Subsea Processing UiO, 9 September 2014 Birgitte Nordheim Tveter, Statoil 2012-09-03

Upload: duongliem

Post on 05-Feb-2018

238 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: Subsea Processing - · PDF filein total recovery Lufeng Multiphase pumping • Installed 1997 • 12 years in operation ... • 50% of equity prod Other major subsea processing projects:

Subsea Processing UiO, 9 September 2014 Birgitte Nordheim Tveter, Statoil

2012-09-03

Page 2: Subsea Processing - · PDF filein total recovery Lufeng Multiphase pumping • Installed 1997 • 12 years in operation ... • 50% of equity prod Other major subsea processing projects:

Content

• Introduction/Motivation

• Why subsea processing?

• Overview of technologies, applications and examples

–Boosting

–Separation

–Compression

–Raw seawater injection

• Other important systems

–Power supply considerations

• Technology needs

2012-09-03 2

Page 3: Subsea Processing - · PDF filein total recovery Lufeng Multiphase pumping • Installed 1997 • 12 years in operation ... • 50% of equity prod Other major subsea processing projects:

3

Page 5: Subsea Processing - · PDF filein total recovery Lufeng Multiphase pumping • Installed 1997 • 12 years in operation ... • 50% of equity prod Other major subsea processing projects:

Development from platforms to ”subsea to beach”

• Gravity based platforms (limited water depth) - Ekofisk

–Platform wells

–Single phase export lines (separate lines for gas and oil)

• Gravity based or floating platforms (increasing water depth) - Statfjord

–Subsea wells (increasing area one platform can drain)

–Single phase export lines (separate lines for gas and oil)

• Gravity based or floating platforms - Troll

–Multiphase export line (reducing platform size through smaller process)

• Subsea to beach (eliminating platform) – Snøhvit/Ormen Lange

–Subsea wells

–Multiphase pipeline directly to shore (increasing distance with time)

• Subsea processing – Åsgard

– Increasing the efficiency of subsea production systems

Picture by Statoil

5

Page 6: Subsea Processing - · PDF filein total recovery Lufeng Multiphase pumping • Installed 1997 • 12 years in operation ... • 50% of equity prod Other major subsea processing projects:

Subsea in Statoil

• Today more than 50% of Statoil production is from

subsea production systems (subsea wells).

• Statoil operates 536 subsea wells

• New development prospects are dominated by;

–Subsea tie-ins to existing infrastructures

–Subsea deep water developments at remote locations

• Subsea processing is a tool to enable new

developments and increase the recovery factor

6

Page 7: Subsea Processing - · PDF filein total recovery Lufeng Multiphase pumping • Installed 1997 • 12 years in operation ... • 50% of equity prod Other major subsea processing projects:

Different challenges around the world

GoM: Ultra deep water and deep reservoirs

Angola: Deep water and limited infrastructure

Arctic: Remote locations and hostile environment

NCS: “Shallow water” and aging infrastructure

Brazil: Heavy oil and deep water

SEA: Deep water

and limited

infrastructure

2012-09-03 7

Page 8: Subsea Processing - · PDF filein total recovery Lufeng Multiphase pumping • Installed 1997 • 12 years in operation ... • 50% of equity prod Other major subsea processing projects:

Future possibilities in Statoil portfolio

• Norwegian Continental Shelf (NCS):

–Tail end production – lower pressure and higher water cut

–Existing infrastructure with space, weight and time limitations

–Smaller discoveries

• Gulf of Mexico

–Tight reservoir

–High shut-in pressure

–Deep-/Ultra-deep water

• Brazil/West Africa

–Deepwater

–Heavy oil

–Lack of infrastructure for gas

• East Africa

–Deep water, limited infrastructure

• Remote areas

–Lack of existing infrastructure

–Likely to be long tie-backs

–Possibly harsh environment

2012-09-03 8

Page 9: Subsea Processing - · PDF filein total recovery Lufeng Multiphase pumping • Installed 1997 • 12 years in operation ... • 50% of equity prod Other major subsea processing projects:

Pressure drops in the system

P PFBH PRES

PFWH PRB

PSEP

2012-09-03 9

Page 10: Subsea Processing - · PDF filein total recovery Lufeng Multiphase pumping • Installed 1997 • 12 years in operation ... • 50% of equity prod Other major subsea processing projects:

Pressure drops in the system

• PFBH-PRES: Pressure drop in reservoir and near wellbore zone. Mostly determined by

reservoir parameters

• PFWH-PFBH: Pressure drop in wellbore. For oil wells dominated by gravity and for gas wells

dominated by friction

• PRB-PFWH: Pressure drop in pipeline. Usually dominated by friction.

• PSEP-PRB: Pressure drop in riser. For oil systems dominated by gravity and for gas systems

dominated by friction

• PRES – Reservoir pressure

• PFBH – Flowing bottom hole pressure

• PFWH – Flowing wellhead pressure

• PRB – Riser base pressure

• PSEP – Separator pressure

2012-09-03 10

Page 11: Subsea Processing - · PDF filein total recovery Lufeng Multiphase pumping • Installed 1997 • 12 years in operation ... • 50% of equity prod Other major subsea processing projects:

Oil vs gas reservoirs

Gas reservoir can be viewed as closed in

volume of gas, where the pressure

decreases as the gas is drained.

Gas cap

Oil zone – where

production is done

Water zone

Gas cap will help maintain pressure as oil

is produced.

Associated gas will be produced from oil

below bubble point.

Water zone will provide pressure support.

Gas reservoir Oil reservoir

2012-09-03 11

Page 12: Subsea Processing - · PDF filein total recovery Lufeng Multiphase pumping • Installed 1997 • 12 years in operation ... • 50% of equity prod Other major subsea processing projects:

0

1

2

0 5 10 15

Time

Pro

duction r

ate

Oil

Gas

Water

Typical production profile

Rapid increase in water

production after water break

through. Production limited by

topsides process facility.

Oil production decreases with

reservoir pressure Gas production increase due to gas

cap (towards end of field life) and

release of associated gas

2012-09-03 12

Page 13: Subsea Processing - · PDF filein total recovery Lufeng Multiphase pumping • Installed 1997 • 12 years in operation ... • 50% of equity prod Other major subsea processing projects:

Accumulated production

0

5

10

15

20

25

30

35

40

45

50

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

Year

Accum

ula

ted

pro

du

ction

Oil

Gas

Water Minimize water production

-Environmental considerations

-Limit process facility

Maximize hydrocarbon recovery

2012-09-03 13

Page 14: Subsea Processing - · PDF filein total recovery Lufeng Multiphase pumping • Installed 1997 • 12 years in operation ... • 50% of equity prod Other major subsea processing projects:

Parameters influencing the development solution

• Reservoir parameters

• Depth of reservoir (length

and height of well)

• Water depth (height of riser)

• Gas oil ratio (GOR) (average

density of fluid)

• Water production (average

density of fluid)

• Step-out length (distance

from well to platform)

• Diameter of wellbore

• Diameter of pipeline

• Separator pressure

2013-09-03 14

Page 15: Subsea Processing - · PDF filein total recovery Lufeng Multiphase pumping • Installed 1997 • 12 years in operation ... • 50% of equity prod Other major subsea processing projects:

Traditional ways of increasing the recovery

• Additional wells

• Riserbase gas lift

–Lower density of column in riser

reduced pressure drop

• Bottom hole gas lift

–Lower density of column in in well

and riser reduced pressure drop

–Additional gas increases frictional

pressure drop

• Water injection

–Replacing the produced volumes

maintains the reservoir pressure

–Water production will increase

with time

• Reduced separator pressure

2012-09-03 15

Page 16: Subsea Processing - · PDF filein total recovery Lufeng Multiphase pumping • Installed 1997 • 12 years in operation ... • 50% of equity prod Other major subsea processing projects:

Oil storage

Gas compression

Gas, oil, produced

water separation

Power distribution

and control

Manifold

Sea water injection

template with pumping

Produced water

injection template

Production

template Produced water

injection pump Production

template

ROV

intervention

Oil pump

Oil export

Gas export

Why Subsea processing?

2012-09-03 16

Page 17: Subsea Processing - · PDF filein total recovery Lufeng Multiphase pumping • Installed 1997 • 12 years in operation ... • 50% of equity prod Other major subsea processing projects:

What is subsea processing?

Manipulating the well stream between wellhead

and host.

•Subsea processing applications are: – Hydrocarbon boosting (pumping)

– Separation systems

– Raw seawater injection

– Gas compression

•Prerequisites and enablers for the above

applications: – Long distance / high voltage power

– Advanced process monitoring and control

– Cost-efficient installation, maintenance and retrieval

2012-09-03 17

Page 18: Subsea Processing - · PDF filein total recovery Lufeng Multiphase pumping • Installed 1997 • 12 years in operation ... • 50% of equity prod Other major subsea processing projects:

Why Subsea processing?

• Increased productivity and recovery

• Reduced investments, operating costs and increased revenue

• Improved flow assurance

• Longer tie-back distances

• HSE

–Less offshore personnel

–Less materials

–Less emissions

–Less to decommission

2012-09-03 18

Page 19: Subsea Processing - · PDF filein total recovery Lufeng Multiphase pumping • Installed 1997 • 12 years in operation ... • 50% of equity prod Other major subsea processing projects:

19

Water

handling

Gas

Treatment

Power

transmission

&distribution Separation Boosting

Gas

compression

Cooling Flow

Assurance

Monitoring System

design

Installation,

intervention

&IMR

Controls

Storage

Structures

Pipelines &

Risers

Subsea

Field centre

technology

HSE?

Oil

Treatment Support

Systems

Main processing systems

Supporting systems

Artificial

Lift

Subsea Factory – Key Building Blocks

Page 20: Subsea Processing - · PDF filein total recovery Lufeng Multiphase pumping • Installed 1997 • 12 years in operation ... • 50% of equity prod Other major subsea processing projects:

Existing Subsea Toolbox within Statoil

Classificati

on: Internal

2013-02-15

20

Gullfaks Compression

• DG3: May 2012

• Inc. recovery: 22 mill boe

Åsgard Compression

• DG3: Aug 2011

• Inc. recovery: 280 mill boe

Subsea Factory

• Realise by 2020

• Towards 60% recovery

• Improved CAPEX OPEX HSE

Troll Water Separation

• Installed 1999

• 10 000 bopd

Tordis Separation and boosting

• Installed 2007

• Designed to increase oil

recovery from 49% to 55%

Tyrihans Sea water injection

• Installed 2009

• Design: 10% increase

in total recovery

Lufeng Multiphase pumping

• Installed 1997

• 12 years in operation

• Enabler for FD

Subsea large share of production:

• 521 subsea wells

• 40% of Statoil operated NCS prod

• 50% of equity prod Other major subsea processing projects: PAZFLOR – subsea separation and boosting

(Total)

MARLIM – subsea separation and water

injection (Petrobras)

Page 21: Subsea Processing - · PDF filein total recovery Lufeng Multiphase pumping • Installed 1997 • 12 years in operation ... • 50% of equity prod Other major subsea processing projects:

Pump system

Production riser Umbilical

riser

2012-09-03 21

Page 22: Subsea Processing - · PDF filein total recovery Lufeng Multiphase pumping • Installed 1997 • 12 years in operation ... • 50% of equity prod Other major subsea processing projects:

Hydrocarbon boosting

• Pump close to wellhead enables

–Reduced wellhead pressure

–Increased drawdown

–More pressure to push production

to platform

• What can be achieved (technologies

will be reviewed in later lecture)

–50 to 150 bar for multiphase

production

–200+ bar for single phase

Pre

ssu

re

Distance

Original pressure profile

With pressure boosting

Wellhead

Riserbase

2012-09-03 22

Page 23: Subsea Processing - · PDF filein total recovery Lufeng Multiphase pumping • Installed 1997 • 12 years in operation ... • 50% of equity prod Other major subsea processing projects:

23

Value Creation – with Subsea Boosting

Page 24: Subsea Processing - · PDF filein total recovery Lufeng Multiphase pumping • Installed 1997 • 12 years in operation ... • 50% of equity prod Other major subsea processing projects:

Value Creation – with Subsea Boosting

24

Page 25: Subsea Processing - · PDF filein total recovery Lufeng Multiphase pumping • Installed 1997 • 12 years in operation ... • 50% of equity prod Other major subsea processing projects:

Pump sizing example

• Power requirement for a single phase pump:

–20000 bbld/d of liquid (3180 m3/d)

–100 bar pressure boost

–Pump efficiency = 0.75

–P [W] = Q [m3/s] * dP [Pa] / Efficiency

–P [W] = 490000

2012-09-03 25

Page 26: Subsea Processing - · PDF filein total recovery Lufeng Multiphase pumping • Installed 1997 • 12 years in operation ... • 50% of equity prod Other major subsea processing projects:

Boosting – Lufeng (1997)

2012-09-03 26

Page 27: Subsea Processing - · PDF filein total recovery Lufeng Multiphase pumping • Installed 1997 • 12 years in operation ... • 50% of equity prod Other major subsea processing projects:

Boosting experience - Lufeng

Business case Artificial lift: enabler for field development

General experience World first – very positive.

Design life 7 years. Expected life 3-5 years, but shut in after

12.

Issues Mechanical seals (in operation, also in transit)

Penetrator

Control system (air conditioning!)

Electrical connectors (beyond design life)

Lessons learned and

applied

Improved testing and qualification procedures.

Improved / more robust component designs.

Further boosting experience is detailed under Troll Pilot / Tordis / Tyrihans.

2012-09-03 27

Page 28: Subsea Processing - · PDF filein total recovery Lufeng Multiphase pumping • Installed 1997 • 12 years in operation ... • 50% of equity prod Other major subsea processing projects:

Subsea separation applications

• Remove water at wellhead

–Reduced water production reduces pressure drop in pipeline to platform

–Can enable increase in production if topsides facility is bottleneck

–Water injected for disposal (or pressure support)

• Gas liquid separation at riser base

–Production in separate gas and liquid riser

–More efficient boosting for single phase liquid

• Separation to send gas and liquid to different facilities

2012-09-03 28

Page 29: Subsea Processing - · PDF filein total recovery Lufeng Multiphase pumping • Installed 1997 • 12 years in operation ... • 50% of equity prod Other major subsea processing projects:

2011-08-11

Subsea processing –gas/liquid separation

Oil riser

Separator P

Gas riser

Umbilical riser

Page 30: Subsea Processing - · PDF filein total recovery Lufeng Multiphase pumping • Installed 1997 • 12 years in operation ... • 50% of equity prod Other major subsea processing projects:

Subsea processing – water separation and -injection

Production riser Umbilical

riser

2012-09-03 30

Page 31: Subsea Processing - · PDF filein total recovery Lufeng Multiphase pumping • Installed 1997 • 12 years in operation ... • 50% of equity prod Other major subsea processing projects:

Separation experience – Troll Pilot

2012-09-03 31

Page 32: Subsea Processing - · PDF filein total recovery Lufeng Multiphase pumping • Installed 1997 • 12 years in operation ... • 50% of equity prod Other major subsea processing projects:

Production profile with water separation and reinjection

0

1

2

0 5 10 15

Time

Pro

duction r

ate

OilGasWaterOilGasWater

Reduction in water production

Increase in oil and gas production due to reduced wellhead pressure

2012-09-03 32

Page 33: Subsea Processing - · PDF filein total recovery Lufeng Multiphase pumping • Installed 1997 • 12 years in operation ... • 50% of equity prod Other major subsea processing projects:

Separation – Troll Pilot (2000)

2012-09-03 33

Page 34: Subsea Processing - · PDF filein total recovery Lufeng Multiphase pumping • Installed 1997 • 12 years in operation ... • 50% of equity prod Other major subsea processing projects:

Separation experience – Troll Pilot

Business case Increased hydrocarbon production and recovery

Currently injecting ~20 000 bbls/day of produced water 13 years after

installation

General experience World first separation and produced water reinjection system

Robust separator design. No sand jetting necessary to date

Stable operation and near 100% uptime from 2008

Issues Electrical connector (start up)

Water ingress to motor due to system design

Inductive level instrument (prototype / backup solution)

Lessons learned and

applied

Improved component design and test / qualification procedures

Improved barrier fluid system design

2012-09-03 34

Page 35: Subsea Processing - · PDF filein total recovery Lufeng Multiphase pumping • Installed 1997 • 12 years in operation ... • 50% of equity prod Other major subsea processing projects:

Separation and boosting – Tordis (2008)

2012-09-03 35

Page 36: Subsea Processing - · PDF filein total recovery Lufeng Multiphase pumping • Installed 1997 • 12 years in operation ... • 50% of equity prod Other major subsea processing projects:

2012-09-03 36

Page 37: Subsea Processing - · PDF filein total recovery Lufeng Multiphase pumping • Installed 1997 • 12 years in operation ... • 50% of equity prod Other major subsea processing projects:

Separation experience - Tordis

Business case Increased hydrocarbon production and recovery through water

reinjection (debottlenecking) and multiphase hydrocarbon boosting

General experience World first application of produced water reinjection with sand

management, multiphase metering, multiphase boosting of

wellstream fluids. Modular design

Successful start up and operation for 4 months (then bypassed due

to injection well issue). Multiphase pump restarted October 2009

for 3 months. System modifications currently underway.

Issues Challenging tie-in to existing control system.

Challenging connection of umbilical barrier fluid supply

Gas evolution (topsides) from new power umbilical

Multiphase meter start up & calibration. Acoustic leak detection

Lessons learned

and applied

High speed communications preferable where sophisticated

instrumentation is utilised (applied on Tyrihans)

2012-09-03 37

Page 38: Subsea Processing - · PDF filein total recovery Lufeng Multiphase pumping • Installed 1997 • 12 years in operation ... • 50% of equity prod Other major subsea processing projects:

Separation experience - Tordis

2012-09-03 38

Page 39: Subsea Processing - · PDF filein total recovery Lufeng Multiphase pumping • Installed 1997 • 12 years in operation ... • 50% of equity prod Other major subsea processing projects:

Pazflor – Gas liquid separation

LC

P

C

From wellhead

Multiphase

Gas

Liquid

Riser to platform

2012-09-03 39

Page 40: Subsea Processing - · PDF filein total recovery Lufeng Multiphase pumping • Installed 1997 • 12 years in operation ... • 50% of equity prod Other major subsea processing projects:

Pazflor – Gas liquid separation

• Start-up 2011 (operated by Total – Statoil ~24%)

• Enables production from Miocene reservoir at 800 m water depth

• Gas /liquid separation

–Liquid boosting 2.3 MW hybrid pumps

• Pumps tolerate gas

–Vertical Separator design

• minimal gas carry under

• Sand removal through liquid line

–Gas free floating to FPSO

2012-09-03 40

Page 41: Subsea Processing - · PDF filein total recovery Lufeng Multiphase pumping • Installed 1997 • 12 years in operation ... • 50% of equity prod Other major subsea processing projects:

Separation qualities

• Separation system must meet requirements from downstream systems

• Water reinjection

–Typically 1000 ppm oil in water

• Gas liquid separation for efficient oil boosting

–5 t0 10 vol % gas in liquid

• Gas scrubbing systems

–Liquid in gas determined by application

• Protection of downstream compressor

• Downstream flow assurance solution

2012-09-03 41

Page 42: Subsea Processing - · PDF filein total recovery Lufeng Multiphase pumping • Installed 1997 • 12 years in operation ... • 50% of equity prod Other major subsea processing projects:

Sand handling

• Maximum sand production is typically 10 ppm by weight

–Sand type and size distribution varies between fields

• Problems caused by sand

–Pumps will be worn out

–Separators will fill up

• 10000 m3/d of liquid with 10 ppm of sand

–100 kg/d of sand

–30 to 40 tons per year

2012-09-03 42

Page 43: Subsea Processing - · PDF filein total recovery Lufeng Multiphase pumping • Installed 1997 • 12 years in operation ... • 50% of equity prod Other major subsea processing projects:

Compression

• Compression is the most recent subsea processing technology

–Not yet implemented – but two projects will be in operation by 2016

• Compression is comparable to pumps but used for fields with mostly gas

–Typically a few volume % liquid

• Traditional topsides compressors have low tolerance for liquid, resulting in two

approaches to subsea compression

–Separate gas so that a “traditional” compressor can be used

–Build a liquid tolerant or “multiphase” compressor

2012-09-03 43

Page 44: Subsea Processing - · PDF filein total recovery Lufeng Multiphase pumping • Installed 1997 • 12 years in operation ... • 50% of equity prod Other major subsea processing projects:

Subsea compression development

Field Gullfaks Åsgard Ormen

Lange

Snøhvit Peon

Planned

Installed

2015 2015 ??? 2023+ 2020+

Design life

(yrs)

20 30 30 30 20

Depth (m) 135 260 850 340 385

Tieback (km) 15 40 120 143/180

No of units 2 2 4 4 2

Pressure

boost (bar)

30 50 60-70 70 40

Power (MW) 10 20 58 5-9

VSD Topside Topside Subsea Subsea Not determ.

2012-09-03 44

Page 45: Subsea Processing - · PDF filein total recovery Lufeng Multiphase pumping • Installed 1997 • 12 years in operation ... • 50% of equity prod Other major subsea processing projects:

Subsea compression development

2012-09-03 45

Page 46: Subsea Processing - · PDF filein total recovery Lufeng Multiphase pumping • Installed 1997 • 12 years in operation ... • 50% of equity prod Other major subsea processing projects:

Subsea compression development

Length 70 meters

Width 54 meters

Height 25 meters

Total weight 6000 Tons

Gas Production 60 MSm3/d

Condensate Production 7200 Sm3/d

Electrical Power Demand 58 MW

Target Availability 97.5%

Ormen Lange is operated by Shell

2012-09-03 46

Page 47: Subsea Processing - · PDF filein total recovery Lufeng Multiphase pumping • Installed 1997 • 12 years in operation ... • 50% of equity prod Other major subsea processing projects:

Control system

HV Power system

Process system

2012-09-03 47

Page 48: Subsea Processing - · PDF filein total recovery Lufeng Multiphase pumping • Installed 1997 • 12 years in operation ... • 50% of equity prod Other major subsea processing projects:

Nyhamna Pit

2012-09-03 48

Page 49: Subsea Processing - · PDF filein total recovery Lufeng Multiphase pumping • Installed 1997 • 12 years in operation ... • 50% of equity prod Other major subsea processing projects:

2012-09-03 49

Page 50: Subsea Processing - · PDF filein total recovery Lufeng Multiphase pumping • Installed 1997 • 12 years in operation ... • 50% of equity prod Other major subsea processing projects:

Subsea compression example

• Need for compressor with:

–40 bar pressure boost

–5 MSm3/d gas flow rate

–50 bar compressor suction pressure (pressure ratio is important)

–40°C inlet temperature

–Power requirement 5.3 MW

–Outlet temperature 100°C

2012-09-03 50

Page 51: Subsea Processing - · PDF filein total recovery Lufeng Multiphase pumping • Installed 1997 • 12 years in operation ... • 50% of equity prod Other major subsea processing projects:

Why subsea seawater injection

• Space and weight is at a premium at existing platforms

–Difficult to fit a water injection system weighting several hundred tons

• New discoveries ar often tied back to existing platforms some distance away

–Pipeline can be expensive

• Different water types can not be mixed in injection systems

–Sea water

–Produced water

2012-09-03 51

Page 52: Subsea Processing - · PDF filein total recovery Lufeng Multiphase pumping • Installed 1997 • 12 years in operation ... • 50% of equity prod Other major subsea processing projects:

Raw seawater injection system

Production riser Umbilical

riser

2012-09-03 52

Page 53: Subsea Processing - · PDF filein total recovery Lufeng Multiphase pumping • Installed 1997 • 12 years in operation ... • 50% of equity prod Other major subsea processing projects:

Subsea raw seawater injection – Tyrihans (2010)

2012-09-03 53

Page 54: Subsea Processing - · PDF filein total recovery Lufeng Multiphase pumping • Installed 1997 • 12 years in operation ... • 50% of equity prod Other major subsea processing projects:

Subsea raw seawater injection experience - Tyrihans

Business case Increased oil recovery through combination of gas and water

injection, using subsea raw seawater injection for the first time in

Statoil. Estimated IOR of 10% from subsea RSWI

General experience

to date

Powerful subsea injection system, utilising 2 x 2.5 MW pumps

Topsides modifications plus pump system onshore wet testing carried

in 2008. Pumps installed 2009. Well completion and system start up

due in Q4 2010

Fault tolerant condition monitoring system and high speed

communications

Issues Challenging control system interfaces (solved by good cooperation

between key suppliers and operator)

Lessons learned

and applied

High speed fibre optic comms system (TCP/IP data transmission) –

learning from Tordis

2012-09-03 54

Page 55: Subsea Processing - · PDF filein total recovery Lufeng Multiphase pumping • Installed 1997 • 12 years in operation ... • 50% of equity prod Other major subsea processing projects:

Other important parts

• Advanced process monitoring and control

–Subsea processing has much higher monitoring needs than traditional

subsea systems

• Shorter response time

• More sensors

• More complex sensors

• Cost-efficient installation, maintenance and retrieval

–Large parts to be installed

–Need for retrieval when parts break or wear out

–Regular inspection

2012-09-03 55

Page 56: Subsea Processing - · PDF filein total recovery Lufeng Multiphase pumping • Installed 1997 • 12 years in operation ... • 50% of equity prod Other major subsea processing projects:

Other important parts

• Long distance power transfer

–Step-out distance below 15 to 20 km

• Power transfer at ~7 kV with topsides VSD

• Examples: Troll Pilot, Tordis SSBI

–Step-out distance ~20 to ~80 km

• Power transfer at 22 to 52 kV with topsides VSD

• Topside step-up and subsea step-down transformer required

• Examples: Tyrihans, Åsgard Subsea Compression,

–Step-out distance above ~80 km

• Power transfer at 132 kV and 16 2/3 Hz (for reduced power loss)

• Subsea VSDs and power distribution

• Example: Ormen Lange, Snøhvit

• Possible step-out distances will depend on power requirement and number of units

2012-09-03 56

Page 57: Subsea Processing - · PDF filein total recovery Lufeng Multiphase pumping • Installed 1997 • 12 years in operation ... • 50% of equity prod Other major subsea processing projects:

Power and control umbilical

• One three phase high voltage (HV)

circuit per pump/compressor

• Barrier fluid (one line per

pump/compressor + one spare)

• Fibre optics

• LV power

• Hydrate inhibitor

• Possibility of combining with control

umbilical for subsea system should be

examined

2012-09-03 57

Page 58: Subsea Processing - · PDF filein total recovery Lufeng Multiphase pumping • Installed 1997 • 12 years in operation ... • 50% of equity prod Other major subsea processing projects:

Technology needs

• Pumps:

–Higher hydrostatic pressure

–Larger capacities (volume, head, higher viscosities, gas tolerance)

–Larger motors

–Reduced weight and size of topsides systems

• Separation

–From 300 to 3000 m water depth – compact technology/in-line separation

–From “normal” fluids to viscous oils – electrostatic coalescence

–From bulk separation to export qualities

• Compression

–Simplified systems – wellstream compression

2012-09-03 58

Page 59: Subsea Processing - · PDF filein total recovery Lufeng Multiphase pumping • Installed 1997 • 12 years in operation ... • 50% of equity prod Other major subsea processing projects:

5

9

ARCTIC FACTORY

HEAVY OIL FACTORY

DEEP WATER FACTORY

EXTENDED REACH FACTORY

COMPACT

SEPARATION

DEEPER

INSTALLATION &

IMR

ARTIFICIAL LIFT

ESP & DUAL

BOOST

SEA WATER

INJECTION

SUBSEA FIELD

CENTRE GAS TREATMENT

HIGH VISCOSITY

BOOSTING

OIL STORAGE

& OFFLOADING OIL TREATMENT

INTERVENTION SIMPLIFIED

COMPRESSION

POWER

DISTRIBUTION

SIMPLIFIED

BOOSTING WATER SEPARATION

& INJECTION

LONG DISTANCE OIL

TRANSPORT

HIGH CAPACITY

BOOSTING

Subsea Factory Menu – Key technology elements

SUBSEA-TO-HOST FACTORY

BROWNFIELD FACTORY

Page 60: Subsea Processing - · PDF filein total recovery Lufeng Multiphase pumping • Installed 1997 • 12 years in operation ... • 50% of equity prod Other major subsea processing projects:

Discussion on economy

• Value of increased production

• Development cost

• Operational expenses

• Other considerations

2012-09-03 60

Page 61: Subsea Processing - · PDF filein total recovery Lufeng Multiphase pumping • Installed 1997 • 12 years in operation ... • 50% of equity prod Other major subsea processing projects:

Assignment

Oil discovery: 10 MSm3 of oil

300 m water depth

5000 m3/d of oil and 5000 m3/d of water

10 km

30 km

Platform B:

Available process

capacity for oil

and water.

Plenty of power

available.

Platform A:

Process capacity

for oil, but only

very limited water

capacity.

Some power

available

2012-09-03 61

Page 62: Subsea Processing - · PDF filein total recovery Lufeng Multiphase pumping • Installed 1997 • 12 years in operation ... • 50% of equity prod Other major subsea processing projects:

Literature

• Offshore Magazine. Review poster of subsea procesing projects

–http://www.offshore-mag.com/content/dam/offshore/maps-posters/SubseaBoosting-022113.pdf

• OTC 24307-MS “Steps to the Subsea Factory” Ole Økland, Simon Davies, Rune Mode Ramberg,

Hege Rognø, Statoil ASA

• OTC 20619 Experience to Date and Future Opportunities for Subsea Processing in Statoil, Simon

Davies and William Bakke, Statoil ASA; Rune Mode Ramberg and Roger Oen Jensen, Statoil Gulf

of Mexico

• OTC 20261 Subsea Power Systems – a Key Enabler for Subsea Processing, Steinar Midttveit,

Bjarne Monsen, Snorre Frydenlund, Karl Atle Stenevik, Statoil ASA.

• OTC 18749 The Tordis IOR Project, Ann Christin Gjerdseth, FMC Technologies and Audun

Faanes and Rune Ramberg, Statoil

• Video- «subsea yellow»:

http://www.statoil.com/en/technologyinnovation/fielddevelopment/aboutsubsea/pages/havbunnsan

legg.aspx

2012-09-03 62

Page 63: Subsea Processing - · PDF filein total recovery Lufeng Multiphase pumping • Installed 1997 • 12 years in operation ... • 50% of equity prod Other major subsea processing projects:

The presentation is based on Håvard Eidsmoen lecture in 2011

2012-09-03 63

Page 64: Subsea Processing - · PDF filein total recovery Lufeng Multiphase pumping • Installed 1997 • 12 years in operation ... • 50% of equity prod Other major subsea processing projects:

Subsea processing – one example

Oil riser

Separator P

Gas riser

Umbilical riser

2012-09-03 64

Page 65: Subsea Processing - · PDF filein total recovery Lufeng Multiphase pumping • Installed 1997 • 12 years in operation ... • 50% of equity prod Other major subsea processing projects:

100m

150m

Cat J cantilever limit (68m oMSL)

Wellhead deck (25m oMSL)

Xmas tree deck (30m oMSL)

Weather deck (35m oMSL) typicals

2013-12-20 65 Classification: Internal