbai -Pune Road,Pimpri,Pune-411 018.

At Ranpar-Golap,dist. Ratnagiri

22 1) 220 kV line from their plant upto 220 kV Pawas S/S.

10 M/s Reliance Industries Ltd, Maker Chanbers IV,3rd Floor,222,Nariman Point,Mumbai 400 021.

Nagothane 345 1) 220 kV RIL Plant-Nagothane D/C line

25

Page 29: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15

STU/TRA�S-PLA�/DOC-4 WEF 01/04/10

SR. NO.

NAME OF APPLICANT Location of the Plant

CAPACITY APPLIED (MW)

Proposed Evacuation Arrangement

11 M/s Ind-Barath Power (Konkan) Ltd. Plot No.321, Br. Nath Pai Road,RamtirthNagar, Belgaum-590016.

At Village Aonda,Dist. Sawanwadi.

300 1) From their Plant at Aronda upto 220 kV Sawantwadi S/S.

12 M/s Wardha Power Company Pvt.Ltd, 8-2-293/82/A/431/A, Road No.22, Jubilee Hills, Hyderabad -500033.

Warora,Dist. Chandrapur

2 x 135 = 270 (Phase

-II)

1) 220 kV line from Warora Plant to 400 kV Warora S/S by making LILO on 220 kV Warora-Bhugaon Line.

13 M/s Finolex Infrastructure Ltd. 26-27,Mumbai -Pune Road, Pimpri, Pune-411 018

At Ranpar-Golap,dist. Ratnagiri

1000 1) 400 kV D/C line from Golap to Korad-II S/S

14 M/s Indiabulls Real Tech Limited. Indiabulls House, 448-451, Udyog Vihar, Phase, Gurgaon -122 001.

Sinnar 2 X 660 = 1320

1) 400 kV Sinnar - Babhaleshwar D/C line with quad cond.

15 M/s Sophia Power Company Limited.At Nandgaon pet Ind.Area.Amravati

Nandgaon Peth

Amravati

4 X 660 = 2640

1) 400 kV Nandgaon Peth- Akola D/C line with quad cond. 2) LILO on Akola-Koradi-II S/C at Nandgaon Peth.

16 M/s Abhijit MADC Nagpur Energy Pvt.Ltd.39, Ambazari Layout, Nagpur-440 033.

At Gumgaon MIHAN SEZ, Dist. Nagpur

4 X 50 = 200

1) LILO on 220 kV Wardha-I to Ambazari S/C line

17 M/s Maharashtra Vidyut Nigam Ltd. 7th Floor,Shriram Towers, Kingsway, S.V.Patel Marg, Sadar,Nagpur.Nagpur

MIDC Deoli. Dist. Wardha

10 1) 132 kV D/C line from Plant at MIDC Deoli - Deoli S/S.

18 M/s Lloyds Metals & Engineers Ltd, Modern Mills Compound,101, Keshavrao Khade Marg, Jacob circle,Mumbai 400 011.

Ghugus, Dist. Chandrapur.

4 X30 = 12 1) 220 kV D/C line from From Plant to Matradevi.

19 M/s IDEAL Energy Projects Ltd, IRB Complex, 2nd Floor, Chandivili Village, Andheri (E), Mumbai -400 072

Near Bela, tal. Umred, Dist.Nagpur

2 X 135 = 270

1) 220 kV D/C line from Bela to Purti 2) LILO on K'khed-Wardha-I at Purti.

20 M/s JSW Steel Ltd. B-6,Tarapur MIDC Industrial Area, Navapur road, Boiser -401 506.

Tarapur. 30 1) 220 kV D/C line from Tarapur to Boiser-II

26

Page 30: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15

STU/TRA�S-PLA�/DOC-4 WEF 01/04/10

SR. NO.

NAME OF APPLICANT Location of the Plant

CAPACITY APPLIED (MW)

Proposed Evacuation Arrangement

21 Uttam Galva Steels Ltd, Donavat Complex,Village Donavat, Tal. Khalapur, Dist. Raigad.

Narangi,Dist. Raigad.

2 X 30 = 60 1) 100 kV D/C line from Donavat to Tambati S/S

22 M/s Jay Mahesh Sugar Industries Ltd, Off. Pawarwadi, tal. Majalgaon, Dist. Beed.

Parewadi,Dist. Beed.

1 X 30 = 30 1) 132 kV D/C line Parewadi to 132 kV Majalgaon S/S.

23 M/s Renuka Sugars Ltd.at Deshbakta Ratnnappanna Kumbhar Panchaganga Sahakari Sakhar Karkhana, Ganga Nagar, Ichalkarangi.

Ganga Nagar, Dist.Ichalkarangi

1 X 30 = 30 1) LILO on 110 kV Kolhapur – Ichalkarangi Line

24 M/s Birla carban, Patalganga Project, Village Lohop, Patalganga, Tal.Khalapur, Dist.Raigad

Patalganga,Dist. Raigad.

2 x 15 = 30 1) 100 kV D/C line from Lohop to Patalganga S/S

25 M/s Gangakhed Sugar and Energy Pvt. Ltd. C/O Sunil Hitech Engineers Ltd,97, East High Court Road, Ramdaspeth

Gangakhed, Dist. Parbhani

1 X 30 = 30 1) 132 kV D/C line from their Plant to 132 kV Gangakhed S/S.

26 M/s Tembhu Power Private Limited, Krishnangan C-7, karad Wakhan Road, Karad Gramin, Tal. Karad, Dist. Satara.

Koregaon, Tal.Karad, Dist.

Satara.

3 X 1.5 = 4.5

1) 110 kV D/C line form Plant to Tembhu S/S.

27 M/s Saikrupa Sakhar Karkhana Ltd, A/P Hiradgaon, Tal.Shigonda,Dist. Kolhapur.

Village Takaliwadi, Tal. Shirol,Dist. Kolhapur.

35 1) 132 kV lines from their plant to 132 kV Shrigonda S/S

28 M/s ISMT Ltd. At Lunkad Towers, Viman Nagar, Pune 411 014.

Kurla, Dist. Chandrapur.

40 1) From their Plant to 132 kV level of 220/132 kV Hinganghat S/S

29 M/s Urjankur Shree Datta Power Company Ltd.at Datta Nagar, Taluka Shirol, Dist. Kolhapur.

Datta Nagar, Tal.Shirol,

Dist.Kolhapur.

36 1) 110 kV D/C line from Dattanagar to Jaysingpur S/S.

30 M/s Urjankur Shree Datta Power Company Ltd.at Shree Tatyasaheb Kore Warna SSKL, Warnanagar, Tal. Panhala, Dist. Kolhapur.

Warnanagar, Tal.

Panhala,Dist. Kolhapur.

44 1) 132 kV line from Warnanagar to 132-110 kV Wathar S/S.

27

Page 31: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15

STU/TRA�S-PLA�/DOC-4 WEF 01/04/10

SR. NO.

NAME OF APPLICANT Location of the

Plant

CAPACITY APPLIED (MW)

Proposed Evacuation Arrangement

31 M/s Purna Sahakari Sahkar Karkhana Ltd,At Basmatnagar Dist. Hingoli.

At Basmatnagar Dist. Hingoli

18 1) 132 kV lines from their plant to 132 kV Basmatnagar S/S.

32 M/s Shree Someshwar Sahakari Sakhar Sakhar Karkhana Ltd.,Someshwarnagar, Taluka- Baramati, Dist. Pune

At Someshwarnagar, Tal. Baramati, Dist.Pune.

18 1) 132 kV Line from their plant to 132 kV Someshwar S/S

33 M/s Daund Sugar Ltd, ICC Trade Tower, B-Wing 201,Senapati Bapat Road, Pune-411 016.

Village Alegaon, Tal. Daund, Dist. Pune.

18 1) LILO on 132 kV Daund -Shrigonda Line.

34 M/s Samarth Sahakari Sakhar Karkhana Ltd, Post. Ankushnagar, Tal. Ambad, Dist. Jalna.

At Ankushnagar, Tal.Ambad, Dist. Jalna.

18 1) 132 kV lines from Plant to Deoli S/S.

35 M/s Vighnahar Sahakari Sakhar Karkhana Ltd, At Nivrutinagar(Dhalewadi),P.O. Shiroli, Tal. Junnar, Dist. Pune.

At Nivrutinagar(Dhalewadi) Tal. Junnar,Dist. Pune

12 1) 132 kV lines from Plant to 132 kV Narayangaon S/S.

36 M/s Baramati Agro Ltd, Pimpli, Baramati, Dist. Pune, Maharashtra - 413 102.

At Pimpli, Tal. Baramati, Dist. Pune.

22 1) 220 kV lines from their plant to Bhigwan S/S.

37 M/s Sonhira Sahakari Sakhar Karkhana Ltd, At Mohanrao Kadamnagar, Wangi, Tal. Kadegaon,Dist. Sangli.

At Mohanrao Kadam Nagar, Wangi. Tal.

Kadegaon Dist.Sangli.

22 1)132 kV lines from their plant to 220/132 kV Kadegaon S/S.

38 M/s Adani Power Maharashtra Ltd, Adani House (Power Division),Plot No.83, Industrial area,Sector-32,Gurgaon-122001

Tiroda,Dist. Gondia 5 X 660 = 3300

1) 765 kV 2 x S/C line from plant to MSETCL's proposed 765 kV Koradi -III S/s. 2) 2 x 1000 MVA, 765/400 kV ICT at plant. 3) 400 kV D/C line from Tiroda to Warora S/S. 4) With 765 kV lines, 400 kV Tiroda - Koradi-II D/C line will not be required.

39 M/s Vidarbha Industries Power Ltd, Dhirubai Ambani Knoledge City,I, Block,2nd Floor, Noth Wing, tane Belapur Road, Koperkhiirne- New Mumbai

MIDC Butibori, Nagpur 50 (300) 1) 220 kV lines from plant to MIDC Butibori S/S.

40 M/s Bhaurao Chavan Sahakari Sakhar Karkhana Ltd,Laxminagar, Degaon-Yelegaon,Post. Laxminagar, Tal. Ardhapur, Dist. Nanded.

Laxminagar, Tal.Ardhapur, Dist.Nanded

16.2 1) 132 kV lines from their plant to 132 kV Ardhapur S/S.

28

Page 32: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15

STU/TRA�S-PLA�/DOC-4 WEF 01/04/10

SR. NO.

NAME OF APPLICANT Location of the Plant

CAPACITY APPLIED (MW)

Proposed Evacuation Arrangement

41 M/s Gurudatt Sugars Ltd, A/P Takaliwadi, Tal. Shirol,Dist. Kolhapur.

Village Takaliwadi,

Tal. Shirol,Dist. Kolhapur.

15 1) 110 kV lines from their plant to 110 kV Kurundhawadi S/S.

42 M/s Spark Green energy (Satara), Ltd,"Link Side" 50, Carter Road, Bandra (West), Mumbai -400 050

MIDC Lonand 25 1) 132 kV level of 220/132 kV MIDC Lonand S/S

43 M/s Spark Green energy (Satara), Ltd,"Link Side" 50, Carter Road, Bandra (West), Mumbai -400 050

MIDC Newasa 25 1) MSETCL proposed 132 kV Ghodegaon S/S

44 M/s Yashvantrao Mohite Krishna Sahakari Sakhar Karkhana Ltd, Rehthare Budruk,Tal. Karad, Dist. Satara, P.P.Shivajinagar -415 108.

Rehthare BK., P.O.

Shivajinagar, Tal. Karad, Dist. Satara

16 1) 110 kV lines from their plant to 110 kV Rethare S/S.

45 M/s A.A. Energy Ltd, 101, Nikalas Tower, Central Bazar Road, Ramdaspeth, Nagpur-440 010.

Kh. No.324, Mauza Wadsa,

Desaiganj, Dist.

Gadchiroli

10 1) 132 kV lines from their plant to 132 kV Bramhapuri S/S.

46 M/s Ballarpur Industries Ltd. P.O.Ballarpur Paper Mills, Dist. Chandrapur-4420901

At Ballarpur, Dist.

Chandrapur

10 (40) 1) 220 kV Line from their plant to 220 kV Ballarpur S/S

47 M/s Mahati Hydro Power Projects Pvt. Ltd.32-33, Shankarshet Road,Behind S.T.Workshop, Pune

Veer NLBC Small HEP,

Tal. Purandar,Dist.

Pune

4.8 1) 110 kV Line from their Plant at sonwade to 110 kV Warna S/S

48 M/s Mahati Hydro Power Projects Pvt. Ltd.32-33, Shankarshet Road,Behind S.T.Workshop, Pune

Sonwade (Chandoli),Tal.

Shirala, Dist.Sangli.

5 1) 110 kV Line from their plant at Veer upto 110 kV Veer S/S.

49 M/s Dudhaganga Vedganga SSK.Ltd. Mouninagar,Tal. Kagal ,Dist. Kolhapur-416 208.

At Mouninagar (Bidri)

Dist.Klhapur.

20 1) From their Plant at Bidri (Mouninagar) Upto 220/132 kV Bidri S/S

29

Page 33: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15

STU/TRA�S-PLA�/DOC-4 WEF 01/04/10

SR. NO.

NAME OF APPLICANT Location of the

Plant

CAPACITY APPLIED (MW)

Proposed Evacuation Arrangement

50 M/s Technocraft Industries Ltd.A-25. MIDC, Street No.3, Marol Indusrial Area, Andheri (E),Mumbai-400 093.

At Village Dahivali, Murbad.

15 1) LILO on 100 kV Padhge-Murbad line

51 M/s R.M Mohite Textile Ltd, R.S.347, Ambapwadi Phata,Off NH4, P.O.1 Wadgaon, Tal. Hatkanagle, Dist.Kolhapur

At Radhanagari Dam Dist. Kolhapur

10 1) 33 kV level of MSETCL existing 110/33 kV Radhanagari S/S

52 M/s Dhariwal Infrastructure(P)Ltd.At Tadali, Dist.Chandrapur.

Tadali(Chandrapur MIDC),Dist. Chandrapur.

300 1) 400 kV Lines from their plant to 400/220 kV Chandrapur -II S/S

53 M/s Shri Vasant Dada Sahakari Sakhar Karkhana Ltd Vithewadi (Lohoner) Tal. Deola, Dist. Nasik

Vithewadi (Lohoner) Tal.

Deola, Dist. Nasik.

17 1) From their Plant at Vithewadi to 132 kV level of 220/132 kV Satana S/S

54 M/s ACI Infotech Ltd, A division of Infocom Ltd, 278, Vasan Udyog Bhawan, Opp. Highstreet Phoenix Mill, Lowar Parel(W), Mumbai-400 013

At Bhigwan, Tal. Indapur, Dist.

Pune.

15 1) 220 kV Line from their plant to 220/22 kV Bhigwan S/S

55 M/s Gopani Iron &Power (India) P.Ltd.A-22 MIDC Growth Centre, Post Tadali-442 406.

MIDC Growth Centre Tadali

8 (15) 1) 33 kV lines from their plant to 220/33 kV Chandrapur MIDC S/S.

56 M/s Uttam Galva Metallics Ltd,Bhugaon Link Road,Wardha -442001.

At Bhugaon Link Road, Wardha.

10 (15) 1) 220 kV Lines from their plant to 220 kV Bhugaon (Wardha-II) S/S

57 M/s Grace Industries Ltd, A-23, MIDC Estate, Tadali Growth Centre, Chandrapur

At MIDC Estate Tadali.

28 (33) 1)LILO on 220 kV Gadchandur –CTPS line

58 M/s Shree Virangana Steels Pvt. Ltd. 126-128, 1st Floor, Shriram Tower, Kingswamy Sadar, near NIT office ,Nagpur-440001

At Mauja Ukerwahi, Village Heti, Umrer Road,

Nagpur.

22 (30) 1) 220 kV Lines from their plant to220 kv Umred S/S.

59 M/s RPL URJA (Division of Rasoya Protiens Ltd), Village Kalmana, Tal.Wani, Dist.Yavatmal.

Village Kalmana, Tal. Wani, Dist.

Yavatmal

8.5 (10) 1) 33kV Lines from their plant to 220/33 kV Wani S/S.

30

Page 34: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15

STU/TRA�S-PLA�/DOC-4 WEF 01/04/10

SR. NO.

NAME OF APPLICANT Location of the

Plant

CAPACITY APPLIED (MW)

Proposed Evacuation Arrangement

60 M/s B.S.Ispat Ltd.Survey No.97, Village Salori, Yensa, Tal. Warora, dist. Chandrapur.

Village Salori, Yensa, Tal. Warora

15 1) 33 kV Lines from their plant to 220/33 kV Warora S/S

61 M/sVikas SSK. Ltd, Vaishali Nagar, Tal. Nivali, Dist. Latur.

At Vaishli Nagar, tal. Nivali. Dist.

Latur

18 1) 132 kV line from their plant to 132/33 kv Nivali S/S

62 M/s Shankar Sahakari Sakhar Karkhana Ltd. -Kaulage, Tal.Kagal Dist.Kolahapur.

At Sadashivnagar, Tal. Malshiras, Dist.Solapur.

17.5 (20) 1) 132 kV Line from their plant to 132kV Purandwade S/S

63 M/s Sadashivrao Mandalik Kagal Taluka SSK.Ltd, Sadashiv Nagar, Hamidwada -Kaulage, Tal.Kagal Dist.Kolahapur.

At Sadashivnagar, Hamidwada, Tal. Kagal,Dist.Kolhap

ur.

12 1) 33 kV Lines from their plant to proposed 220/33 kV Hamidwada S/S-

64 M/s Vayunandana Power Ltd, 12-2-460,Plot No.2, New Huda layout, Gudimalkapur, Mahadipatnam, Hyderabad-500 028.

At Village Kaneri,Dist. Gadchiroli.

10 (12) 1) 132 kV line from their plant to 220/132 kV Gadchiroli S/S

65 M/s M/s Bombay Rayon Fashions Ltd,Plot No.C-7, Tarapur MIDC, Near Tarapur Vidya Mandir, Boisar, Tal. Palghar, Dist. Thane.

At Tarapur MIDC 6 (8) 1) 33 kV lines from their plant toMSETCL 220/132/33 kV Boiser –II S/S

66 M/s Shri Shankar Maharshi Shankarrao Mohite-Patil SSK Ltd, Shankarnagar, Akluj Tal. Malshiras, Dist. Solapur.

At Akluj,Tal. Malshiras,Solapur

33 1) 132 kV line from their plant to MSETCL proposed 132 kV Shankarnagar S/S

67 M/s Pepsico India Holdings Pvt. Ltd, L.U.Gadkari Marg, Village Anik,Mahul, Chembur,Mumbai 400 074.

t Sadawaghapur, Dist. Satara

1.85 1) 33 kV line from their plant to 220/33 kV Sadvaghapur S/S

68 M/s Shree Renuka Sugars Ltd,7th floor, Devchand House, Shiv sagar Estate, Dr.Annie Beasant Road, Worli, Mumbai-400 018.

At Ajinkyatara SSK,Shahunagar,Shendre,Satara

22 (24) 1) LILO on 220 kV Vankuswadi –Satara MIDC S/S

69 M/s Dwarkadhish SSSK Ltd, KarkhanaShalivahana Projects Ltd,1582,7th Floor, Minerva Complex, S.D. Road, Secunderabad.

At Village Seware,

Taharabad, tal. Satana,Dist.

Nasik

10 1) 132kV lines from their plant to 132 kV Taharabad S/S.

31

Page 35: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15

STU/TRA�S-PLA�/DOC-4 WEF 01/04/10

SR. NO.

NAME OF APPLICANT Location of the

Plant

CAPACITY APPLIED (MW)

Proposed Evacuation Arrangement

70 M/s Kalyani Renewable Energy India Ltd,D.No.5-6,Prathipadu Village, Tadepalligudem, west Godavari, Dist. A.P.534 146.

At Balapur MIDC, Dist. Akola

13.8 (15) 1) 132 kV Lines from their plant to 220/132/33 kV Balapur S/S.

71 M/s The Sanjivani (Takli) Sahakari Sakhar Karkhana Ltd.Sahajanandnagar, P.O.Shinganapur - 423 603, Tal. Kopargaon, Dist. Ahmednagar

Sahajanandnagar, Tal. Kopargaon,Dist. Ahmednagar.

6.6 (15.9) 1) 33 kV Lines from their plant to 132/33 kV Kopergaon S/S.

72 M/s Kisanveer Satara Sahakari Sakhar Karkhana Ltd, Kianveer Nagar, Tal. Wai, dist.Satara.

At Kisan Veer Nagar, Tal.

Wai.Dist. Satara

19.56 (22) 1) LILO on IInd circuit of 132 kV Lonand-Wai line

73 M/s Ideal Energy Projects Ltd,122, 2nd Floor, Telecom Nagar, Near Ranta Pratap square, Nagpur-440 022.

Kundal, Tal. Palus, Dist. Sangli.

Addil.1 X

270 = 270

1) 400 kV D/C line from thier plant to 440 kV Warora S/S.

74 M/s Shriram Jawahar Shetkari Sahakari Sakhar Udyog,Phaltan, Tal.Phaltan,Dist.Satara

Phaltan, Tal.Satara

1.2 (1.5) 1) 33 kV lines from their plant to 132/33 kV Phaltan S/S

75 M/s Hindustan Electricity Generation Company Pvt. Ltd.Olympia, Central Avenue, Hiranandani Business Park.

At Navlakhumbre, pune

350 1) LILO on 400 kV Lonikand – Kalwa S/C Line upto their plant

76 M/s Vidarbha Energy and Infrastructure P.Ltd, 4th Floor, MG House, R.T. Road, Civil Lines, Nagpur.

Village Choramba, Tal. Ghatangi, Dist.

Yeotmal.

10 1) 132 kV lines from their plant to 132 kV Ghatangi S/S.

77 M/s Mahalaxmi Vidyut Private Ltd, 363/11, Balaji Niwas,Deep Bangalow Chowk, Shiwaji Nagar, Pune-411 016.

At Konal, Sindhudurg

2 X 5 MW 1) LILO on 220 kV Kolhapur-III – Phonda S/C Line upto their plant

32

Page 36: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15

STU/TRA�S-PLA�/DOC-4 WEF 01/04/10

SR. NO.

NAME OF APPLICANT Location of the

Plant

CAPACITY APPLIED (MW)

Proposed Evacuation Arrangement

78 M/s Malegaon Sahakari Sakhar Karkhana Ltd.At Post. Shivajinagar,Tal. Baramati, Dist. Pune.

Village Shivajinagar,tal.

Baramati,Dist.Pune

14 (21) 1) LILO on 400 kV Lonikand – Kalwa S/CLine upto thier plant

79 M/s M/s Greta Energy Ltd, Station Road, Brahampuri- 441206. Dist. Chandrapur.

Mul MIDC,Tal Mul, Dist. Chandrapur

15 1) 132 kV lines from their plant to 132 kV Mul S/S

80 M/s Shree Sidhabali Ispat Ltd, Plot No.C-2, MIDC Area, Tadali, Dist. Chandrapur-442406.

C-2 MIDC Area

Tadali,Dist. Chandrapur.

10 (20) 1) 33 kV lines from their plant to 220 /33 kV Chandrapur MIDC S/S

81 M/s Renuka Sugar Ltd, 7th Floor, Devchand House, Shiv Sagar Estate, Dr. Annie Besant Road, Worli, Mumbai-400 018.

Balaji nagar, Nandur, Tal.

Mangalweda Dist. Solapur

26 (30) 1) LILO on 132 kV Pandharpur –Mangalwedha line

82 M/s Kukadi Sahakari Sakhar Karkhana Ltd, At Pimpalgaon Pisa, Tal. Shrigonda, Dist.Ahmednagar.

Pimpalgaon Pisa, Tal. Shrigonda, Dist.Ahmednagar

10 (16) 1) 132 kV Lines from their plant upto MSETCL proposed 220/132 kV Belwandi S/S

33

Page 37: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15

STU/TRA�S-PLA�/DOC-4 WEF 01/04/10

9. Wind Generation

In this plan the aspect of wind generation is also covered. Existing wind generation is

2526MW out of which 260 MW generation (considering 10.28 % PLF) has been considered

in the study.

10.28 % PLF is obtained during peak load conditions as per Demo results of Wind mills

installed by MEDA

Table 9.1 - Existing Wind Generation as on 31.03.10

SR. NO DISTRICT CAPACITY (MW)

1 Satara 885

2 Sangli 700

3 Ahmednagar 108

4 Dhule 729

5 Nasik 90

6 Solapur 2

7 Sindhudurg 2

6 Beed 10

GRAND TOTAL 2526

TOTAL WIND POWER GENERATION (10.28 % of total capacity)

260

34

Page 38: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15

STU/TRA�S-PLA�/DOC-4 WEF 01/04/10

Table 9.2 - Proposed Wind Generation Developerwise for the year 2010-11

SR. NO.

DISTRICT NAME OF

SITE

CAPACITY

(MW)

Peak

Capacity

( 80 %)

MW in

Monsoon

Proposed Evacuation Arrangement

M/s. Suzlon Energy Pvt. Ltd.

1 Satara Sadawaghapur

100 80 1) 220/33 KV, 2 X 100 MVA S/S. at Sadawaghapur. 2) 220 KV DC Line Froam Munde S/S to Sadawaghapur S/S.-30KM. 3) 220 KV Line Bays at Mundhe S/S.-2 Nos

2 Satara 70 56

3 Satara Amberi 127.5 102

1) 132/33 KV, 3 X 50 MVA S/S. at Amberi 2) 132 KV DC Line Froam Phaltan S/S to Kas S/S.- 24.5 KM. 3) 132 KV Line Bays at Phaltan S/S.-2 Nos

4 Satara Kas 100 80

1) 132/33 KV, 2 X 50 MVA S/S. at Kas. 2) 132 KV DC Line Froam Satara Road S/S to Kas S/S.- 44KM. 3) 132 KV Line Bays at Satara Road S/S.-2 Nos

5 Satara GudePanchgani 50 40 1) 132/33 KV, 1 X 50 MVA Transformer installation at Shirala S/S. 2) 33KV Line Bays at Shirala S/S.-2 Nos

6 Satara GudePanchgani 170 136 1) 220/33 KV, 2 X 100 MVA S/S. at Nigade. 2) 220 KV DC Line From Nigade S/S to LILO point.-40KM.

7 Satara Matrewadi 50 40

1) 132/33 KV, 1 X 50 MVA S/S at Wind Farm Site. 2) 132KV Line Bays at Kale S/S.-1 Nos 3) 132 KV line second ckt. Stringing - 29KM. 4) 132 KV SC on DC line - 20KM.

8 Sangli Dhalgaon 50 40

1) 220/33 KV, 1 X 50 MVA T/F at Hivare S/S. 2) 220 KV SC on DC Line Froam Hivare S/S to Lamboti S/S.-125KM. 3) 220 KV Line Bays at Lamboti S/S.- 1 Nos

9 Sangli Ghatnandre 85 68

1) 220/33 KV, 1 X 100 MVA T/F installation at Ghatnandre S/S. 2) 220 KV line second ckt. Stringing from Ghatnandre to Vita.- 40KM. 3) 220 KV Line Bays at Vita S/S.- 1 No.

10 Sangli Dhalgaon 40 32 1) 220/33 KV, 1 X 50 MVA Transformer installation at Vita S/S. 2) 33KV Line Bays at Vita S/S.- 2 Nos

35

Page 39: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15

STU/TRA�S-PLA�/DOC-4 WEF 01/04/10

SR. NO.

DISTRICT NAME OF

SITE

CAPACITY

(MW)

Peak

Capacity

( 80 %)

MW in

Monsoon

Proposed Evacuation Arrangement

M/s. Suzlon Energy Pvt. Ltd.

11 Sangli Dhalgaon 300 240

1) 220/33 KV, 3 X 100 MVA S/S. at Hivare. 2) 220 KV DC Line From Hivare S/S to Lamboti S/S.-125KM. 3) 220 KV Line Bays at Lamboti S/S.-2 Nos

12 Dhule Brahamanwel 245 196

1) 220/33 KV, 2 X 100 MVA S/S. at Mogarpada. 2) 220 KV SC on DC Line From Mogarpada S/S to Gangapur S/S.-25KM. 3) 220 KV DC on DC Line From Mogarpada S/S to Satana & Second Ckt. Stringing on Satana Malegaon Line 4)220 KV Line Bay at Satana & Malegaon & Gangapur S/S.-3 Nos

13 Dhule Balsane 100 80

1) 132/33 KV, 2 X 50 MVA S/S at Wind Farm Site. 2) 132KV Line Bays at Nardhane S/S.-2 Nos 3) 132 KV DC line - 70KM.

14 Nasik Sinnar 50 40 1) 132/33 KV, 1 X 50 MVA Transformer at Khaprale S/S.

15 Nasik Panchpatta 170 136

1) 220/33 KV, 2 X 100 MVA T/F Adwadi S/S.. 2) 220 KV DC Line From Adwadi S/S to Babhaleshwr S/S.-70KM. 3) 220 KV Line Bays at Babhaleshwr S/S.-2 Nos

16 Ahmednagar Kolgaon 100 80 2x50 MVA, 132/33 kV SS 132 kV DC ACSR Panther Line-28 KM 132 kV bay at 220/132 KV Nagar SS

17 Ahmednagar Kolgaon 127.5 102

1) 132/33 KV, 2 X 50 MVA S/S at Kolgaon Wind Farm Site. 2) 132KV Line Bay at Shrigonda & Karjat S/S.-1 No at each S/S. 3) 132 KV S/C on DC line - 25 KM.

18 Ahmednagar Sautada 170 136

1) 220/33 KV, 2 X 100 MVA S/S at Wind Farm. 2) 220 KV DC Line From wind farm S/S to Patoda S/S. 3) 220 KV Line Bays at Patoda S/S.-2 Nos

36

Page 40: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15

STU/TRA�S-PLA�/DOC-4 WEF 01/04/10

SR. NO.

DISTRICT NAME OF

SITE

CAPACITY

(MW)

Peak

Capacity

( 80 %)

MW in

Monsoon

Proposed Evacuation Arrangement

M/s. Suzlon Energy Pvt. Ltd.

19 Nasik Gavalwadi 100 80

1) 132/33 KV, 2 X 50 MVA S/S at Gavalwadi Wind Farm Site. 2) 132KV Line Bays at Dindori S/S.-2 Nos 3) 132 KV DC line from Wind farm S/S.to Dindori S/S.

20 Nasik Khaprale 50 40 1) 132/33 KV, 1 X 50 MVA Transformer at Khaprale S/S.

21 Beed Sautada 100 80

1) 132/33 KV, 2 X 50 MVA S/S at Chikhali Wind Farm Site. 2) 132KV Line Bays at Raimoha S/S.-2 Nos 3) 132 KV DC line - 28KM.

22 Beed Khandke 170 136

1) 220/33 KV, 2 X 100 MVA S/S. 2) 220 KV DC Line From wind farm S/S to Ahmednagar. 3) 220 KV Line Bays at Ahmednagar S/S.-2 Nos

23 Pune Lonavala 170 136

1) 220/33 KV, 2 X 100 MVA S/S. 2) 220 KV DC Line From wind farm S/S to Urse. 3) 220 KV Line Bays at Urse S/S.-2 Nos

24 Pune Lonavala 200 160

1) 220/33 KV, 2 X 100 MVA S/S. 2) 220 KV DC Line From wind farm S/S to Chakan S/S. 3) 220 KV Line Bays at Chakan S/S.-2 Nos

25 Nandurbar Chakla 255 204

1) 220/33 KV, 3 X 100 MVA S/S. at Gangapur. 2) 220 KV SC Line From Gangapur S/S to Valve S/S. 3) 220 KV DC Line Froam Gangapur S/S to Satana & Malegaon S/S. 4) 220 KV Line Bay at Valve, Satana & Malegaon S/S.- 1 No. at each S/S.

37

Page 41: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15

STU/TRA�S-PLA�/DOC-4 WEF 01/04/10

SR. NO.

DISTRICT NAME OF

SITE

CAPACITY

(MW)

Peak

Capacity

( 80 %)

MW in

Monsoon

Proposed Evacuation Arrangement

M/s. Suzlon Energy Pvt. Ltd.

26 Nandurbar Chakla 50 40 1) 33 KV DC Panther Line From Ranala S/S to Wind Farm. 2) 33 KV 2 No. Bays at Nandurbar S/S.

27 Nandurbar Chakla 10 8 1) 33 KV SC Dog Line From Ranala S/S to Wind Farm.- 5KM. 2) 33 KV 1 No. Bay at Ranala S/S.

28 Aurangabad Kankora 121 96.8

1) 132/33 KV, 2 X 50 MVA S/S at Wind Farm Site. 2) 132KV DC Line from Wind Farm S/S. to LILO point - 8KM. 3) 33 KV Bay- 1No.

TOTAL WIND GENERATION OF M/S. SUZLON ENERGY PVT.LTD. : - 3331 MW

M/s. Enercon India Pvt. Ltd.

1 Pune Andhra Lake 100 80

1) 2 x 50 MVA, 132-110/33 kV Transformer at Bhayara (Andhra Lake) S/S. 2) 132 kV DC line on DC Tower using 0.2 ACSR Panther Conductor from Proposed Wind Farm SS Bhayara to Existing LILO on 132-110 kV DC line from Talegaon – Lonavala of MSETCL's – 20 kms.

2 Pune Andhra Lake 25 20 1) 132-110 kV Line Bay at 132-110/33 kV Bhayara SS – 2 Nos. 2) 33 kV Outlets – 08 Nos

3 Satara Khanapur 100 80

1) 2 x 50 MVA, and 1 x 25 MVA , 132-110 / 33 kV Transformer at Wind Farm 2) LILO on 110 kV Sangola – Oglewadi Line to Wind Farm. 3) 110 kV Line Bays at Wind Farm S/S.– 02 Nos

4 Satara Chavaneshwar 76.8 61.44

1) 2 x 50 MVA, 132/33 KV S/S at Chawaneshwar 2) LILO on 132 KV Lonand - Wai line 3) 33 KV outlets - 3 nos. at Chavaneshwar & 01 no at Satara Road SS

38

Page 42: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15

STU/TRA�S-PLA�/DOC-4 WEF 01/04/10

SR. NO.

DISTRICT NAME OF

SITE

CAPACITY

(MW)

Peak

Capacity

( 80 %)

MW in

Monsoon

Proposed Evacuation Arrangement

M/s. Enercon India Pvt. Ltd.

5 Nashik Aundhewadi 75 60

1) 2 x 50 MVA, 132/33 KV T/F at Ghoti S/S 2) 132 KV D/C line from M/s. Suzlon S/S located near by Sinnar 3) 33 KV outlets - 4 nos. 4) Space for 33 KV outlets -8 nos.

6 Kolhapur Vedganga 200 160

1) 2 x 100 MVA, 220/33 kV TF at Wind Farm Site ( Ghargoti). 2) LILO on 220 kV Talandge - Sawantwadi S/C line at Ghargoti. 3) 220 kV Bays at Ghargoti : 2 Nos. 4) 33 kV bays at Ghargoti : 14 Nos.

7 Sangli Dongerwadi 32 25.6

1) 33 kV D/C line from Wind farm site to 110/33 kV Kavathemahakal S/s. 2) 33 kV Bays at 110/33 kV Kavathemahakal S/s. : 2 Nos.

TOTAL WIND GENERATION OF M/S. ENERCON INDIA PVT.LTD. : - 608.8 MW

M/s. Shri Maruti Wind Park Developoers Pvt. Ltd.

1 Satara Amberi, Tal. Khatav

24 19.2 1) 1 x 25 MVA, 132/33 kV TF at 132 kV Aundh. 2) 33 kV Bays - 2 Nos. at 132/33 kV Aundh.

2 Satara Amberi, Tal. Khatav

10 8

1) 33 kV S/C line from Wind farm site to 110/33 kV Satara Road S/s. 2) 33 kV bays at 110/33 kV Satara Road S/s.: 1 No.

3 Satara Bhud/Kaledhon, Tal. Khatav/Man

25 20

1) 33 kV S/C line from Wind farm site to 132-110/33 kV Mayni S/s. 2) 1 x 25 MVA, 132-110/33 kV TF at 110/33 kV Mayni S/s. 3) 33 kV Bay at Mayni : 1 No.

4 Satara Bhud/Kaledhon, Tal. Khatav/Man

75 60

1) LILO of 110 kV Mayni - Dighanchi S/C line at Wind farm Site. 2) 1 x 50 & 1 x 25 MVA, 132-110/33 kV TF at Wind farm site.

39

Page 43: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15

STU/TRA�S-PLA�/DOC-4 WEF 01/04/10

SR. NO.

DISTRICT NAME OF

SITE

CAPACITY

(MW)

Peak

Capacity

( 80 %)

MW in

Monsoon

Proposed Evacuation Arrangement

M/s. Shri Maruti Wind Park Developoers Pvt. Ltd.

5 Sangli Vaspeth, Tal. Jath

40 32

1) 1 x 50 MVA, 132-110/33 kV TF at Jath S/s. 2) 33 kV D/C line with 0.2 ACSR Panther conductor from wind farm site to 110/33 kV Jath S/s. 3) 33 kV bays at 110/33 kV Jath S/s. : 2 Nos.

6 Sangli Vaspeth, Tal. Jath

50 40

1) TF : 1 x 50, 1 x 25 MVA, 132-110/33 kV at 110/33 kV Valsang wind farm s/s. 2) 110 kV S/C line from wind farm s/s to LILO on existing 110 kV Jath - Sankh line of MSETCL. 3) 33 kV outlets : 3 nos.

7 Sangli Vaspeth, Tal. Jath

100 80

1) 132 kV D/C line from Wind farm site to 132 kV Sangola S/S, 2) TF : 2 x 50, 1 x 25 MVA, 132/33 kV at wind farm S/S. 3) 132 kV Line bay at 132 kV Sangola : 2 nos 4) 132 kV line bay at 132 kv wind farm s/s.

8 Beed Sautada 80 64

1) TF : 2 x 50 MVA, 220/33 kV at proposed 220 kV Patoda s/s. 2) 2 nos. of 33 kV D/C lines from wind farm s/s to proposed 220 kV Patoda s/s. of MSETCL. 3) 33 kV line bays at 220/33 kV Patoda s/s : 4 nos.

TOTAL WIND GENERATION OF M/S. ENERCON INDIA PVT.LTD. : - 404 MW

M/s. T.S. Wind Power Developers Pvt. Ltd.

1 Satara Amberi, Tal. Khatav

25 20

1) 1 x 25 MVA, 132/33 kV TF at 132 kV Aundh S/s. 2) 33 kV D/C line from Wind farm Site to 132/33 kV Aundh S/s. 3) 33 kV byas at 132/33 kV Aundh : 2 Nos.

2 Satara Bhud, Tal. Man/Khatav

100 80

1) LILO of 220 kV Vita - Solapur S/C line at Wind farm Site. 2) 2 x 50 MVA, 220/33 kV TF at wind farm site. 3) 33 kV bays at wind farm site S/s. : 5 Nos.

40

Page 44: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15

STU/TRA�S-PLA�/DOC-4 WEF 01/04/10

SR. NO.

DISTRICT NAME OF

SITE

CAPACITY

(MW)

Peak

Capacity

( 80 %)

MW in

Monsoon

Proposed Evacuation Arrangement

M/s. T.S. Wind Power Developers Pvt. Ltd.

3 Satara Gudepachgani 100 80

1) LILO of 220 kV Karad - Kolhapur Ckt. IV at Wind farm Site. 2) 2 x 50 MVA, 220/33 kV TF at Wind Farm Site. 3) 33 kV Bays at Wind Farm Site : 5 Nos.

4 Satara Vankuswade 25 20

1) 1 x 50 MVA, 220/33 kV TF at 220 kV Vankuswade S/s. 2) 33 kV D/C Line from Wind Farm Site to 220/33 kV Vankuswade S/s. 3) 33 kV Bays at 220/33 kV Vankuswade S/s. : 2 Nos.

TOTAL WIND GENERATION OF M/S. T.S.WIND POWER DEVELOPERS PVT.LTD. : - 250 MW

M/s. Acorn Properties Pvt. Ltd.

1 Satara Amberi, Tal. Khatav

24 19.2

1) 1 x 25 MVA, 132/33 kV TF at 132 kV Aundh. 2) 33 kV Bays - 2 Nos. at 132/33 kV Aundh.

2 Satara Amberi, Tal. Khatav

50 40

1) LILO of 110 kV Satara Road - Satara MIDC S/C line at Wind farm site. 2) 2 x 50 MVA, 132-110/33 kV TF at Wind farm site. 3 ) 33 kV bays at wind farm site : 5 Nos.

TOTAL WIND GENERATION OF M/S. ACORN PROPERTIES PVT.LTD. : - 74 MW

M/s. Theolia Wind Pvt. Ltd.

1 Sangli Sankh & Jath 20 16 1) 2x33KV bay at 132KV Sankh S/S

2 Sangli Sankh & Jath 10 8 1) 1x33kv bay at 110KV Jath S/S

3 Sangli Vaspet 100 80

1) 2 X 50 MVA, 132/33 kV TF at Wind Famr Site. 2) 132 kV D/C line from Wind Farm Site - 220 kV Jath 3) 2 x 132 KV bays at 220 Jath S/s. 4) 132 kV bays at Wind Farm S/s. : 2 Nos.

TOTAL WIND GENERATION OF M/S. THEOLIA WIND PVT.LTD. : - 130 MW

41

Page 45: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15

STU/TRA�S-PLA�/DOC-4 WEF 01/04/10

SR. NO.

DISTRICT NAME OF

SITE

CAPACITY

(MW)

Peak

Capacity

( 80 %)

MW in

Monsoon

Proposed Evacuation Arrangement

M/s. Shri Ram EPC Pvt. Ltd.

1 Satara Amberi, Tal. Man

15 12

1) 1 x 25 MVA, 132/33 kV TF at 132 kV Aundh., 2) 33 kV D/C line from Wind Farm Site to 132/33 kV Aundh S/s. 3) 33 kV Bays - 2 Nos. at 132/33 kV Aundh.

2 Satara Amberi 90 72

1) TF : 2 x 50 MVA, 132-110/33 kV at Amberi s/s with bays. 2) LILO for Karad - Dighanchi 110 kV line 2nd ckt. At Mayni s/s. 3) 110 kV bays at Mayni - 4 nos. & at Amberi - 2 nos. 4) 33 kV outlets at Amberi s/s - 8 nos 5) 132/110 kV line from Amberi s/s to Mayni s/s.

TOTAL WIND GENERATION OF M/S. SHRI RAM EPC PVT.LTD. : - 105 MW

M/s. RRB Pvt. Ltd.

1 Nashik Mahir 75 60

1) TF : 3 x 50 MVA, 132/33 kV at 132 kV Mahir ( Wind Farm Site ) s/s. 2) 132 kV Mahir - Nampur D/C line. 3) 132 kV Dongarpada - Mahir SCDC line. 4) 132 kV Mahir - Sakri D/C Line. 5) 33 kV outlets : 18 nos.

2 Dhule Ayne ( Tek)

75 60

1) TF : 2 x 50 MVA, 132/33 kV at Ayne(Tek) wind farm s/s. 2) 132 kV Dule-II -- Ayne(Tek) D/C line. 3) 132 kV line bays - 4 nos. 4) 33 kV outlets - 4 nos.

TOTAL WIND GENERATION OF M/S. RRB PVT.LTD. : - 150 MW

TOTAL PROPOSED WIND POWER GENERATION : - 5273 MW

TOTAL PROPOSED WIND POWER GENERATION CONSIDERED IN PLAN ( 10.28 % of total capacity ) : - 542 MW

TOTAL (EXISTING + PROPOSED) WIND POWER GENERATION (10.28 % of total capacity) : - 260 + 542 = 802 MW

42

Page 46: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15

STU/TRA�S-PLA�/DOC-4 WEF 01/04/10

Table – 10 - Power scenario in Maharashtra (including Mumbai) Generation Available By - A. Mahagenco (Table - 3.3) B. State Govt/Inter State /MAHADISCOM (Table - 4.2) C. Central Sector (Table - 5.2)

D. Mumbai (Table- 7) E. IPP (Table- 8.2.2) F. Wind Generation(Table-9.2)

Year A B C D E F Total

A+B+C+D+E+F (Availibility)*

Total Demand

(coincident)

Total Demand (Non

coincident)

Peak Shortfall (-) / Surplus (+) (MW) (coinc)

2010-11 8775 2087 3582 3130 2281 802 20657 20795 27449 (-)138

2011-12 9414 2166 4422 3342 4304 802 24450 22635 29199 (+)1815

2012-13 11497 3228 5372 3571 7154 802 31624 24638 31291 (+)6986

2013-14 12113 3228 5838 3817 7244 802 33042 26610 32996 (+)6432

2014-15 13301 3228 5838 4174 7244 802 34587 28738 35067 (+)5849

Note – * Availability Considered subject to timely commissioning of upcoming generation

Graph – Present and Future scenario in Maharashtra

43

Page 47: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15

STU/TRA�S-PLA�/DOC-4 WEF 01/04/10

Maharashtra has catered Peak demand of 14,952 MW as against the requirement of 19,120

MW during peak load condition during the year 2009-10.

With the capacity addition from State Generation companies and Central Generation

companies with Generation from IPP’s, the demand and availability that would prevail in each

year would be:

Year Peak Demand (Coincidence)

(MW)

Peak Demand (Non-Coincidence) (MW)

Availability (MW)

Peak Shortfall (-) / Surplus (+) (MW)

(coinc)

2010-11 20795 27449 20657 (-) 138

2011-12 22635 29199 24450 (+) 1815

2012-13 24638 31291 31624 (+) 6986

2013-14 26610 32996 33042 (+) 6432

2014-15 28738 35067 34587 (+) 5849

Load Growth

The draft STU Five year transmission plan was formulated taking in to account previous

years load growth and upcoming load centers SEZ’s, New Cities, Malls etc

Load Growth is considered as per District wise Load forecasting carried out by this office.

44

Page 48: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15

STU/TRA�S-PLA�/DOC-4 WEF 01/04/10

Methodology

The EHV network of 400 kV, 220 kV and 132 kV networks are modelled in detailed along with

their respective transformer capacities.

To make critical analysis of the network in terms of voltage profile and network

loading, load flow & Short Circuit studies are carried out on MiPower Software. The

simulation was carried out by matching the power flows at 400 kV and 220 kV levels along

with voltage profile at various buses

The standard practices followed by CEA as well as the guidelines by MERC have been

incorporated while conducting the simulation studies which are as follows:

CEA – Transmission system planning & design criteria:

Central Electricity Authority (CEA) has evolved transmission system planning & design

criteria for the National Electricity Plan. The planning criteria as per CEA are

• In the national approach N-2 criteria may be adopted for large generating complex

(3000 MW or above) and multi line corridors (3 D/C lines or more), on case-to-case

basis. Whereas, regional planning may be continued with N-1 criteria. However,

while N-1 would be applied to test withstand without necessitating load shedding or

rescheduling of generation during steady state operation, N-2 would be applied to

test withstand without necessitating load shedding but could be with rescheduling

of generation during steady state operation.

• The steady state voltage limit on 400kV system is within 380kV to 420kV.

The Maharashtra State Grid Code:

Maharashtra Electricity Regulatory Commission (MERC) has published the Final State

Grid code 2006 which lays down the rules, guidelines and standards to be followed by

various agencies and participants in the intra –State transmission system to plan, develop,

maintain and operate the intra-state transmission system apart of Western Regional Grid

System, in the most efficient, reliable and economic manner, while facilitating a healthy

competition on in the generation and supply of electricity.

Section 9 of the Grid Code prescribes the planning criterion to be followed for planning

the transmission system. The planning criterions as per the regulation are:

45

Page 49: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15

STU/TRA�S-PLA�/DOC-4 WEF 01/04/10

9.1 The planning criterion shall be based on the security philosophy on which the ISTS (Inter

State Transmission System) has been planned. The security philosophy may be as per the

Transmission Planning Criteria and other guidelines as given by the authority provided that

State Transmission Utility shall carry out appropriate system studies while developing the

transmission system plan.

9.2 The intra state transmission system, as a general rule, shall be capable of

With standing and be secured against the following contingency outages without

Necessitating load shedding or rescheduling of generation during Steady State

Operation:

1) Outage of a 110kV /132 kV D/C line or,

2) Outage of a 220 kV D/C Line or,

3) Outage of a 400 kV S/C line or,

4) Outage of a single Interconnecting Transformer or,

5) Outage of a one pole of HVDC Bi-pole or,

6) Outage of a 765 kV S/C Line.

Provided that the above contingencies shall be considered assuming a pre-contingency

system deletion (planned outage) of another 220 kV D/C line or 400 kV S/C line

in another corridor and not emanating from the same substation.

9.3 All the Generating Units may operate within their reactive capability curves and the

network voltage profile shall be maintained within voltage limits specified.

9.4 The intra-State transmission system shall be capable of withstanding the loss of most

severe single in feed without loss of stability

9.5 Any one of the events defined in the Regulation 9.2 above shall not cause:

(i) Loss of supply;

(ii) Prolonged operation of the system frequency below & above specified

limits;

(iii) Unacceptable high or low voltage;

(iv) System instability;

(v) Unacceptable overloading of ISTS elements.

46

Page 50: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15

STU/TRA�S-PLA�/DOC-4 WEF 01/04/10

9.6 In all substations (66kV/110kV/132kV and above), except HVDC, suitable number and

capacity of transformers shall be provided to have adequate redundancy required to

maintain firm capacity at the substation. In HVDC substations, at least one spare

converter/inverter transformer shall be kept ready to use at any time.

Explanation – for the purpose of Regulation 9.6, the term firm capacity shall mean the

minimum transformation capacity available at the substation in case of outage of

any one transformer.

9.7 State Transmission Utility shall carry out planning studies for Reactive Power

compensation of ISTS including reactive power compensation at the in-State Generating

Station’s switchyard.

Section 22.24 of the Grid Code/CEA Transmission planning criteria describes the

voltage profile as per

Voltage (kV – rms)

Nominal Maximum Minimum

765 800 728

400 420 380

220 245 198

132 145 122

66 73 60

With the operational study as initial conditions, prioritization study was carried out with the

following assumptions

� Priority

i. Generation Evacuation schemes – High priority

ii. Meeting the Demand

iii. Improving quality of power supply

iv. Improving reliability satisfying grid code security requirements

� While carrying out system requirement, network of PGCIL (existing and proposed) is

also considered. The details of the same are given below

47

Page 51: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15

STU/TRA�S-PLA�/DOC-4 WEF 01/04/10

11. PGCIL NETWORK IN MAHARASHTRA

Table -11.1- Existing Network of PGCIL

Sr. No.

Name of s/s Total Scope of Work

PGCIL'S Existing S/s’s and associated Lines in Maharashtra

1 400KV Boisar (PG) 1 400/220 KV, 2X315 MVA ICT with bays

2 400 KV Tarapur - Boisar(PG) D/C Line

3 LILO on 400 KV Padghe-I - Gandhar S/C Line at Boisar (PG)

4 400 KV Tarapur – Padghe-I D/C Line

2 400KV Bhadravati (PG) 1

400 KV Bhadravati (PG) – Chandrapur-I 4 ckts.

2 400 KV Bhadravati (PG) - Raipur 3 ckts

3 400 KV Bhadravati (PG) - Bhilai S/C Line

4 +/-500 KV Bhadravati (PG)-Ramagundam BTB HVDC

3 400KV Wardha (PG) 1

Establishment of New 400/220 KV, 2X315 MVA ICT with bays

2 400 KV Wardha (PG) – Akola-I D/C Line

3 400 KV Akola-I – Aurangabad-I D/C Line

4 765 kV 1st S/C Seoni (PG)–Wardha (PG) line (Initially to be operated at 400kV)

PGCIL'S Existing Interstate Lines in Maharashtra

1 400 KV Bhilai – Koradi-I S/C Line

2 400 KV Satpur – Koradi-I S/C Line

3 400 KV Khandva – Dhule-I D/C Line

4 400 KV Sardar Sarovar – Dhule-I D/C Line

5 400 KV Kolhapur - Mhapusa D/C Line

48

Page 52: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15

STU/TRA�S-PLA�/DOC-4 WEF 01/04/10

Table -11.2 - Proposed Network of PGCIL

Sr. No.

Name of S/s Total Scope of Work Length (km)

Month of Comm.

1 400KV Wardha (PG) (Comm.) 1

765 kV 2nd S/C Seoni (PG)–Wardha (PG) line (Initially to be operated at 400kV)

275 Mar-11

2 400 kV Wardha (PG)–Parli (PG) (Quad.) D/C Line

363 Dec-10

3 400 kV Raipur (PG)–Wardha (PG) D/C Line 363 Mar-11

2 400KV Parli (PG) Switching Station (Sept-10)

1 400 kV Bhadravati (PG)-Parli (PG) D/C Line 380 July-10

2 400 kV Parli (MSEB) – Parli (PG) D/C Line 7 July-10

3 400 kV Parli (PG) – Pune (PG) D/C Line 308 June-11

4 400 kV Parli (PG) - Solapur (PG ) D/C Line 196 May-11

3 400 KV Pune (PG) (July-10) 1

Establishment of New 400/220 KV, 2X315 MVA ICT with bays (ICT-1 Errected)

July-10

2 400 kV Pune (PG) – Aurangabad-I (MSEB) D/C Line

225 Apr-11

3 LILO of 400 kV Lonikand (MSEB) – Kalwa (MSEB) D/C at Pune (PG )

24 Feb-10

4 400 KV South Solapur (PG) (May-10)

1 Establishment of New 400/220 KV, 2X315 MVA ICT with bays (ICT-1 Errected)

May-10

2 400 kV South Solapur (PG) – Kolhapur(MSEB) D/C Line

189 May-11

3 LILO of 400 kV Solapur (MSEB) – Karad (MSEB) S/C at South Solapur (PGCIL ) (25 Km D/C + 2Km S/C)

27 May-10

5 400 KV Navi Mumbai (PG)

1 Establishment of New 400/220 KV, 2X315 MVA ICT with bays

2 400 kV Navi Mumbai (PG) – Vapi D/C Line 185 Mar-11

3 LILO of 400 kV Pune (PG) – Kalwa (MSEB) S/C at Navi Mumbai (PG )

10 Mar-11

6 400 KV GIS New location near Mumbai

1 400 kV D/C Line from Navsari (PG) will be terminated at Boisar (PG).

220 Oct-12

49

Page 53: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15

STU/TRA�S-PLA�/DOC-4 WEF 01/04/10

The transmission system proposed and indicated in the Minutes of the 29th meeting

of standing Committee on Power System Planning in western region.

� Transmission System within WR associated with New IPP projects in Chattishgarh

(i) Raipur Pooling station- Wardha 765 kV 2XD/C or 4XS/C.

(ii) Wardha- Aurangabad (PG) 765 kV 2XD/C or 4XS/C.

(iii) Aurangabad (PG) - Padge(PG) 765 kV 1XD/C or 2XS/C.

(iv) Establishment of 765/400 kV 2x1500 MVA substations at Aurangabad and

Padghe (GIS)

(v) Aurangabad (PG)-Khargar 400 kV D/C (quad)

(vi) Padghe (PG)- Padghe 400 kV D/C (quad)

(vii) Vadodra-Asoj (GETCO) 400 kV D/C (quad)

(viii) Establishment of 2X315 MVA, 400/220 kV Dhule (PG).

(ix) Dhule (PG) – Dhule (IPTC) 400 kV 2X D/C (quad)

(x) Dhule (PG) – Nasik (MSETCL) 400 kV D/C (quad)

(xi) Dhule (PG) – Malegaon (MSETCL) 400 kV D/C (quad)

(xii) + 600 kV 4000 MW HVDC bipole between Raigarh pooling station (Kotra) – Dhule

(PG) with mettalic return conductor.

(xiii) 4000 MW, + 600 kV HVDC bipole terminal each at Raigarh pooling station (Kotra)

and Dhule (PG).

(xiv) Aurangabad- Dhule (IPTC) 765 kV S/C

(xv) Dhule (IPTC) – Vadodara (PG) 765 kV S/C

(xvi) Establishment of 765/400 kV 2x1500 MVA substations at Dhule (IPTC)

(xvii) Dhule (IPTC) – Dhule (MSETCL) 400 kV D/C (quad)

50

Page 54: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15

STU/TRA�S-PLA�/DOC-4 WEF 01/04/10

� Transmission system associated with Krishnapatnam (5x800 MW)

(WR Portion)

(i) Raichur – Solapur 765 kV S/c

(ii) Solapur – Pune 765 kV S/c

(iii) Establishment of new 765/400 kV substations at Solapur & Pune with

2x1500 MVA transformation capacity

� Tr. System associated with South-West interconnection

(i) Establishment of 2 x 500MW HVDC back-to-back station at Kolhapur

(ii) Narendra – Kolhapur 400 kV D/c line with Lapwing conductor

(iii) LILO of both circuits of existing Kolhapur –Mapusa 400 kV D/c line at

(iv) Kolhapur HVDC back-to-back station

51

Page 55: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15

STU/TRA�S-PLA�/DOC-4 WEF 01/04/10

Spill Over Upto Year 2009-10

In the year 2009-10, it is estimated that Maharashtra met a demand of about

14952 MW considering the available generation against the requirement of 19120 MW at

peak load condition.

The substation requirement for the year for meeting the demand is tabulated in Table 12,

Augmentation in Table 13 & Additional link lines in Table 14

Table: 12 - No. of Substation requirement upto year

2009-10

Sr. No

Voltage Level (kV) Spill over

1 400 6

2 220 42

3 132 31

4 110/100 2

Total 81

Table 13: No. of Augmentations upto year 2009-10

Table: 13.1 - No. of Augmentation by Addition of transformers upto year 2009-10

Sr. No

Voltage Ratio Spill over

1 400/220 11

2 220/132, 110 33

3 220/33, 22 70

4 132/33 147

5 110/33, 22 15

Total 276

52

Page 56: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15

STU/TRA�S-PLA�/DOC-4 WEF 01/04/10

Table: 13.2 - No. of Augmentation by Replacement of transformer upto year 2009-10

Sr. No

Voltage Ratio Spill over

1 400/220 2

2 220/132, 110 41

3 220/33, 22 9

4 132/33 116

5 110/33, 22 35

Total 203

Table 14: No. of Additional Link Lines required upto year 2009-10

Table: 14.1 - No. of Additional link lines upto year 2009-10 for S/S’s where only single source is available

Sr. No

Voltage (kV) Spill over

1 400 -

2 220 4

3 132 32

4 110-100 4

Total 40

Table: 14.2 - No. of Additional link lines upto year 2009-10 to meet Demand without Load shedding and to insure reliability and quality of supply

Sr. No

Voltage (kV) Spill over

1 400 -

2 220 11

3 132 11

4 110-100 6

Total 28

53

Page 57: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15

STU/TRA�S-PLA�/DOC-4 WEF 01/04/10

Table: 14.3 - No. of Additional link lines upto year 2009-10 for evacuation arrangement

Sr. No

Voltage (kV) Spill over

1 400 -

2 220 7

3 132 2

4 110-100 -

Total 9

Table: 14.4 - No. of Additional link lines upto year 2009-10 for New substations to have alternate source

Sr. No

Voltage (kV) Spill over

1 400 -

2 220 1

3 132 6

4 110-100 -

Total 7

List of substations commissioned during 2009-10.

Sr No.

Name of substation

Voltage level

District Zone

1) Chakan 400 KV Pune Pune

2) Khaparkheda 400 KV Nagpur Nagpur

3) Bhusawal 400 KV Jalgaon Vashi

4) Knowledge Park Airoli

220 KV Thane Vashi

5) Pahur 132 KV Akola Amaravati

List of substations proposed for 2008-09 but could not commission during the year 2009-10 (Spill Over). Sr No. Name of substation Voltage level District Zone

1) Vasai 220 KV Thane Vashi

2) Bapgaon 220 KV Thane Vashi

3) Bhandup (GIS) 220 KV Thane Vashi

54

Page 58: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15

STU/TRA�S-PLA�/DOC-4 WEF 01/04/10

4) Kudus 220 KV Thane Vashi

5) Bhiwandi-III 220 KV Thane Vashi

6) Bhiwandi-IV 220 KV Thane Vashi

7) Khadakwasala 220 KV Pune Pune

8) Talegaon 220 KV Pune Pune

9) Kharadi (GIS) 220 KV Pune Pune

10) Rajgurunagar 220 KV Pune Pune

11) Shendra 220 KV Aurangabad Aurangabad

12) Hingoli 220 KV Hingoli Aurangabad

13) Paranda 220 KV Osmanabad Aurangabad

14) Patoda 220 KV Beed Aurangabad

15) Wani 220 KV Yeotamal Amaravati

16) Mankapur 220 KV Nagpur Nagpur

17) New Pardi 220 KV Nagpur Nagpur

18) New Butibori 220 KV Nagpur Nagpur

19) Matradevi* 220 KV Chandrapur Nagpur

20) Bibawewadi 132 KV Pune Pune

21) Rasta Peth 132 KV Pune Pune

22) Navi Vesh 132 KV Solapur Pune

23) Badanapur 132 KV Jalna Aurangabad

24) Shelu 132 KV Pabhani Aurangabad

25) Ghatanji 132 KV Yeotamal Amaravati

26) Barshi Takali 132 KV Akola Amaravati

27) Bharshingi 132 KV Amaravati Amaravati

28) Jam 132 KV Wardha Nagpur

55

Page 59: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15

STU/TRA�S-PLA�/DOC-4 WEF 01/04/10

29) Lakhandur 132 KV Bhandara Nagpur

30) Lendra (GIS) 132 KV Nagpur Nagpur

31) Serum Institute* 132 KV Pune Pune

32) Mumbra 100 KV Thane Vashi

33) Neral 100 KV Raigad Vashi

*Covered under ORC

List of substations proposed for 2009-10 but could not commission during the year. Sr No. Name of substation Voltage level District Zone

1) Lonikand-II 400 KV Pune Pune

2) Nanded 400 KV Aurangabad Aurangabad

3) Warora 400 KV Nagpur Nagpur

4) Ulhasnagar 220 KV Thane Vashi

5) Vashi 220 KV Thane Vashi

6) Goregaon Film City 220 KV Mumbai Vashi

7) South Solapur 220 KV Solapur Pune

8) Akurdi 220 KV Pune Pune

9) Jath 220 KV Sangli Karad

10) Mudhal titha 220 KV Kolhapur Karad

11) Lonand (MIDC) 220 KV Satara Karad

12) Phaltan (MIDC) 220 KV Satara Karad

13) Kadegaon 220 KV Sangli Karad

14) Pimpalgaon 220 KV Nasik Nasik

15) Bhambori 220 KV Jalgaon Nasik

16) Kopargaon 220 KV Ahamadnagad Nasik

17) Sinnar- II 220 KV Nasik Nasik

56

Page 60: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15

STU/TRA�S-PLA�/DOC-4 WEF 01/04/10

18) Valandi 220 KV Latur Aurangabad

19) Tuljapur 220 KV Osmanabad Aurangabad

20) Narsi -II 220 KV Latur Aurangabad

21) Malegaon 220 KV Washim Amaravati

22) Nandgaon Peth 220 KV Amaravati Amaravati

23) Ghatodi 220 KV Yeotamal Amaravati

24) Uppalwadi 220 KV Nagpur Nagpur

25) Ballarshah 220 KV Chandrapur Nagpur

26) Dapcheri 132 KV Thane Vashi

27) Someshwarnagar 132 KV Pune Pune

28) Borivel 132 KV Pune Pune

29) Karajagi 132 KV Solapur Pune

30) Waghadari 132 KV Solapur Pune

31) Soregaon 132 KV Solapur Pune

32) Shankarnagar 132 KV Solapur Pune

33) Ruddewadi 132 KV Solapur Pune

34) Taharabad 132 KV Nasik Nasik

35) Vadgire 132 KV Ahmadnagar Nasik

36) Ghargaon 132 KV Ahmadnagar Nasik

37) Soygaon 132 KV Aurangabad Aurangabad

38) Mahakala 132 KV Jalna Aurangabad

39) Niwali 132 KV Latur Aurangabad

40) Mahur 132 KV Nanded Aurangabad

41) Pandharkavada 132 KV Yeotamal Amaravati

42) Deolgaon Raja 132 KV Buldana Amaravati

57

Page 61: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15

STU/TRA�S-PLA�/DOC-4 WEF 01/04/10

43) Murtizapur 132 KV Akola Amaravati

44) Jafarabad 132 KV Gadchiroli Nagpur

45) Pulgaon 132 KV Wardha Nagpur

46) Sahuli 132 KV Nagpur Nagpur

47) Allapalli 132 KV Gadchiroli Nagpur

48) Yetapalli 132 KV Gadchiroli Nagpur

Conclusion

According to Load flow studies overloading can be removed by constructing proposed

400kV, 220kV, 132kV, 110/100kV S/s and Augmentation of transformer capacity in existing

S/s.

58

Page 62: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15

STU/TRA�S-PLA�/DOC-4 WEF 01/04/10

Year 2010-11

In the year 2010-11, it is estimated that Maharashtra will meet a demand of about

20657 MW considering the available generation against the requirement of 20795 MW

at peak load condition.

The substation requirement for the year for meeting this demand is tabulated in Table 15,

Augmentation in Table 16 & Additional link lines in Table 17

Table: 15 - No. of Substation requirement for the year 2010-11

Sr. No

Voltage Level (kV) 2010-11

1 400 5

2 220 13

3 132 14

4 110 -

Total 32

Table 16: No. of Augmentations for the year 2010-11

Table: 16.1 - No. of Augmentation by Addition of transformers for the year 2010-11

Sr. No

Voltage Ratio 2010-11

1 400/220 -

2 220/132, 110 3

3 220/33, 22 12

4 132/33,22,11 8

5 110/33, 22 1

Total 24

59

Page 63: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15

STU/TRA�S-PLA�/DOC-4 WEF 01/04/10

Table: 16.2 - No. of Augmentation by Replacement of transformer for the year 2010-11

Sr. No

Voltage Ratio 2010-11

1 400/220 -

2 220/132, 110 22

3 220/33, 22 19

4 132/33 13

5 110/33, 22 6

Total 60

Table 17: No. of Additional Link Lines required for the year 2010-11

Table: 17.1 - No. of Additional link lines for the year 2010-11 for S/S’s where only single source is available

Sr. No

Voltage (kV) 2010-11

1 400 -

2 220 8

3 132 15

4 110-100 3

Total 26

Table: 17.2 - No. of Additional link lines for the year 2010-11 to meet Demand without Load shedding and to insure reliability and quality of supply

Sr. No

Voltage (kV) 2010-11

1 400 -

2 220 8

3 132 13

4 110-100 1

Total 22

60

Page 64: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15

STU/TRA�S-PLA�/DOC-4 WEF 01/04/10

Table: 17.3 - No. of Additional link lines for the year 2010-11 for evacuation arrangement

Sr. No

Voltage (kV) 2010-11

1 400 -

2 220 3

3 132 -

4 110-100 -

Total 3

Table: 17.4 - No. of Additional link lines for the year 2010-11 for New substations to have alternate source

Sr. No

Voltage (kV) 2010-11

1 400 -

2 220 4

3 132 6

4 110-100 -

Total 10

List of substations proposed for commissioning during 2010-11. Sr No. Name of substation Voltage level District Zone

1) Koradi -II 400 KV Nagpur Nagpur

2) Bhusawal 400 KV Jalgaon Nasik

3) Hinjewadi 400 KV Pune Pune

4) Karad -II 400 KV Satara Karad

5) Kesurdi 400 KV Satara Karad

6) Palghar 220 KV Thane Vashi

7) Biosar MIDC 220 KV Thane Vashi

8) Vile Bhagad 220 KV Raigad Vashi

9) Yeolewadi

(VSNL Dighi)

220 KV Pune Pune

61

Page 65: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15

STU/TRA�S-PLA�/DOC-4 WEF 01/04/10

10) Kondhawa 220 KV Pune Pune

11) Hamidwada 220 KV Kolhapur Karad

12) Kalwan 220 KV Nasik Nasik

13) Sayane 220 KV Nasik Nasik

14) Deogaon Rangari 220 KV Aurangabad Aurangabad

15) Bhokardan 220 KV Jalna Aurangabad

16) Anjangaon 220 KV Amaravati Amaravati

17) Tadali 220 KV Chandrapur Nagpur

18) Katol - II 220 KV Nagpur Nagpur

19) Nimboni 132 KV Solapur Pune

20) Mhaswad 132 KV Satara Karad

21) Ghodegaon 132 KV Ahmednagar Nasik

22) Panchincholi 132 KV Latur Aurangabad

23) Shengaon 132 KV Hingoli Aurangabad

24) Sonpeth 132 KV Parbhani Aurangabad

25) Jalgaon Jamod 132 KV Buldana Amaravati

26) Yeotmal MIDC 132 KV Yeotmal Amaravati

27) Jat Tirodi 132 KV Nagpur Nagpur

28) Morgaon Arjuni 132 KV Gondia Nagpur

29) Seloo 132 KV Wardha Nagpur

30) Paghora* 132 KV Nagpur Nagpur

31) Mokhabardi 132 KV Nagpur Nagpur

*Covered under ORC Conclusion

According to Load flow studies overloading can be removed by constructing proposed

400kV, 220kV, 132kV, 110/100kV S/s and Augmentation of transformer capacity in existing

S/s.

62

Page 66: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15

STU/TRA�S-PLA�/DOC-4 WEF 01/04/10

Year 2011-12

In the year 2011-12, it is estimated that Maharashtra will meet a demand of about

22635 MW considering the available generation of 24450 MW indicating surplus position of

state.

The substation requirement for the year for meeting this demand is tabulated in Table 18,

Augmentation in Table 19 & Additional link lines in Table 20

Table: 18 – No. of Substation requirement for the year

2011-12

Sr. No

Voltage Level (kV) 2011-12

1 400 2

2 220 14

3 132 3

4 110/100 -

Total 19

Table 19: No. of Augmentations for the year 2011-12

Table: 19.1 - No. of Augmentation by Addition of transformers required for the year 2011-12

Sr. No

Voltage Ratio 2011-12

1 400/220 3

2 220/132, 110 -

3 220/33, 22 12

4 132/33 14

5 110/33, 22 2

Total 31

63

Page 67: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15

STU/TRA�S-PLA�/DOC-4 WEF 01/04/10

Table: 19.2 - No. of Augmentation by Replacement of transformer for the year 2011-12

Sr. No

Voltage Ratio 2011-12

1 400/220 1

2 220/132, 110 5

3 220/33, 22 12

4 132/33 9

5 110/33, 22 0

Total 27

Table 20 : No. of Additional Link Lines required for the year 2011-12

Table: 20.1 - No. of Additional link lines for the year 2011-12 for S/S’s where only single source is available.

Sr. No

Voltage (kV) 2011-12

1 400 -

2 220 10

3 132 12

4 110-100 -

Total 22

Table: 20.2 - No. of Additional link lines for the year 2011-12 to meet Demand without Load

shedding and to insure reliability and quality of supply.

Sr. No

Voltage (kV) 2011-12

1 400 -

2 220 8

3 132 8

4 110-100 2

Total 18

64

Page 68: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15

STU/TRA�S-PLA�/DOC-4 WEF 01/04/10

Table: 20.3 - No. of Additional link lines for the year 2011-12 for evacuation arrangement.

Sr. No

Voltage (kV) 2011-12

1 400 3

2 220 7

3 132 -

4 110-100 -

Total 10

Table: 20.4 - No. of Additional link lines for the year 2011-12 for New substations to have

alternate source.

Sr. No

Voltage (kV) 2011-12

1 400 -

2 220 4

3 132 1

4 110-100 -

Total 5

Conclusion

According to Load flow studies overloading can be removed by constructing proposed

400kV, 220kV, 132kV, 110/100kV S/s and Augmentation of transformer capacity in existing

S/s.

65

Page 69: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15

STU/TRA�S-PLA�/DOC-4 WEF 01/04/10

Year 2012-13

In the year 2012-13, it is estimated that Maharashtra will meet a demand of about

24638 MW considering the available generation of 31624 MW indicating surplus position of

state.

It is anticipated that there will not be any load shedding during this year and we can supply

power to all categories of consumers without any interruption due to generation shortage or

transmission network inadequacy.

The substation requirement for the year for strengthening of the network is tabulated in Table

21, Augmentation in Table 22 & Additional link lines in Table 23.

Table: 21 – No. of Substation requirement for the year

2012-13

Sr. No

Voltage Level (kV) 2012-13

1 765 2

2 400 4

3 220 -

4 132 -

5 110/100 -

Total 6

Table 22: No. of Augmentations for the year 2012-13

Table: 22.1 - No. of Augmentation by Addition of transformers required for the year 2012-13

Sr. No

Voltage Ratio 2012-13

1 400/220 2

2 220/132, 110 1

3 220/33, 22 6

4 132/33 6

5 110/33, 22 1

Total 16

66

Page 70: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15

STU/TRA�S-PLA�/DOC-4 WEF 01/04/10

Table: 22.2 - No. of Augmentation by Replacement of transformer for the year 2012-13

Sr. No

Voltage Ratio 2012-13

1 400/220 -

2 220/132, 110 -

3 220/33, 22 4

4 132/33 9

5 110/33, 22 2

Total 15

Table 23: List of Additional Link Lines required for the year 2012-13

Table: 23.1 – No. of Additional link lines for the year 2012-13 For S/S’s where only single source is available.

Sr. No

Voltage (kV) 2012-13

1 400 -

2 220 1

3 132 12

4 110-100 2

Total 15

Table: 23.2 - No. of Additional link lines for the year 2012-13 to meet Demand without Load

shedding and to insure reliability and quality of supply.

Sr. No

Voltage (kV) 2011-12

1 400 -

2 220 2

3 132 13

4 110-100 -

Total 15

67

Page 71: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15

STU/TRA�S-PLA�/DOC-4 WEF 01/04/10

Table: 23.3 - No. of Additional link lines for the year 2012-13 for evacuation arrangement.

Sr. No

Voltage (kV) 2013-14

1 400 -

2 220 -

3 132 -

4 110-100 -

Total 0

Table: 23.4 - No. of Additional link lines for the year 2012-13 for New substations to have

alternate source.

Sr. No

Voltage (kV) 2011-12

1 400 -

2 220 -

3 132 3

4 110-100 -

Total 3

Conclusion

According to Load flow studies overloading can be removed by constructing proposed

400kV, 220kV, 132kV, 110/100kV S/s and Augmentation of transformer capacity in existing

S/s. Also from this year we can meet Unrestricted Demand.

68

Page 72: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15

STU/TRA�S-PLA�/DOC-4 WEF 01/04/10

Year 2013-14

In the year 2013-14, it is estimated that Maharashtra will meet a demand of about

26610 MW considering the available generation of 33042 MW indicating surplus position of

state.

It is anticipated that there will not be any load shedding during this year and we can supply

power to all categories of consumers without any interruption due to generation shortage or

transmission network inadequacy.

The substation requirement for the year for strengthening of the network is tabulated in Table

24, Augmentation in Table 25 & Additional link lines in Table 26.

Table: 24 – No. of Substation requirement for the year

2013-14

Sr. No

Voltage Level (kV) 2013-14

1 765 0

2 400 4

3 220 1

4 132 -

5 110/100 -

Total 5

Table 25: No. of Augmentations for the year 2013-14

Table: 25.1 - No. of Augmentation by Addition of transformers required for the year 2013-14

Sr. No

Voltage Ratio 2013-14

1 400/220 2

2 220/132, 110 -

3 220/33, 22 6

4 132/33 2

5 110/33, 22 1

Total 11

69

Page 73: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15

STU/TRA�S-PLA�/DOC-4 WEF 01/04/10

Table: 25.2 - No. of Augmentation by Replacement of transformer for the year 2013-14

Sr. No

Voltage Ratio 2013-14

1 400/220 -

2 220/132, 110 1

3 220/33, 22 3

4 132/33 3

5 110/33, 22 1

Total 8

Table 26: List of Additional Link Lines required for the year 2013-14

Table: 26.1 – No. of Additional link lines for the year 2013-14 For S/S’s where only single source is available.

Sr. No

Voltage (kV) 2013-14

1 400 -

2 220 -

3 132 1

4 110-100 -

Total 1

Table: 26.2 – No. of Additional link lines for the year 2013-14 to meet Demand without Load

shedding and to insure reliability and quality of supply.

Sr. No

Voltage (kV) 2013-14

1 400 -

2 220 2

3 132 5

4 110-100 -

Total 7

70

Page 74: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15

STU/TRA�S-PLA�/DOC-4 WEF 01/04/10

Table: 26.3 - No. of Additional link lines for the year 2013-14 for evacuation arrangement.

Sr. No

Voltage (kV) 2013-14

1 400 2

2 220 -

3 132 -

4 110-100 -

Total 2

Table: 26.4 - No. of Additional link lines for the year 2013-14 for New substations to have

alternate source.

Sr. No

Voltage (kV) 2013-14

1 400 -

2 220 4

3 132 6

4 110-100 -

Total 10

Conclusion

According to Load flow studies overloading can be removed by constructing proposed

765kV, 400kV, 220kV, 132kV, 110/100kV S/s and Augmentation of transformer capacity in

existing S/s. Also from this year we can meet Unrestricted Demand.

71

Page 75: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15

STU/TRA�S-PLA�/DOC-4 WEF 01/04/10

Year 2014-15

In the year 2014-15, it is estimated that Maharashtra will meet a demand of about

28738 MW considering the available generation of 34587 MW indicating surplus position of

state.

It is anticipated that there will not be any load shedding during this year and we can supply

power to all categories of consumers without any interruption due to generation shortage or

transmission network inadequacy.

The substation requirement for the year for strengthening of the network is tabulated in Table

27, Augmentation in Table 28 & Additional link lines in Table 29.

Table: 27 – No. of Substation requirement for the year

2014-15

Sr. No

Voltage Level (kV) 2014-15

1 765 -

2 400 2

3 220 -

4 132 -

5 110/100 -

Total 2

Table 28: No. of Augmentations for the year 2014-15

Table: 28.1 - No. of Augmentation by Addition of transformers required for the year 2014-15

Sr. No

Voltage Ratio 2014-15

1 400/220 -

2 220/132, 110 -

3 220/33, 22 1

4 132/33 -

5 110/33, 22 -

Total 1

72

Page 76: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15

STU/TRA�S-PLA�/DOC-4 WEF 01/04/10

Table: 28.2 - No. of Augmentation by Replacement of transformer for the year 2014-15

Sr. No

Voltage Ratio 2014-15

1 400/220 -

2 220/132, 110 -

3 220/33, 22 -

4 132/33 2

5 110/33, 22 -

Total 2

Table 29: List of Additional Link Lines required for the year 2014-15

Table: 29.1 – No. of Additional link lines for the year 2014-15 For S/S’s where only single source is available.

Sr. No

Voltage (kV) 2014-15

1 400 -

2 220 -

3 132 -

4 110-100 -

Total 0

Table: 29.2 – No. of Additional link lines for the year 2014-15 to meet Demand without Load

shedding and to insure reliability and quality of supply.

Sr. No

Voltage (kV) 2014-15

1 400 -

2 220 -

3 132 -

4 110-100 -

Total 0

73

Page 77: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU FIVE YEAR TRANSMISSION PLAN FOR THE YEAR 2010-11 TO 2014-15

STU/TRA�S-PLA�/DOC-4 WEF 01/04/10

Table: 29.3 - No. of Additional link lines for the year 2014-15 for evacuation arrangement.

Sr. No

Voltage (kV) 2014-15

1 400 -

2 220 -

3 132 -

4 110-100 -

Total 0

Table: 29.4 - No. of Additional link lines for the year 2014-15 for New substations to have

alternate source.

Sr. No

Voltage (kV) 2014-15

1 400 -

2 220 2

3 132 -

4 110-100 -

Total 2

Summary Report

Maharashtra system is modeled with all the above considerations so as to ensure catering

the demand prevailing by 2014-15 including exporting power outside the state in such

a way that in all Sub-stations suitable numbers of lines and capacity of transformers are

available with sufficient redundancy in the transmission system.

This will also ensure following:

1) N-1 criteria for Transformers and all link lines.

2) N-2 criteria for Generation evacuation lines.

Western Maharashtra will be connected very strongly with the rest of the grid thereby

ensuring synchronized operation of the entire Maharashtra system to the maximum

possible extent.

74

Page 78: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

MAHARASHTRA STATE

TRANSMISSION COMPANY

LTD.

75

Page 79: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS-PLAN/DOC-04/ WEF 01.04.10

2008-09 2009-10

1 765 KV 0 0 0 0 2 0 0 2

2 400 KV 0 4 5 2 4 4 2 21

3 220 KV 18 22 13 14 0 1 0 68

4 132 KV 11 13 12 2 0 0 0 38

5 110-100 KV 3 0 0 0 0 0 0 3

32 39 30 18 6 5 2 132

1 220 KV 2 1 0 0 0 0 0 3

2 132 KV 2 6 1 1 0 0 0 10

4 7 1 1 0 0 0 13

36 46 31 19 6 5 2 145

1 765 KV 0 0 0 0 900 0 0 900

2 400 KV 0 230 630 272 672 100 60 1964

3 220 KV 763 1878 1024 1049 412 394 35 5554

4 132 KV 420 1295 763 943 0 25 0 3446

5 110-100 KV 99 0 20 0 0 0 0 119

1282 3403 2437 2264 1984 519 95 11983

1 765 KV 0 0 0 0 0 0 0 0

2 400 KV 0 0 0 0 0 0 0 0

3 220 KV 76 30 321 85 42 0 0 554

4 132 KV 718 251 475 732 277 37 0 2490

5 110-100 KV 72 56 0 18 42 0 0 188

866 337 796 835 361 37 0 3232

1 765 KV 0 0 0 0 0 0 0 0

2 400 KV 0 0 0 0 0 0 0 0

3 220 KV 55 257 275 212 40 153 0 992

4 132 KV 119 162 138 57 307 80 0 863

5 110-100 KV 90 3145 25 55 0 0 0 3315

264 3564 438 324 347 233 0 5170

1 765 KV 0 0 0 0 0 0 0 0

2 400 KV 0 0 0 0 0 0 0 0

3 220 KV 0 0 90 255 0 280 80 705

4 132 KV 26 82 155 0 180 75 0 518

5 110-100 KV 0 0 15 0 0 0 0 15

26 82 260 255 180 355 80 1238

1 765 KV 0 0 0 0 0 0 0 0

2 400 KV 0 0 0 273 0 100 0 373

3 220 KV 200 95 30 94 0 0 0 419

4 132 KV 0 30 0 32 0 0 0 62

5 110-100 KV 0 0 0 0 0 0 0 0

200 125 30 399 0 100 0 854

1 765 KV 0 0 0 0 900 0 0 900

2 400 KV 0 230 630 545 672 200 60 2337

3 220 KV 1094 2260 1740 1695 494 827 115 8224

4 132 KV 1283 1820 1531 1764 764 217 0 7379

5 110-100 KV 261 3201 60 73 42 0 0 3637

2637 7511 3961 4077 2872 1244 175 22477

1 765 KV 0 0 0 0 3000 3000 0 6000

2 400 KV 830 4434 7002 3334 2427 4000 2000 24027

3 220 KV 4500 6175 2300 3400 0 200 0 16575

4 132 KV 818 1650 600 200 0 0 3268

5 110-100 KV 150 0 0 0 0 0 0 150

6298 12259 9902 6934 5427 7200 2000 50020

1 765 KV 0 0 0 0 0 0 0 0

2 400 KV 2815 3315 500 500 0 0 0 7130

3 220 KV 4725 3605 1425 725 425 300 25 11230

4 132 KV 2175 2400 275 350 175 50 0 5425

5 110-100 KV 350 400 50 0 25 25 0 850

10065 9720 2250 1575 625 375 25 24635

1 765 KV 0 0 0 0 0 0 0 0

2 400 KV 0 370 0 370 185 0 0 925

3 220 KV 1245 2742 2530 625 100 175 0 7417

4 132 KV 1724 1098 455 425 225 75 50 4051

5 110-100 KV 423 260 160 38 25 25 0 931

3392 4470 3145 1458 535 275 50 13324

1 765 KV 0 0 0 0 3000 3000 0 6000

2 400 KV 3645 8119 7502 4204 2612 4000 2000 32082

3 220 KV 10470 12522 6255 4750 525 675 25 35222

4 132 KV 4716.9 5147.5 1330 975 400 125 50 12744

5 110-100 KV 923 660 210 37.5 50 50 0 1931

19755 26449 15297 9967 6587 7850 2075 87979

TOTAL

TOTALTransmission Lines to have Alternate Source

TOTALTransmission Lines for Strengthening of Evacuation

TOTALTransmission Lines for S/S/ where only Single Source & Single ckt is available

TOTAL

TOTAL EHV LINES

TOTAL

TOTAL CAPACITY

Capacity Addition (MVA)Capacity addition by New Sub-Station

TOTALCapacity addition by Augmentation by Addition of Transformer

TOTALCapacity addition by Augmentation by Replacement of Transformer

2012-13 2013-14

Transmission Lines to ensure Reliability

New Sub-Station for 66KV Elimination

TOTAL

Transmission Lines (Ckt. KM)Transmission Lines for New Sub-Station

TOTAL NEW

2014-15 Total

TOTAL EHV LINES (Ckt.KM)

TOTAL CAPACITY ADDITION

TECHNICAL ABSTRACT (MSETCL)

New Sub-Station

TOTAL

SPILL OVER SCHEMESSr. No. Voltage Level 2010-11 2011-12

76

Page 80: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

EVACUATION SCHEMES

77

Page 81: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS-PLAN/DOC-04/WEF 01/04/10

SR NO NAME OF THE

SUBSTATION

DISTRICT REMARKS

1) 400/220 KV , 2X500 MVA ICTS WITH BAYS

400/220KV, 1X 167 MVA 1 PHASE ICT SPARE

2) LILO OF 400KV BHUSAWAL - I - KORADI - I AT KORADI -II - 15 KM

3) LILO OF 400KV SATPURA - KORADI -I AT KORADI-II - 15 KM

4) 220 KV KORADI -II - MANKAPUR M/C -25KM WITH BAYS

5) 220 KORADI - II - BUTTIBORI D/C -55KM WITH BAYS

6) 220 KORADI - II - NEW KHAPERKHEDA D/C -15KM WITH BAYS

7) KORADI -II - KORADI - III 400KV QUAD D/C LINE- 25 KM

1) 400/220 KV, 2 X 500 MVA ICTS WITH BAYS

400/220 KV, 1 X 167 MVA 1 PHASE ICT SPARE

2) LILO ON 400 KV CHANDRAPUR - PARLI D/C AT CHANDRAPUR -II -

S/STN - 1.8 KM WITH BAYS

3) 400 KV D/C CHANDRAPUR-II - WARRORA - 20 KM

4) 400KV D/C WARORA - WARDHA (PG) - 110KM

5) 220 KV CHANDRAPUR(MIDC) - CHANDRAPUR - II S/STN -20 KM

6) 2X400KV QUAD D/C FROM KORADI - WARDHA(PG) - 70KM

1) UPGRADATION OF EXISTING 220 KV BOTH D/C URAN- APTA LINE

WITH ACCC TW 620 SQ MM CONDUCTOR

2) 220KV URAN - KHARGHAR D/C LINE USING 0.5 ZEBRA ON M/C

WITH BAYS - 36 KMS (ONLY STRINGING)

1) 400/220 KV, 2 X 500 MVA ICTS WITH BAYS 400/220 KV, 1 X 167

MVA 1 PHASE ICT SPARE

LOA Date 23/01/07

2) 400 KV BHUSAWAL (KHADKA) - BHUSAWAL-II - D/C - 10 KM WITH

BAYS

3) 400 KV BHUSAWAL-II- AURANGABAD-I D/C LINE - 185 KM WITH

BAYS

4) 220 KV D/C ON M/C TOWER FROM 400 KV BHUSAWAL(II) -

BHUSAWAL (KHADKA) -10 KM WITH BAYS

5) 220KV BHUSAWAL-II- AMALNER D/C - 90 KM WITH BAYS

6) 400KV LINE BAYS EACH AT EXISTING 400KV KHADKA &

AURANGABAD S/S & 4NOS. 400KV LINE BAYS WITH ONE & HALF

BREAKER TYPE CONST. AT BHUSAWAL-II S/S

1) 220KV PARLI - NANDED D/C LINE - 110 KMS

2) 220KV PARLI GCR - BEED AT PARLI D/C LINE -70 KMS

1) 2 X 25 MVA, 220/33 KV T/FS WITH BAYS AT BALAPUR MIDC

2) 2 X 100 MVA, 220/132 KV ICTS WITH BAYS AT BALAPUR MIDC

3) 220KV PARAS-BALAPUR MIDC M/C LINE - 6 KM WITH BAYS

4) LILO OF 220 KV AKOLA-CHIKHALI AT PARAS EXTENSION - 15 KM

5) REORIENTATION OF 132KV LINES-30 KM WITH BAYS

6) 132 KV BAYS -2 NOS

7) 33 KV OUTLETS - 8 NOS

1) 400/220 KV, 2 X 500 MVA ICTS WITH BAYS 400/220 KV, 1 X 167

MVA 1 PHASE ICT SPARE

2) 400KV KHAPERKHEDA - 765 KORADI-III D/C QUAD -5 KMS

3) 220KV KHAPERKHEDA- II -220 KV KHAPERKHEDA OLD - 7 KM , M/C

LINE WITH BAYS

4) LILO OF 01 CKT AT CHANDRAPUR - I - KORADI-I AT KHAPERKHEDA -

10KM

COMMISSIONED

1) 400KV D/C DHULE-II-DHULE-I - 15 KM WITH BAYS

2) 400 KV D/C LINE FROM 400 KV DHULE-II - NASHIK - 190KMS.

3) 2x315MVA,400/220kV ICT

4) 220 KV D/C LINE TO DONDAICHA ( existing) S/S -15 KMS .

8 400KV DHULE-II S/S

( DONDAICHA)

(2012-13)

DHULE Evacuation of Power from

central sector & to feed the

upcoming load.

6 EVACUATION OF POWER

FROM PARAS EXTENSION

PROJECT

(2008-09)

1 X 250 MW EXP.

1 X 300 MW REP.

AKOLA LOA Date 31/08/06

20.5% Civil Work

Completed

LOA Date 23/01/07

3.5% Civil Work Completed

NAGPUR400KV KHAPERKHEDA S/S

(500MW GENERATION

EVACUATION PROJECT)

(2009-10)

7

4 400/220 KV BHUSAWAL - II

SUB-STATION

2 X 500 MW EXP.

(2010 - 11)

1 X 300 MW REP.

(2010 - 11)

JALGAON

LOA for Civil Works Date

05/11/07

5 EVACUATION OF POWER

FROM PARLI TPS

EXTENSION

1 X 250 MW EXP.

( 2008-09)

1 X 300 MW REP.

( 2011-12)

BEED LOA Date 31/08/06 24.5%

Civil Work Completed

2 400/220 KV CHANDRAPUR-II

S/S ALONG WITH

SWITCHING STATION

(CHANDRAPUR

2 X 500 MW)

(2011-12)

CHANDRAPUR LOA Date 30/04/08 Land

Available

3 EVACUATION OF POWER

FROM URAN G.T.

EXPANSION PROJECT

1) Block No. -I - 700 MW

2) Block No. - II - 340 MW

(2009-10)

RAIGAD LOA Date 30/04/08

Land Available

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

EVACUATION SCHEMES

TOTAL SCOPE OF WORK

EVACUATION SCHEMES ( MAHAGENCO )

1 400/220 KV KORADI -II SUB-

STATION

(KORADI 3 X 660 MW)

(ADANI 2 X 660 MW)

(2010-11)

NAGPUR Evacuation of M/s Adani

Generation at Gondia &

MAHAGenco

78

Page 82: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

EHV CC O&M ZONE :

WASHI

79

Page 83: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04/ W.E.F 01/04/2010

SR

NO

NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEME

1) 220/100KV, 2 X 100MVA T/FS WITH BAYS

2)

3)

2 X 220KV BAYS

LILO ON 220 KV PADGHE-BOISAR AT VASAI S/S- 9 KM

4) 2 NOS.OF 100KV LINE BAYS EACH AT OLD & NEW

SWITCHYARDS

5) REORIENTATION OF 100KV LINES - 15KM

1) 2X200MVA,220/100KV ICT

2) 2X50 MVA, 220/22KV T/F

3) D/C LINE LILO ON 220KV PADGHE - KALWA LINE WITH

BAYS - 3 KM

4) LILO OF 100 KV PADGHE - BHIWANDI SC LINE - 1 KM

5) LILO OF 100KV PADGHE - PANJARPUR SC LINE - 1

KM

6) D/C LILO OF 100 KV PADGHE - PISE LINE - 4 KM

7) LILO OF 220KV NASIK - KALWA CKT 3&4 AT BAPGAON-

3 KM

8) 12X22 KV OUTLETS

1) 4 X 50 MVA, 220/22 KV T/FS WITH BAYS

2) LILO ON 220 KV BORIVALI- MULUND S/C LINE AT

BHANDUP S/S- 3KM

3) 22 KV OUTLETS - 24 NOS.

1) LILO OF 220 KV PADGHE-WADA - 3.0 KM WITH BAYS

AT KUDUS S/S

2) 2X50MVA, 220/22KV T/F WITH BAYS

3) 22KV OUTLETS - 12 NOS.

1) 2 X 50 MVA, 220/22 KV T/FS WITH BAYS

2)

3)

22KV OUTLETS - 12 NOS.

LILO ON 220KV KALWA - PADGHE LINE WITH BAYS - 1

KM

1) 4 X 50 MVA, 220/22 KV T/F'S WITH BAYS

2) LILO OF 220KV PADGHE - KALWA CKT-I - 7 KM WITH

BAYS

3) 24 X 22KV OUTLETS

1) 2 X 50 MVA, 220/22 KV T/FS WITH BAYS

2) 22KV OUTLETS - 12 NOS.

3) LILO ON KALWA - PADGHE LINE WITH BAYS - 2.5 KM

1) 2 X 50 MVA, 110/22 KV T/FS WITH BAYS

2) LILO ON 110KV KALWA - DOMBIVALI LINE - 4 CKM

WITH BAYS

3) 10 x 22KV OUTLETS

1) 100/22KV, 2 X 25MVA T/FS WITH BAYS

2) 100KV D/C LINE AMBERNATH II - NERAL - 25 KM

3) 6 X 22KV OUTLETS

1)

SCOPE OF WORK BY MSETCL

LILO ON 220KV APTA - KALWA S/C TO NAVI MUMBAI

(PGCIL) - 10 KMS WITH BAYS

2) LILO ON 220KV KANDALGAON - KHARGHAR FOR

NAVI MUMBAI -5KM.

1) 2 X 50 MVA, 220/22 KV T/FS WITH BAYS

2)

3)

12 X 22KV OUTLETS

LILO ON 220KV PADGHE - JAMBHUL LINE - 10 KMS

WITH BAYS

1) 220KV KHARGHAR - WASHI D/C LINE WITH BAYS - 20

KMS

2) 2 X 100MVA, 220/100KV ICTS WITH BAYS

3) 2 X 50MVA, 220/22KV T/FS WITH BAYS

4) 2 X 100KV BAYS

5) 12 X 22KV OUTLETS

6) REORIENTATION OF 100 KV LINES -20 KM

1) 2 X 50 MVA, 220/33-22 KV T/FS WITH BAYS

2) 12 X 33-22KV OUTLETS

3) 220KV U/G CABLE FROM BORIVALI - 8 KMS

1) 2 X 25 MVA, 132/33 KV T/FS WITH BAYS

2) 8 X 33KV OUTLETS

3) 132KV DHANU - DAPCHERI D/C LINE WITH BAYS - 25

KMS

220 KV

GOREGAON FILM CITY S/S

(2009-10)

14

10 400KV NAVI MUMBAI

(PGCIL)

(2009-10)

132 KV DAPCHERI S/S

(2009-10)

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

WASHI EHV CONSTRUCTION CUM (O&M) ZONE

TOTAL SCOPE OF WORK

13

220KV

ULHASNAGAR S/S

(2009-10)

11

12 220KV WASHI GIS

(2009-10)

Present recorded peak load on Mahane-100kV, Amernath-100kV

S/S are 50MW and 40MW respectively. It is anticipated by the

year 2009-10 that total load will reach to about 108MW. Hence it

is necessary to go in for new 220kV sub-station at Ulhasnagar.

THANE

THANE

Voltage improvement & load catering.

Dapcheri-132kV S/S is considered in year 2009-10 for reducing

the loading and to feed the upcomming load at proper voltage.

THANE

THANE

Present recorded peak load on Vashi-100kV is 110MW. It is

anticipated by the year 2009-10 that the load will reach to about

135MW. Hence it is necessary to go in for new 220kV sub-station

at Vashi The new substation Vashi -220kV S/S is proposed in

year 2009-10 for reducing loading on Vashi-100kV S/S and

improve voltage profile. By the commissioning of this substation,

voltage profile will improve .

Goregaon FC-220kV is considered to reduce the loading of Kalwa-

220kV S/S.

MUMBAI

110 KV

MUMBRA S/S

(2008-09)

THANE Voltage improvement & load catering.8

Voltage improvement & load catering.

THANE220KV KUDUS S/S

(2008-09)

Voltage improvement & load catering.220KV BHIWANDI - III

(2008-09)

Voltage improvement & load catering.

220KV BAPGAON S/S

(2008-09)

2

7 THANE

4

Voltage improvement & load catering.220 KV BHANDUP GIS

(2008-09)

THANE

9 Neral 100kV S/S is considered for reducing the loading on

Ambernath 220kV S/S. This new Substation is fed from

Ambernath 220 kV S/S by constructing 100kV D/C line of 25kM.

100 KV NERAL

(KOLHARE) S/S

(2008-09)

RAIGAD

1 220KV VASAI S/S

(2008-09)

3

Present recorded peak load on Kolshet and Wada S/S are 90MW

and 72MW. It is anticipated by the year 2007-08 the load will

reach to about 172MW. Hence it is necessary to go in for 220kV

sub-station at Kudus. Kudus-220kV S/S is proposed on LILO of

220kV existing Padghe–Wada line in year 2007-08 for reducing

loading on Kolshet and Wada network.

MUMBAI

SPILL OVER SCHEMES

THANE6 220 KV BHIWANDI - IV S/S

(2008-09)

5 * 220KV KNOWLEDGE

PARK, AIROLI

(2008-09)

THANE

THANE

Voltage improvement & load catering.

This station is considered to meet the load growth in Kalwa circle

and to improve the voltage profile. Bapgaon -220kV S/S is

proposed on LILO on 220kV existing Padghe –Kalwa D/C & 220

kV Nasik-Kalwa ckt 3&4 at Bapgaon.

80

Page 84: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04/ W.E.F 01/04/2010

SR

NO

NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEME

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

WASHI EHV CONSTRUCTION CUM (O&M) ZONE

TOTAL SCOPE OF WORK

1 132 KV LINK LINE

(2009-10)

THANE 1) 132kV BOISAR-II - DAPCHERI SCDC LINE - 25 KM To provide uninterrupted supply during planned outages it is

necessary to add proposed line

1 220 KV LINK LINE

(2009-10)

RAIGAD 1) 220KV KHARGHAR - NERUL SCDC LINE WITH BAYS-

10 KMS

Since the existing 220kV Kharghar-Nerul S/c line is critically

loaded to an extent of 186 MW. Hence it is suggested to add

proposed line to reduce the loading of existing line and to meet

additional load growth and contingency.

2 220 KV LINK LINE

(2008-09)

MUMBAI 1) 220KV D/C LINE NAGOTHANE - IPCL - 9 KMS WITH

BAYS

Since the existing 220kV Nagothane-IPCL S/c line is getting

loaded to an extent of 147 MW. It is anticipated the load will

reach to critical value by the year 2011-12. Hence it is suggested

to add proposed line to meet additional load growth and

contingency.

3 220 KV LINK LINE

(2009-10)

RAIGAD 1) 220KV TROMBAY(MSETCL) - NERUL SCDC LINE

WITH BAYS-30 KMS

Since the existing 220kV Trombay-Nerul S/c line is loaded to an

extent of 136 MW during Non-Coinsident peak condition.

Considering the increasing developement at Nerul it is necessary

to propose additional line to meet additional load growth and

contingency.

4 220 KV LINK LINE

(2008-09)

THANE 1) 220KV BOISAR (PGCIL) - 220KV BOISAR (MSETCL)

LINE - 15 KM

Since the existing 220kV Boisar-II-Boisar-PG S/c line is critically

loaded to an extent of 241 MW. Hence it is suggested to add

proposed line to reduce the loading of existing line and to meet

additional load growth and contingency.

5 220 KV LINK LINE

(2008-09)

RAIGAD 1) 220 KV NAGOTHANE -WADKHAL D/C LINE - 30 KM For strengthening of evacuation of Dabhol power.

6 220 KV LINK LINE

(2009-10)

THANE 1) 220KV KALWA - TROMBAY SCDC LINE WITH BAYS-

25.56 KMS

Line is required for evacuation of proposed Generation at

Trombay

7 132 KV LINK LINE

(2008-09)

THANE 1) 132KV LINE FROM 220KV BOISAR - 132KV BOISAR

MIDC SCDC LINE - 8.7KM

Since the existing 132kV Boisar-Boisar MIDC S/c line is critically

loaded to an extent of 68 MW. Hence it is suggested to add

proposed line to reduce the loading of existing line and to meet

additional load growth and contingency.

8 100 KV LINK LINE

(2008-09)

THANE 1) 100 KV BAPGAON-MOHANE SCDC LINE - 20 KM Since the existing 100kV Mohane-Padghe S/c line is 60 MW.

Mohane Being the industrial estate and considering heavy load

growth it is suggested to add proposed line to meet additional

load growth and contingency.

9 100 KV LINK LINE

(2009-10)

THANE 1) 100KV BHIVANDI - PADGHE SCDC LINE WITH BAYS-

16 KMS

Since the existing 100kV Bhiwandi-Padghe S/c line is critically

loaded to an extent of 106 MW. Hence it is suggested to add

proposed line to reduce the loading of existing line and to meet

additional load growth and contingency.

10 100 KV LINK LINE

(2009-10)

THANE 1) 100 KV BAPGAON - BHIWANDI - 15 KM WITH BAYS Since the existing 100kV Bhiwandi-Padghe S/c line is critically

loaded to an extent of 106 MW. Hence it is suggested to add

proposed line to reduce the loading of existing line and to meet

additional load growth and contingency.

1 220 KV LINK LINE

(2009-10)

RAIGAD 1) 220KV APTA - CHICHWAD M/C LINE WITH BAYS- 60

KMS

For strengthening of evacuation scheme of Uran.

2 220 KV LINK LINE *

(2009-10)

RAIGAD 1) LILO ON 220KV APTA - MAHAD LINE AT NAGOTHANE

WITH BAYS- 5 KMS

For strengthening of evacuation scheme of Uran.

ADDITIONAL LINK LINES FOR S/S WHERE ONLY SINGLE CKT AND SINGLE SOURCE IS AVAILABLE

As per the methodology stipulated in the guideline of State Grid Code Regulation No. 9.4

STRENGTHENING FOR EVACUATION ARRANGEMENT

ADDITIONAL LINK LINES

ADDITIONAL LINK LINES TO MEET DEMAND WITHOUT LOAD SHEDDING AND TO ENSURE RELIABILITY AND QUALITY OF SUPPLY

81

Page 85: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04/ W.E.F 01/04/2010

SR

NO

NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEME

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

WASHI EHV CONSTRUCTION CUM (O&M) ZONE

TOTAL SCOPE OF WORK

1) ADD. 1X100 MVA, 220/100KV ICT WITH BAYS

2) 100 KV D/C LINE ON D/C TOWER FOR AMBARNATH I

TO INTERCONNECTION - 5 KM

3) 2X100KV BAYS AT AMBERNATH - I

1) 1X 25MVA , 220/22KV T/FS WITH BAYS

2) 2 X 22KV OUTLETS.

3 220 KV DOMBIVALI II S/S

(2008-09)

THANE 1) 1X200 MVA, 220/100 KV ICT WITH BAYS To avoid loss of supply in case of outages or interruptions on any

one transformer

1) 1X50 MVA, 100/22 KV T/F WITH BAYS

2) 22KV OUTLETS - 6 NOS

1) 1 X 25MVA , 132/33KV T/F WITH BAYS

2) 4 X 33KV OUTLETS.

3) 3 CORE, 400SQMM, XLPE CABLE - 0.5 KM

1) 1 X 25MVA , 100/22KV T/F WITH BAY

2) 4 X 22KV OUTLETS.

7 220 kV NAGOTHANE

(2009-10)

Raigad 1)

2)

Add 1 X 25 MVA 220/22 KV T/F with bay

4 x 22 kV outlets

Existing transformer capacity available in S/s is 1 x 25 MVA and

the Load reach is 8 MVA.To avoid the loss of supply in case of

outages or interruptions of transformers.

8 132 kV DAHANU

(2009-10)

THANE 1)

2)

Add 1 X 25 MVA, 132/33 kV T/F with bay.

4 X 33 kV out lets

Existing Transformer capacity avaible is 1 X 50, 1 X 25 MVA and

the load reached is 33 MVA To avoid loss of supply in case of

outages or interruptions on transformer.

1) 1X50 MVA,220/22 KV T/F

2) 6X22 KV OUTLETS

3) 3 CORE, 300SQMM, XLPE CABLE - 0.6 KM

1) 1X200 MVA, 220/100 KV ICT WITH BAYS

2) 100 KV BAYS - 2 NOS

1) 1 X25MVA , 220/22KV T/F WITH BAYS

2) 6 X 22KV OUTLETS.

3) 3 CORE, 400SQMM, XLPE CABLE - 0.5 KM

1) 1 X 50MVA , 220/33-22KV T/F WITH BAYS

2) 3 X 22KV OUTLETS

3) 2 X 33KV OUTLETS

4) 3 CORE, 400SQMM, XLPE CABLE - 0.6 KM

1) 1X50 MVA, 220/33-22KV T/F WITH BAYS

2) 4X33KV OUTLET

3) 2X22KV OUTLET

1) CONST. OF 220KV D/C LINE ON D/C TOWERS LILO ON

220KV PADGHE - COLOURCHEM LINE TO TEMGHAR

S/S - 10 KM

2) 220KV LINE BAYS AT TEMGHAR S/S - 2 NOS.

3) REPLACEMENT OF 2X50MVA, 100/22KV T/FS BY

2X50MVA, 220/22KV T/FS AT 220KV TEMGHAR S/S

WITH 12 X 22KV OUTLETS

4) CONST. OF 100KV SCDC LINE FOR DIVERSION OF

100KV LINE AT TEMGHAR S/S - 0.5KM

5) ADDITION OF 1X50MVA, 100/22KV T/F AT 100/22KV

BHIWANDI S/S WITH 4X 22KV GIS BAYS

7 400KV NAGOTHANE S/S

(2009-10)

RAIGAD 1) 1 X 500 MVA, 400/220KV ICT WITH BAYS Existing transformer capacity available in S/s is,400/220kV, 2 x

315 MVA and the load reached is 487 MVA Considering the

maximum load reach on the transformer, in event of

interruption/outage on any one of the transformer other

transformer should take care of existing load so as to avoid load

shedding.

8 400 KV KALWA S/S

(2009-10)

THANE 1) 1 X 500 MVA 400/220 KV ICT WITH BAYS Existing transformer capacity available in S/s is,400/220kV, 2 x

600 MVA and the load reached is 979 MVA Considering the

maximum load reach on the transformer, in event of

interruption/outage on any one of the transformer other

transformer should take care of existing load so as to avoid load

shedding.

9 132 kV PALGHAR

(2009-10)

Thane 1)

2)

Add 1 X 50 MVA ,132/33 kV T/F with bays.

6 X 33 kV out lets.

Existing transformer capacity available in S/s is 2 X 25 MVA and

load is 44 MVA. Considering the maximum load reached on the

transformer in the event of interruptions/outage on any one of the

transformer other transformer should take care of existing load

3

220 KV PADGHE S/S

(2008-09)

2 THANE Existing transformer capacity available in S/s is,

220/100 - 2 x 200 - 281 MVA

Considering the maximum load reach on the transformer, in event

of interruption/outage on any one of the transformer other

transformer should take care of existing load so as to avoid load

shedding.

Existing transformer capacity available in S/s is,

220/22 - 2 x 50 - 44 MVA

Hence it is necessary to propose additional transformer to meet

additional load growth and contingency.

RAIGAD220K KV MAHAD S/S

(2008-09)

132 KV TALEBAZAR S/S*

(2008-09)

5

4 220 KV PADGHE S/S

(2008-09)

To avoid loss of supply in case of outages or interruptions on any

one transformer

220 KV MAHAPE S/S

(2008-09)

THANE Existing transformer capacity available in S/s is,

220/22 - 2 x 50 - 66 MVA

Considering the maximum load reach on the transformer, in event

of interruption/outage on any one of the transformer other

transformer should take care of existing load so as to avoid load

shedding.

AUGMENTATION OF S/S BY ADDITION TO REDUCE LOADING OF TRANSFORMER

220 KV WASHALA S/S*

(2008-09)

6 100 KV JITE S/S*

(2008-09)

RAIGAD

1

4 Existing transformer capacity available in S/s is,

220/33 - 2 x 50 - 55 MVA

Considering the maximum load reach on the transformer, in event

of interruption/outage on any one of the transformer other

transformer should take care of existing load so as to avoid load

shedding.

Existing transformer capacity available in S/s is,

220/33 - 2 x 50 - 73 MVA load

Considering the maximum load reach on the transformer, in event

of interruption/outage on any one of the transformer other

transformer should take care of existing load so as to avoid load

shedding.

THANE

THANE

To avoid loss of supply in case of outages or interruptions on any

one transformer

To avoid loss of supply in case of outages or interruptions on any

one transformer

SINDHUDUR

G

THANE

RAIGAD

Existing transformer capacity available in Temghar S/s is,

220/22 - 2 x 50 - 85 MVA load

100/22 - 2 x 50 - 74 MVA load

Considering the maximum load reach on the transformer, in event

of interruption/outage on any one of the transformer other

transformer should take care of existing load so as to avoid load

shedding.

To avoid loss of supply in case of outages or interruptions on any

one transformer

220KVAMBERNATH - II*

S/S (JAMBHUL)

(2008-09)

To avoid loss of supply in case of outages or interruptions on any

one transformer

AUGMENTATION OF S/S BY ADDITION OF ICT/T/F

AUGMENTATION OF S/S BY ADDITION WHERE ONLY SINGLE TRANSFORMER IS AVAILABLE

2

1

220 KV ONGC S/S PANVEL

(2008-09)

5 220KV NERUL S/S

(2008-09)

THANE

6 COMPREHENSIVE

SCHEME FOR CAPACITY

ADDITION AT EHV S/S IN

BHIWANDI AREA

(2008-09)

THANE

82

Page 86: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04/ W.E.F 01/04/2010

SR

NO

NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEME

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

WASHI EHV CONSTRUCTION CUM (O&M) ZONE

TOTAL SCOPE OF WORK

10 100 kV VASAI

(2009-10)

Thane 1)

2)

Add 1x50 MVA 100/22 KV T/F with bay

6 x 22 kV outlets

Existing transformer capacity available in S/s is 3 x 50

And the Load reach is 126 MVA.Considering the maximum load

reached on the transformer in the event of interruptions/outage on

any one of the transformer other transformer should take care of

existing load

11 100 kV SHAHAPUR

(2009-10)

Thane 1)

2)

Add 1x25 MVA 100/22 KV T/F with bay

4 x 22 kV outlets

Existing transformer capacity available in S/s is 2 x 25

And the Load reach is 32 MVA.Considering the maximum load

reached on the transformer in the event of interruptions/outage on

any one of the transformer other transformer should take care of

existing load

12 100 kV PATALGANGA

(2009-10)

Raigad 1)

2)

Add 1x25 MVA 100/22 KV T/F with bay

4 x 22 kV outlets

Existing transformer capacity available in S/s is 2 x 25

And the Load reach is 32 MVA.Considering the maximum load

reached on the transformer in the event of interruptions/outage on

any one of the transformer other transformer should take care of

existing load

13 100 kV MHSALA

(2009-10)

Raigad 1)

2)

Add 1x25 MVA 100/22 KV T/F with bay

4 x 22 kV outlets

Existing transformer capacity available in S/s is 2 x 12.5

And the Load reach is 19 MVA.Considering the maximum load

reached on the transformer in the event of interruptions/outage on

any one of the transformer other transformer should take care of

existing load

14 100 kV ROHA

(2009-10)

Raigad 1)

2)

Add 1x50 MVA 100/22 KV T/F with bay

6 x 22 kV outlets

Existing transformer capacity available in S/s is 2 x 25

And the Load reach is 46 MVA.Considering the maximum load

reached on the transformer in the event of interruptions/outage on

any one of the transformer other transformer should take care of

existing load

15 220 kV KALWA

(2009-10)

Thane 1)

2)

Add 1x50 MVA 220/22 KV T/F with bay

6 x 22 kV outlets

Existing transformer capacity available in S/s is 2 x 50

And the Load reach is 81 MVA.Considering the maximum load

reached on the transformer in the event of interruptions/outage on

any one of the transformer other transformer should take care of

existing load

16 220 kV URAN

(2009-10)

Raigad 1)

2)

Add 1x50 MVA 220/22 KV T/F with bay

6 x 22 kV outlets

Existing transformer capacity available in S/s is 2 x 25

And the Load reach is 41 MVA.Considering the maximum load

reached on the transformer in the event of interruptions/outage on

any one of the transformer other transformer should take care of

existing load

17 220 kV TEMGHAR *

(2009-10)

Thane 1)

2)

Add 1x50 MVA 220/22 KV T/F with bay

6 x 22 kV outlets

Existing transformer capacity available in S/s is 2 x 50

And the Load reach is70 MVA.Considering the maximum load

reached on the transformer in the event of interruptions/outage on

any one of the transformer other transformer should take care of

existing loadTo remove 100/22 kV Temghar I.

18 220 kV ANANDNAGAR

(AMBARNATH - III )

(2009-10)

Thane 1)

2)

Add 1x50 MVA 220/22 KV T/F with bay

6 x 22 kV outlets

Existing transformer capacity available in S/s is 2 x 50

And the Load reach is 62 MVA.Considering the maximum load

reached on the transformer in the event of interruptions/outage on

any one of the transformer other transformer should take care of

existing load

19 220 kV DOMBIVALI-II (PAL)

(2009-10)

Thane 1)

2)

Add 1x50 MVA 220/22 KV T/F with bay

6 x 22 kV outlets

Existing transformer capacity available in S/s is 2 x 50

And the Load reach is 54 MVA.Considering the maximum load

reached on the transformer in the event of interruptions/outage on

any one of the transformer other transformer should take care of

existing load

20 220 kV MAHAD

(2009-10)

Raigad 1)

2)

Add 1x50 MVA 220/22 KV T/F with bay

6 x 22 kV outlets

Existing transformer capacity available in S/s is 2 x 50

And the Load reach is 54 MVA.Considering the maximum load

reached on the transformer in the event of interruptions/outage on

any one of the transformer other transformer should take care of

existing load

21 220 kV WADA

(2009-10)

Raigad 1)

2)

Add 1x50 MVA 220/22 KV T/F with bay

6 x 22 kV outlets

Existing transformer capacity available in S/s is 3 x 50

And the Load reach is 99 MVA.Considering the maximum load

reached on the transformer in the event of interruptions/outage on

any one of the transformer other transformer should take care of

existing load

83

Page 87: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04/ W.E.F 01/04/2010

SR

NO

NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEME

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

WASHI EHV CONSTRUCTION CUM (O&M) ZONE

TOTAL SCOPE OF WORK

1) 1 X (50-20)MVA, 100/22KV T/F WITH BAYS

2) 2X22KV OUTLETS

1) 1 X (50-25) MVA, 132/33 KV T/FS.

2) 3 X 33 KV OUTLETS

1) 1 X (50-25) MVA, 132/33 KV T/F

2) 3 X 33KV OUTLETS.

1) REP. 1 X (50-25)MVA, 100/22KV T/FS.

2) 3 X 22KV OUTLETS

1) 1 X (50-25)MVA, 100/22KV T/FS.

2) 4 X 11KV OUTLETS

1) 1 X (50-25)MVA, 100/22KV T/F WITH BAYS

2) 2X22KV OUTLETS

7 100KV

AMBERNATH I S/S

(2008-09)

THANE 1)

2)

1 X (50-25)MVA, 100/22KV T/F WITH BAYS

2X22KV OUTLETS

Existing transformer capacity available in S/s is,

100/22 - 1 x 50 - 34 load

100/22 - 2 x 25 - 30 load

Considering the maximum load reach on the transformer, in event

of interruption/outage on any one of the transformer other

transformer should take care of existing load so as to avoid load

shedding.

1) 1 X (50-25)MVA, 100/22KV T/F WITH BAYS

2) 2X22KV OUTLETS

1) 1 X (50-25)MVA, 100/22KV T/F WITH BAYS

2) 2X22KV OUTLETS

10 220 kV KANDALGAON

(2009-10)

Raigad 1)

2)

1 X ( 50-20) MVA , 220/22 kV T/F with bays.

4 X 22 kV outlets.

Existing transformer capacity available in S/s is 1 x 20 ,

1 x 50 and the Load reach is 39 MVA. The T/F is replaced to meet

anticipated load growth

11 220KV KALWA S/S

(2009-10)

THANE 1)

2)

1x(200-125)MVA, 220/100KV ICT'S WITH BAYS

100KV BAYS - 2NOS

Existing transformer capacity available in S/s is,

220/100kV, 4 x 125MVA and the load reached is 368MVA

considering the maximum load reach on the transformer, in event

of intruption/outage on any one of the transformer other

transformer should take care of existing load so as to avoid load

shedding. 12 220KV TROMBAY S/S

(2009-10)

MUMBAI 1)

2)

1x(200-125)MVA, 220/100KV ICT'S WITH BAYS

100KV BAYS - 2NOS

Existing transformer capacity available in S/s is 220/100kV, 2 x

125 MVA and the load reached is 165 MVA,Considering the

maximum load reach on the transformer, in event of

interruption/outage on any one of the transformer other

transformer should take care of existing load so as to avoid load

shedding.

13 220KV BORIVLI S/S

(2009-10)

MUMBAI 1)

2)

1x(200-125)MVA, 220/100KV ICT'S WITH BAYS

100KV BAYS - 2NOS

Existing transformer capacity available in S/s is 220/100kV, 2 x

125 MVAand the load reached is 223MVA,Considering the

maximum load reach on the transformer, in event of

interruption/outage on any one of the transformer other

transformer should take care of existing load so as to avoid load

shedding.

14 220KV PADGHE S/S

(2009-10)

THANE 1)

2)

1x(200-125)MVA, 220/100KV ICT'S WITH BAYS

100KV BAYS - 2NOS

Existing transformer capacity available in S/s is,220/100kV,2 x

200 MVA and 220/100 kV,1 x 125MVA and the load reached is

263MVA and 98 MVA respectively.Considering the maximum

load reach on the transformer, in event of interruption/outage on

any one of the transformer other transformer should take care of

existing load so as to avoid load shedding.

15 220KV BOISAR II S/S

(2009-10)

THANE 1)

2)

1X(200-150)MVA, 220/132KV ICT WITH BAYS

100KV BAYS - 2NOS

Existing transformer capacity available in S/s is 220/132kV 2 x

150MVAand1X 200MVA the load reached is

315MVA,Considering the maximum load reach on the

transformer, in event of interruption/outage on any one of the

transformer other transformer should take care of existing load so

as to avoid load shedding.

AUGMENTATION OF S/S BY REPLACEMENT OF ICT/T/F

4 100KV

DOMBIVALI S/S

(2008-09)

THANE Existing transformer capacity available in S/s is,

100/22 - 1 x 50 - 49 MVA load

100/22 - 3 x 25 - 46 MVA load

Considering the maximum load reach on the transformer, in event

of interruption/outage on any one of the transformer other

transformer should take care of existing load so as to avoid load

shedding.

3 132 KV BOISAR MIDC S/S

(2008-09)

THANE Existing transformer capacity available in S/s is,

132/33 - 2 x 25 - 36 MVA load

Considering the maximum load reach on the transformer, in event

of interruption/outage on any one of the transformer other

transformer should take care of existing load so as to avoid load

shedding.

Existing transformer capacity available in S/s is,

100/22 - 2 x 20 - 12 load

The transformers are replaced to meet anticipated load growth.

220KV

APTA S/S

(2008-09)

THANE1

2 132 KV DAHANU S/S

(2008-09)

THANE Existing transformer capacity available in S/s is,

132/33 - 2 x 25 - 16 MVA load

The transformers are replaced to meet anticipated load growth.

5 100KV VASHI S/S

(2008-09)

THANE Existing transformer capacity available in substation is 100/22kv,

2x25MVA - 12MVA load . The transformer is replaced to meet

anticipated load growth

100KV

ROHA S/S

(2008-09)

9 RAIGAD Existing transformer capacity available in S/s is,

100/22 - 2 x 25 - 38 load

Considering the maximum load reach on the transformer, in event

of interruption/outage on any one of the transformer other

transformer should take care of existing load so as to avoid load

shedding.

8

Existing transformer capacity available in S/s is,

100/22 - 2 x 25 - 22 load

The transformers are replaced to meet anticipated load growth.

RAIGAD100KV

TAMBATI S/S

(2008-09)

6

100KV

THAL WAISHET S/S

(2008-09)

RAIGAD Existing transformer capacity available in S/s is,

100/22 - 2 x 25 - 26 load

Considering the maximum load reach on the transformer, in event

of interruption/outage on any one of the transformer other

transformer should take care of existing load so as to avoid load

shedding.

84

Page 88: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04/ W.E.F 01/04/2010

SR

NO

NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEME

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

WASHI EHV CONSTRUCTION CUM (O&M) ZONE

TOTAL SCOPE OF WORK

16 220 KV TALOJA S/S

(2009-10)

RAIGAD 1)

2)

1X(200-100)MVA, 220/100KV WITH BAYS 100KV

BAYS - 2NOS

Existing Transformer capacity available is 2 X 100 MVA and load

reached is 83 MVA, Considering the maximum load reach on the

transformer, in event of intruption/outage on any one of the

transformer other transformer should take care of existing load so

as to avoid load shedding.

17 220KV APTA S/S

(2009-10)

RAIGAD 1)

2)

1X(200-125)MVA, 220/100KV WITH BAYS

100KV BAYS - 2NOS

Existing transformer capacity available in S/s is 220/100 kV, 2 x

200 MVA and 2 X 125 MVA the load reached is 235 MVA

Considering the maximum load reach on the transformer, in event

of interruption/outage on any one of the transformer other

transformer should take care of existing load so as to avoid load

shedding.

18 100 kV NOCIL

(2009-10)

Raigad 1)

2)

2x(50-25) MVA 100/22 KV T/F with bay

4 x 22 kV outlets

Existing transformer capacity available in S/s is 2 x 25

And the Load reach is 38 MVA.Considering the maximum load

reached on the transformer in the event of interruptions/outage on

any one of the transformer other transformer should take care of

existing load

19 100 kV AMBERNATH-I

(2009-10)

Thane 1)

2)

1 X ( 50-25)MVA, 100/22 kV T/F with bays.

4 X 22 kV outlets.

Existing transformer capacity available in S/s is 1 x 50,

2 x 25 and the Load reach is 57 MVA. The T/F is replaced to

meet anticipated load growth

20 100 kV MURBAD

(2009-10)

Thane 1)

2)

1 X ( 50-25) 100/22 kV T/F with bays.

4 X 22 kV outlets.

Existing transformer capacity available in S/s is 1 x 50 ,

1 x 25 and the Load reach is 29 MVA. The T/F is replaced to meet

anticipated load growth

21 100 kV VASHI

(2009-10)

Thane 1)

2)

1 X ( 50-25)MVA, 100/22 kV T/F with bays.

4 X 22 kV outlets.

Existing transformer capacity available in S/s is 2 x 50,

1 x 25 and the Load reach is 85 MVA. The T/F is replaced to meet

anticipated load growth

22 100 kV KHOPOLI (2009-

10)

Raigad 1)

2)

1 X ( 50-25)MVA, 100/22 kV T/F with bays.

4 X 22 kV outlets.

Existing transformer capacity available in S/s is 1 x 50 ,

1 x 25 and the Load reach is 41 MVA. The T/F is replaced to meet

anticipated load growth

23 100 kV ROHA

(2009-10)

Raigad 1)

2)

1 X ( 50-25) MVA , 100/22 kV T/F with bays.

4 X 22 kV outlets.

Existing transformer capacity available in S/s is 2 x 25 MVA and

the Load reach is 46 MVA. The T/F is replaced to meet

anticipated load growth

24 100 kV TALOJA-I

(2009-10)

Raigad 1)

2)

1X ( 50-20)MVA, 100/22 kV T/F WITH BAYS

2X22KV OUTLETS

Existing transformer capacity available in S/s is 2 x 20, 1 x 25 and

the Load reach is 46 MVA.Considering the maximum load

reached on the transformer in the event of interruptions/outage on

any one of the transformer other transformer should take care of

existing load

85

Page 89: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04/ W.E.F 01/04/2010

SR

NO

NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEME

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

WASHI EHV CONSTRUCTION CUM (O&M) ZONE

TOTAL SCOPE OF WORK

1) 220KV NALASOPARA - PALGHAR D/C LINE WITH BAYS

- 40 KMS

2) 2 X 50MVA, 220/22KV T/FS WITH BAYS

1) 220 KV D/c LINE FROM BOISER (PG) - 10 KMs

2) 220 KV D/c LINE FROM 220 KV PALGHAR - 20 KMs

3) 2 X 100 MVA 220/132 KV ICT WITH BAYS

4) 2 X 50 MVA 220/33 KV T/F WITH BAYS

5) 132 KV D/C LINE TO BOISER MIDC S/S - 10 KM WITH

BAYS1) LILO OF ONE CIRCUIT OF 220KV D/C APTA -

PEDAMBE LINE - 4KM2) 2X25MVA , 220/22K V TF

3) 33KV OUTLETS - 08 NOS

1) 2 X 50 MVA, 220/22 KV TFS WITH BAYS

2) 220KV PADGHE - KALYAN D/C LINE WITH BAYS - 20

KMS3) 12 X 22KV BAYS FOR FUTURE EXPANSION

1) LILO ON 132 KV BOISAR-I - DAHANU S/C LINE AT

JAWHAR - 75 KM WITH BAYS2) 2 X 25 MVA, 132/33 KV T/FS WITH BAYS

3) 8 NOS OF 33 KV BAYS

BY PGCIL

1 MSETCL SCOPE

400KV PADGHE(PG) - 400KV PADGHE -II (KUDUS)

MSETCL USING D/C QUAD MOOSE CONDUCTOR-

10KM

2) 400KV D/C QUAD LINE FOR NALASOPARA S/STN-

57KM

1) 2X 500 MVA , 400/220KV ICT'S WITH BAYS

1X167 MVA 400/220 KV 1 PHASE ICT SPARE

2) LILO ON 400 KV TARAPUR - PADGHE D/C AT PADGHE

- II (KUDUS) -15 KM

3) INTERCONNECTING D/C LINE BETWEEEN 220 KV D/C

LINE TO 220 KV KUDUS- -5 KMS

4) 220 KV D/C LINE TO 220 KV BHIVANDI IV-

30 KMS5) 220KV LINE FROM KUDUS TO BHIVANDI-III -

30 KM1) LILO ON 400 KV KHARGHAR - KALWA AT NERUL -10

KM

2) LILO ON 400 KV KHARGHAR - PADGHE AT NERUL -10

KM

3) 2 X 500 MVA 400/220 KV ICT'S WITH BAYS

4) 220 KV D/C LINE FROM 400 KV NERUL TO 220 KV

NERUL-5 KM

1) 2X500MVA ,400/220KV ICT

2) SCOPE CONSIDERED IN 765KV PADGHE-II (PG)

S/STN3) 220KV NALASOPARA-VASAI D/C LINE-20KM

4) INTER LINK D/C LINES BETWEEN EXISTING 220KV

NALASOPARA - 400KV NALASOPARA 15KM1) 2X500MVA ,400/220KV ICT

2) LILO ON 400KV PADGHE - NAGOTHANE D/C LINE AT

400KV AMBERNATH- 10KM3) 220KV D/C LINE BETWEEN 400KV AMBERNATH-

220KV AMBERNATH(ANANDNAGAR) -2.5KM4) REORIENTATION OF 220KV LINES - 20KM

1 100KV LINK LINE

(2012-13)

RAIGAD 1) 100 KV MHASALA -KANDALGAON SCDC LINE 37 KM 100kV Mhasala S/S is fed from 100kV Kandalgaon S/s with S/c

line. Hence to provide uninterrupted supply during planned

outages it is necessary to add proposed line

2 100kV LINK LINE

(2012-13)

THANE 1) 100KV IOL - STANDARD D/C LINE USING U.G CABLE -

5KM

Single source to be made double.

1 220 KV LINK LINE

(2010-11)

THANE 1) 220KV AMBERNATH -II - PADGHE D/C LINE WITH BAYS-

20 KMS

Since the existing 220kV Ambernath-Padghe S/c line is critically

loaded to an extent of 199 MW. Hence it is suggested to add

proposed line to reduce the loading of existing line and to meet

additional load growth and contingency.

2 220 KV LINK LINE

(2010-11)

THANE 1) 220KV AMBERNATH - II - DOMBIVLI-II SCDC LINE

WITH BAYS- 15 KMS

Since the existing 220kV Dombivali-Ambernath S/c line is loaded

to an extent of 147 MW during Non-Coinsident peak condition and

Ambernath is an industrial zone hence it is necessary to propose

additional line to meet additional load growth and contingency.

400 KV Nerul S/s is Considered for upcomming load near by

Nerul and to feed the area at proper voltage.

ADDITIONAL LINK LINES TO MEET DEMAND WITHOUT LOAD SHEDDING AND TO ENSURE RELIABILITY AND QUALITY OF SUPPLY

9

THANE 400 KV Ambernath S/s is considered for existing and upcomming

load near by area.

400 KV Nalasopara S/s is Considered for upcomming load near

by area.

400KV NALASOPARA S/S

(2013-14)

400KV AMBERNATH S/S

(2014-15)

10

To improve the voltage profile of the area and to meet the

upcomming load.

ADDITIONAL LINK LINES

ADDITIONAL LINK LINES FOR S/S WHERE ONLY SINGLE CKT AND SINGLE SOURCE IS AVAILABLE

THANE

To overcome low voltage & to feed the upcomming load.

Voltage improvement & load catering.THANE

Evacuation of Central Sector Power.

Voltage improvement & load catering.

7 400KV PADGHE - II

(KUDUS) S/S

(2012 -13)

THANE

132 KV JAWHAR S/S (2011-

12)

Palghar 220kV S/S is considered to cater increasing loads in the

area.

220 KV BOISAR MIDC

(2010-11)

4

5

2

It is necessary to go in for new 220kV sub-station at kalyan to

FEED THE UPCOMMING LOAD

220 KV

KALYAN S/S

(2011-12)

3 220KV VILE-BAGAD (2010-

11)

RAIGAD

8

NEW SCHEMES

220 KV PALGHAR S/S

(2010-11)

1

THANE

400 KV NERUL

(2013-14)

THANE

THANE

THANE

765KV

PADGHE-II S/S (PG)

(2012-13)

6 THANE

86

Page 90: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04/ W.E.F 01/04/2010

SR

NO

NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEME

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

WASHI EHV CONSTRUCTION CUM (O&M) ZONE

TOTAL SCOPE OF WORK

1) COVERSION OF EXISTING D/C TOWER IN TO M/C

NARROW BASE TOWER USING EXISTING CORRIDOR

FROM 220KV KHARGHAR-KALWA-BORIVALI-BOISAR.

2) REPLACEMENT OF 0.4 ACSR CONDUCTOR, WITH AAAC

TWIN CONDUCTOR

a) 220KV LILO PT OF TARAPUR - BORIVALI- 95KM

b) 220 KV LILO PT OF MULUND- BORIVALI - 15KM

c)220 KV KALWA -LILO PT OF MULUND -6.2KM

d) 220KV KALWA - LILO PT OF MAHAPE - 8.1KM

e) 220 KV LILO PT OF MAHAPE- LILO PT OF TIFFIL- 1.6KM

f) 220KV LILO PT OF TIFFIL - LILO PT OF TROMBAY - 31KM

g) 220KV LILO PT OF NERUL - KHARGHAR -9.7KM

3) REPLACEMENT OF 0.4 ACSR CONDUCTOR, WITH AAAC

TWIN CONDUCTOR OF 220KV KHARGHAR - KALWA -

BORIVALI - BOISAR S/C ON M/C.

4) STRINGING OF D/C ON M/C FROM 220KV KHARGHAR -

BORIVALI-BOISAR WITH AAAC TWIN CONDUCTOR

BYPASSING KALWA SWITCHYARD WITH 220KV CABLES.-

125KM

5) *LILO OF EXISTING S/C BOISER (MSETCL) - BORIVALI

(MSETCL) AT 220KV GHODBUNDER (R-INFRA). (*THIS

WORK WILL BE DONE BY M/S R-INFRA) - 10KM

4 220KV LINK LINE

(2010-11)

THANE 1 200KV PEDAMBE- TAMBATI (APTA) LINE AT MAHAD -

160KM

Strengthining of existing network.

5 132KV LINK LINES

(2010-11)

THANE 1 2ND CIRCUIT STRINGING OF 132KV LINE FROM 220KV

BOISER-132KV BOISAR MIDC- 8.5KM

Since the existing 132kV Boisar - Boisar MIDC S/C line is loaded

to an extent of 67MW during Non-Coinsident peak condition. It is

anticipated the load will reach to about critical value in future.

Hence it is necessary to propose additional line to meet additional

load growth and contingency.

6 220 KV LINK LINE

(2011-12)

THANE 1) 220 KV APTA - IPCL SCDC LINE - 55 KM Since the existing 220kV Wadkhal-IPCL S/c line is getting loaded

to an extent of 151 MW. It is anticipated the load will reach to

critical value by the year 2011-12. Hence it is suggested to add

proposed line to meet additional load growth and contingency.

7 100kV LINK LINE

(2011-12)

THANE 1) 100kV MURBAD - SHAHAPUR DC LINE WITH BAYS-30

KMS

Strengthining of existing network.

8 220KV LINK LINE (2011-

12)

THANE 1) 220KV APTA - WADKHAL D/C -25KM Strengthining of existing network.

9 220KV LINK LINE (2011-

12)

THANE 1) 220KV COLOURCHEM - KOLSHET D/C -8KM Strengthining of existing network.

10 132KV LINK LINES

(2011-12)

THANE 1) 132KV DAHANU - PALGHAR D/C LINE WITH BAYS - 30

KMS

Strengthining of existing network.

11 100kV LINK LINE

(2011-12)

THANE 1) 100KV BHIVANDI - PADGHE D/C -25KM USING HIGH

AMPICITY CONDUCTOR

Strengthining of existing network.

12 100kV LINK LINE

(2011-12)

THANE 1) CONVERSION OF TEMGHAR TAP OF 100KV BHIVANDI -

PADGHE LINE USING HIGH AMPICITY CONDUCTOR

(BETWEEN LOC NO. 1 - 53) .

Strengthining of existing network.

13 132KV LINK LINES

(2011-12)

THANE 1) 132KV BOISAR-I - BOISAR-II - 7 KM USING HIGH

AMPICITY CONDUCTOR

Strengthining of existing network.

14 220 KV LINK LINE

(2013-14)

THANE 1) 220KV TALOJA - 400KV PANVEL (PG) D/C LINE - 28 KM Line is required considering increasing load growth in nearby area

1 220 KV LINK LINE

(2011-12)

RAIGAD 1) 220KV KHARGHAR - NEW MUMBAI SCDC LINE WITH

BAYS- 50 KMS

Linking to New 400 kV New

Mumbai S/s

1 400 KV LINK LINE

(2011-12)

AHMEDNAGA

R/ THANE

1) 400KV D/C LINE FROM 400KV BABLESWAR - PADGHE -

II(KUDUS) -153KM

Strengthening for wind power evacuation at Nasik and

Doindaicha

1 400 kV PADGHE

( 2010 - 11 )

THANE 1)

2)

Add 1x500 MVA 400/220 KV ICT bays

3 x 220 kV Line bays

Existing transformer capacity available in S/s is 3 x 315 MVA

And the Load reach is 875 MVA.Considering the maximum load

reached on the ICTs in the event of interruptions/outage on any

one of the transformer other ICTs' should take care of existing

load

2 220 kV KOLSHET

(2010-11)

Thane 1)

2)

Add 1x50 MVA 220/22 KV T/F with GIS bays

4 x 22 kV outlets

Existing transformer capacity available in S/s is 2 x 25

And the Load reach is 63 MVA.Considering the maximum load

reached on the transformer in the event of interruptions/outage on

any one of the transformer other transformer should take care of

existing load

2 220 kV KALWA

(2010-11)

Thane 1)

2)

Add 1x50 MVA 220/22 KV T/F with bay

6 x 22 kV outlets

Existing transformer capacity available in S/s is 2 x 50

And the Load reach is 81 MVA.Considering the maximum load

reached on the transformer in the event of interruptions/outage on

any one of the transformer other transformer should take care of

existing load

3 220 kV TEMGHAR

(2010-11)

Thane 1)

2)

Add 1x50 MVA 220/22 KV T/F with bay

6 x 22 kV outlets

Existing transformer capacity available in S/s is 2 x 50

And the Load reach is 78 MVA.Considering the maximum load

reached on the transformer in the event of interruptions/outage on

any one of the transformer other transformer should take care of

existing load

4 220 kV MAHAPE

(2010-11)

Thane 1)

2)

Add 1x50 MVA 220/22 KV T/F with bay

6 x 22 kV outlets

Existing transformer capacity available in S/s is 2 x 50

And the Load reach is 82 MVA.Considering the maximum load

reached on the transformer in the event of interruptions/outage on

any one of the transformer other transformer should take care of

existing load

3 220 KV LINK LINE (2010-11,

JULY 2010)

THANE

ADDITIONAL LINK LINES FOR NEW S/S TO HAVE ALTERNATE SOURCE

STRENGTHENING FOR EVACUATION ARRANGEMENT

AUGMENTATION OF S/S BY ADDITION TO REDUCE LOADING OF ICT / TF

AUGMENTATION OF S/S BY ADDITION OF ICT / TF

Existing Kharghar-Kalwa S/C line is of 1971. Existing Boiser

(MSETCL)- Borivali (MSETCL) S/C line is of 1973. For

srengthening of network and upcoming future demand of mumbai

area this work is proposed.

87

Page 91: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04/ W.E.F 01/04/2010

SR

NO

NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEME

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

WASHI EHV CONSTRUCTION CUM (O&M) ZONE

TOTAL SCOPE OF WORK

5 220 kV NERUL

(2010-11)

Thane 1)

2)

Add 1x50 MVA 220/33-22 KV T/F with bay

6 x 22 kV outlets

Existing transformer capacity available in S/s is 2 x 50

And the Load reach is 75 MVA.Considering the maximum load

reached on the transformer in the event of interruptions/outage on

any one of the transformer other transformer should take care of

existing load

6 220 kV WADA

(2010-11)

Raigad 1)

2)

Add 1x50 MVA 220/22 KV T/F with GIS bay

6 x 22 kV outlets

Existing transformer capacity available in S/s is 3 x 50

And the Load reach is 99 MVA.Considering the maximum load

reached on the transformer in the event of interruptions/outage on

any one of the transformer other transformer should take care of

existing load

7 220 kV VASAI

(2010-11)

Raigad 1)

2)

Add 2x50 MVA 220/22 KV T/F with bay

8 x 22 kV outlets

To reduce the loading on 100 kV VASAI

8 100 kV MOHNE

(2010-11)

Thane 1)

2)

Add 1x50 MVA 220/22 KV T/F with 22KV GIS bay

6 x 22 kV outlets

Existing transformer capacity available in S/s is 2 x 50

And the Load reach is 56 MVA.Considering the maximum load

reached on the transformer in the event of interruptions/outage on

any one of the transformer other transformer should take care of

existing load

9 100 kV APTA

(2010-11)

Raigad 1)

2)

Add 1x25 MVA 100/22 KV T/F with bay

4 x 22 kV outlets

Existing transformer capacity available in S/s is 2 x 20

And the Load reach is 15 MVA.Considering the maximum load

reached on the transformer in the event of interruptions/outage on

any one of the transformer other transformer should take care of

existing load

10 400KV KHARGHAR S/S

(2011-12)

THANE 1) 1 X 500 MVA, 400/220KV ICT WITH BAYS Existing transformer capacity available in S/s is,400/220 kV , 2 x

315 MVA and the load reached is 386 MVA

Considering the maximum load reach on the transformer, in event

of interruption/outage on any one of the transformer other

transformer should take care of existing load so as to avoid load

shedding.

11 220 kV KOLSHET

(2011-12)

Thane 1)

2)

Add 1x50 MVA 220/22 KV T/F with GIS bay

6 x 22 kV outlets

Existing transformer capacity available in S/s is 2 x 50

And the Load reach is 63 MVA.Considering the maximum load

reached on the transformer in the event of interruptions/outage on

any one of the transformer other transformer should take care of

existing load

12 100 kV JITE

(2012-13)

Raigad 1)

2)

Add 1 X 25 MVA 100/22 KV T/F with bay

4 x 22 kV outlets

Existing transformer capacity available in S/s is 1 x 25 MVA and

the Load reach is 8 MVA.To avoid the loss of supply in case of

outages or interruptions of transformers.

13 220 kV MAHAD

(2013-14)

Raigad 1)

2)

Add 1x50 MVA 220/22 KV T/F with bay

6 x 22 kV outlets

Existing transformer capacity available in S/s is 3 x 50

And the Load will reach 102 MVAin year 2013-14. Considering

the maximum load reached on the transformer in the event of

interruptions/outage on any one of the transformer other

transformer should take care of existing load

14 220KV KAMBA

( 2013-14)

THANE 1) Add 1x 50 MVA ,220/22kV with GIS Bays. For redundancy.

15 100 kV SHAHAPUR

(2013-14)

Thane 1)

2)

Add 1x25 MVA 100/22 KV T/F with bay

4 x 22 kV outlets

Existing transformer capacity available in S/s is 2 x 25

And the Load reach is 32 MVA.Considering the maximum load

reached on the transformer in the event of interruptions/outage on

any one of the transformer other transformer should take care of

existing load

1 220 kV BOISAR-II

(2010-11)

Thane 1)

2)

1 X(100- 50) MVA ,220/33-22 kV T/F with bays.

6 X 33/22 kV out lets.

Existing transformer capacity available in S/s is 2 X 50 MVA and

load is 40. MVA. Considering the maximum load reached on the

transformer in the event of interruptions/outage on any one of the

transformer other transformer should take care of existing load

2 220KV KALWA S/S

(2010-11)

THANE 1)

2)

1x(200-125)MVA, 220/100KV ICT'S WITH BAYS

100 KV BAYS - 02 NOS

Existing transformer capacity available in S/s will be ,220/100kV,

3 x 125MVA and 1 X 200 MVA and load will reach 440MVA

considering the maximum load reach on the transformer, in event

of intruption/outage on any one of the transformer other

transformer should take care of existing load so as to avoid load

shedding.

3 220KV TROMBAY S/S

(2010-11)

MUMBAI 1)

2)

1x(200-125)MVA, 220/100KV ICT'S WITH BAYS

100 KV BAYS - 02 NOS

Existing transformer capacity available in S/s will be 220/100kV,

1 x 125MVAand1X 200 MVA and the load will

reach198MVA,Considering the maximum load reach on the

transformer, in event of interruption/outage on any one of the

transformer other transformer should take care of existing load so

as to avoid load shedding.

4 220KV BORIVLI S/S

(2010-11)

MUMBAI 1)

2)

1x(200-125)MVA, 220/100KV ICT'S WITH BAYS

100 KV BAYS - 02 NOS

Existing transformer capacity available in S/s is 220/100kV 2 x

125MVAand the load reached is 223MVA,Considering the

maximum load reach on the transformer, in event of

interruption/outage on any one of the transformer other

transformer should take care of existing load so as to avoid load

shedding.

5 220KV BOISAR II S/S

(2010-11)

THANE 1)

2)

1x(200-150)MVA, 220/100KV ICT'S WITH BAYS

100 KV BAYS - 02 NOS

Existing transformer capacity available in S/s is 220/132kV 2 x

150MVAand the load reached is 207MVA,Considering the

maximum load reach on the transformer, in event of

interruption/outage on any one of the transformer other

transformer should take care of existing load so as to avoid load

shedding.

6 220 KV TALOJA S/S

(2010-11)

RAIGAD 1)

2)

1x(200-100)MVA, 220/100KV ICT'S WITH BAYS

100 KV BAYS - 02 NOS

Existing Transformer capacity available is 2 X 100 MVA and load

reached is 83 MVA, Considering the maximum load reach on the

transformer, in event of intruption/outage on any one of the

transformer other transformer should take care of existing load so

as to avoid load shedding.

AUGMENTATION OF S/S BY REPLACEMENT OF ICT

88

Page 92: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04/ W.E.F 01/04/2010

SR

NO

NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEME

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

WASHI EHV CONSTRUCTION CUM (O&M) ZONE

TOTAL SCOPE OF WORK

7 220 kV WADKHAL

(2010-11)

Raigad 1)

2)

1x(50-20) MVA 220/22 KV T/F with bay

4 x 22 kV outlets

Existing transformer capacity available in S/s is 1 x 20 , 1 x 50

and the Load reach is 25 MVA.Considering the maximum load

reached on the transformer in the event of interruptions/outage on

any one of the transformer other transformer should take care of

existing load

8 220 kV COLOURCHEM

(2010-11)

Thane 1)

2)

1x(100-50) MVA 220/22-22 KV T/F with bay

6 x 22 kV outlets

Existing transformer capacity available in S/s is 4 x 50

And the Load reach is 130 MVA.Considering the maximum load

reached on the transformer in the event of interruptions/outage on

any one of the transformer other transformer should take care of

existing load

9 220 kV MULUND

(2010-11)

Mumbai 1)

2)

1x(100-50) MVA 220/22-22 KV T/F with bay

6 x 22 kV outlets

Existing transformer capacity available in S/s is 4 x 50

And the Load reach is 169 MVA.Considering the maximum load

reached on the transformer in the event of interruptions/outage on

any one of the transformer other transformer should take care of

existing load

10 100 kV THAL

(2010-11)

Raigad 1)

2)

2x(50-25) MVA 100/22 KV T/F with bay

4 x 22 kV outlets

Existing transformer capacity available in S/s is 2 x 25

And the Load reach is 27 MVA.Considering the maximum load

reached on the transformer in the event of interruptions/outage on

any one of the transformer other transformer should take care of

existing load

11 220KV KAMBA

( 2010-11)

THANE 1)

2)

1x(100- 50) MVA ,220/22-22kV with GIS Bays.

4 x 22 kV outlets

For redundancy.

12 132 kV PALGHAR

(2010-11)

Thane 1)

2)

1 X (50-25) MVA,132/33 kV T/F with bays.

4 X 33 kV outlets.

Existing transformer capacity available in S/s is 2 X 25 MVA and

load is 44 MVA. The transformer is replaced to meet anticipated

load growth.

13 100 kV TALOJA-I

(2010-11)

Raigad 1)

2)

1 X ( 50-20) 100/22 kV T/F with bays.

4 X 22 kV outlets.

Existing transformer capacity available in S/s is 2 x 20 ,

1 x 25 and the Load reach is 46 MVA. The T/F is replaced to meet

anticipated load growth

14 100 kV MHSALA

(2010-11)

Raigad 1)

2)

1 X ( 50-12.5) 100/22 kV T/F with bays.

4 X 22 kV outlets.

Existing transformer capacity available in S/s is 2 x 12.5

and the Load reach is 19 MVA. The T/F is replaced to meet

anticipated load growth

15 220 kV URAN

(2010-11)

Raigad 1)

2)

1 X ( 50-25) 220/22 kV T/F with bays.

4 X 22 kV outlets.

Existing transformer capacity available in S/s is 2 x 25

and the Load reach is 41 MVA. The T/F is replaced to meet

anticipated load growth

16 220 kV NALASOPARA

(2010-11)

Thane 1)

2)

1x(100-50) MVA 220/22-22 KV T/F with GIS bay

6 x 22 kV outlets

Existing transformer capacity available in S/s is 3 x 50

And the Load reach is 63 MVA.Considering the maximum load

reached on the transformer in the event of interruptions/outage on

any one of the transformer other transformer should take care of

existing load

17 220 kV MULUND

(2011-12)

Mumbai 1)

2)

1x(100-50) MVA 220/22-22 KV T/F with bay

6 x 22 kV outlets

Existing transformer capacity available in S/s is 4 x 50

And the Load reach is 169 MVA.Considering the maximum load

reached on the transformer in the event of interruptions/outage on

any one of the transformer other transformer should take care of

existing load

18 400 KV NAGOTHANE S/S

(2011-12)

RAIGAD 1)

2)

1 X (500-315)MVA, 400/220KV ICT WITH BAYS

220KV BAYS - 02 NOS

Existing Transformer capacity available is 2 X 315 MVA and load

reached is 487 MVA, Considering the maximum load reach on the

transformer, in event of intruption/outage on any one of the

transformer other transformer should take care of existing load so

as to avoid load shedding.

19 220 kV COLOURCHEM

(2011-12)

Thane 1)

2)

1x(100-50) MVA 220/22-22 KV T/F with bay

6 x 22 kV outlets

Existing transformer capacity available in S/s is 4 x 50

And the Load reach is 130 MVA.Considering the maximum load

reached on the transformer in the event of interruptions/outage on

any one of the transformer other transformer should take care of

existing load

20 220 kV BOISAR-II

(2011-12)

Thane 1)

2)

1 X(100- 50) MVA ,220/22-22 kV T/F with bays.

6 X 33 kV out lets.

Existing transformer capacity available in S/s is 2 X 50 MVA and

load is 40. MVA. Considering the maximum load reached on the

transformer in the event of interruptions/outage on any one of the

transformer other transformer should take care of existing load

21 220KV KAMBA

( 2011-12)

THANE 1)

2)

1x(100- 50) MVA ,220/22-22kV with GIS Bays.

4 x 22 kV outlets

For redundancy.

22 132 kV BOISAR MIDC

(2011-12)

Thane 1)

2)

1 X (50-25) MVA , 132/33 kV T/F with bays.

4 X 33 kV outlets.

Existing transformer capacity available in s/s is 2 X 25 MVA. And

the load reached is 40 MVA The transformer is replaced to meet

anticipated load growth.. 23 100 kV TALOJA-I

(2011-12)

Raigad 1)

2)

1 X ( 50-25) 100/22 kV T/F with bays.

4 X 22 kV outlets.

Existing transformer capacity available in S/s is 2 x 20 ,

1 x 25 and the Load reach is 46 MVA. The T/F is replaced to meet

anticipated load growth

24 100 kV MHSALA

(2011-12)

Raigad 1)

2)

1 X ( 50-12.5) 100/22 kV T/F with bays.

4 X 22 kV outlets.

Existing transformer capacity available in S/s is 2 x 12.5

and the Load reach is 19 MVA. The T/F is replaced to meet

anticipated load growth

25 220 kV NALASOPARA

(2011-12)

Thane 1)

2)

1x(100-50) MVA 220/22-22 KV T/F with GIS bay

6 x 22 kV outlets

Existing transformer capacity available in S/s is 3 x 50

And the Load reach is 63 MVA.Considering the maximum load

reached on the transformer in the event of interruptions/outage on

any one of the transformer other transformer should take care of

89

Page 93: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04/ W.E.F 01/04/2010

SR

NO

NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEME

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

WASHI EHV CONSTRUCTION CUM (O&M) ZONE

TOTAL SCOPE OF WORK

26 100 kV PATALGANGA

(2012-13)

Raigad 1)

2)

1 X ( 50-25) 100/22 kV T/F with bays.

4 X 22 kV outlets.

Existing transformer capacity available in S/s is 2 x 25

and the Load reach is 32 MVA. The T/F is replaced to meet

anticipated load growth

27 220 kV TAMBATI-II

(2012-13)

Raigad 1)

2)

1 X ( 50-25) 220/22 kV T/F with bays.

4 X 22 kV outlets.

Existing transformer capacity available in S/s is 2 x 25

and the Load reach is 32 MVA. The T/F is replaced to meet

anticipated load growth

28 100 kV NOCIL

(2012-13)

Raigad 1)

2)

1 X ( 50-25) 100/22 kV T/F with bays.

4 X 22 kV outlets.

Existing transformer capacity available in S/s is 2 x 25

and the Load reach is 38 MVA. The T/F is replaced to meet

anticipated load growth

29 132 kV DAHANU

(2012-13)

Thane 1)

2)

1 X (50-25) MVA , 132/33 kV T/F with bays.

4 X 33 kV outlets.

Existing transformer capacity available in s/s is 1 X 25 MVA, 1 X

50 MVA. And the load reached is 33 MVA The transformer is

replaced to meet anticipated load growth..

30 100 kV PATALGANGA

(2013-14)

Raigad 1)

2)

1 X ( 50-25) 100/22 kV T/F with bays.

4 X 22 kV outlets.

Existing transformer capacity available in S/s is 2 x 25

and the Load reach is 32 MVA. The T/F is replaced to meet

anticipated load growth

31 220 kV TAMBATI-II

(20013-14)

Raigad 1)

2)

1 X ( 50-25) 220/22 kV T/F with bays.

4 X 22 kV outlets.

Existing transformer capacity available in S/s is 2 x 25

and the Load reach is 32 MVA. The T/F is replaced to meet

anticipated load growth

32 220 kV URAN

(2013-14)

Raigad 1)

2)

1 X ( 50-25) 220/22 kV T/F with bays.

4 X 22 kV outlets.

Existing transformer capacity available in S/s is 2 x 25

and the Load reach is 41 MVA. The T/F is replaced to meet

anticipated load growth

* COMMISSIONED IN 2009-10 ** 1No. TF COMMISSIONED IN 2009-10

90

Page 94: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

EHV CC O&M ZONE : PUNE

91

Page 95: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 - W.E.F 01/04/2010

SR

NO.

NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEME

1) 2 X 315 MVA, 400/220KV ICT WITH BAYS & 1 X 105MVA

SPARE ICT

2) 400KV CHAKAN - PUNE (PG) S/C LINE - 20 KM

3) LILO OF 400 KV LONIKAND-PADGHA AT CHAKAN S/S -

15 KM

4) 220KV CHAKAN - TALEGAON (PG) D/C - 20KMS

5) 220KV LILO ON EXISTING BHOSARI-CHINCHWAD S/C

LINE - 15 KMS

6) 3 X 50 MVA, 220/22KV T/F

7) 22 KV OUTLETS - 18 NOS.

1) LILO OF 220 KV CHINCHWAD-THEUR S/C- 12 CKTS

WITH BAYS

2) 2X50 MVA, 220/22KV T/FS WITH BAYS

3) 12X22KV OUTLETS

1) 2 X 50 MVA, 220/22 KV T/FS WITH BAYS

2) 400KV PGCIL PUNE -TALEGAON S/S - 40 KM D/C LINE

WITH BAYS

3) 220 KV URSE-TALEGAON D/C LINE.

4) 12 X 22 KV OUTLETS

1) 2 X 50 MVA, 220/33KV T/FS WITH BAYS

2) 33KV OUTLETS - 12 NOS.

3) 220KV D/C LINE FROM LONIKAND-KHARDI 5 KMS WITH

BAYS

1) 2 X 50 MVA, 220/33KV T/FS WITH BAYS

2) 2 X 100MVA, 220/132KV ICT WITH BAYS

3) 220 KV LINE FROM CHAKAN - RAJGURUNAGAR D/C -

15 KMS

4) LILO ON 220KV LONIKAND - PARGAON S/C AT

RAJGURUNAGAR 10 KMS WITH BAYS

5) LILO ON 132 KV CHINCHWAD-NARAYANGAON-10 KM

WITH BAYS

6) 33KV OUTLETS - 8 NOS

1) 132/33KV, 2 X 25MVA T/FS WITH BAYS

2) 8 X 33KV OUTLETS.

3) 132KV LINE BAYS -02 NOS

1) LILO ON 132 KV PHURSUNGI - RAHATANE- 10 KM

2) 2 X 50 MVA, 132/22 KV T/FS WITH BAYS

3) 22 KV OUTLET - 12 NOS,

1) 2 X 50MVA, 132/22KV T/FS WITH BAYS

2) 2 X 25MVA, 132/11KV T/FS WITH BAYS

3) 12 X 22KV OUTLETS, BUS SECTIONALISER &

INCOMMERS

4) 12 X 11KV OUTLETS, BUS SECTIONALISER &

INCOMMERS

5) SCADA SYSTEM FOR 132 KV

6) 132KV U.G CABLE XLPE SINGLE CORE 4 CABLE FROM

PARVATI - RASTAPETH - 8KM.

9 RENOVATION OF 100KV

GANESHKHIND -

KHOPOLI D/C

PUNE 1) RENOVATION OF 100KV LINE GANESHKHIND -

KHOPOLI - 70 CKM.

STRENTHENING THE SUPPLY NETWORK

1) ERECTION 2 X 25 MVA, 132/22KV T/FS WITH BAYS

2) 3 X 25 MVA, 132/11 KV T/FS WITH BAYS

3) REPLACEMENT OF 22KV EQUIPMENT

4) DISMENTALLING OF 110/33KV/110/11KV T/F AT BARSHI,

SANGOLA, PULUJ, DIGANCHI, DEGAON11 400KV PUNE (PG)

(2009-10)

PUNE

1)

SCOPE OF WORK BY MSETCL

LILO ON 220KV HINJEWADI - CHINCHWAD S/C TO

PUNE (PG) - 25 KMS WITH BAYS

Pune-PGCIL is constructed by PGCIL and will facilitate

additional infeed to pune circle

1)

SCOPE OF WORK BY MSETCL

400KV D/C LINE FROM SOUTH SOLAPUR(PG)-

SOLAPUR (MSETCL)-20KM

2) 220 KV DC LINE FROM 400/220KV SOUTH SOLAPUR

(PG) - SOUTH SOLAPUR (MSETCL) S/S - 5 KM WITH

BAYS

3) 220KV DC LINE FROM 400KV SOUTH SOLAPUR -

PANDHARPUR - 60KM

3 220KV TALEGAON

(2008-09)

PUNE

132 KV BIBWEWADI S/S

(2008-09)

400 KV SOUTH

SOLAPUR S/S(PGCIL)

(2009-10)

12 SOLAPUR Evacuation of Power from PG.

Talegaon 220kV S/S is considered for meeting the existing

loads in Pune circle. Talegaon-220kV S/S is feed from

Urase by constructing 220kV M/C line of 7kM.

6

Rastapeth 132kV S/S is considered for reducing loading on

Parvathi S/S and for strengthening in Pune circle.

Rastapeth-132kV S/S is fed from Parvati 220/132 kV S/S

by constructing 132kV S/C line of 8kM

132KV

RASTAPETH G.I.S S/S

(2008-09)

PUNE

PUNE

220KV KHADAKWASLA

S/S (NANDED CITY)

(2008-09)

8

2

PUNE

4

SPILL OVER SCHEMES

7 Bibwewadi132kV S/S is considered for reducing the loading

on Phursangi & Khothrod and also to improve the voltage

profile in Pune Circle. This new Substation is proposed on

LILO of existing Phursangi–Khothrod 132kV line.

1 * 400KV CHAKAN S/S

(2008-09)

PUNE The existing 400/220kV station at Lonikand is overloaded

leading low voltage profile in pune circle. By the

commissioning of this substation, voltage profile of Pune

ring main Circle will improve to 0.93pu. Chakan-400kV is

connected from Lonikand by onstructing 400kV D/C line of

28kM length.

VOLTAGE IMPROVEMENT & LOAD CATERING

VOLTAGE IMPROVEMENT & LOAD CATERING

132KV

NAVI - VES S/S

(2008-09)

220KV GIS-KHARDI

(2008-09)

PUNE Present recorded peak load on Khardi-132 V is 70MW. It is

anticipated by the year 2009-10 the load will reach to about

90MW. Hence it is necessary to go in for 220kV sub-station

at Khardi. Khardi-220kV S/S is fed from Lonikand-

400/220kV S/S by constructing 220kV D/C line of 25kM

length.

5

SOLAPUR

UPGRADATION OF

100KV GANESHKHIND

S/S TO 132KV

220KV RAJGURUNAGAR

(2008-09)

PUNE

10 PUNE STRENTHENING THE SUPPLY NETWORK

VOLTAGE IMPROVEMENT & LOAD CATERING

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

PUNE EHV CONSTRUCTION CUM (O&M) ZONE

TOTAL SCOPE OF WORK

92

Page 96: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 - W.E.F 01/04/2010

SR

NO.

NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEME

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

PUNE EHV CONSTRUCTION CUM (O&M) ZONE

TOTAL SCOPE OF WORK

1) 2 X 500 MVA, 400/220 KV ICT WITH BAYS

1 X 167 MVA, 400/220 KV SPARE ICT WITH BAYS

2) LILO OF 400 KV PARLI (PG)-PUNE (PG) D/C AT

LONIKAND-II S/S-30 KM

3) 220 KV LONIKAND-II-THEUR D/C LINE WITH BAYS- 18

KM

4) 220 KV LONIKAND-II-CHAKAN D/C LINE WITH BAYS- 28

KM5) 220 KV LONIKAND-II-RAJGURUNAGAR D/C LINE WITH

BAYS- 40 KM6) 220 KV DC LINE FROM 400KV LONIKAND-II - 220KV

VSNL DIGHI WITH BAYS- 25 KM ( OH LINE 16.9KM &UG

CABLE 8.1KM ) (2010 -2011)1) 2 X 100 MVA, 220/132 KV ICT'S WITH BAYS

2) 2 X 25 MVA, 220/33 KV T/FS WITH BAYS

3) LILO OF 132 KV SOLAPUR - AKKALKOT AT SOUTH

SOLAPUR S/S - 5 KM

4) 220KV DC LINE FROM 220KV SOUTH SOLAPUR - BALE -

10KM

5) 33KV OUTLETS - 8 NOS

1) 3 X 50MVA, 220/22KV T/FS WITH BAYS

2) LILO ON 220KV BHOSARI (AKURDI) -TELCO S/C LINE

1.6 KMS WITH BAYS

3) 33KV OUTLETS - 8 NOS

1) 2 X 25 MVA, 132/33 KV T/FS WITH BAYS

2) LILO ON 132KV LONAND -PHALTAN LINE 7KM FROM

LOCATION NO. 29

3) 8 X 33 KV OUTLETS

1) 2 X 50MVA, 220/22KV T/FS WITH BAYS

2) 12 X 22KV OUTLETS

3) 220 KV D/C ON D/C FROM 220 KV PARGAON TO 220 KV

CHAKAN -20KMS

4) 220 KV M/C ON M/C FROM 220 KV CHAKAN- 132 KV

NARAYANGAON -20 KMS

5) 220 KV D/C ON D/C FROM 220 KV NARAYANGAON

SUBSTATION TO 220 KV ALEPHATA S/S -19 KMS

6) 220 KV M/C ON M/C FROM 220 KV CHAKAN- 220 KV

CHINCHWAD -35 KMS

7) 220 KV M/C ON M/C LILO ON 220 KV CHAKAN- 220 KV

CHINCHWAD -5 KMS

8) 220 KV LINE BAYS - 8 NOS

9) 132 KV LINE BAYS-7 NOS

10) 220 KV XLPE CABLE- 1.62 KM

11) 132 KV XLPE CABLE-0.9 KM

1) 2 X 25MVA, 132/33KV T/FS WITH BAYS

2) 132KV SCDC LINE FROM AKKALKOT-KARAJGI - 20 KM

WITH BAYS

3) 33KV OUTLETS - 8 NOS

1) 2 X 25MVA, 132/33KV T/FS WITH BAYS

2) 132KV AKKALKOT-WAGDARI (GOGAON) - S/C LINE ON

D/C TOWER - 25 KM WITH BAY

3) 132KV NALDURG-WAGDARI (GOGAON) S/C D/C - 25 KM

WITH BAY

4) 33KV OUTLETS - 8 NOS

1) 2 X 25MVA, 132/33KV T/FS WITH BAYS

2) LILO ON 132KV MANDRUP - DEGAON S/STN - 5 KM

WITH BAYS

3) 33KV OUTLETS - 8 NOS

1) 132 KV D/D LINE FROM 220 KV MALINAGAR S/S 6 KMS

WITH BAYS

2) 2 X 25 132/33 KVT/F

3) 33 KV OUTLETS 8 NOS.

1) 2X25MVA, 132/33KV T/F

2) 132KV D/C LINE FROM 220KV KURKUMBH S/STN-15KM

3) 33KV OUTLETS - 8 NOS

1) 2X25MVA, 132/33KV T/F

2) 132KV D/C LINE FROM AKKALKOT -22KM

3) 33KV OUTLETS - 8 NOS

132KV BORIVEL

(2009-10)

132KV RUDDEWADI

(2009-10)

22

23

The loads around Chinchwad-is 80MW. It is anticipated by

the year 2009-10 that the load will reach to about 96MW.

Hence it is necessary to go in for new 220kV sub-station at

Akurdi.

15

21

18 132 KV KARAJGI S/S

(2009-10)

132 KV WAGDARI S/S

(GOGAON)

(2009-10)

132 KV SHANKARNAGAR

(2009-10)

19

It is anticipated by the year 2009-10 that the load will reach

to its extent near baramati region . To avoid interruptions

due to over loading Someshwar nagar-132kV S/S is

considered.

SOLAPUR

SOLAPUR

16 132 KV SOMESHWAR

NAGAR S/S

(2009-10)

400 KV LONIKAND-II S/S

(2009-10)

14

220KV AKURDI

(2009-10)

Soregaon-132kV S/S is considered to meet the load growth

in Solapur ring main.

PUNE

PUNE

PUNE

South Solapur-220kV S/S is considered for evacuating

power from the proposed 400/22kV sub-station of South

solhapur by PGCIL. By the commissioning of this

substation, voltage profile will improve to 1.0pu from

0.93pu.

To improve the voltage profile of the area and to cater the

upcomming load.

220 KV SOUTH

SOLAPUR (MSETCL) S/S

(2009-10)

13

SOLAPUR Present recorded peak load on Akkakalkot-132kV is 40MW.

It is anticipated by the year 2009-10 that the load will reach

to about 50MW. Hence it is necessary to go in for new

132kV sub-station at Karjagi. The new Karjagi-132kV S/S is

proposed in year 2009-10 for reducing loading on

Akkakalkot-132kV.

SOLAPUR

UPGRADATION OF

220KV CHAKAN S/S

(2009-10)

20 132 KV SOREGAON S/S

(2009-10)

17 PUNE VOLTAGE IMPROVEMENT & LOAD CATERING

Wagdari (Gogaon)-132kV S/S is considered for meeting

load growth in and around Solhapur.

132 KV Shankarnagar substation is proposed for catering

upcomming load nearby Akaluj.

PUNE

SOLAPUR

System Strengthining

System Strengthining

SOLAPUR

93

Page 97: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 - W.E.F 01/04/2010

SR

NO.

NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEME

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

PUNE EHV CONSTRUCTION CUM (O&M) ZONE

TOTAL SCOPE OF WORK

1 132KV LINK LINE

(2008-09)

PUNE 1) 132KV YAWAT - THEUR SCDC LINE - 23 KM 132kV Yawat S/S is fed from 132kV Theur S/s with S/c line.

Hence to provide uninterrupted supply during planned

outages it is necessary to add proposed line

2 132KV LINK LINE

(2008-09)

PUNE 1) 132KV KURULI - RANJANGAON SCDC - 20 KM 132kV Kuruli S/S is connected with 132kV Ranjangaon S/s

with S/c line. Hence to provide uninterrupted supply during

planned outages it is necessary to add proposed line

3 132KV LINK LINE*

(2009-10)

SOLAPUR 1) 132KV LINE FROM 220KV SOLAPUR II - MOHOL SCDC

LINE - 32 KM

132kV Mohol S/S is connected with 220kV Solapur S/s with

S/c line. Hence to provide uninterrupted supply during

planned outages it is necessary to add proposed line

1 132KV LINK LINE

(2008-09)

PUNE 1) 132 KV CHINCHWAD - MARKAL SCDC LINE - 29 KMS

WITH BAYS

Since the existing 132kV Theur-Kharadi S/c line is getting

loaded to an extent of 34 MW. It is anticipated the load in

Pune district will reach to critical value by the year 2011-12.

Hence it is suggested to add proposed line to meet

additional load growth and contingency.

2 132KV LINK LINE

(2008-09)

PUNE 1) 132 KV NCL PUNE - KOTHRUD SCDC LINE - 6.4 KMS

WITH BAYS

Since the existing 132kV NCL-Rahatane S/c line is critically

loaded to an extent of 75 MW. Hence it is suggested to add

proposed line to reduce the loading of existing line and to

meet additional load growth and contingency.

3 132KV LINK LINE

(2008-09)

PUNE 1) 132 KV CHINCHWAD - RAHATANE SCDC LINE - 6 KMS

WITH BAYS

Since the existing 132kV Chinchwad-Rahatane S/c line is

critically loaded to an extent of 82.6 MW. Hence it is

suggested to add proposed line to reduce the loading of

existing line and to meet additional load growth and

contingency.

4 132KV LINK LINE

(2008-09)

PUNE 1) 132 KV PHURSUNGI - THEUR SCDC LINE - 14 KMS

WITH BAYS

Since the existing 132kV Theur-Phursangi S/c line is

critically loaded to an extent of 103 MW. Hence it is

suggested to add proposed line to reduce the loading of

existing line and to meet additional load growth and

contingency.

5 132KV LINK LINE

(2008-09)

PUNE 1) 132 KV PHURSUNGI - MUNDWA SCDC LINE - 12 KMS

WITH BAYS

Since the existing 132kV Mundwa-Phursangi S/c line is

critically loaded to an extent of 103 MW. Hence it is

suggested to add proposed line to reduce the loading of

existing line and to meet additional load growth and

contingency.

6 132KV LINK LINE

(2008-09)

PUNE 1) 132 KV NCL PUNE - RAHATANE SCDC LINE - 6.4 KMS

WITH BAYS

Since the existing 132kV NCL Pune-Rahatane S/c line is

critically loaded to an extent of 75 MW. Hence it is

suggested to add proposed line to reduce the loading of

existing line and to meet additional load growth and

contingency.

7 132KV LINK LINES

(2009-10)

PUNE 1) 132KV STRINGING OF IIND CIRCUIT CHINCHWAD -

RAHATANE -NCL-12.4KM

Since the existing 132kV Chinchwad - Rahatane line is

loaded to an extent of 67 MW and 132kV Rahatane - NCL

line is loaded to an extent of 89 MW during Non-Coinsident

peak condition. It is anticipated the load will reach to about

critical value in future. Hence it is necessary to propose

additional line to meet additional load growth and

contingency.

1 132KV LINK LINE

(2009-10)

PUNE 1) 132 KV CHAKAN - URSE SCDC LINE - 20 KMS WITH

BAYS

Only single ckt and single source is available at Urse S/S.

2 220 KV LINK LINE

(2009-10)

RAIGAD 1) LILO ON 220 KV APTA - CHINCHWAD LINE FOR URSE

S/S ON IIND CKT - 22 KM

Linking to New 220 kV Urse S/s

1 400KV AUGMENTATION

AT JEJURI & SOLAPUR *

(2008-09)

PUNE SOLAPUR 1) 3 X 167 MVA, 400/220KV ICT WITH BAYS To avoid loss of supply in case of outages or interruptions

on any one transformer

1) ADDL. 1 X 25 MVA, 132/33 KV T/F WITH BAYS

2) 4 X 33 KV OUTLETS

1) ADDL. 1 X 25 MVA, 132/33 KV T/F WITH BAYS

2) 4 X 33 KV OUTLETS

1) 1X200 MVA, 220/132 KV T/F WITH BAYS

2) 2X132 KV BAYS

1) 1X100 MVA, 220/132 KV T/F WITH BAYS

2) 2X132 KV BAYS

1) 1X100 MVA, 220/132 KV T/F WITH BAYS

2) 1X50 MVA, 220/22 KV T/F WITH BAYS

3) 132 KV BAY - 2 NOS.

4) 6X22 KV OUTLETS

1) 1X25 MVA, 132/33 KV T/F WITH BAYS

2) 4X22 KV OUTLETS

3) 3 CORE, 400SQMM, XLPE CABLE - 0.8 KM

3

4 220 KV KURKUMBH S/S

(2008-09)

132KV PAREWADI S/S

(2008-09)

To avoid loss of supply in case of outages or interruptions

on any one transformer

To avoid loss of supply in case of outages or interruptions

on any one transformer

SOLAPUR

PUNE

132 KV SANASWADI S/S

(2008-09)

7

220 KV BARAMATI S/S

(2008-09)

5

6

To avoid loss of supply in case of outages or interruptions

on any one transformer

PUNE

PUNE220 KV RANJANGAON

S/S

(2008-09)

ADDITIONAL LINK LINES FOR NEW S/S TO HAVE ALTERNATE SOURCE

To avoid loss of supply in case of outages or interruptions

on any one transformer

To avoid loss of supply in case of outages or interruptions

on any one transformer

PUNE

AUGMENTATION OF S/S BY ADDITION OF T/F

AUGMENTATION OF S/S BY ADDITION WHERE ONLY SINGLE TRANSFORMER IS AVAILABLE

2 132 KV JANAI S/S

(2008-09)

PUNE To avoid loss of supply in case of outages or interruptions

on any one transformer

ADDITIONAL LINK LINES TO MEET DEMAND WITHOUT LOAD SHEDDING AND TO ENSURE RELIABILITY AND QUALITY OF SUPPLY

ADDITIONAL LINK LINES

ADDITIONAL LINK LINES FOR S/S WHERE ONLY SINGLE CKT AND SINGLE SOURCE IS AVAILABLE

94

Page 98: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 - W.E.F 01/04/2010

SR

NO.

NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEME

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

PUNE EHV CONSTRUCTION CUM (O&M) ZONE

TOTAL SCOPE OF WORK

1) ADDL. 1 X 25 MVA, 132/33 KV T/F WITH BAYS

2) 4 X 33 KV OUTLETS

1) 1X100 MVA, 220/132 KV T/F WITH BAYS

2) 2X132 KV BAYS

1) ADDL. 1 X 25 MVA, 132/33 KV T/F WITH BAYS

2) 4 X 33 KV OUTLETS

2) 22 KV OUTLETS - 4 NOS.

1) ADDL. 1 X 25 MVA, 132/33 KV T/F WITH BAYS

2) 4 X 33 KV OUTLETS

1) ADDL. 1 X 50 MVA, 132/22 KV T/F WITH BAYS

2) 4 X 33 KV OUTLETS

3) 4 X 22 KV OUTLETS

13 400KV JEJURI S/S *

(2009-10)

PUNE 1) 1 X 500 MVA, 400/220 KV ICT WITH BAYS The existing Trans,Capacity is 400/220 kV 1 X500 MVA and

the load reach is 529 MVA To avoid loss of supply in case

of outages or interruptions on any one ICT addil. ICT Is

proposed

14 220 KV PHURSUNGI S/S*

(2009-10)

PUNE 1) 1X200 MVA, 220/132 KV T/F WITH BAYS Existing transformer capacity available in S/s is 220/132 kV

,1 x 100 - load reach is 154MVA To avoid loss of supply in

case of outages or interruptions on any one ICT addil. ICT

Is proposed.

15 132 kV KAMTHADI

(2009-10)

Pune 1)

2)

Add 1 X 25 MVA, 132/33 kV T/F with bay.

4 X 33 kV out lets

Existing Transformer capacity avaible is 1 X 10 MVA. And

the load reached is 6 MVA.To avoid loss of supply in case

of outages or interruptions on transformer.

16 132 kV KURUDUWADI *

(2009-10)

Solapur 1)

2)

Add 1 X 50 MVA 132/33 kV T/F with bay.

8 X 33 kV out lets

Existing Transformer capacity avaible is 1 X 50 MVA. And

the load reached is 26 MVA.To avoid loss of supply in case

of outages or interruptions on transformer.

17 132 kV MARKAL*

(2009-10)

Pune 1)

2)

Add 1 X 25 MVA, 132/33 kV T/F with bay.

4 X 33 kV out lets

Existing Transformer capacity avaible is 1 X 25 MVA. To

avoid loss of supply in case of outages or interruptions on

transformer.

18 220 kV PIRANGUT

(2009-10)

Pune 1)

2)

Add 1 X 25 MVA, 220/33 kV T/F with bay.

4 X 33 kV out lets

Existing Transformer capacity avaible is 1 X 25 MVA. And

the load reached is 15.1 MVA.To avoid loss of supply in

case of outages or interruptions on transformer.

19 132 kV VELAPUR

(2009-10)

Solapur 1)

2)

Add 1 X 25 MVA, 132/33 kV T/F with bay.

4 X 33 kV out lets

Existing Transformer capacity avaible is 1 X 25 MVA. And

the load reached is 14 MVA.To avoid loss of supply in case

of outages or interruptions on transformer.

20 132 kV SHIRUR

(2009-10)

Pune 1)

2)

Add 1 X 25 MVA, 132/33 kV T/F with bay.

4 X 33 kV out lets

Existing Transformer capacity avaible is 1 X 25 MVA. And

the load reached is 5 MVA.To avoid loss of supply in case

of outages or interruptions on transformer.

21 220 kV BHIGWAN *

(2009-10)

Pune 1)

2)

Add 1 X 25 MVA, 220/33 kV T/F with bay.

4 X 33 kV out lets

Existing Transformer capacity avaible is 1 X 25 MVA. And

the load reached is 14 MVA.To avoid loss of supply in case

of outages or interruptions on transformer.

1) Add 1 X 50 MVA 220/22 KV T/F with bay

2) 6 x 22 kV outlets

1) 2X200MVA, 220/132KV ICTS WITH BAYS

2) 4X132KV LINE BAYS

3) 1X132KV TBC BAY

4) 220KV D/C LINE ON M/C TOWERS - 4 KM WITH BAYS

5) 132KV D/C LINE ON M/C TOWERS - 4 KM (STRINGING

ONLY)

1) 1X50 MVA, 220/22 KV T/F WITH BAYS

2) 6X22 KV OUTLETS

1) 1X50 MVA, 220/22 KV T/F WITH BAYS

2) 6X22 KV OUTLETS

1) ADDL. 1 X 25 MVA, 132/22 KV T/F WITH BAYS

2) 4 X 33 KV OUTLETS

22

8 132 KV YAWAT S/S

(2008-09)

PUNE

220 KV PARVATI S/S

(2008-09)

12 132 KV KAMTHADI S/S

(2008-09)

PUNE

PUNE

220 KV URSE S/S

(2008-09)

1

3

4 132 KV MARKAL S/S *

(2008-09)

To avoid loss of supply in case of outages or interruptions

on any one transformer

To avoid loss of supply in case of outages or interruptions

on any one transformer

Existing transformer capacity available in S/s is,

132/33 - 1 x25 - 5

To avoid loss of supply in case of outages or interruptions

on any one transformer

Existing transformer capacity available in S/s is,

132/33 - 1 x 10 - 8MVA load

132/22 - 1 x 25 - 16MVA load

To avoid loss of supply in case of outages or interruptions

on any one transformer

Newly Introduced 220/132kV level to feed Rastapeth S/s &

the nearby area at proper voltage and to take care of

anticipated load growth of the area.

New S/s

AUGMENTATION OF S/S BY ADDITION TO REDUCE LOADING OF TRANSFORMER

PUNE

PUNE220KV PARVATI S/S

(2008-09)

PUNE132 KV DAUND S/S

(2008-09)

132KV PURANDWADE

S/S

(2008-09)

SOLAPUR

SOLAPUR

PUNE

220 kV PIRANGUT*

(2009-10)

11

10

9 220 KV JEUR S/S

(2008-09)

To avoid loss of supply in case of outages or interruptions

on any one transformer

Existing transformer capacity available in S/s is,

220/22 - 3 x 50 -141 load

Considering the maximum load reach on the transformer, in

event of interruption/outage on any one of the transformer

other transformer should take care of existing load so as to

avoid load shedding.

Existing transformer capacity available in S/s is,

132/33 - 1 x 25 - 13 load

132/22 - 1 x 25 - Nil load

132/22 - 1 x 12.5 - 11 load

Hence it is necessary to propose additional transformer to

meet additional load growth and contingency.

2

Pune Existing transformer capacity available in S/s is 1 X 50 and

load reach is 24 MVA.To avoid loss of supply in case of

outages or interruptions on transformer.

95

Page 99: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 - W.E.F 01/04/2010

SR

NO.

NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEME

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

PUNE EHV CONSTRUCTION CUM (O&M) ZONE

TOTAL SCOPE OF WORK

1) ADDL. 1X25MVA, 220/33KV T/F WITH BAYS

2) 4X33KV OUTLETS

1) 1 X 50MVA, 132/33KV T/F WITH BAYS

2) 1X 200MVA, 220/132KV ICT WITH BAYS

3) 6 X 33KV OUTLETS

4) 1 X 132KV BAY

7 220 KV ALEPHATA S/S

(2009-10)

PUNE 1) 1X100 MVA, 220/132 KV T/F WITH BAYS Existing transformer capacity available in S/s is 220/132 kV

,2 x 100 - load reach is 100MVA To avoid loss of supply in

case of outages or interruptions on any one transformer

addil. Trans. is proposed.

8 220KV THEUR S/S

(2009-10)

PUNE 1) 1X200 MVA, 220/132KV ICT WITH BAYS Existing transformer capacity available in S/s is,220/132, 1

x 150 MVA and 1 X 200 MVA and the load reach is 268

MVA Considering the maximum load reach on the

transformer, in event of interruption/outage on any one of

the transformer other transformer should take care of

existing load so as to avoid load shedding.

9 132kV MANGALWEDHA *

(2009-10)

Solapur 1)

2)

Add 1 X 25 MVA , 132/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in S/s is 1 X 25 MVA

and load is 20 MVA. Considerinh thre maximum load

reached on the transformer in the event of

interruptions/outage on any one of the transformer other

transformer should take care of existing load.

10 132 kV BARAMATI

(2009-10)

Pune 1)

2)

Add 1 X 25 MVA , 132/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in S/s is 1 X 25, 1 X

50 MVA and load is 34 MVA. Considerinh thre maximum

load reached on the transformer in the event of

interruptions/outage on any one of the transformer other

transformer should take care of existing load.

11 132 kV JEJURI

(2009-10)

Pune 1)

2)

Add 1 X 25 MVA , 132/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in S/s is 2 X 25MVA

and load is 27 MVA. Considerinh thre maximum load

reached on the transformer in the event of

interruptions/outage on any one of the transformer other

transformer should take care of existing load.

12 132 kV NARAYANGAON

(2009-10)

Pune 1)

2)

Add 1 X 25 MVA , 132/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in S/s is 2 X 25MVA

and load is 31 MVA. Considerinh thre maximum load

reached on the transformer in the event of

interruptions/outage on any one of the transformer other

transformer should take care of existing load.

13 132 kV CHAKAN - I *

(2009-10)

Pune 1)

2)

Add 1 X 50 MVA , 132/33 kV T/F with bays.

6 X 33 kV out lets.

Existing transformer capacity available in S/s is 1 X 25, 1 X

50 MVA and load is 51 MVA. Considerinh thre maximum

load reached on the transformer in the event of

interruptions/outage on any one of the transformer other

transformer should take care of existing load

14 132 kV SANGOLA

(2009-10)

Solapur 1)

2)

Add 1 X 25 MVA , 132-110/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in s/s is 2 X 50

MVA. And the load reached is 48 MVA The transformer is

replaced to meet anticipated load growth

15 132 kV SOLAPUR - I

(DEGAON)

(2009-10)

Solapur 1)

2)

1) Add 1 X 25 MVA , 132-110/33 kV T/F with bays.

2) 4 X 33 kV out lets.

Existing transformer capacity available in s/s is 2 X 25

MVA. And the load reached is 22 MVA The transformer is

replaced to meet anticipated load growth.

16 132 kV KURUDUWADI

(2009-10)

Solapur 1)

2)

Add 1 X 50 MVA , 132/33 kV T/F with bays.

6 X 33 kV out lets.

Existing transformer capacity available in s/s is 1 X 50

MVA. And the load reached is 26 MVA The transformer is

replaced to meet anticipated load growth.

17 220 kV ALEPHATA

(2009-10)

Pune 1)

2)

Add 1 X 50 MVA , 220/33 kV T/F with bays.

6 X 33 kV out lets.

Existing transformer capacity available in s/s is 2 X 50

MVA. And the load reached is 47 MVA Considerinh thre

maximum load reached on the transformer in the event of

interruptions/outage on any one of the transformer other

transformer should take care of existing load.

18 220 kV JEUR

(2009-10)

Solapur 1)

2)

Add 1 X 25 MVA , 220/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in S/s is 2 X 25 MVA

and load is 36 MVA. Considerinh thre maximum load

reached on the transformer in the event of

interruptions/outage on any one of the transformer other

transformer should take care of existing load.

1) Add 1x50 MVA 132/22 KV T/F with bay

2) 6 x 22 kV outlets

1) Add 1x25 MVA 132/22 KV T/F with bay

2) 4 x 22 kV outlets

1) Add 1x50 MVA 220/22 KV T/F with bay

2) 6 x 22 kV outlets

1) Add 1x50 MVA 220/22 KV T/F with bay

2) 6 x 22 kV outlets

220 KV MALINAGAR

(2008-09)

6 SOLAPUR

SOLAPUR220KV TEMBHURNI S/S *

(2008-09)

5

Existing transformer capacity available in S/s is,

220/132 - 1 x 100 - 48 load

220/33 - 2 x 50 - 56 load

Considering the maximum load reach on the transformer, in

event of interruption/outage on any one of the transformer

other transformer should take care of existing load so as to

avoid load shedding.

21 220 kV LONIKAND

(2009-10)

Pune Existing transformer capacity available in S/s is 2 X 50 and

load reach is 53 MVA.Considering the maximum load

reached on the transformer in the event of

interruptions/outage on any one of the transformer other

transformer should take care of existing load.

Existing transformer capacity available in S/s is 3 X 50 and

load reach is 120 MVA.Considering the maximum load

reached on the transformer in the event of

interruptions/outage on any one of the transformer other

transformer should take care of existing load.

Existing transformer capacity available in S/s is 1 X 50, 1 x

25 and load reach is 45 MVA.Considering the maximum

load reached on the transformer in the event of

interruptions/outage on any one of the transformer other

transformer should take care of existing load.

19 132 kV YAVAT

(2009-10)

Pune

New S/s

132 kV PHURSANGI-I

(2009-10)

Pune Existing transformer capacity available in S/s is 2 X 25 and

load reach is 40 MVA.Considering the maximum load

reached on the transformer in the event of

interruptions/outage on any one of the transformer other

transformer should take care of existing load.

22 220 kV CHINCHWAD

(2009-10)

20

Pune

96

Page 100: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 - W.E.F 01/04/2010

SR

NO.

NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEME

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

PUNE EHV CONSTRUCTION CUM (O&M) ZONE

TOTAL SCOPE OF WORK

1) Add 1x50 MVA 220/22 KV T/F with bay

2) 6 x 22 kV outlets

1) Add 1x50 MVA 220/22 KV T/F with bay

2) 6 x 22 kV outlets

1) Add 1x50 MVA 220/22 KV T/F with bay

2) 6 x 22 kV outlets

1) Add 1x50 MVA 220/22 KV T/F with bay

2) 6 x 22 kV outlets

1 220 KV KARKAMBH S/S*

(2008-09)

SOLAPUR 1) 1 X ( 50 - 25) MVA, 220/33 KV T/F WITH BAYS Existing transformer capacity available in S/s is,

220/33 - 2 x 25 - 34.40 load

Considering the maximum load reach on the transformer, in

event of interruption/outage on any one of the transformer

other transformer should take care of existing load so as to

avoid load shedding.

2 220 KV SOLAPUR II S/S*

(BALE)

(2008-09)

SOLAPUR 1) 1 X (50-25) MVA, 132/33 KV T/FS WITH BAYS Existing transformer capacity available in S/s is,

132/33 - 1 x 25 -18 load

132/33 - 1 x 50 - 31.43 load

Considering the maximum load reach on the transformer, in

event of interruption/outage on any one of the transformer

other transformer should take care of existing load so as to

avoid load shedding.

3 132 KV CHAKAN S/S *

(2008-09)

PUNE 1) REP. 1 X (50-25) MVA, 132/22 KV T/FS WITH BAYS Existing transformer capacity available in S/s is,

132/22 - 2 x 50 - 76 load

132/22 - 2 x 25 - 39 load

Considering the maximum load reach on the transformer, in

event of interruption/outage on any one of the transformer

other transformer should take care of existing load so as to

avoid load shedding.

1) 1X50 MVA 132-110/33KV T/F

2) 6X33KV OUTLETS

5 132 KV MOHOL S/S*

(2008-09)

SOLAPUR 1) REP. 1 X (50-25) MVA, 132/33 KV T/FS WITH BAYS Existing transformer capacity available in S/s is,

132/22 - 1 x 50 - 39.3 load

110/22 - 1 x 25 - 20 load

Considering the maximum load reach on the transformer, in

event of interruption/outage on any one of the transformer

other transformer should take care of existing load so as to

avoid load shedding.

1) 2 X (50-25) MVA, 132/33 KV T/FS WITH BAYS

2) 33 KV OUTLETS - 4 NOS.

7 132 KV SOLAPUR MIDC

S/S*

(2008-09)

SOLAPUR 1) REPL. 1 X (50- 25) MVA, 132/33 KV T/FS WITH BAYS Existing transformer capacity available in S/s is,

132/33 - 1 x 50 - 30 load

132/33 - 1 x 25 - 19 load

Considering the maximum load reach on the transformer, in

event of interruption/outage on any one of the transformer

other transformer should take care of existing load so as to

avoid load shedding.

1) REP.1 X ( 50 -25) MVA, 132/33 KV T/FS WITH BAYS

2) 33 KV OUTLETS - 3 NOS.

9 132 KV SANGOLA S/S*

(2008-09)

SOLAPUR 1) REPL. 1 X (50- 25) MVA, 132-110/33 KV T/FS WITH BAYS Existing transformer capacity available in S/s is,

132/33 - 2 x 25 - 36 load

Considering the maximum load reach on the transformer, in

event of interruption/outage on any one of the transformer

other transformer should take care of existing load so as to

avoid load shedding.

1) (25-16) MVA, 132/33 KV T/F

2) 2X33 KV OUTLETS

AUGMENTATION OF S/S BY REPLACEMENT OF T/F

Existing transformer capacity available in S/s is,

132/33 - 2 x 25 - 43 load

Considering the maximum load reach on the transformer, in

event of interruption/outage on any one of the transformer

other transformer should take care of existing load so as to

avoid load shedding.

Existing transformer capacity available in S/s is,

132/33 - 1 x 25 - 19 load

132/33 - 1 x 16 - 15 load

Considering the maximum load reach on the transformer, in

event of interruption/outage on any one of the transformer

other transformer should take care of existing load so as to

avoid load shedding.

10 132 KV INDAPUR S/S*

(2008-09)

PUNE

SOLAPUR8

25

132 KV DEGAON S/S*

(2008-09)

6 132 KV AKKALKOT S/S*

(2008-09)

SOLAPUR Existing transformer capacity available in S/s is,

132/33 - 2 x 25 - 37 load

Considering the maximum load reach on the transformer, in

event of interruption/outage on any one of the transformer

other transformer should take care of existing load so as to

avoid load shedding.

132KV SANGOLA S/S *

(2008-09)

4 SOLAPUR Existing transformer capacity available in S/s is,

132-110/33 - 2 x 25 - 36 load

Considering the maximum load reach on the transformer, in

event of interruption/outage on any one of the transformer

other transformer should take care of existing load so as to

avoid load shedding.

24 220 kV PHURSANGI-II

(2009-10)

23 220kV HINJEWADI -I

(2009-10)

Pune Existing transformer capacity available in S/s is 2 X 25 and

load reach is 41 MVA.Considering the maximum load

reached on the transformer in the event of

interruptions/outage on any one of the transformer other

transformer should take care of existing load.

26 220 kV THEUR

(2009-10)

Pune Existing transformer capacity available in S/s is 2 X 50 and

load reach is 75 MVA.Considering the maximum load

reached on the transformer in the event of

interruptions/outage on any one of the transformer other

transformer should take care of existing load.

220 kV TELCO

(2009-10)

Existing transformer capacity available in S/s is 2 X 50 and

load reach is 66 MVA.Considering the maximum load

reached on the transformer in the event of

interruptions/outage on any one of the transformer other

transformer should take care of existing load.

Pune

Pune Existing transformer capacity available in S/s is 2 X 50 and

load reach is 70 MVA.Considering the maximum load

reached on the transformer in the event of

interruptions/outage on any one of the transformer other

transformer should take care of existing load.

97

Page 101: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 - W.E.F 01/04/2010

SR

NO.

NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEME

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

PUNE EHV CONSTRUCTION CUM (O&M) ZONE

TOTAL SCOPE OF WORK

11 110KV KURDUWADI S/S*

(2008-09)

SOLAPUR 1) 1X(50 - 25)MVA, 132-110/33KV T/F WITH BAYS Existing transformer capacity available in S/s is,

132/22 - 1 x 50 - 34.34 load

110/22 - 1 x 25 - 22.41 load

Considering the maximum load reach on the transformer, in

event of interruption/outage on any one of the transformer

other transformer should take care of existing load so as to

avoid load shedding.

12 220KV RANJANGAON

S/S (2009-10)

PUNE 1) 1X(200-100) MVA, 220/132KV ICT WITH BAYS Existing transformer capacity available in S/s is, 220/132,1

x 100 MVA - load reach is- 86MVA replacement of existing

transformer of 220/132 kV 1 x 100 MVA is being proposed

during2009-10 to have sufficient capacity during interuption

and to cater the load.

13 220KV CHINCHWAD

( 2009-10)

PUNE 1) 1X(200-50) MVA ,220/132-110KV WITH BAYS Existing transformer capacity available in S/s is, 220/132,1

x 200 MVA and 2 x 50 MVA and the load reach is 144

MVA. Considering the maximum load reach on the

transformer in event of interruption/outage on any one of the

transformer other transformer should take care of existing

load so as to avoid load shedding.

14 220KV CHINCHWAD

( 2009-10)

PUNE 1) 1X(200-50) MVA ,220/110-100KV WITH BAYS Existing transformer capacity available in S/s is, 220/110,1

x 50 MVAand 1 X 100 MVA and the load reach is 54.60

MVA. Considering the maximum load reach on the

transformer, in event of interruption/outage on any one of

the transformer other transformer should take care of

existing load so as to avoid load shedding.

15 220 KV SOLAPUR-II S/S

(2009-10)

SOLAPUR 1) 1X(200-100)MVA, 220/132KV WITH BAYS Existing transformer capacity available in S/s is, 220/132,1

x200 MVA,1X150 and1X100MVA the load reach is 358

MVA Considering the maximum load reach on the

transformer, in event of interruption/outage on any one of

the transformer other transformer should take care of

existing load so as to avoid load shedding.

16 220KV PANDHARPUR

S/S(2009-10)

SOLAPUR 1) 1X(200-100)MVA, 220/132KV WITH BAYS Existing transformer capacity available in S/s is,

220/132 - 1 x 100 - load reach is 70

220/100 - 1 x 100 - 52

The transformers are replaced to meet anticipated load

growth.

17 220KV BARAMATI S/S

(2009-10)

PUNE 1) 1X(100-50)MVA, 220/132KV WITH BAYS Existing transformer capacity available in S/s is, 220/132,1

x 50 MVA and the load reach is 30 MVA Considering the

maximum load reach on the transformer, in event of

interruption/outage on any one of the transformer other

transformer should take care of existing load so as to avoid

load shedding.

18 220 kV KARKUMBH *

(2009-10)

Solapur 1)

2)

1 X (50-25) MVA, 220/33 kV T/F with bays.

4 X 33 kV outlets.

Existing transformer capacity available in s/s is 1 X 50 & 1

X 25 MVA and the load reached is 35 MVA The transformer

is replaced to meet anticipated load growth.

1) 1X(50-25) MVA, 132/22 KV T/F WITH BAYS

2) 22 KV OUTLETS - 2 NOS.

20 132 kV NCL PUNE*

(2009-10)

Pune 1)

2)

2 X ( 50-25) MVA 132/22 kV T/F with bays

4 X 22 kV outlets.

Existing transformer capacity available in S/s is 2 x 25

and the Load reach is 30 MVA.The T/F is replaced to meet

anticipated load growth

21 132 kV SHIRUR

(2009-10)

Pune 1)

2)

2 X ( 50-25) MVA 132/22 kV T/F with bays

4 X 22 kV outlets.

Existing transformer capacity available in S/s is 2 x 25

and the Load reach is 26 MVA. The T/F is replaced to

meet anticipated load growth

22 132 kV

WALCHANDNAGAR*

(2009-10)

Pune 1)

2)

2 X ( 50-25) MVA 132/22 kV T/F with bays

4 X 22 kV outlets.

Existing transformer capacity available in S/s is 2 x 25

and the Load reach is 32 MVA. The T/F is replaced to meet

anticipated load growth

23 132 kV MUNDHAWA

(2009-10)

Pune 1)

2)

1 X ( 50-25) MVA 132/22 kV T/F with bays

4 X 22 kV outlets.

Existing transformer capacity available in S/s is 3 x 25

and the Load reach is 51 MVA. The T/F is replaced to meet

anticipated load growth

24 132 kV KURULI

(2009-10)

Pune 1)

2)

1 X(50- 25) MVA, 132/33 kV T/F with bay.

4 X 33 kV out lets

Existing Transformer capacity avaible is 1 X 25 MVA. And

the load reached is 19 MVA.To avoid loss of supply in case

of outages or interruptions on transformer.25 100 kV LONAWALA

(2009-10)

Pune 1)

2)

1 X ( 50-25) MVA 132-100/22 kV T/F with bays

4 X 22 kV outlets.

Existing transformer capacity available in S/s is 1 x 16, 1 x

12.5 and the Load reach is 15 MVA.The T/F is replaced to

meet anticipated load growth

26 100 kV TALEGAON-I

(2009-10)

Pune 1)

2)

1 X ( 50-20) MVA 132-100/22 kV T/F with bays

4 X 22 kV outlets.

Existing transformer capacity available in S/s is 1 x 28, 1 x

25, 1 x 20 and the Load reach is 47 MVA.The T/F is

replaced to meet anticipated load growth

19 132 KV MUNDHWA S/S

(2009-10)

PUNE Existing transformer capacity available in S/s is,

132/22 - 3 x 25 - 53.49 load

Considering the maximum load reach on the transformer, in

event of interruption/outage on any one of the transformer

other transformer should take care of existing load so as to

avoid load shedding.

98

Page 102: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 - W.E.F 01/04/2010

SR

NO.

NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEME

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

PUNE EHV CONSTRUCTION CUM (O&M) ZONE

TOTAL SCOPE OF WORK

1) 2 X 500 MVA, 400/220 KV ICT WITH BAYS

1 X 167 MVA, 400/220 KV SPARE

2) 400 KV HINJEWADI - KESURDI D/C - 60 KM WITH BAYS

3) 220 KV INTERCONNECTION FROM 400 KV HINJEWADI-

HINJEWADI-II - 5 KM

1) 2 X 50 MVA, 220/22 KV T/FS WITH BAYS

2) LILO ON 220 KV LONIKAND - KHADAKI LINE - 2.2 KM

3) 22 KV OUTLET - 12 NOS

1) 2X50MVA,220/22KV T/F

2) LILO ON 220KV CHINCHWAD-THEUR AT KONDHWA -

1KM

3) 22KV OUTLETS -12Nos

1) 132KV D/C LINE FROM 132KV MANGALWEDHA - 22KM

2) 2X25MVA, 132/33KV T/F

3) 33KV OUT LETS - 6 NOS.

1) 2X25MVA,132/33KV T/F

2) 2nd CKT STRINGING OF 132KV JEUR - KARJAT LINE -

42KM

3) LILO OF ONE CKT OF 132KV JEUR - KARJAT LINE AT

KARMALA - 16KM

4) 33KV OUTLETS - 06NOS.

1) 220 KV D/C LINE FROM 220 KV BARAMATI -20 KM

2) 220 KV D/C LINE FROM 220 KV PHALTAN (MIDC) -26 KM

3) 2 X 100 MVA, 220/132 KV ICT'S WITH BAYS

4) 132 KV D/C LINE TO 132 KV WALCHANDNAGAR - 5 KM

4) 132 KV D/C TO INDAPUR - 35 KM

1) 2 X 500 MVA, 400/220 KV ICT WITH BAYS

1 X 167 MVA, 400/220 KV SPARE

2) LILO ON 400 KV AURANGABAD-PUNE(PG) D/C - 20 KM WITH BAYS

3) 220 KV INTERCONNECTION FROM 400 KV RETWADI-

RAJGURUNAGAR - 5 KM

1 132KV LINK LINE

(2010-11)

PUNE 1) 132 KV DUAND - YAWAT SCDC LINE - 6 KMS WITH

BAYS

132kV Yawat S/S is fed from 132kV Theur S/s with S/c line.

Hence to provide uninterrupted supply during planned

outages it is necessary to add proposed line

2 132KV LINK LINE

(2010-11)

SOLAPUR 1) 132KV PANDHARPUR - MANGALWEDHA SCDC LINE -

22 KM

132kV Mangalwedha S/S is fed from 132kV Pandharpur S/s

with S/c line. Hence to provide uninterrupted supply during

planned outages it is necessary to add proposed line

3 132KV LINK LINE

(2010-11)

SOLAPUR 1) 132KV KARAJGI - MANDRUP SCDC LINE - 22 KM 132kV Mandrup S/S is fed from 132kV Degaon S/s with S/c

line. Hence to provide uninterrupted supply during planned

outages it is necessary to add proposed line

4 132KV LINK LINE*

(2012-13)

SOLAPUR 1) 132 KV CHINCHOLIKATE TAP ON BALE (SOLAPUR-II)-

MOHOL S/C LINE - 1.8 KM

132kV Chincholikate S/S is Tapped on 132kV Bale-Mohol

S/c line & Also the requirement from MIDC of 40 MW.

Hence to provide uninterrupted supply during planned

outages it is necessary to add proposed line

5 132KV LINK LINE

(2012-13)

SOLAPUR 1) 132 KV 2ND CIRCUIT LINE STRINGING FROM

PAREWADI -JEUR 22 KM

132kV Parewadi S/S is fed from 132kV Jeur S/s with S/c

line. Hence to provide uninterrupted supply during planned

outages it is necessary to add proposed line

6 132KV LINK LINE

(2012-13)

PUNE 1) 132 KV SHIRUR -FROM 220KV RANJANGAON SCDC

LINE - 26.0 KM

132kV Shirur S/S is fed from132kV Supa S/s with S/c line.

Hence to provide uninterrupted supply during planned

outages it is necessary to add proposed line

1 220 KV LINK LINE

(2010-11)

RAIGAD /PUNE 220 KV KANDALGAON -CHINCHWAD D/C ON M/C LINE -

60 KMS

This line is of 1962. For strengthning of network this work is

proposed.

2 132KV LINK LINE

(2010-11)

SOLAPUR 1) 132KV LINE FROM 220KV BALE - SOLAPUR MIDC DC

STRINGING OF 2ND CIRCUIT- 16.5KM

Since the existing132kV Solapur - solapur MIDC line is

loaded to an extent of 56 MW during Non-Coinsident peak

condition. It is anticipated the load will reach to about critical

value in future. Hence it is necessary to propose additional

line to meet additional load growth and contingency.

3 220KV LINK LINE

(2011-12)

SOLAPUR 1) 220 KV D/C LINE FROM VITA (KHARSUNDI) -

PANDHARPUR -LAMBOTI- 160km

Since the existing 220kV Vita-Pandharpur-Lamboti S/c lines

are getting overloaded during noncoincident peak condition.

Hence it is suggested to add proposed line to meet

additional load growth and contingency. 4 132KV LINK LINES

(2011-12)

SOLAPUR 1) 132KV LINK LINE FROM 220KV SOUTH SOLAPUR TO

SOLAPUR MIDC - 30KMS

System strengthining

5 132KV LINK LINES

(2011-12)

SOLAPUR 1) 132KV CABLE FROM 220KV MAGARPATTA TO

RASTAPETH - 2X12KM

System strengthining

1 220KV LINK LINE

(2010-11)

PUNE 1) 220 KV BHOSARI - CHAKAN D/C LINE - 22 KMS WITH

BAYS

Linking to New 400 kV Chakan S/s

2 132KV LINK LINES

(2010-11)

SOLAPUR 1) 132KV CABLE FROM 220KV MAGARPATTA TO KHARADI

- 7.5KM

To have alternate source for Kharadi

3 220KV LINK LINE

(2011-12)

PUNE 1) 220KV SOLAPUR -KARKAMB D/C LINE - 100KM To cater additional load on the S/S

1 400 KV HINJEWADI S/S

(2010-11)

NEW SCHEMES

400 kV Hinjewadi S/s is considered to cater the upcoming

EHV load and for strengthening of Pune region.

ADDITIONAL LINK LINES FOR S/S WHERE ONLY SINGLE CKT AND SINGLE SOURCE IS AVAILABLE

400 KV RETWADI S/S

(KHED,RAJGURUNAGAR

)

(2014-15)

PUNE 400 kV Retwadi S/s is considered to cater the upcoming

SEZ load of 500MW of Pune region.

7

PUNE

ADDITIONAL LINK LINES TO MEET DEMAND WITHOUT LOAD SHEDDING AND TO ENSURE RELIABILITY AND QUALITY OF SUPPLY

System strengthining

ADDITIONAL LINK LINES

ADDITIONAL LINK LINES FOR NEW S/S TO HAVE ALTERNATE SOURCE

VOLTAGE IMPROVEMENT & LOAD CATERING

3 220KV KONDHWA

(2010-11)

PUNE

4

2 220 KV YEWALEWADI

S/S (VSNL DIGHI)

(2010-11)

132KV NIMBONI

(2010-11)

SOLAPUR

PUNE

System strengthining

5 132KV KARMALA

(2010-11)

SOLAPUR System strengthining

6 220 KV Walchandnagar substation is proposed to reduce

overloading of 132 KV Walchandnagar- Indapur line and to

cater upcomming load in that area.

PUNE220 KV

WALCHANDNAGAR

(2011-12)

99

Page 103: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 - W.E.F 01/04/2010

SR

NO.

NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEME

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

PUNE EHV CONSTRUCTION CUM (O&M) ZONE

TOTAL SCOPE OF WORK

1 132 kV KURULI

(2011-12)

Pune 1)

2)

Add 1 X 25 MVA, 132/33 kV T/F with bay.

4 X 33 kV out lets

Existing Transformer capacity avaible is 1 X 25 MVA. To

avoid loss of supply in case of outages or interruptions on

transformer.

1 220 KV MALINAGAR

(2010-11)

SOLAPUR 1) 1X 100MVA, 220/132KV ICT WITH BAYS Existing transformer capacity available in S/s is, 220/132, 2

x 100 MVA and the load will reach 108 MVA. Considering

the maximum load reach on the transformer, in event of

interruption/outage on any one of the transformer other

transformer should take care of existing load so as to avoid

load shedding.

2 220 KV JEUR S/S

(2010-11)

SOLAPUR 1) 1X100 MVA, 220/132 KV T/F WITH BAYS Existing transformer capacity available in S/s is, 220/132

kV, 2 X100 MVA and the load will be 100 MVA To avoid

loss of supply in case of outages or interruptions on any one

transformer addil. trans. is proposed.

1) Add 1x50 MVA 132/22 KV T/F with bay

2) 6 x 22 kV outlets

4 132 kV AKKALKOT

(2010-11)

Solapur 1)

2)

Add 1 X 25 MVA , 132/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in s/s is 1 X 50 & 1

X 25 MVA. And the load reached is 46 MVA Considerinh

thre maximum load reached on the transformer in the event

of interruptions/outage on any one of the transformer other

transformer should take care of existing load.

5 132 kV CHINCHOLI KATE

(2010-11)

Solapur 1)

2)

Add 1 X 25 MVA , 110/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in S/s is 2 X 25 MVA

and load is 22 MVA. Considerinh thre maximum load

reached on the transformer in the event of

interruptions/outage on any one of the transformer other

transformer should take care of existing load.

6 132 kV SOLAPUR MIDC

(2010-11)

Solapur 1)

2)

Add 1 X 50 MVA , 132/33 kV T/F with bays.

6 X 33 kV out lets.

Existing transformer capacity available in S/s is 1 X 25 ,

1X50 MVA and load is 52 MVA. Considering the maximum

load reached on the transformer in the event of

interruptions/outage on any one of the transformer other

transformer should take care of existing load.

7 132 kV

WALCHANDNAGAR

(2010-11)

Pune 1)

2)

Add 1 X 25 MVA , 132/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in S/s is 2 X 25 MVA

and load is 20 MVA. Considering the maximum load

reached on the transformer in the event of

interruptions/outage on any one of the transformer other

transformer should take care of existing load.

8 132 kV INDAPUR

( 2011-12)

Pune 1)

2)

Add 1 X 25 MVA , 132/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in S/s is 1 X 25, 1 X

16 MVA and load is 19 MVA. Considering the maximum

load reached on the transformer in the event of

interruptions/outage on any one of the transformer other

transformer should take care of existing load.

1) Add 1x50 MVA 220/22 KV T/F with bay

2) 6 x 22 kV outlets

1) Add 1x50 MVA 132/22 KV T/F with bay

2) 6 x 22 kV outlets

11 132 kV BAWDA

(2012-13)

Pune 1)

2)

Add 1 X 25 MVA , 132/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in S/s is 2 X 25 MVA

and load is 18 MVA. Considering the maximum load

reached on the transformer in the event of

interruptions/outage on any one of the transformer other

transformer should take care of existing load.

1 220KV RANJANGAON

S/S (2010-11)

PUNE 1) 1X(200-100) MVA, 220/132KV ICT WITH BAYS Existing transformer capacity available in S/s will be

220/132 - 2 x 100 MVA the maximum load reach will

be150MVA

replacement of existing transformer of 220/132 kV 1 x 100

MVA is being proposed during2010-1 to have sufficient

capacity during interuption and to cater the load.

2 220 KV MALINAGAR

(2010-11)

SOLAPUR 1) 1X(200-100) MVA, 220/132KV WITH BAYS Existing transformer capacity available in S/s is, 220/132, 1

x100 MVA and the load reach is 81 MVA Considering the

maximum load reach on the transformer, in event of

interruption/outage on any one of the transformer other

transformer should take care of existing load so as to avoid

load shedding.

3 220 KV SOLAPUR-II S/S

(2010-11)

SOLAPUR 1) 1X(200-150) MVA, 220/132KV WITH BAYS Existing transformer capacity available in S/s will be,

220/132,2 X 200,1 X 100 and the load will reach 392 MVA

Considering the maximum load reach on the transformer, in

event of interruption/outage on any one of the transformer

other transformer should take care of existing load so as to

avoid load shedding.

4 132 kV MUNDHAWA

(2010-11)

Pune 1)

2)

1 X ( 50-25) MVA, 132/22 kV T/F with bays

4 X 22 kV outlets.

Existing transformer capacity available in S/s is 3 x 25,

And the Load reach is 51 MVA. The T/F is replaced to meet

anticipated load growth

5 220KV KHADKI S/S

(2010-11)

PUNE 1) 1X(100-50)MVA, 220/22-22KV TF WITH BAYS To meet upcoming load of MSEDCL

AUGMENTATION OF S/S BY REPLACEMENT OF ICT/T/F

AUGMENTATION OF S/S BY ADDITION TO REDUCE LOADING OF ICT/T/F

9 220 kV RANJANGAON

(2011-12)

Pune

AUGMENTATION OF S/S BY ADDITION OF ICT/T/F

AUGMENTATION OF S/S BY ADDITION WHERE ONLY SINGLE T/F IS AVAILABLE

132 kV KHARADI

(2010-11)

Pune Existing transformer capacity available in S/s is 2 X 50

and the Load reach is 60 MVA.Considering the maximum

load reached on the transformer in the event of

interruptions/outage on any one of the transformer other

transformer should take care of existing load.

10 132 kV CHAKAN-I *

(2012-13)

Pune Existing transformer capacity available in S/s is 2 X 50 and

the Load reach is 36 MVA.Considering the maximum load

reached on the transformer in the event of

interruptions/outage on any one of the transformer other

transformer should take care of existing load.

Existing transformer capacity available in S/s is 2 X 50

MVA,Load reached is 39 MVAConsidering the maximum

load reached on the transformer in the event of

interruptions/outage on any one of the transformer other

transformer should take care of existing load.

3

100

Page 104: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 - W.E.F 01/04/2010

SR

NO.

NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEME

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

PUNE EHV CONSTRUCTION CUM (O&M) ZONE

TOTAL SCOPE OF WORK

6 220KV BHOSARI S/S

(2010-11)

PUNE 1) 1X(100-50)MVA, 220/22-22KV TF WITH BAYS To meet upcoming load of MSEDCL

7 220KV PARVATI S/S

(2010-11)

PUNE 1) 1X(100-50)MVA, 220/22-22KV TF WITH BAYS To meet upcoming load of MSEDCL

8 220KV CHINCHWAD S/S

(2010-11)

PUNE 1) 1X(100-50)MVA, 220/22-22KV TF WITH BAYS To meet upcoming load of MSEDCL

9 132KV MARKAL

(2010-11)

PUNE 1) 1(50-25)MVA,132/33KV TF WITH BAYS To meet upcoming load of MSEDCL

10 220 KV MALINAGAR

(2011-12)

SOLAPUR 1) 1X(200-100) MVA, 220/132KV WITH BAYS Existing transformer capacity available in S/s is, 220/132,1

x100 MVA and the load reach is 98 MVA Considering the

maximum load reach on the transformer, in event of

interruption/outage on any one of the transformer other

transformer should take care of existing load so as to avoid

load shedding.

11 132 kV MUNDHAWA

(2011-12)

Pune 1)

2)

1 X ( 50-25) MVA, 132/22 kV T/F with bays

4 X 22 kV outlets.

Existing transformer capacity available in S/s is 3 x 25,

And the Load reach is 51 MVA.The T/F is replaced to meet

anticipated load growth

12 100 kV TALEGAON-I

(2011-12)

Pune 1)

2)

1 X ( 50-28) MVA, 132-100/22 kV T/F with bays

4 X 22 kV outlets.

Existing transformer capacity available in S/s is 1 x 28, 1 x

25, 1 x 20 and the Load reach is 47 MVA. The T/F is

replaced to meet anticipated load growth

13 220KV KHADKI S/S

(2011-12)

PUNE 1) 1X(100-50)MVA, 220/22-22KV TF WITH BAYS To meet upcoming load of MSEDCL

14 220KV BHOSARI S/S

(2011-12)

PUNE 1) 1X(100-50)MVA, 220/22-22KV TF WITH BAYS To meet upcoming load of MSEDCL

15 220KV PARVATI S/S

(2011-12)

PUNE 1) 1X(100-50)MVA, 220/22-22KV TF WITH BAYS To meet upcoming load of MSEDCL

16 220KV CHINCHWAD S/S

(2011-12)

PUNE 1) 1X(100-50)MVA, 220/22-22KV TF WITH BAYS To meet upcoming load of MSEDCL

17 220 kV BARSHI

( 2012-13)

Solapur 1)

2)

1 X (50-25) MVA, 220/33 kV T/F with bays.

4 X 33 kV outlets.

Existing transformer capacity available in s/s is 2 X 25 MVA

and the load reached is 40 MVA The transformer is

replaced to meet anticipated load growth.

18 220KV CHINCHWAD

( 2013-14)

PUNE 1) 1X(200-100) MVA ,220/132-100KV WITH BAYS Existing transformer capacity available in S/s is, 220/110,1

x 100 MVA and 1 X 150 MVA the max.load will reach 98

MVA. Considering the maximum load reach on the

transformer, in event of interruption/outage on any one of

the transformer other transformer should take care of

existing load so as to avoid load shedding.

1 110KV PANDHARPUR

(2010-11)

PUNE 1)

2)

2X25MVA, 132-110/33KV T/F

33KV OUTLETS - 8 NOS

NEW VOLTAGE LEVEL INTRODUCED

2 220 kV BARSHI

( 2011-12)

PUNE 1) 1X100 MVA, 220/132 KV T/F WITH BAYS NEW VOLTAGE LEVEL INTRODUCED

3 220 kV BARSHI

( 2012-13)

PUNE 1) 1X100 MVA, 220/132 KV T/F WITH BAYS NEW VOLTAGE LEVEL INTRODUCED

* COMMISSIONED IN 2009-10 ** 1No. TF COMMISSIONED IN 2009-10

ICT PROPOSED TO INTRODUCE 132 LEVEL.

101

Page 105: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

EHV CC O&M ZONE :

KARAD

102

Page 106: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 - W.E.F 01/04/2010

SR

NO.

NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEME

1) 220KV MAISAL - JATH D/C LINE - 70 KMS WITH BAYS

2) 2X100MVA, 220/132KV ICTS WITH BAYS

3) 2X25MVA, 220/33KV T/FS WITH BAYS

4) 8X132KV BAYS

5) 8X33KV OUTLETS

6) D/C ON D/C FROM 132KV JATH TO 220KV JATH - 0.5 KM

7) STRINGING OF 2ND CIRCUIT FROM PROPOSED JATH

220KV S/STN TO 132KV SANKH S/STN - 40 KM

8) 132KV KAVATHE MAHNKAL-JATH DC LINE -35 KM

1) LILO ON 220KV KOLHAPUR -SAWANTWADI LINE -

10KMS WITH BAYS

2) IIND CKT STRINGING OF KOLHAPUR - SAWANTWADI

LINE - 40 KMS

3) 132 KV SCDC LINE TO 110 KV KOTHALI S/S- 35 KMS

4) 2 X 100 MVA 220/132 -110 KV ICT'S WITH BAYS

5) 2 X 25MVA, 220/33KV T/FS WITH BAYS

6) 8 X 33KV OUTLETS.

1) LILO ON 220KV KANDALGAON - LONAND AT 220KV

LONAND MIDC S/STN - 10KM

2) 220KV LINE FROM 400KV JEJURI TO LONAND MIDC DC -

30KM3) 2X100, 220/132KV ICT

4) 2X50 , 220/33KV TF

5) 132KV D/C INTERLINK TO 220 KV LONAND- 10KM

6) 132KV LINE BAYS - 4 NOS

7) 33KV BAYS - 12 NOS

1) 220KV LINE FROM LONAND MIDC D/C LINE- 30KM

2) LILO OF 220KV LINE FROM LONAND - BOTHE - 4.5KM

3) 132 KV D/C LINE TO PHALTAN S/S - 10KM

4) 2X100MVA , 220/132KV ICT

5) 2X50 MVA, 220/33KV

6) 33KV BAYS - 12 NOS

1) LILO OF 220KV KARAD - MIRAJ S/C AT KADEGAON -

2.5KM

2) LILO ON TWO CIRCUITS OF 220KV M/C LINE FROM

KARAD TO MIRAJ AT KADEGAON- 5 KMS

2) 2X100MVA , 220/132KV ICT

3) 2X50 MVA, 220/33KV

4) 132 KV SCDC LINE TO KIRLOSKARWADI S/S-20 KM

5) 33KV BAYS - 12 NOS

1 220KV LINK LINE

(2008-09)

KOLHAPUR 1) 220KV LILO ON 2ND CKT OF KOLHAPUR - PHONDA - 2

KM WITH BAYS FOR HALKARNI

220kV Phonda S/S is fed from 400kV Talandge S/s with

S/c line. Hence to provide uninterrupted supply during

planned outages it is necessary to add proposed line

2 220KV LINK LINE*

(2008-09)

KOLHAPUR 1) 220KV LILO ON 2ND CKT OF KOLHAPUR - PHONDA -10

KM WITH BAYS FOR MUMEWADI

220kV Phonda S/S is fed from 400kV Talandge S/s with

S/c line. Hence to provide uninterrupted supply during

planned outages it is necessary to add proposed line

3 220KV LINK LINE

(2008-09)

KOLHAPUR 1) 220KV LILO ON HALKARNI - PHONDA FOR TILLARI ON

IIND CKT - 26 KM WITH BAYS

220kV Phonda S/S is fed from 400kV Talandge S/s with

S/c line. Hence to provide uninterrupted supply during

planned outages it is necessary to add proposed line

4 132 KV LINK LINE (2008-

09)

SATARA 1) 132KV SATARA (MIDC)- AUNDH SCDC -60 KM 132kV Aundh S/S is fed from 132kV Dahiwadi S/s with

S/c line. Hence to provide uninterrupted supply during

planned outages it is necessary to add proposed line

5 132KV LINK LINE

(2008-09)

SATARA 1) 132KV SATARA ROAD - SATARA MIDC -D/C LINE-15 KM 110kv satara road s/stn is fed from 110kv satara MIDC

S/S with S/C line .Hence to provide uninterrupted supply

during planned outages it is necessary to add proposed

line.

6 110 KV LINK LINE

(2008-09)

SATARA 1) 110KV SCDC LINE FROM 220KV OGALEWADI S/S -

110KV MAYNI S/S - 40 KM

110kV Mayani S/S is fed from 220kV Ogalewadi S/s with

S/c line. Hence to provide uninterrupted supply during

planned outages it is necessary to add proposed line

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

KARAD EHV CONSTRUCTION CUM (O&M) ZONE

TOTAL SCOPE OF WORK

220KV PHALTAN (MIDC)

S/STN

(2009-10)

220KV MUDHALTITTA

(BIDRI) S/S

(2009-10)

Lonand MIDC-220kV S/S is considered to meet the load

growth in Karad Circle and load requirement of MIDC

SPILL OVER SCHEMES

To take care of industrial load growth.

SANGLI220KV KADEGAON S/S

(2009-10)

ADDITIONAL LINK LINES FOR S/S WHERE ONLY SINGLE CKT AND SINGLE SOURCE IS AVAILABLE

ADDITIONAL LINK LINES

Present recorded peak load on Jath-110kV,

Kavathemankal-110kV and Sankh-110kV S/S are 30MW,

30MW and 25MW respectively. It is anticipated by the

year 2009-10 that the load will reach to about 105MW.

Hence it is necessary to go in for new 220kV sub-station

at Jath. By the commissioning of this substation, voltage

profile of Karad Circle will improve .

Mudal Tal is considerd for reducing loading of Kolhapur-

220kV S/S & to meet upcoming load

1 220 KV JATH S/S

(2009-10)

SANGLI

KOLHAPUR2

220 kV Kadegaon s/s is considered to take care of

industrial growth & additional load requirement of MIDC.

SATARA

SATARA

5

4

3 220KV MIDC LONAND

S/STN (2009-10)

103

Page 107: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 - W.E.F 01/04/2010

SR

NO.

NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEME

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

KARAD EHV CONSTRUCTION CUM (O&M) ZONE

TOTAL SCOPE OF WORK

7 110KV LINK LINES

(2008-09)

KOLHAPUR 1) 110KV MIRAJ - JISINGPUR D/C LINE-16 KM 110kV Jaysingpur S/S is fed from 220kV Miraj S/s with

S/c line. Hence to provide uninterrupted supply during

planned outages it is necessary to add proposed line

8 132 KV LINK LINE

(2009-10)

SANGLI 1) 132KV PETH - SHIRALA SCDC LINE - 26 KM 132kV Shirala S/S is fed from 132kV Peth S/s with S/c

line. Hence to provide uninterrupted supply during

planned outages it is necessary to add proposed line

9 132 KV LINK LINE

(2009-10)

SINDHUDURG 1) 132kV KUDAL - KANKAVALI SCDC LINE - 30 KM To provide uninterrupted supply during planned outages it

is necessary to add proposed line

10 110 KV LINK LINE

(2009-10)

SANGLI 1) 110KV TASGAON S/S - 220KV MIRAJ S/S SCDC LINE - 23

KM

110kV Tasgaon S/S is fed from 220kV Miraj S/s with S/c

line. Hence to provide uninterrupted supply during

planned outages it is necessary to add proposed line

11 110 KV LINK LINE

(2009-10)

KOLHAPUR 1) 220KV ICHALKARANJI S/S - 110KV KURUNDWAD S/S

SCDC LINE - 25 KM

110kV Kurundwad S/S is fed from 220kV Ichalkaranj S/s

with S/c line. Hence to provide uninterrupted supply

during planned outages it is necessary to add proposed

line

1 220KV LINK LINE

(2008-09)

KOLHAPUR 1) 220KV MIRAJ - ICHALKARANJI D/C LINE-30 KM Since the existing 220kV Ichalkaranji-Mudshingi S/c line

is critically loaded to an extent of 74 MW. Hence it is

suggested to add proposed line to reduce the loading of

existing line and to meet additional load growth and

contingency.

2 132 KV LINK LINE

(2008-09)

SATARA 1) 132KV PHALTAN - WALCHANDNAGAR SCDC LINE - 36

KM

Since the existing 132kV Phaltan-Walchandnagar S/c line

is critically loaded to an extent of 89 MW. Hence it is

suggested to add proposed line to reduce the loading of

existing line and to meet additional load growth and

contingency.

3 110 KV LINK LINE

(2008-09)

SANGLI 1) 110 KV DC LINE MIRAJ - KAVATHEMAHANKAL - 35 KM

WITH BAYS

Since the existing line is loaded to an extent of 71 MW

during Non-Coinsident peak condition. Hence it is

suggested to add proposed line to meet additional load

growth and contingency.

4 220kV LINK LINES

(2009-10)

KARAD 1) 220KV KARAD - GUDEPACHGANI (NIGADE) SCDC - 15KM To have the facility for wind evacuation at Gudepachgani

and nearby Karad S/s

5 220KV LINK LINE

(2009-10)

SATARA 1)

2)

220KV KARAD - KOYNA (POPHALI) D/C LINE - 40 KM

WITH BAYS

220KV GIS BAYS AT 400KV KARAD S/STN - 02 NOS

Since the existing 220kV Karad-Koyna S/c line is loaded

to an extent of 160 MW during Non-Coinsident peak

condition. It is anticipated the load will reach to about

critical value by the year 2011-12. Hence it is necessary

to propose additional line to meet additional load growth

and contingency.

6 110 KV LINK LINE

(2009-10)

SATARA 1) 110KV KARAD - TEMBU SCDC LINE - 20 KM Since the existing 110kV Karad-Tembhu S/c line is

loaded to an extent of 42 MW during Non-Coinsident

peak condition. It is anticipated the load will reach to

about critical value by the year 2011-12. Hence it is

necessary to propose additional line to meet additional

load growth and contingency.

7 110 KV LINK LINE

(2009-10)

KOLHAPUR 1) 110KV SHIROLI - KALE SCDC LINE - 25 KM Since the existing 110kV Shiroli-Bapat Camp S/c line is

critically loaded to an extent of 80 MW. Hence it is

suggested to add proposed line to reduce the loading of

existing line and to meet additional load growth and

contingency.

1) 1 X 25MVA , 220/33KV T/F WITH BAYS

2) 4 X 33KV OUTLETS.

1) 1 X 25MVA , 220/33KV T/F WITH BAYS

2) 4 X 33KV OUTLETS.

3) 3 CORE, 400SQMM, XLPE CABLE - 0.5 KM

1) 1 X 25MVA , 220/33KV T/F WITH BAYS

2) 4 X 33KV OUTLETS.

3) 3 CORE, 400SQMM, XLPE CABLE - 0.5 KM

To avoid loss of supply in case of outages or interruptions

on any one transformer

To avoid loss of supply in case of outages or interruptions

on any one transformer

To avoid loss of supply in case of outages or interruptions

on any one transformer

220K KV NIVALIPHATA

S/S

(2008-09)

RATNAGIRI

ADDITIONAL LINK LINES TO MEET DEMAND WITHOUT LOAD SHEDDING AND TO ENSURE RELIABILITY AND QUALITY OF SUPPLY

AUGMENTATION OF S/S BY ADDITION OF T/F

AUGMENTATION OF S/S BY ADDITION WHERE ONLY SINGLE TRANSFORMER IS AVAILABLE

220K KV FINOLEX S/S

(2008-09)

1 220K KV SAWANTWADI

S/S*

(2008-09)

SINDHUDURG

2

3 RATNAGIRI

104

Page 108: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 - W.E.F 01/04/2010

SR

NO.

NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEME

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

KARAD EHV CONSTRUCTION CUM (O&M) ZONE

TOTAL SCOPE OF WORK

1) 1 X 25MVA , 220/33KV T/F WITH BAYS

2) 4 X 33KV OUTLETS.

3) 3 CORE, 400SQMM, XLPE CABLE - 0.5 KM

1) 1 X 25 MVA, 220/33 KV T/F WITH BAYS

2) 33 KV OUTLETS - 4 NOS.

1) 1 X 100MVA, 220/132KV ICT WITH BAY

2) 1 X 132KV BAY

1) ADDL. 1X25 MVA 132/33KV T/F WITH BAYS

2) 4X33KV OUTLETS

1) ADDL. 1 X 50 MVA, 132/33 KV T/F WITH BAYS

2) 33 KV OUTLETS - 4 NOS.

1) ADDL. 1 X 25 MVA, 132/33 KV T/F WITH BAYS

2) 33 KV OUTLETS - 4 NOS.

1) ADDL. 1 X 25 MVA, 132-110/33 KV T/F WITH BAYS

2) 33 KV OUTLETS - 4 NOS.

1) ADDL. 1 X 25 MVA, 132/33 KV T/F WITH BAYS

2) 4 X 33 KV OUTLETS

1) ADDL. 1 X 25 MVA, 132-110/33 KV T/F WITH BAYS

2) 33 KV OUTLETS - 4 NOS.

1) ADDL. 1 X 25 MVA, 132-110/33 KV T/F WITH BAYS

2) 33 KV OUTLETS - 4 NOS.

1) ADDL. 1 X 25 MVA, 132-110/33 KV T/F WITH BAYS

2) 33 KV OUTLETS - 4 NOS.

15 400 kV NEW KOYNA

(2009-10)

Ratnagiri 1)

2)

Add 1 X 25 MVA, 220/33 kV T/F with bay.

4 X 33 kV out lets

Existing Transformer capacity avaible is 1 X 25 MVA.

And the load reached is 14 MVA To avoid loss of supply

in case of outages or interruptions on transformer.

16 220 kV KARAD-I

(OGALEWADI)

(2009-10)

Satara 1)

2)

Add 1 X 25 MVA, 220/33 kV T/F with bay.

4 X 33 kV out lets

Existing Transformer capacity avaible is 1 X 25 MVA.And

the load reached is 16 MVA. To avoid loss of supply in

case of outages or interruptions on transformer.

17 220 kV TALANDAGE

(5 STAR MIDC)

(2009-10)

Kolhapur 1)

2)

Add 1 X 25 MVA, 220/33 kV T/F with bay.

4 X 33 kV out lets

Existing Transformer capacity avaible is 1 X 25 MVA.

And the load reached is 50 MVA. To avoid loss of supply

in case of outages or interruptions on transformer.

18 220 kV ONI

(2009-10)

Ratnagiri 1)

2)

Add 1 X 25 MVA, 220/33 kV T/F with bay.

4 X 33 kV out lets

Existing Transformer capacity avaible is 1 X 25 MVA.

And the load reached is 8 MVA To avoid loss of supply in

case of outages or interruptions on transformer.

19 220KV PETH S/S

(2009-10)

SANGLI 1) 1 X 50 MVA.220/132 kV ICT WITH BAYS The existing Transformer capacity available is 220/132

kV 1X50MVA and the load reached is 32 MVA To avoid

loss of supply in case of outages or interruptions on any

one transformer other transformer should take care of

existing load so as to avoid load shedding.20 220KV SATARA MIDC S/S

(2009-10)

SATARA 1) 1 X 100 MVA, 220/132KV ICT WITH BAYS The existing Transformer capacity available is 220/132

kV 1X100MVA and the load reached is 65 MVA. To avoid

loss of supply in case of outages or interruptions on any

one transformer other transformer should take care of

21 132 kV DAHIWADI

(2009-10)

Satara 1)

2)

Add 1 X 25 MVA, 132/33 kV T/F with bay.

4 X 33 kV out lets

Existing Transformer capacity avaible is 1 X 25 MVA.

And the load reached is 4 MVA. To avoid loss of supply

in case of outages or interruptions on transformer.

22 132 kV KALE-T

(2009-10)

Satara 1)

2)

Add 1 X 25 MVA, 132/33 kV T/F with bay.

4 X 33 kV out lets

Existing Transformer capacity avaible is 1 X 25 MVA.

And the load reached is 16 MVA. To avoid loss of supply

in case of outages or interruptions on transformer.

12 132-110/33 KV KOTHALI

S/S

(2008-09)

KOLHAPUR

To avoid loss of supply in case of outages or interruptions

on any one transformer

Existing transformer capacity available in S/s is,

132-110/33 -1 x 25 -19

To avoid loss of supply in case of outages or interruptions

on any one transformerSANGLI

SANGLI110 KV BORGAON S/S

(2008-09)

132 KV SHIRVAL S/S

(2008-09)

SATARA

KOLHAPUR132 KV KURUNDWAD S/S

(2008-09)

SATARA

To avoid loss of supply in case of outages or interruptions

on any one transformer

To avoid loss of supply in case of outages or interruptions

on any one transformer

To avoid loss of supply in case of outages or interruptions

on any one transformer

132 KV AUNDH S/S

(2008-09)

To avoid loss of supply in case of outages or interruptions

on any one transformer

To avoid loss of supply in case of outages or interruptions

on any one transformer

6

7

8

SANGLI

SANGLI132KV DIGHANCHI

(2008-09)

COMMISSIONED

Existing transformer capacity available in S/s is,

110/33 -1 x 25 -24

To avoid loss of supply in case of outages or interruptions

on any one transformer

To avoid loss of supply in case of outages or interruptions

on any one transformer

Existing transformer capacity available in S/s is,

132/22 -1 x 25 -16

132/33 -1 x 12.5 -6

To avoid loss of supply in case of outages or interruptions

on any one transformer

11

SATARA

110 KV SANKH S/S

(2008-09)

5

4 220K KV KHAREPATAN

S/S

(2008-09)

SINDHUDURG

10

220KV HALKARNI S/S *

(2008-09)

220KV PETH S/S

(2008-09)

132 KV WAI S/S

(2008-09)

KOLHAPUR

13

9

14

105

Page 109: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 - W.E.F 01/04/2010

SR

NO.

NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEME

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

KARAD EHV CONSTRUCTION CUM (O&M) ZONE

TOTAL SCOPE OF WORK

23 132 kV WAI

(2009-10)

Satara 1)

2)

Add 1 X 25 MVA , 132/33 kV T/F with bay.

4 X 33 kV out lets

Existing Transformer capacity avaible is 1 X 25 MVA.

And the load reached is 23 MVA. To avoid loss of supply

in case of outages or interruptions on transformer.

24 132 kV KANKAVALI

(2009-10)

Sindhudurg 1)

2)

Add 1 X 25 MVA, 132/33 kV T/F with bay.

4 X 33 kV out lets

Existing Transformer capacity avaible is 1 X 16 MVA.

And the load reached is 10 MVA To avoid loss of supply

in case of outages or interruptions on transformer.

1 400KV KARAD &

KOLHAPUR S/S

(2008-09)

SATARA

KOLHAPUR

1) ADDL. 1 X 500 MVA, 400/220KV ICT WITH BAYS AT EACH

S/S

Existing transformer capacity available in S/s is,

KARAD-

400/220 -3 x 315 - 592

Kolhapur-

400/220 -2 x 315 - 390

1) 1 X 25 MVA, 220/33 KV T/F WITH BAYS

2) 33 KV OUTLETS - 4 NOS.

1) 1X200MVA, 220/132-110 KV ICT WITH BAYS

2) 2 X 132KV OUTLETS

1) ADDL. 1 X 25 MVA, 132/33 KV T/F WITH BAYS

2) 4 X 33 KV OUTLETS

1) ADDL. 1 X 50 MVA, 132/33 KV T/F WITH BAYS

2) 33 KV OUTLETS - 4 NOS.

1) 1 X 25MVA , 132-110/33KV T/F WITH BAYS

2) 4 X 33KV OUTLETS.

3) 3 CORE, 400SQMM, XLPE CABLE - 0.5 KM

1) ADDL. 1 X 25 MVA, 132-110/33 KV T/F WITH BAYS

2) 33 KV OUTLETS - 4 NOS.

8 400KV N-KOYNA S/S

(2009-10)

RATNAGIRI 1) 1 X 500 MVA, 400/220KV ICT WITH BAYS Existing transformer capacity available in S/s

is,400/220kV, 2 x 315 MVA and the load reached is 473

MVA Considering the maximum load reach on the

transformer, in event of interruption/outage on any one of

the transformer other transformer should take care of

existing load so as to avoid load shedding.

9 220KV KARAD S/S

(OGALEWDI)

(2009-10)

SATARA 1) ADDL. 1 X 100 MVA, 220/132-110 KV ICT WITH BAYS Existing transformer capacity available in S/s is,220/110

kV, 1 x 100 MVA, 1X75 MVA &1X50 MVA - load reach is-

134 MVA Considering the maximum load reach on the

transformer, in event of interruption/outage on any one of

the transformer other transformer should take care of

existing load so as to avoid load shedding.

10 220 kV LOTE

PARSHURAM (2009-

10)

Ratnagiri 1)

2)

Add 1 x 25 MVA, 220/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in s/s is 2 X 25

MVA. And the load reached is 40 MVA Considering the

maximum load reached on the transformer in the event of

interruptions/outage on any one of the transformer other

transformer should take care of existing load

11 220 kV DASTURI

(2009-10)

Ratnagiri 1)

2)

Add 1 x 25 MVA, 220/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in s/s is 2 X 25

MVA. And the load reached is 27 MVA The transformer is

replaced to meet anticipated load growth..

12 220 kV KOLHAPUR-II

(MUDSHINGI)

(2009-10)

Kolhapur 1)

2)

Add 1 X 50 MVA , 220/33 kV T/F with bays.

8 X 33 kV out lets.

Existing transformer capacity available in S/s is 1 X 50 &

1 X 25 MVA and load is 45 MVA.Considering the

maximum load reached on the transformer in the event of

interruptions/outage on any one of the transformer other

transformer should take care of existing load.

7

2

220 KV ICHALKARANJI*

(2008-09)

3

132 KV SATARA MIDC

S/S

(2008-09)

4 SATARA

5 SATARA

132 KV KANKAVLI S/S

(2008-09)

SINDHUDURG

KOLHAPUR Existing transformer capacity available in S/s is,

132/33 -1 x 25 -18

132/33 -2 x 16 -25

Considering the maximum load reach on the transformer,

in event of interruption/outage on any one of the

transformer other transformer should take care of existing

load so as to avoid load shedding.

Existing transformer capacity available in S/s is,

132/22 -2 x 25 -34

132/33 -1 x 25 -21

To avoid loss of supply in case of outages or interruptions

on any one transformer

110KV SHIROLI S/S*

(2008-09)

Existing transformer capacity available in S/s is,

132/33 - 2 x 25 - 27 MVA load

132/33 - 1 x 16 - 6 MVA load

Considering the maximum load reach on the transformer,

in event of interruption/outage on any one of the

transformer other transformer should take care of existing

load so as to avoid load shedding.

Newly introduced 220/132-110 Level

Existing transformer capacity available in S/s is,

132/33 -2 x 25 -49.8

Considering the maximum load reach on the transformer,

in event of interruption/outage on any one of the

transformer other transformer should take care of existing

load so as to avoid load shedding.

220 KV MUMEWADI S/S

(2008-09)

KOLHAPUR

KOLHAPUR

Existing transformer capacity available in S/s is,

220/33 -2 x 25 -36

Considering the maximum load reach on the transformer,

in event of interruption/outage on any one of the

transformer other transformer should take care of existing

load so as to avoid load shedding.

132 KV PHALTAN S/S

(2008-09)

AUGMENTATION OF S/S BY ADDITION TO REDUCE LOADING OF TRANSFORMER

6

106

Page 110: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 - W.E.F 01/04/2010

SR

NO.

NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEME

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

KARAD EHV CONSTRUCTION CUM (O&M) ZONE

TOTAL SCOPE OF WORK

13 220 kV ICHALKARNJI-II

(TILWANI)

(2009-10)

Kolhapur 1)

2)

Add 1 X 50 MVA, 220/33 kV T/F with bays.

6 X 33 kV out lets.

Existing transformer capacity available in S/s is 2 X 50

MVA and load is 71 MVA. Considerin the maximum load

reached on the transformer in the event of

interruptions/outage on any one of the transformer other

transformer should take care of existing load

14 220 kV MALHARPETH

(2009-10)

Satara 1)

2)

Add 1 X 50 MVA ,220/33 kV T/F with bays.

6 X 33 kV out lets.

Existing transformer capacity available in S/s is 2 X 50

MVA and load is 51 MVA. Considering the maximum

load reached on the transformer in the event of

interruptions/outage on any one of the transformer other

transformer should take care of existing load.

15 220 kV MUMEWADI

(2009-10)

Kolhapur 1)

2)

Add 1 X 25 MVA, 220/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in S/s is 2 X 25

MVA and load is 36 MVA. Considering the maximum

load reached on the transformer in the event of

interruptions/outage on any one of the transformer other

transformer should take care of existing load.

16 220 kV PETH

(2009-10)

Sangli 1)

2)

Add 1 X 25 MVA , 220/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in S/s is 2 X 25

MVA and load is 30 MVA. Considering the maximum

load reached on the transformer in the event of

interruptions/outage on any one of the transformer other 17 132 kV SAVLAJ

(2009-10)

Sangli 1)

2)

Add 1 X 25 MVA, 132/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in s/s is 1 X 25

MVA. And the load reached is 12 MVA The transformer is

replaced to meet anticipated load growth..

18 110 kV RATNAGIRI

(2009-10)

Ratnagiri 1)

2)

Add 1 X 25 MVA , 132-110/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in S/s is 2 X 25

MVA and load is 35 MVA. Considering the maximum

load reached on the transformer in the event of

interruptions/outage on any one of the transformer other

transformer should take care of existing load

19 110 kV ASHTA

(2009-10)

Sangli 1)

2)

Add 1 X 25 MVA , 132-110/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in S/s is 2 X 25

MVA and load is 36 MVA. Considering the maximum

load reached on the transformer in the event of

interruptions/outage on any one of the transformer other

transformer should take care of existing load

20 110 kV GOKUL

SHIRGAON

(2009-10)

Kolhapur 1)

2)

Add 1 X 25 MVA, 132-110/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in S/s is 2 X 50

MVA and load is 47 MVA. Considering the maximum

load reached on the transformer in the event of

interruptions/outage on any one of the transformer other

transformer should take care of existing load.

21 110 kV KALE KOLHAPUR

(2009-10)

Kolhapur 1)

2)

Add 1 X 25 MVA, 132-110/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in S/s is 2 X 25

MVA and load is 27.75 MVA. Considering the maximum

load reached on the transformer in the event of

interruptions/outage on any one of the transformer other

transformer should take care of existing load.

22 110 kV KOLHAPUR-I

(BAPAT CAMP)

(2009-10)

Kolhapur 1)

2)

Add 1 X 25 MVA, 132-110/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in S/s is 2 X 25

MVA and load is 38 MVA. Considering the maximum

load reached on the transformer in the event of

interruptions/outage on any one of the transformer other

transformer should take care of existing load.

23 110 kV PUIKHADI

(2009-10)

Kolhapur 1)

2)

Add 1 X 25 MVA, 132-110/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in S/s is 2 X 25

MVA and load is 32 MVA. Considering the maximum

load reached on the transformer in the event of

interruptions/outage on any one of the transformer other

transformer should take care of existing load.

24 110 kV VISHRAMBAUG

(2009-10)

Sangli 1)

2)

Add 1 X 25 MVA , 132-110/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in S/s is 1 X 25 &

1 X 20 MVA and load is 29 MVA. Considering the

maximum load reached on the transformer in the event of

interruptions/outage on any one of the transformer other

transformer should take care of existing load.

25 110 kV JAYSINGPUR

(2009-10)

Kolhapur 1)

2)

Add 1 X 25 MVA , 132-110/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in s/s is 3 X 25

MVA. And the load reached is 47 MVA Considering the

maximum load reached on the transformer in the event of

interruptions/outage on any one of the transformer other

transformer should take care of existing load.

26 110kV WATHAR-I

(2009-10)

Kolhapur 1)

2)

Add 1 X 25 MVA, 132-110/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in S/s is 2 X 25

MVA and load is 34 MVA. CConsidering the maximum

load reached on the transformer in the event of

interruptions/outage on any one of the transformer other

transformer should take care of existing load.

107

Page 111: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 - W.E.F 01/04/2010

SR

NO.

NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEME

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

KARAD EHV CONSTRUCTION CUM (O&M) ZONE

TOTAL SCOPE OF WORK

1 220 KV VITA S/S

(2008-09)

SANGLI 1) 1 X ( 50 - 25) MVA, 220/33 KV T/FS WITH BAYS Existing transformer capacity available in S/s is,

220/33 -1 x 50 -38

220/33 -1 x 25 -12.22

Considering the maximum load reach on the transformer,

in event of interruption/outage on any one of the

transformer other transformer should take care of existing

load so as to avoid load shedding.

2 220 KV MIRAJ S/S

(2008-09)

SANGLI 1) 1 X ( 50-25) MVA, 220/33 KV T/F WITH BAYS Existing transformer capacity available in S/s is,

220/33 -1 x 50 -35

220/33 -1 x 25 -21

Considering the maximum load reach on the transformer,

in event of interruption/outage on any one of the

transformer other transformer should take care of existing

load so as to avoid load shedding.

1) (50 -25)MVA, 220/33KV T/F

2) (25-10)MVA, 110/33KV T/F

1) 1 X ( 200-100) MVA, 220/132-110 KV ICTS WITH BAYS

2) 132 KV BAYS - 1NOS.

3) 33 KV OUTLETS - 4 NOS.

5 110KV MAYANI S/S

(2008-09)

SATARA 1) (12.5-7.5) MVA 132/110-22KV T/F WITH BAYS Existing transformer capacity available in S/s is,

110/22 -3 x 7.5 -18

110/33 -1 x 25 -15

Considering the maximum load reach on the transformer,

in event of interruption/outage on any one of the

transformer other transformer should take care of existing

load so as to avoid load shedding.

6 110 KV ASHTA *

(2008-09)

SANGLI 1) 2(25-16/12.5) MVA, 110/33 KV T/F Existing transformer capacity available in S/s is,

110/33 -1 x 16 -12

110/33 -1 x 12.5 -9.5

Considering the maximum load reach on the transformer,

in event of interruption/outage on any one of the

transformer other transformer should take care of existing

load so as to avoid load shedding.

7 110 KV KAVATHE

MAHANKAL S/S

(2008-09)

SANGLI 1) REP. 1 X ( 25-16) MVA, 110/33 KV T/F WITH BAYS Existing transformer capacity available in S/s is,

110/33 -1 x 25 -18

110/33 -1 x 16 -14

Considering the maximum load reach on the transformer,

in event of interruption/outage on any one of the

transformer other transformer should take care of existing

load so as to avoid load shedding.

1) REP. 2 X ( 50 -20/25) MVA, 132-110/33 KV T/FS WITH

BAYS

2) 33 KV OUTLETS - 8 NOS.

1) REP. 2 X ( 25-10) MVA, 132-110/33 KV T/FS WITH BAYS

2) 33 KV OUTLETS - 4 NOS.

1) REP. 2 X ( 25-12.5) MVA, 132-110/33 KV T/FS WITH BAYS

2) 33 KV OUTLETS - 4 NOS.

1) REP. 2 X ( 25-12.5) MVA, 132-110/33 KV T/FS WITH BAYS

2) 33 KV OUTLETS - 4 NOS.

8

10

SANGLI

9 110KV JATH S/S**

(2008-09)

SANGLI

4 220KV MIRAJ S/S

(2008-09)

SANGLI Existing transformer capacity available in S/s is,

220/132 - 3 x 100 - 252

Considering the maximum load reach on the transformer,

in event of interruption/outage on any one of the

transformer other transformer should take care of existing

load so as to avoid load shedding.

SANGLI

Existing transformer capacity available in S/s is,

110/33 -1 x 16 -13

110/33 -1 x 12.5 -10

Considering the maximum load reach on the transformer,

in event of interruption/outage on any one of the

transformer other transformer should take care of existing

load so as to avoid load shedding.

Existing transformer capacity available in S/s is,

110/33 -1 x 10 -9

110/33 -1 x 12.5 -7.4

Considering the maximum load reach on the transformer,

in event of interruption/outage on any one of the

transformer other transformer should take care of existing

load so as to avoid load shedding.

Existing transformer capacity available in S/s is,

110/33 -1 x 20 -15.55

110/33 -1 x 25 -16.66

Considering the maximum load reach on the transformer,

in event of interruption/outage on any one of the

transformer other transformer should take care of existing

load so as to avoid load shedding.

Existing transformer capacity available in S/s is,

110/33 -2 x 10 -19

Considering the maximum load reach on the transformer,

in event of interruption/outage on any one of the

transformer other transformer should take care of existing

load so as to avoid load shedding.

SANGLI

SATARA

110 KV VISHRAMBAG

S/S**

(2008-09)

AUGMENTATION OF S/S BY REPLACEMENT OF T/F

Existing transformer capacity available in S/s is,

220/33 - 1 x 25 - 24

110/33 - 1 x 10 - 9

Additional transformer of 220/33 kV

25 MVA is being added during the year 2007-08 to have

redundancy during outage/interuption to cater the load.

So to take care of anticipated load growth replcement is

required.

3 220KV OGALEWADI S/S

(2008-09)

110KV KIRLOSKARWADI

S/S**

(2008-09)

110KV TASGAON S/S**

(2008-09)

11

108

Page 112: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 - W.E.F 01/04/2010

SR

NO.

NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEME

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

KARAD EHV CONSTRUCTION CUM (O&M) ZONE

TOTAL SCOPE OF WORK

1) REP.1 X ( 50-25) MVA, 132-110/33 KV T/FS WITH BAYS

2) 33 KV OUTLETS - 4 NOS.

1) REP. 1 X ( 25-10) MVA, 132-110/33 KV T/FS WITH BAYS

2) 33 KV OUTLETS - 2 NOS.

1) REP.1 X ( 25-10) MVA, 132-110/33 KV T/FS WITH BAYS

2) 33 KV OUTLETS - 4 NOS.

1) 1X(25-12.5)MVA, 132-110/33KV T/F WITH BAYS

2) 1X(25-10)MVA, 132-110/33KV T/F WITH BAYS

3) 33KV OUTLETS - 4 NOS

2) 33 KV OUTLETS - 2 NOS.

16 220KV MIRAJ S/S

(2009-10)

SANGLI 1) 1 X ( 200-100) MVA, 220/132-110 KV ICTS WITH BAYS Existing transformer capacity available in S/s

is,220/110kV 3 x 100MVA and the load reached is 258

MVA.The transformer is replaced to meet the anticipated

load growth.

17 220 KV LONAND *S/S

(2009-10)

SATARA 1) 1 X (200- 63) MVA, 220/132 KV ICT WITH BAYS Existing transformer capacity available in S/s

is,220/132kV ,2 X 63+1 x 115 MVA and the load reached

is 249 MVA.The transformer is replaced to meet the

anticipated load growth.

18 220 KV KOLHAPUR-II

(MUDSHINGI) S/S

(2009-10)

KOLHAPUR 1) 1 X ( 200 - 100) MVA, 220/132-110 KV ICT WITH BAYS Existing transformer capacity available in S/s

is,220/110kV ,3 X 100 MVA and the load reached is 300

MVA.The transformer is replaced to meet the anticipated

load growth.

19 220 KV KARAD S/S

(2009-10)

SATARA 1 1 X (100-75) MVA,220/132-110 KV ICT WITH BAYS Existing transformer capacity available in S/s

is,220/110kV,1 x 100 MVA,1X75MVA &1X50MVA - load

reach is- 134 MVA Considering the maximum load reach

on the transformer, in event of interruption/outage on any

one of the transformer other transformer should take care

of existing load so as to avoid load shedding.

20 220 KV KARAD S/S

(2009-10)

SATARA 1 1 X (100-50) MVA,220/132-110 KV ICT WITH BAYS Existing transformer capacity available in S/s

is,220/110kV,1 x 100 MVA,1X75MVA &1X50MVA - load

reach is- 134 MVA Considering the maximum load reach

on the transformer, in event of interruption/outage on any

one of the transformer other transformer should take care

of existing load so as to avoid load shedding.

21 220 kV KARAD-I

(OGALEWADI)

(2009-10)

Satara 1)

2)

1 X(50- 25) MVA , 132/33-22 kV T/F with bay.

4 X 33 kV out lets

Existing Transformer capacity avaible is 1 X 25 MVA.And

the load reached is 16 MVA. To avoid loss of supply in

case of outages or interruptions on transformer.

22 220KV PETH S/S

(2009-10)

SANGLI 1) 1 x(100-50 )MVA.220/132 kV ICT WITH BAYS The existing Transformer capacity available is 220/132

kV 1X50MVA and the load reached is 32 MVA To avoid

loss of supply in case of outages or interruptions on any

one transformer other transformer should take care of

existing load so as to avoid load shedding.

23 132 kV WAI

(2009-10)

Satara 1)

2)

1 X(50- 25) MVA , 132/33-22 kV T/F with bay.

4 X 33 kV out lets

Existing Transformer capacity available is 1 X 25 MVA.

And the load reached is 23 MVA. To avoid loss of supply

in case of outages or interruptions on transformer.

24 132 kV DIGHANCHI

(2009-10)

Sangli 1)

2)

1 X (25-12.5) MVA, 132-110/33 kV T/F with bay.

4 X 33 kV out lets

Existing Transformer capacity avaible is 1 X 25 MVA. To

avoid loss of supply in case of outages or interruptions on

transformer.

25 132 kV

KAVATHEMAHAKAL

(2009-10)

Sangli 1)

2)

1 X (50-25) MVA MVA, 132-110/33 kV T/F with bays.

2 X 33 kV outlets.

Existing transformer capacity available in s/s is 2 X 25

MVA. And the load reached is 32 MVA The transformer is

replaced to meet anticipated load growth.

26 132 kV DIGHANCHI

(2009-10)

Sangli 1)

2)

1 X (25-12.5) MVA , 132-110/33 kV T/F with bays.

2 X 33 kV outlets.

Existing Transformer capacity avaible is 1 X 12.5 MVA.

To avoid loss of supply in case of outages or interruptions

on transformer.27 132 kV PHALTAN *

(2009-10)

Satara 1)

2)

1 X (50-25) MVA,132/22 kV T/F with bays.

4 X 22 kV outlets.

Existing transformer capacity available in S/s is 2 x

25,132/22 kV and load reach is 26 MVA. The T/F is

replaced to meet anticipated load growth

KOLHAPUR110KV RADHANAGARI*

S/S

(2008-09)

14

KOLHAPUR Existing transformer capacity available in S/s is,

110/33 -1 x 25 -22.2

110/33 -1 x 10 -9

Considering the maximum load reach on the transformer,

in event of interruption/outage on any one of the

transformer other transformer should take care of existing

load so as to avoid load shedding.

Existing transformer capacity available in S/s is,

110/33 - 2 x 10 - 18.14

Considering the maximum load reach on the transformer,

in event of interruption/outage on any one of the

transformer other transformer should take care of existing

load so as to avoid load shedding.

KOLHAPUR

110KV KALE S/S *

(2008-09)

15

110KV GOKULSHIRGAON

S/S

(2008-09)

13

12

110KV CHABUKHEDI

S/STN

(2008-09)

Existing transformer capacity available in S/s is,

110/33 -1 x 50 -27

110/33 -1 x 25 -20

Considering the maximum load reach on the transformer,

in event of interruption/outage on any one of the

transformer other transformer should take care of existing

load so as to avoid load shedding.

KOLHAPUR Existing transformer capacity available in S/STN

110/33 - 1 x 12.5MVA & 110/33KV, 10 MVA- 22MVA

Considering the maximum load reach on the transformer,

in event of interruption/outage on any one of the

transformer other transformer should take care of existing

load so as to avoid load shedding.

109

Page 113: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 - W.E.F 01/04/2010

SR

NO.

NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEME

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

KARAD EHV CONSTRUCTION CUM (O&M) ZONE

TOTAL SCOPE OF WORK

28 132 kV DAHIWADI

(2009-10)

Satara 1)

2)

1 X (25-12.5) MVA,132/22 kV T/F with bays.

4 X 22 kV outlets.

Existing transformer capacity available in S/s is 1 x 25,

1 X 12.5 ,132/22 kV and load reach is 14 MVA. The T/F

is replaced to meet anticipated load growth

29 110 kV RADHANAGARI *

(2009-10)

Sangli 1)

2)

1 X (25-10) MVA MVA, 132-110/33 kV T/F with bays.

2 X 33 kV outlets.

Existing transformer capacity available in s/s is 1 X 10 &

1 X 25 MVA. And the load reached is 13 MVA The

transformer is replaced to meet anticipated load growth.

30 110 kV MAYNI

(2009-10)

Satara 1)

2)

1 X (25-7.5) MVA , 132-110/33 kV T/F with bays.

2 X 33 kV outlets.

Existing transformer capacity available in s/s is 1 X 25 &

1X 7.5 MVA. And the load reached is 19 MVA The

transformer is replaced to meet anticipated load growth

31 110 kV MAYNI

(2009-10)

Satara 1)

2)

1 X (25-7.5) MVA,110/22 kV T/F with bays.

4 X 22 kV outlets.

Existing transformer capacity available in S/s is,

15 MVA. And the Load reach is 7 MVA. The T/F is

replaced to meet anticipated load growth

32 110 kV ICHALKARANGI-I

(2009-10)

Sangli 1)

2)

1 X (50-20) MVA MVA, 132-110/33 kV T/F with bays.

2 X 33 kV outlets.

Existing transformer capacity available in s/s is 1 X 10 &

1 X 20 , 1 X 25 MVA. And the load reached is 31 MVA

The transformer is replaced to meet anticipated load

growth

1) 2 X500MVA 400/220 KV ICT'S WITH BAYS

1 X 167 MVA , 400/220 KV 1 PHASE ICT SPARE

2) LILO ON BOTH CIRCUITS OF 400 KV NEW KOYNA -

KARAD-I AT KARAD - II WITH BAYS -5KM

3) 220 KV D/C LINE TO 220 KV MALHARPETH S/S - 10KM

4) 220KV D/C TO 220KV KADEGAON - 40KM

1) 400/220 KV , 2X 500 MVA ICT'S WITH BAYS

400/220 KV , 1 X 167 MVA 1 PHASE ICT SPARE 2) LILO OB BOTH CIRCUITS OF 400KV KOYNA - LONIKAND /

JEJURI AT KESURDI - 15 KM

3) 400 KV D/CLINE FROM 400 KV KARAD II (MALHARPETH)

TO KESURDI S/S 60 KM

4) 400 KV KESURDI - LONIKAND - II D/C LINE - 55KM

5) 220 KV LINE FROM 400KV KESURDI - 220 KV LONAND

MIDC D/C LINE - 30 KM WITH BAYS 6) 220KV LINE BETWEEN KESURDI - 400KV JEJURI D/C

LINE - 40 KM1) 220KV D/C LINE FROM FIVE STAR MIDC KAGAL - 220KV

HAMIDWADA(KAGAL) WITH BAYS - 35 KMS2) 2 X 50MVA, 220/33KV T/FS WITH BAYS

3) 12 X 33 KV OUTLETS

1) LILO OF 110KV OGALEWADI - PANDHARPUR LINE - 15

KM2) 2X25MVA, 132-110/33KV T/FS WITH BAYS

3) 33KV OUTLETS - 8NOS.

1) 2X100 MVA , 220/132KV ICT'S

2) 2 X 25 MVA, 220/33KV T/FS WITH BAYS

3) 220KV D/C LINE FROM GHTNANDRE - KHARSUNDI - 30

KMS4) 132KV SCDC LINE FROM 220KV KHARSUNDI - MAYANI -

23KMS5) 132KV SCDC LINE FROM 220KV KHARSUNDI -

DIGHANCHI - 25KMS6) 132KV SCDC LINE FROM 220KV KHARSUNDI - SAWALAJ -

28KMS7) 8 X 33 KV OUTLETS

1) 220KV MIRAJ - SANGLI D/C LINE WITH BAYS - 12 KMS

2) LILO ON 220KV MIRAJ - TILWANI LINE -35KM

3) 2 X 100 MVA 220/132 -110 KV ICT'S WITH BAYS

4) 132 KV VISHRAMBAG SCDC LINE -10 KMS

5) 132 KV ASHTA SCDC LINE -15 KMS

6) 2 X 50 MVA, 220/33KV T/FS WITH BAYS

7) 12X 33 KV OUTLETS

1) FROM 220KV TALANDGE S/S D/C LINE- 20KM

2) 2X50MVA , 132/33KV TF

3) 33KV OUTLET - 08 NOS.

1) LILO OF ONE CKT OF 400KV SOUTH SOLAPUR (PG) -

KOLHAPUR AT 400 KV ALKUD - 15KM

2) 400KV D/C LINE FROM KARAD -II - ALKUD - 100KM

3) LILO OF 0NE CKT OF 220KV VITA MHAISHAL LINE -18KM

4) LILO OF ONE CKT OF 220KV MHAISHAL - JATH LINE -

23KM5) 220KV D/C FROM 400KV ALKUD - KHARSUNDI LINE -

40KM

6) 2X500MVA 400/220KV ICT

7) 1X167 MVA , 400/220KV SPARE ICT

4 132KV MHASWAD

(2010-11)

SATARA

400 KV KESURDI S/S

(2010-11)

132 KV SHIRADWAD S/S

(2011-12)

Present recorded peak on Vishrambag is 70MW . It is

anticipated by the year 2011-12, the load will reach about

106MW. Hence it is necessary to go in for new 220kV

sub-station at Sangli.

SANGLI

8 SANGLI Strengthining of existing network.400KV ALKUD

(SANGLI)

(2012-13)

6

5

220 KV SANGLI S/S

(2011-12)

2

220 KV KHARSUNDI S/S

(2011-12)

3 220 KV HAMIDWADA

(KAGAL) S/S

(2010-11)

SATARA

SATARA

7

1 400 KV KARAD-II S/S

(MALHAR PETH)

(2010-11)

NEW SCHEMES

System Strengthining & Voltage improvement.

Kesurdi 400kV S/S is proposed for strenghtning for

evacuation of power, upcoming load and to improve

voltage profile of the area.

Kagal-220kV S/S is considered to meet the load growth

in Karad Circle and load requirement of MIDC area.

To meet the upcoming load.

Kharsundi 220kV S/S is considered for upcoming load

requirement in karad area

SANGLI

KOLHAPUR

kOLHAPUR

To improve voltage profile of the area and to meet the

upcoming load.

110

Page 114: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 - W.E.F 01/04/2010

SR

NO.

NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEME

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

KARAD EHV CONSTRUCTION CUM (O&M) ZONE

TOTAL SCOPE OF WORK

1 220 KV LINK LINE

(2010-11)

KOLHAPUR 1) 220KV KOLHAPUR - SAWANTWADI (STRINGING ONLY) -

122 KM

220kV Sawantwadi S/S is fed from 220kV Talandge S/s

with S/c line. Hence to provide uninterrupted supply

during planned outages it is necessary to add proposed

line2 220 KV LINK LINE

(2010-11)

SATARA 1) LILO ON 2ND CIRCUIT OF 220KV PEDAMBE -

KANDALGAON AT LOTE PARSHURAM -30KM

For redundancy.

3 220 KV LINK LINE

(2010-11)

SATARA 1) LILO ON 2ND CIRCUIT OF 220KV PEDAMBE -

KANDALGAON AT DASTURI - 29KM

For redundancy.

4 132 KV LINK LINE

(2010-11)

KOLHAPUR 1) 132KV D/C LINE FROM 220KV OGALEWADI - 132KV

KALE(T) -15 KM

For redundancy.

5 220KV LINK LINE

(2011-12)

SATARA 1) 220KV LONAND - VANKUSWADI SCDC LINE - 85 KM

WITH BAYS

To have the facility for wind evacuation at Vankuswadi

and nearby Lonand S/s

6 132KV LINK LINES

(2011-12)

SATARA 1) 132KV LONAND-SHIRWAL D/C LINE WITH BAYS -25KM To provide uninterrupted supply during planned outages it

is necessary to add proposed line

7 132KV LINK LINES

(2011-12)

SATARA 1) 132KV SCDC LINE FROM 220KV TILAWANI - 110KV

JAYSINGPUR - 18KM

For redundancy.

8 132KV LINK LINES

(2011-12)

SATARA 1) 132KV SCDC LINE FROM 220KV LONAND - 132KV

SATARA ROAD -35 KM

For redundancy.

9 132KV LINK LINES

(2011-12)

KOLHAPUR 1) 132KV D/C LINE FROM 132KV KALE(T) - 220KV WATHAR -

35 KM

For redundancy.

10 132KV LINK LINES

(2011-12)

SATARA 1) 132KV D/C LINE FROM 132KV DAHIWADI - 132KV

PHALTAN 40 KM

For redundancy.

11 132KV LINK LINES

(2011-12)

SATARA 1) 132KV D/C LINE FROM 220KV KOLHAPUR - 110KV

PUIKHADI -8 KM

For redundancy.

12 132KV LINK LINES

(2011-12)

SATARA 1) 132KV SCDC LINE FROM 132KV KALE(T) - WARNA 20KM For redundancy.

13 132KV LINK LINES

(2011-12)

SATARA 1) 2ND CIRCUIT STRINGING FROM 132KV SCDC LINE

FROM LONAND - PHALTAN 55 KM

For redundancy.

14 132KV LINK LINES

(2011-12)

SATARA 1) 2ND CIRCUIT STRINGING FROM 132KV SCDC LINE

FROM 220KV TILAWANI - KURUNDWAD 25 KM

For redundancy.

15 132KV LINK LINES

(2011-12)

SATARA 1) 2ND CIRCUIT STRINGING FROM 132KV SCDC LINE

FROM 132KV AUNDH - DAHIWADI 30KM

For redundancy.

16 220KV LINK LINE

(2012-13)

RATNAGIRI 1) 220 KV NIVALIPHATA TAP ON NEW-KOYNA -FINOLEX -

42 KM

Nivaliphata S/s is presently tapped on New Koyna-

Phinolex line. Hence to provide uninterrupted supply

during planned outages it is necessary to add proposed

line

17 132KV LINK LINE

(2012-13)

SATARA 1) 132 KV WAI-LONAND SECOND CKT STRINGING - 41.86

KM

132kV Wai S/S is fed from 220kV Lonand S/s with S/c

line. Hence to provide uninterrupted supply during

planned outages it is necessary to add proposed line

1 132KV LINK LINE

(2010-11)

KOLHAPUR 1) UPGRADATION OF EXISTING 110KV MUDSHINGI TO

BAPAT CAMP LINE TO 132KV LINE USING SAME ROW.

System strengthining & redundancy.

2 110 KV LINK LINE

(2010-11)

KOLHAPUR 1) LILO ON 110KV CHAMBUKHADI - KALE LINE FOR

BAMBVADE -25 KM

System strengthining & redundancy.

3 220KV LINK LINE

(2011-12)

SATARA 1) 220KV KESURDI TO VANKUSWADI SCDC LINE - 85 KM

WITH BAYS

To have the facility for wind evacuation at Vankuswadi

and nearby Lonand S/s

4 132KV LINK LINE

(2011-12)

KOLHAPUR 1) UPGRADATION OF EXISTING 110KV SCDC LINE FROM

220KV MUDSHINGI - KOTHALI -RADHANAGARI -

KANKAVALI LINE TO 132KV LINE USING SAME ROW.

System strengthining & redundancy.

5 132KV LINK LINE

(2011-12)

KOLHAPUR 1) UPGRADATION OF EXISTING 110KV SC LINE FROM

220KV PEDAMBE - ARAVALI -NIWALI - RATNAGIRI LINE

TO 132KV D/C LINE USING SAME ROW.

System strengthining & redundancy.

6 132KV LINK LINE

(2011-12)

KOLHAPUR 1) UPGRADATION OF EXISTING 110KV SC LINE FROM

220KV MUDSHINGI TO ICHALKARANJI LINE TO 132KV

LINE USING SAME ROW.

System strengthining & redundancy.

7 220KV LINK LINE

(2013-14)

KOLHAPUR 1) CONVERSION OF EXISTING S/C 220KV KARAD TO

PEDAMBE LINE TO PARTLY M/C (UP TO

KOYANANAGAR) AND D/C LINE FROM KOYANANAGR TO

POPHALI AND KOYANANAGAR TO PEDAMBE.

System strengthining & redundancy.

1 110 KV LINK LINE

(2010-11)

KOLHAPUR 1) 220KV KAGAL S/S (5 STAR MIDC.) - 110KV

GOKULSHIRGAON SCDC LINE - 15 KM

Linking to New 220 kV Kagal S/s

2 132 KV LINK LINE

(2012-13)

SANGLI 1) 132KV KAVATHEMAHAKAL - SAVALAJ SCDC LINE - 25KM To have alternate source for Kavathemahakal.

1 220KV LINK LINE

(2011-12)

KARAD 1) 220KV KDPH - VANKUSWADI SCDC LINE -32KM To have evacuation facility af 2x40mw generation at

KDPH

ADDITIONAL LINK LINES FOR NEW S/S TO HAVE ALTERNATE SOURCE

ADDITIONAL LINK LINES

ADDITIONAL LINK LINES FOR S/S WHERE ONLY SINGLE CKT AND SINGLE SOURCE IS AVAILABLE

ADDITIONAL LINK LINES TO MEET DEMAND WITHOUT LOAD SHEDDING AND TO ENSURE RELIABILITY AND QUALITY OF SUPPLY

STRENGTHENING FOR EVACUATION ARRANGEMENT

111

Page 115: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 - W.E.F 01/04/2010

SR

NO.

NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEME

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

KARAD EHV CONSTRUCTION CUM (O&M) ZONE

TOTAL SCOPE OF WORK

1 132 kV KANKAVALI

(2011-12)

Sindhudurg 1)

2)

Add 1 X 25 MVA, 132/33 kV T/F with bay.

4 X 33 kV out lets

Existing Transformer capacity avaible is 1 X 16 MVA.

And the load reached is 10 MVA To avoid loss of supply

in case of outages or interruptions on transformer.

2 132 kV WAI

(2011-12)

Satara 1)

2)

1 X 25 MVA ,220/33 kV T/F with bays.

2 X 33 kV out lets.

Existing Transformer capacity avaible is 1 X 25 MVA. To

avoid loss of supply in case of outages or interruptions on

transformer.

1) Add 1 x 25 MVA, 132/22 KV T/F with bays.

2) 4 x 22 kV outlets

1) Add 1 x 25 MVA, 132-110/22 KV T/F with bays.

2) 4 x 22 kV outlets

1) 1 x 25 MVA, 132-110/33 KV T/F with bays.

2) 4 x 33 kV outlets

3 110 kV SATARA MIDC

(2011-12)

Satara 1)

2)

Add 1 X 25 MVA , 132-110/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in s/s is 2 X 25

MVA. And the load reached is 46 MVA Considering the

maximum load reached on the transformer in the event of

interruptions/outage on any one of the transformer other

transformer should take care of existing load.

1) Add 1 x 25 MVA, 132/22 KV T/F with bays.

2) 4 x 22 kV outlets

1) 2X25MVA, 220/33KV T/FS WITH BAYS

2) 33KV OUTLETS - 6NOS

1 220KV MIRAJ S/S

(2010-11)

SANGLI 1) 1 X ( 200-100) MVA, 220/132-110 KV ICTS WITH BAYS Existing transformer capacity available in S/s

is,220/110kV 3 x 100MVA and the load reached is 258

MVA.The transformer is replaced to meet the anticipated

load growth.

2 220 KV KOLHAPUR-II

(MUDSHINGI) S/S

(2010-11)

KOLHAPUR 1) 1X ( 200-100) MVA, 220/132-110 KV ICTS WITH BAYS Existing transformer capacity available in S/s

is,220/110kV ,1 X 100 MVA and the load reached is 328

MVA.The transformer is replaced to meet the anticipated

load growth.

3 220KV TILAWANI

(2010-11)

kOLHAPUR 1) 1X(100-50)MVA, 220/33-33KV T/F WITH BAYS To cater upcoming load of MSEDCL

4 220KV PETH

(2010-11)

Sangli 1) 1X(50-25)MVA, 220/33KV To cater upcoming load of MSEDCL

5 110 kV ICHALKARANJI-I

(2010-11)

KOLHAPUR 1)

2)

1 X (50-25) MVA MVA, 132-110/33 kV T/F with bays.

2 X 33 kV outlets.

Existing transformer capacity available in s/s is 1 X 10 &

1 X 20 , 1 X 25 MVA. And the load reached is 31 MVA

The transformer is replaced to meet anticipated load

growth.

6 110 kV

KAVATHEMAHAKAL

(2010-11)

Sangli 1)

2)

1 X (50-25) MVA MVA, 132-110/33 kV T/F with bays.

2 X 33 kV outlets.

Existing transformer capacity available in s/s is 2 X 25

MVA. And the load reached is 32 MVA The transformer is

replaced to meet anticipated load growth.

7 110 kV MAYNI

(2010-11)

Satara 1)

2)

1 X (25-7.5) MVA,132-110/22 kV T/F with bays.

4 X 22 kV outlets.

Existing transformer capacity available in S/s is,

15 MVA and the Load reach is 7 MVA. The T/F is

replaced to meet anticipated load growth

8 220KV TILAWANI

(2011-12)

1) 1X(100-50)MVA, 220/33-33KV T/F WITH BAYS To cater upcoming load of MSEDCL

9 220 KV KOLHAPUR-II

(MUDSHINGI) S/S

(2011-12)

KOLHAPUR 1) 1 X ( 200 - 100) MVA, 220/132-110 KV ICT WITH BAYS Existing transformer capacity available in S/s is,

220/110kV, 2 X 200 MVA & 1 x 100 MVA and the load

reached is 353 MVA.The transformer is replaced to meet

the anticipated load growth.

10 220 kV LOTE

PARSHURAM

(2011-12)

Ratnagiri 1)

2)

1 X (50-25) , 220/33 kV T/F with bays.

4 X 33 kV out ets.

Existing transformer capacity available in s/s is 2 X 25

MVA. And the load reached is 40 MVA The transformer is

replaced to meet anticipated load growth.

11 220KV KHAREPATAN

S/S

(2011-12)

SINDHUDURG 1) 1X (100-50) MVA 220/132KV ICT WITH BAYS Existing transformer capacity available in S/s is

220/132kV, 1 x 50MVAand the load reached is 30 MVA

Considering the maximum load reach on the transformer,

in event of interruption/outage on any one of the

transformer other transformer should take care of existing

load so as to avoid load shedding.

132 kV SHIRVAL

(2013-14)

Existing transformer capacity available in S/s is 1 x 25,

132/22 kV and load reach is 14 MVA. To avoid the loss of

supply in case of outages or interruptions of transformers

110KV ARAVALI S/S

(2010-11)

RATNAGIRI For redundancy.2

3 Satara

AUGMENTATION OF S/S BY ADDITION OF ICT/T/F

AUGMENTATION OF S/S BY ADDITION WHERE ONLY SINGLE ICT/T/F IS AVAILABLE

AUGMENTATION OF S/S BY ADDITION TO REDUCE LOADING OF ICT/T/F

1 132-110 kV SATARA

ROAD

(2010-11)

AUGMENTATION OF S/S BY REPLACEMENT OF TRANSFORMER

4

Satara Existing transformer capacity available in S/s is

2 x 20, 132-110/22 kV and load reach is 19 MVA.

Considering the maximum load reached on the

transformer in the event of interruptions/outage on any

one of the transformer other transformer should take care

of existing load

220KV MHAISHAL

(2010-11)

1 SANGLI To reduce loading of 220kv Miraj & 110kV Vishrambag

S/Stn.

INTRODUCTION OF 33KV LEVEL

132 kV LONAND

(2011-12)

Satara Existing transformer capacity available in S/s is 2 x 25,

132/22 kV and load reach is 23 MVA. The T/F is replaced

to meet anticipated load growth

112

Page 116: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 - W.E.F 01/04/2010

SR

NO.

NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEME

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

KARAD EHV CONSTRUCTION CUM (O&M) ZONE

TOTAL SCOPE OF WORK

12 400KV N-KOYNA S/S

(2012-13)

RATNAGIRI 1)

2)

1 X (500-315) MVA, 400/220KV ICT WITH BAYS

220KV BAYS - 02 NOS.

Existing Transformer capacity available is 2 X 315 MVA

and load reached is 473 MVA, Considering the maximum

load reach on the transformer, in event of

intruption/outage on any one of the transformer other

transformer should take care of existing load so as to

avoid load shedding.

13 220 kV MUDSHINGI

(KOLHAPUR-II)

(2012-13)

Kolhapur 1)

2)

2 X (50-25) MVA , 220/33 kV T/F with bays.

4X 33 kV outlets.

Existing transformer capacity available in s/s is 2 X 10

MVA. And the load reached is 12 MVA The transformer is

replaced to meet anticipated load growth.

14 220 kV LOTE

PARSHURAM

(2013-14)

Ratnagiri 1)

2)

1X (50-25) , 220/33 kV T/F with bays.

4 X 33 kV outlets.

Existing transformer capacity available in s/s is 2 X 25

MVA. And the load reached is 40 MVA The transformer is

replaced to meet anticipated load growth.

15 132 kV PHALTAN

(2013-14)

Satara 1)

2)

1 X (50-25) MVA,132/22 kV T/F with bays.

4 X 22 kV outlets.

Existing transformer capacity available in S/s is 2 x 25,

132/22 kV and load reach is 26 MVA. The T/F is replaced

to meet anticipated load growth

16 132 kV WAI

(2014-15)

Satara 1)

2)

1 X(50- 25) MVA ,132/33-22 kV T/F with bays.

2 X 33 kV out lets.

Existing Transformer capacity avaible is 1 X 25 MVA. To

avoid loss of supply in case of outages or interruptions on

transformer.

1 220 KV SAWANTWADI

S/S

(2011-12)

SINDHUDURG 1) 2 X 100 MVA , 220/132 KV ICT WITH BAYS To introduce 132 kV Level to feed the nearby area.

2 220KV PEDAMBE S/S

(2011-12)

Satara 1) 1 X 100 MVA , 220/132-110 KV ICT WITH BAYS To introduce 132 kV Level to feed the nearby area.

3 220KV PEDAMBE S/S

(2012-13)

Satara 1) 1 X 100 MVA , 220/132-110 KV ICT WITH BAYS To introduce 132 kV Level to feed the nearby area.

* COMMISSIONED IN 2009-10 ** 1No. TF COMMISSIONED IN 2009-10

ICT PROPOSED TO INTRODUCE 132 LEVEL.

113

Page 117: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

EHV CC O&M ZONE :

NASIK

114

Page 118: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 - W.E.F 01/04/2010

SR NO NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEME

1) 2X100MVA, 220/132KV ICTS WITH BAYS

2) 220KV NASIK (EKLAHARE )- PIMPALGAON D/C

LINE - 43.72 KM

3) 132KV OUTLETS - 4NOS.

4) 132KV D/C LINE TO RANVAD S/S-17 KMS

5) 132KV D/C LINE TO DINDORI S/S-17 KMS

1) LILO ON 220 KV BHUSAWAL - AMALNER

CKT. I AT 220 KV BHAMBORI - 3 KMS.

2) 2X100MVA, 220/132KV ICT WITH BAYS

3) 2X25MVA, 220/33KV T/F WITH BAY

4) 132KV SCDC LINE FROM 220KV PROPOSED

BHAMBORI TO DHARANGAON S/STN - 28 KM

5) 132KV DC ON MC FROM 220KV PROPOSED

BHAMBORI TO 132KV JALGAON MIDC - 8 KM

7) 33KV OUTLETS - 8 NOS.

1) 2 X 200MVA, 220/132KV ICTS WITH BAYS

2) 2 X 50 MVA, 220/33 KV T/FS WITH BAYS

3) LILO OF 220 KV BABHALESHWAR-CHALISGAON

S/C AT KOPARGAON-10 KM

4) 220 KV BABHALESHWAR-KOPARGAON D/C-20

KM

5) 132 KV D/C LINE TO 132 KV KOPARGAON -10

KM

6) 132 KV SCDC LINE TO YEOLAS/S -25 KM

7) 12 X 33 KV OUTLETS

1) 2 X 25 MVA, 132/33 KV T/FS WITH BAYS

2) 132 KV D/C LINE SUPA - VADJIRE - 25 KM

3) 8 X 33 KV OUTLETS

1) LILO ON 220KV BABHALESHWAR - NASIK D/C

LINE - 10 KMS

2) 2X100MVA, 220/132KV ICT WITH BAYS

3) 2X50MVA, 220/33KV T/FS WITH BAYS

4) 12 X 33KV OUTLETS

5) LILO OF 132 KV EKLAHARE - SINNAR LINE AT

220 KV SINNAR - II - 23.79 KMS

6) 132KV LINE TO SINNAR (MALEGAON) MIDC -10

KMS

1) 132KV D/C LINE FROM 220 KV ALEPHATA -

GHARGAON - 33.46KM

2) 2X25 MVA, 132/33KV T/F WITH BAYS

3) 33KV OUTLETS-8 NOS

1 132 KV LINK LINE

( 2008 - 09)

AHMEDNAGAR 1) 132KV YEOLA - KOPERGAON SCDC LINE - 25 KM 132kV Yeola S/S is fed from 132kV Manmad S/s

with S/c line. Hence to provide uninterrupted

supply during planned outages it is necessary to

add proposed line

2 132 KV LINK LINE

( 2008 - 09)

NASIK 1) 132 KV SAKRI - VISARWADI D/C LINE - 40 KMS

WITH BAYS

132kV Sakri S/S is fed from 132kV Dhule S/s with

S/c line. Hence to provide uninterrupted supply

during planned outages it is necessary to add

proposed line

3 132 KV LINK LINE

( 2008 - 09)

NASIK 132KV NAMPUR - MALEGAON SCDC LINE-30 KM 132kV Nampur S/S is fed from220/132kV

Malegaon S/s with S/c line. Hence to provide

uninterrupted supply during planned outages it is

necessary to add proposed line

4 132 KV LINK LINE

( 2008 - 09)

NASIK 132KV MALEGAON - MANMAD D/C LINE-34 KM 132kV Manmad S/S is fed from220kV Malegaon

S/s with S/c line. Hence to provide uninterrupted

supply during planned outages it is necessary to

add proposed line

SUBSTATION SCHEMES

TOTAL SCOPE OF WORK

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

NASIK EHV CONSTRUCTION CUM (O&M) ZONE

1 220KV PIMPALGAON

(RANWAD)

(2009-10)

NASIK Present recorded peak load on Ranwad-132kV,

Lasalgaon-132kV, Chandwad-132kV are 60MW,

45MW, 15MW respectively. It is anticipated by the

year 2009-10 the load will reach to about 150MW.

Hence it is necessary to go in for 220kV sub-

station at Ranwad.

2 220KV BHAMBORI

(JALGAON)

(2009-10)

JALGAON It is necessary to go in for 220kV sub-station at

Bhambori. To improve voltage profile of the area

and to meet the demand.

3 220 KV KOPERGAON S/S

(2009-10)

AHMEDNAGAR Present recorded peak load on Vaijapur-132kV,

Yeola-132kV and Kopargaon-132kV S/S are

30MW, 40MW and 40MW respectively. It is

anticipated by the year 2009-10 the load will reach

to about 135MW. Hence it is necessary to go in

for new 220kV sub-station at Kopergaon

4 132 KV VADJIRE S/S

(2009-10)

AHMEDNAGAR Present recorded peak load on Kedgaon-132kV is

70MW. It is anticipated by the year 2009-10 the

load will reach to about 85MW. Hence it is

necessary to go in for new 132kV sub-station at

Vadjire. The new substation Vadjire-132kV S/S is

proposed in year 2009-10 for reducing loading on

Kedgaon-132kV.

5 220KV SINNAR II S/S

(2009-10)

NASIK Present recorded peak load on Sinnar-132kV is

90MW. It is anticipated by the year 2009-10 the

load will reach to about 110MW. Hence it is

necessary to go in for 220kV sub-station at

Sinnar. By the commissioning of this substation,

voltage profile will improve to 0.97pu from 0.93pu.

6 132KV GHARGAON S/S

(2009-10)

AHMEDNAGAR Ghargaon-132kV S/S is considered in year 2009-

10 for reducing the loading of Rahuri-132kV S/S &

bhenda-132kV S/S. & to meet the increased load

in the area.

ADDITIONAL LINK LINES

ADDITIONAL LINK LINES FOR S/S WHERE ONLY SINGLE CKT AND SINGLE SOURCE IS AVAILABLE

115

Page 119: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 - W.E.F 01/04/2010

SR NO NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEMETOTAL SCOPE OF WORK

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

NASIK EHV CONSTRUCTION CUM (O&M) ZONE

5 220KV LINK LINE

(2009-10)

NASIK 1) 220 KV SATANA - MALEGAON SCDC LINE - 30

KMS

220kV Satana S/S is fed from 220kV Malegaon

S/s with S/c line and this line is also critically

loaded to an extent of 210 MW. Hence to provide

uninterrupted supply during planned outages &

Reduce the loading of line it is necessary to add

proposed line

6 132KV LINK LINE

(2009-10)

AHMEDNAGAR 1) 2ND CIRCUIT STRINGING OF 132 KV AKOLE-

SANGAMNER - 20 KM.

132kV Sangamner S/S is fed from 220kV

Babhaleshwar S/s with S/c line and this line is

also critically loaded to an extent of 71 MW.

Hence to provide uninterrupted supply during

planned outages & Reduce the loading of line it is

necessary to add proposed line

1 220 KV LINK LINE

(2009-10)

NASIK 1) 220KV DHULE - MALEGAON D/C LINE - 40 KMS Since the existing 220kV Dhule-Malegaon S/c line

is loaded to an extent of 162 MW during Non-

Coinsident peak condition. It is anticipated the

load will reach to about critical value by the year

2011-12. Hence it is necessary to propose

additional line to meet additional load growth and

contingency.

2 132KV LINK LINE

(2009-10)

NASIK 1) 132 KV AMALNER - NARDANE SCDC LINE - 35

KMS

Since the existing 132kV Dhule-Nardane S/c line

is getting loaded to an extent of 66 MW during

Non-coinsident peak condition. It is anticipated the

load will reach to about critical value by the year

2011-12. Hence it is suggested to add proposed

line to reduce the loading of existing line and to

meet additional load growth and contingency.

1) ADDL. 1X 50 MVA, 220/33 KV T/F WITH BAYS

2) 6 X 33 KV OUTLETS

1) ADDL. 1 X 200 MVA, 220/132 KV ICT WITH BAYS

2) 132 KV BAYS - 2 NOS.

1) ADDL. 1 X 100 MVA, 220/132 KV ICT WITH BAY

2) 132 KV BAYS - 2 NOS.

1) 1 X 25 MVA , 220/33KV T/F WITH BAYS

2) 33 KV OUTLETS - 4 NOS.

1) 1X100MVA, 220/132KV ICT WITH BAYS

2) 132 KV BAYS - 2 NOS.

1) 1 X 25 MVA, 132/33 KV T/F WITH BAYS

2) 33 KV OUTLETS - 4 NOS.

1) ADDL. 1X50 MVA, 132/33KV T/F WITH BAYS

2) 6 X 33KV OUTLETS

1) ADDL. 1 X 25 MVA, 132/33 KV T/F WITH BAYS

2) 33 KV OUTLETS - 4 NOS.

1) ADDL. 1 X 25 MVA, 132/33 KV T/F WITH BAYS

2) 33 KV OUTLETS - 4 NOS.

1) ADDL. 1X25MVA, 132/33KV T/F WITH BAYS

2) 33 KV OUTLETS - 4 NOS.

1) 1 X 25 MVA, 132/33 KV T/F WITH BAYS

2) 33 KV OUTLETS - 4 NOS.

ADDITIONAL LINK LINES TO MEET DEMAND WITHOUT LOAD SHEDDING AND TO ENSURE RELIABILITY AND QUALITY OF SUPPLY

AUGMENTATION OF S/S BY ADDITION OF T/F

AUGMENTATION OF S/S BY ADDITION WHERE ONLY SINGLE TRANSFORMER IS AVAILABLE

1 220 KV MALEGAON - II

S/S ( 2008 - 09 )

NASIK To avoid loss of supply in case of outages or

interruptions on any one transformer

2 220 KV SATANA

( 2008 - 09 )

NASIK To avoid loss of supply in case of outages or

interruptions on any one transformer

3 220 KV SHAHADA

( 2008 - 09 )

NANDURBAR To avoid loss of supply in case of outages or

interruptions on any one transformer

4 220 KV DHULE S/S *

( 2008 - 09 )

DHULE To avoid loss of supply in case of outages or

interruptions on any one transformer

5 220KV DONDAICHA S/S*

( 2008 - 09 )

DHULE To avoid loss of supply in case of outages or

interruptions on any one transformer

6 132 KV PIMPERKHED S/S

( 2008 - 09 )

NASIK To avoid loss of supply in case of outages or

interruptions on any one transformer

7 132KV JALGAON (MIDC)

S/S

( 2008 - 09 )

JALGAON To avoid loss of supply in case of outages or

interruptions on any one transformer

8 132 KV BODWAD S/S (

2008 - 09 )

JALGAON To avoid loss of supply in case of outages or

interruptions on any one transformer

9 132 KV PAROLA S/S (

2008 - 09 )

JALGAON To avoid loss of supply in case of outages or

interruptions on any one transformer

10 132 KV NARDANE S/S (

2008 - 09 )

DHULE To avoid loss of supply in case of outages or

interruptions on any one transformer

11 132 KV NIMBHORA S/S

( 2008 - 09 )

JALGAON Existing transformer capacity available in S/s is,

132/33 - 1 x 25 - 16

To avoid loss of supply in case of outages or

interruptions on any one transformer

116

Page 120: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 - W.E.F 01/04/2010

SR NO NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEMETOTAL SCOPE OF WORK

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

NASIK EHV CONSTRUCTION CUM (O&M) ZONE

12 220 KV NASIK - II S/S

(RAYMOND)*

( 2008 - 09 )

NASIK 1)

2)

ADDL. 1 X 200 MVA, 220/132 KV ICT WITH BAYS

132 KV BAYS - 2 NOS.

Existing transformer capacity available in S/s is,

220/132 - 1 x 200 - 152

Considering the maximum load reach on the

transformer, in event of interruption/outage on any

one of the transformer other transformer should

take care of existing load so as to avoid load

shedding.

13 400 KV BHUSAWAL

S/S(2009-10)

JALGAON 1)

2)

1 X 315 MVA, 400/220 KV ICT WITH BAYS

220 KV BAYS - 2 NOS.

Existing Transformer capacity available is 400/220

kV, 1 X 315 MVA and load reached is 198 MVA,

Considering the maximum load reach on the

transformer, in event of intruption/outage on any

one of the transformer other transformer should

take care of existing load so as to avoid load

shedding.

14 AHEMADNAGAR

(2009-10)

AHMEDNAGAR 1)

2)

ADDL. 1 X 100 MVA, 220/132 kV T/F with bays.

132 KV BAYS - 2 NOS.

The existing Transformer capacity available is

220/132 kV 1X100MVA and the load reached is

64 MVA. To avoid loss of supply in case of

outages or interruptions on any one transformer

other transformer should take care of existing load

so as to avoid load shedding.

15 220 kV DHULE-II *

(2009-10)

Dhule 1)

2)

Add 1 X 25 MVA, 220/33 kV T/F with bay.

4 X 33 kV out lets

Existing Transformer capacity avaible is 1 X 25

MVA. To avoid loss of supply in case of outages

or interruptions on transformer.

1) ADDL. 2X 25 MVA, 220/33 KV T/FS WITH BAYS

2) 33 KV OUTLETS - 8 NOS.

1) ADDL. 2 X 25 MVA, 132/33 KV T/FS WITH BAYS

2) 8 X 33 KV OUTLETS

1) 1X 50 MVA, 132/33 KV T/F WITH BAYS

2) 6 X 33 KV OUTLETS

1) ADDL. 1X25MVA,132/33KV TF'S WITH BAYS

2) 33KV OUT LET-04 nos

5 400 KV DHULE S/S

(2009-10)

DHULE 1)

2)

1 X 500 MVA, 400/220KV ICTS WITH BAYS

220 KV BAYS - 4 NOS.

Existing Transformer capacity available is 400/220

kV, 2 X 315 MVA and load reached is 503 MVA,

Considering the maximum load reach on the

transformer, in event of intruption/outage on any

one of the transformer other transformer should

take care of existing load so as to avoid load

shedding.

6 400 KV BABHALESHWAR

S/S

(2009-10)

AHMEDNAGAR 1)

2)

1 X 500 MVA, 400/220KV ICTS WITH BAYS

220 KV BAYS - 4 NOS.

Existing Transformer capacity available is 400/220

kV, 2 X 315 MVA and load reached is 598 MVA,

Considering the maximum load reach on the

transformer, in event of intruption/outage on any

one of the transformer other transformer should

take care of existing load so as to avoid load

shedding.

7 220KV EKLAHARE GCR*

(2009-10)

NASIK 1)

2)

ADDL. 1X150MVA,220/132KV ICT WITH BAYS

132 KV BAYS - 3 NOS.

Existing Transformer capacity available is 220/132

kV, 2X 150 and 1 X 200 MVA and load reached is

290 MVA. Considering the maximum load reach

on the transformer, in event of intruption/outage

on any one of the transformer other transformer

should take care of existing load so as to avoid

load shedding.

AUGMENTATION OF S/S BY ADDITION TO REDUCE LOADING OF TRANSFORMER

1 220 KV AHMEDNAGAR

S/S(2008-09)

AHMEDNAGAR Newly established LV level (33 kV) to feed the

nearby area at proper voltage

2 132 KV OZAR S/S

(2008-09)

NASIK To eliminate 11 kV level from the existing

S/s.33KV is introduced.

NASIK Existing transformer capacity available in S/s is,

132/33 - 2 x 50MVA - LOAD IS 78 MVA.

Considering the maximum load reach on the

transformer, in event of interruption/outage on any

one of the transformer other transformer should

take care of existing load so as to avoid load

shedding.

4 132KV VARANGAON NASIK Consedering the maximum load reach on the

transformer, in event of interruption/outage on any

one of the transformer other transformer should

take care of existing load so as to avoid load

shedding.

3 132 KV MALEGAON S/S

(2008-09)

117

Page 121: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 - W.E.F 01/04/2010

SR NO NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEMETOTAL SCOPE OF WORK

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

NASIK EHV CONSTRUCTION CUM (O&M) ZONE

8 220 KV MALEGAON S/S

(2009-10)

NASIK 1)

2)

1 X 200 MVA, 220/132 KV ICTS WITH BAYS

132 KV BAYS - 4 NOS.

Existing Transformer capacity available is 220/132

kV, 2 X 100 MVA and load reached is 185

MVA.The transformer is replaced to meet the

anticipated load growth. Considering the

maximum load reach on the transformer, in event

of intruption/outage on any one of the transformer

other transformer should take care of existing load

so as to avoid load shedding.

9 220KV DHULE S/S

(2009-10)

DHULE 1)

2)

1X 150 MVA, 220/132KV WITH BAYS

132 KV BAYS - 3 NOS.

Existing Transformer capacity available is 220/132

kV, 2 X150 MVA and load reached is 201

MVA.The transformer is replaced to meet the

anticipated load growth.

10 132 kV SATANA

(2009-10)

Nasik 1)

2)

Add 1 X 25 MVA , 132/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in S/s is 2

X 25 MVA and load is 27 MVA. Considering the

maximum load reached on the transformer in the

event of interruptions/outage on any one of the

transformer other transformer should take care of

existing load

11 132 kV DHARANGAON

(2009-10)

Jalgaon 1)

2)

Add 1 X 25 MVA , 132/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in s/s is 1

X 25 & 1 X 16 MVA. And the load reached is 20

MVA Considering the maximum load reached on

the transformer in the event of

interruptions/outage on any one of the transformer

other transformer should take care of existing load

12 132 kV RAHURI

(2009-10)

Ahmednagar 1)

2)

Add 1 X 25 MVA , 132/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in s/s is 1

X 50 & 1 X 25 MVA. And the load reached is 37

MVA Considering the maximum load reached on

the transformer in the event of

interruptions/outage on any one of the transformer

other transformer should take care of existing load

13 132 kV AMBAD NASIK

(2009-10)

Nasik 1)

2)

Add 1 X 25 MVA , 132/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in s/s is 2

X 25 MVA. And the load reached is 42 MVA

TConsidering the maximum load reached on the

transformer in the event of interruptions/outage on

any one of the transformer other transformer

should take care of existing load

14 132 kV AHMEDNAGAR

MIDC

(2009-10)

Ahmednagar 1)

2)

Add 1 X 25 MVA, 132/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in S/s is 2

X 25 MVA and load is 26 MVA. Considering the

maximum load reached on the transformer in the

event of interruptions/outage on any one of the

transformer other transformer should take care of

existing load

15 132 kV AHMEDNAGAR

(Kedgaon)

(2009-10)

Ahmednagar 1)

2)

Add 1 X 50 MVA, 132/33 kV T/F with bays

6 X 33 kV out lets.

Existing transformer capacity available in S/s is 1

X 50 &1 X 25 MVA and load is 39 MVA.

Considering the maximum load reached on the

transformer in the event of interruptions/outage on

any one of the transformer other transformer

should take care of existing load

16 132 kV AKOLE

(2009-10)

Ahmednagar 1)

2)

Add 1 X 25 MVA, 132/33 kV T/F with bay.

2) 4 X 33 kV out lets

Existing transformer capacity available in S/s is 1

X 50 MVA and load is 32 MVA. Considering the

maximum load reached on the transformer in the

event of interruptions/outage on any one of the

transformer other transformer should take care of

existing load

17 132 kV CHALISGAON-I

(2009-10)

Jalgaon 1)

2)

Add 1 X 25 MVA, 132/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in S/s is 2

X 25 MVA and load is 37 MVA. Considering the

maximum load reached on the transformer in the

event of interruptions/outage on any one of the

transformer other transformer should take care of

existing load

118

Page 122: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 - W.E.F 01/04/2010

SR NO NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEMETOTAL SCOPE OF WORK

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

NASIK EHV CONSTRUCTION CUM (O&M) ZONE

18 132 kV CHOPDA

(2009-10)

Jalgaon 1)

2)

1 X 50 MVA, 132/33 kV T/F with bays.

6 X 33 kV out lets.

Existing transformer capacity available in S/s is 1

X 50 & 1X 25 MVA and load is 63 MVA.

Considering the maximum load reached on the

transformer in the event of interruptions/outage on

any one of the transformer other transformer

should take care of existing load

19 132 kV DHULE-I *

(2009-10)

Dhule 1)

2)

Add 1 X 25 MVA, 132/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in S/s is 1

X 25, 1 X 50 MVA and load is 44 MVA.

Considering the maximum load reached on the

transformer in the event of interruptions/outage on

any one of the transformer other transformer

should take care of existing load.

20 132 kV SHIRPUR

(2009-10)

Nandurbar 1)

2)

Add1 X 50 MVA , 132/33 kV T/F with bays.

6 X 33 kV out lets.

Existing transformer capacity available in S/s is 1

X 50 & 1 X 25 MVA and load is 49 MVA.

Considering the maximum load reached on the

transformer in the event of interruptions/outage on

any one of the transformer other transformer

should take care of existing load

21 132 kV NANDURBAR (2009-

10)

Nandurbar 1)

2)

Add 1 X 25 MVA, 132/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in S/s is 1

X 25, 1 X 50 MVA and load is 44 MVA.

Considering the maximum load reached on the

transformer in the event of interruptions/outage on

any one of the transformer other transformer

should take care of existing load

22 132 kV TALODA

(2009-10)

Nandurbar 1)

2)

Add 1 X 25 MVA, 132/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in S/s is 2

X 25MVA and load is 34 MVA. Considering the

maximum load reached on the transformer in the

event of interruptions/outage on any one of the

transformer other transformer should take care of

existing load

23 132 kV DEEPNAGAR (2009-

10)

Jalgaon 1)

2)

Add 1 X 25 MVA, 132/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in S/s is 1

X 25, 1 X 16 MVA and load is 28 MVA.

Considering the maximum load reached on the

transformer in the event of interruptions/outage on

any one of the transformer other transformer

should take care of existing load

24 132 kV DINDORI

(2009-10)

Nasik 1)

2)

Add1 X 50 MVA , 132/33 kV T/F with bays.

6 X 33 kV out lets.

Existing transformer capacity available in S/s is 1

X 50 & 1 X 25 MVA and load is 49 MVA.

Considering the maximum load reached on the

transformer in the event of interruptions/outage on

any one of the transformer other transformer

should take care of existing load

25 132 kV KARJAT

(2009-10)

Ahmednagar 1)

2)

Add 1 X 25 MVA, 132/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in S/s is 2

X 25 MVA and load is 26 MVA. Considering the

maximum load reached on the transformer in the

event of interruptions/outage on any one of the

transformer other transformer should take care of

existing load

26 132 kV KOPERGAON

(2009-10)

Ahmednagar 1)

2)

Add 1 X 25 MVA, 132/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in S/s is 2

X 25 MVA and load is 34 MVA. Considering the

maximum load reached on the transformer in the

event of interruptions/outage on any one of the

transformer other transformer should take care of

existing load

27 132 kV LASALGAON

(2009-10)

Nasik 1)

2)

Add 1 X 25 MVA , 132/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in S/s is 2

X 25 MVA and load is 25 MVA. Considering the

maximum load reached on the transformer in the

event of interruptions/outage on any one of the

transformer other transformer should take care of

existing load

119

Page 123: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 - W.E.F 01/04/2010

SR NO NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEMETOTAL SCOPE OF WORK

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

NASIK EHV CONSTRUCTION CUM (O&M) ZONE

28 132 kV MALEGAON-I

(2009-10)

Nasik 1)

2)

Add 1 X 50 MVA , 132/33 kV T/F with bays.

6 X 33 kV out lets.

Existing transformer capacity available in S/s is 2

X 50 MVA and load is 88 MVA. Considering the

maximum load reached on the transformer in the

event of interruptions/outage on any one of the

transformer other transformer should take care of

existing load

29 132 kV MANMAD

(2009-10)

Nasik 1)

2)

Add 1 X 25 MVA , 132/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in S/s is 1

X 25 & 1 X 50 MVA and load is 33 MVA.

Considering the maximum load reached on the

transformer in the event of interruptions/outage on

any one of the transformer other transformer

should take care of existing load

30 132 kV NAMPUR

(2009-10)

Nasik 1)

2)

Add 1 X 25 MVA , 132/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in S/s is 2

X 25 MVA and load is 24 MVA. Considering the

maximum load reached on the transformer in the

event of interruptions/outage on any one of the

transformer other transformer should take care of

existing load

31 132 kV NEWASA

(2009-10)

Ahmednagar 1)

2)

Add 2 X 25 MVA, 132/33 kV T/F with bays.

8 X 33 kV out lets.

Existing transformer capacity available in S/s is 1

X 50 &1 X 25 MVA and load is 40 MVA.

Considering the maximum load reached on the

transformer in the event of interruptions/outage on

any one of the transformer other transformer

should take care of existing load

32 132 kV SATPUR MIDC

(2009-10)

Nasik 1)

2)

Add 1 X 25 MVA , 132/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in S/s is 2

X 25 MVA and load is 22 MVA. Considerin the

maximum load reached on the transformer in the

event of interruptions/outage on any one of the

transformer other transformer should take care of

existing load

33 132 kV SHAHADA

(2009-10)

Dhule 1)

2)

Add 1 X 50 MVA , 132/33 kV T/F with bays.

6 X 33 kV out lets.

Existing transformer capacity available in S/s is 1

X 25, 1 X 50 MVA and load is 50 MVA.

Considerin the maximum load reached on the

transformer in the event of interruptions/outage on

any one of the transformer other transformer

should take care of existing load

34 132 kV SHEVGAON

(2009-10)

Ahmednagar 1)

2)

Add 1 X 25 MVA, 132/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in S/s is 2

X 25 MVA and load is 28 MVA. Considering the

maximum load reached on the transformer in the

event of interruptions/outage on any one of the

transformer other transformer should take care of

existing load

35 132 kV SUPA

(2009-10)

Ahmednagar 1)

2)

Add 1 X 25 MVA, 132/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in S/s is 2

X 25 MVA and load is 26 MVA. Considering the

maximum load reached on the transformer in the

event of interruptions/outage on any one of the

transformer other transformer should take care of

existing load

36 132 kV TAKLI

(2009-10)

Nasik 1)

2)

Add 1 X 25 MVA , 132/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in S/s is 2

X 25 MVA and load is 34 MVA. Considering the

maximum load reached on the transformer in the

event of interruptions/outage on any one of the

transformer other transformer should take care of

existing load

37 132 kV YAVAL

(2009-10)

Jalgaon 1)

2)

Add 1 X 25 MVA, 132/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in S/s is 1

X 25 & 1 X 16 MVA and load is 31 MVA.

Considering the maximum load reached on the

transformer in the event of interruptions/outage on

any one of the transformer other transformer

should take care of existing load

120

Page 124: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 - W.E.F 01/04/2010

SR NO NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEMETOTAL SCOPE OF WORK

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

NASIK EHV CONSTRUCTION CUM (O&M) ZONE

38 132 kV PACHORA

(2009-10)

Jalgaon 1)

2)

Add 1 X 25 MVA, 132/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in S/s is 1

X 10.8 MVA and load is 10 MVA. Considering the

maximum load reached on the transformer in the

event of interruptions/outage on any one of the

transformer other transformer should take care of

existing load

39 132 kV DHARANGAON

(2009-10)

Jalgaon 1)

2)

Add 1 X 25 MVA 132/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in s/s is 1

X 25 & 1 X 16 MVA. And the load reached is 20

MVA Considering the maximum load reached on

the transformer in the event of

interruptions/outage on any one of the transformer

other transformer should take care of existing load

40 220 kV DONDAICHA (2009-

10)

Dhule 1)

2)

Add 1 X 25 MVA 220/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in s/s is 1

X 25 MVA. And the load reached is 20 MVA

Considering the maximum load reached on the

transformer in the event of interruptions/outage on

any one of the transformer other transformer

should take care of existing load

41 220 kV BABHALESHWAR

(2009-10)

Ahmednagar 1)

2)

Add 1 X 50 MVA, 220/33 kV T/F with bays.

6 X 33 kV out lets.

Existing transformer capacity available in S/s is 2

X 50 MVA and load is 45 MVA. Considering the

maximum load reached on the transformer in the

event of interruptions/outage on any one of the

transformer other transformer should take care of

existing load

121

Page 125: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 - W.E.F 01/04/2010

SR NO NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEMETOTAL SCOPE OF WORK

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

NASIK EHV CONSTRUCTION CUM (O&M) ZONE

1) 1 X ( 50-25) MVA, 132/33 KV T/FS

2) 33 KV OUTLETS - 2 NOS.

1) 1 X ( 25 - 16) MVA, 132/33 KV T/FS

2) 33 KV OUTLETS - 2 NOS.

1) REP.1 X ( 50-25) MVA, 132/33 KV T/FS

2) 33 KV OUTLETS - 2 NOS.

4 132 KV AKOLE S/S

(2008 - 09 )

AHMEDNAGAR 1)

2)

REP. 1 X ( 50-25) MVA, 132/33 KV T/FS

33 KV OUTLETS - 2 NOS.

Existing transformer capacity available in S/s

is,132/33 - 2 x 25 MVA and load is 30

MVA.Considering the maximum load reach on the

transformer, in event of interruption/outage on any

one of the transformer other transformer should

take care of existing load so as to avoid load

shedding.

1) REP. 1 X ( 50-25) MVA, 132/33 KV T/FS

2) 33 KV OUTLETS - 2 NOS.

1) REP.1 X ( 50-25) MVA, 132/33 KV T/FS

2) 33 KV OUTLETS - 2 NOS.

1) 2 X (200-100) MVA, 220/132 KV ICTS

2) 4 X 132KV BAYS

1) 2 X (200-100)MVA 220/132KV ICTS

2) 2 X ( 50 - 25) MVA, 132/33 KV T/FS

3) 2 X 33KV OUTLETS

4) 2 X 132 KV OUTLETS

AUGMENTATION OF S/S BY REPLACEMENT OF TRANSFORMER

1 132 KV PACHORA S/S

(2008 - 09 )

JALGAON Existing transformer capacity available in S/s

is,132/33 - 2 x 25 MVA and load is 44

MVA.Considering the maximum load reach on the

transformer, in event of interruption/outage on any

one of the transformer other transformer should

take care of existing load so as to avoid load

shedding.

2 132 KV DHARANGAON

S/S

(2008 - 09 )

JALGAON Existing transformer capacity available in S/s

is,132/33 - 2 x 16 MVA and load is 28

MVA.Considering the maximum load reach on the

transformer, in event of interruption/outage on any

one of the transformer other transformer should

take care of existing load so as to avoid load

shedding.

3 132 KV DHULE S/S*

(2008 - 09 )

DHULE Existing transformer capacity available in S/s

is,132/33 - 2 x 25 MVA and load is 50

MVA.Considering the maximum load reach on the

transformer, in event of interruption/outage on any

one of the transformer other transformer should

take care of existing load so as to avoid load

shedding.

5 132 KV SHRIGONDA S/S*

(2008 - 09 )

AHMEDNAGAR Existing transformer capacity available in S/s

is,132/33 - 2 x 25 MVA and load is 20

MVA.Considering the maximum load reach on the

transformer, in event of interruption/outage on any

one of the transformer other transformer should

take care of existing load so as to avoid load

shedding.

6 132 KV SANGAMNER S/S

(2008 - 09 )

AHMEDNAGAR Existing transformer capacity available in S/s

is,132/33 - 1 x 25 MVA and load is 24 MVA,

132/33 - 1 x 20 MVA and load is 19.66

MVA.Considering the maximum load reach on the

transformer, in event of interruption/outage on any

one of the transformer other transformer should

take care of existing load so as to avoid load

shedding.

7 220 KV MALEGAON - II

S/S

(2008 - 09 )

NASIK Existing transformer capacity available in S/s

is,220/132KV - 2 x 100 MVA and load is 160

MVA. Considering the maximum load reach on the

transformer, in event of interruption/outage on any

one of the transformer other transformer should

take care of existing load so as to avoid load

shedding.

8 220 & 132KV

CHALISGAON S/S

(2008 - 09 )

JALGAON Existing transformer capacity available in S/s

is,220/132 KV - 1 x 150 MVA and load is 119

MVA, 220/100 KV - 1 x 100 MVA and load is 79

MVA. 132/33 KV - 2 x 25 MVA and load is 40

MVA. Considering the maximum load reach on the

transformer, in event of interruption/outage on any

one of the transformer other transformer should

take care of existing load so as to avoid load

shedding.

122

Page 126: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 - W.E.F 01/04/2010

SR NO NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEMETOTAL SCOPE OF WORK

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

NASIK EHV CONSTRUCTION CUM (O&M) ZONE

1) REP. (25 -16)MVA, 132/33KV T/F

2) 2 X 33KV OUTLETS

1) 1 X ( 50-25) MVA, 132/33 KV T/F

2) 33 KV OUTLETS - 2 NOS.

1) 1 X (25-16) MVA, 132/33 KV T/F

2) 33 KV OUTLETS - 2 NOS.

1) 2 X (50-25/10) MVA, 132/33 KV T/F

2) 33 KV OUTLETS - 6 NOS.

1) REP. 2 X ( 50-25) MVA, 132/33 KV T/FS

2) 33 KV OUTLETS - 4 NOS.

14 220 KV CHALISGAON S/S

(2009-10)

JALGAON 1)

2)

1 X (200-100)MVA 220/132 KV ICTS

132 BAYS - 2 NOS.

Existing Transformer capacity available is 220/132

kV, 2 X 100 MVA and load reached is 141 MVA,

The transformer is replaced to meet the

anticipated load growth.

15 220 KV BHUSAWAL

(2009-10)

JALGAON 1)

2)

1X(200-100)MVA, 220/132KV ICT

132 KV BAYS - 2 NOS.

Existing Transformer capacity available is 220/132

kV, 2 X 100 MVA and load reached is 102

MVA,The transformer is replaced to meet the

anticipated load growth.

16 220KV BABHALESHWAR

S/S

(2009-10)

AHMEDNAGAR 1)

2)

1X(200-100)MVA, 220/132KV

132 KV BAYS - 2 NOS.

Existing transformer capacity available in S/s

is,220/132kV, 1 x 200 and 1 X 100 MVA and the

load reached is 115 MVA and 110 MVA

respectively.Considering the maximum load reach

on the transformer, in event of interruption/outage

on any one of the transformer other transformer

should take care of existing load so as to avoid

load shedding.

17 132 kV IGATPURI

(2009-10)

Nasik 1)

2)

Add 2 X (25-12.5) , 132/25 kV T/F

4 X 33 kV out lets.

Existing transformer capacity available in s/s is 2

X 12.5 MVA. And the load reached is 15 MVA The

transformer is replaced to meet anticipated load

growth..

18 132 kV AMALNER

(2009-10)

Jalgaon 1)

2)

Add 2X (50-12.5) MVA , 132/33 kV T/F

6 X 33 kV out lets.

Existing transformer capacity available in s/s is 2

X 12.5 MVA. And the load reached is 15 MVA The

transformer is replaced to meet anticipated load

growth..

19 132 kV DEEPNAGAR (2009-

10)

Jalgaon 1)

2)

1 X (20-12.5) MVA, 132/25 kV T/F

25 KV BAYS - 2 NOS.

Existing transformer capacity available in s/s is 1

X 12.5 & 1 X 20 MVA. And the load reached is 28

MVA The transformer is replaced to meet

anticipated load growth..

9 132KV MALEGAON

( MIDC) S/S

(2008 - 09 )

NASIK Existing transformer capacity available in S/s

is,132/33 KV - 2 x 25 MVA and load is 40.52

MVA, 132/33 KV - 1 x 16 MVA and load is 9.76

MVA. Considering the maximum load reach on the

transformer, in event of interruption/outage on any

one of the transformer other transformer should

take care of existing load so as to avoid load

shedding.

10 132 KV NANDURBAR S/S*

(2008 - 09 )

NANDURBAR Existing transformer capacity available in S/s

is,132/33 KV - 2 x 25 MVA and load is 30 MVA.

Considering the maximum load reach on the

transformer, in event of interruption/outage on any

one of the transformer other transformer should

take care of existing load so as to avoid load

shedding.

11 132 KV DEEPNAGAR S/S (

BHUSAWAL)

(2008 - 09 )

JALGAON Existing transformer capacity available in S/s

is,132/33 KV - 1 x 25 MVA and load is 17 MVA,

132/33 KV - 1 x 16 MVA and load is 12

MVA.Considering the maximum load reach on the

transformer, in event of interruption/outage on any

one of the transformer other transformer should

take care of existing load so as to avoid load

shedding.

12 132 KV RAVER S/S**

(2008 - 09 )

JALGAON Existing transformer capacity available in S/s

is,132/33 KV - 1 x 25 MVA and load is 15 MVA,

132/33 KV - 1 x 10 MVA and load is 9

MVA.Considering the maximum load reach on the

transformer, in event of interruption/outage on any

one of the transformer other transformer should

take care of existing load so as to avoid load

shedding.

13 132 KV JALGAON S/S*

(2008 - 09 )

JALGAON Existing transformer capacity available in S/s

is,132/33 KV - 1 x 50 MVA and load is 32 MVA,

132/33 KV - 2 x 25 MVA and load is 29

MVA.Considering the maximum load reach on the

transformer, in event of interruption/outage on any

one of the transformer other transformer should

take care of existing load so as to avoid load

shedding.

123

Page 127: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 - W.E.F 01/04/2010

SR NO NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEMETOTAL SCOPE OF WORK

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

NASIK EHV CONSTRUCTION CUM (O&M) ZONE

20 220 kV NASIK OCR

(2009-10)

Nasik 1)

2)

Add 1X (50-25) MVA, 132/33 kV T/F

2 nos. of 33 kV outlets

Existing transformer capacity available in s/s is 3

X 25 MVA. And the load reached is 43 MVA The

transformer is replaced to meet anticipated load

growth..

21 132 kV JALGAON ( Old)

(2009-10)

Jalgaon 1)

2)

1 X (50 -25 ) 132/33 kV T/F.

2 X 33 kV out lets.

Existing transformer capacity available in S/s is 1

X 50, 1 X 25 MVA and load is 42 MVA. The

transformer is replaced to meet anticipated load

growth.

22 132 kV SAVDA

(2009-10)

Jalgaon 1)

2)

1 X (50 -20 ) 132/33 kV T/F

2 X 33 kV out lets.

Existing transformer capacity available in S/s is 3

X 20 MVA and load is 55 MVA. The transformer

is replaced to meet anticipated load growth.

23 132 kV SATPUR*

(2009-10)

Nasik 1)

2)

1 X (50 -25 ) 132/33 kV T/F.

2 X 33 kV out lets.

Existing transformer capacity available in S/s is 1

X 50, 1 X 25 MVA and load is 38 MVA. The

transformer is replaced to meet anticipated load

growth.

24 132 kV SINNAR ( Old)

(2009-10)

Nasik 1)

2)

1 X (50 -25 ) 132/33 kV T/F

2 X 33 kV out lets.

Existing transformer capacity available in S/s is 1

X 50, 1 X 25 MVA and load is 36 MVA. The

transformer is replaced to meet anticipated load

growth.

124

Page 128: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 - W.E.F 01/04/2010

SR NO NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEMETOTAL SCOPE OF WORK

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

NASIK EHV CONSTRUCTION CUM (O&M) ZONE

1) 220KV MALEGAON - KALWAN D/C LINE - 48.56

KMS WITH BAYS2) 2X100MVA, 220/132KV ICTS WITH BAYS

3) 2X50MVA, 220/33KV T/FS WITH BAYS

4) 2 X 132KV BAYS

5) 12 X 33KV OUTLETS

6) 132KV DC LINE TO 132 KV KALWAN S/S - 10 KM

1) LILO OF 220 KV DHULE - MALEGAON CKT. - I AT

220 KV SAYANE - 10 KMS.2) 2X25 MVA, 220/33KV T/F WITH BAYS

3) 33KV OUTLETS-8 NOS

1) 2X50MVA, 132/33KV T/F WITH BAYS.

2) 132KV SCDC LINE FROM SHEVGAON S/STN -

GHODGAON -37KM3) 33KV OUTLETS - 12 NOS

1) 400 KV D/C LINE FROM 400 KV BABHALESHWAR

- NASHIK LINE - 60 KMS

2) 400 KV SINNAR (IPP) - NASIK D/C LINE. -10KMS.

3) 2 X 500 MVA 400/220 KV ICT'S WITH BAYS.

4) 220 KV D/C LINE TO SINNAR II S/S -15 KMS .

5) LILO of 220 KV EKLAHARE - BABHALESHWAR

LINE AT 400 KV NASHIK - 15 KMS.1) LILO ON 220 KV MALEGAON - GANGAPUR S/C

LINE AT 220 KV SAKRI - 45 KMS.

2) LILO OF 220 KV SATANA - GANGAPUR S/C LINE

AT 220 KV SAKRI - 45 KMS.3) 2X100 MVA, 220/132KV T/F WITH BAYS

4) 132 KV SCDC LINE TO VISARWADI- 15 KMS

5) 132KV SCDC LINE TO NAMPUR S/S - 20 KMS

6) LILO OF 132 KV SATANA - TAHARABAD LINE AT

220 KV SAKRI - 10 KMS.

1) 220KV D/C A'NAGAR-BHOSE - 45 KM WITH BAYS

2) 2X100 MVA, 220/132KV T/F WITH BAYS

4) 132KV LINE BHOSE - KARJAT D/C- 80 KMS

5) 132KV LINE BHOSE - SHRIGONDA D/C - 30 KMS.

1) LILO ON 220 KV BHUSAWAL - AMALNER

CKT. II LINE AT 220 KV VIRODA - 10 KMS.

2) 2 X 200MVA, 220/132KV ICTS WITH BAYS

3) 2 X 50 MVA 220/33 KV T/F WITH BAYS

4) 132 KV VIRODA - YAWAL D/C LINE - 30 KM

5) 132 KV VIRODA - SAWADA M/C LINE - 10 KM

(OUT OF 4 CKTS TWO CIRCUITS TO SAWADA

AND TWO CIRCUITS TO BE CONNECTED TO 6) 132 KV D/C LINE FROM SAWDA TO NIMBHORA -

16 KM7) 132 KV SCDC LINE FROM NIMBHORA TO RAVER

- 20 KM8) 132KV VIRODA - BHUSAWAL-II M/C LINE -

25 KM

NEW SCHEMES

3 132 KV GHODEGAON S/S (

2010 - 11)

AHMEDNAGAR Strengthening of existing network.

1 220KV KALWAN II S/S

(2010-11)

NASIK Upgradation of existing 132 kv Kalwan s/s for the

load requrement in Nasik area.

2 220KV SAYANE S/S

(2010-11)

NASIK Sayne-220kV is considered for reducing the

loading of Dhule-220kV S/S. to meet the

upcoming load in the area.

5 220KV SAKRI S/S

(2011-12)

DHULE Present recorded peak on Sakri and Nampur

132kV S/S are 70 and 28 MW respectively. It is

anticipated by the year 2011-12, the load will

reach to criticle value. Hence it is necessary to go

in for new 220kV sub-station at Sakri.

4 400 KV NASIK S/S

(2011-12)

NASIK

AHMEDNAGAR Bhose 220kV S/S is considered to improve the

voltage profile in Ahemadnagar District & to meet

the upcoming load.

7 220 KV VIRODA S/S

(2011-12)

JALGAON 220 KV Viroda substation is proposed to meet

requirement of alternate feed to existing S/c lines

to 132 KV substations. Will improve voltage profile

and meet upcoming load.

Evacuation of Power from central sector & to

cater the increasing load in nearby area

6 220KV BHOSE S/S

( BELWANDI)

(2011-12)

125

Page 129: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 - W.E.F 01/04/2010

SR NO NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEMETOTAL SCOPE OF WORK

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

NASIK EHV CONSTRUCTION CUM (O&M) ZONE

1) 2X500MVA,400/220KV ICT

2) 400KV D/C LINE FROM DHULE-

MALEGAON(NASIK) D/C - 60KM WITH BAYS

3) 220KV LINE FROM MALEGAON - CHALISGAON

SCDC -69KM

4) REORINTATION OF EXISTING 220 KV

MALEGAON - SATANA S/C LINE AT 400 KV

MALEGAON ( Proposed) - 10 kms.

5) 220KV D/C LINE FROM 400KV

MALEGAON(SATANA) - 220KV NASIK -80KM6) 220KV D/C LINE FROM 400KV

MALEGAON(SATANA) - KALWAN -32KM

7) INTER LINK D/C LINE FROM EXISTING 220KV

MALEGAON - 400KV MALEGAON (SATANA) -

10KM1) 2X100MVA, 220/132KV ICT WITH BAYS

2) 220KV D/C LINE FROM MANMAD - 400KV

MALEGAON (SATANA) - 38KM

3) 132KV INTER LINK FROM 220KV MANMAD TO

MANMAD ( Existing) - 15KM

4) REORINTATION OF EXISTING 132 KV MANMAD -

YEOLA LINE AT 220 KV MANMAD ( Proposed) - 10

kms.

1 132KV LINK LINE

(2011-12)

NASIK 1) 132 KV SHIRPUR - FROM 220/132KV DONDAICHA

S/S SCDC LINE - 50 KMS WITH BAYS

132kV Shirpur S/S is fed from 132kV Nardane S/s

with S/c line. Hence to provide uninterrupted

supply during planned outages it is necessary to

add proposed line

2 132KV LINK LINE

(2012-13)

NASIK 1) 132 KV CHOPADA- YAWAL SCDC LINE - 43 KM 132kV Chopda S/S is fed from132kV Yawal S/s

with S/c line. Hence to provide uninterrupted

supply during planned outages it is necessary to

add proposed line

3 132KV LINK LINE

(2012-13)

JALGAON 1) 132 KV PAROLA - AMALNER 2ND CKT

STRINGING - 17.16 KM

132kV Parola S/S is fed from132kV Amalner S/s

with S/c line. Hence to provide uninterrupted

supply during planned outages it is necessary to

add proposed line

4 132KV LINK LINE

(2012-13)

DHULE 1) 132 KV TALODA - SHAHADA SCDC LINE -

28.61KM

132kV Taloda S/S is fed from220/132kV Shahada

S/s with S/c line. Hence to provide uninterrupted

supply during planned outages it is necessary to

add proposed line

5 132KV LINK LINE

(2013-14)

AHMEDNAGAR 1) 2ND CIRCUIT STRINGING OF 132 KV SHEVGAON

- GHODEGAON - 37 KMS.

132kV Ghodegaon S/S is fed from132kV

Shevgaon S/s with S/c line. Hence to provide

uninterrupted supply during planned outages it is

necessary to add proposed line

1 132KV LINK LINE

(2010-11)

NASIK 1) 132 KV MALEGAON-II - MALEGAON ONLY

STRINGING OF 2ND CKT - 2.5 KMS WITH BAYS

Since the existing 132kV Malegaon -II - Malegaon

S/c line is getting loaded to an extent of 35 MW

during Non-coinsident peak condition. It is

anticipated the load will reach to about critical

value by the year 2011-12. Hence it is suggested

to add proposed line to reduce the loading of

existing line and to meet additional load growth

and contingency.

2 132KV LINK LINE

(2010-11)

NASHIK 1) 2ND CIRCUIT STRINGING OF 132 KV MANMAD -

YEOLA - 25 KMS.

It is anticipated the load will reach to about critical

value in future. Hence it is necessary to propose

additional line to meet additional load growth and

contingency.

3 132KV LINK LINE

(2010-11)

DHULE 1) 132 KV D/C LINE FROM NANDURBAR - TALODA -

35 KMS.

For System Strengthening.

4 220KV LINK LINE

(2011-12)

JALGAON 1) 220KV BHUSAWAL - CHALISGAON D/C LINE -

123.88 KM WITH BAYS

Since the existing 220kV Bhusawal-Chalisgaon

D/c line is loaded to an extent of 126.5(EACH)

MW during Non-Coinsident peak condition. It is

anticipated the load will reach to about critical

value by the year 2011-12. Hence it is necessary

to propose additional line to meet additional load

growth and contingency.

To cater the increasing load in nearby area9 220KV MANMAD

(2013-14)

NASIK

8 400KV MALEGAON

(SATANA)

(2013-14)

NASIK To improve voltage profile of the area and to meet

the upcoming demand.

ADDITIONAL LINK LINES

ADDITIONAL LINK LINES FOR S/S WHERE ONLY SINGLE CKT AND SINGLE SOURCE IS AVAILABLE

ADDITIONAL LINK LINES TO MEET DEMAND WITHOUT LOAD SHEDDING AND TO ENSURE RELIABILITY AND QUALITY OF SUPPLY

126

Page 130: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 - W.E.F 01/04/2010

SR NO NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEMETOTAL SCOPE OF WORK

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

NASIK EHV CONSTRUCTION CUM (O&M) ZONE

5 132KV LINK LINE

(2011-12)

NASHIK 1) LILO OF 132 KV RAYMONDS - ADGAON AT 132

KV MHASRUL S/S. - 10 KMS.

For System Strengthening.

6 132KV LINK LINE

(2012-13)

NASIK 1) 2ND CIRCUIT STRINGING 132 KV KOPARGAON -

YEOLA-20 KM

It is anticipated the load will reach to about critical

value in future. Hence it is necessary to propose

additional line to meet additional load growth and

contingency.

7 132KV LINK LINE

(2012-13)

NASIK 1) 132KV LASALGAON - RANWAD SCDC -14KM Since the existing 132kV Lasalgaon - Ranwad

S/C line is loaded to an extent of 39 MW during

Non-Coinsident peak condition. It is anticipated

the load will reach to about critical value in future.

Hence it is necessary to propose additional line to

meet additional load growth and contingency.

8 132KV LINK LINE

(2012-13)

NASIK 1) 132KV EKLAHARE(OCR) - TAKLI SCDC -12KM Since the existing 132kV Eklahare (OCR) - Takli

line is loaded to an extent of 63 MW during Non-

Coinsident peak condition. It is anticipated the

load will reach to about critical value in future.

Hence it is necessary to propose additional line to

meet additional load growth and contingency.

9 132KV LINK LINE

(2012-13)

NASIK 1) 132KV AMBAD - EKLAHARE (OCR) SCDC -19KM Since the existing 132kV Eklahare (OCR) -

Ambad line is loaded to an extent of 24 MW

during Non-Coinsident peak condition. It is

anticipated the load will reach to about critical

value in future. Hence it is necessary to propose

additional line to meet additional load growth and

contingency.

10 132KV LINK LINE

(2012-13)

NASIK 1) 132KV EKLAHARE(GCR)-OZAR SCDC -17KM Since the existing 132kV Eklahare (GCR) - Ozar

D/C line is loaded to an extent of 90 MW during

Non-Coinsident peak condition. It is anticipated

the load will reach to about critical value in future.

Hence it is necessary to propose additional line to

meet additional load growth and contingency.

11 132KV LINK LINE

(2012-13)

JALGAON 1) 132 KV SCDC LINE FROM CHOPDA - SHIRPUR -

50 KMS.

For System Strengthening.

12 132KV LINK LINE

(2012-13)

NASHIK 1) 2ND CIRCUIT STRINGING OF 132 KV MALEGAON

- NAMPUR LINE - 30 KMS.

It is anticipated the load will reach to about critical

value in future. Hence it is necessary to propose

additional line to meet additional load growth and

contingency.

1 400 KV LINK LINE

(2013-14)

NASHIK 1) 400 KV D/C LINE FROM 400 KV MALEGAON (

Proposed) - NASHIK - 100 KMS.

Strengthening for power evacuation of proposed

generations at Nashik & Dondaicha.

1 132 KV LINK LINE

(2010-11)

DHULE 132 KV DONDAICHA(220 S/S)- DONDAICHA D/C

LINE -10KMS.

Strengthening for wind power evacuation

2 132 KV LINK LINE

(2010-11)

NASIK 2ND CIRCUIT STRINGING OF 132 KV KALWAN -

SATANA LINE -20KMS

For System Strengthening.

1 220KV LINK LINE

(2011-12)

JALGAON 1) CONVERSION OF S/C TO D/C OF 220KV

CHALSIGAON - BABHALESHWAR LINE UPTO

KOPERGAON TAP - 120 KM

To reduce the loading of the existing line

1 220 KV BHENDA

( BELWANDI)

( 2010-11)

1)

2)

ADDL. 1 X 100 MVA, 220/132 kV T/F with bays

132 KV BAYS - 2 NOS.

The Transformer capacity available is 220/132 kV

1X100MVA . To avoid loss of supply in case of

outages or interruptions on any one transformer

other transformer should take care of existing load

so as to avoid load shedding.

STRENGTHENING FOR EVACUATION ARRANGEMENT

STRENGTHENING FOR WIND POWER EVACUATION

ADDITIONAL LINK LINES FOR NEW S/S TO HAVE ALTERNATE SOURCE

AUGMENTATION OF S/S BY ADDITION OF T/F

AUGMENTATION OF S/S BY ADDITION WHERE ONLY SINGLE ICT IS AVAILABLE

127

Page 131: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 - W.E.F 01/04/2010

SR NO NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEMETOTAL SCOPE OF WORK

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

NASIK EHV CONSTRUCTION CUM (O&M) ZONE

1 132 kV AMBAD NASIK

(2010-11)

Nasik 1)

2)

Add 1 X 25 MVA , 132/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in s/s is 2

X 25 MVA. And the load reached is 42 MVA

TConsidering the maximum load reached on the

transformer in the event of interruptions/outage on

any one of the transformer other transformer

should take care of existing load

2 132 kV SANGAMNER

(2011-12)

Ahmednagar 1)

2)

Add 1 X 25 MVA , 132/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in s/s is 1

X 50 & 1 X 25 MVA. And the load reached is 42

MVA Considering the maximum load reached on

the transformer in the event of

interruptions/outage on any one of the transformer

other transformer should take care of existing load

3 132 kV SATPUR

(2011-12)

Nashik 1)

2)

Add 1 X 25 MVA , 132/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in s/s is 1

X 50 & 1 X 25 MVA. And the load reached is 38

MVA Considering the maximum load reached on

the transformer in the event of

interruptions/outage on any one of the transformer

other transformer should take care of existing load

4 132 kV KHARDA

(2011-12)

Ahmednagar 1)

2)

Add 1 X 25 MVA, 132/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in S/s is 2

X 25 MVA and load is 20 MVA. Considering the

maximum load reached on the transformer in the

event of interruptions/outage on any one of the

transformer other transformer should take care of

existing load

5 132 kV RANWAD

(2011-12)

Nasik 1)

2)

Add 1 X 50 MVA , 132/33 kV T/F with bays.

6 X 33 kV out lets.

Existing transformer capacity available in S/s is 2

X 50 MVA and load is 40 MVA. Considering the

maximum load reached on the transformer in the

event of interruptions/outage on any one of the

transformer other transformer should take care of

existing load

6 132 kV RAVER

(2011-12)

Jalgaon 1)

2)

Add 1 X 25 MVA, 132/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in S/s is 1

X 25 & 1 X 10 MVA and load is 22 MVA.

Considering the maximum load reached on the

transformer in the event of interruptions/outage on

any one of the transformer other transformer

should take care of existing load

7 132 KV PIMPARKHED S/S.

( 2011 - 12)

NASHIK 1)

2)

Add 1 X 25 MVA , 132/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in S/s is 1

X 25 MVA . Considering the maximum load

reached on the transformer in the event of

interruptions/outage on any one of the transformer

other transformer should take care of existing load

8 132 KV SINNAR

(MALEGAON) S/S.

( 2011 - 12)

NASHIK 1)

2)

Add 1 X 50 MVA , 132/33 kV T/F with bays.

6 X 33 kV out lets.

Existing transformer capacity available in s/s is 1

X 25 & 1 X 50 MVA. And the load reached is 43

MVA .Considering the maximum load reached on

the transformer in the event of

interruptions/outage on any one of the transformer

other transformer should take care of existing load

9 132 kV RAMACHE

PIMPLAS

(2012-13)

Nasik 1)

2)

Add 1 X 25 MVA , 132/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in S/s is 2

X 25 MVA and load is 22 MVA. Considering the

maximum load reached on the transformer in the

event of interruptions/outage on any one of the

transformer other transformer should take care of

existing load

10 220 kV BHENDA

(2013-14)

Ahmednagar 1)

2)

Add 1 X 25 MVA, 220/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in S/s is 2

X 25 MVA and load is 18 MVA. Considering the

maximum load reached on the transformer in the

event of interruptions/outage on any one of the

transformer other transformer should take care of

existing load

AUGMENTATION OF S/S BY ADDITION TO REDUCE LOADING OF TRANSFORMER

128

Page 132: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 - W.E.F 01/04/2010

SR NO NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEMETOTAL SCOPE OF WORK

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

NASIK EHV CONSTRUCTION CUM (O&M) ZONE

11 132 kV CHALISGAON-I

(2013-14)

Jalgaon 1)

2)

Add 1 X 25 MVA, 132/25 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in S/s is 1

X 10.8 MVA . Considering the maximum load

reached on the transformer in the event of

interruptions/outage on any one of the transformer

other transformer should take care of existing load

1 220 KV PIMPALGAON

( BASVANT) S/S

(2010-11)

NASHIK 1)

2)

1 X 50 MVA 220/33 KV T/F WITH BAYS

33 KV OUTLETS : 6 NOS.

Creation of new 33 KV level

2 220 KV SAKRI S/S.

( 2011-12)

DHULE 1)

2)

2 X 25 MVA , 220/33 KV T/F WITH BAYS

33 KV OUTLETS : 8 NOS.

Creation of new 33 KV level

3 220 KV PIMPALGAON

( BASVANT) S/S

(2011-12)

NASHIK 1)

2)

1 X 50 MVA 220/33 KV T/F WITH BAYS

33 KV OUTLETS : 6 NOS.

Creation of new 33 KV level

4 220 KV SAKRI S/S.

( 2012-13)

DHULE 1)

2)

2 X 25 MVA , 220/33 KV T/F WITH BAYS

33 KV OUTLETS : 8 NOS.

Creation of new 33 KV level

5 220 KV BHOSE S/S

(2012-13)

NASHIK 1)

2)

1 X 50 MVA 220/33 KV T/F WITH BAYS

33 KV OUTLETS : 6 NOS.

Creation of new 33 KV level

6 220 KV BHOSE S/S

(2013-14)

NASHIK 1)

2)

1 X 50 MVA 220/33 KV T/F WITH BAYS

33 KV OUTLETS : 6 NOS.

Creation of new 33 KV level

7 220 KV MANMAD S/S.

( 2013-14)

NASHIK 1)

2)

1 X 25 MVA , 220/33 KV T/F WITH BAYS

33 KV OUTLETS : 4 NOS.

Creation of new 33 KV level

8 220 KV MANMAD S/S.

( 2014-15)

NASHIK 1)

2)

1 X 25 MVA , 220/33 KV T/F WITH BAYS

33 KV OUTLETS : 4 NOS.

Creation of new 33 KV level

1 220 KV RAYMONDS S/S. (

2011 - 12 )

NASHIK 1)

2)

1 X 50 MVA 220/33 KV T/F WITH BAYS

33 KV OUTLETS : 6 NOS.

Creation of new 33 KV level

2 220 KV RAYMONDS S/S. (

2012 - 13 )

NASHIK 1)

2)

1 X 50 MVA 220/33 KV T/F WITH BAYS

33 KV OUTLETS : 6 NOS.

Creation of new 33 KV level

3 220 KV AMALNER S/S

(2012-13)

DHULE 1)

2)

1 X 25 MVA 220/33 KV T/F WITH BAYS

33 KV OUTLETS : 4 NOS.

Creation of new 33 KV level

4 220 KV AMALNER S/S

(2013-14)

DHULE 1)

2)

1 X 25 MVA 220/33 KV T/F WITH BAYS

33 KV OUTLETS : 4 NOS.

Creation of new 33 KV level

1 400 KV BABHALESHWAR

S/S

(2010-11)

NASIK 1)

2)

1X(500-315)MVA, 400/220 KV ICT

220 KV BAYS - 2 NOS.

Existing Transformer capacity available is 400/220

kV, 2 X 315 MVA and load reached is 598

MVA.The transformer is replaced to meet the

anticipated load growth.

2 220 KV MALEGAON S/S

(2010-11)

NASIK 1)

2)

1 X (200-100) MVA, 220/132 KV ICTS

132 KV BAYS - 2 NOS.

Existing Transformer capacity available is 220/132

kV, 2 X 100 MVA and load reached is 185

MVAThe transformer is replaced to meet the

anticipated load growth.

3 220 KV CHALISGAON S/S

(2010-11)

JALGAON 1)

2)

1 X (200-100)MVA 220/132 KV ICTS

132 KV BAYS - 2 NOS.

Existing Transformer capacity availablewill be

220/132 kV, 1 X 100 MVA and1 X 200 MVA load

reached is 158 MVA.The transformer is replaced

to meet the anticipated load growth.

4 220 KV BHUSAWAL

(2010 -11)

JALGAON 1)

2)

1X(200-100)MVA, 220/132KV ICT

132 KV BAYS - 2 NOS.

Existing Transformer capacity available will be

220/132 kV, 1 X 100 MVAand 1 X 200 MVA and

load reached will be 115 MVA.The transformer is

replaced to meet the anticipated load growth.

5 220KV BABHALESHWAR

S/S

(2010-11)

AHMEDNAGAR 1)

2)

1X(200-100)MVA, 220/132KV

132 KV BAYS - 2 NOS.

Existing transformer capacity available in S/s

is,220/132kV, 2 x 200 and 1 X 100 MVA and the

load reached will be 165 and 115 MVA

respectively.Considering the maximum load reach

on the transformer, in event of interruption/outage

on any one of the transformer other transformer

should take care of existing load so as to avoid

load shedding.

Creation of new 33 KV level ( Existing EHV substations ).

AUGMENTATION OF S/S BY REPLACEMENT OF TRANSFORMER

AUGMENTATION OF S/S BY ADDITION OF T/F

Creation of new 33 KV level ( EHV substations already proposed in STU plan).

129

Page 133: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 - W.E.F 01/04/2010

SR NO NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEMETOTAL SCOPE OF WORK

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

NASIK EHV CONSTRUCTION CUM (O&M) ZONE

6 220 kV NASIK OCR

(2010-11 )

Nasik 1)

2)

Add 1 X (50-25) MVA, 132/33 kV T/F.

2 nos. of 33 kV outlets

Existing transformer capacity available in s/s is 3

X 25 MVA. And the load reached is 43 MVA The

transformer is replaced to meet anticipated load

growth..

7 132 kV SAVDA

(2010-11)

Jalgaon 1)

2)

1 X (50 -20 ) 132/33 kV T/F

2 X 33 kV out lets.

Existing transformer capacity available in S/s is 3

X 20 MVA and load is 55 MVA. The transformer

is replaced to meet anticipated load growth.

8 220 KV BHAMBORI

( Proposed in 2009-10) S/S.

( 2010 - 11)

JALGAON 1)

2)

Add 1 X (50-25) MVA, 220/33 kV T/F .

2 nos. of 33 kV outlets

To meet additional demand of MSEDCL.

9 220 KV BHAMBORI

( Proposed in 2009-10) S/S.

( 2011 - 12)

JALGAON 1)

2)

Add 1 X (50-25) MVA, 220/33 kV T/F .

2 nos. of 33 kV outlets

To meet additional demand of MSEDCL.

10 220 KV SAYANE

( Proposed in 2010-11) S/S.

( 2011 - 12)

NASHIK 1)

2)

Add 1 X (50-25) MVA, 220/33 kV T/F .

2 nos. of 33 kV outlets

To meet additional demand of MSEDCL.

11 220 KV SAYANE

( Proposed in 2010-11) S/S.

( 2012 - 13)

NASHIK 1)

2)

Add 1 X (50-25) MVA, 220/33 kV T/F .

2 nos. of 33 kV outlets

To meet additional demand of MSEDCL.

12 132 KV MANMAD S/S.

( 2012-13)

NASHIK 1)

2)

Add 1 X (50-25) MVA, 132/33 kV T/F

2 nos. of 33 kV outlets

Existing transformer capacity available in S/s is 1

X 25 & 1 X 50 MVA and load is 52 MVA. The

transformer is replaced to meet anticipated load

growth.

13 132 KV NAMPUR S/S. (

2012-13)

NASHIK 1)

2)

Add 1 X (50-25) MVA, 132/33 kV T/F .

2 nos. of 33 kV outlets

Existing transformer capacity available in S/s is 2

X 25 MVA and load is 38 MVA. The transformer

is replaced to meet anticipated load growth.

14 220 KV BHENDA S/S.

( 2012-13)

AHMEDNAGAR 1)

2)

Add 1 X (50-25) MVA, 132/33 kV T/F .

2 nos. of 33 kV outlets

To meet additional demand of MSEDCL.

15 220 KV KHARDA S/S.

( 2012-13)

1)

2)

Add 1 X (50-25) MVA, 132/33 kV T/F

2 nos. of 33 kV outlets

To meet additional demand of MSEDCL.

16 220 KV BHENDA S/S.

( 2013-14)

AHMEDNAGAR 1)

2)

Add 1 X (50-25) MVA, 132/33 kV T/F .

2 nos. of 33 kV outlets

To meet additional demand of MSEDCL.

17 220 KV KHARDA S/S.

( 2013-14)

1)

2)

Add 1 X (50-25) MVA, 132/33 kV T/F .

2 nos. of 33 kV outlets

To meet additional demand of MSEDCL.

18 220 KV BHENDA S/S.

( 2014 - 15)

AHMEDNAGAR 1)

2)

Add 1 X (200-100) MVA, 220/132 kV T/F

132 KV BAYS - 2 NOS.

To cater the increasing load in nearby area

130

Page 134: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

EHV CC O&M ZONE :

AURANGABAD

131

Page 135: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 - W.E.F 01/04/2010

SR NO NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEME

1) 2X50MVA, 220/33KV T/FS WITH BAYS

2) 10X33KV OUTLETS

3) 2X100MVA, 220/132KV ICTS WITH BAYS

4) 220KV CHITEGAON -SHENDRA SCDC LINE-25 KM

5) 132 KV SHENDRA DEOLAI SCDC LINE -25 KMS.

6) LILO ON 220KV WALUJ-JALNA D/C ON M/C - 3 KM

D/C ON D/C-12 KM

1) 2X 100 MVA, 220/132 KV ICTS WITH BAYS

2) 2X 50 MVA, 220/33 KV T/F'S WITH BAYS

3) LILO ON 220 KV PUSAD - PARBHANI LINE - 22 KM WITH

BAYS

4) 132KV BAYS - 4 NOS

5) 33KV OUTLETS - 12 NOS

6)

7)

LILO ON BOTH CKT OF 132KV DC KURANDA - HINGOLI

LINE ON M/C -10KM

132KV AKHADA BALAPUR - 220KV HINGOLI SCDC LINE -

25 KM

1) 2X25MVA, 220/33KV T/FS WITH BAYS

2) 2 X 100 MVA 220/132 KV ICT'S WITH BAYS

(2010-11)

3) 8X33KV OUTLETS

4) 220KV D/C LINE FROM 220KV BARSHI S/S- 30 CKM

WITH BAYS5) 132 KV SCDC LINE TO BHOOM S/S - 30 KMS

1) 220KV D/C LINE BEED - PATODA - 45 KM WITH BAYS

2) 2X50MVA, 220/33KV T/FS WITH BAYS

3) 12X33KV OUTLETS

1) 2 X 25MVA, 132/33KV T/F'S WITH BAYS

2) LILO OF 132 KV PADEGAON - JALNA AT BADNAPUR

S/S WITH BAYS -10KM

3) 8X33KV OUTLETS

1) 2 X 25MVA, 132/33KV T/F'S WITH BAYS

2) LILO ON 132KV PARBHANI-PARTUR AT SHELU S/S - 5

CKM WITH BAYS3) 8X33KV OUTLETS

1) LILO ON 400KV PARLI -CHANDRAPUR ON S/C AND

LILO ON ONE CIRCUIT OF 400KV PARLI -CHANDRAPUR

D/C -40KM EACH2) 2 X 500 MVA, 400/220KV ICTS WITH BAYS AND 1 X 167

SINGLE PHASE SPARE ICT

3) 220KV D/C LINE TO 220 KV NANDED (WAGHALA) S/S -

10KMS WITH BAYS

1) 2X100MVA, 220/132KV ICTS WITH BAYS

2) 2 X 50MVA, 220/33KV T/FS WITH BAYS

3) 220KV D/C LINE HARANGUL - VALANDI - 60 KM WITH

BAYS

4) 132KV LINE TO NILANGA S/S - 15 KM WITH BAYS

5) 132KV LINE TO UDGIR S/S - 20 KM WITH BAYS

4X132KV BAYS

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

AURANGABAD EHV CONSTRUCTION CUM (O&M) ZONE

TOTAL SCOPE OF WORK

SPILL OVER SCHEMES

1 220KV SHENDRA S/S

(2008-09)

AURANGABAD VOLTAGE IMPROVEMENT & LOAD CATERING

2 220 KV HINGOLI S/S

(2008-09)

HINGOLI This station is considered to meet the load growth

in Aurangabad Circle and improving voltage

profile. Hingoli-220kV S/S is proposed on LILO of

220kV existing Pusad -Nanded D/C line – 4kM

5 132 KV BADNAPUR

S/S

(2008-09)

JALNA VOLTAGE IMPROVEMENT & LOAD CATERING

BEED VOLTAGE IMPROVEMENT & LOAD CATERING

6 132KV SHELU S/S

(2008-09)

PARBHANI Shelu132kV S/S is considered to improve the

voltage profile in Aurangabad circle and to cater

the new loads coming in nearby area. Shelu132kV

S/S is fed from Pathri132kV S/S by constructing

132kV D/C line of 10kM.

3 220KV PARANDA S/S

(2008-09)

OSMANABAD VOLTAGE IMPROVEMENT & LOAD CATERING

4 220KV

PATODA S/S

(2008-09)

7 400KV NANDED S/S

(2009-10)

NANDED To improve the voltage profile and to meet the

upcoming load.

8 220KV

VALANDI S/S

(2009-10)

LATUR To improve the voltage profile and to meet the

upcoming load.

132

Page 136: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 - W.E.F 01/04/2010

SR NO NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEME

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

AURANGABAD EHV CONSTRUCTION CUM (O&M) ZONE

TOTAL SCOPE OF WORK

1) 2X100MVA, 220/132KV ICTS WITH BAYS

2) 220KV D/C FROM SOLAPUR II (BALE) TO TULJAPUR -

50KM

3) 220KV D/C FROM GIRAVALI TO TULJAPUR - 80KM

4) 2X25MVA, 220/33KV T/FS WITH BAYS

5) 132 KV TULAJAPUR-UJANI S/C-25 KM

6) 133 KV TULAJAPUR-NALDURG S/C-25 KM

7) 4X132KV BAYS

1) 400KV NANDED - NARSI WITH BAYS-60 KMS

2) 2X100MVA, 220/132KV ICTS WITH BAYS

3) 2 X 25MVA, 220/33KV T/FS WITH BAYS

4) 132KV MUKHED-NARSI S/C-30KM

5) 132KV KUNDALWADI-NARSI S/C- 30KM

6) LILO ON 132 KV NARSI - DEGLOOR- 30KM

7) 132KV-220KV NARSI -10KM

8) 8 X 33KV OUTLETS

1) 2X25MVA, 132/33KV T/FS WITH BAYS

2) 132KV SCDC PAHUR-BULDHANA - 60 KMS WITH BAYS

3) 132KV SCDC SILLOD - SOYGAON - 35 KMS WITH BAYS

4) 132KV SOYAGAON - PAHUR SCDC - 14KM WITH BAYS

5) 8X33KV OUTLETS

1 132KV PANGRI

(2009-10)

BEED 1)

2)

LILO ON PARLI - TELGAON - 15KM

2X25 MVA,132/33KV

8 X 33KV OUTLETS

To eliminate 33KV level from GCR Parli.

1 132KV LINK LINE

(2008-09)

JALNA 1) 132KV PADEGAON - PISHOR SCDC LINE - 40KM WITH

BAYS

132kV Pishor S/S is fed from 132kV Padegaon S/s

with S/c line. Hence to provide uninterrupted

supply during planned outages it is necessary to

add proposed line

2 132KV LINK LINE

(2008-09)

JALNA 1)

2)

132KV AMBAD - 220KV JALNA SCDC LINE - 29 KM

GIS BAY AND CABLE

132kV Ambad S/S is fed from 220kV Jalna S/s

with S/c line. Hence to provide uninterrupted

supply during planned outages it is necessary to

add proposed line. ( GIS bays & cable is proposed

due to no space at Ambad & Jalana and ROW

problem at Jalana.)

3 132KV LINK LINE

(2008-09)

AURANGABAD 1) 132KV DEOLAI - 220KV CHITEGAON LINE (STRINGING

ONLY ) - 28.9 KM

132kV Deolai S/S is fed from 132kV Chitegaon S/s

with S/c line. Hence to provide uninterrupted

supply during planned outages it is necessary to

add proposed line

4 132KV LINK LINE

(2008-09)

AURANGABAD 1) 132KV GANGAPUR - VAIJAPUR SCDC LINE - 40 KM 132kV Gangapur S/S is fed from 132kV Padegaon

S/s with S/c line. Hence to provide uninterrupted

supply during planned outages it is necessary to

add proposed line

5 132KV LINK LINE

(2009-10)

OSMANABAD 1) 132KV NILANGA - OMERGA SCDC LINE - 31.22KM 132kV Killari S/S is Tapped on 132kV Ujani-

Omerga S/c line. Hence to provide alternate supply

during planned outages it is necessary to add

proposed line considering the anticipated load

growth in that region

6 132KV LINK LINE

(2009-10)

OSMANABAD 1) 132KV DC LINE BHOOM - PARANDA - 20 KM WITH

BAYS

132kV Bhoom S/S is fed from 132kV Kalamb S/s

with S/c line. Hence to provide uninterrupted

supply during planned outages it is necessary to

add proposed line

11 132KV SOYGAON S/S

(2009-10)

AURANGABAD Present recorded peak load on Pahur-132kV,

Sillod-132kV S/S, Pishor-132kV are 35MW, 60MW

and 30MW respectively. It is anticipated by the

year 2009-10 the load will reach to about 150MW.

Hence it is necessary to go in for new 132kV sub-

station at Soygaon. The new Soygaon-132kV S/S

is proposed in year 2009-10 for reducing loading

on Pahur-132kV, Sillod-132kV S/S, and Pishor-

132kV S/S. By the commissioning of this

substation, voltage profile of Aurangabd Circle will

improve.

9 220KV TULJAPUR S/S

(2009-10)

OSMANABAD Tuljapur is considered to meet the increasing loads

in Osmanabad district and improve the voltage

profile.

10 220KV

NARSI II S/S

(2009-10)

NANDED 220 kV Narsi is considered to meet the increasing

loads in Latur District. By constructing this station,

the voltage profile improves.

NEW SUBSTATION TO ELIMINATE 33 KV LEVEL AT GENERATION SWITCHYARD AT PARLI GEN.

ADDITIONAL LINK LINES

ADDITIONAL LINK LINES FOR S/S WHERE ONLY SINGLE CKT AND SINGLE SOURCE IS AVAILABLE

133

Page 137: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 - W.E.F 01/04/2010

SR NO NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEME

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

AURANGABAD EHV CONSTRUCTION CUM (O&M) ZONE

TOTAL SCOPE OF WORK

1 132KV LINK LINE

(2009-10)

LATUR 1) 132 KV D/C CHAKUR - RENAPUR LINE- 35 KMS.

(ONE CKT WILL BE CONNECTED TO LATUR MIDC S/S {

PARTIAL M/C AT LATUR MIDC END} AND ANOTHER TO

RENAPUR)

Since the existing 132kV Parli (girwali)-Renapur

S/c line is critically loaded to an extent of 86 MW.

Hence it is suggested to add proposed line to

reduce the loading of existing line and to meet

additional load growth and contingency.

2 132KV LINK LINE

(2009-10)

AURANGBAD 1) 132 KV DC LINE FROM SAWANGI - HARSOOL -10KM It is anticipated the load will reach to about critical

value in future. Hence it is necessary to propose

additional line to meet additional load growth and

contingency.

1 132KV LINK LINE

(2008-09)

JALNA 1) 132KV KHULTABAD - SAVANGI SCDC LINE - 26KM

WITH BAYS

Only single ckt and single source is available at

Sawangi S/S.

1 220KV LINK LINE

(2008-09)

JALNA 1) 220 KV D/C LINE JALNA - CHIKHALI - 75 KM WITH BAYS To have evacuation facility at Paras Generation

1) 1X100 MVA, 220/132 KV ICT WITH BAYS

2) 1 X 132 KV BAYS

1) 1 X 200MVA, 220/132KV ICT WITH BAYS

2) 2X132KV BAYS

1) ADD. 1 X 25 MVA, 132/33 KV T/F WITH BAYS

2) 33 KV OUTLETS - 4 NOS.

1) 1X25 MVA, 132/33KV T/F WITH BAYS

2) 4X33KV OUTLETS

1) 1 X25 MVA, 132/33 KV T/F WITH BAYS

2) 33 KV OUTLET - 4 NOS.

1) 1 X50 MVA, 132/33 KV T/F WITH BAYS

2) 33 KV OUTLET - 6 NOS.

1) ADD. 1 X 25 MVA, 132/33 KV T/F WITH BAYS

2) 33 KV OUTLETS - 4 NOS.

3) 4 X 33 KV OUTLETS

1) ADDL. 1 X50 MVA, 132/33 KV T/F WITH BAYS

2) 33 KV OUTLET - 6 NOS.

1) ADDL. 1 X25 MVA, 132/33 KV T/F WITH BAYS

2) 33 KV OUTLET - 4 NOS.

1) ADD. 1 X 50 MVA, 132/33 KV T/F WITH BAYS

2) 33 KV OUTLETS - 6 NOS.

1) ADDL. 1X25 MVA, 132/33KV T/F WITH BAYS

2) 4X33KV OUTLETS

1) ADDL. 1X25 MVA, 132/33KV T/F WITH BAYS

2) 4X33KV OUTLETS

1) ADDL. 1X25 MVA, 132/33KV T/F WITH BAYS

2) 4X33KV OUTLETS

1) ADDL. 1 X25 MVA, 132/33 KV T/F WITH BAYS

2) 33 KV OUTLET - 4 NOS.

1) 1 X 25 MVA, 132/33 KV T/F WITH BAYS

2) 33KV OUTLETS - 4 NOS.

ADDITIONAL LINK LINES TO MEET DEMAND WITHOUT LOAD SHEDDING AND TO ENSURE RELIABILITY AND QUALITY OF SUPPLY

ADDITIONAL LINK LINES FOR NEW S/S TO HAVE ALTERNATE SOURCE

STRENGTHENING FOR EVACUATION ARRANGEMENT

AUGMENTATION OF S/S BY ADDITION OF T/F

AUGMENTATION OF S/S BY ADDITION WHERE ONLY SINGLE TRANSFORMER IS AVAILABLE

1 220 KV PARLI GCR

(2008-09)

BEED To avoid loss of supply in case of outages or

interruptions on any one transformer

2 220KV JALNA S/S

(2008-09)

JALNA To avoid loss of supply in case of outages or

interruptions on any one transformer

3 132 KV KHULTABAD

S/S

(2008-09)

AURANGABAD To avoid loss of supply in case of outages or

interruptions on any one transformer

4 132KV

AKHADA-BALAPUR S/S

(2008-09)

HINGOLI To avoid loss of supply in case of outages or

interruptions on any one transformer

5 132 KV PURNA S/S

(2008-09)

PARBHANI To avoid loss of supply in case of outages or

interruptions on any one transformer

6 132 KV BASMATH S/S

(2008-09)

PARBHANI To avoid loss of supply in case of outages or

interruptions on any one transformer

7 132 KV MAJALGAON

S/S

(2008-09)

BEED To avoid loss of supply in case of outages or

interruptions on any one transformer

8 132KV AUSA S/S

(2008-09)

LATUR To avoid loss of supply in case of outages or

interruptions on any one transformer

9 132KV CHAKUR S/S

(2008-09)

LATUR To avoid loss of supply in case of outages or

interruptions on any one transformer

10 132 KV RENAPUR S/S

(2008-09)

LATUR To avoid loss of supply in case of outages or

interruptions on any one transformer

11 132KV

MUKHED S/S

(2008-09)

NANDED To avoid loss of supply in case of outages or

interruptions on any one transformer

12 132KV

HIMAYATNAGAR S/S

(2008-09)

NANDED To avoid loss of supply in case of outages or

interruptions on any one transformer

13 132KV

DEGLOOR S/S

(2008-09)

NANDED To avoid loss of supply in case of outages or

interruptions on any one transformer

14 132KV LATUR MIDC

S/S

(2008-09)

LATUR Existing transformer capacity available in S/s is,

132/33 - 1 x 12.5 - 12.22 LOAD

To avoid loss of supply in case of outages or

interruptions on any one transformer

15 132 KV KILLARI S/S

(2008-09)

LATUR To avoid loss of supply in case of outages or

interruptions on any one transformer

134

Page 138: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 - W.E.F 01/04/2010

SR NO NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEME

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

AURANGABAD EHV CONSTRUCTION CUM (O&M) ZONE

TOTAL SCOPE OF WORK

1) 1X25 MVA,132/33 KV TF

2) 33KV BAY - 04 NOS

17 220 KV PARLI GCR

(2009-10)

BEED 1) 1X100 MVA, 220/132 KV ICT WITH BAYS The existing transformer capacity available is

220/132 kV, 1X100 MVA and the load reached is

144 MVA To avoid loss of supply in case of

outages or interruptions on any one transformer

additional transformer is proposed.

18 220 KV CHITEGAON

S/S

(2009-10)

AURANGABAD 1) 1 X 100 MVA, 220/132 KV ICT WITH BAYS The existing transformer capacity available is

220/132 kV, 1X100 MVA and the load reached is

59 MVA.To avoid loss of supply in case of outages

or interruptions on any one transformer additional

transformer is proposed.

19 132 kV KUNDALWADI

(2009-10)

Nanded 1)

2)

Add. 1 X 25 MVA, 132/33 kV T/F with bays.

4 X 33 kV bays

Existing Transformer capacity avaible is 1 X 25

MVA. And the load reached is 16 MVATo avoid

loss of supply in case of outages or interruptions

on transformer.

20 132 kV RAIMOHA

(2009-10)

Beed 1)

2)

Add 1 X 25 MVA, 132/33 kV T/F with bay.

4 X 33 kV out lets

Existing Transformer capacity avaible is 1 X 25

MVA. And the load reached is 21 MVATo avoid

loss of supply in case of outages or interruptions

on transformer.

21 132 kV GHANSAWANGI

(2009-10)

Jalna 1)

2)

Add 1 X 25 MVA, 132/33 kV T/F with bay.

4 X 33 kV out lets

Existing Transformer capacity avaible is 1 X 25

MVA. And the load reached is 6 MVATo avoid loss

of supply in case of outages or interruptions on

transformer.

22 132 kV KURUNDA

(2009-10)

Hingoli 1)

2)

Add 1 X 25 MVA, 132/33 kV T/F with bay.

4 X 33 kV out lets

Existing Transformer capacity avaible is 2 X 25

MVA. And the load reached is 26 MVATo avoid

loss of supply in case of outages or interruptions

on transformer.

23 132 kV NARSI

(2009-10)

Nanded 1)

2)

Add 1 X 25 MVA, 132/33 kV T/F with bay.

4 X 33 kV out lets

Existing Transformer capacity avaible is 1 X 25, 1 x

16 MVA. And the load reached is 23 MVATo avoid

loss of supply in case of outages or interruptions

on transformer.

24 132 kV UMRI

(2009-10)

Nanded 1)

2)

Add 1 X 25 MVA, 132/33 kV T/F with bay.

4 X 33 kV out lets

Existing Transformer capacity avaible is 1 X 25

MVA. And the load reached is 20 MVATo avoid

loss of supply in case of outages or interruptions

on transformer.

25 132 kV BASMATH

(2009-10)

Parbhani 1)

2)

Add 1 X 25 MVA, 132/33 kV T/F with bay.

4 X 33 kV out lets

Existing Transformer capacity avaible is 1 X 25

MVA. To avoid loss of supply in case of outages or

interruptions on transformer.

26 132 kV DEOLAI

(SATARA)

(2009-10)

Aurangabad 1)

2)

Add 1 X 25 MVA, 132/33 kV T/F with bay.

4 X 33 kV out lets

Existing Transformer capacity avaible is 1 X 25

MVA. And the load reached is 20 MVATo avoid

loss of supply in case of outages or interruptions

on transformer.

27 132 kV KAIJ *

(2009-10)

Beed 1)

2)

Add 1 X 25 MVA, 132/33 kV T/F with bay.

4 X 33 kV out lets

Existing Transformer capacity avaible is 1 X 25

MVA. And the load reached is14 MVATo avoid loss

of supply in case of outages or interruptions on

transformer.

1 400KV S/S -

AURANGABAD, PARLI

S/S

(2008-09)

AURANGABAD

BEED

1) ADDL. 1 X 500 MVA 400/220 KV, ICT WITH BAYS AT -

AURANGABAD, PARLI S/S

Existing transformer capacity available in

Aurangabad S/s is,400/220 - 2 x 315 - 244 &

Existing transformer capacity available in Parli S/s

is,400/220 - 2 x 315 - 316

Considering the maximum load reach on the 1) 1 X 25 MVA, 220/33 KV T/F WITH BAYS

2) 33KV OUTLETS - 4 NOS.

1) 1 X 100 MVA, 220/132 KV ICT WITH BAYS

2) 132KV BAYS - 2 NOS.

16 132KV ARDHAPUR

S/STN

(2008-09)

AURANGABAD To avoid loss of supply in case of outages or

interruptions on any one transformer

AUGMENTATION OF S/S BY ADDITION TO REDUCE LOADING OF TRANSFORMER

2 220 KV JALNA S/S

(2008-09)

JALNA Existing transformer capacity available in S/s

is,132/33 - 1 x 50 - 41 load

132/33 - 1 x 25 - 20 load Considering the

maximum load reach on the transformer, in event

of interruption/outage on any one of the

transformer other transformer should take care of

existing load so as to avoid load shedding.

3 220 KV Osmanabad S/S

(2008-09)

OSMNABAD To feed nearby 132 kv S/s on 132 kv level.

135

Page 139: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 - W.E.F 01/04/2010

SR NO NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEME

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

AURANGABAD EHV CONSTRUCTION CUM (O&M) ZONE

TOTAL SCOPE OF WORK

1) ADDL. 1X25 MVA, 132/33KV T/F WITH BAYS

2) 4X33KV OUTLETS

1) ADDL. 1X25 MVA, 132/33KV T/F WITH BAYS

2) 4X33KV OUTLETS

1) ADD. 1 X 25 MVA, 132/33 KV T/F WITH BAYS

2) 33KV OUTLETS - 4 NOS.

7 220 KV HARANGUL S/S

(2009-10)

LATUR 1) 1 X 200 MVA, 220/132 KV ICT WITH BAYS The existing transformer capacity available is

220/132 kV, 2X200 MVA and the load reached is

181MVATo avoid loss of supply in case of outages

or interruptions on any one transformer additional

transformer is proposed.

8 220 kV OSMANABAD

(2009-10)

Osmanabad 1)

2)

Add1 X 25 MVA , 220/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in s/s is 2 X

50MVA. And the load reached is 49 MVA

Considerig the maximum load reached on the

transformer in the event of interruptions/outage on

any one of the transformer other transformer

should take care of existing load.

9 220 kV MURUD

(2009-10)

Latur 1)

2)

Add 1 X 50 MVA, 220/33 kV T/F with bays.

6 X 33 kV out lets.

Existing transformer capacity available in S/s is 1 X

25 & 1 X 50 MVA and load is 50 MVA.

Considering the maximum load reached on the

transformer in the event of interruptions/outage on

any one of the transformer other transformer

should take care of existing load

10 220 kV JALNA-II

(2009-10)

Jalna 1)

2)

Add 1 X 50 MVA, 220/33 kV T/F with bays.

6 X 33 kV out lets.

Existing transformer capacity available in S/s is 2 X

50 MVA and load is 61 MVA. Considering the

maximum load reached on the transformer in the

event of interruptions/outage on any one of the

transformer other transformer should take care of

existing load

11 132 kV AMBAD (JALNA)

(2009-10)

Jalna 1)

2)

Add 1 X 25 MVA, 132/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in S/s is 2 X

25 MVA and load is 36 MVA. Considering the

maximum load reached on the transformer in the

event of interruptions/outage on any one of the

transformer other transformer should take care of

existing load

12 132 kV ASHTI (BEED)

(2009-10)

Beed 1)

2)

Add 1 X 25 MVA, 132/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in S/s is,2 X

25 MVA and load is 30 MVA. Considering the

maximum load reached on the transformer in the

event of interruptions/outage on any one of the

transformer other transformer should take care of

existing load

13 132 kV BEED

(2009-10)

Beed 1)

2)

Add 1 X 50 MVA, 132/33 kV T/F with bays.

6 X 33 kV out lets.

Existing transformer capacity available in S/s is 1 X

25 & 1 X 50 MVA and load is 47 MVA.

Considering the maximum load reached on the

transformer in the event of interruptions/outage on

any one of the transformer other transformer

should take care of existing load

14 132 kV GANGAPUR

(2009-10)

Aurangabad 1)

2)

Add 1 X 25 MVA, 132/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in S/s is, 1

X 25, 1 x 16 MVA and load is 24 MVA.

Considering the maximum load reached on the

transformer in the event of interruptions/outage on

any one of the transformer other transformer

should take care of existing load

4 132KV

MANTHA S/S

(2008-09)

JALNA New S/s

5 132KV

GHANSAWANGI S/S

(2008-09)

JALNA New S/s

6 132 KV KINWAT S/S

(2008-09)

NANDED To Eliminate 66 KV level at Kinwat S/s.

136

Page 140: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 - W.E.F 01/04/2010

SR NO NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEME

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

AURANGABAD EHV CONSTRUCTION CUM (O&M) ZONE

TOTAL SCOPE OF WORK

15 132 kV OMERGA

(2009-10)

Osmanabad 1)

2)

Add 1 X 25 MVA , 132/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in S/s is 1 X

25, 1 x 16 MVA and load is 30 MVA. Considering

the maximum load reached on the transformer in

the event of interruptions/outage on any one of the

transformer other transformer should take care of

existing load

16 132 kV SILLOD

(2009-10)

Aurangabad 1)

2)

Add1 X 50 MVA, 132/33 kV T/F with bays.

6 X 33 kV out lets.

Existing transformer capacity available in S/s is 2 X

25 & 1 X 50 MVA and load is 54 MVA.

Considering the maximum load reached on the

transformer in the event of interruptions/outage on

any one of the transformer other transformer

should take care of existing load

17 132 kV TAMSA

(2009-10)

Nanded 1)

2)

Add 1 X 25 MVA A, 132/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in s/s is 1 X

25 & 1 X 12.5 MVA. And the load reached is 24

MVA Considerig the maximum load reached on the

transformer in the event of interruptions/outage on

any one of the transformer other transformer

should take care of existing load..

18 132 kV ELICHPUR

(2009-10)

Aurangabad 1)

2)

Add 1 X 25 MVA A, 132/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in s/s is 2 X

25 MVA. And the load reached is 35 MVA

Considerig the maximum load reached on the

transformer in the event of interruptions/outage on

any one of the transformer other transformer

should take care of existing load..

19 132 kV PARBHANI

(2009-10)

Parbhani 1)

2)

Add 1 X 50 , 132/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in s/s is 1 X

50 & 1 X 25 MVA. And the load reached is 45 MVA

Considerig the maximum load reached on the

transformer in the event of interruptions/outage on

any one of the transformer other transformer

should take care of existing load..

20 132 kV GEORAI

(2009-10)

Beed 1)

2)

Add1 X 25 MVA , 132/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in s/s is 2 X

25MVA. And the load reached is 24 MVA

Considerig the maximum load reached on the

transformer in the event of interruptions/outage on

any one of the transformer other transformer

should take care of existing load..

21 132 kV PISHOR

(2009-10)

Aurangabad 1)

2)

Add1 X 25 MVA , 132/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in s/s is 1 X

25MVA. And the load reached is 13 MVA

Considerig the maximum load reached on the

transformer in the event of interruptions/outage on

any one of the transformer other transformer

should take care of existing load..

22 132 kV JALNA-I

(2009-10)

Jalna 1)

2)

Add1 X 25 MVA , 132/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in s/s is 2 X

25MVA. And the load reached is 24 MVA

Considerig the maximum load reached on the

transformer in the event of interruptions/outage on

any one of the transformer other transformer

should take care of existing load..

23 132 kV NANDED-I

(2009-10)

Nanded 1)

2)

Add1 X 25 MVA , 132/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in s/s is 2 X

50MVA. And the load reached is 53 MVA

Considerig the maximum load reached on the

transformer in the event of interruptions/outage on

any one of the transformer other transformer

should take care of existing load..

24 132 kV HARSOOL

(2009-10)

Aurangabad 1)

2)

Add 1 X 50 MVA, 132/33 kV T/F with bays.

6 X 33 kV out lets.

Existing transformer capacity available in S/s is 2 X

50 MVA and load is 47 MVA. Considering thr

maximum load reached on the transformer in the

event of interruptions/outage on any one of the

transformer other transformer should take care of

existing load

137

Page 141: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 - W.E.F 01/04/2010

SR NO NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEME

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

AURANGABAD EHV CONSTRUCTION CUM (O&M) ZONE

TOTAL SCOPE OF WORK

1 220 KV PADEGAON S/S

(2008-09)

AURANGABAD 1) 1 X (200-100) MVA, 220/132 KV ICT WITH BAYS Existing transformer capacity available in S/s is,

220/132 - 4 x 100 - 282

Considering the maximum load reach on the

transformer, in event of interruption/outage on any

one of the transformer other transformer should

take care of existing load so as to avoid load

shedding.

1) 1 X (50-25) MVA, 220/33 KV T/F WITH BAYS

2) 33 KV OUTLET - 2 NOS.

1) 1X (200-100) 220/132 KV ICTS WITH BAYS

2) 132KV BAY - 4 NO.

1) 2X(50-25) MVA,132/33KV T/FS WITH BAYS

2) 33 KV OUTLETS - 4 NOS.

1) REP.(200-80)MVA, 220/132 KV T/F WITH BAYS

2) 132KV BAYS - 2 NOS

1) 2 X (50-25) MVA, 132/33 KV T/F WITH BAYS

2) 33 KV OUTLETS - 8 NOS.

1) 2X(50-25) 132/33 KV T/FS WITH BAYS

2) 33 KV OUTLETS - 8 NOS.

1) 1X(25-16) MVA, 132/33 KV T/F WITH BAYS

1x (50-25)MVA,132/33kv

2) 2X33 KV OUTLETS

3) 8 X 33KV OUTLETS

1) 1 X (50-25) MVA, 132/33 KV T/F WITH BAYS

2) 33 KV OUTLET - 4 NOS.

AUGMENTATION OF S/S BY REPLACEMENT OF T/F

6 132 KV KALAMB S/S

(2008-09)

OSMANABAD Existing transformer capacity available in S/s

is,132/33 - 2 x 25 - 43.1 load

Considering the maximum load reach on the

transformer, in event of interruption/outage on any

one of the transformer other transformer should

take care of existing load so as to avoid load

shedding.

NANDED

132 KV BEED S/S

(2008-09)

BEED Existing transformer capacity available in S/s

is,132/33 - 2 x 25 - 43.82 load

Considering the maximum load reach on the

transformer, in event of interruption/outage on any

one of the transformer other transformer should

take care of existing load so as to avoid load

shedding.

3 220 KV BEED S/S

(2008-09)

BEED Existing transformer capacity available in S/s

is,220/132 - 2 x 100 - 147 load

Considering the maximum load reach on the

transformer, in event of interruption/outage on any

one of the transformer other transformer should

take care of existing load so as to avoid load

shedding.

5 220KV NANDED II S/S

(WAGHALA)

(2008-09)

Existing transformer capacity available in S/s

is,220/132 - 1 x 200 - 120 load

220/132 - 1 x 150 - 83 load

220/132 - 1 x 80 - 57 load

Considering the maximum load reach on the

transformer, in event of interruption/outage on any

one of the transformer other transformer should

take care of existing load so as to avoid load

shedding.

132 KV OMERGA S/S

(2008-09)

LATUR Existing transformer capacity available in S/s

is,132/33 - 1 x 25 - 19 load

132/33 - 1 x 16 - 12 load

Considering the maximum load reach on the

transformer, in event of interruption/outage on any

one of the transformer other transformer should

take care of existing load so as to avoid load

shedding.

9 132 KV JALNA MIDC

S/S

(2008-09)

JALNA Existing transformer capacity available in S/s

is,132/33 - 2 x 25 - 44 load

Considering the maximum load reach on the

transformer, in event of interruption/outage on any

one of the transformer other transformer should

take care of existing load so as to avoid load

shedding.

7

8

4 220KV NANDED II

(WAGHALA) S/S

(2008-09)

NANDED Existing transformer capacity available in S/s

is,132/33 - 2 x 25 - 36 load

Considering the maximum load reach on the

transformer, in event of interruption/outage on any

one of the transformer other transformer should

take care of existing load so as to avoid load

shedding.

2 220 KV MURUD S/S

(2008-09)

LATUR Existing transformer capacity available in S/s is,

220/33 - 1 x 25 - 22.33

220/33 - 2 x 50 - 58.20

Considering the maximum load reach on the

transformer, in event of interruption/outage on any

one of the transformer other transformer should

take care of existing load so as to avoid load

shedding.

138

Page 142: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 - W.E.F 01/04/2010

SR NO NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEME

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

AURANGABAD EHV CONSTRUCTION CUM (O&M) ZONE

TOTAL SCOPE OF WORK

1) 1X (50-25)MVA, 132/33KV T/FS WITH BAYS

2) 33 KV OUTLET - 4 NOS.

1) 1X(50-25) MVA, 132/33 KV T/FS WITH BAYS

2) 8X33KV OUTLETS

1) 1 X (50-12.5) MVA, 132/33 KV T/FS WITH BAYS

2) 33 KV OUTLET - 4 NOS.

1) 1 X (50-25) MVA, 132/33 KV T/FS WITH BAYS

2) 33 KV OUTLET - 8 NOS.

1) 2X(50-25)MVA, 132/33KV T/FS WITH BAYS

2) 8 X 33KV OUTLETS

1) 1 X (50-25/12.5) MVA, 132/33 KV T/F WITH BAYS

2) 33 KV OUTLET - 4 NOS.

1) 1 X (50-25) MVA, 132/33 KV T/F WITH BAYS

2) 33 KV OUTLET - 4 NOS.

17 132 KV PARLI S/S

(2008-09)

BEED 1) 2X(50-25) MVA, 132/33 KV T/FS WITH BAYS Existing transformer capacity available in S/s

is,132/33 - 2 x 25 - 44.4

Considering the maximum load reach on the

transformer, in event of interruption/outage on any

one of the transformer other transformer should

take care of existing load so as to avoid load

shedding.

10 132KV CHIKALTHANA

S/S

(2008-09)

AURANGABAD Existing transformer capacity available in S/s

is,132/33 - 2 x 25 - 41load

Considering the maximum load reach on the

transformer, in event of interruption/outage on any

one of the transformer other transformer should

take care of existing load so as to avoid load

shedding.

11 132 KV PAITHAN S/S

(2008-09)

AURANGABAD Existing transformer capacity available in S/s

is,132/33 - 2 x 25 - 30 load

Considering the maximum load reach on the

transformer, in event of interruption/outage on any

one of the transformer other transformer should

take care of existing load so as to avoid load

shedding.

12 132 KV KANNAD S/S

(2008-09)

AURANGABAD Existing transformer capacity available in S/s

is,132/33 -2 x 12.5 - 13 load

132/33 - 1 x 10 - 5 load

Considering the maximum load reach on the

transformer, in event of interruption/outage on any

one of the transformer other transformer should

take care of existing load so as to avoid load

shedding.

13 132 KV VAIJAPUR S/S

(2008-09)

AURANGABAD Existing transformer capacity available in S/s

is,132/33 - 2 x 25 - 40 load

Considering the maximum load reach on the

transformer, in event of interruption/outage on any

one of the transformer other transformer should

take care of existing load so as to avoid load

shedding.

14 132KV KURUNDA S/S

(2008-09)

HINGOLI Existing transformer capacity available in S/s

is,132/33 - 2 x 25 - 29 load

Considering the maximum load reach on the

transformer, in event of interruption/outage on any

one of the transformer other transformer should

take care of existing load so as to avoid load

shedding.

15 132 KV JINTOOR S/S

(2008-09)

PARBHANI Existing transformer capacity available in S/s

is,132/33 - 1 x 25 - 15 load

132/33 - 1 x 10 - 8 load

Considering the maximum load reach on the

transformer, in event of interruption/outage on any

one of the transformer other transformer should

take care of existing load so as to avoid load

shedding.

AURANGABAD Existing transformer capacity available in S/s

is,132/33 - 2 x 25 - 37

Considering the maximum load reach on the

transformer, in event of interruption/outage on any

one of the transformer other transformer should

take care of existing load so as to avoid load

shedding.

16 132KV WALUJ

(2008-09)

139

Page 143: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 - W.E.F 01/04/2010

SR NO NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEME

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

AURANGABAD EHV CONSTRUCTION CUM (O&M) ZONE

TOTAL SCOPE OF WORK

1) 1X(25-16) MVA, 132/11 KV T/F WITH BAYS AT LATUR

MIDC S/S

2) 1X(25-10) MVA, 132/11 KV T/F WITH BAYS AT LATUR

S/S

3) 4X11KV OUTLETS

1) REP 1X(50-25) 132/33 KV T/FS WITH BAYS

2) 33 KV OUTLETS - 8 NOS.

1) 1X(50-25) MVA,132/33KV T/FS WITH BAYS

2) 33 KV OUTLETS - 8 NOS.

1) 1X(50-25) MVA,132/33KV T/FS WITH BAYS

2) 33 KV OUTLETS - 8 NOS.

1) 2 X (50-25/12.5) MVA, 132/33 KV T/F WITH BAYS

2) 33 KV OUTLET - 7 NOS.

1) 1 X (25-16) MVA, 132/33 KV T/F WITH BAYS

2) 33 KV OUTLET - 2 NOS.

1) 1X(50-25) MVA,132/33KV T/FS WITH BAYS

2) 33 KV OUTLETS - 4 NOS.

1) 1 X (50-16) MVA, 132/33 KV T/F WITH BAYS

2) 33 KV OUTLET - 2 NOS.

1) 1 X (25-12.5) MVA, 132/33 KV T/F WITH BAYS

2) 33 KV OUTLET - 2 NOS.

18 132 KV LATUR &

LATUR MIDC S/S

(2008-09)

LATUR Existing transformer capacity available in S/s

is,Latur MIDC 132/11 - 1 x 16 - 12.11

Latur-132/11 -2 x 10 - 16.8

Considering the maximum load reach on the

transformer, in event of interruption/outage on any

one of the transformer other transformer should

take care of existing load so as to avoid load

shedding.

19 132 KV NILANGA S/S

(2008-09)

LATUR Existing transformer capacity available in S/s

is,132/33 -2 x 25 - 44 load

Considering the maximum load reach on the

transformer, in event of interruption/outage on any

one of the transformer other transformer should

take care of existing load so as to avoid load

shedding.

20 132 KV JALNA (I) S/S

(2008-09)

JALNA Existing transformer capacity available in S/s

is,132/33 - 2 x 25 - 41load

Considering the maximum load reach on the

transformer, in event of interruption/outage on any

one of the transformer other transformer should

take care of existing load so as to avoid load

shedding.

21 132 KV AMBAD S/S

(2008-09)

JALNA Existing transformer capacity available in S/s is,

132/33 - 2 x 25 -45

Considering the maximum load reach on the

transformer, in event of interruption/outage on any

one of the transformer other transformer should

take care of existing load so as to avoid load

shedding.

22 132 KV PARTUR S/S

(2008-09)

JALNA Existing transformer capacity available in S/s is,

132/33 - 2 x 25 - 45

Considering the maximum load reach on the

transformer, in event of interruption/outage on any

one of the transformer other transformer should

take care of existing load so as to avoid load

shedding.

23 132 KV GANGAPUR

S/S

(2008-09)

AURANGABAD Existing transformer capacity available in S/s

is,132/33 - 1 x 25 - 17MW,132/33 - 1 x 16 -

12MWConsidering the maximum load reach on the

transformer, in event of interruption/outage on any

one of the transformer other transformer should

take care of existing load so as to avoid load

shedding.

BEED Existing transformer capacity available in S/s

is,132/33 - 2 x 25 - 44 MW Considering the

maximum load reach on the transformer, in event

of interruption/outage on any one of the

transformer other transformer should take care of

existing load so as to avoid load shedding.

25 132 KV NARSI S/S

(2008-09)

NANDED Existing transformer capacity available in S/s is,

132/33 - 1 x 25 - 16.5

132/33 - 1 x 16 - 10.2

Considering the maximum load reach on the

transformer, in event of interruption/outage on any

one of the transformer other transformer should

take care of existing load so as to avoid load

shedding.

26 132 KV TAMSA S/S

(2008-09)

NANDED Existing transformer capacity available in S/s is,

132/33 - 1 x 25 - 23

132/33 - 1 x 12.5 - 10

Considering the maximum load reach on the

transformer, in event of interruption/outage on any

one of the transformer other transformer should

take care of existing load so as to avoid load

shedding.

24 132 KV ASHTI S/S

(2008-09)

140

Page 144: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 - W.E.F 01/04/2010

SR NO NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEME

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

AURANGABAD EHV CONSTRUCTION CUM (O&M) ZONE

TOTAL SCOPE OF WORK

1) 1 X (25-12.5) MVA, 132/33 KV T/F WITH BAYS

2) 33 KV OUTLET - 2 NOS.

1) 1 X (50-25) MVA, 132/33 KV T/F WITH BAYS

2) 33 KV OUTLET - 2 NOS.

1) 1 X (25-10) MVA, 132/33 KV T/F WITH BAYS

2) 33 KV OUTLET - 2 NOS.

1) 1 X (50-25) MVA, 132/33 KV T/F WITH BAYS

2) 1X(200-100)MVA, 220/132KV ICT

3) 33 KV OUTLET - 4 NOS.

31 132 KV LATUR MIDC

S/S

(2008-09)

LATUR 1) 1 X (25-12.5) MVA, 132/33 KV T/F WITH BAYS Existing transformer capacity available in S/s is,

132/33 - 1 x 12.5 - 12.22

Additional transformer of 132/33 kV

25 MVA is being added during the year 2007-08 to

have redundancy during outage/interuption to cater

the load.So to take care of anticipated load growth

replcement is required.

32 132 KV RENAPUR S/S

(2008-09)

LATUR 1) 1 X (50-25) MVA, 132/33 KV T/F WITH BAYS Existing transformer capacity available in S/s is,

132/33 - 1 x 25 - 22.3

Additional transformer of 132/33 kV

25 MVA is being added during the year 2008-09 to

have redundancy during outage/interuption to cater

the load.So to take care of anticipated load growth

replacement is required.

1) 1 X (50-25) MVA, 132/33 KV T/F WITH BAYS

2) 33 KV OUTLET - 4 NOS.

1) 1X (50-25) MVA, 132/33 KV T/F WITH BAYS

2) 33 KV OUTLET - 4 NOS.

35 132 KV KAIJ

(2008-09)

BEED 1) 1X(50-25)MVA ,132/33KV TF 'S WITH BAYS To avoid loss of supply in case of outages or

interruptions on any one transformer

36 132KV BHOOM

(2008-09)

AURANGABAD 1) 1X(50-25)MVA ,132/33KV TF'S WITH BAYS To avoid loss of supply in case of outages or

interruptions on any one transformer

27 132 KV GEORAI S/S

(2008-09)

BEED Existing transformer capacity available in S/s is,

132/33 - 1 x 25 - 18.55

132/33 - 1 x 12.5 - 9.33

Considering the maximum load reach on the

transformer, in event of interruption/outage on any

one of the transformer other transformer should

take care of existing load so as to avoid load

shedding.

28 132 KV TELGAON S/S

(2008-09)

BEED Existing transformer capacity available in S/s is,

132/33 - 2 x 25 - 45MVA Considering the

maximum load reach on the transformer, in event

of interruption/outage on any one of the

transformer other transformer should take care of

existing load so as to avoid load shedding.

29 132 KV UJANI S/S

(2008-09)

OSMANABAD Existing transformer capacity available in S/s

is,132/33 - 1 x 25 - 15.5 , 132/33 - 1 x 10 - 8.22

.Considering the maximum load reach on the

transformer, in event of interruption/outage on any

one of the transformer other transformer should

take care of existing load so as to avoid load

shedding.

30 132 KV PARBHANI S/S

(2008-09)

PARBHANI Existing transformer capacity available in S/s is,

132/33 - 1 x 25 - 15.2

132/33 - 1 x 50 - 30.4

220/132- 2 x 100 - 143

Considering the maximum load reach on the

transformer, in event of interruption/outage on any

one of the transformer other transformer should

take care of existing load so as to avoid load

shedding.

33 132 KV LATUR (K) S/S

(2008-09)

LATUR Existing transformer capacity available in S/s is,

132/33 - 2 x 25 - 32.22

Considering the maximum load reach on the

transformer, in event of interruption/outage on any

one of the transformer other transformer should

take care of existing load so as to avoid load

shedding.

34 132 KV UDGIR S/S

(2008-09)

LATUR Existing transformer capacity available in S/s is,

132/33 - 2 x 25 - 38.66

Considering the maximum load reach on the

transformer, in event of interruption/outage on any

one of the transformer other transformer should

take care of existing load so as to avoid load

shedding.

141

Page 145: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 - W.E.F 01/04/2010

SR NO NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEME

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

AURANGABAD EHV CONSTRUCTION CUM (O&M) ZONE

TOTAL SCOPE OF WORK

37 132KV NALDURG

(2008-09)

LATUR 1) 1X(50-25)MVA ,132/33KV TF'S WITH BAYS To avoid loss of supply in case of outages or

interruptions on any one transformer

38 220 KV BEED S/S

(2009-10)

BEED 1) 1X (200-100) 220/132 KV ICTS WITH BAYS Existing transformer capacity available in S/s is

220/132kV, 2 x 100 MVA. And the load reached is

122 MVA. The transformer is replaced to meet the

anticipated load growth.

39 220 KV PADEGAON S/S

(2009-10)

AURANGABAD 1) 1 X (200-100) MVA, 220/132 KV ICT WITH BAYS Existing transformer capacity available in S/s is

220/132kV,4 X 100 MVA. The load reached is 233

mVA.The transformers are replaced to meet the

anticipated load growth.

40 220 KV PARLI

GIRAVALI

(2009-10)

BEED 1) 1 X (200-100) MVA, 220/132 KV ICT WITH BAYS Existing transformer capacity available in S/s is

220/132kV,3 X 100 MVA. The load reached is 144

MVA.The transformers are replaced to meet the

anticipated load growth.

41 220 kV NANDED-II

(WAGHALA)

(2009-10)

Nanded 1)

2)

1 X (50-25) MVA, 132/33 kV T/F with bays.

6 X 33 kV out lets.

Existing transformer capacity available in S/s is 1X

50MVA and load is 36 MVA. Considering the

maximum load reached on the transformer in the

event of interruptions/outage on any one of the

transformer other transformer should take care of

existing load growth

42 220 kV PARLI GIRWALI

(2009-10)

Beed 1)

2)

1 X (50-25) MVA, 132/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in S/s is 2 X

25 MVA and load is 26 MVA. The transformer is

replaced to meet anticipated load growth

43 132 kV HINGOLI

(2009-10)

Hingoli 1)

2)

Add 1 X (50-25) MVA , 132/33 kV T/F 4

X 33 kV out lets.

Existing transformer capacity available in S/s is 1 X

25,1 X 50 MVA and load is 32 MVA. Considering

the maximum load reached on the transformer in

the event of interruptions/outage on any one of the

transformer other transformer should take care of

existing load growth

44 132 kV WALUJ

(2009-10)

Aurangabad 1)

2)

Add 1 X (50-25) MVA , 132/33 kV T/F 4

X 33 kV out lets.

Existing transformer capacity available in S/s is 1 X

25,1 X 50 MVA and load is 32 MVA. Considering

the maximum load reached on the transformer in

the event of interruptions/outage on any one of the

transformer other transformer should take care of

existing load growth

45 132 kV CHIKHALTHANA

(2009-10)

Aurangabad 1)

2)

Add 1 X (50-25) MVA , 132/33 kV T/F 4

X 33 kV out lets.

Existing transformer capacity available in S/s is 2 X

25 MVA and load is 29.5 MVA. Considering the

maximum load reached on the transformer in the

event of interruptions/outage on any one of the

transformer other transformer should take care of

existing load growth

46 132 kV GANGKHED*

(2009-10)

Parbhani 1)

2)

Add 1 X (50-25) MVA , 132/33 kV T/F with bays.

2 X 33 kV out lets.

Existing transformer capacity available in S/s is 2 X

25 MVA and load is 33 MVA. Considering the

maximum load reached on the transformer in the

event of interruptions/outage on any one of the

transformer other transformer should take care of

existing load growth

47 132 kV JALNA MIDC

(2009-10)

Jalna 1)

2)

Add 1 X (50-25) MVA , 132/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in S/s is 2 X

25 MVA and load is 34 MVA. The transformer is

replaced to meet anticipated load growth

48 132 kV KANNAD

(2009-10)

Aurangabad 1)

2)

1 X (25-10) MVA, 132/33 kV T/F with bays

2 X 33 kV out lets.

Existing transformer capacity available in S/s is 2 X

12.5 MVA and load is 12 MVA. The transformer is

replaced to meet anticipated load growth

49 132 kV SILLOD *

(2009-10)

Aurangabad 1)

2)

1 X (50-25) MVA, 132/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in S/s is 2 X

25 MVA and load is 50 MVA. The transformer is

replaced to meet anticipated load growth

142

Page 146: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 - W.E.F 01/04/2010

SR NO NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEME

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

AURANGABAD EHV CONSTRUCTION CUM (O&M) ZONE

TOTAL SCOPE OF WORK

50 132 kV UDGIR

(2009-10)

Latur 1)

2)

1 X (50-25) MVA , 132/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in S/s is 2 X

25 MVA and load is 24 MVA. The transformer is

replaced to meet anticipated load growth

51 132 kV PAITHAN

(2009-10)

Aurangabad 1)

2)

1 X (50-25) MVA, 132/33 kV T/F with bays.

2 X 33 kV out lets.

Existing transformer capacity available in S/s is 2 X

25 MVA and load is 36 MVA. Considering the

maximum load reached on the transformer in the

event of interruptions/outage on any one of the

transformer other transformer should take care of

existing load growth

1) 2X200MVA, 220/132KV ICTS WITH BAYS

2) 2 X 50MVA, 220/33KV T/FS WITH BAYS

3) LILO ON 220 KV BABHALESHWAR - WALUJ LINE AT

DEOGAON RANGARI - 20 KMS

4) 132KV D/C LINE FROM 220 KV DEOGAON RANGARI

(ONE CKT WILL BE CONNECTED TO KANNAD AND

ANOTHER TO PISHOR) {PARTLY D/C AND PARTLY

SCDC} - 30 KM

5) 132KV VAIJAPUR- DEOGAON-RANGARI D/C LINE-

35KM

6) 132KV GANGAPUR - DEOGAON-RANGARI D/C LINE-

40KM

1) 220KV SAWANGI - BHOKARDHAN D/C LINE - 60 KMS

2) 220KV CHIKHALI - BHOKARDHAN D/C LINE - 60 KMS

3) 132KV BHOKARDHAN-SILLOD D/C LINE - 20 KMS

4) 2X100MVA, 220/132KV ICTS WITH BAYS

5) 2 X 50MVA, 220/33KV T/FS WITH BAYS

6) 4X132KV BAYS

7) 132KV LINE - 40 KM WITH BAYS

8) LILO ON 132KV RAJUR - JAFRABAD FOR

BHOKARDHAN-10 KM

1) 132KV LINE FROM 220 KV VALANDI - PANCHINCHOLI

D/C LINE - 20KMS

2) 2 X 25MVA, 132/33KV T/F'S WITH BAYS

3) 8X33KV OUTLETS

1) 132KV HINGOLI - SHENGAON D/C LINE - 30KMS

2) 2 X 25MVA, 132/33KV T/F'S WITH BAYS

3) 8X33KV OUTLETS

1) 132KV GANGAKHED - SONPETH D/C LINE - 40 KMS

WITH BAYS

2) 2 X 25MVA, 132/33KV T/F'S WITH BAYS

3) 8X33KV OUTLETS

1) 220KV D/C LINE FROM 400KV NANDED - 40 KM WITH

BAYS

2) 2X100MVA, 220/132KV ICTS WITH BAYS

3) 2X25MVA, 220/33KV T/FS WITH BAYS

4) 132 KV BHOKAR-HIMAYATNAGAR S/C 30 KM

5) 132 KV BHOKAR-TAMASA S/C 16 KM

6) 8X33KV OUTLETS

1) 132KV LINE FROM 220KV SHELU - PARTUR D/C LINE -

30KMS WITH BAYS

2) 2X100MVA, 220/132KV ICTS WITH BAYS

3) 132KV LINE FROM 220KV SHELU - PATHRI D/C LINE -

22KMS WITH BAYS

4) 220KV LINE FROM 220KV PARBHANI - 220KV SHELU

S/STN -40 KM

NEW SCHEMES

1 220KV DEOGAON

RANGARI S/S

(2010-11)

AURANGABAD Deogaon Rangari-220kV S/S is considered to

meet the load growth in Aurangabd Circle.

2 220KV

BHOKARDHAN S/S

(2010-11)

JALNA Present recorded loading on Sillod-132kv,

Jafrabad-132kV, and Pisor-132kV S/S are 45MW,

15MW, and 25MW respectively. It is anticipated by

the year 2010-11 the load will reach to about

110MW. Hence it is necessary to go in for new

220kV sub-station at Bhokardan.

3 132KV

PANCHINCHOLI S/S

(2010-11)

LATUR Present recorded peak load on Omerga-132kV

and Latur 132kV is 40MW and 50 MW

respectively. It is anticipated by the year 2010-11

the load will reach to about 120 MW. Hence it is

necessary to go in for new 132kV sub-station at

Panchincholi. The new substation Panchincholi-

132kV is proposed in year 2010-11 for reducing

loading on 132kV Nilanga and 132 Latur S/S.

4 132KV

SHENGAON S/S

(2010-11)

HINGOLI Sengaon-132kV S/S is considered to meet the

load growth in Hingoli District.

5 132KV

SONPETH S/S

(2010-11)

PARBHANI Present recorded peak load on Majalgaon-132kV,

Telgaon-132kV and Pathari 30 MW, 30 MW and

20MW. It is anticipated by the year 2010-11 the

load will reach to about 105MW. The new

substation Sonpeth –132kV S/S is proposed in

year 2010-11 for reducing loading on Majalgaon-

132kV, Telgaon-132kV and Pathari 132kV.

6 220KV BHOKAR S/S

(2011-12)

NANDED Present recorded peak on Umerkhed, Tamsa and

Kinwat 132kV S/S are 35, 36 and 20 MW

respectively. It is anticipated by the year 2011-12,

the load will reach about 97MW. Hence it is

necessary to go in for new 220kV sub-station at

Bhokar.

7 220KV

SHELU S/S

(2011-12)

PARBHANI This substation will help to meet the increased

load in Jalna & Parbhani district.

143

Page 147: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 - W.E.F 01/04/2010

SR NO NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEME

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

AURANGABAD EHV CONSTRUCTION CUM (O&M) ZONE

TOTAL SCOPE OF WORK

1) LILO OF 220KV SAWANGI - BHOKARDAN AT

PHULAMBRI D/C LINE - 25KMS WITH BAYS

2) 132 KV PHULAMBRI-RAJUR D/C WITH BAYS - 25 KM

3) 2 X 100MVA, 220/132KV ICTS WITH BAYS

4) 2 X 50 MVA, 220/33KV T/FS WITH BAYS

5) 12 X 33KV OUTLETS

1) 220KV D/C LINE FROM 400KV NANDED - KRISHNOOR -

30 KMS WITH BAYS

2) 2X200MVA, 220/132KV ICTS WITH BAYS

3) 2X50MVA, 220/33KV T/FS WITH BAYS

4) 132 KV KRISHNOOR - UMRI S/C-15 KM

5) 12 X 33KV OUTLETS

1) 220KV D/C LINE FROM 400KV NANDED TO JALKOT -

65 KMS

2) 2X100MVA, 220/132KV T/F WITH BAY

3) 132KV SCDC LINE TO DEGLOOR S/S - 20 KM

4) 132KV SCDC LINE TO AHAMEDPUR S/S - 20 KM

4) 132KV OUTLETS - 4 NOS

1) 220KV FROM CHITEGAON - PACHOD D/C WITH BAYS-

25KM

2) 132KV AMBAD - PACHOD D/C -30KM

3) 132KV GHANSAWANGI - PACHOD D/C- 30KM

4) LILO ON PAITHAN-GEORAI AT PACHOD- 20KM

5) 2X100MVA, 220/132KV T/F WITH BAY

6) 132KV OUTLETS - 4 NOS

1) 2 X 315 MVA, 400/220KV ICT'S WITH BAYS ,

1 X 105 MVA , 400/ 220 KV 1 PHASE ICT SPARE

2) LILO ON BOTH CKT OF 400 KV DC BHUSAWAL - II -

AURANGABAD - 15 KM

3) 220KV D/C LINE TO PADEGAON S/S -15 KMS WITH

BAYS

13 765KV

AURANGABAD S/S

(2012-13)

AURANGABAD BY PGCIL 400 KVD/C LINE FOR AURANGABAD-II S/S

FROM 765 KV AURANGABAD S/S

Evacuation of Power.

1) 2X500 MVA, 400/220 KV ICT'S WITH BAYS

2) LILO ON 400 KV PARLI (PG) - SOUTH SOLAPUR (PG)

S/C LINE - 10 KM

3) LILO ON 220KV MURUD - SOLAPUR (BALE) AT

OSMANABAD - 10KM

4) 220KV OSMANABAD-II - BARSHI S/C LINE -10KM

5) INTER LINK D/C LINES BETWEEN EXISTING

220 KV OSMANABAD - 400 KV OSMANABAD - 10KM

6) 220KV OSMANABAD-II - TULJAPUR D/C LINE - 40KM

A 66 KV KINWAT

66/33 1X10MVA,1X5MVA , 66/11 1X5MVA

B 66KV HINGOLI

66/33 2X10MVA, 66/11 1X10MVA

C 66 KV PUSAD

66/33 KV 2 x10MVA , 66/11 KV 2X10 MVA

D. 220/66kv PUSAD

220/66KV 2x50MVA,

8 220 KV

PHULAMBRI S/S

(2011-12)

AURANGABAD This substation will help to meet the increased

load in Aurangabad district.

9 220KV

KRISHNOOR S/S

(2011-12)

NANDED Krishnoor is considered to cater the increasing

loads in Nanded District.

10 220KV JALKOT S/S

(2011-12)

LATUR JALKOT 220kV S/S is considered to meet the load

growth and for reliable operation in Parli circle and

also to improve the voltage profile.

11 220KV PACHOD S/S

(2011-12)

AURANGABAD This S/Stn will help to meet the increased load in

Aurangabad district.

12 400/220 KV

AURANGABAD - II

S/S(PANDHARI

PIMPALGAON)

(2012-13)

AURANGABAD Evacuation of Power and to improve voltage

profile.

14 400/220KV

OSMANABAD S/S

(2013-14)

OSMANABAD To reduce the over loading of the existing 220 kV

network in Osmanabad area.To improve the

voltage profile and to meet the upcoming demand.

66KV LEVEL ELIMINATION

1 ELIMINATION OF 66 KV

LEVEL AT

AURANGABAD

NANDED A.132 KV Kinwat s/stn is in existance.To eliminate

66/11 KV at 66 kV Kinwat new 33 /11kv s/stn along

with 2x10 MVA T/F and 33 kv line from 132 kv

Kinwat s/stn is to be established by Discom at

Kinwat. After complition of above said work

66/11kv Kinwat s/stn will be absolate.

HINGOLI B.132 KV Hingoli s/stn is in existance.To eliminate

66/11 KV at 66 kV Hingoli a new 33 /11kv s/stn

alongwith 2x10 MVA T/F and 33 kv line from 132

kv Hingoli s/stn is to be established by Discom at

Hingoli. After complition of above said work

66/11kv Hingoli s/stn will be absolate.

YAVATMAL C.220 KV Pusad s/stn is in existance.To eliminate

66/33 KV & 66/11 KV T/Fs at Pusad s/stn, 2 nos

of new 33 kv s/stn alongwith 2x10 MVA T/F each

and 33 kv line from 220 kv Pusad s/stn

considering load centre are to be established by

Discom at Pusad. After complition of above said

work 66/33kv & 66/11 KV T/Fs at Pusad s/stn will

be absolate.

YAVATMAL D.On getting the above work done at

Sr.No. A, B & C the 220/66 kV 2X50MVA T/F at

220 kv Pusad will be absolate.

144

Page 148: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 - W.E.F 01/04/2010

SR NO NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEME

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

AURANGABAD EHV CONSTRUCTION CUM (O&M) ZONE

TOTAL SCOPE OF WORK

1 132KV LINK LINE

(2010-11)

BEED 1) 132KV PARANDA - KALAMB DC LINE - 66 KM 132kV Kalamb S/S is fed from 132kV Kaij S/s with

S/c line. Hence to provide uninterrupted supply

during planned outages it is necessary to add

proposed line

2 132KV LINK LINE

(2010-11)

BEED 1) 132KV ASHTI - RAIMOHA SCDC LINE - 40 KM 132kV Ashti S/S is fed from 220kV Ahemadnagar

S/s with S/c line. Hence to provide uninterrupted

supply during planned outages it is necessary to

add proposed line

3 132KV LINK LINE

(2010-11)

LATUR 1) 132KV AHMEDPUR - CHAKUR SCDC LINE - 22 KM 132kV Chakur S/S is Tapped on 132kV Harangul-

Udgir S/c line. Hence to provide uninterrupted

supply during planned outages it is necessary to

add proposed line

4 132KV LINK LINE

(2010-11)

OSMANABAD/

AHMEDNAGAR

1) 2ND CIRCUIT STRINGING OF 132 KV SCDC LINE FROM

PARANDA - KHARDA - 30 KM

Strengthening for wind power evacuation

5 132KV LINK LINE

(2010-11)

LATUR 1) 220KV JALKOT - UDGIR SCDC LINE - 25 KM 132kV Udgir S/S is fed from 220kV Harangul S/s

with S/c line. Hence to provide uninterrupted

supply during planned outages it is necessary to

add proposed line

6 132KV LINK LINE

(2010-11)

LATUR 1) 220KV JALKOT - DEGLOOR SCDC LINE - 27 KM 132kV Degloor S/S is fed from 132kV Narsi S/s

with S/c line. Hence to provide uninterrupted

supply during planned outages it is necessary to

add proposed line

7 132KV LINK LINE

(2010-11)

LATUR 1) 220KV JALKOT - AHMEDPUR SCDC LINE - 29 KM 132kV Ahemadpur S/S is Tapped on 132kV

Girwali-Renapur S/c line. Hence to provide

uninterrupted supply during planned outages it is

necessary to add proposed line

8 132KV LINK LINE

(2010-11)

PARBHANI 1) 132KV PURNA - BASMATH SCDC LINE - 21 KM 132kV Purna S/S is fed from 132kV Parbhani S/s

with S/c line. Hence to provide uninterrupted

supply during planned outages it is necessary to

add proposed line

9 132KV LINK LINE

(2011-12)

NANDED 1) 132KV NANDED - UMRI 2ND CKT STRINGING - 31.73 KM 132kV Umri S/S is fed from 132kV Nanded S/s

with S/c line. Hence to provide uninterrupted

supply during planned outages it is necessary to

add proposed line

10 132KV LINK LINE

(2011-12)

LATUR 1) 132KV UJANI - KILLARI SCDC LINE - 25 KM 132kV Killari S/S is Tapped on 132kV Ujani-

Omerga S/c line. Hence to provide uninterrupted

supply during planned outages it is necessary to

add proposed line

11 132KV LINK LINE

(2011-12)

JALNA 1) 132KV MAJALGAON - PATHRI SCDC LINE - 35KM To provide uninterrupted supply during planned

outages it is necessary to add proposed line

12 132KV LINK LINE

(2011-12)

JALNA 1) 132KV DUSARBID - MANTHA SCDC LINE - 36 KM To provide uninterrupted supply during planned

outages it is necessary to add proposed line

13 132KV LINK LINE

(2012-13)

JALNA 1) 132KV MAJALGAON - GEORAI SCDC LINE - 25KM To provide uninterrupted supply during planned

outages it is necessary to add proposed line

14 132KV LINK LINE

(2012-13)

PARBHANI 1) 132 KV HIMAYATNAGAR - UMARKHED LINE 2ND CKT

STRINGING - 28.6 KM

132kV Himayatnagar S/S is fed from 132kV

Umarkhed S/s with S/c line. Hence to provide

uninterrupted supply during planned outages it is

necessary to add proposed line

15 132KV LINK LINE

(2012-13)

LATUR 1) 132 KV LILO ON HARANGUL -UJANI SCDC LINE FOR

AUSA- 43KM

132kV Ausa S/S is Tapped on 132kV Harngul-

Ujani S/c line. Hence to provide uninterrupted

supply during planned outages it is necessary to

add proposed line

ADDITIONAL LINK LINES

ADDITIONAL LINK LINES FOR S/S WHERE ONLY SINGLE CKT AND SINGLE SOURCE IS AVAILABLE

As per the methodology stipulated in the guideline of State Grid Code Regulation No. 9.4

The intrastate transmission system shall be capable of withstanding the loss of most severe single infeed without loss of stability.

145

Page 149: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 - W.E.F 01/04/2010

SR NO NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEME

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

AURANGABAD EHV CONSTRUCTION CUM (O&M) ZONE

TOTAL SCOPE OF WORK

1 220 KV LINK LINE

(2010-11)

AURANGABAD 1) 220 KV SHENDRA -SAVANGI SCDC LINE - 25KM Since the existing 220kV Shendra-Savangi line is

critically loaded to an extent of 86 MW. Hence it is

suggested to add proposed line to reduce the

loading of existing line and to meet additional load

growth and contingency.

2 132KV LINK LINE

(2010-11)

BEED /

AHMEDNAGAR

1) LILO ON 132 KV PARLI - PARBHANI AT GANGAKHED

D/C - 15KM

Since the existing 132kV Gangakhed-Parli line is

getting loaded to an extent of 52 MW during Non-

coinsident peak condition. It is anticipated the load

will reach to about critical value by the year 2011-

12. Hence it is suggested to add proposed line to

reduce the loading of existing line and to meet

additional load growth and contingency.

3 132KV LINK LINE

(2010-11)

BEED/

AHMEDNAGAR

1) 132KV SCDC LINE FROM RAIMOHA-PATHARDI -

10KM

It is anticipated the load will reach to about critical

value in future. Hence it is necessary to propose

additional line to meet additional load growth and

contingency.

4 132KV LINK LINE

(2010-11)

BEED 1) 132KV SCDC LINE FROM PATODA - KHARDA -

15KM

It is anticipated the load will reach to about critical

value in future. Hence it is necessary to propose

additional line to meet additional load growth and

contingency.

5 132KV LINK LINE

(2010-11)

BEED 1) 132KV SCDC LINE FROM PATODA - RAIMOHA - 12KM It is anticipated the load will reach to about critical

value in future. Hence it is necessary to propose

additional line to meet additional load growth and

contingency.

6 132KV LINK LINE

(2012-13)

BEED 1) 132KV BEED - GEORAI LINE 2ND CKT STRINGING -

36KM

Since the existing 132kV Beed - Georai line is

loaded to an extent of 120 MW during Non-

Coinsident peak condition. It is anticipated the load

will reach to about critical value in future. Hence it

is necessary to propose additional line to meet

additional load growth and contingency.

7 132KV LINK LINE

(2012-13)

JALNA 1) 132KV SCDC LINE FROM 220KV PADEGAON-

HARSOOL - 15KM

It is anticipated the load will reach to about critical

value in future. Hence it is necessary to propose

additional line to meet additional load growth and

contingency.

8 220KV LINK LINE

(2012-13)

AURANGABAD 1) 220KV D/C LINE FROM 400KV WALUJ TO SAWANGI -

20KMS

It is anticipated the load will reach to about critical

value in future. Hence it is necessary to propose

additional line to meet additional load growth and

contingency.

9 132KV LINK LINE

(2012-13)

AURANGABAD 1) 132 KV D/C LINE FROM 220 KV PADEGAON TO

SAWANGI - 20KM

It is anticipated the load will reach to about critical

value in future. Hence it is necessary to propose

additional line to meet additional load growth and

contingency.

10 132KV LINK LINE

(2012-13)

BEED 1) CONVERSION OF TAP TO LILO OF 132KV PARLI -

RENAPUR LINE AT AHEMADPUR S/S BY 2ND CKT

STRINGING OF EXISTING AHEMADPUR LINE - 45KMS

It is anticipated the load will reach to about critical

value in future. Hence it is necessary to propose

additional line to meet additional load growth and

contingency.

11 220KV LINK LINE

(2012-13)

AURANGABAD 1) 220KV D/C LINE FROM 400KV BHUSAWAL TO CHIKHALI

- 70KMS

It is anticipated the load will reach to about critical

value in future. Hence it is necessary to propose

additional line to meet additional load growth and

contingency.

12 132KV LINK LINE

(2013-14)

AURANGBAD 1) 132KV LILO ON 2ND CIRCUIT PADEGAON - PAITHAN AT

132KV CHITEGAON - 10KM

Since the existing 132kV Padegaon - Harsool 3

ckts are loaded to an extent of 154 MW during Non-

Coinsident peak condition. It is anticipated the load

will reach to about critical value in future. Hence it

is necessary to propose additional line to meet

additional load growth and contingency.

13 132KV LINK LINE

(2013-14)

AURANGBAD 1) LILO OF 132KV PADEGAON- SAWANGI - BOTH CIRCUIT

AT CHIKHALTHANE- 10KM.

It is anticipated the load will reach to about critical

value in future. Hence it is necessary to propose

additional line to meet additional load growth and

contingency.

ADDITIONAL LINK LINES TO MEET DEMAND WITHOUT LOAD SHEDDING AND TO ENSURE RELIABILITY AND QUALITY OF SUPPLY

146

Page 150: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 - W.E.F 01/04/2010

SR NO NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEME

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

AURANGABAD EHV CONSTRUCTION CUM (O&M) ZONE

TOTAL SCOPE OF WORK

14 132KV LINK LINE

(2013-14)

JALNA 1) 132KV SCDC FROM 220 KV CHIKHALI TO JAFRABAD -

40 KM

It is anticipated the load will reach to about critical

value in future. Hence it is necessary to propose

additional line to meet additional load growth and

contingency.

1 220 KV LINK LINE

(2010-11)

BEED /LATUR/

OSMANABAD

1) 220KV GIRAVALI-HARANGOOL-MURUD SCDC LINE-55

KM

For System strengthning

2 132KV LINK LINE

(2010-11)

HINGOLI 1) 132KV AKHADA BALAPUR - 220KV HINGOLI SCDC LINE -

25 KM

Linking to 132 kV AkhadaBalapur S/S

3 132KV LINK LINE

(2010-11)

LATUR 1) 220KV VALANDI - UDGIR SCDC LINE - 35 KM Linking to Proposed 220 kV Valandi S/s

4 132KV LINK LINE

(2010-11)

LATUR 1) 132KV HARANGUL - LATUR (MIDC) SCDC LINE - 60 KM For System strengthning

5 132 KV LINK LINE

(2010- 11)

AURANGABAD -

AHMEDNAGAR

1) 132KV KHARDA -ASHTI D/C LINE - 35 KM Strengthening for wind power evacuation

6 132KV LINK LINE

(2011-12)

LATUR 1) 132KV NILANGA - PANCHINCHOLI SCDC LINE - 20 KMS Alternate source for proposed 132 kV

Panchincholi S/Stn.

7 132 KV LINK LINE

(2012- 13)

BEED 1) 132KV PANGRI -SONPETH D/C LINE - 15 KMS ALTERNATE SOURCE FOR PROPOSED 132 KV

PANGRI S/S

8 220KV LINK LINE

(2013-14)

JALNA 1) 220KV JALNA - SHELU D/C LINE - 70 KMS ALTERNATE SOURCE FOR PROPOSED 220 KV

SHELU S/S

9 220KV LINK LINE

(2013-14)

BEED 1) 220KV BEED - PACHOD D/C LINE - 70 KMS ALTERNATE SOURCE FOR PROPOSED 220 KV

PACHOD S/S

10 132KV LINK LINE

(2013-14)

AURANGABAD 1) 132KV SCDC LINE FROM 220 KV PHULAMBRI TO

PISHOR - 10 KMS

ALTERNATE SOURCE FOR PROPOSED 220 KV

PHULAMBRI S/S

11 132KV LINK LINE

(2013-14)

NANDED 1) 132KV SCDC LINE FROM 220 KV KRISHNOOR TO

PURNA - 35 KMS

ALTERNATE SOURCE FOR PROPOSED 220 KV

KRISHNOOR S/S

12 132KV LINK LINE

(2013-14)

NANDED 1) 132KV SCDC LINE FROM 220 KV KRISHNOOR TO

KANDHAR - 30 KMS

ALTERNATE SOURCE FOR PROPOSED 220 KV

KRISHNOOR S/S

13 220KV LINK LINE

(2014-15)

NANDED 1) 220KVMALEGAON (WASHIM) - HINGOLI D/C LINE - 40

KMS

ALTERNATE SOURCE FOR PROPOSED 220 KV

HINGOLI S/S

1 132 kV DEOLAI

(SATARA)

(2011-12)

Aurangabad 1)

2)

Add 1 X 25 MVA, 132/33 kV T/F with bay.

4 X 33 kV out lets

Existing Transformer capacity avaible is 1 X 25

MVA. And the load reached is20 MVATo avoid loss

of supply in case of outages or interruptions on

transformer.

1 220 KV PARBHANI S/S

(2010-11)

PARBHANI 1) 1 X 100 MVA, 220/132 KV ICT WITH BAYS The existing transformer capacity available is

220/132 kV, 2X100 MVA and the load reached is

136MVA.To avoid loss of supply in case of

outages or interruptions on any one transformer

additional transformer is proposed.

2 220 kV BEED

(2010-11)

Beed 1)

2)

Add 1 X 50 MVA, 220/33 kV T/F with bays.

6 X 33 kV out lets.

Creation of new 33kV level to meet the anticipated

load growth.

3 400 kV WALUJ

(2011-12)

Aurangabad 1)

2)

Add 1 X 50 MVA , 220/33 kV T/F with bays.

6 X 33 kV out lets.

Existing transformer capacity available in s/s is 1

X 50 MVA. And the load reached is 42 MVA

Considerig the maximum load reached on the

transformer in the event of interruptions/outage on

any one of the transformer other transformer

should take care of existing load

4 220 kV BEED

(2011-12)

Beed 1)

2)

Add 1 X 50 MVA, 220/33 kV T/F with bays.

6 X 33 kV out lets.

To meet the anticipated load growth.

5 132 kV LATUR

(2012-13)

Latur 1)

2)

Add 1 X 25 MVA, 132/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in S/s is 1 X

25 & 1 X 20 MVA and load is18 MVA. Considering

the maximum load reached on the transformer in

the event of interruptions/outage on any one of the

transformer other transformer should take care of

existing load

6 132 kV RENAPUR

(2012-13)

Latur 1)

2)

Add 1 X 25 MVA, 132/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in S/s is 2 X

25 MVA and load is 22 MVA. Considerig the

maximum load reached on the transformer in the

event of interruptions/outage on any one of the

transformer other transformer should take care of

existing load

ADDITIONAL LINK LINES FOR NEW S/S TO HAVE ALTERNATE SOURCE

AUGMENTATION OF S/S BY ADDITION OF ICT

AUGMENTATION OF S/S BY ADDITION WHERE ONLY SINGLE ICT IS AVAILABLE

AUGMENTATION OF S/S BY ADDITION TO REDUCE LOADING OF TRANSFORMER

147

Page 151: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 - W.E.F 01/04/2010

SR NO NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEME

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

AURANGABAD EHV CONSTRUCTION CUM (O&M) ZONE

TOTAL SCOPE OF WORK

1 220 KV BEED S/S

(2010-11)

BEED 1) 1X (200-100) 220/132 KV ICTS WITH BAYS Existing transformer capacity available in S/s is

220/132kV, 1 x 100 MVA and 1X 200 MVA. The

load reached is 132 MVA. The transformer is

replaced to meet the anticipated load growth.

2 220 KV PADEGAON S/S

(2010-11)

AURANGABAD 1) 1 X (200-100) MVA, 220/132 KV ICT WITH BAYS Existing transformer capacity available will be

220/132kV,3 X 100 MVA and 1 X 200 MVA.. The

load will reached 262 MVA.The transformers are

replaced to meet the anticipated load growth.

3 220 KV PARLI

GIRAVALI

(2010-11)

BEED 1) 1 X (200-100) MVA, 220/132 KV ICT WITH BAYS Existing transformer capacity available in S/s will

be 220/132kV,2 X 100 MVA and 1 X 200 MVA. The

load reachedwill be 162 MVA.The transformers are

replaced to meet the anticipated load growth.

4 400KV AURANGABAD

S/S

(2011-12)

AURANGABAD 1) 1X(500-315) MVA, 400/220 KV ICT WITH BAYS The existing transformer capacity available is

400/220 kV, 2X315 MVA and the laod reached is

510 MVA.The transformer is replaced to meet the

anticipated load growth.

5 132 kV GANGKHED

(2010-11)

Parbhani 1)

2)

Add 1 X (50-25) MVA , 132/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in S/s is 2 X

25 MVA and load is 33 MVA. Considering the

maximum load reached on the transformer in the

event of interruptions/outage on any one of the

transformer other transformer should take care of

existing load growth

6 132 kV JALNA MIDC

(2010-11)

Jalna 1)

2)

1 X (50-25) MVA , 132/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in S/s is 2 X

25 MVA and load is 34 MVA. The transformer is

replaced to meet anticipated load growth

7 132 kV UDGIR

(2010-11)

Latur 1)

2)

1 X (50-25) MVA , 132/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in S/s is 2 X

25 MVA and load is 24 MVA. The transformer is

replaced to meet anticipated load growth

8 132 kVPAITHAN

(2010-11)

Aurangabad 1)

2)

1 X (50-25) MVA, 132/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in S/s is 2 X

25 MVA and load is 36 MVA. The transformer is

replaced to meet anticipated load growth

9 220 kV PARLI GIRWALI

(2010-11)

Beed 1)

2)

1 X (50-25) MVA, 132/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in S/s is 2 X

25 MVA and load is 26 MVA. The transformer is

replaced to meet anticipated load growth

10 132 kV UJANI

(2011-12)

Latur 1)

2)

1 X (50-25) MVA, 132/33 kV T/F with bays.

4 X 33 kV out lets.

The transformer is replaced to meet anticipated

load growth

11 132 kV AUSA

(2011-12)

Latur 1)

2)

1 X (50-25) MVA, 132/33 kV T/F with bays.

4 X 33 kV out lets.

The transformer is replaced to meet anticipated

load growth

12 132 kV AHMEDPUR

(2012-13)

Latur 1)

2)

Add 1 X (50-25) MVA , 132/33 kV T/F 2

X 33 kV out lets.

Existing transformer capacity available in s/s is 1 X

25 & 1 X 50 MVA. And the load reached is 21 MVA

The transformer is replaced to meet anticipated

load growth..

13 132 kV UJANI

(2014-15)

Latur 1)

2)

Add 1 X (50-25) MVA , 132/33 kV T/F 2

X 33 kV out lets.

The transformer is replaced to meet anticipated

load growth

** 1No. TF COMMISSIONED IN 2009-10* COMMISSIONED IN 2009-10

AUGMENTATION OF S/S BY REPLACEMENT OF T/F

148

Page 152: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

EHV CC O&M ZONE :

AMRAVATI

149

Page 153: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 - W.E.F 01/04/2010

SR NO NAME OF THE SUBSTATION DISTRICT REMARKS / PURPOSE OF SCHEME

1) 2 x 25 MVA, 220/33 KV T/S WITH BAYS

2) 8 x 33 KV OUTLETS

3) 220 KV D/C LINE WARORA - WANI - 35 KM

4) 2X100MVA,220/132KV

5)132 KV Wani - Pandharkavda D/C line - 30 Kms (

Considered in Additional Link Line)

1) 2 X 25 MVA, 132/33 KV T/F

2) 132 KV D/C ON D/C TOWER ON LILO PARAS-

MALEGAON - 18 CKT.KM

3) 8 X 33 KV OUTLET

1) 132 KV D/C YAVATMAL TO GHATANJI S/S - 36

KM

2) 2X25 MVA, 132/33KV T/F WITH BAY

3) 33KV OUTLET - 8 NOS.

4) 132KV LINE BAY- 04NOS

1) 2X25MVA, 132/33KV T/FS WITH BAYS

2) 132KV D/C LINE FROM AKOLA MIDC S/STN TO

BARSHI TAKLI - 50 KM

3) 33KV OUTLETS - 08NOS

1) 2 X 25 MVA , 132/33KV T/F WITH BAY.

2) 132 KV D/C YAVATMAL TO PANDHARKAWADA -

60 KM

3) 33KV OUTLETS - 08NOS

1) 2X100MVA, 220/132KV ICTS WITH BAYS

2) 220KV BALAPUR - MALEGAON D/C LINE - 52

KM WITH BAYS

3) 132KV SCDC LINE FROM MALEGAON - II TO

PATUR - 25KM

4) 132KV REORIENTATION FROM OLD 132KV TO

PROPOSED 220KV MALEGAON S/STN -20KM

1)

2)

3)

LILO ON 220KV AMRAVATI -BADNERA AT

NANDGAON PETH - 10KMS WITH BAYS

2nd CKT STRINGING OF 220 KV AMARAVATI-

BADNERA-15 KM WITH BAYS

132 KV WARUD-NANDGAON PETH SCDC LINE-

50 KM WITH BAYS

4)

5)

2 X 50 MVA, 220/33KV T/FS WITH BAYS

2 X 100 MVA, 220/132KV T/FS WITH BAYS

6) 12 X 33KV OUTLETS

1) 2 X 100 MVA, 220/132KV T/FS WITH BAYS

2) 2 X 50 MVA, 220/33 KV T/FS WITH BAYS

3) LILO ON 220KV PUSAD - NANDED AT GHATODI

- 10 KMS WITH BAYS

4) LILO ON 132KV PUSAD - JAMBAZAR AT

GHATODI - 10 KMS WITH BAYS

5) LILO ON132KV PUSAD - DIGRAS AT GHATODI -

10 KMS WITH BAYS

6) 33 KV OUTLETS - 8 NOS

1) 2 X 25 MVA, 132/33 KV T/FS WITH BAYS

2) 132 KV DUSARBID - DEOLGAON RAJA D/C

LINE - 20 KM WITH BAYS

3) 33 KV OUTLETS - 8 NOS

1) 2 X 25 MVA, 132/33 KV T/FS WITH BAYS

2) 132 KV MURTIZAPUR D/C LINE FROM AKOLA -

220KV APATAPA S/STN- 45 KM WITH BAYS

3) 33 KV OUTLETS - 8 NOS

132 KV S/S

PANDHARKAWADA -II

(2009-10)

YAVATMAL

7 220 KV NANDGAON PETH S/S

(2009-10)

5 To eliminate 66kV level

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

AMRAVATI EHV CONSTRUCTION CUM (O&M) ZONE

SPILL OVER SCHEMES

TOTAL SCOPE OF WORK

4

VOLTAGE IMPROVEMENT & LOAD CATERING. 132

KV Wani - Pandharkavda D/C line - 30 Kms. Is

proposed in 2009 - 10.

2 132 KV PATUR S/S *(2008-09)

AKOLA It is necessary to go in for new 132kV sub-station at

Partur. The new substation Partur-132kV is proposed on

LILO of existing 132kV Paras-Malegaon line of 10kM in

year 2009-10 for reducing loading on Akola-132kV S/S.

1 220 KV WANI S/S

(2008-09)

YAVATMAL

132KV BARSHI-TAKLI S/S

(2008-09)

AKOLA VOLTAGE IMPROVEMENT & LOAD CATERING

3 132KV

GHATANJI S/S

(2008-09)

YAVATMAL VOLTAGE IMPROVEMENT & LOAD CATERING

6 220KV MALEGAON II S/S

(2009-10)

WASHIM Present recorded peak load on Malegaon-132kV,

Mehkar 132kV and Partur 132kV S/S are 26MW, 35

MW and 20 MW respectively. It is anticipated by the

year 2010-11 the load will reach to about 105MW.

Hence it is necessary to go in for 220kV sub-station at

Malegaon. By the commissioning of this substation,

voltage profile of Amaravathi Circle will improve.

AMRAVATI Amravati-MIDC 220kV S/S is considered for Amravati

industrial load.

9 132 KV DEOLGAON RAJA S/S

(2009-10)

BULDHANA Present recorded peak load on Jalna-132kV is 50MW. It

is anticipated by the year 2009-10 that the load will

reach to about 60MW. Hence it is necessary to go in for

new 132kV sub-station at Deolgaon-Raja.

8 220KV GHATODI S/S

(2009-10)

YAVATMAL Ghatodi-220 kV S/S is considered for reducing the

loading of Pusad-132kV & Digas-132kV S/S and also

for reducing the loading of existing 220/66kV

transformer at Pusad-220kV S/S. This S/Stn is

proposed for evacuation of power.

10 132 KV MURTIZAPUR S/S

(2009-10)

AKOLA Inplace of 132 kv Durgwada s/s as existing 132 kV

Durgwada S/s having sinking problem

150

Page 154: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 - W.E.F 01/04/2010

SR NO NAME OF THE SUBSTATION DISTRICT REMARKS / PURPOSE OF SCHEME

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

AMRAVATI EHV CONSTRUCTION CUM (O&M) ZONE

TOTAL SCOPE OF WORK

A 66KV AMRAVATI

66/33KV , 1 X 10 MVA

B 66/11KV AMRAVATI MIDC

66/11 KV, 2 X 10 MVA

C 66/33 KV MURTIZAPUR

66/33 KV , 2 X 5 MVA

D 66 KV KARANJA

66/33KV 2x10MVA , 66/11 KV,2 X 10 MVA

E 66/11 KV CHANDUR RLY.

66/11 KV 2 X 5 MVA

F 66/11 KV DHAMANGAON RLY

66/11 KV 2 X 5 MVA

G 66/33KV OF 132/66KV AMRAVATI

66/33 KV 1X10 MVA

H 132/66 KV PARAS

132/66 KV , 1X 25 MVA

1 132KV LINK LINE

(2008-09)

WASHIM 1) 132KV WASHIM - JAMBAZAR SCDC LINE - 43

KM

132kV Jambazar S/S is fed from 132kV Pusad S/s with

S/c line. Hence to provide uninterrupted supply during

planned outages it is necessary to add proposed line

2 132KV LINK LINE

(2008-09)

AMARAVTI 1) 132 KATOL - WARUD SCDC LINE -76 KM WITH

BAYS

132kV Katol S/S is fed from 132kV Kalmeshwar S/s with

S/c line. Hence to provide uninterrupted supply during

planned outages it is necessary to add proposed line

3 132KV LINK LINE

(2009-10)

AKOLA 1) 132 KV WASHIM - MANGURLPIR (STRINGING

ONLY) - 33 KM WITH BAYS

132kV Mangrulpir S/S is fed from 132kV Malegaon S/s

with S/c line. Hence to provide uninterrupted supply

during planned outages it is necessary to add proposed

line

4 132KV LINK LINE

(2009-10)

YAVATMAL 1) 132KV UMARKHED - GUNJ (STRINGING ONLY) -

21.67 KM

132kV Gunj S/S is fed from 132kV Pusad S/s with S/c

line. Hence to provide uninterrupted supply during

planned outages it is necessary to add proposed line

1 132KV LINK LINE

(2009-10)

YAVATMAL 1) LILO ON YAVATMAL - PANDHARKAWADA LINE

AT GHATANJI S/S - 15KM

Since 132kv D/C line from Yavatmal - Ghatanji S/Stn

proposed in year 2008-09 under new scheme is

practically not feasible so this alternate arrangement is

proposed.

1 132KV LINK LINE

(2009-10)

YAVATMAL 1) 132 KV WANI - PANDHARKAVDA D/C LINE - 30

KMS WITH BAYS

To have evacuation facility for open access

D.132kv Karanja s/stn is proposed during 2008-09.To

Eliminate 66 kV Karanja S/stn, new 33/11kv substation

with 3x 10 MVA T/F and 33 kv line from 132 Karanja

S/stn is to be established by DISCOM at Karanja. After

completing the said work the 66 kV, Karanja s/stn will be

absolate.

AKOLA

AMARAVATI

YAVATMAL F. 220 kV Dhamangaon s/stn is in existance.To

Eliminate 66 kV Dhamangaon Rly. S/stn, new 33/11kv

substation with 2x 5 MVA T/F and 33 kv line from 220 kv

Dhamangaon S/stn is to be established by DISCOM at

Dhamangaon Rly.After completing the said work the 66

kV, Dhamangaon RLy s/stn will be absolate.

STRENGTHENING FOR EVACUATION ARRANGEMENT

G. After completing work at Sr.No.A&B a 66/33 KV T/F

at 132/66 kv Amravati S/stn will be absolate.

H. After completion of works at Sr.No. A to G 132/66 kv

T/F at Amravati s/stn will be absolate and also 132/66

kv T/F at Paras s/stn will be absolate.

AKOLA

ADDITIONAL LINK LINES FOR NEW S/S TO HAVE ALTERNATE SOURCE

ADDITIONAL LINK LINES

ADDITIONAL LINK LINES FOR S/S WHERE ONLY SINGLE CKT AND SINGLE SOURCE IS AVAILABLE

66KV LEVEL ELIMINATION IN AMARAVATI, AKOLA DISTRICT

1 ELIMINATION OF 66KV LEVEL IN

AKOLA DISTRICT

(2008-09)

AMARAVATI A.To Eliminate 66 kV Amravati S/stn, new 33/11kv

substation with 2x 5 MVA T/F and 33 kv line from 220 kv

Amravati S/stn is to be established by DISCOM at

Amravati. After completing the said work the 66 kV,

Amravati s/stn will be absolate.

AMARAVATI B.To Eliminate 66 kV MIDC Amravati S/stn, new

33/11kv substation with 2x 10 MVA T/F and 33 kv line

from 220 kv Amravati S/stn is to be established by

DISCOM at MIDC Amravati. After completing the said

work the 66 kV, MIDC Amravati s/stn will be absolate.

AKOLA C. 132kv Murtizapur s/stn is proposed during 2009-

10.To Eliminate 66 kV Murtizapur S/stn, new 33/11kv

substation with 2x 5 MVA T/F and 33 kv line from 132

Murtizapur S/stn is to be established by DISCOM at

Murtizapur. After completing the said work the 66 kV,

Murtizapur s/stn will be absolate.

E. To Eliminate 66 kV Chandur Rly S/stn, new 33/11kv

substation with 2x 5 MVA T/F and 33 kv line from 220 kv

Dhamangaon S/stn is to be established by DISCOM at

Chandur Rly. After completing the said work the 66 kV,

Chandur Rly. s/stn will be absolate.

AMARAVATI

151

Page 155: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 - W.E.F 01/04/2010

SR NO NAME OF THE SUBSTATION DISTRICT REMARKS / PURPOSE OF SCHEME

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

AMRAVATI EHV CONSTRUCTION CUM (O&M) ZONE

TOTAL SCOPE OF WORK

1) 1X100MVA, 220/132KV ICT WITH BAY

2) 1X (50-25)MVA, 220/33 KV T/F

3) 132 KV BAYS - 2 NOS.

4) 2X33 KV OUTLETS

1) ADDL. 1X 25 MVA, 132/33KV T/F WITH BAYS

2) 4 X 33KV OUTLETS.

1) 1X25 MVA 220/33KV T/F

2) 33KV OUTLETS - 4NOS.

4 220KV CHIKHALI S/S

(2008-09)

BULDHANA 1)

2)

1 X 100MVA, 220/132KV ICT WITH BAYS

132 KV BAYS - 2 NOS.

To avoid loss of supply in case of outages or

interruptions on any one transformer

1) ADDL 1X25 MVA 132/33KV T/F WITH BAYS

2) 4 X 33KV OUTLETS.

1) 1X25MVA, 132/33KV T/F WITH BAYS

2) 33KV OUTLETS - 4 NOS.

1) 1X25 MVA, 132/33KV T/F WITH BAYS

2) 33 KV OUTLETS - 4 NOS.

1) ADD 1X25 MVA, 132/33KV T/F WITH BAYS

2) 33 KV OUTLETS - 4 NOS.

1) ADD 1X25 MVA, 132/33KV T/F WITH BAYS

2) 33KV OUTLETS - 4NOS.

1) ADD 1X25 MVA, 132/33KV T/F WITH BAYS

2) 33KV OUTLETS - 4NOS.

1) ADD 1X25 MVA, 132/33KV T/F WITH BAYS

2) 33KV OUTLETS - 4NOS.

1) ADD 1X25 MVA, 132/33KV T/F WITH BAYS

2) 33KV OUTLETS - 4NOS.

1) 1X25 MVA, 132/33KV T/F WITH BAYS

2) 33KV OUTLETS - 4NOS.

14 400kV AKOLA S/S

(2009-10)

Akola 1)

2)

3x105MVA , 400/220KV ICT WITH BAYS

220 KV BAYS - 3 NOS.

To avoid loss of supply in case of outages or interruption

on any one transformer

15 220 kV DHAMANGAON

(2009-10)

Yeotamal 1)

2)

Add 1 X 25 MVA, 220/33 kV T/F with bay.

4 X 33 kV out lets

Existing Transformer capacity avaible is 1 X 25 MVA. &

load reached is 4 MVA To avoid loss of supply in case

of outages or interruptions on transformer.

16 132 kV DARYAPUR

(2009-10)

Amaravati 1)

2)

Add 1 X25 MVA, 132/33 kV T/F with bays

4 x 33 kV outlets

Existing transformer capacity available in S/s is 1 X

25MVA and load is 11. MVA. The transformer is

replaced to meet anticipated load growth.

17 132 kV HIVERKHED

(2009-10)

Akola 1)

2)

Add 1 X 25 MVA, 132/33 kV T/F with bay.

4 X 33 kV out lets

Existing Transformer capacity avaible is 1 X 25 MVA. &

load reached is 7 MVA To avoid loss of supply in case

of outages or interruptions on transformer.

18 132 kV TIWSA

(2009-10)

Amaravati 1)

2)

Add 1 X 25 MVA, 132/33 kV T/F with bay.

4 X 33 kV out lets

Existing Transformer capacity avaible is 1 X 25 MVA.&

load reached is 8 MVA To avoid loss of supply in case

of outages or interruptions on transformer.

AMRAVATI To avoid loss of supply in case of outages or

interruptions on any one transformer

1 220KV PUSAD S/S

(2008-09)

YAVATMAL To avoid loss of supply in case of outages or

interruptions on any one transformer

5 132KV DUSARBID S/S

(2008-09)

3 220KV DHAMANGAON S/S *

(2008-09)

To avoid loss of supply in case of outages or

interruptions on any one transformer

BULDHANA

BULDHANA

AUGMENTATION OF S/S BY ADDITION OF T/F

AUGMENTATION OF S/S BY ADDITION WHERE ONLY SINGLE TRANSFORMER IS AVAILABLE

220KV AKOLA - II S/S *

(2008-09)

AKOLA To avoid loss of supply in case of outages or

interruptions on any one transformer

To avoid loss of supply in case of outages or

interruptions on any one transformer

2

7 132 KV DARYAPUR S/S

(2008-09)

AMRAVATI

6 132KV MOTALA

(2008-09)

To avoid loss of supply in case of outages or

interruptions on any one transformer

8 132 KV RISOD S/S *

(2008-09)

WASHIM To avoid loss of supply in case of outages or

interruptions on any one transformer

9 132KV DARWHA S/S*

(2008-09)

YAVATMAL To avoid loss of supply in case of outages or

interruptions on any one transformer

10 132KV UMERKHED S/S*

(2008-09)

YAVATMAL To avoid loss of supply in case of outages or

interruptions on any one transformer

11 132KV DIGRAS S/S*

(2008-09)

YAVATMAL To avoid loss of supply in case of outages or

interruptions on any one transformer

12 132KV JAMBAZAR S/S

(2008-09)

YAVATMAL To avoid loss of supply in case of outages or

interruptions on any one transformer

132KV GUNJ S/S

(2008-09)

YAVATMAL To avoid loss of supply in case of outages or

interruptions on any one transformer

13

152

Page 156: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 - W.E.F 01/04/2010

SR NO NAME OF THE SUBSTATION DISTRICT REMARKS / PURPOSE OF SCHEME

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

AMRAVATI EHV CONSTRUCTION CUM (O&M) ZONE

TOTAL SCOPE OF WORK

1 220KV YAVATMAL *

(2009-10)

YAVATMAL 1) 1X100 MVA, 220/132KV ICTS WITH BAYS Newly Introduced 220/132kV Level to feed 132 kV

Darwha S/s as an alternate source.

1) 1X25 MVA, 132/33KV T/F WITH BAYS

2) 33 KV OUTLETS - 4 NOS.

1) 2X25 MVA, 132/33KV T/F WITH BAYS

2) 33KV OUTLETS - 8 NOS.

1) 1X25 MVA, 132/33KV T/F WITH BAYS

2) 33KV OUTLETS - 4NOS.

1) REP.2X25MVA, 132/66KV T/FS BY 132/33KV

2) DOWN GRADATION OF 66KV TO 33KV S/S

1) 1X(200-150)MVA, 220/132KV ICT

2) 2X132KV BAYS

1) 1X(50-25)MVA, 220/33KV T/FS WITH BAYS

2) 33KV OUTLETS - 8 NOS.

1) 1 X (50 -25) MVA, 132/33KV T/FS WITH BAYS

2) 33 KV OUTLETS - 8 NOS.

1) 1X(25-12.5), 132/33KV T/FS WITH BAYS

2) 33KV OUTLETS - 4 NOS.

1) 1 x (25-10) MVA, 132/33 KV T/F

2) 33KV OUTLETS - 2 NOS.

1) 1X(50-25) MVA, 132/33KV T/FS WITH BAYS

2) 33 KV OUTLETS - 2 NOS.

8 132KV MORSHI S/S

(2008-09)

AMRAVATI 1) 1X(25-10), 132/33KV T/FS WITH BAYS Existing transformer capacity available in S/s is,

132/33 - 2 x 10 - 15.1 load

Considering the maximum load reach on the

transformer, in event of interruption/outage on any one

of the transformer other transformer should take care of

existing load so as to avoid load shedding.

ICT PROPOSED TO INTRODUCE 132 LEVEL.

AUGMENTATION OF S/S BY ADDITION TO REDUCE LOADING OF TRANSFORMER

1 132 KV ACHALPUR S/S*

(2008-09)

AMRAVATI Existing transformer capacity available in S/s is,

132/33 - 1 x 25 - 21.8 load

132/33 - 2 x 10 - 20.4 load

Considering the maximum load reach on the

transformer, in event of interruption/outage on any one

of the transformer other transformer should take care of

existing load so as to avoid load shedding.

2 132 KV LALKHEDI S/S * *

(2008-09)

AMRAVATI Existing transformer capacity available in S/s is,

132/33 - 2 x 16 - 13 load

Hence it is necessary to propose additional transformer

to meet additional load growth and contingency.

3 132KV AKOLA MIDC S/S

(2008-09)

AKOLA Existing transformer capacity available in S/s is,

132/33 - 2 x 25 - 29 load

Considering the maximum load reach on the

transformer, in event of interruption/outage on any one

of the transformer other transformer should take care of

existing load so as to avoid load shedding.

AUGMENTATION OF S/S BY REPLACEMENT OF T/F

5 132KV ANJANGAON*

(2008-09)

AMRAVATI Existing transformer capacity available in S/s is,

132/33 - 2 x 12.5 - 19.8 load

Considering the maximum load reach on the

transformer, in event of interruption/outage on any one

of the transformer other transformer should take care of

existing load so as to avoid load shedding.

6 132KV CHANDURBAZAR S/S

(2008-09)

AMRAVATI Existing transformer capacity available in S/s is,

132/33 - 2 x 10 - 19.4 load

Considering the maximum load reach on the

transformer, in event of interruption/outage on any one

of the transformer other transformer should take care of

1 220KV AMARAVATI S/S

(2008-09)

AMRAVATI To Eliminate 66 kV Level

2 220KV AMRAVATI S/S *

(2008-09)

AMRAVATI Existing transformer capacity available in S/s is,

220/132 - 1 x 150 - 114.5 load

220/132 - 1 x 100 - 80.2 load

Considering the maximum load reach on the

transformer, in event of interruption/outage on any one

of the transformer other transformer should take care of

existing load so as to avoid load shedding.

3 220KV YAVATMAL*

(2008-09)

YAVATMAL Existing transformer capacity available in S/s is,

132/33 - 2 x 25 - 37.2 load

Considering the maximum load reach on the

transformer, in event of interruption/outage on any one

of the transformer other transformer should take care of

existing load so as to avoid load shedding.

4 220KV CHIKHALI S/S *

(2008-09)

BULDHANA Existing transformer capacity available in S/s is,

132/33 - 2 x 25 - 19.3 load

The transformers are replaced to meet anticipated load

growth.

7 132KV MEHEKAR S/S *

(2008-09)

BULDHANA Existing transformer capacity available in S/s is,

132/33 - 2 x 25 - 24.2 load

Considering the maximum load reach on the

transformer, in event of interruption/outage on any one

of the transformer other transformer should take care of

existing load so as to avoid load shedding.

153

Page 157: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 - W.E.F 01/04/2010

SR NO NAME OF THE SUBSTATION DISTRICT REMARKS / PURPOSE OF SCHEME

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

AMRAVATI EHV CONSTRUCTION CUM (O&M) ZONE

TOTAL SCOPE OF WORK

9 132KV WARUD S/S *

(2008-09)

AMRAVATI 1) 1X(25-10), 132/33KV T/FS WITH BAYS Existing transformer capacity available in S/s is,

132/33 - 1 x 25 - 12.7load

132/33 - 1 x 10 - 5.06 load

The transformers are replaced to meet anticipated load

growth.

10 132KV

AKOT S/S**

(2008-09)

AKOLA 1) 2 X (50 -25) MVA, 132/33KV T/FS WITH BAYS Existing transformer capacity available in S/s is,

132/33 - 1 x 25, 1 x 10 - 31.78 load

Considering the maximum load reach on the

transformer, in event of interruption/outage on any one

of the transformer other transformer should take care of

existing load so as to avoid load shedding.

1) 1X(25-12.5), 132/33KV T/FS WITH BAYS

2) 33KV OUTLETS - 4 NOS.

12 220KV AKOLA S/S

(2009-10)

AMRAVATI 1) 1X(200-150) MVA, 220/132KV ICT WITH BAYS The existing transformer capacity available in S/s is

220/132kV 2 X 150 MVA.The load reached is 163 MVA.

The transformer is replaced to meet the anticipated load

growth.

13 220 KV CHIKHALI S/S

(2009-10)

BULDHANA 1) 1X(200-100) MVA, 220/132KV ICT WITH BAYS The existing transformer capacity available in S/s is

220/132kV 2 X 100 MVA.The load reached is

138MVA.The transformer is replaced to meet the

anticipated load growth.

14 132 KV MORSHI

(2009-10)

Amaravati 1)

2)

1 X (50-25) , 132/33 kV T/F with bays.

2 X 33 kV out lets.

Existing transformer capacity available in s/s is 1 X 10 &

1 X 25 MVA. And the load reached is 10 MVA

TConsidering the maximum load reached on the

transformer in the event of interruptions/outage on any

one of the transformer other transformer should take

care of existing load

15 132 KV MEHKAR *

(2009-10)

Buldana 1)

2)

1 X (50-25) MVA , 132/33 kV T/F with bays.

2 X 33 kV out lets.

Existing transformer capacity available in S/s is 2 X 25

MVA and load is 44 MVA. The transformer is replaced

to meet anticipated load growth.

16 220 KV CHIKHALI *

(2009-10)

Buldana 1)

2)

2 X (50-25) MVA, 132/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in s/s is 1 X 50 &

1 X 25 MVA. And the load reached is 24 MVA

TConsidering the maximum load reached on the

transformer in the event of interruptions/outage on any

one of the transformer other transformer should take

care of existing load

11 132KV ANJANGAON S/S

(2008-09)

AMRAVATI Existing transformer capacity available in S/s is,

132/33 -2 x 12.5 - 19.8 load

Considering the maximum load reach on the

transformer, in event of interruption/outage on any one

of the transformer other transformer should take care of

existing load so as to avoid load shedding.

154

Page 158: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 - W.E.F 01/04/2010

SR NO NAME OF THE SUBSTATION DISTRICT REMARKS / PURPOSE OF SCHEME

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

AMRAVATI EHV CONSTRUCTION CUM (O&M) ZONE

TOTAL SCOPE OF WORK

1) 220KV LINE FROM 400KV AKOLA -

ANJANGAON D/C LINE - 45KMS WITH BAYS

2) 2 X 100MVA, 220/132KV ICTS WITH BAYS

3) 2 X 50 MVA, 220/33KV T/FS WITH BAYS

4) 4 X 132KV BAYS

5) 12 X 33KV OUTLETS

6) LILO ON 132KV KATOL -132KV ANJANGAON

S/S AT 220KV ANJANGAON NEW S/STN-14 KM 7) LILO ON 132KV ACHALPUR -132KV

ANJANGAON S/S FOR 220KV ANJANGAON 8) 132KV SCDC LINE TOD ARYAPUR S/S- 30 KM

WITH BAYS1) 2 X 25 MVA, 132/33 KV T/FS WITH BAYS

2) 132 KV FROM 220KV BALAPUR - JALGAON

JAMOD D/C LINE-30 KM WITH BAYS

3) 33 KV OUTLETS - 8 NOS

1) 2 X 25 MVA, 132/33 KV T/FS WITH BAYS

2) 132 KV YAVATMAL - YAVATMAL MIDC D/C

LINE - 13 KM WITH BAYS

3) 33 KV OUTLETS - 8 NOS

1) 2 X 100 MVA, 220/132 KV T/FS WITH BAYS

2) 220 KV D/C KALMESHWAR -WARUD - 70 KM

WITH BAYS

3) 132 KV OUTLETS - 4 NOS

4) 132 KV D/C LINE TO WARUD- I S/S -5 KM WITH

BAYS

5) LILO OF 132 KV WARUD - MORSHI S/S AT

220KV WARUD - 30 KM

1) 765/400 KV , 4 X 500 MVA , 1 - PHASE ICT'S

WITH BAYS

2) 765 KV AKOLA -II - AURANGABAD 2 X S/C

QUAD LINE - 420 KM

3) 400KV LINE FROM AKOLA - II - AKOLA -I D/C

QUAD

A 66 KV DARWHA

(66/33 KV,1X10 MVA, 66/11 KV 1 X5 MVA)

B 66 KV DIGRAS

(66/11KV, 2X 5 MVA, 66/33 KV 1 X 10 MVA)

C 66 KV GHATANJI

66/33 KV,2X10 MVA

D 66 KV PANDHARKAVDA

66/33 2x10 ,66/11 KV, 2 X 5 MVA

E 220/66 KV YAVATMAL

(220/66 KV, 1X 50 MVA)

NEW SCHEMES

2 132 KV S/S AT JALGAON - JAMOD

(2010-11)

BULDHANA Jalgaon Jamod is considered for catering increasing

loads in Buldhana District.

1 220 KV ANJANGAON II S/S

(2010-11)

YAVATMAL It is necessary to go in for 220kV sub-station at

Anjangaon. Anjangaon-220kV S/S is fed from

Amaravathi by constructing 220kV D/C line of 52kM

length.

3 132 KV YAVATMAL MIDC S/S

(2010-11)

YAVATMAL Yavatamal MIDC –132kV S/S is considered for the

Industrial load coming in year 2010-11.

4 220KV WARUD II S/S

(2011-12)

AMRAVATI To meet the increased load in that area.

5 765/400 KV AKOLA -II S/S

( 2012-13)

AKOLA Evacuation of Power.

66KV LEVEL ELIMINATION IN AMARAVATI, AKOLA DISTRICT

1 ELIMINATION OF 66KV LEVEL IN

YAVATMAL DISTRICT

(2010-11)

YAVATMAL A.132kv Darwha s/stn is in existance.To Eliminate 66

kV Darwha S/stn, new 33/11kv substation with

2x 5 MVA T/F and 33 kv line from 132 Darwha S/stn is

to be established by DISCOM at Darwha. After

completing the said work the 66 kV, Darwha s/stn will be

absolate.

B.132kv Digras s/stn is in existance.To Eliminate 66 kV

Digras S/stn, new 33/11kv substation with 2x 10 MVA

T/F and 33 kv line from 132 Digras S/stn is to be

established by DISCOM at Digras. After completing the

said work the 66 kV, Digras s/stn will be absolate.

C.132kv Ghatanji s/stn is proposed during 208-09.To

Eliminate 66 kV Ghatanji S/stn, new 33/11kv substation

with 2x 10 MVA T/F and 33 kv line from 132 Ghatanji

S/stn is to be established by DISCOM at Ghatanji. After

completing the said work the 66 kV, Ghatanji s/stn will

be absolate.

D.132 kv Pandarkavda s/stn is proposed during 2009-

10.To Eliminate 66 kV Pandharkavda S/stn,new

33/11kv substation with 3x 10 MVA T/F and 33 kv line

from 132 kv Pandharkavda S/stn is to be established by

DISCOM at Pandharkavda. After completing the said

work the 66 kV, Pandharkavda s/stn will be absolate.

E. After getting the above work done at Sr.No. A,B,C&D

the 220/66 kv T/F at 220 kv Yavatmal S/stn.will be

absolate.

155

Page 159: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 - W.E.F 01/04/2010

SR NO NAME OF THE SUBSTATION DISTRICT REMARKS / PURPOSE OF SCHEME

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

AMRAVATI EHV CONSTRUCTION CUM (O&M) ZONE

TOTAL SCOPE OF WORK

1 132KV LINK LINE

(2010-11)

YAVATMAL 1) 132KV DIGRAS - DARWHA SCDC LINE - 27 KM 132kV Darwha S/S is fed from 132kV Digraj S/s with S/c

line. Hence to provide uninterrupted supply during

planned outages it is necessary to add proposed line

2 132KV LINK LINE

(2011-12)

AMRAVATI 1) 132KV DARYAPUR - ANJANGAON SCDC LINE -

30 KM

132kV Daryapur S/S is fed from 132kV Durgwada S/s

with S/c line. Hence to provide uninterrupted supply

during planned outages it is necessary to add proposed

line

3 132KV LINK LINE

(2011-12)

AKOLA 1) 132KV DC LINE FROM 132KV MURTIZAPUR -

RAILWAY TSS - 15KM

System Strengthining.

4 132KV LINK LINE

(2011-12)

YAVATMAL 1) 132KV SCDC LINE FROM 132KV YAVATMAL -

DARVA - 40 KM

System Strengthining.

5 132KV LINK LINE

(2011-12)

AKOLA 1) 2ND CIRCUIT STRINGING OF 132KV AKOT-

HIWARKHED LINE-20 KM

132 kV Hiwarkhed S/s. is fed from 132 kV Akot S/s. with

S/C line. Hence to provide uninterrupted supply during

planned outages it is necessary to add proposed line

6 132KV LINK LINE

(2012 - 13 )

AMRAVATI 1) 2ND CIRCUIT STRINGING OF 132KV KATOL-

BHARSHINGI-WARUD LINE-50 KM

System Strengthining.

7 132KV LINK LINE

(2012 - 13 )

BULDHANA 1) 2ND CIRCUIT STRINGING OF 132KV CHIKHALI -

DHAD LINE - 22 KM

132 kV Dhad S/s. is fed from 132 kV Chikhali S/s. with

S/C line. Hence to provide uninterrupted supply during

planned outages it is necessary to add proposed line

1 220KV LINK LINE

(2010-11)

WARDHA 1) 220KV WARDHA II -YAVATMAL SCDC LINE - 80

KM WITH BAYS

Since the existing 220kV Wardha-I-Yavatmal S/c line is

critically loaded to an extent of 263 MW. Hence it is

suggested to add proposed line to reduce the loading of

existing line and to meet additional load growth and

contingency.

1 220KV LINK LINE

(2011-12)

AKOLA 1) 220 KV AKOLA -BALAPUR (MIDC) D/C LINE - 27

KM WITH BAYS

To have evacuation facility for additional 1 x 250 MW for

gen at Paras

2 220KV LINK LINE

(2011-12)

YAVATMAL 1) 220KV GHATODI - WANI D/C -320KM To have evacuation facility for open access

1 220KV LINK LINE

(2011-12)

HINGOLI 1) 220 KV D/C LINE FROM GHATODI - HINGOLI

SCDC LINE -85 KM WITH BAYS

Additional Line is considered to

strengthen the Network

2 132KV LINK LINE

(2012-13)

AKOLA 1) 132KV SCDC LINE FROM 132KV MURTIZAPUR -

KARANJA - 35KM

Additional Line is considered to

strengthen the Network

3 132KV LINK LINE

(2012-13)

BULDHANA 1) 132KV SCDC LINE FROM 132KV DEOLGAON

RAJA - DHAD -50KM

Additional Line is considered to

strengthen the Network

4 132KV LINK LINE

(2012-13)

BULDHANA 1) 132KV SCDC LINE FROM 132KV JALGAON

JAMOD - HIWARKHED - 40KM

Additional Line is considered to

strengthen the Network

1 220KV YAVATMAL

(2010-11)

YAVATMAL 1) 1X100 MVA, 220/132KV ICTS WITH BAYS

132KV BAYS - 2NOS

Newly Introduced 220/132kV Level to feed 132 kV

Darwha S/s as an alternate source.

1 132 kV CHANDUR BAZAR *

(2010-11)

Amaravati 1)

2)

1 X 25 MVA , 132/33 kV T/F with bays.

4X 33 kV out lets.

Existing transformer capacity available in s/s is 1X 25 &

1 X 10 MVA. And the load reached is 22 MVA

Considering the maximum load reached on the

transformer in the event of interruptions/outage on any

one of the transformer other transformer should take

care of existing load

2 220 kV DHAMANGAON

(2013-14)

YAVATMAL 1)

2)

Add 1 X 25 MVA, 220/33 kV T/F with bay.

4 X 33 kV out lets

Existing Transformer capacity avaible is 1 X 25 MVA. &

load reached is 4 MVA To avoid loss of supply in case

of outages or interruptions on transformer.

1 220 KV AKOLA S/S

(2010-11)

AMRAVATI 1) 1X(200-150) MVA, 220/132KV ICT WITH BAYS

132KV BAYS - 2NOS

The existing transformer capacity available in S/s is

220/132kV 1 X 150and 1 X 200 MVA.The load reach will

be 175 MVA.The transformer is replaced to meet the

anticipated load growth.

2 220 KV CHIKHALI S/S (2010-

11)

BULDHANA 1) 1X(200-100) MVA, 220/132KV ICT WITH BAYS

132KV BAYS - 2NOS

The existing transformer capacity available in S/s is

220/132kV 1 X 100and 1 X 200 MVA.The load will be

reach156 MVA.The transformer is replaced to meet the

anticipated load growth.

3 220KV WANI S/S

(2010-11)

1)

2)

1 X (50-25) MVA , 220/33 kV T/F with bays.

2 X 33 kV out lets.

To cater upcoming load & for redundacy.

4 132 KV MEHKAR

(2010-11)

Buldana 1)

2)

1) 1 X (50-25) MVA , 132/33 kV T/F with bays.

2) 2 X 33 kV out lets.

Existing transformer capacity available in S/s is 2 X 25

MVA and load is 44 MVA. The transformer is replaced

to meet anticipated load growth.

5 132 KV AKOT *

(2011-12)

Akola 1)

2)

1 X (50-25) MVA , 132/33 kV T/F with bays.

2 X 33 kV out lets.

Existing transformer capacity available in s/s is 2 X

25MVA. And the load reached is 23 MVA The

transformer is replaced to meet anticipated load growth.

6 220KV WANI S/S

(2011-12)

1)

2)

1 X (50-25) MVA , 220/33 kV T/F with bays.

2 X 33 kV out lets.

To cater upcoming load & for redundacy.

ADDITIONAL LINK LINES

ADDITIONAL LINK LINES FOR S/S WHERE ONLY SINGLE CKT AND SINGLE SOURCE IS AVAILABLE

ADDITIONAL LINK LINES TO MEET DEMAND WITHOUT LOAD SHEDDING AND TO ENSURE RELIABILITY AND QUALITY OF SUPPLY

STRENGTHENING FOR EVACUATION ARRANGEMENT

AUGMENTATION OF S/S BY REPLACEMENT OF ICT/TF

ADDITIONAL LINK LINES FOR NEW S/S TO HAVE ALTERNATE SOURCE

AUGMENTATION OF S/S BY ADDITION OF ICT/ TF

AUGMENTATION OF S/S BY ADDITION WHERE ONLY SINGLE TRANSFORMER IS AVAILABLE

AUGMENTATION OF S/S BY ADDITION TO REDUCE LOADING OF ICT/TF

156

Page 160: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 - W.E.F 01/04/2010

SR NO NAME OF THE SUBSTATION DISTRICT REMARKS / PURPOSE OF SCHEME

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

AMRAVATI EHV CONSTRUCTION CUM (O&M) ZONE

TOTAL SCOPE OF WORK

7 132 KV AKOT *

(2012-13)

Akola 1)

2)

1 X (50-25) MVA , 132/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in s/s is 2 X

25MVA. And the load reached is 23 MVA The

transformer is replaced to meet anticipated load growth.

* * * 1 No. TF. COMMISSIONED IN 2009 - 10.COMMISSIONED IN 2009 - 10

157

Page 161: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

EHV CC O&M ZONE :

NAGPUR

158

Page 162: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 -W.E.F 01/04/2010

SR

NO

NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEME

1) 132 KV DC LINE FROM 220 KV HINGANGHAT

S/S - 24 KM

2) 2 x 25 MVA, 132/33 KV T/F WITH BAYS

3) 8 x 33 KV OUTLETS

1) 132 KV D/C LINE FROM ASGOAN TO

LAKHANDUR 46 KM

2) 2 X 25 MVA, 132/33 KV T/F WITH BAYS

3) 33 KV OUTLET - 8 NOS.

1) A) ESTABLISHMENT OF 220/132/33 KV S/S

WITH 2x50MVA, 220/33 KV T/F AT

UPPALWADI

B) ESTABLISHMENT OF 220/132/33 KV S/S

WITH 2x100 MVA, 220/132 KV ICT, 2x50MVA,

220/33 KV T/F AT MANKAPUR

C) ESTABLISHMENT OF 220/132/33 KV S/S

WITH 2x100 MVA, 220/132 KV ICT, 1x50MVA,

220/33 KV T/F AT NEW PARDI

D) ESTABLISHMENT OF 220/132/33 KV S/S

WITH 2x100 MVA, 220/132 KV ICT AT

BUTIBORI II

E)2x50MVA, 220/33 KV T/F AT BUTIBORI III

CONSTRUCTION OF 220 KV LINK LINES

CONNECTING THE SUBSTATIONS ON NAGPUR

RING MAIN, viz.

i) 220 KV Khaperkheda - Uppalwadi D/C line

O/H - 12KM & U/G - 1 KM

ii)220KV UPPALWADI - MANKAPUR M/C line

O/H - 8KM & U/G - 2.5KM

iii)220KV UPPALWADI - PARDI M/C line

O/H - 13.5KM & U/G - 0.5KM

iv) 220KV NEW PARDI -BUTTIBORI III D/C line

1)M/C line from Pardi to Loc . No 68 of Ex. 132KV

line 21KM

2)Only stringing from Loc. No 68 to 47 on M/C tower

6KM

3)D/C line from Loc . No 68 of Ex. 132KV line to

Butibori III 14.5KM & U/G - 1KM ( Pardi end)

v) 220KV OLD BUTTIBORI - BUTTIBORI III with

reorientation near Old B'bori -D/C on M/C line - 1.5

KM

Only stringing on M/c towers of 220KV Koradi-

Butibori 38KM & U/G - 0.5KM ( M/C near A'zari

end)

220KV AMBAZARI - MANKAPUR M/C line

O/H - 13KM & U/G - 4KM

i) IInd ckt. stringing of 220KV Kanhan Umred

O/H : 51 KM & LILO of same at Pardi S/s

O/H : 7 KM U/G : 4KM

ii) LILO ON KHAPARKHEDA (OLD) - WARDHA

FOR BUTTIBORI III D/C on M/C line- 1 KM

Additional Lines : i) 132 KV M/C Butibori I to

Butibori II line for reorientation at Butibori II - 5 km

O/H : 3.5KM U/G : 1.5KM

2) ii)220 KV D/C Tower line for reorientation at Butibori

II - 1 KM

iii) Reorientation of 132KV lines at Mankapur

(0.5KM), Pardi (0.5KM)

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

NAGPUR EHV CONSTRUCTION CUM (O&M) ZONE

TOTAL SCOPE OF WORK

1 132 KV JAM S/S

(2008-09)

WARDHA

SPILL OVER SCEHEMES

VOLTAGE IMPROVEMENT & LOAD CATERING

2 132KV LAKHANDUR S/S

(2008-09)

BHANDARA VOLTAGE IMPROVEMENT & LOAD CATERING

3 NAGPUR RING MAIN

MANKAPUR

NEW PARDI

NEW BUTTIBORI

(2008-09)

NAGPUR 220kV Uppalwadi, Mankapur, New Pardi, New

Buttibori S/S are considered to meet the load

growth and to improve the voltage profile in Nagpur

circle.

159

Page 163: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 -W.E.F 01/04/2010

SR

NO

NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEME

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

NAGPUR EHV CONSTRUCTION CUM (O&M) ZONE

TOTAL SCOPE OF WORK

1) 2X50 MVA 132/33KV T/FS WITH BAYS

2) 132KV LILO ON MANKAPUR-HINGNA -I AT

LENDRA - 16 CKM O/H : 7CKM & U/G : 9CKM

3) LILO ON 132KV AMBAZARI - HINGNA -I AT

LENDRA S/STN -10KM

4) 12 X 33KV OUTLETS.

1)*

SCOPE OF WORK BY MSETCL

LILO ON 220KV WARDHA-I - BADNERA S/C TO

WARDHA (PGCIL) - 10 KMS WITH BAYS

2) 220KV LINE FROM PGCIL WARDHA 400KV -

GHATODI D/C LINE-50 KM WITH BAYS

3) LILO OF 220KV BHUGAON - PUSAD S/C AT

400KV WARDHA(PG) - 15KM

1) 400KV WARDHA (PG) - WARORA - 70 KM

(ALREADY CONSIDERED IN CHANDRAPUR

EVA.)

2) 2 X 500 MVA 400/220 KV ICT'S WITH BAYS

3) LILO ON ONE CIRCUIT OF 220 KV WARDHA-II

(BHUGAON) - WARORA D/C LINE AT 400 KV

WARORA - 10KM

1) 2 X 100 MVA, 220/132 KV T/FS WITH BAYS

2) 2 X 50 MVA, 220/33 KV T/FS WITH BAYS

3)

i)

(A) 220 KV MC ON MC LINES (0.4 SQ.MM

ACSR ZEBRA COND.)

i ) KHAPARKHEDA (OLD) - UPPALWADI D/C -

12.6 KM (O/H -11.8KM & U/G -0.8KM.)

ii) UPPALWADI - MANKAPUR D/C - 10 KM (O/H -

7.5KM & U/G -2.5KM).

III) UPPALWADI - PARDI -D/C - 15 km (O/H -

14.5KM & U/G -0.5KM)

4) REORIENTATION OF 132KV LINES-20KM

5) 33 KV OUTLETS - 12 NOS.

1) 2 X 25MVA, 132/33KV T/FS WITH BAYS

2) 132KV KATOL-BHARSHINGI-WARUD SCDC

LINE-50 KM

3) 33KV BAYS - 08 NOS

2 220 KV BALLARSHAH S/S

(2009-10)

CHANDRAPUR 1)

2)

2X25 MVA 220/33KV T/FS WITH BAYS

220 KV CHANDRAPUR-MIDC-BALLARSHAH

D/C LINE-20 KM

ELIMINATION OF 66 KV LEVEL

3 132KV PULGAON S/S

(2009-10)

WARDHA 1)

2)

3)

4)

2X25MVA 132/33KV T/FS WITH BAYS

132 KV WARDHA-II-PULGAON D/C LINE-15 KM

132KV PULGAON - ARVI - 35 KM

8X33KV OUTLETS

ELIMINATION OF 66 KV LEVEL

4 132KV SAHULI S/S

(2009-10)

NAGPUR 1)

2)

3)

4)

2X25MVA 132/33KV T/FS WITH BAYS

LILO ON 132 KV BHANDARA-AMBHORA AT

SAHULI-5 KM

132 KV PARDI - SAHULI SCDC LINE - 25 KM

WITH BAYS

8X33KV OUTLETS

ELIMINATION OF 66 KV LEVEL

1) 2 X 25 MVA, 132/33 KV T/FS WITH BAYS

2) 132 KV ASHTI - ALAPPALI D/C LINE - 35 KM

3) 33 KV OUTLETS - 8 NOS

1) 2 X 25 MVA, 132/33 KV T/FS WITH BAYS

2) 132 KV YETAPALLI - ALAPPALI D/C LINE - 35

KM

3) 33 KV OUTLETS - 8 NOS

ELIMINATION OF 66 KV LEVEL1 132KV BHARSHINGI

(2008-09)

NAGPUR

Wardha-PGCIL is constructed by PGCIL.

5 132 KV ALLAPALLI

(2009-10)

GADCGHIROLI Allapali-132kV S/S is considered to cater increasing

loads in Chandrapur circle and to eliminate 66 kv

level.

4 132KV GIS LENDRA S/S

(2008-09)

NAGPUR VOLTAGE IMPROVEMENT & LOAD CATERING

5

7 220 KV

UPPALWADI S/S

(2009-10)

NAGPUR

WARDHA400KV WARDHA (PG) *

(2009-10)

6 400KV WARORA S/S

(2009-10)

WARDHA Warora 400kV station is proposed to take care of

open access consumer’s power injections and feed

the area.

NEW SUBSTATION TO ELIMINATE 66 KV LEVEL

6 132 KV YETAPALLI

(2009-10)

GADCGHIROLI Yetapalli-132kV S/S is considered to cater

increasing loads in Chandrapur circle and to

eliminate 66 kv level.

220kV Uppalwadi S/S IS considered to meet the

load growth and to improve the voltage profile in

Nagpur circle.

160

Page 164: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 -W.E.F 01/04/2010

SR

NO

NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEME

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

NAGPUR EHV CONSTRUCTION CUM (O&M) ZONE

TOTAL SCOPE OF WORK

A 66 KV TUMSAR

66/11KV 2x5 MVA and 66/33 kV 1x5

MVA,1x3MVA

B 66 KV MORGAON ARJUNI

66/33KV, 1X5MVA, 66/11 2X5MVA

C 132kV MADGI

132/66 kv 2x25 MVA

A 66 KV SEVAGRAM

66/11 KV 2X10 MVA

B 66 KV NANDURI

2X10 MVA 66/33KV, 1X5 MVA 66/11KV

C 66KV SONEGAON

2x5MVA 66/11kv

D 66 KV PULGAON

66/33 KV 1 X 5MVA, 66/11 KV 2 X 5MVA

E 66KV HINGANGHAT

2X10MVA 66/11KV, 1X5MVA 66/11KV

F 66/11 KV SELDOH

2x5MVA 66/11KV

G 66 KV SEL00

1 X 10MVA 66/11 KV

H 66 KV WARDHA -I

66/11 KV, 3 X 10 MVA

I 220/66 KV WARDHA -I

220/66 KV, 2 X 50 MVA

H. To eliminate 66/11 kv T/Fs at Wardha - I s/stn.

new 33 kv s/stn alongwith 3x10 MVA T/F and 33 kv

line from 220 kv Wardha - I s/stn. is to be

established by Discom at Wardha.After completion

of above said work 66/11 kv T/Fs at Wardha - I

s/stn will be absolate.

I. After completing all the works at Sr.No. A to H the

2x50 MVA 220/66 kv T/F at 220 kv Wardha will be

absolate.

66KV LEVEL ELIMINATION

1 ELIMINATION OF 66KV

LEVEL AT MADGI,

TIRODA, SAHULI,

GONDIA, TUMSAR IN

BHANDARA & GONDIA

DISTRICT

(2008-09)

BHANDARA &

GONDIA

A.132kv Tumsar s/stn is proposed during 2011-

12.To eliminate 66 kV Tumsar s/stn, new 33 /11kv

s/stn alongwith 2x10 MVA T/F and 33 kv line from

132 kv Tumsar s/stn is to be established by

DISCOM at Tumsar. After complition of above said

work 66/11kv Tumsar s/stn will be absolate.

B. 132KV Morgaon Arjuni s/stn is proposed during

2010-11.To eliminate 66/11 KV at 66 kV Morgaon

Arjuni new 33 /11kv s/stn alongwith 2x5 MVA T/F

and 33 kv line from 132 kv Morgaon Arjuni s/stn is

to be established by Discom at Morgaon Arjuni after

complition of above said work 66/11kv s/stn will be

absolate.

C. After getting the above work the 132/66 kv

2 X 25MVA T/F at 132 kv Madgi s/stn will be

absolate.

2 ELIMINATION OF 66KV

LEVEL IN WARDHA

DISTRICT 2009-10

WARDHA A. To eliminate 66 kv Sewagram s/stn, a new 33 kv

s/stn with 2x10 MVA T/F and 33 kv line from 220 kv

Wardha s/stn is to be established by DISCOM.After

completing this work 66 kv Sewagram s/stn will be

absolate.

B. To eliminate 66 kv Nanduri s/stn, new 33 kv s/stn

alongwith 3x10MVA T/F and 33 kv line from 220 KV

Hinganghat substation is to be established by

Discom at Nanduri.After compltion of above said

work 66kv Nanduri s/stn will be absolate.

C. To eliminate 66 kv sonegaon s/stn, new 33 kv

s/stn alongwith 2x5 MVA T/F and 33 kv line from

132kv Khapri s/stn.is to be established by Discom

at sonegaon.after completion of above said work 66

kv Sonegaon s/stn will be absolate.

D. To eliminate 66 kv Pulgaon s/stn. a new 33 kv

s/stn with 2x10 MVA T/F and 33 kv line from 220 kv

Wardha s/stn is to be established by DISCOM.After

completing this work 66 kv Pulgaon s/stn will be

absolate.

E. 220/33 kv Hinganghat s/stn.is in existance.To

eliminate 66 kv Hinganghat s/stn, new 33 kv s/stn.

with 3x10 MVA T/F alongwith 33 kv line from 220

KV Hinganhat s/stn is to be established by discom.

F. 132 kv Seloo is proposed during 2009-10.To

eliminate 66 KV Seldoh s/stn new 33 /11kv s/stn

alongwith 2x5 MVA T/F and 33 kv line from 132 kv

Seloo S/stn. is to be established by Discom at

Seldoh after complition of above said work 66kv

Seldoh s/stn will be absolate.

G. 66 KV consumer M/s.NOBLE EX is connected to

66 kv seloo s/stn. Now the consumer is PD. 132 kv

seloo s/stn is proposed to be commossioned during

2009-10.To eliminate 66 kv Seloo s/stn new 33 kv

s/stn alongwith 2x5 MVA T/F and 33 kv line from

132kv seloo s/stn. is to be established by Discom at

Seloo. After completion of said work 66 kV seloo

s/stn will be absolate.

161

Page 165: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 -W.E.F 01/04/2010

SR

NO

NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEME

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

NAGPUR EHV CONSTRUCTION CUM (O&M) ZONE

TOTAL SCOPE OF WORK

1 132KV LINK LINE

(2008-09)

NAGPUR 1) 132KV KALMESHWAR - SAONER (STRINGING

ONLY) - 49 KM

132kV Saoner S/S is fed from 132kV Kalameshwar

S/s with S/c line. Hence to provide uninterrupted

supply during planned outages it is necessary to

add proposed line

2 132KV LINK LINE

(2008-09)

BHANDARA 1) 132 KV KARDHA - ASGAON LINE (2ND

CIRCUIT STRINGING ) - 58 KM WITH BAYS

132kV Asgaon S/S is fed from 132kV Kardha S/s

with S/c line. Hence to provide uninterrupted supply

during planned outages it is necessary to add

proposed line

3 132KV LINK LINE

(2008-09)

NAGPUR 1) 132 KV KATOL - SAONER D/C with 2nd CKT

LILO at 220 KV KATOL

132kV Saoner S/S is fed from 132kV Kalameshwar

S/s with S/c line. Hence to provide uninterrupted

supply during planned outages it is necessary to

add proposed line for the connectivity at 220KV

Katol S/stn

4 132KV LINK LINE

(2008-09)

GONDIA 1) 132 KV AMGAON -AMGAON TSS SCDC LINE -

5 KM

To avoid overloading on 132 kV Amgaon-TSS-

Gondia S/c the additional 132 kV Amgaon-TSS -

Amgaon S/c is proposed

5 132KV LINK LINE

(2008-09)

WARDHA 1) 132 KV WARDHA-II-HINGANGHAT D/C LINE-

28.1 KM (OH LINE-27.1KM ,U/G CABLE-

1.011KM)

To Eliminate 66 kV level at Hinganghat S/s.

6 132KV LINK LINE

(2008-09)

NAGPUR 1) 132 KV BUTTIBORI - KHAPRI D/C LINE - 25 KM

WITH BAYS

For Strengthing of Nagpur Ring Main

1 220KV LINK LINE

(2009-10)

NAGPUR 1) 2ND CKT STRINGING OF 220KV KANHAN-

UMRED LINE AND LILO OF THIS CIRCUIT AT

NEW PARDI S/STN -56 KM

Since 220kV M/C line from New Pardi- Umred

proposed in earlier plan is practically not feasible so

this alternate line is proposed.

2 132KV LINK LINE

(2009-10)

NAGPUR 1) STRINGING OF 2ND CKT FROM 132 KV

KHAPRI - BUTTIBORI LINE - 20 KM WITH

BAYS

Since the existing 132kV Khapri-Besa S/c line is

loaded to an extent of 38 MW and 132kV Khapri-

Hingana-I S/c line is loaded to an extent of 43 MW

during Non-Coinsident peak condition. It is

anticipated the load will reach to about critical value

by the year 2011-12 due to load growth in the

vicinity of Khapri. Hence it is necessary to add

additional line to meet additional load growth and

contingency.

3 132KV LINK LINE

(2009-10)

GONDIA 1) LILO ON ONE CKT OF 132 KV GONDIA -

AMGAON TSS AT AMGAON S/STN - 5 KM

Since 132kV Amgaon TSS - Amgaon S/S -5km

proposed in year 2008-09 is practically not feasible

this alternate line is proposed .

1 132KV LINK LINE

(2009-10)

NAGPUR 1) 132 KV KALMESHWAR - HINGANA - I -

HINGANA -II D/C LINE - 25 KM WITH BAYS

For Strengthing of Nagpur Ring Main

1 220KV LINK LINE

(2009-10)

CHANDRAPUR 1) LILO ON 220KV CHANDRAPUR MIDC -

GADCHANDUR LINE AT WANI -30KM

Strengthening for Chandrapur Evacuation

1) ADDL. 1X25 MVA 220/33 KV T/F WITH BAYS

2) 4 X 33 KV OUTLETS

1)

2)

1 X 100MVA, 220/132KV ICTS WITH BAYS

132 KV BAYS - 2 NOS.3) 1 X 25MVA, 132/33KV T/FS WITH BAYS

4) 4 X 33KV OUTLETS.

1) ADDL. 1X 25 MVA, 132/33KV T/F WITH BAYS

2) 4 X 33KV OUTLETS.

1) ADDL. 1X 25 MVA, 132/33KV T/F WITH BAYS

2) 4 X 33KV OUTLETS.

1) ADDL. 1X 25 MVA, 132/33KV T/F WITH BAYS

2) 4 X 33KV OUTLETS.

132KV

DEOLI S/S

(2008-09)

WARDHA To avoid loss of supply in case of outages or

interruptions on any one transformer

3 132KV

MUL S/S

(2008-09)

CHANDRAPUR To avoid loss of supply in case of outages or

interruptions on any one transformer

4 132KV

ARVI S/S

(2008-09)

CHANDRAPUR To avoid loss of supply in case of outages or

interruptions on any one transformer

2 220KV

VIRUR S/S

(2008-09)

WARDHA To avoid loss of supply in case of outages or

interruptions on any one transformer

5

ADDITIONAL LINK LINES

ADDITIONAL LINK LINES FOR S/S WHERE ONLY SINGLE CKT AND SINGLE SOURCE IS AVAILABLE

ADDITIONAL LINK LINES TO MEET DEMAND WITHOUT LOAD SHEDDING AND TO ENSURE RELIABILITY AND QUALITY OF SUPPLY

ADDITIONAL LINK LINES FOR NEW S/S TO HAVE ALTERNATE SOURCE

STRENGTHENING FOR EVACUATION ARRANGEMENT

AUGMENTATION OF S/S BY ADDITION OF T/F

AUGMENTATION OF S/S BY ADDITION WHERE ONLY SINGLE TRANSFORMER IS AVAILABLE

1 220KV WARORA S/S *

(2008-09)

CHANDRAPUR Existing transformer capacity available in S/s

is,220/33 - 1 x 25 - 11.42 load

To avoid loss of supply in case of outages or

interruptions on any one transformer

162

Page 166: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 -W.E.F 01/04/2010

SR

NO

NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEME

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

NAGPUR EHV CONSTRUCTION CUM (O&M) ZONE

TOTAL SCOPE OF WORK

1)

2)

1 X 100MVA, 220/132KV ICTS WITH BAYS

132 KV BAYS - 2 NOS.

3) 1 X 50MVA, 220/33KV T/FS WITH BAYS

4) 1X25MVA, 132/33KV T/F

5) 10 X 33KV OUTLETS.

1) 1X25 MVA, 132/33 KV T/F WITH BAYS

2) 33 KV OUTLETS - 4 NOS.

1) 1X25 MVA, 220/33 KV T/F WITH BAYS

2) 33 KV OUTLETS - 4 NOS.

1) 1X25MVA, 132/33KV T/F WITH BAYS

2) 33KV OUTLETS - 4 NOS.

1) 1X25MVA, 132/33KV T/F WITH BAYS

2) 33KV OUTLETS - 4 NOS.

11 220KV HINGANGHAT S/S

(2009-10)

WARDHA 1)

2)

1 X 80 MVA, 220/132KV ICTS WITH BAYS

132 KV BAYS - 2 NOS.

The existing transformer capacity available is

220/132 kV,1 X80 MVA and the laod reached is 11

MVA.To avoid loss of supply in case of outages or

interruptions on any one ICT additional ICT is

proposed.

12 220KV WARDHA II

(BHUGAON) S/S

(2009-10)

WARDHA 1)

2)

1 X 100 MVA, 220/132KV ICT WITH BAYS

132 KV BAYS - 2 NOS.

The existing transformer capacity available is

220/132 kV,1 X100 MVA and the laod reached is

20 MVA.To avoid loss of supply in case of outages

or interruptions on any one ICT additional ICT is

proposed.

13 132 kV HINGANA-I

(2009-10)

Nagpur 1)

2)

Add 1 X 25 MVA, 132/33 kV T/F with bay.

4 X 33 kV out lets

Existing Transformer capacity avaible is 1 X 25

MVA. & load reach is 13 MVA.To avoid loss of

supply in case of outages or interruptions on

transformer.

14 132 kV SINDEWAHI

(2009-10)

Gadchiroli 1)

2)

Add 1 X 25 MVA, 132/33 kV T/F with bay.

4 X 33 kV out lets

Existing Transformer capacity avaible is 1 X 25

MVA. & load reach is 14 MVA.To avoid loss of

supply in case of outages or interruptions on

transformer.

15 132 Kv ASHTI

GADCHIROLI

(2009-10)

Gadchiroli 1)

2)

Add 1 X 25 MVA, 132/33 kV T/F with bay.

4 X 33 kV out lets

Existing Transformer capacity avaible is 1 X 10

MVA. & load reach is 5 MVA.To avoid loss of

supply in case of outages or interruptions on

transformer.

16 220 kV HINGANGHAT

(2009-10)

Wardha 1)

2)

Add 1 X 25 MVA, 132/33 kV T/F with bay.

4 X 33 kV out lets

Existing Transformer capacity avaible is 1 X 25

MVA. & load reach is 5 MVA.To avoid loss of

supply in case of outages or interruptions on

transformer.

17 220 kV WARDHA-II

(BHUGAON) *

(2009-10)

Wardha 1)

2)

Add 1 X 25 MVA, 220/33 kV T/F with bay.

4 X 33 kV out lets

Existing Transformer capacity avaible is 1 X 25

MVA. To avoid loss of supply in case of outages or

interruptions on transformer.

18 220 kV GADCHIROLI

(2009-10)

Gadchiroli 1)

2)

Add 1 X 25 MVA, 220/33 kV T/F with bay.

4 X 33 kV out lets

Existing Transformer capacity avaible is 1 X 25

MVA. & load reach is 13 MVA.To avoid loss of

supply in case of outages or interruptions on

transformer.

19 220 kV UMRED *

(2009-10)

Nagpur 1)

2)

Add 1 X 25 MVA, 220/33 kV T/F with bay.

4 X 33 kV out lets

Existing Transformer capacity avaible is 1 X 25

MVA. & load reach is 9 MVA.To avoid loss of

supply in case of outages or interruptions on

transformer.

1) ADDL. 1 X500 MVA, 400/220KV ICT WITH

BAYS AT - KORADI S/S

2) 220 KV BAYS - 3 NOS.

1) ADD 2X 25 MVA, 220/33KV T/FS WITH BAYS

2) 33 KV OUTLETS - 8 NOS.

To avoid loss of supply in case of outages or

interruptions on any one transformer

To avoid loss of supply in case of outages or

interruptions on any one transformer

9 132KV SAKOLI S/S

(2008-09)

BHANDARA To avoid loss of supply in case of outages or

interruptions on any one transformer

8 220 KV KAULEWADA S/S

(2008-09)

BHANDARA

7 NAGPUR To avoid loss of supply in case of outages or

interruptions on any one transformer

Newly Introduced 220/33 kV Level to feed proposed

Discom S/s.

132 KV KHAPRI S/S

(2008-09)

Existing transformer capacity available in S/s

is,400/220 - 1 x 315 - 220 load 400/220 - 1 x 300 -

245 load Considering the maximum load reach on

the transformer, in event of interruption/outage on

any one of the transformer other transformer should

take care of existing load so as to avoid load

shedding.

6 220KV

HINGANGHAT S/S

(2008-09)

WARDHA

To avoid loss of supply in case of outages or

interruptions on any one transformer

2

AUGMENTATION OF S/S BY ADDITION TO REDUCE LOADING OF TRANSFORMER

1 400KV S/S - KORADI S/S

(2008-09)

NAGPUR

220 KV S/S

WARDHA - II

(BHUGAON) S/S *

(2008-09)

WARDHA

10 132KV AMGAON S/S

(2008-09)

GONDIA

163

Page 167: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 -W.E.F 01/04/2010

SR

NO

NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEME

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

NAGPUR EHV CONSTRUCTION CUM (O&M) ZONE

TOTAL SCOPE OF WORK

1) ADDL. 1X100 MVA 220/132 KV ICT WITH BAYS

2) 2 X 132 KV BAYS

3) 220KV BUTTIBORI TO 132KV KHAPRI S/S

SCDC LINE - 20 CKT.KM WITH BAY

1) 1X50 MVA 220/33 KV T/F WITH BAYS

2) 6X33 KV OUT LETS

5 220KV GADCHANDUR S/S

(2008-09)

CHANDRAPUR 1)

2)

ADD 1X25 MVA, 220/33KV T/F WITH BAYS

33 KV OUTLETS - 4 NOS.

Newly Introduced 220/33 kV Level to remove 66/33

kV Level by introduing 220/33 transformer.

1) ADD 1X 50 MVA, 220/33KV T/FS WITH BAYS

2) 33 KV OUTLETS - 6 NOS.

1) 1X25 MVA, 132/33KV T/F WITH BAYS

2) 4 X 33 KV OUTLETS

1) 1X25 MVA, 132/33 KV T/F WITH BAYS

2) 33 KV OUTLETS - 4 NOS.

1) ADD 2X25 MVA, 220/33 KV T/F WITH BAYS

2) 33 KV OUTLETS - 8 NOS.

1) ADDL. 1X200 MVA 220/132 KV ICT WITH BAYS

2) 132 KV BAYS - 4 NOS.

1) ADDL. 1X200 MVA 220/132 KV ICT WITH BAYS

2) 132 KV BAYS - 4 NOS.

12 132 kV KATOL*

(2009-10)

Nagpur 1)

2)

Add 1 X 25,132/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in s/s is 1 X

12.5, 1 x 25 MVA. And the load reached is 23 MVA

Considering the maximum load reached on the

transformer in the event of interruptions/outage on

any one of the transformer other transformer should

take care of existing load

13 132 kV BESA

(2009-10)

Nagpur 1)

2)

Add 1 X 50 MVA , 132/33 kV T/F with bays.

6 x 33 kV outlets.

Existing transformer capacity available in s/s is 3 x

25 MVA. And the load reached is 54 MVA

Considering the maximum load reached on the

transformer in the event of interruptions/outage on

any one of the transformer other transformer should

take care of existing load

14 132 kV GONDIA

(2009-10)

Gondia 1)

2)

Add 1 X 25 MVA, 132/33 kV T/F with bays.

4 X 33 kV out lets.

Existing transformer capacity available in S/s is 1 X

25 MVA and load is 24 MVA. Considering tre

maximum load reached on the transformer in the

event of interruptions/outage on any one of the

transformer other transformer should take care of

existing load

15 132 kV MADGI

(2009-10)

Gondia 1)

2)

Add 2 X 25 MVA , 132/33 kV T/F with bays.

4 X 33 kV out lets.

To eliminate 66 kV level.

3 220KV

BUTTIBORI S/S *

(2008-09)

NAGPUR Newly Introduced 220/132 kV Level to feed 132 kV

Khapri S/s as an alternate source

4 Existing transformer capacity available in S/s

is,220/33 - 2 x 50 - 66 load Considering the

maximum load reach on the transformer, in event of

interruption/outage on any one of the transformer

other transformer should take care of existing load

so as to avoid load shedding.

220KV

BUTTIBORI S/S *

(2008-09)

NAGPUR

6 220 KV SICOM -

CHANDRAPUR S/S *

(2008-09)

CHANDRAPUR Newly Introduced 220/33 kV Level to remove

220/66 kV Level by introduing 220/33 transformer.

7 220 KV KANHAN S/S *

(2008-09)

NAGPUR Newly Introduced 132/33 kV Level to eliminate 11

kV level from the existing S/s

8 132 KV AMBHORA S/S

(2008-09)

NAGPUR Existing transformer capacity available in S/s

is,132/33 - 2 x 25 - 10 load

Considering the maximum load reach on the

transformer, in event of interruption/outage on any

one of the transformer other transformer should

take care of existing load so as to avoid load

shedding.

9 220 KV BHANDARA

S/S *

(2008-09)

BHANDARA Newly Introduced 220/33 kV Level to eliminate 11

kV level from the existing S/s

10 220 KV AMBAZARI S/S*

(2009-10)

NAGPUR

11 220KV KALMESHWAR

S/S (2009-10)

NAGPUR The eisting transformer capacity available is

220/132 kV,2 X100 MVA and the laod reached is

193 MVA.To avoid loss of supply in case of outages

or interruptions on any one transformer additional

transformer is proposed.

The eisting transformer capacity available is

220/132 kV,1 X150 MVA AND 1 x 250 MVA and the

laod reached is 307 MVA.To avoid loss of supply in

case of outages or interruptions on any one

transformer additional transformer is proposed.

164

Page 168: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 -W.E.F 01/04/2010

SR

NO

NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEME

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

NAGPUR EHV CONSTRUCTION CUM (O&M) ZONE

TOTAL SCOPE OF WORK

1) 2X(200-100) MVA 220/132 KV ICT'S

2) 132 KV BAYS - 2 NOS.

3) 132 KV LINE - 40 KM

1) REP. 1 X (25-10) 132/33 KV T/FS

2) 33KV OUTLETS - 2 NOS.

1) 1X(50-25)MVA, 132/33KV T/FS

2) 33KV OUTLETS - 2 NOS.

1) 2X(50-25)MVA, 132/33KV T/F

2) 33KV OUTLETS - 2 NOS.

1) 2X(50-25)MVA, 132/33KV T/FS

2) 33KV OUTLETS - 2 NOS.

1) 1X(50-25)MVA, 132/33KV T/FS

2) 33KV OUTLETS - 2 NOS.

1) 1X(500-315) MVA, 400/220 KV ICT

2) 220 KV BAYS - 2 NOS.

1) 1X(200-100) MVA 220/132 KV ICT'S

2) 132 KV BAYS - 2 NOS.

1) 1 X (250-150) ,220/132KV ICT

2) 132 KV BAYS - 2 NOS.

1) 1 X ( 200-100) ,220/132KV ICT

2) 132 KV BAYS - 2 NOS.

11 132 kV KATOL*

(2009-10)

Nagpur 1)

2)

1 X (25-12.5)MVA, 132/33 kV T/F

2 X 33 kV out lets.

Existing transformer capacity available in s/s is 2 X

12.5 MVA. And the load reached is 23 MVA The

transformer is replaced to meet anticipated load

growth.

12 132 kV MANSAR*

(2009-10)

Nagpur 1)

2)

1 X (50-25) MVA, 132/33 kV T/F

2 X 33 kV out lets.

Existing transformer capacity available in s/s is 1 X

50, 1 X 25 MVA. And the load reached is 30 MVA

The transformer is replaced to meet anticipated load

growth.

13 132 kV TALEGAON (2009-

10)

Wardha 1)

2)

1 X (25-10) MVA, 132/33 kV T/F

2 X 33 kV out lets.

Existing transformer capacity available in s/s is 1 X

10, 1 X 25 MVA. And the load reached is 19 MVA

The transformer is replaced to meet anticipated load

growth..

Existing transformer capacity available in S/s is

220/132kV, 1 x 100 MVA and the load reached is

88MVA.The transformer is replaced to meet the

anticipated load growth.

Existing transformer capacity available in S/s is

220/132kV, 1 x 150 MVA and the load reached is

124MVA.The transformer is replaced to meet the

anticipated load growth.

Existing Transformer capacity available is 400/220

kV, 1 X 300 MVA and load reached is 263 MVA.The

transformer is replaced to meet the anticipated load

growth.

AUGMENTATION OF S/S BY REPLACEMENT OF T/F

1 220KV

KALMESHWAR S/S

(2008-09) * *

NAGPUR Existing transformer capacity available in S/s

is,220/132 KV - 2 x 100 MVA and LOAD is 158.4

MVA.Considering the maximum load reach on the

transformer, in event of interruption/outage on any

one of the transformer other transformer should

take care of existing load so as to avoid load

shedding.

2 132 KV TALEGAON S/S

(2008-09) * *

WARDHA Existing transformer capacity available in S/s

is,132/33 KV - 2 x 10 MVA and load is 14

MVA.Considering the maximum load reach on the

transformer, in event of interruption/outage on any

one of the transformer other transformer should

take care of existing load so as to avoid load

shedding.

3 132KV SAONER S/S *

(2008-09)

NAGPUR Existing transformer capacity available in S/s

is,132/33 KV - 2 x 25 MVA and load is 20 MVA.The

transformers are replaced to meet anticipated load

growth.

4 132KV MANSAR S/S *

(2008-09)

NAGPUR Existing transformer capacity available in S/s

is,132/33 KV - 1 x 25 MVA and load is 19.55

MVA,132/33 KV - 1 x 10 MVA and load is Nil

Considering the maximum load reach on the

transformer, in event of interruption/outage on any

one of the transformer other transformer should

take care of existing load so as to avoid load

shedding.

5 132KV NAGPUR-I

MANKAPUR S/S *

(2008-09)

NAGPUR Existing transformer capacity available in S/s

is,132/33 KV -3 x 25 MVA and load is 58

MVA.Considering the maximum load reach on the

transformer, in event of interruption/outage on any

one of the transformer other transformer should

take care of existing load so as to avoid load

shedding.

6 132KV BRAHMAPURI S/S

*

(2008-09)

CHANDRAPUR Existing transformer capacity available in S/s

is,132/33 KV - 2 x 25 MVA and load is 35.1 MVA.

Considering the maximum load reach on the

transformer, in event of interruption/outage on any

one of the transformer other transformer should

take care of existing load so as to avoid load

shedding.

9 220kV AMBAZARI S/S*

(2009-10)

NAAGPUR

10 Existing Transformer capacity available is 220/132

kV, 2 X 100 MVA and load reached is 133 MVA.The

transformer is replaced to meet the anticipated load

growth.

220 KV KANHAN S/S

(2009-10)

NAGPUR

7 400KV KORADI S/S

(2009-10)

NAGPUR

8 220KV KALMESHWAR

S/S*

(2009-10)

NAGPUR

165

Page 169: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 -W.E.F 01/04/2010

SR

NO

NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEME

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

NAGPUR EHV CONSTRUCTION CUM (O&M) ZONE

TOTAL SCOPE OF WORK

14 132 kV MANKAPUR (NGP-

I)*

(2009-10)

Nagpur 1)

2)

1 X (50-25) MVA, 132/33 kV T/F

2 X 33 kV out lets.

Existing transformer capacity available in s/s is 1 X

50, 2 X 25 MVA. And the load reached is 51 MVA

The transformer is replaced to meet anticipated load

growth.

15 132 kV PARDI (NGP-II)*

(2009-10)

Nagpur 1)

2)

1 X (50-25) MVA, 132/33 kV T/F

2 X 33 kV out lets.

Existing transformer capacity available in s/s is 1 X

50, 2 X 25 MVA. And the load reached is 30 MVA

The transformer is replaced to meet anticipated load

growth.

1) 2X25 MVA, 220/33KV T/FS WITH BAYS

2) 220KV LILO OF CHANDRAPUR GCR -

GADCHANDUR AT MATRADEVI

3) 33KV OUTLETS-4 NOS.

ORC WORKS

1 220KV MATRADEVI S/S

(2008-09)

CHANDRAPUR Matradevi-220kV S/S is considered for reducing

loading on Chandrapur and Chandur 220kV S/S.

This Substation is proposed on LILO of existing

Chandrapur–Chandur 220kV line in year 2007-08.

By the commissioning of this substation, voltage

profile will improve.

166

Page 170: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 -W.E.F 01/04/2010

SR

NO

NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEME

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

NAGPUR EHV CONSTRUCTION CUM (O&M) ZONE

TOTAL SCOPE OF WORK

1) 2X50MVA, 220/33KV T/FS WITH BAYS

2) LILO ON 220KV CHANDRAPUR -PARLI FOR

TADALI -1 KM

3) 12X33KV OUTLETS

1) 2 X 100 MVA, 220/132 KV T/FS WITH BAYS

2) 220KV D/C KALMESHWAR-KATOL-40KM

WITH BAYS

3) 132 KV OUTLETS - 4 NOS 132 KV D/C

INTERLINK BETWEEN KATOL I TO KATOL II-

10 KM WITH BAYS

4) 132KV LINE FROM KATOL - SAONER SCDC -

49KMS

5) 4KM UG CABLE

1) 132 KV U.G. CABLE - 10 CKT. KM NAGPUR - II

TO JAT - TARODI SCDC - 5 CKT KM

2) 2 X 25 MVA, 132/33 KV T/FS WITH BAYS

3) 8 X 33KV OUTLETS.

1) 2X25MVA 132/33KV T/FS WITH BAYS

2) 132KV LAKAHNDUR - MORGAON ARJUNI D/C

LINE - 20 KMS

3) 8X33KV OUTLETS

1) 2 X 25 MVA, 132/33 KV T/FS WITH BAYS

2) 132 KV S/C D/C WARDHA-II-SELOO-18 KM

WITH BAYS

3) 33 KV OUTLETS - 8 NOS

1) 2X25MVA 132/33KV T/FS WITH BAYS

2) 132KV GONDIA - TUMSAR D/C LINE - 44 KMS

3) 132kV MADGI - TUMSAR DC LINE -7 KM

1) 765/400 KV, 4 X 500 MVA , 1-Phase ICT WITH

BAYS

2) 765 KV KORADI -AKOLA , 2 X S/C QUAD LINE -

480 KM

3) INTERCONNECTING LINES BETWEEN 400 KV

KORADI-765 KV KORADI -15 KM

1) 2 X 25 MVA T/F WITH BAYS

2) 33 KV OUTLETS - 8NOS.

3) LILO OF 132KV KARDHA-ASGAON LINE AT

PAGHORA- 10KM

1) 2 X 25 MVA T/F WITH BAYS

2) 33 KV OUTLETS - 8NOS.

3) LILO OF 132KV BHANDARA-AMBHORA LINE

AT MOKHABARDI-10KM

A 66KV BHARSHINGI

66/33KV 1X5MVA, 66/11KV 1X5MVA,1X2MVA

B 132/66 KV KATOL

132/66 KV 1X25MVA,1X10MVA

C 132/66 KV WARUD

132/66KV 1X12MVA

NEW SCHEMES

220KV TADALI S/S

(2010-11)

CHANDRAPUR TADALI -220kV S/S is considered to meet the load

growth in Chandrapur Circle.

1

132 KV JAT-TARODI S/S

(2010-11)

3

4 132KV MORGAON

ARJUNI S/S

(2010-11)

GONDIA Morgaon Arjuni is upgraded to 132kV S/S to reduce

the eliminate 66kV network in Nagpur circle.

5 132 KV

SELOO S/S

(2010-11)

WARDHA Seloo-132kV S/S is considered to meet the load

growth in Chandrapur Circle.

2 220 KV

KATOL II S/S

(2010-11)

NAGPUR Present recorded peak load on Katol-132kV, Warud

–132kV S/S is 50MW and 40MW. It is anticipated

by the year 2010-11 the load will reach to about

130MW. Hence it is necessary to go in for 220kV

sub-station at Katol. By the commissioning of this

substation, voltage profile will improve to 0.95pu

from 0.92pu.

NAGPUR Jat Tirodi-132kV S/S is considered for strengthning

the Nagpur ring main.

6 132KV TUMSAR S/S

(2011-12)

GONDIA To eliminate 66 kV level.

7 765 KV KORADI-III S/S

(2012-13)

NAGPUR Evacuation of Generation coming in nearby area

ORC SCHEMES

1 132 KV PAGHORA S/S

(2010-11)

NAGPUR 132 KV Paghora substation is proposed to cater the

load of LIS.

2 132KV MOKHABARDI

(2010-11)

NAGPUR 132kV Mokhabardi substation is proposed to cater

the load of LIS.

66KV LEVEL ELIMINATION

1 ELIMINATION OF 66KV

LEVEL IN NAGPUR (U)

DISTRICT

(2011-12)

NAGPUR A.132kv Bharsingi S/stn is proposed during 2008-

09.To eliminate 66 kV Bharshingi s/stn, new 33 kv

s/stn alongwith 2x5 MVA T/F and 33 kv line from

132 kv Bharshingi s/stn is to be established by

Discom at Bharshingi after complition of above said

work 66/11kv s/stn at Bharshingi will be absolate.

B. After getting above work at Sr.No. A 132/66 kv

T/Fs at Katol will be absolate.

C. After getting above work at Sr.No. A 132/66 kv

T/Fs at Warud will be absolate.

167

Page 171: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 -W.E.F 01/04/2010

SR

NO

NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEME

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

NAGPUR EHV CONSTRUCTION CUM (O&M) ZONE

TOTAL SCOPE OF WORK

A 66 KV KANHAN W/W

66/11 KV, 1X10 MVA

66/11KV SAHULI

66/11 KV, 2x10MVA

132 KV PARDI

132/66 KV , 2X50 MVA

66 KV UMRED

66/33KV 1x10MVA, 66/11KV 2x5MVA

66 KV BHANDAK

66/11 KV 1X 10MVA,

1 X5 MVA

66KV GHUGHUS

66/11 KV 1 X 5 MVA,

1 X 3 MVA

66 KV CHANDRAPUR MIDC

(66/11 KV, 2 X 5 MVA)

66 KV WANI

66/33 KV 2 X10 MVA, 66/11 KV

2 X10 MVA

220/66 KV WARORA

220/66 KV 2 X 50 MVA,

66/11, 1X10 MVA

2 ELIMINATION OF 66KV

LEVEL IN NAGPUR (U)

DISTRICT

(2011-12)

NAGPUR

A.132 kv Sahuli s/stn is proposed during 2009-10.

To eliminate 66 kV Sahuli s/stn. new 33 /11kv s/stn

alongwith 2x10 MVA T/F and 33 kv line from 132 kv

Sahuli s/stn is to be established by Discom at

Sahuli. After complition of above said work 66/11kv

s/stn will be absolate.

B B.After getting above work done at Sr.No. A the

2x50 MVA 132/66 kv T/F at Pardi will become

absolate.

A.To eliminate 66/11 KV substation at 66 kV

Kanhan, new 33 /11kv s/stn alongwith 3x5 MVA T/F

and 33 kv line from 220 kv Kanhan s/stn is to be

established by Discom at Kanhan. After complition

of above said work 66/11kv s/stn will be absolate.

4 ELIMINATION OF 66KV

LEVEL IN NAGPUR (U)

DISTRICT

(2011-12)

NAGPUR A A. 220/33 KV Umred s/stn is already commissioned.

To eliminate 66 kV Umred s/stn, new 33 /11kv s/stn

alongwith 2x5 MVA T/F and 33 kv line from 220kv

Umred s/stn is to be established by Discom at

Umred. After complition of above said work 66/11kv

Umred s/stn will be absolate.

3 ELIMINATION OF 66KV

LEVEL IN NAGPUR (U)

DISTRICT

(2011-12)

NAGPUR A

5 ELIMINATION OF 66KV

LEVEL IN CHANDRAPUR

DISTRICT

(2010-11)

CHANDRAPUR A

D

A. To eliminate 66 kV Bhandak S/stn, new 33

/11kv s/stn alongwith 2x10 MVA T/F and 33 kv line

from 220 kv Chandrapur MIDC s/stn is to be

established by Discom at Bhandak after complition

of above said work 66/11kv s/stn will be absolate.

B B. 66kv Ghuggus s/stn is feeding to 66kv

consumers. (1.66kV WCL Majri 2. 66 kV LLoyd

metal). 66 kv Ghughus s/stn can be eliminated only

after connecting these 66 kv consumers on

220/33/11 kv.Further new 33 kv s/stn alongwith

2x10 MVA T/F and 33 kv line from 220 kv

Chandrapur MIDC s/stn to be established by

Discom at Ghughus after complition of above said

work 66/11 kv T/Fs at Ghughus s/stn will be

absolate.

C C. To eliminate 66 kV Chandrapur MIDC new 33 kv

s/stn alongwith 2x10 MVA T/F and 33 kv line from

220 kv Chandrapur MIDC s/stn to be established

by Discom at chandrapur MIDC after complition of

above said work 66kv s/stn at Chandrapur MIDC

will be absolate.

D. 220 kv Wani s/stn is proposed during 2008-

09.66kv Wani s/stn is feeding 66kV Ghuggus s/stn

which is feeding to 66kv consumers (1. 66kV WCL

Majri 2. 66 kV LLoid metal).66 kv level at Wani can

be eliminated only after connecting these 66 kv

consumers on 220/33/11 kv.Till the conversion of

existing 66 KV consumers to 220/33/11/KV, 66 kV

Wani s/stn will act as a switching s/stn.Further 2

nos of new 33 kv s/stn alongwith 2x10 MVA T/F

each and 33 kv line from 220 kv Wani s/stn is to be

established by Discom considering load centre at

Wani. After complition of above said work 66/33 kv

& 66/11 kv T/Fs at Wani s/stn will be absolate.

E E. After getting the work at Sr.No. A to D 220/66 kv

T/F at Warora will be absolate.

168

Page 172: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 -W.E.F 01/04/2010

SR

NO

NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEME

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

NAGPUR EHV CONSTRUCTION CUM (O&M) ZONE

TOTAL SCOPE OF WORK

66KV SHASTRINAGAR

66/33 KV, 2X10 MVA, 66/11KV, 2X10 MVA

66/11KV CHANDRAPUR TPS

66/11 KV 2X10MVA

66 KV BALLARSHA

66/11 kv 1x14MVA ,1x12.5MVA

66 KV GONDPIMPRI

66/11 KV 2 X5 MVA

66KV ALLAPALLI

66/11KV , 2X1.5MVA

66 KV YETAPALLI

66/11KV , 1X5MVA, 1X3MVA

66 KV SIRONCHA

66/11KV 1X5MVA,1X1MVA, 66/33KV,1X5MVA

66KV JAMALGATTA

66/11KV , 1X1MVA

220 KV SICOM

220/66KV, 1X50 MVA

6 ELIMINATION OF 66KV

LEVEL IN CHANDRAPUR

DISTRICT(2010-11)

CHANDRAPUR A A.To eliminate 66 kV shastrinagar s/stn. new 33

/11kv s/stn alongwith 3x10 MVA T/F and 33 kv line

from 220 kv SICOM s/stn is to be established by

Discom at Shastrinagar. After complition of above

said work 66 KV Shastrinagar s/stn will be absolate.

B B. To eliminate 66 kV Chandrapur TPS S/stn., new

33 /11kv s/stn alongwith 2x10 MVA T/F and 33 kv

line from 220 kv Chandrapur MIDC s/stn is to be

established by Discom at Chandrapur TPS after

complition of above said work 66kv Chandrapur

TPS s/stn will be absolate.

After getting work at Sr.No. A & B the 66 kv

Chandrapur TPS s/stn will be absolate.

B. B. To eliminate 66 kV Gondpimpri S/stn, new 33

/11kv s/stn alongwith 2x5 MVA T/F and 33 kv line

from 132 kv Aashti s/stn is to be established by

Discom at Gondpimpri. After complition of above

said work 66/11kv Gondpimpri s/stn will be

absolate.

C C. 132 kv Allapalli s/stn is to be commissioned by

2009-10.To eliminate 66 kV Allapalli s/stn, new 33

/11kv s/stn alongwith 1 x 3 MVA T/F and 33 kv line

from 132 kv Allapalli s/stn is to be established by

Discom at Allapalli. After complition of above said

work the 66/11kv Allapalli s/stn will be absolate.

A.ELIMINATION OF 66KV

LEVEL IN CHANDRAPUR

DISTRICT

(2010-11)

CHANDRAPUR

G

D. 132 kv Allapalli s/stn is to be commissioned by

2009-10.To eliminate 66 kV Yetapalli s/stn, new 33

/11kv s/stn alongwith 2x5 MVA T/F and 33 kv line

from 132 kv Allapalli s/stn to be established by

Discom at Yetapalli. After complition of above said

work the 66/11kv Yetapalli s/stn will be absolate.

E E.New 132 KV Jafarabad substation is proposed

during 2009-10. To eliminate 66/33/11 KV AT 66 kV

Sironcha new 33 /11kv s/stn alongwith 2x3 MVA

T/F and 33 kv line from 132 kv Jafrabad s/stn is to

be established by Discom at Sironcha. After

complition of above said work 66/11kv Sironcha

s/stn will be absolate.

F F.New 132 KV Jafarabad substation is proposed

during 2009-10.To eliminate 66/11 KV AT 66 kV

Jamalgatta new 33 /11kv s/stn alongwith 2x3 MVA

T/F and 33 kv line from 132 kv Jafrabad s/stn

(Proposed) to be established by Discom at

Jamalgatta. After complition of above said work

66/11kv Jamalgatta s/stn will be absolate

D

A. 220kv Ballarsha s/stn is to be commissioned by

2009-10.A 66 kv consumer Ballarpur Paper Mill is

feeded from 66 kv Ballarsha s/stn.To eliminate 66

kV Ballarsha s/stn. this 66kv consumer is to be

connected on 220/33/11 kv . Further a new 33

/11kv s/stn alongwith 3x10 MVA T/F and 33 kv line

from 220 kv Ballarsha s/stn to be established by

Discom at Ballarsha. After complition of above said

work the 66/11kv Ballarsha s/stn will be absolate.

G.A 66 kv consumer WCL at Sashti is feeding from

220/66 kv SICOM s/stn. This consumer is to be

connected on 220/33/11 kv. After conversion of the

existing 66 KV consumer 220/66 KV ICT at

Chandrapur SICOM will be absolate.

After getting work done at Sr.No. A to G the 1x50

MVA 220/66 KV T/F at SICOM will be absolate.

7

169

Page 173: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 -W.E.F 01/04/2010

SR

NO

NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEME

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

NAGPUR EHV CONSTRUCTION CUM (O&M) ZONE

TOTAL SCOPE OF WORK

A 66 KV MANIKGHAD (EHV CONSUMER) A.The 66kv manikgadh s/ckt. Consumer is feeded

from 220/66 kv Gadchandur s/stn.

B 66 KV L & T (EHV CONSUMER) B.The 66kv L&T ( awarpur) D/ckt. consumer is

feeded from 220/66 kv Gadchandur s/stn.

C 220/66/33/11 KV GADCHANDUR

220/66KV 2X150MVA , 66/33KV 1X10MVA,

66/11KV 2X5 MVA

1 132KV LINK LINE

(2010-11)

CHANDRAPUR 1) 132 KV SINDEWAHI - BRAHMAPURI SCDC

LINE -50 KM WITH BAYS

132kV Sindewahi S/S is fed from 132kV Mul S/s

with S/c line. Hence to provide uninterrupted supply

during planned outages it is necessary to add

proposed line

2 132KV LINK LINE

(2010-11)

CHANDRAPUR 1) 132KV VIRUR - ASHTI SCDC LINE - 55 KM

WITH BAYS

132kV Ashti S/S is fed from 132kV Virur S/s with

S/c line. Hence to provide uninterrupted supply

during planned outages it is necessary to add

proposed line

3 132KV LINK LINE

(2010-11)

GONDIA 1) 132 KV LILO OF GONDIA - AMGAON (TSS) AT

AMGAON LINE - 10 KM

To avoid overloading on 132 kV Amgaon-Gondia

S/c the additional 132 kV Amgaon - Gondia S/c is

proposed

4 132KV LINK LINE

(2010-11)

BHANDARA 1) 2ND CIRCUIT STRINGING OF EXISTING 132

KV KARDHA - ASGAON SCDC LINE - 58 KM

132kV Asgaon S/S is fed from 132kV Kardha S/s

with S/c line. Hence to provide uninterrupted supply

during planned outages it is necessary to add

proposed line

5 132KV LINK LINE

(2011-12)

GONDIA 1) 132 KV PARDI - SAHULI SCDC LINE - 40 KM

WITH BAYS

132kV Gondia S/S is fed from 132kV Kaulewada

S/s with S/c line. Hence to provide uninterrupted

supply during planned outages it is necessary to

add proposed line

6 132KV LINK LINE

(2011-12)

WARDHA 1) 132 KV DEOLI -WARDHA-II SCDC LINE - 28

KM (ONLY STRINGING)

132kV Deoli S/S is fed from 132kV Wardha-II S/s

with S/c line. Hence to provide uninterrupted supply

during planned outages it is necessary to add

proposed line

5 132KV LINK LINE

(2012-13)

NAGPUR 1) REPLACEMENT OF CONDUCTOR AMBAZARI-

NAGPUR-I (MANKAPUR) -9 KM

Since the existing 132kV Ambazari - Nagpur-I line is

loaded to an extent of 99 MW during Non-

Coinsident peak condition and there is no space in

Ambazari S/s. It is anticipated the load will reach to

about critical value in future. Hence it is necessary

to propose additional line to meet additional load

growth and contingency.

1 400KV LINK LINES

(2011-12)

NAGPUR 1) 400KV DC LINE FROM 400KV KORADI-II TO

WARDHA - 120KM

To have evacuation facility .

2 220KV LINK LINE

(2011-12)

CHANDRAPUR 1) 22OKV WANI - WARORA D/C LINE -35KM To have evacuation facility at Warora S/S

1 220KV VIRUR S/S

(2012-13)

CADCHIROLI 1)

2)

1 X 100 MVA, 220/132KV ICTS WITH BAYS

132 KV BAYS - 2 NOS.

The existing transformer capacity available is

220/132 kV,1 X100 MVA and the laod reached is

55 MVA.To avoid loss of supply in case of outages

or interruptions on any one ICT additional ICT is

proposed.

2 400KV CHANDRAPUR-I

(2011-12)

Chandrapur 1)

2)

1X50MVA, 220/33KV TF WITH BAYS

33 KV OUTLETS - 6 NOS.

To have redundancy

3 220 kV SICOM

(2011-12)

Chandrapur 1)

2)

Add 2 X 25 MVA, 220/33 kV T/F with bay.

8 X 33 kV out lets

To eliminate 66 kV level.

4 220 kV HINGANGHAT

(2012-13)

Wardha 1)

2)

Add 1 X 25 MVA, 132/33 kV T/F with bay.

4 X 33 kV out lets

Existing Transformer capacity avaible is 1 X 25

MVA. & load reach is 5 MVA.To avoid loss of

supply in case of outages or interruptions on

transformer.

AUGMENTATION OF S/S BY ADDITION OF T/F

AUGMENTATION OF S/S BY ADDITION WHERE ONLY SINGLE TRANSFORMER IS AVAILABLE

ADDITIONAL LINK LINES

ADDITIONAL LINK LINES FOR S/S WHERE ONLY SINGLE CKT AND SINGLE SOURCE IS AVAILABLE

ADDITIONAL LINK LINES TO MEET DEMAND WITHOUT LOAD SHEDDING AND TO ENSURE RELIABILITY AND QUALITY OF SUPPLY

STRENGTHENING FOR EVACUATION ARRANGEMENT

8 ELIMINATION OF 66KV

LEVEL IN CHANDRAPUR

DISTRICT(2010-11)

CHANDRAPUR

C.To eliminate 66/33 kv 1x10MVA & 66/11KV 2X5

MVA T/F at 220 kv Gadchandur s/stn, new 33 kv

s/stn with 2x10MVA T/F with 33 kv line from 220 kv

Gadchandur s/stn is to be established by DISCOM

at Gadchandur. After completing the said work the

66/33 kv & 66/11 kv T/F at Gadchandur will be

absolate.

After connecting the above 66 kv consumers at

Sr.No. A, B on 220/33/11kV & after completing work

at Sr.No.C the 2 x 150 MVA 220/66 KV ICT at 220

KV Gadchandur s/stn. Will be absolate.

170

Page 174: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 -W.E.F 01/04/2010

SR

NO

NAME OF THE

SUBSTATION

DISTRICT REMARKS / PURPOSE OF SCHEME

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

NAGPUR EHV CONSTRUCTION CUM (O&M) ZONE

TOTAL SCOPE OF WORK

1 220 kV BUTTIBORI-I

(2011-12)

Nagpur 1)

2)

Add 1 X 50 MVA , 220/33 kV T/F with bays.

6 X 33 kV out lets.

Existing transformer capacity available in S/s is 2 X

50 MVA and load is 68 MVA. Considering the

maximum load reached on the transformer in the

event of interruptions/outage on any one of the

transformer other transformer should take care of

existing load

1) Add 1 x 50 MVA, 220/22 KV T/F with bays.

2) 6 x 22 kV outlets

3 220 kV WARDHA - I (2012-

13)

Wardha 1)

2)

Add 1 X 50 MVA, 220/33 kV T/F with bays.

6 X 33 kV out lets.

To eliminate 66 kV level.

1 220KV KALMESHWAR

S/S

(2010-11)

NAGPUR 1)

2)

1X(200-100) MVA 220/132 KV ICT'S

132 KV BAYS - 2 NOS.

Existing transformer capacity available in S/s is

220/132kV, 1 x 100 MVA and the load reached is

90MVA.The transformer is replaced to meet the

anticipated load growth.

2 220 KV KANHAN S/S

(2010-11)

NAGPUR 1)

2)

1 X ( 200-100) ,220/132KV ICT

132 KV BAYS - 2 NOS.

Existing Transformer capacity available is 220/132

kV, 1 X 100 MVAand 1 X 200 MVA and load will

reach 154 MVA.The transformer is replaced to meet

the anticipated load growth.

3 132 kV AMGAON

(2010-11)

Gondia 1)

2)

2 X (50-25)MVA,132/33 kV T/F

33 KV PUTLETS - 2 NOS.

Existing transformer capacity available in s/s is 2x

25 MVA. And the load reached is 25 MVA

Considering the maximum load reached on the

transformer in the event of interruptions/outage on

any one of the transformer other transformer should

take care of existing load

4 132 kV MOUDA

(2010-11)

Nagpur 1)

2)

2 X (50-25)MVA,132/33 kV T/F

33 KV OUTLETS - 2 NOS.

Existing transformer capacity available in S/s is 2 X

25 MVA and load is 24 MVA. Considering the

maximum load reached on the transformer in the

event of interruptions/outage on any one of the

transformer other transformer should take care of

existing load

5 132 kV BESA * (2010-11)

Nagpur 1)

2)

Replac. (50-25) MVA 132/33 kV T/F

2x 33 kV outlets.

Existing transformer capacity available in s/s is 3 X

25 MVA. And the load reached is 24 MVA The

transformer is replaced to meet anticipated load

growth.

6 132 kV PARDI (NGP-II)

(2010-11)

Nagpur 1)

2)

1 X (50-25)MVA, 132/33 kV T/F

2 X 33 kV out lets.

Existing transformer capacity available in s/s is 1 X

50, 2 X 25 MVA. And the load reached is 30 MVA

The transformer is replaced to meet anticipated load

growth..

7 220 kV KALAMESHWAR

(2010-11)

Nagpur 1)

2)

1 X (50-25) MVA, 220/33 kV T/F

2 X 33 kV out lets.

Existing transformer capacity available in s/s is 2 X

25 MVA. And the load reached is 21 MVA The

transformer is replaced to meet anticipated load

growth..

8 220 kV KALAMESHWAR

(2011-12)

Nagpur 1)

2)

1 X (50-25) MVA, 220/33 kV T/F

2 X 33 kV out lets.

Existing transformer capacity available in s/s is 2 X

25 MVA. And the load reached is 21 MVA The

transformer is replaced to meet anticipated load

growth..

9 132 kV HINGNA-II (MIDC)

(2011-12)

Nagpur 1)

2)

1 X (50-25) MVA, 132/33 kV T/F

2 X 33 kV out lets.

Existing transformer capacity available in s/s is 2 X

25 MVA. And the load reached is 20 MVA The

transformer is replaced to meet anticipated load

growth..

10 132 kV HINGNA-II (MIDC)

(2012-13)

Nagpur 1)

2)

1 X (50-25) MVA,132/33 kV T/F

2 X 33 kV out lets.

Existing transformer capacity available in s/s is 2 X

25 MVA. And the load reached is 20 MVA The

transformer is replaced to meet anticipated load

growth..

* ** 1 No. TF. COMMISSIONED IN 2009 - 10.COMMISSIONED IN 2009 - 10.

AUGMENTATION OF S/S BY ADDITION TO REDUCE LOADING OF ICT/T/F

2 220 kV SICOM

(2013-14)

Nagpur Existing transformer capacity available in S/s is 2 x

40 and load reach is 46 MVA. The T/F is replaced

to meet anticipated load growth

AUGMENTATION OF S/S BY REPLACEMENT OF T/F

171

Page 175: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

CAPACITOR & REACTOR

REQUIREMENT

172

Page 176: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 - WEF 01.04.2010

Sr No Name of S/s VoltageCapacitor

(MVAR)

1 NEWASE 132 kV 10

2 SATANA 132 kV 20

3 AKOLE 132 kV 20

4 RAHATNE 132 kV 10

5 VARASGAON 132 kV 10

6 KALWAN 132 kV 10

TOTAL 80

From

BusTo bus

1 765 kV TIRODA 120

2 x 240

(7 x 80

MVAR

1-ph unit)

-

2 765 kV KORADI - III 282

2 x 240

(7 x 80

MVAR

1-ph unit)

2 x 240

(7 x 80

MVAR

1-ph unit)

3 765 kV AKOLA - II 210

2 x 240

(7 x 80

MVAR

1-ph unit)

2 x 240

(7 x 80

MVAR

1-ph unit)

Sr No Name of S/s Name of Line

1 765 kV KORADI - III

2 x 240

(7 x 80 MVAR

1-ph unit)

2 765 kV AKOLA - II

2 x 240

(7 x 80 MVAR

1-ph unit)

CAPACITOR REQUIREMENT DURING 2010-11

REACTOR REQUIREMENT

765 kV Tiroda - Koradi-III 2 x S/c Line

Sr No Name of S/s Name of Line

Line

Length/ckt

(km)

LINE REACTOR

BUS REACTOR

766 kV Koradi-III - Akola-II 2 x S/c Line

767 kV Akola-II - Aurangabad (PG) 2 x S/c

Line

Line Reactor

(MVAR)

173

Page 177: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

RELIANCE

INFRASTRUCTURE LTD.

174

Page 178: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 - W.E.F 01/04/2010

Sr. No. Voltage Level 2010-11 2011-12 2012-13 2013-14 2014-15 Total

1 765kV 0 0 0 0 0 0

2 400kV 0 0 0 0 2 2

3 220kV 2 3 4 3 3 16

4 132kV 0 0 0 0 0 0

5 110/100kV 0 0 0 0 0 0

6 HVDC IGBT Technology 0 2 0 0 0 2

2 5 4 4 5 20

1 765kV 0 0 0 0 0 0

2 400kV 0 0 0 0 152 152

3 220kV 11.8 49 73 62 42 248.8

4 132kV 0 0 0 0 0 0

5 110/100kV 0 0 0 0 0 0

6 HVDC Cable 0 300 0 0 0 300

11.8 349 73 73 194 700.8

1 765kV 0 0 0 0 0 0

2 400kV 0 0 0 0 0 0

3 220kV 0 0 0 16 44 60

4 132kV 0 0 0 0 0 0

5 110/100kV 0 0 0 0 0 0

6 HVDC Cable 0 0 0 0 0 0

0 0 0 16 44 60

1 765kV 0 0 0 0 0 0

2 400kV 0 0 0 0 0 0

3 220kV 10 0 0 0 0 10

4 132kV 0 0 0 0 0 0

5 110/100kV 0 0 0 0 0 0

6 HVDC Cable 0 0 0 0 0 0

10 0 0 0 0 10

1 765kV 0 0 0 0 0 0

2 400kV 0 0 0 0 1800 1800

3 220kV 625 1125 1250 750 750 4750

4 132kV 0 0 0 0 0 0

5 110/100kV 0 0 0 0 0 0

6 HVDC Cable 0 2400 0 0 0 2400

625 3525 1250 1000 2550 8950Total

New Sub-Station (Nos.)

Transmission Lines (Ckt kM)

Total (Ckt kM)

Capacity Addition (MVA)

Capacity addition by New Sub Station

Total (Ckt kM)

Transmission lines for s/s where only single source or single ckt is available

Total (Ckt kM)

Transmission lines to have alternate source

RELIANCE INFRASTRUCTURE LTD. (TRANSMISSION) FIVE YEAR TRANSMISSION PLAN FOR THE

YEAR 2010-11 TO 2014-15

TECHNICAL ABSTRACT (R Infra-T)

Total

Tansmission lines for New Sub -Station

175

Page 179: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 -W.E.F 01/04/2010

SR

NO

NAME OF THE

SUBSTATION

DISTRICT Total Scope of Work Justification

A)1)3X 125 MVA ,220/33 kV T/F With 220 kV GIS Bays

2) D/C 3X1/c 1200sqmm 220 kV cables 8.5KM/ckt With 220kV GIS Bays

3) 3X220 kV GIS Bays at MSETCL Trombay

1)3X125MVA,220/33 kV T/F with 220 kV GIS bays

2) 2x 220 kV GIS bay at MSETCL Borivali

3) 9X 220 kV GIS bay at Nagari Niwara

4) 2X 220 kV GIS bay at Aarey

5)3X 33 kV GIS 13 pannel board

6)D/C 3X1/c 1200sqmm ,220 kV cable -15KM/ckt, (MSETCL Borivali to

Aarey via Nagari Niwara

1)3X125MVA, 220/33 kV T/F with 220 kV GIS bays

2) 3x 220 kV GIS bay at MSETCL Borivali

3) 10X 220 kV GIS bay at Rinfra-Borivali

4)D/C 3X1/c 1200sqmm , 220 kV cable -3.5KM/ckt, (MSETCL Borivali to

RInfra Borivali)

5) 3X 33 kV GIS 13 pannel board

6) LILO of TPC Borivli to Rinfra Aarey one line at Rinfra-Borivli)

1)3X125MVA,220/33 kV T/F with 220 kV GIS bays

2)2X 220kV GIS bay at Aarey

3)9X 220 kV GIS bay at Saki

4)D/C 3X1/c 1200sqmm ,220 kV cable 6 KM/ckt,(Aarey to Saki)

5)3X 33 kV GIS 13 pannel board

1)3X125MVA,220/33 kV T/F with 220 kV GIS bays

2)9X 220 kV GIS bay at Gorai

3)3X 33 kV GIS 13 pannel board

4)D/C 3X1/c 1200sqmm , 220 kV cable 12.56 KM/ckt,(MSETCL Borivali to

Gorai & Gantry to Gorai)

5) LILO of Versova Godbunder 220 kV OH line SC at Gorai ( near Tower

no 307)

1)2X125MVA, 220/33 kV T/F with 220 kV GIS bays

2)9X 220 kV GIS bay at Goregaon

3)2X 33 kV GIS 13 pannel board

4)LILO of Aarey -Versova D/C lines at Goregaon

1)3X125MVA,220/33 kV T/F with 220 kV GIS bays

2)2X 220 kV GIS bay at Ghodbunder

3)9X 220 kV GIS bay at Dahisar Housing

4)3X 33 kV GIS 13 pannel board

5)D/C 3X1/c 1200sqmm , 220 kV cable 6.5 KM/ckt,(Rinfra Ghodbunder to

Dahisar Housing)

8 Procurrement of Land for

costruction of proposed EHV

stations

(2012-13)

Mumbai /

Thane

Procurrement of Land for costruction of proposed EHV stations at

Ghodbunder, Aarey, Irla, Bhayander, Dahisar, KIE, Kandivli, Malavani

HVDC IGBT(Connectivity from MSETCL New Padghe-II 400 kV EHV

Station) , Nagari Niwara, Valnai Goregaon, Khar Danda, Vikhroli.

MERC approval received. Land procurement is in progress.

B NEW Schemes

220kV EHV Stations

220/33 kV Airport EHV Station 1)2X125MVA,220/33 kV T/F with 220 kV GIS bays

( 2012-13) 24 Months after

MERC Approval 2)2X 220 kV GIS bay at Aarey

3)2X 220 kV GIS bay at Versova

4)10X 220 kV GIS bay at Airport

5)2X 33 kV GIS 13 pannel board

6)D/C 3X1/c 1200sqmm ,220 kV cable 5 KM/ckt (Aarey to Airport)

7)D/C 3X1/c 1200sqmm ,220 kV cable 15 KM/ckt( Versova to Airport)

220/33 kV Golibar EHV Station 1)2X125MVA,220/33 kV T/F with 220 kV GIS bays

( 2013-14) 30 Months after

MERC/STU Approval 2)6X 220 kV GIS bay at Golibar

3)2X 33 kV GIS 13 pannel board

4) D/C 3X1/C 1200sqmm 220 kV cable from Airport to Golibar 5KM/ckt

5) Static VAR Compensator

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

2 Mumbai RInfra-D indicated the requirment of additional 132MW load for SRA projects

and commercial complex in Santacruz (E) & Khar (E) area required 17 outlets.

This station is proposed to meet future growth, to meet transformation

redundancy at Aarey , Reduce losses, Enhance reliability.

1 Mumbai STU approval received & basic engineering work completed. DPR submitted

to MERC. As per MERC Standard Of Performance of distribution Licensees,

period for giving supply and determination of compensation Regulations,

2005, 2 bays has been considered for loads by MAIL as the requirement of

load is above 5MVA. Existing 50 MVA load is fed from Aarey is to be

relocated at Airport. To meet new load from this area RInfra-D has requested

for additional 6 nos of 33kV outlets.This station is proposed to meet future

growth, to meet transformation redundancy at Aarey ,Reduce losses,

Enhance reliability.

6 220 /33kV Goregaon EHV

Station

(2010-11)

Mumbai 1) STU & MERC approval received. 2) Major equipment orders are placed. 3)

40% civil work is completed. 4) Relieve transformers at Versova 5)Outlets

released on firm basis to Rinfra-D at (i) Elanza (ii) Andhri (iii) SRA Goregaon

(iv) C B Sons (v) Oshiwara SRA (vi) Ozone (v) Emgeen (vi) Vijay

Associates, Oshiwara.Targeted to be commissioned by 2010-11

7 220/33 kV Dahisar Housing EHV

Station

(2012-13)

Mumbai 1) STU & MERC approval received. 2)Lad procurement is under legal vetting..

3) Specifications for PR ready. 4) Relieve transformers at

Ghodbunder.Targeted to be commissioned by 2012-13

4 220/33 kV Saki EHV Station

(2010-11)

Mumbai 1) STU & MERC approval received. 2) Major equipments & 220kV cable order

placed. 3) 40% civil work is completed. 4) HDPE pipes are laid for cable

laying. 5)Relieve transformers at Aarey. 6)Outlets released on firm basis to

Rinfra-D at (i)Kanakia Chandivali (ii)Saki R/s (iii) Metro Rail (iv)Akruti City (v)

Sumer Corporation (vi) Eliza Chandivali (vii) Seven Hills Health Care

(viii)Nahar Shakti. Targeted to be commissioned by 2010-11

5 220/33 kV Gorai EHV Station

Commissioning(2011-12)

Mumbai 1) STU & MERC approval received. 2) Major equipment order placed. 3)

Building civil work is in progress. 4) HDPE pipes are laid for cable laying. 4)

Forest approval received for cable laying job. However, station will be

commissioned by LILO of existing Ghodbunder-Versova line. 5)Outlets

released on firm basis to Rinfra-D at (i) Kanti Park (ii) Universal SRA

(iii)MHADA Sector 8 (iv) KIE-5 (v) CPWD (vi) East & West RNA Park. Part

commissioning targeted by March-11.

2 220/33 kV Nagariniwara EHV

Station

(2012-13)

Mumbai STU & MERC approval received. Approval from forest awaited to take up job

of cable laying. This scheme will relieve overload of Aarey-Borivali Tie lines.

Targeted to be commissioned by 2012-13

3 220/33 kV Borivli EHV Station

(2011-12)

Mumbai 1) STU & MERC approval received. 2) Orders processed for GIS, 125MVA

Transformers & 220kV cable. 3) Civil work initiated. 4) Outlets released on firm

basis to Rinfra-D at (i)Kanakia CCI (ii)Neev Infrastructure (iii)Lokhandwala

(iv)Vasant Marvals (v) EKTA Meadows (vi) Vinod Silk Mill. Part commissioning

targeted by March-11

R-INFRA POWER CO. LTD.

ONGOING SCHEMES1 220/33 kV Chembur EHV

Station

Commissioning (2011-12)

Mumbai 1) STU & MERC approval received. 2) Major equipment order placed. 3) 30%

of Civil work is completed. 4)Outlets released on firm basis to Rinfra-D at

(i)Raheja Acropois (ii) Natwar Parekh (iii) HDIL Chunabhatti (iv) Infrastructure

Venture (v) Chembur Trading Corporation. Targeted to be commissioned by

2011-12

176

Page 180: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 -W.E.F 01/04/2010

SR

NO

NAME OF THE

SUBSTATION

DISTRICT Total Scope of Work Justification

220/33 kV Khar Danda EHV

Station

1)2X125MVA,220/33 kV T/F with 220 kV GIS bays

(2014-15) 30 Months after

MERC/STU Approval 2)2X 220 kV GIS bay at Versova

3)6X 220 kV GIS bay at Khar Danda

4)2X 33 kV GIS 13 pannel board

5) D/C 3X1/C 1200sqmm 220 kV cable from Versova to Khar Danda 10

KM/ckt

220/33 kV Bhayander Rai EHV

Station

1)2X125MVA,220/33 kV T/F with 220 kV GIS bays

(20014-15) 24 Months after

MERC/STU Approval 2)6X 220 kV GIS bay at Bhayander Rai

3)2X 33 kV GIS 13 pannel board

4)LILO of Dahanu Vesova OH line at Bhyander Rai by 1/C, 1200sqmm

220kV cable from tower to Bhayander Rai EHV Station (3kM/ckt).

220/33 kV KIE EHV Station 1)2X125MVA,220/33 kV T/F with 220 kV GIS bays

(20013-14) 24Months after

MERC/STU Approval 2)2X 220 kV GIS bay at Gorai

3)6X 220 kV GIS bay at KIE

4)2X 33 kV GIS 13 pannel board

5) D/C 3X1/C 1200sqmm 220 kV cable from Gorai to KIE 6 KM/ckt

220/33 kV Drive In Theater EHV

Station

1)2X125MVA,220/33 kV T/F with 220 kV GIS bays

(20012-13) 24 Months after

MERC/STU Approval 2)2X 220 kV GIS bay at Chembur

3)6X 220 kV GIS bay at Drive In Theater

4)2X 33 kV GIS 13 pannel board

5) D/C 3X1/C 1200sqmm 220 kV cable from Chembur to Drive In Theater

10 KM/ckt

220/33 kV Mankhurd EHV

Station

1)2X125MVA,220/33 kV T/F with 220 kV GIS bays

(20013-14)24 Months after

MERC/STU Approval 2)2X 220 kV GIS bay at Chembur

3)6X 220 kV GIS bay at Mankhurd

4)2X 33 kV GIS 13 pannel board

5) D/C 3X1/C 1200sqmm 220 kV cable from Chembur to Mankhurd 5

KM/ckt

220/33 kV Vikhroli EHV Station 1)2X125MVA,220/33 kV T/F with 220 kV GIS bays

(2014-15) 24 months after STU

/MERC approval 2)2X 220 kV GIS bay at Saki

3)6X 220 kV GIS bay at Vikhroli

4)2X 33 kV GIS 13 pannel board

5) D/C 3X1/C 1200sqmm 220 kV cable from Saki to Vikhroli 8 KM/ckt

400 kV EHV Stations

400/220 kV Ghodbunder EHV

Station

1)3X400/220 kV 600 MVA T/F With GIS Bays

(Connectivity from PGCIL

Boisar) 2) D/C 400 kV OH lines from Boisar (PGCIL) 76 KM/ckt

(2014-15) 48 months after STU

/MERC approval 3) 400 kV GIS bays at Boisar(PGCIL) -02 nos

4) 400 kV GIS bays at Ghodbunder -09 nos

5) 220 kV GIS bays at Ghodbunder -09 nos

400kV PGCIL Mumbai-II to

Rinfra-Ghodbunder

1) D/C 400 kV OH lines from Mumbai-II (PGCIL) to Rinfra Ghodbunder

(Approx 17kM /ckt)

(2014-15) onward 48 months

after STU /MERC approval

2) 400 kV GIS bays at Ghodunder- 3 nos

3) 400 kV GIS bays at Mumbai-II (PGCIL) -2 nos

4) 400 kV BUS Reactor at Ghodbunder

400/220 kV or HVDC IGBT at

Malvani EHV Station

1)3X400/220 kV 600 MVA T/F With GIS Bays

(2014-15) onwards 48 months

after STU/MERC approval

2) D/C 400 kV OH lines from MSETCL Padghe-II(Kudus) / Dahanu

80kM/ckt

3) 400 kV GIS bays at MSETCL Padghe-II / Dahanu -02 nos

4) 400 kV GIS bays at Malvani-09 nos

5) 220 kV GIS bays at Malvani -09 nos

HVDC IGBT EHV Stations

2x400 MW HVDC IGBT

Technology at Aarey EHV

Station

1) 2X 150/220 kV Transformer

(2011-12) 24 months after

MERC approval 2)150 kV, 600 MVA Inverter unit( Bipole)

2x400 MW HVDC IGBT

Technology at Nagothane EHV

1) 2X 220/150 kV Transformer

(2011-12) 24 months after

MERC approval 2)150 kV, 600 MVA Converter unit (Bipole)

3) 5X 1/C +/- 150 kV 1200sqmm DC cable from Nagothane to Aarey- 180

KM/ckt

13 Mumbai To meet increamental and future demand, Overcome limitation in power

transfer capacity over length of AC cable, Source Bulk Power, Reduce

losses, Enhance reliability, Create Corridor to wheel in Power, VAR control,

Voltage Fluctuation Mitigation, Block Short power frequency and switching

surges. STU approval is received.

14 Thane To meet increamental and future demand, Overcome limitation in power

transfer capacity over length of AC cable, Source Bulk Power, Reduce

losses, Enhance reliability, Create Corridor to wheel in Power, VAR control,

Voltage Fluctuation Mitigation, Block Short power frequency and switching

surges. STU approval is received.

11 Thane To meet increamental and future demand, Source Bulk Power, Reduce

losses, Enhance reliability, Create Corridor to wheel in Power

12 Mumbai To meet increamental and future demand, Source Bulk Power, Reduce

losses, Enhance reliability, Create Corridor to wheel in Power

8 Mumbai Existing 30MW load of this area is fed from Aarey.RInfra-D requested for 8

additional outlets for this area. Aarey peak reached to 412MW (2009-10) and

are incapable to meet the load growth.The 30 MW load is to be relocated at

Vikhroli. This station is proposed to meet future growth, to meet transformation

redundancy at Aarey, Reduce losses, Enhance reliability,

10 Thane To meet increamental and future demand, Source Bulk Power, Reduce

losses, Enhance reliability, Create Corridor to wheel in Power

6 Mumbai Existing 65 MW load of this area is fed from RInfra Aarey & TPC Dharavi is to

be relocated at Drive In Theater. RInfra-D requested for 24 additional outlets

for this area & 4 outlets for Mumbai Metro-II. This station is proposed to meet

future load growth, Reduce losses, Enhance reliability,

7 Mumbai RInfra-D requested for 11 additional outlets for this area & 4 outlets for

Mumbai Metro-II. This station is proposed to meet future load growth, Reduce

losses, Enhance reliability,

4 Thane Existing 50 MW load of this area is fed from Ghodbunder.RInfra-D requested

for 6 additional outlets for this area. Ghodbunder peak reached to 269MW

and incapable to meet the load growth.The 50 MW load is to be relocated at

Bhayander Rai. This station is proposed to meet future growth, to meet

transformation redundancy at Ghodbunder, Reduce losses, Enhance

reliability,

5 Mumbai Existing 36 MW load of this area is fed from Ghodbunder is to be relocated at

KIE. RInfra-D requested for 15 additional outlets for this area & 4 outlets for

Mumbai Metro-II. This station is proposed to meet future load growth, Reduce

losses, Enhance reliability. The firm capacity of Gorai EHV station is already

commited.

3 Mumbai Existing 80 MW load of this area is fed from Versova.RInfra-D requested for 8

additional outlets for this area. Versova peak reached to 343MW and are

incapable to meet the load growth.The 80 MW load is to be relocated at Khar

Danda. This station is proposed to meet future growth, to meet transformation

redundancy at Versova, Reduce losses, Enhance reliability.

177

Page 181: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 -W.E.F 01/04/2010

SR

NO

NAME OF THE

SUBSTATION

DISTRICT Total Scope of Work Justification

C Additional Link Lines

1

Nil

2

i) 220 kV D/C cables between 220

kV Dahisar to 220 kV Rinfra /

TPC Borivli (2013-14)

Mumbai D/C 3x1/C220 kV 1200 mm2 XLPE cable: 8 KM / ckt, Enhance reliability, Flexibility of load transfer

ii) 220 kV D/C cables between 220

kV TPC Ghatkoper to 220 kV

Rinfra Mankhurd (2014-15)

Mumbai D/C 3x1/C220 kV 1200 mm2 XLPE cable: 7 KM / ckt, Enhance reliability, Flexibility of load transfer

iii) 220 kV D/C cables between 220

kV Drive In Theater to 220 kV

Rinfra Golibar (2014-15)

Mumbai D/C 3x1/C220 kV 1200 mm2 XLPE cable: 5 KM / ckt, Enhance reliability, Flexibility of load transfer

iv) 220 kV D/C cables between 220

kV TPC Saki to 220 kV Rinfra

Saki (2014-15)

Mumbai D/C 3x1/C220 kV 1200 mm2 XLPE cable: 3 KM / ckt, Enhance reliability, Flexibility of load transfer

v) 220 kV D/C cables between 220

kV Golibar to 220 kV Rinfra

Versova (2014-15)

Mumbai D/C 3x1/C220 kV 1200 mm2 XLPE cable: 10 KM / ckt, Enhance reliability, Flexibility of load transfer

vi)

220 kV D/C cables between 220

kV TPC Dharavi to 220 kV

Rinfra Khar Danda (2014-15)

Mumbai D/C 3x1/C220 kV 1200 mm2 XLPE cable: 7 KM / ckt, Enhance reliability, Flexibility of load transfer

D

E Others Schemes

1)220 kV Gantry near Tower no TRP-BVL-257 & cable Interfaces:

2)DC 3x1/C 220 kV 1200 mm2 XLPE cable: 5KM/ckt,

3)220 kV GIS bays: 4 nos at Ghodbunder,

Conversion of 220 kV AIS to

GIS at Existing Aarey

(2010-11) 24 Months after

MERC Approval

Refurbishment of existing 220kV

Transmission Lines

( 2010-11)

Conversion of 220 kV AIS to

GIS at Existing Ghodbunder

(2013-14) 30 Months after

MERC Approval

4 Mumbai 220 kV GIS Bays: 9 nos at RInfra Ghodbunder Future expansion is not possible due to unavalability of space at Ghodbunder

or requirement of land as given in land DPR. This proposal will create space

for proposed 400kV GIS EHV Station at Ghodbunder to enhance reliability &

to source bulk power in Mumbai.Short circuit study for Maharashtra

Transmission network carried out in March 2010 by STU (from PRDC)

recommanded for increasing breaker capacity to 63kA at RInfra Ghodbunder

& this can be achieved by conversion of AIS to GIS.

2 Mumbai 220 kV GIS Bays: 14 nos at RInfra Aarey Future expansion is not possible due to unavalability of space at Aarey or

requirement of land as given in land DPR. This proposal will create space for

HVDC IGBT Technology at Aarey to enhance reliability & to source bulk power

in Mumbai.

3 Thane /

Mumbai

Replacement of existing old 220kV Porcelain Insulators by Composite

Polymer Insulators & refurbishment of transmission tower foundation.

MERC approval is received. 10% work completed.

ADDITIONAL 400kV LINK LINES TO MEET DEMAND WITHOUT LOAD SHEDDING AND TO ENSURE RELIABILITY & QUALITY OF SUPPLY

ADDITIONAL220kV LINK LINES TO MEET DEMAND WITHOUT LOAD SHEDDING AND TO ENSURE RELIABILITY & QUALITY OF SUPPLY

AUGMENTATION OF S/S BY ADDITION OF TRANSFORMER

NIL

1 LILO MSETCL Boisar- Borivli at

RInfra Ghodbunder (2010-

11) 18 Months after MERC

Approvals

Thane STU approval is received.Existing load on Aarey-Borivli line reached to 400

MW , Kalwa-Salsete reached to 545 MW & above SIL limit.This proposal will

relieve Aarey Borivli and Kalwa Salsete Lines.Enhance Stability of DTPS,

Create Corridor to wheel in Power, Additional Back Up to DTPS.

178

Page 182: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

TATA POWER COMPANY

LTD.

179

Page 183: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS/DOC-04 - W.E.F 01/04/2010

Sr No Voltage Level 2009-10 2010-11 2011-122012-13

& BeyondTotal

1 765 kV - - - - -

2 400 kV - - 3 3

3 220 kV - - 3 7 10

4 132 kV - - - - 0

5 110 kV 1 1 7 9

Total 0 1 4 17 22

1 765 kV - - - - -

2 400 kV - - - 681 681

3 220 kV 0 0 116 63 179

4 132 kV - - - - -

5 110 kV 0 16 15 59 90

Total (ckt km) 0 16 131 803 950

1 400kV 0 0 0 3000 3000

2 220kV 0 0 1250 2800 4050

3 132kV 0 0 0 0 0

4 110kV 0 150 180 1440 1770

Total 0 150 1430 7240 8820

1 400kV 0 0 0 0 0

2 220kV 0 0 0 0 0

3 132kV 0 0 0 0 0

4 110kV 250 75 655 250 1230

Total 250 75 655 250 1230

Total (MVA) 250 225 2085 7490 10050

Capacity Addition (MVA):

By New S/S

By Augmentation of Transformer

TPC FIVE YEAR TRANSMISSION PLAN

Year 2010-11 to 2014-15

TATA POWER (TPC) Technical Abstract

New Sub-Stations (Nos.)

Transmission Line / Cable Ckt kms:

180

Page 184: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS-PLAN/DOC-04 - WEF 01/04/10

A)

1 Uprating of 110KV

Transmission Lines for

System strengthening

Raigad / Thane

/ Mumbai

a) Replacement of existing 0.2 ACSR Conductor by

2X 0.15 ACSR Conductor of 110KV Khopoli-

Chembur, Khopoli-Mankhurd and Mankhurd-Parel

Lines ( 80 Circuit kms).

b) Two Circuit KM of XLPE Cable between Taping

structure at Chembur & Chembur R/S .

c) Terminal equipments at taping structures &

Chembur R/S.

FY10 To bring more power to Mumbai area from outside.

Scheme approved by MERC.

70% work completed.

2 Expansion of existing

110KV Receving Stations

at Mahalaxmi

Mumbai a) Construction of 145KV GIS Building.

b) Installation of 12 Bays of 145 KV GIS.

c) Diversion of existing 110KV Cables to GIS by

addition of cables.

d)Additional cables between GIS & 3 nos Power

Transformers.

e) Associated SCADA,Protection& Control and Aux

System.

FY09 To provide additional outlets to Railways and BEST for

Central Mumbai area.

Scheme approved by MERC.

Scheme Completed in FY09.

3 Establishing 220KV GIS

R/S at Mahalaxmi

Mumbai a) 1 Km of 220KV underground cable system.

b) 5, 245 kV GIS bays.

c) 1, 220/110/33KV, 250 MVA, ICT.

d) 600 Mtrs of 630 Sqmm XLPE power cable.

e) SCADA, Protection & other associated auxiliary

equipments.

FY12 To augment input capacity to Mahalaxmi and to meet

the additional requirement of BEST, Railways & Tata

Power-D reliably.

Scheme approved by MERC.

4 220KV Interconnection

with MSETCL at Borivali

Mumbai a) Construction of two, 220KV bays at MSETCL.

b) Construction of 0.5 KM of 220KV transmission

line.

c) Replacement of conductor on the existing line ( 3

C - KM).

d) Addition of 220KV cable (700 mtr) between the

Gantry and existing 220KV GIS bays.

e) Associated protection, Terminal equipments etc.

FY10 To bring more power from MSETCL/ National Grid to

Mumbai area for meeting the requirements of

distribution companies in Mumbai & Suburban area.

Scheme approved by MERC.

40% work complete.

6 Land for new Receiving

Stations.

Mumbai /

Thane

Procurement of Land for setting up of 220 / 110KV

Receving stations at various Load centers like

Hiranandani, Parel, Bangur nagar.

a) Plot at Hiranandani

b) Plot at Parel

c) Plot at Bangur Nagar

FY11 Required for setting up the EHV Receving stations to

meet the additional load requirement of distribution

utilities.

Scheme approved by MERC.

Hiranandani land - agreement under finalization.

7 Establishment of new

145 kv GIS R/S at

Hiranandani, Powai

Mumbai a) LILO of 110 kV Salsette-Dharavi by addition of 5

circuit Km 110kV cable system from Vikhroli to

Hiranandani.

b) Construction of 145/33 KV GIS Bldg.

c) 7, 145 kV GIS bays.

d) 2, 100 MVA 110/33 kV power transformers.

e) 17, 33 kV GIS bays..

f) Protection, SCADA and Associated auxiliary

equipment, Fire protection & ventilation system etc.

FY11 The existing 22 kV Substation is inadequate to meet

the growing demand of the distribution licencees

requirement in the Hiranandani area.

Existing area is supplied from Tata Power Vikhroli (E) &

Saki & Salsette Stations. Load growth about 8% to10%.

Present 22 kV network is not adequate. Proposal will

efficiently and adequately meet the load.

Scheme Approved by MERC

8 Establishment of 110 kV

R/S at Bandra - Kurla

Complex

Mumbai a) Purchase of land from MMRDA.

b) Construction of 145 kV GIS Bldg.

c) 6, 145KV GIS bays.

d) 2, 75 MVA 110/33 kV power transformers.

e) 1 Km 110 kV power cable system.

f) 15 bays of 33 kV GIS.

g) Protection, SCADA & Associated equipments.

FY11 The existing 22 kV network is inadequate to meet the

additional load in BKC area. The proposal will meet the

additional requirement in BKC area.

Existing area is supplied from Tata Power's Dharavi

(Matunga West) at 22 kV. Load growth is about 6% to

8%. Present 22 kV network not adequate.

Conversion of BKC station to 110 kV will enhance the

efficiency of transmission lines which are presently

utilised at 22 kV.

Scheme Approved by MERC

Land acquisition in final stage.

9 220 / 110 KV four Circuit

Transmission line with

245KV GIS at Saki.

Mumbai a) Construction of 220KV Transmission line

between Salsette & Narayan Industrial estate (14

Cir Kms).

b) Laying of 220KV cable from Narayan Industrial

estate to Saki.

c) Construction of GIS building.

d) installation of 8 nos 220KV GIS bays.

e) Insatallation of two nos 250MVA, 220 / 110 /

33KV ICTs.

f) Installation of 33KV GIS with two incomer, 1 Bus

coupler and 18 outlets.

FY12 To improve the supply reliabilty and to meet demand

growth of Saki area.

To provide n-1 redundnacy at Saki.

Scheme approved by MERC.

ONGOING SCHEMES STARTED PRIOR TO APRIL 2009

5 220KV Trombay- Dharavi-

Salsette Line

Mumbai a) Construction of four circuit transmission line from

Tromaby to Salsette (60 cir Kms).

b) Construction of Transmission line from Trombay

to Pratiskha nagar ( 10 Cir Kms) and laying of

220KV cable system from Pratiskha nagar to

Dharavi.

c) Additional GIS bays at Dharavi and Salsette.

d) Associated Protection, SCADA System, Aux

Power Supply & Civil works etc.

FY12 For meeting the additional load growth in North &

Centeral Mumbai.

Scheme approved by MERC.

STU TRANSMISSION PLAN FOR MAHARASHTRA STATE

YEAR 2010-11 TO 2014-15

NAME OF THE

SUBSTATION

DISTRICT TOTAL SCOPE OF WORK Date of

Completion

TATA POWER CO.LTD.

REMARK / PURPOSE / JUSTIFICATIONSR.

NO.

181

Page 185: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS-PLAN/DOC-04 - WEF 01/04/10

10 145 kV GIS at Versova

R/S

Mumbai a) Land from BMC.

b) 11, 145KV GIS Bays.

c) 1, 90 MVA, 110/33KV Transformer.

d) 14, 33KV Switchgear panels

e) Associated power cables, Auxiliaries, Control &

Protection panels etc.

FY12 To meet the additional power requirement of Versova

area.

Conversion of AIS to GIS will enhance the life of the

station equipments. They will serve efficently and

adequately.

Scheme approved by MERC.

11 220 kV South Mumbai

Ring system

Mumbai a) Construction of additional 220 KV Trombay-Sewri

Overhead line (1 km).

b) 16 circuit KM of 220 KV Cable sytem from

Sewri-Backbay.

c) 1, 250 MVA 220/110/33 KV ICT.

d) 1, circuit Km of 110 kV cable system.

e) 11, 145 kV GIS bays.

f) Protection, SCADA & Associated equipments.

FY12 To meet N-1 criteria.

To improve reliability.

To meet additional load. The existing cable rated for

860 Amp cannot meet the load.

Proposal will reduce the overloading of Carnac R/S

and thus release the capacity for Carnac local load

growth.

Proposal will also make sure availability of alternate

supply due to ring system.

Scheme Approved by MERC.

12 Installation of additional

interconnecting

transformer alongwith 33

kv outlets at Dharavi R/S

Mumbai a) 1, 250 MVA, 220/110/33KV ICT.

b) 1, 110 kV Hybrid switchgears

c) 120 Mtr of 220 kV Bus duct.

d) 675 Mtr of 110 kV 1600 Sqmm power cable

e) 7, 33KV Switchgear panels.

f) 33 kV power cables, protection SCADA system

and other auxiliary systems.

FY10 To augment the input capacity to Dharavi R/S.

To meet the additional power requirement in Dharavi

area through additional outlets.

Scheme Approved by MERC.

13 Installation of additional

new 4th, 75 MVA, 110 /22

kV transformer at Vikhroli

Mumbai a) Installation of 1, 110 kV Bay at Vikhroli

b) 1, 75 MVA,110/22 KV power transformer.

c) 1, 22 KV Switchgear.

d) 500 Mtrs of 22 kV cable.

e) Associated protection, SCADA etc.

FY09 To meet the additional load requirements in Vikhroli

area through additional outlets.

Scheme Approved by MERC

Scheme completed in FY 09.

14 Uprating of 110KV

Transmission line by High

Ampacity Super

Conductor

Mumbai a) Replacement of existing conductor (900 A) by

Highampacity super Conductor (1800 A) on the

existing 110KV Borivali - Malad, Salsette - Saki

Transmission lines (32 cir Kms)

b) Uprating of 110KV bay equipments at Borivali,

Malad,Salsette & Saki.

FY10 To improve supply reliability and to meet demand

growth in Saki & Malad areas.

Scheme approved by MERC.

B)

1 110 kV New R/S at

Borivali (west)

Mumbai a) Procurement of land.

b) Construction of Two 110 kV Bays at Tata Power

Borivali (East).

c) 6 circuit Km of underground cable system

between Borivai (east) and west s/s.

d) Nine 110 kV GIS Bays.

e) 2, 100 MVA 110 /33 kV Transformers.

f) 17 outlets of 33 kV GIS Bays.

g) Protection, Scada and other auxiliary

equipments.

FY14 To meet the additional power requirement of

distribution licencees in the Borivali West area.

Borivli West area is served by Tata Power Borivli

(East) Station at 22 kV.

The load growth is about 10%. The existing 22 kV

network inadequate. Proposal will efficiently and

adequately meet the load.

2 Establishment of 220KV

R/S at Antop Hill

(Wadala)

Mumbai a) Loop in Loop out of proposed 220 kV Trombay-

Dharavi and laying of 1.5 circuit Km of 220KV cable

system to the proposed GIS Bldg at Antop Hill.

b) Construction of GIS Bldg.

c) 6 bays of 220 kV GIS.

d) 2, 100 MVA, 220/33 kV power transformers.

e) 17, 33 kV GIS bays.

f) Protection, SCADA and Associated Auxiliary

system etc.

FY14 To provide input capacity to Antop Hill (Wadala) and to

meet the additional requirement of distribution

licencees.

Existing area is supplied from Tata Power Dharavi

(Matunga West). Load growth about 5% to 6%. Present

22/33 kV network not adequate.

3 Establishment of new

220/33 kV GIS R/S at

Chunabhatti

Mumbai a) LILO of existing 220 KV Bhira-Dharavi line.

b) Construction of 220 kV GIS Bldg.

c) Installation of 9, 220 kV GIS bays.

d) Installation of 2, 220/33 kV power transformers.

e) Installation of 17, 33 kV GIS bays.

f) Associated protection, SCADA, Auxiliary

equipments.

FY15 The load growth of about 5% to 6% is expected due to

rehabilitation of Dharavi slums. The existing Tata

Power's R/S capacity at Matunga (W) will be

inadequate to meet the additional load growth. Hence it

is proposed to construct a new station at Chunabhatti

to meet the requirements of distribution licencees (33

kV outlets).

4 Establishment of new

110/33 KV R/S at Bangur

Nagar R/S

Mumbai a) LILO of existing 110 kV Malad-Versova lines.

b) Construction of GIS Bldg.

c) Installation of 7 bays of 145 kV GIS.

d) Installation of 2 x 100 MVA, 110/33 kV

transformers.

e) Installation of 17 bays of 33 kV GIS.

f) Asscoiated protection, SCADA & Associated

auxiliary system.

FY14 Adequate space is not available at the existing Malad-

Versova R/S for expansion and hence it is proposed to

construct an additional 110/33 kV R/S at Bangur Nagar

for meeting the load requirement of Distribution

Licencees in that area.

The load are supplied from Tata Power Malad &

Versova R/S. Load grwoth 8% to 10%. Present network

/ infrastructre not adequate therefore the existing EHV

lines are getting tapped to meet loads efficently.

5 Establishment of new

110 /33 KV R/S at L&T

Mumbai a) Loop in Loop out of existing 110 kV Salsette-Saki

lines.

b) Procurement of land.

c) Construction of 145/33 kV GIS Bldg.

d) Installation of 9 bays of 145 kV GIS bays.

e) 2, 100 MVA, 110/33 kV power transformers.

f) 17 bays of 33 KV GIS bays.

g) Associated protection, SCADA, Auxiliary

equipment, Fire system etc.

FY15 To meet the additional power requirement of

distribution licencees in the Powai area.

Existing area is supplied from Tata Power Salsette

(Bhandup West) / Saki Stations at 22 kV. Load growth

about 8% to10%. Present network not adequate.

Proposal will efficiently and adequately meet the load.

MERC has approved 220 kV Saki proposal, which will

enhance the upgradation and setting up of the stations

to benefit the consumers including licencees.

NEW SCHEMES

182

Page 186: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS-PLAN/DOC-04 - WEF 01/04/10

6 New 400/220/33 kV

Station at

Ghatkopar

Mumbai a)400 KV Ghatkopar - Kharghar D/C Line - 20 km

b) 400 KV Ghatkopar - New Panvel (PGCIL) S/C

Line - 40 km.

c) 400 KV PGCIL, Kalher - Ghatkopar line - 40 km

d) Construction of 400/220/33 kV GIS Bldgs.

e) 3 x 500 MVA, 400/220/33 kV power

transformers.

f) 3 x 250 MVA, 220/110/33 kV ICTs

g) Installation of 400 kV GIS bays.

h) Installation of 220 kV GIS bays.

i) LILO of 220kV Trombay - Salsette - Saki lines

j) LILO of MSETCL Trombay - Mulund/Kalwa line

k) 2 x 220kV lines for Godrej & Boyce

l) Installation of 33 kV GIS bays.

m) Installation of 145 kV GIS bays.

n) Asscoiated protection, SCADA, auxiliary

equipment, fire protection system etc.

FY14 To increase power input to Mumbai from Natonal

Power Grid.

The proposal will bring reliable and cheap power to

Mumbai to mitigte the shortage face today.

7 New 220/33 KV R/S at

Air Port Area (Vidyavihar

West)

Mumbai a) LILO of 220 KV UG Salsette - Saki cable system

from Narayan Ind Estate to Air Port are, route

length 15 KM.

b) Development of land at Airport S/S.

c) Construction of 220/33 kV GIS Bldg.

d) Installation of 7 bays of 220 kV GIS.

e) 2, 220/33 kV, 125 MVA Power transformers.

f) Installation of 17 bays of 33 kV GIS bays.

g) Associated protection, SCADA, auxiliary

equipment etc.

FY12 To meet the growing power requirements in Airport

area (expected load about 300MVA eventually.)

Existing area is supplied from Tata Power's Dharavi &

Saki. Load growth about 6% to 8%. Present 22 kV

network not adequate.

Proposal will meet the loads efficiently and adequately.

8 New 400/220/33 kV R/S

at Marve

Mumbai/ Thane a) 400 KV S/C line from PGCIL Kalher to Marve,

S/C line from Majlipada to Marve

b) Purchase of land at Marve.

c) Construction of 400/220/33 kV GIS Bldgs.

d) 3 x 315 MVA, 400/220/33 kV ICTs.

e) Installation of 400 kV GIS bays.

f) Installation of 220 kV GIS bays.

g) Installation of 33 kV GIS bays.

h) Asscoiated protection, SCADA, auxiliary

equipment, fire protection system etc.

FY15 To get more power input from PGCIL;s proposed

Kalher / Panvel 400 kV Stations to meet the load

requirements of entire North-West Mumbai area.

Present supply is from Tata Power's Trombay/ Borivli

at 220 kV. The load growth is about 8% to 10%, the

network is not adequate. The proposal will bring in bulk

power efficiently and adequately.

9 New 400/220/33 kV R/S

at Majlipada

Mumbai/ Thane a) LILO of 400kV Kalher-Marve line.

b) 400 kV D/C line from PGCIL Boisar to Majlipada

c) Purchase of land at Majlipada.

d) Construction of 400/220/33 kV GIS Bldgs.

e) 3 x 315 MVA, 400/220/33 kV ICTs

f) Installation of 400 kV GIS bays.

g) Installation of 220 kV GIS bays.

h) Installation of 33 kV GIS bays.

i) 2 X 220 kV lines to DFCC.

j) Associated protection, SCADA, auxiliary

equipment, fire protection system etc.

FY15 To get more power input from PGCIL Kalher/ Panvel

to meet the load requirements of North Mumbai

covered in PGCIL report for power evacuation.

Present supply is from Tata Power's Trombay/ Borivli

at 220 kV. The load growth is about 8% to 10%, the

network is not adequate. The proposal will bring in bulk

power efficiently and adequately.

Proposal under discussions with PGCIL and STU

10 New 220/33 kV R/S at

Mira Road (West)

Mumbai/ Thane a) 220 KV D/C UG cable system from Majlipada to

Mira Road (West), route length 12 KM.

b) Purchase of land at Mira Road (West)

c) Construction of 220/33 kV GIS Bldg.

d) Installation of 220 kV GIS.

e) 2 X 125 MVA, 220/33 kV Power transformers.

f) Installation of 33 kV GIS bays.

g) Associated protection, SCADA, auxiliary

equipment etc.

FY14 To meet the growing load of Mira Road (West) area.

Mira Road (West) area is served by Tata Power's

Borivli (East) Station at 22 kV.

The load growth about 10%. The existing network

inadequate. Proposal will efficiently and adequately

meet the load, it will also load the proposed 400 kV

Majlipada station mentioned above.

11 New 220/33 KV Versova

(West) S/S

Mumbai a) 220 KV D/C UG cable system from Marve to

Versova (West), route length 10 Km.

b) Purchase of land at Versova (West)

c) Construction of 220/33 kV GIS Bldg.

d) Installation of 220 kV GIS.

e) 2 X 250 MVA 220/110/33 kV Power transformers.

f) Installation of 33 kV GIS bays.

g) Associated protection, SCADA, auxiliary

equipment etc.

FY15 To meet the growing load of Versova area.

Versova (West) area is served by Tata Power's

Versova R/S at 22 kV. The Versova station cannot be

expanded due to shortage of space.

The load growth is about 10%. The existing network

inadequate. Proposal will efficiently and adequately

meet the load, it will also load the proposed 400 kV

Marve station mentioned above.

12 New 220kV/33kv Godrej

(East) S/S

Mumbai a) 220 KV D/C UG cable system from Ghatkopar to

Godrej (East), route length- 4 KM.

b) Construction of 220/33 kV GIS Bldg.

c) Installation of 220 kV GIS.

d) 2 X 125 MVA, 220/33 kV Power transformers.

e) Installation of 33 kV GIS bays.

f) Associated protection, SCADA, auxiliary

equipment etc.

FY13 To meet load growth arising out of development of

Godrej property in Vikhroli (East) and additional loads

in that area.

Presently loads in Godrej area are fed at 22kV which

will not be economical with increased load.

Expected load in this area is about 120 MVA by

FY13/14

13 New 220kV/33kv Godrej

(West) S/S

Mumbai a) 220 KV D/C UG cable system from Ghatkopar to

Godrej (West), route length- 4 KM.

b) Construction of 220/33 kV GIS Bldg.

c) Installation of 220 kV GIS.

d) 2 X 125 MVA, 220/33 kV Power transformers.

e) Installation of 33 kV GIS bays.

f) Associated protection, SCADA, auxiliary

equipment etc.

FY14 To meet load growth arising out of development of

Godrej property in Vikhroli (West) and additional loads

in that area.

Presently loads in Godrej area are fed at 22kV which

will not be economical with increased load.

Expected load in this area is about 120 MVA by

FY13/14

183

Page 187: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS-PLAN/DOC-04 - WEF 01/04/10

14 New 220kV/33kV S/S at

Bombay Dyeing, Wadala

Mumbai a) LILO of 110kV Trombay-Parel line at Sewri Fort

b) 110kV S/C Cable system Sewri fort - Wadala -

Parel, route length 7 km

c) 220kV GIS bays at Wadala

d) 2X90 MVA Transformers

e) Associated protection, SCADA, auxiliary

equipment etc.

FY14 To meet increased load demand in Wadala area.

Expected loads in due to development of commercial &

residential complexes in Bombay Dyeing, Wadala area

is about 70 MVA

15 New 220kV/33kV S/S at

Bombay Dyeing, Worli

Mumbai a) 110kV Cable system to Worli from Dharavi and

Parel R/S, route length - 10 km

b) Construction of GIS building

c) Instalaltion of 145kV GIS bays at Bombay

Dyeing, Worli

d) Installation of 33 kV GIS bays.

e) Associated protection, SCADA, auxiliary

equipment etc.

FY14 To meet increased load demand in Worli area.

Expected loads in due to development of commercial &

residential complexes in Bombay Dyeing, Worli area is

about 60 MVA

16 New 220kV/33kV S/S at

HDIL, Kurla

Mumbai a) Uprating of 22kV overhead lines from Dharavi

R/S to Mithi river - 2.5 km

b) 110kV D/C cable system from Mithi river to HDIL,

Kurla - 4 km

c) Instalaltion of 145kV GIS bays

d) 2 x 90 MVA Transformers

e) Installation of 33kv GIS bays

f) Associated protection, SCADA, auxiliary

equipment etc.

FY14 To meet prospective loads in Kurla (West) area - about

50 MVA

Subsequently, the expected load growth in Kurla

(West) area is about 5%.

17 New 110kV/33kV R/S at

Chembur Tapping

Structure

Mumbai a) LILO of existing 110kV Trombay-Chembur and

Khopoli - Lodhiwali-Chembur lines at tapping

structure

b) Installation of 145kV GIS bays

c) Installation of 2X90 MVA Transformers

d) Installation of 33kV GIS bays

e) Associated protection, SCADA, auxiliary

equipment etc.

FY14 There is no scope for expansion of existing Chembur

R/S for additional outlets.

To meet increased demand in Chembur area

C)

III

1 220kV Kalwa - Salsette

Third Line

Thane Uprating of existing 110kV Kalwa - Salsette to 220

kV

FY12 To meet increased Mumbai demand reliably.

The existing 220kV Kalwa-Salsette lines have reached

full capacity and tripping any one line jeopardises

system stability.

III

IV FOR STRENGTHENING OF EVACUATION ARRANGEMENT

1 Evacuation of power from

the proposed 3x800 MW

power plant at Dehrand /

Mankule, Maharashtra

Mumbai /

Thane / Raigad

a) 400 kV D/C lines (twin conductor) from Dehrand

to Ghatkopar - 65 Km.

b) 400 kV D/C lines (twin conductor) from Dehrand

to Nagothane - 65 Km.

FY14 To provide evacuation of Tata Power's proposed

Thermal station to Tata Power area and to

MSETCL/and other states through PGCIL's 400 kV

network from Panvel / Pune.

Proposal included in PGCIL evacuation report.

D)

I

II

1 Installation of additional

interconnecting

transformer alongwith 33

kv outlets at Borivli R/S

Mumbai a) 1, 250 MVA, 220/110/33KV ICT.

b) 1, 110 kV Hybrid switchgears

c) 120 Mtr of 220 kV Bus duct.

d) 675 Mtr of 110 kV 1600 Sqmm power cable

e) 7, 33KV Switchgear panels.

f) 33 kV power cables, protection SCADA system

and other auxiliary systems.

FY13 To augment the input capacity to Borivli R/S.

To meet the additional power requirement in Borivli

area through additional outlets.

2 Installation of additional

75 MVA, 110/33kV

Transformer along with

33kV GIS bays at Parel

Mumbai a) Installation of 1X75 MVA Transformer

b) Instalaltion of 33kV GIS bays

c) 33 kV power cables, protection SCADA system

and other auxiliary systems.

FY11 The expected load on 33kV at Parel is about 160 MVA

which will exceed firm capacity of 75 MVA.

To meet increased load on 33kV reliably additional

transformer is required.

3 Installation of additional

315 MVA, 220kV/110kV

ICT at Trombay

Mumbai a) Installation of 1x315 MVA additional ICT at

Trombay

b) Construction of 110kV O/H line from Trombay

220kV to 110kV - 2 ckt km

FY12

III

1 Life extension

(Replacement) of existing

transformer 2 at Saki &

existing transformer 2 at

Mahalaxmi and

transformer 2 at Carnac

R/S

Mumbai Procurement, Installation, Testing Commissioing of

3 Nos. 75/90 MVA, 110/22 kV power transformers

at Saki & Mahalaxmi R/S respectively.

FY12 The transformers are having high Furan content. The

transformers cannot be repaired.

Transformers are 35 years old. Hence they are

required to be replaced.

E)

1 Expansion and life

extension of existing 110

kV R/S at Mankhurd

Mumbai a) Construction of 145 KV GIS Bldg.

b) Installation of 9, 145 kV GIS bays.

c) Associated protection, SCADA & Auxiliary

equipments.

FY13 The existing AIS equipments are old and served there

utility therefore they need replacement by GIS.

To increase the reliability of station and to meet

additional load.

To provide additional 110 kV outlets to consumers.

TO MEET DEMAND WITHOUT LOAD SHEDDING AND TO ENSURE RELIABILITY AND

NIL

AUGMENTATION OF SUB-STATIONS BY REPLACEMENT OF TRANSFORMER

LIFE EXTENSION AND MODERNISATION

ADDITIONAL LINK LINES

FOR SUB-STATIONS WHERE ONLY SINGLE CIRCUIT AND SINGLE SOURCE IS

FOR NEW SUBSTATIONS TO HAVE ALTERNATE SOURCE

NIL

TO REDUCE LOADING ON EXISTING TRANSFORMER (N-1)

AUGMENTATION OF SUB-STATIONS BY ADDITION OF TRANSFORMER

WHERE ONLY SINGLE TRANSFORMER IS AVAILABLE

184

Page 188: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

STU/TRANS-PLAN/DOC-04 - WEF 01/04/10

2 Expansion and life

extension of existing 110

kV R/S at Dharavi

Mumbai a) Construction of 145 KV GIS Bldg.

b) Installation of 30, 145 kV GIS bays.

c) Associated protection, SCADA & Auxiliary

equipments.

d) 110 kV power cables between GIS and power

transformers.

FY14 The existing AIS equipments are old and served there

utility therefore they need replacement by GIS.

To increase the reliability of station to meet consumers

load.

To provide additional 110 kV outlets to consumers and

other Satelite R/S to be setup.

3 Expansion and life

extension of existing 110

kV R/S at Malad

Mumbai a) Construction of 145 KV GIS Bldg.

b) Installation of 9, 145 kV GIS bays.

c) Associated protection, SCADA & Auxiliary

equipments.

d) 110 kV power cables between GIS and power

transformers.

FY14 Increase in reliability.

To provide additional outlets to consumers.

4 Expansion and life

extension of existing 110

kV R/S at Parel

Mumbai a) Construction of 145 kV GIS Bldg.

b) Installation of 15 bays of 145 kV GIS Bldg.

c) Associated protection, SCADA etc.

d) 110 kV cable system between Transformer /

Lines & GIS.

FY14 Increase in reliability.

Creation of additional outlets for meeting the

requirement of customers.

5 Expansion and life

extension of existing 110

kV R/S at Saki

Mumbai a) Construction of 145 kV GIS Bldg.

b) Installation of 9 bays of 145 kV GIS Bldg.

c) Associated protection, SCADA etc.

d) 110 kV cable system between Transformer /

Lines & GIS.

FY15 Increase in reliability.

Creation of additional outlets for meeting the

requirement of customers.

6 Expansion and life

extension of existing 110

kV R/S at Carnac

Mumbai a) Installation of 5 bays of 145 kV GIS.

b) Associated protection, SCADA etc.

c) 110 kV cable system between Transformer /

Lines & GIS.

FY15 Increase in reliability.

Creation of additional outlets for meeting the

requirement of customers.

7 Replacement and life

extension of exising

switchgear/auxiliary

equipment etc. of existing

17 Receiving Stations of

Tata Power.

Mumbai a) Replacement of switchgear.

b) Replacement of Station transformers.

c) Replacement of batteries and chargers.

d) Replacement of UPS.

e) Replacement of AC & DC boards.

f) Other fire system equipment.

g) SCADA & Communication system.

To meet the annual capital expenditure requirement of

replacing the old outdated transmission assets in the

Tata Power's R/S.

185

Page 189: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

756 KV & 400 KV TRANSMISSION

NETWORK OF MAHARASHTRA STATE

INCLUDING INTERSTATE LINES

186

Page 190: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

400 KV BOISAR PG

400 KV TARAPUR PG

}

Towards400 KV VAPI

400 KV KUDUS (MSETCL)

400 KV NAGOTHANE

400 KV PADGHE

400 KV KHARGHAR

TowardsOSMANB2N 220 kV

{

2 x 668 MW

190 km, Quad Moose

77.1 km, Twin Moose

175 km, Quad Moose

765 kV & 400 kV TRANSMISSION NETWORK OF MAHARASHTRA INCLUDING INTERSTATE LINES

}

TowardsRAICHUR

150 km, Quad Moose

91 km, Twin Moose

102 km, Twin Moose

102km, Twin Moose

Towards400 KV INDIABULLS,

NASHIK

185 km, Twin Moose

58 km, Twin Moose

136 km, Quad Moose

116.315 km, Twin AAAC

116 .315 km, Twin AAAC

20 km, Quad Moose

20 km, Twin Moose

270 km, Quard Moose

230 km, Twin Moose

TowardsNALPSOPARA 220 kV

}

Towards400 KV

AURANGABAD-I}

400 KV PADGHE PG

55 km, Twin Moose

765 KV PUNE PG765 KV PADGHE PG

Towards400 KV

NAGOTHANE

174 km, Twin Moose

2 x 635MVA

2 x 1500 MVA

106 km, Twin Moose

15 km, Twin Moose

15 km, Twin Moose

400 KV CAHKAN

HEGC GEN.

Towards KESURDI 220 kV

400 KV HINJEWADI

400 KV KESURDI

20 km, Twin Moose

144 km, Twin Moose

84 km Twin Moose

60 km, Quad Moose

55 km, Quad Moose

260 km, Q

uad Bersimis

Twin Moose

400 KV KOYNA

55 km, Quad Moose

110 km

270 km, Twin Moose

270 km, Twin MooseTowards400 KV PARLI-PG}

84 km, Twin Moose

} TowardsBABLESHWAR

230 km, Twin Moose

285 km, Twin Moose

400 KV LONIKAND-II

Twin Moose

Towards 400 KV KESURDI

765 KV SOUTH SOLAPUR PG

55 km, Twin Moose

400 KV SOUTH SOLAPUR PG

400 KV KARAD-II

118 km

14

60 km, Quad Moose

400 KV NEW KOYNA

56 km, Twin Moose

400 KV RGPPL

136 km, Quad Moose

139 km, Quad Moose

400 KV KOLHAPUR

}

Towards400 KV KARAD-I

161.05 km, Twin Moose

120 km, Quad Moose

}

Towards400 KV PADGHE

230 km, Quad Bersimis400 KV SOLAPUR

20 km, Quad Moose

400 KV GHODBUNDER 129 km, Twin moose

400 KV MHAPUSA PG

400 KV JAIGAD

}

Towards400 KV LONIKAND-I

139 km, Quad Moose

139 km, Quad Moose

2x 500 MW

Towards400 KV JAIGAD

20 km, Quad Moose

50 km,Quad Zebra

189 km, Twin Moose

Towards220 kV NAGOTHANE

TowardsKARAD

37 km, Twin Moose

161.05 km, Twin Moose

400 KV JEJURI

284 km, Twin Moose

20 km, Twin Moose

400 KV NAVI MUMBAI PG

TowardsVAPI

150 km, Quad Moose

22 km, Twin moose

230 km, Quad Bersimis

2 x 1500 MVA

4 x 250MW

4 x 355 MVA

116

60 km, Quad Moose

2 x 500 MVA3 x 315 MVA

2 x 500 MVA

2 x 315 MVA

3 x 315 MVA

2 x 315 MVA

2 x 500 MVA

2 x 500 MVA

{

2 x 315 MVA

2 x 500 MVA

2 x 1500 MVA

2 x 500 MVA

2 x 500 MVA

2 x 600 MVA

TowardsPADGHA 220 kV

400 KV KALWA

1 x 500 MVA

Towards220 kV KARAD-I

2 x 786 MVA

Towards220 KV KARAD-II

4 x 300 MW

{

2x 500 MVA

TowardsSOL-III2 220 kV

TowardsKUDUS 220 kV

TowardsNASIK 220 kV

}

TowardsKALWA 220 kV

TowardsNERUL 220 kV

2 x 315 MVA

TowardsPUNE-PG 220 kV

Towards400 KV PARLI

TowardsLONIKAND-220kV

Towards220 KV CHAKAN-II

TowardsJEJURI 220kV

TowardsHINJEWADI 220kV

Towards220 KV

LONIKAND-II

Towards JEJURI

}

56 km, Twin Moose

Twin Moose

2 x 500 MVA

14

Twin Moose

116.315 km, Twin AAAC

196km, Twin Moose

192.7 km, Twin Moose

71.5 km, Twin Moose

20.5 km, Twin Moose

23

22 km, Twin Moose

2x 500 MVA

2x 600 MVA

3 x 315 MVA

Towards220 kV KOLHAPUR-III

LEGEND

PARTICULARS

765 kV PROPOSED LINES (PGCIL)

400 kV PROPOSED LINES (MSETCL)

State Transmission Utility,4th Floor, Prakashganga',Bandra Kurla ComplexBandra (E), MUMBAI - 400 051 SHEET - I

2 x 315 MVA

Towards400 KV AURANGABAD PG

Towards220 kV MHAPUSA

TARAPUR GEN 3&4

20.5 km, Twin Moose

76 km

, Twin Moose

40 km

, Twin Moose

Towards220KV GHODBUNDER

196km, Twin Moose

105 km, Twin Moose192.7 km, Twin Moose

}

1 x 315 MVA

RGPPL GEN-1

RGPPL GEN 2&3

1 x 500 MVA

1 x 753 MVA

2 x 540 MW

1 x 640 MW

3 x 315 MVA

2 x 500 MVA

}

{

400 KV KARAD

400 KV OSMANABAD

246 km, Twin Moose

1 x 500 MVA

Towards400 KV PARLI PG

182 km, Twin Moose

Towards NMUM-PG2 220kV

1 x 500 MVA

105 km, Twin Moose

2x 500 MW

400 KV VIKROLI(GHATKOPER)

185 km, Twin Moose

40 km, Twin Moose

76 km

, Twin Moose

TowardsGHTKOPR2 220kV

3x 600 MVA

190 km, Quad Moose

175 km, Quad Moose

30 km, Quad Moose

30 km, Quad Moose

Towards400 KV NAVSARI PG}

} Towards400 KV DHULE PG

71.5 km, Twin Moose

400 KV NERUL

Twin Moose

SSOLPRNG [110]

Towards220kVSOUTH SOLAPUR PG

56 km, Twin Moose

56 km, Twin Moose

400 KV FINOLEXFINOLEX GEN

2x 500 MVA

Quad Moose

150 km

150 km

60 km, Quad Moose

Quad Moose

2x 600 MVA

139 km, Quad Moose120 km, Quad Moose

JAIGAD GEN

1 x 315 MVA

KOYNA-4 GEN

TowardsNEW KOYNA 220 kV

TowardsKHARGAR 220 kV

116.315 km, Twin AAAC

174 km, Twin Moose

CHANDRAPUR

80 km, Twin Moose

270 km, Quard Moose

}

250 km, Quad Bersimis

250 km, Quad Bersimis

}

400 KV DHULE-II(DONDAICHA)

Towards NARENDRA

2 x 500 MVA

4 x 300 MVA

48 km, Twin Moose

400 KV NALASOPARA

2 x 500 MVA

TowardsBOISAR 220 kV

3 x 315 MVA

Towards765 KV AURANGABAD-PG

28 km, Twin Moose

Twin Moose

Twin Moose

2 x 315 MVA

Towards400 KV PARLI-PG

67 km, Twin moose

Towards400 KVPARLI

50 km,Quad Zebra

400 KV PUNE PG

1x 350 MW

400 KV LONIKAND-I400 KV HEGC

400 kV EXISTING LINES (MSETCL)

765 kV EXISTING LINES (PGCIL)

400 KV NASHIK

Towards400 KV DHULE- I 15 km, Quad Moose

95 km, Quad Moose15 km, Quad Moose

95 km, Quad Moose

2 x 635MVA

DONDAICHA GEN 1&2

2 x 660 MW

MAHARASHTRA STATE ELECTRICITY TRANSMISSION CO. LTD.

HVDC back to back converter

400 kV EXISTING LINES (PGCIL)

400 kV PROPOSED LINES (PGCIL)

765 kV EXISTING LINES (MSETCL)

765 kV PROPOSED LINES (MSETCL)

187

Page 191: STU/TRANS-PLAN/DOC-4 /WEF 01/04/10 - · PDF fileSubstations Nomenclature used in plan 1 400 kV Akola (existing) 400 kV Akola-I ... Mauda - 350 - - - Mundra UMPP - - 480 - - Sipat -

765 KV & 400 kV TRANSMISSION NETWORK OF MAHARASTRA

INCLUDING INTERSTATE LINES

765 KV AURANGABAD PG

2 x 660 MW

765 KV AKOLA - II

210 km, Quad Bersimis

210 km, Quad Bersimis

400 KV AURANGABAD PG

400 KV AURANGABAD-II(MSETCL)

30 km, Quad Moose

25 km, Quad Moose

25 km, Quad Moose

400 KV BHUSAWAL-II

190 km, Quad Moose

190 km, Quad Moose

400 KV BHUSAWAL-I

7 km, Twin Moose

2 x 500 MW

238 km, Twin Moose

765 K KORADI - III

90 km

Quad Moose

400 KV AKOLA - II

5 x 270 MW

400 KV AKOLA-I

10 km, Quad Moose

10 km, Quad Moose

400 KV INDIABULLS,NANDGAONPETH

400 KV KORADI-I

138 km, Twin Moose

Towards220 kV KHAPERKHEDA-II

400 KV KORADI-III

{

Twin Moose

182 km

400 KV DHULE PG

400 KV BABHALESHWAR

}

7 km, Twin Moose

170 km, Twin Moose

Towards BHUSAWAL-220 kV

131 km, Twin Moose

Towards400 KV NASIK

Towards 400 KV MAUDA

2 x 500 MVA

3 x 660 MW

10 km, Quad Moose

10 km, Quad Moose

Towards BHILAI

400 KV ADANI,GONDIA

3 x 660 MW

Towards400 KV KHARGHAR

400 km,Quad Bersimis

400 KV IDEAL

70 km, Quad Moose

MAUDA GEN.

2 x 500 MW

1 x 600 MVA

10 kmTwin moose

40 kmQuad Moose

400 KV CHANDRAPUR-I

Twin Moose

24 km, Twin Moose

24 km, Twin Moose

22.5 km, Twin Moose

22.5 km, Twin Moose

400 KV PARLI PG

322 kmTwin Moose

388 km, Twin Moose

400 KV PARLI (MSETCL)

7 km, Twin Moose

Towards 400 KV OSMANABAD

}

Towards400 KV BHILAI

3 x 600 MVA

3 x 210 MW

3 x 500 MW

400 KV CHANDRAPUR-II

30 km, Twin Moose

30 km, Twin Moose

400 KV NANDED

281 km, Twin Moose

156 km, Twin Moose

Towards765 K SEONI

(Charged at 400 kV)

341 km, Quard Moose

341 km, Quard Moose

400 KV AURANGABAD-I

Towards400 KV WARDHA (PG)

Towards BHUSWALII 220 kV

210 kmTwin Moose }

142 km, Twin Moose

142 km, Twin Moose

}

76 km, Quard Moose

174 km, Twin Moose

230 km, Twin Moose

230 km, Twin Moose

}Towards 400 KV PUNE PG

400 KV KORADI-II

WARORA40 [2504044]

174 km, Quad Moose

81 kmQuad Moose}

50 km, Quad Moose

50 km, Quad Moose

}

Towards 400 KV PUNE PG}

284 km, Twin Moose1 x 500 MVA

270 km, Twin Moose

129 km, Twin Moose

130 km, Quad Bersimis

400 km, Quad Bersimis

160 km, Twin Moose

81km, Quad Moose

265

265

Twin Moose

2 x 500 MW

2 x 500 MVA

81 kmQuad Moose

2 x 500 MVA

TowardsAURANGABAD-II 220 kV

2 x 500 MVA

TowardsCHANDRAPUR-I 220 kV

345 km, Twin Moose

333 km, Twin Moose

345 km, Twin Moose

285 km km, Twin moose

Towards PRLI-GR 220 kV

1 x 500 MVA

81 km, Quad Moose

2 x 1500 MVA

400 KV WARDHA PG

2 x 315 MVA

765 KV KUDUS (PADGHE) PG Towards

SATPURA

400 KV BHADRAVATI PG

210 kmTwin Moose

170 km, Twin Moose

250 km, Quad Bersimis

}

2x500 MVA

2 x 1500 MVA

TowardsKORADI-220 kV

Towards SARDAR SAROVAR

Towards DHULE 220 kV

Towards400 K RAIPUR

3 x 780 MVA

TowardsWARORA 220 kV

TowardsNANDED 220 kV

2 x 600 MVA

2 x 500 MVA

1 x 315 MVA3 x 250 MVA

2 x 500 MVA

1 x 500 MW

Towards KORADI-II-220 kV

TowardsAKOLA-220 kV

Towards 132 kV BHUSAWAL

2 x 600 MVA

2 x 315 MVA

1 x 315 MVA

2 x 500 MVA

156 km

Twin Moose

240 km

130 km, Quad Bersimis

Towards400 KV NASHIK

40 kmQuad Moose

2 x 1500 MVA

2 x 780 MVA

160 km, Twin Moose

3 x 780 MVA

269 km,

Towards765 KV BARODA

}

220 km, Twin Moose

120 km, Quad Moose

174 km, Quad Moose

Towards 400 KV SOLAPUR

182 km, Twin Moose

2 x 600MVA

3 x 210 MW

2 x 500 MVA

Towards 400 KV

BHUSAWAL-I

343km, Twin Moose Towards 400 KV KORADI-II

250 km, Quad Bersimis

Towards400 KV KUDUS PG

765 KV ADANI( GONDIA)2 x 1500 MVA

ADANI GEN. 4 & 5

2 x 1500 MVA

2 x 780 MVA

400 KV MALEGAON

175 km, Quad MooseQuad Moose

}

Towards400 KV KHANDWATowards

220kV MALEGAON

2 x 1500 MVA

Quad Bersimis400 km, Quad Bersimis

400 km, Quad Bersimis

400 km, Quad Bersimis

250 km, Quad Bersimis

765 KV WARDHA PG

269 km,Quad Bersimis

400 km,Quad Bersimis

400 km,Quad Bersimis

400 km,Quad Bersimis

}

TowardsWARDHAPG 220 kV

Quad Bersimis

130 km, Quad Bersimis

240 km

Quad Bersimis

90 km

Quad Moose

INDIABULLS GEN.

174 km, Twin Moose

KORADI2 GEN

270 km, Quad Moose

270 km, Quad Moose

}

363 km, Twin Moose

400 km, Quad Moose

120 km, Quad Moose

70 km, Quad Moose

Towards 220 KVAURANGABAD-I

}

1 x 315 MVA

BHUSAWAL EXP

2 x 315 MVA

}

400 KV INDIABULLS NASHIK

174 km, Twin Moose

30 km, Quard Moose

Towards220 KV BABHALESHWAR

}

INDIABULLS,NASHIK GEN.

76 km, Quard Moose

30 km, Quard Moose

} TowardsPADGHA

2 x 500 MVA

3 x 250 MVA272 km, Twin Moose

5 k

m,

5 k

m,

Qu

ad

Mo

ose

KORADI-II GEN.

2 x 1000 MVA

Qu

ad

Mo

ose

CHANDRAPUR GEN.3

CHANDRAPUR GEN.2

1 x 500 MVA

}

ADANI GEN. 1,2 & 3

388 km, Twin Moose

TowardsRAMAGUNDAM

(HVDC back to back converter)

340 km, Twin Moose

30 km, Twin Moose

}

Towards 400 KV LONIKAND-I

2 x 315 MVA

C'PUR EXP.2 x 500 MVA2 x 315 MVA

400 KV DHARIVAL

340 km, Twin Moose

30 km, Twin Moose DHARIVAL GEN.

2 x 600 MVA

400 KV NAGPUR ENERGYNAGPUR ENERGY GEN.

4 x 160 MVA

2 x 500 MW

4 x 135 MW

50 km, Quard Moose

50 km, Quard Moose

TowardsCHANDRAPUR-II 220 kV

3 x 200 MVA

2 x 660 MW

2 x 500 MVA

2 x 780 MVA

K'KHEDA EXP.

TowardsRAIPUR 400 kV

State Transmission Utility,4th Floor, Prakashganga',Bandra Kurla ComplexBandra (E), MUMBAI - 400 051

SHEET - II

LEGEND

PARTICULARS

400 kV Proposed Lines (MSETCL)

400 KV DHULE (IPTC)

765 KV DHULE (IPTC)

400 km, Quad Moose

363 km, Twin Moose

}

TowardsWARORA 400 kV

Raipur PGCIL 400 kV

40 kmQuad Moose

40 kmQuad Moose

PADGHE

Towards 400 KV KORADI-III

400 KV KHAPERKHEDA

175 km, Quad Moose

30 km, Quad Moose

270 km, Twin Moose

7 km, Twin Moose

189 km, Twin MooseTowards 400 KV SOUTH SOLAPUR (PG)

400 kV Commissioned Lines (MSETCL)

765 kV Commissioned Lines (MSETCL)

765 kV Proposed Lines (MSETCL)

IDEAL GEN.

2 x 270 MW

400 KV MAUDA

50 km, Quad Moose

50 km, Quad Moose } Towards400 KV NASHIK

400 KV DHULE (MSETCL)

Quad Moose

Quad Moose

RAIGHAR (KOTRA)

765 kV Commissioned Lines (PGCIL)

765 kV Proposed Lines (PGCIL)

400 kV Commissioned Lines (PGCIL)

400 kV Proposed Lines (PGCIL)

15 km, Twin Moose

15 km, Twin Moose

Towards400 KV DHULE-II (DONDAICHA)

} 50 km, Quad Moose

50 km, Quad Moose Quad Moose

MAHARASHTRA STATE ELECTRICITY TRANSMISSION CO. LTD.

188