subbase methodology

Upload: sidney-musonda

Post on 03-Apr-2018

214 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/28/2019 Subbase Methodology

    1/6

    UPGRADING OF APPROXIMATELY 104KM OF ROAD D104/D791 CHIPATATO MFUWE IN EASTERN PROVINCE

    SUBBASE CONSTRUCTION METHODOLOFY

    1.0 SCOPEThis method statement covers the construction of Sub-bases from

    approved natural gravel or partially crushed gravels.

    2.0 MATERIALS

    2.1 General

    Gravel material shall be obtained from approved sources in borrow

    areas or cuts. Tests will have been made on potential borrow pits,

    cuts and on the roadbed along the centre line of the route

    envisaged, and the results will be reflected on the Drawings, which

    also show the use for which the material could possibly be suitable.

    The requirements to be complied with by the material are set out on

    the Drawings and in the Project Specifications for the subbase. It

    shall be ensured that only material which complies with the

    prescribed requirements is used for subbase construction. Where

    natural gravel does not fully comply with the requirements in

    respect of maximum size, after having been broken down as

    determined in Clause 3204, or after light crushing, oversize material

    shall be removed as specified in Clause 3210.

    2.2 Material

    Sub-base materials shall be obtained from approved sources in

    borrow or cut or such other sources as may be specified or

    approved from time to time. The completed sub-base shall contain

    no material having a maximum dimension larger than 63 mm or

    larger than two thirds of the compacted layer thickness when

    approved by the Engineer. Sub-base material shall, unless otherwise

    authorised, conform to the following requirements when finally

    placed:

    (i) Grading Modulus

  • 7/28/2019 Subbase Methodology

    2/6

    The minimum grading modulus shall be 1.5 unless authorised by

    the Engineer, in which case a minimum of 1.2 may be permitted.

    The grading modulus may be relaxed to below 1.2 at the

    discretion of the Engineer when no alternative sub-base materialexists provided that the specified CBR strength is obtained.

    (ii)Plasticity Index

    The maximum plasticity index of the natural material shall be

    10% and that for material to be stabilised shall not exceed 6%

    after treatment with the selected stabilising agent.

    (iii) California Bearing Ratio

    The minimum soaked CBR of the natural material shall be 30% at

    the specified in situ density (not less than 95% Modified

    AASHTO).

    2.2 Compaction requirements

    The minimum in situ compaction of gravel material shall be 95%

    Mod AASHTO

    2.3 Electrical conductivity

    The maximum electrical conductivity of the dumped material on theroad shall not exceed 0.15 Sm-1 at 25C when tested in accordancewith TMH 1 Method A-21T.

    3.0 EQUIPMENT

    The following equipment shall be available for the work:-

    i. 2 No 140G Grader

    ii. 1 No. Bull dozeriii. 1 No. Front End Loaderiv. 6 No 15 ton Tipper Trucksv. 4 No Rollers (1No. grid roller, 2 No. Vibrating Steel Drum Rollers,

    1 No. Pneumatic Roller)vi. 2 No Water Bowser (each of capacity 21,000 litres)

    4.0 PERSONNEL

    4.1 Working Force

    1 Site Engineer

  • 7/28/2019 Subbase Methodology

    3/6

    1 Earthworks Foreman on site1 Soils Technician2 Laboratory Assistants3 General Workers for checking levels4 General Workers for picking rejected material

    1 Machine Attendant for each item of plant and equipment2 Mechanics for daily servicing and minor repairs

    4.2 Plant Operators and Drivers

    1 Bulldozer Operator1 Loader Operator1 Operator for each Grader1 Operator for each Roller1 Driver for each Water tanker1 Driver for each Tipper Truck1 driver Tractor (disk harrow)

    5.0 CONSTRUCTION

    5.1 Requirements applying prior to the construction of the layer

    The subbase shall be constructed only where the underlying

    subgrade layer meets all the specified requirements and has been

    approved by the Engineer. Before the construction of the subbase

    layer, and also before any material is dumped on the road, the

    underlying layer shall be checked to establish whether there is any

    damage, wet spots or other defects, which shall be rectified in

    accordance with the instructions of the Engineer.

    5.2 Placing and compacting

    The material for a pavement layer shall be placed, spread, broken

    down, watered if necessary and mixed, and oversize material shallbe removed and the layer compacted, all in accordance with therequirements of Section 3200.

    6.0 PROTECTION AND MAINTENANCE

    It shall be ensured that the completed subbase layers are protected

    against rain and flood water and against any undue wear and tear of

    or damage to unsealed layers by construction or other traffic.

    Maintenance shall include, the immediate repair of any damage ordefects that may occur.

  • 7/28/2019 Subbase Methodology

    4/6

    7.0 CONSTRUCTION TOLERANCES

    The completed pavement layers shall comply with the construction

    tolerances given below:

    7.1 Level

    The level tolerances referred to in Clause 7205 shall be as follows:

    H90 Hmax

    Selected layer................................. 25 mm 33 mm

    Sub-base........................................ 20 mm 25 mm

    Base............................................... . 15 mm 20 mm

    7.2 Layer thicknesses

    The thickness tolerances referred to in Clause 7205 shall be

    as follows:

    D90 Dmax

    Daverage

    Selected layer.......................... 30 mm 40 mm 10 mm

    Sub-base.................................. 21 mm 27 mm 5 mm

    Base........................................ 21 mm 27 mm 5 mm

    Wearing course....................... - 30 mm 0 mm

    Shoulders................................ - 30 mm 0 mm

    7.3 Width

    The average width of the layer shall not be less than the specified

    width, and nowhere shall the outer edge deviate by more than the

    following from the edge lines shown on the Drawings: 3400-4

    Selected layer . . . . . . . . . . . . . . . . . . . . . . . . . . . . 80 mm

    Sub-base . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 75 mm

    Base . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 50 mm

    Shoulders and wearing course . . . . . . . . . . . . . . 75 mm

    7.4 Cross-section

  • 7/28/2019 Subbase Methodology

    5/6

    When tested with a 3 m straight-edge laid at right angles to the

    road centre line, the surface shall not deviate from the bottom of

    the straight-edge by more than 6 mm. At any cross-section the

    difference in level between any two points shall not vary from theirdifference in level computed from the cross-sections shown on the

    Drawings by more than 15 mm.

    8.0 ROUTINE INSPECTION AND TESTS

    The Engineer will do routine inspections and conduct routine tests to

    determine whether the quality of material and workmanship

    provided comply with the requirements of this Section. The test

    results and measurements shall be assessed in accordance with the

    provisions of Section 7200.

    9.0 SAFETY, WORKERS AND PROTECTIVE CLOTHING

    All works shall overally be supervised by a Site Engineer, who shall

    ensure that a safe working environment is always maintained, and

    that on-site safety procedures are followed at all times.

    The Site Engineer shall see to it that adequate measures are taken

    to warn and protect road users and construction workers. He shall

    instruct all supervisors and foremen in safety measures including

    traffic control and use of clean standard temporary road signs

    The Safety Officer shall conduct regular on-site inspections of works,

    equipment, tools and personnel. He shall also hold regular safety

    meetings with all work groups to discuss and instruct in safety, and

    shall produce weekly reports to Management.

    Good working and handling practices shall be ensured on site

    All workers shall be provided with such protective clothing such as

    hand gloves, overall suits, boots, reflective jackets and dust masks.

    Only suitable hand tools and devices, free from any defect, shall be

    used.

    Only experience operators shall be used to operate plant andequipment on site.

  • 7/28/2019 Subbase Methodology

    6/6

    All detours shall be maintained in serviceable condition.