submission to the coordination of generation and … · the public interest advocacy centre the...

13
Level 5, 175 Liverpool Street, Sydney NSW 2000 Phone: 61 2 8898 6500 Fax: 61 2 8898 6555 www.piac.asn.au Submission to the Coordination of Generation and Transmission Investment discussion paper 23 May 2018

Upload: dangtram

Post on 10-Oct-2018

219 views

Category:

Documents


0 download

TRANSCRIPT

Level 5, 175 Liverpool Street, Sydney NSW 2000

Phone: 61 2 8898 6500 • Fax: 61 2 8898 6555 • www.piac.asn.au

Submission to the Coordination of Generation and Transmission Investment discussion paper

23 May 2018

The Public Interest Advocacy Centre

The Public Interest Advocacy Centre (PIAC) is an independent, non-profit legal centre based in

New South Wales. Established in 1982, PIAC tackles systemic issues that have a significant

impact upon disadvantaged and marginalised people. We ensure basic rights are enjoyed across

the community through litigation, public policy development, communication and training.

Energy and Water Consumers’ Advocacy Program

The Energy + Water Consumers’ Advocacy Program (EWCAP) represents the interests of low-

income and other residential consumers of electricity, gas and water in New South Wales,

developing policy and advocating in energy and water markets. PIAC receives policy input to the

program from a community-based reference group whose members include:

• Council of Social Service of NSW (NCOSS);

• Combined Pensioners and Superannuants Association of NSW;

• Ethnic Communities Council NSW;

• Salvation Army;

• St Vincent de Paul Society NSW;

• Physical Disability Council NSW;

• Anglicare;

• Good Shepherd Microfinance;

• Financial Rights Legal Centre;

• Affiliated Residential Park Residents Association;

• Tenants Union; and

• Mission Australia.

2 • Public Interest Advocacy Centre • Submission to the Coordination of Generation and Transmission

Investment discussion paper

The transformation of the NEM

The National Electricity Market (NEM) is in the process of significant transformation, driven by a

variety of concurrent factors – commonly summarised in terms of the energy trilemma of

reliability, affordability and sustainability. It is transforming from a market dominated by

centralised, fossil-fuelled generation meeting passive demand, to one where a far greater role will

be played by decentralised, renewable generation and storage responding to more active and

responsive demand.

As a result, the fundamental role of the transmission network itself will change – not only as the

location of the centralised generation moves from coal fields to areas of viable wind and solar

resources, but also as reliance on the transmission network decreases. The greater role of

distributed energy resources will see a smaller proportion of total electricity demand passing

through the transmission network.

While this transformation is well underway, the path ahead is not without uncertainty given the

numerous, complex, competing factors driving it. PIAC’s view is that the long-term interests of

consumers in the NEM is best served by managing this uncertainty through adaptable, long-term

plans rather than relying heavily on narrow forecasts or overly prescriptive reforms.

The treatment of storage in the NEM is a good example of the need for a more holistic solution

which not only anticipates the transformation, but also encourages it in a way which minimises

risk and maximises benefit. Another example is the treatment of transmission network costs to

enable new generation in a way which effectively manages the potential risk to consumers of

both over- and under-investment.

Congestion

PIAC agrees with the AEMC’s analysis that congestion in dispatch and operation of the

transmission network is currently not a significant issue in the NEM. However, this may change

as major flow paths and patterns shift as a result of new generation centres developing and older

generation exiting the market.

The transformation of energy generation may lead to congestion in connecting to the network, as

illustrated in the NSW transmission network map in Figure 1, showing the size of connection

enquiries often greatly exceed the available network capacity to connect them. Ignoring this may

result in misleadingly low levels of congestion in network dispatch and operation as otherwise

efficient generation is not connected in the first place. Renewable Energy Zones (REZ) are one

way of addressing this and PIAC’s position is discussed in the section Enabling and coordinating

new generation connection.

Public Interest Advocacy Centre • Submission to the Coordination of Generation and Transmission

Investment discussion paper • 3

Figure 1 Current generation connection enquiries exceed available network capacity in many parts of the NSW

transmission network1

In order to model the occurrence of congestion in the future, the impact of the energy

transformation underway must be assessed. The NEM’s historical reliance on centralised supply

and transmission major flow paths will change and, therefore, trends developed purely from

historical data and the underlying relationships may prove misleading. Instead, any modelling

must be mindful of the impact from:

• The many substantive reforms recently implemented or substantially underway which may

shift the quantum and location of new generation and loads connecting to the NEM but have

not yet been fully reflected in the data;

• A greater role played by decentralised energy including distribution-connected assets (as

opposed to transmission-connected assets) and behind-the-meter products. This may see

1 TransGrid, Submission to the Integrated System Plan, February 2018, 22.

4 • Public Interest Advocacy Centre • Submission to the Coordination of Generation and Transmission

Investment discussion paper

more electricity flows staying within the distribution network rather than the transmission

network and also a change in the reliance on the network for the supply of electricity;

• A greater role played by non-build solutions to supply-demand imbalances such as using

demand response to address not only network constraints but also potential shortfalls in

generation capacity, reliability or security; and

• The change in electricity flows caused by increasing use of storage in the network, both

behind-the-meter and grid-connected. In modelling the impact of grid-connected storage in

particular, it is essential to consider the ability and financial incentives2 to coordinate the size,

location, timing and charge/discharge patterns of storage with nearby generation output to

remove peaks in electricity flows through the network. This could potentially alleviate or

prevent the instance of network congestion.

Recommendation 1

PIAC recommends the AEMC expands its consideration of transmission network congestion to

include constraints in connecting to the network and, in forecasting future levels of congestion,

that the AEMC considers the impact of the energy transformation.

Regulatory treatment of storage

Whilst there are examples of grid-scale storage being connected in the NEM, PIAC considers that

additional clarity regarding its regulatory treatment would be beneficial. As storage exhibits

behaviour of both generation and load, it raises questions about the appropriate charging and

registration arrangements. While it is related, PIAC considers this issue to be distinct from any

proposal to introduce TUOS charges to generators more broadly.

PIAC recommends a separate registration category for storage and hybrid facilities. The creation

of a storage-specific registration category would allow a decision to be made about whether or

not storage facilities should be charged TUOS, independent of any decision on charging

generators. A separate registration category would also encourage a more holistic integration of

grid-connected storage into the regulatory and operations system of the NEM rather than

potentially having to compromise between the generation and load categories. This is particularly

important given the transition currently underway and expectations that grid-connected storage

will become more common in the future.

The definition of the new storage-specific category must be agnostic of the technology used and

the particular arrangements behind the connection point. Instead, it must be based on the

potential impact from the point of view of the wholesale market and network – such as whether

the particular facility both draws and injects material quantities of energy through its connection

point. This impact-based categorisation allows for the many possible configurations of storage

with and without co-located generation or load (both with respect to relative sizing and dispatch

patterns).

2 These financial incentives include reduced upfront connection costs as well as improved ongoing revenue

through enhancing existing or unlocking additional value streams.

Public Interest Advocacy Centre • Submission to the Coordination of Generation and Transmission

Investment discussion paper • 5

For example, a storage facility which is co-located with generation (or load) may display the same

behaviour from the system-side as a pure generation (or load) facility and hence would not

require being registered under the new storage-specific category. This could be due to the

storage capacity being considerably smaller than the co-located generation (or load) capacity or

by restrictions on its charge and discharge profile.

Recommendation 2

PIAC recommends that the AEMC creates a separate registration category for grid-connected

storage and hybrid facilities. This category should remain technology neutral and be based on

whether the facility both injects and draws material quantities of energy through its connection

point.

Enabling and coordinating new generation connection

As part of the energy transformation in the NEM, many prospective generation proponents are

looking to connect in areas which currently have limited network capacity if the network reaches

the area at all. PIAC supports the timely and efficient connection of new generation to meet

Australia’s emission reduction obligations and to pass through the benefits of low cost generation

in wholesale prices to consumers. Experience has shown that the current regulatory framework is

insufficient to fully realise the benefits of the coordinated connection of new generation.

Socialising costs to enable generation connections

In general, PIAC agrees with the AEMC’s conclusion that it

does not necessarily think that it is appropriate for consumers to bear the costs associated

with centralised resources… This risk is better placed with the generation and transmission

businesses themselves.3

While PIAC considers this to be the first-best option, there may be certain cases where it is in the

long-term interests of consumers for some costs and risks to be socialised (i.e. borne by

consumers).

Imposing a new charge on generation may favour incumbents where their connection costs are

already sunk or were socialised through earlier expansions of the transmission network.

Furthermore, it may disadvantage new renewable generation connections where locating in

remote areas provides benefits to the total system through higher capacity factors or greater

diversity of generation sources (such as the time of wind generation). Both these measures would

impede the effective transition to a cleaner, more flexible energy system.

If costs are to be socialised, scrutiny and transparency is required to ensure that this is indeed in

the long-term interests of consumers and not simply providing a windfall gain to generation or

transmission businesses. PIAC considers that, as the National Transmission Planner and in

developing the Integrated System Plan for 2018, AEMO should identify any potential locations

where such network expansions to facilitate new generation would be long-term interests of

consumers. Further, PIAC considers that this should not be a one-off occurrence, it must instead

3 AEMC, Coordination of generation and transmission investment Discussion Paper, 2018, 64.

6 • Public Interest Advocacy Centre • Submission to the Coordination of Generation and Transmission

Investment discussion paper

be periodically updated to reflect revised load forecasts, changes in patterns of major

transmission power flows, developments in generation technologies and the overall cost-benefit

outcomes for consumers.

Recommendation 3

PIAC recommends that AEMO should identify and periodically update potential locations where

network expansions to facilitate new generation would be long-term interests of consumers.

In addition to scrutiny of the cost and size of the investment, the manner in which the socialised

costs are recovered from consumers is also very important. Affordability of energy services has

been a growing concern throughout the NEM and new mechanisms should not be introduced

which exacerbate this problem. Instead, it is preferable for socialised costs to be recovered in a

progressive way. As electricity charges are not linked to a customer’s ability to pay, they have a

tendency towards being regressive rather than progressive. PIAC advocates for more

progressive recovery of socialised costs such as, where possible, through government funding

recovered from consumers via the tax system.

The AEMC’s options for Renewable Energy Zones

Given the potential impact – both risks and benefits to consumers – to emissions and affordability

from the introduction of REZs to the NEM, checks and balances are required to ensure that the

risk of under- or over-investment is not borne unfairly by consumers. While this submission

focusses on the framework for allocating risk and recovering costs for a REZ, the process for

identifying and declaring a REZ are also of importance.

Option 1 – Enhanced information provision

PIAC supports the increased provision and coordination of information. In particular, PIAC sees

that there is a strong opportunity for AEMO to play in providing this in its role as the national

transmission planner and in developing its Integrated System Plan. PIAC also notes industry and

stakeholders have already taken steps to proactively make this information available such as the

Network Opportunity Maps developed by the Institute for Sustainable Futures and Energy

Networks Australia.4

While enhanced information provision alone is unlikely to fully unlock the benefits of new

generation connection, it is an important enabler. Therefore, PIAC considers that this is should be

examined further and implemented in addition to other regulatory arrangements for REZs.

Recommendation 4

PIAC recommends that enhanced information provision for coordinated generation and

transmission investment be examined in addition to any regulatory arrangements for Renewable

Energy Zones.

Option 2 – Generator coordination

There are significant efficiencies possible if prospective generators were to coordinate their

connections. Despite this, and despite the Scale Efficient Network Extensions (SENE)

4 Network Opportunity Maps < https://www.uts.edu.au/research-and-teaching/our-research/institute-sustainable-

futures/our-research/energy-and-climate-2 >

Public Interest Advocacy Centre • Submission to the Coordination of Generation and Transmission

Investment discussion paper • 7

mechanism being in the Rules since 2011, this has not happened. Therefore, barring substantial

changes to the current regulatory framework including the SENE provisions, PIAC does not

consider this a viable option for delivering efficient or timely coordinated generation connections.

Option 3 – TNSP speculative investment

PIAC supports the prudent creation and use of a speculative investment mechanism for REZs

similar to that intended for gas networks. As noted in our submission to the AEMC’s Review into

the scope of economic regulation applied to covered pipelines, we support

incentivising pipeline service providers to use the speculative capital expenditure account with

appropriate return on the risk associated with that expenditure but remain concerned about the

operation of this mechanism. 5

While PIAC supports the concept on the grounds that networks are better placed to bear the risk

of speculative investment and are entitled to enjoy the benefits of successful speculation, our

concerns stem from the shift in cost-recovery for connection assets from the connection

proponents themselves to consumers. In particular we are concerned regarding:

• The appropriateness of applying this mechanism (which was designed for additional capacity

in gas pipeline expansions to facilitate potential new load connections) to a REZ (to expand

the transmission network to facilitate potential new generation connections); and

• The lack of detail regarding the higher rate of return to be applied.

Appropriateness of the speculative gas mechanism to electricity networks

The speculative investment mechanism for gas pipelines was designed to allow network

operators, while expanding their core regulated network to meet load growth, to build additional

capacity in expectation of further load in the future. The return allowed on the original assets and

the higher return allowed on the speculative portion of the assets would both be recovered from

consumers. In the absence of the speculative investment, should the further load growth

eventuate, additional assets would need to be constructed alongside the original which would be

recovered from consumers.

By contrast, for a REZ, the benefit of the speculative investment is reduced connection costs for

new generation. In the absence of the speculative investment, these higher connection costs

would have been borne by the connection generators and not by consumers.

This is further complicated if the speculative investment is unable to piggy-back off a regulated

investment to the shared transmission network. For instance, it might be expanding the shared

transmission network into a new geographic area with the primary target of connecting new

generation.

Determining a rate of return for speculative investments

While the AEMC’s review into gas pipeline regulation has recommended that the rate of return

set as part of a revenue determination can act as a floor, there is no further detail. This lack of

detail and guidance not only makes it very difficult for PIAC and other consumer advocates to

5 PIAC, Submission to the AEMC Review into the scope of economic regulation applied to covered pipelines Draft

Report, 2018, 10.

8 • Public Interest Advocacy Centre • Submission to the Coordination of Generation and Transmission

Investment discussion paper

support this proposal, it may also discourage network businesses from using the provisions at all.

PIAC considers that additional detail and guidance is required regarding:

• How should the AER and/or AEMO determine when a speculative investment has been

undertaken? To ensure that TNSPs are not merely rent-seeking, it is essential that the

speculative investment is additional to what would be prudent under the normal regulatory

framework.

• How should the AER determine when and what portion of a speculative investment has been

utilised and should begin earning a return?

• How can the AER accurately determine the additional risk, if any, the network business has

borne by undertaking the speculative investment? This includes how this process relates to

the new binding rate of return instrument the AER is intended to develop.

• How the higher rate of return for the speculative investment is applied to the assets once

they are being utilised?

o For instance, it could be defined as an uplift factor added to the base rate of return

determined by the AER for its regulated services (e.g.: an additional 1% on top of the

base rate of return). In this case, it raises questions of whether this uplift factor should

be universal for any such investment or whether it is to be determined on a case-by-

case basis.

o Alternatively, it could be determined as a completely separate rate of return

determined by the AER in parallel to the base rate of return.

• How long the assets will earn a higher rate of return? For instance, it could be for the life of

the assets (which could potentially lock in higher returns for 40 to 50 years) or for a finite

duration (e.g.: 10 years) before it its rolled into the normal Regulated Asset Base (RAB) and

earns the base rate of return.

• Will assets continue to earn a higher rate of return if they are replaced? This is of particular

relevance for secondary systems, such as protection relays, which typically have a shorter

life than other assets such as transformers.

Option 4 – TNSP prescribed service

Similar to Option 3, this option would represent a shift in cost-recovery for connection assets from

the connection proponents themselves to consumers. As noted earlier, in certain instances there

can be in the long-term interests of consumers to socialise some costs of enabling new

generation connection. However, PIAC has reservations regarding this proposal for a REZ given

the affordability crisis currently facing many energy consumers and the role that growth in the

RAB of many network businesses has played in driving this affordability crisis in the first place.

Recovering costs purely as a prescribed transmission service places the risk of underutilisation

entirely on the consumer – i.e.: consumers will continue to pay a regulated return for the life of

these assets even if they are completely unused.

Public Interest Advocacy Centre • Submission to the Coordination of Generation and Transmission

Investment discussion paper • 9

Therefore, if this proposed model is to proceed, very strong and independent oversight is

required to ensure that it does not provide a windfall gain to TNSPs and that the benefits of

unlocking new low-emissions and low-cost generation is passed through to consumers.

Oversight will be required of the prudent timing and capacity to meet upcoming generation

connections. A threshold may also be required to determine the necessary level of commitment

of prospective connections to justify qualifying as a REZ under this model. The Integrated System

Plan to be developed by AEMO may play a role in providing this. As the assets are to rolled into

the TNSP’s RAB and recovered as prescribed transmission services, oversight will also be

required as to the efficient cost of the network investment.

Recommendation 5

PIAC recommends that the AEMC develops a framework to provide the regulatory and planning

oversight required to ensure that options 3 and 4 for a REZ only allow prudent investments which

pass benefits through to consumers and do not provide windfall gains to generators or TNSPs. In

particular, PIAC recommends further consultation on the merit of socialising of a portion of

connection costs under a range of different scenarios.

Option 5 – “Clustering” connection applications

From the point of view of a TNSP’s network planning and investment, PIAC considers there is

potential benefit in being able to “cluster” connection applications to allow a more coordinated set

of connection assets and process. However, while this may optimise the network component, it

may not necessarily lead to the best whole-of-system outcome in regard to enabling efficient

generation connections. PIAC’s concerns include:

• Whether the incumbent TNSP is an appropriate body to run this process given that it would

require discretion to delay or refuse a connection. Since the design, construction and

ownership of transmission connection assets will become open to contestability,6 this

discretion over connection applications may provide (or appear to provide) an unfair

advantage to the incumbent TNSP over other potential providers.

• Whether the proposed use of a ‘season’ for accepting connection applications may prevent

otherwise efficient generation connections from proceeding due to the added time and

uncertainty imposed on the connection proponent.

Recommendation 6

PIAC recommends that, if developing the option of clustering connection applications, that the

AEMC considers the potential impact on the effectiveness of transmission connection

contestability.

Impact of loss factors in coordinating generation connections

The marginal loss factors (MLF) are changing at a faster rate than earlier in the NEM. This means

that an existing generator’s MLF can change due to the subsequent connection of another

6 Following the implementation of the Transmission Connection and Planning Arrangements rule change which

come into effect from July 2018.

10 • Public Interest Advocacy Centre • Submission to the Coordination of Generation and Transmission

Investment discussion paper

generator. This change in MLF can materially affect the future revenue, and hence value

proposition, of the generator. As the MLF is calculated for each connection point in the

transmission network and not apportioned according to a causer-pays principle, there is limited

incentive (or signal) for connecting parties to reduce their impact on the MLF of other participants.

As the transformation continues and more generators connect to the network in more remote

locations, the potential volatility in MLF can be expected to increase.

A possible way to address this is to introduce a system which better signals the impact that a

single connecting party has on loss factors, as illustrated in Figure 2. Connecting parties could

have their MLF ‘locked in’ by AEMO for a standard period of time – allowing the party greater

certainty of its future revenue. If a new party were to connect nearby and affect the local MLF,

this change would be borne by the second party alone rather than being spread across both

parties. This provides a much stronger signal to minimise the impact on loss factors, such as by

incorporating storage. Once the determined period of time has elapsed, the MLFs are no longer

‘locked in’ and the revised loss factor at the connection point is applied to both parties.

Current arrangements Proposed arrangements

1st mover

2nd mover

2nd mover

with storage

to address

impact on

MLF

Figure 2 An alternative method for allocating the impact on Marginal Loss Factor (MLF) from incremental connections

Gen 1

MLF = 0.97

Gen 1

MLF = 0.95

Gen 2

MLF = 0.95

Gen 1

MLF = 0.97

Gen 2

MLF = 0.92

Gen 1

MLF = 0.99

Gen 2

MLF = 0.99

Gen 1

MLF = 0.97

Gen 2

MLF = 1.01

Public Interest Advocacy Centre • Submission to the Coordination of Generation and Transmission

Investment discussion paper • 11

Further engagement

PIAC thanks AEMC for the opportunity to respond to the Discussion Paper, and would welcome

the opportunity to discuss the issues raised in more depth. Please contact Miyuru Ediriweera,

Senior Policy Officer, Energy and Water, at [email protected] or on

(02) 8898 6525.