TEPUK – Subsea Europe 30/10/08

Subsea technology

& potential significance to the UK

2 - TEPUK – Subsea Europe 30/10/08

Top 18 Operators

2,927 Subsea Trees 439 Projects

Top 18 Operators responsible for

74% of subsea trees

Source:Quest Subsea Forecast Awards August2008

TO

TA

L

3 - TEPUK – Subsea Europe 30/10/08

Total subsea assets – Mid 2008–

Gulf of MexicoGulf of Mexico Matterhorn ( Matterhorn (injinj))

UKUK EllonEllon Grant Grant Nuggets Nuggets Otter Otter ForvieForvie Jura Jura

FlowingFlowing

Under studyUnder study

Under ConstructionUnder Construction

CLOV CLOV Bloc 32 Bloc 32

ANGOLAANGOLA Girassol Girassol Dalia Dalia Rosa Rosa

CONGOCONGO MohoMoho BilondoBilondo

NORWAYNORWAY SkyrneSkyrnebyggvebyggve

KessogKessogLagganLaggan / /TormoreTormore

NigeriaNigeria AkpoAkpo UsanUsan

Egina - Preowei

HildHild Victoria Victoria

ArgentineArgentine ArgoArgo

MohoMoho NorthNorth MTPS MTPS

NetherlandNetherland L4G L4G K5F K5F

RUSSIA RUSSIA ShtokmanShtokman

Major non op.Major non op.

AustraliaAustralia Ichthys Ichthys

SnohvitSnohvit Tordis Tordis

AasgardAasgardTyrihansTyrihans

ChinookChinook Tahiti Tahiti

Bloc 31Bloc 31

PazflorPazflor

BrazilBrazilXereleteXerelete

BongaBonga

400 subsea wells

operating from 2015

37% of operated production

4 - TEPUK – Subsea Europe 30/10/08

0

500

1000

1500

2000

2500

1960 1970 1980 1990 2000 2010

Years

Wa

ter

De

pth

(m

)

North Sea

West Africa

Golf of Mexico

Note : Bubble size represents the number of subsea wells

TOTAL Subsea Projects Track Records

10 Wells

5 - TEPUK – Subsea Europe 30/10/08

Numerous technological challenges

Deep Water

Long tie backs

Complex fluids (Viscous, heavy, low energy)

Smaller reservoirs

Environment (metoecan conditions, protection)

Industry cost current trend

New architectural concepts

Extended tie-back for paraffinic and none paraffinic fluids

Subsea boosting up to 200 bars

Subsea processing : decanter well, subsea water treatmentand injection

All electric technology : K5F AET pilot start-up, ElectricalDHSV development

Innovative materials : insulation, composite

Subsea « autonomous » vehicles

Subsea gas compression

6 - TEPUK – Subsea Europe 30/10/08

The challenge of deep water - Girassol – AngolaA challenging Flower…

Block 17, Angola

Deepest and largest subsea development

at Project Sanction in July 1998

Production capacity 240,000 bopd

FPSO : 2 Mbls storage, 23,900t topsides

39 wells and 11 manifolds

First use of Riser Towers (3 off)

Extensive qualification program

Startup December 2001

Girassol has opened new

perspectives to the Subsea

Technology

Riser

Towers

7 - TEPUK – Subsea Europe 30/10/08

The challenge of deep water

DALIA – ANGOLA

Integrated Production Bundles

8 - TEPUK – Subsea Europe 30/10/08

The challenge of subsea processing and boostingPaz Flor – Angola

Project Sanctioned in Jan. 2008

Production capacity 230,000 bopd

FPSO : 2 Mbls storage, 34,000t

topsides

49 wells and 3 manifolds

3 Subsea Separation Units with

multiphase booster pumps

Startup in 2011

Why Subsea Separation

Effective solution to manage flow assurance

issues with the Miocene Heavy Oil

9 - TEPUK – Subsea Europe 30/10/08

The challenge of long tie backs - Canyon Express( Gulf of Mexico )

Water depth world record in year 2002

with 2,225 meters

100km tie-back from 3 fields

Capacity : 500 MMCFD (14 MMSm /d)

2 x 12” looped flowlines, 9 wells

Multiphase flow

Intelligent well completions

Start-up September 2002

Subsea tree

12-inch flow line

Main umbilical

Methanol line

Electro-hydraulicdistribution unit

Camden Hills(Marathon)

2,225m / 2wells

Aconcagua(Total)

2,170m / 4wells

King’s Peak(BP)

2,000m / 3wells

10 - TEPUK – Subsea Europe 30/10/08

Step Change – All electric trees K5F Netherland

First Subsea development with DC electric

Xmas Trees

Production Capacity 2MMsmd

2 wells 10 km subsea tie back to K6N Plaftform

Water depth 40m

Extensive qualification program

First Gas in September 2008

Stimulus for all Electric Subsea Technology

Step change improvement in reliability &

availability

Address limitations of electro-hydraulic systems

Ultra deepwater applications

Long tieback distances

Electro-hydraulic components failures

Environmental Issues

Enhanced Functionality

Response times

Condition monitoring

Performance trending

11 - TEPUK – Subsea Europe 30/10/08

The challenge of HP/HT subsea developments Kessog field

15 000 psi

185 deg.C

73 tons

12 - TEPUK – Subsea Europe 30/10/08

FRIGG FIELD

ELECTRICAL

CABLE

MeOH LINE

16” SEA LINE

INSTRUMENT

CABLES

TEMPLATE

UMBILICALS

FIELD CONTROL

STATION

Significance forthe North Sea

1983 : First Gas of North East Frigg

Subsea Template , Field control from

articulated column

1) To develop small or marginal

reservoirs with tie-back to

existing infrastructure

2) Extend production plateau of our

mature fields

3) To develop deepwater discoveries

Subsea developments allow

2002 : Otter First Oil, 3 production wells

equipped with ESPs for artificial lift

13 - TEPUK – Subsea Europe 30/10/08

North Sea - Subsea to extend production plateauThe Alwyn Area Story …

Initial Production in 1987 for 12 years

21st anniversary celebrated last june and… another 20 years still to go

Alwyn North Fields

Dunbar Platform & Rig

14 - TEPUK – Subsea Europe 30/10/08

15 - TEPUK – Subsea Europe 30/10/08

1st subsea well PN1 1988

The Alwyn Area example… First Gas in 1987

140

Production forecast

16 - TEPUK – Subsea Europe 30/10/08

17 - TEPUK – Subsea Europe 30/10/08

The Alwyn Area example… Ellon & Grant 1994-98

18 - TEPUK – Subsea Europe 30/10/08

The Alwyn Area example… Tie back of Nuggets 2001

68 Kms tie-back -10”

Subsea control from Dunbar

Trunkline always operates

in hydrates region

Horizontal trees

19 - TEPUK – Subsea Europe 30/10/08

Forvie 20051 subsea well

1 subsea manifold

for future tie-backs

20 - TEPUK – Subsea Europe 30/10/08

The Alwyn Area example…

JURA 2008….ISLAY 2010….

Islay

Historical fields have

their life extended

140

21 - TEPUK – Subsea Europe 30/10/08

Jura Project - UK

Fast Track Project : First Gas May ’08,

only 17 month after discovery

One of the largest discovery for

TEPUK. Increase Alwyn Area

remaining reserves by 50% (170 Mboe)

Capacity 8Mscmd (50,000 boepd)

The field is located in 113 m water

depth, 32km from Alwyn and 20km

from Dunbar

2 well subsea tieback to existing Forvie

Subsea Manifold

3km bundle integrating all process

functions

HP/HT development (600b / 120°C)

Innovation

IL3 Subsea HIPPS

Communication through Optic Fiber

Largest Bundle towhead ever installed

Chemical Injection Metering Valve

22 - TEPUK – Subsea Europe 30/10/08

Deep water challenge – West of Shetland -Laggan &Tormore A New Subsea Challenge

Laggan field discovered in 1986 (Block

206/1a)

Tormore field discovered in 2007 (Block

205/5a)

Production Capacity 500 MMscfd

125km north west of the Shetland Island

600 m water depth

2 six slot template manifolds

Provision for subsea compression in the

late field life

TEPUK – Subsea Europe 30/10/08

Going to the West of Shetlands…Harshest environment in UK

Extreme waves : 100yr Hs-18m; Hmax 33m

Persistent weather – little / no calm

High winds, low water temperatures,strong currents

Laggan Site - Wave Height (1 Year Return Period)

0

5

10

15

20

25

30

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

Metr

es Hs

Hmax

_

= 11.6m

Source : Metocean Criteria for the Laggan Field (UK Block 206/1). PhysE 28th October 2005

Weather WindowWeather Window

600m

24 - TEPUK – Subsea Europe 30/10/08

New 500 MMscfd Gas

Processing Plant at Sullom Voe

2 x 18” gas lines

chemical injection

line

control

umbilical

rock dump

material

140km Multiphase

Pipelines

(500 MMscfd)

374km 24” Gas Export Pipeline

SVT to St Fergus

500 MMscfd Laggan-Tormore

Tormore

Sullom Voe

St Fergus

Laggan /Tormore – Long tie back Alternative

Subsea Production System

(600m water depth)

Laggan & Tormore (5 + 3 wells)

25 - TEPUK – Subsea Europe 30/10/08

Total E&P UK Operated Production

0

50

100

150

200

250

300

350

400

2001 2003 2005 2007 2009 2011 2013 2015 2017 2019

Op

era

ted

Pro

du

cti

on

in

kb

oe

/d

0%

10%

20%

30%

40%

50%

60%

In 2007, 20% of TepUK production was Subsea

From 2013 onwards, it will be 50%

Operared Platform Production

Operated Subsea Production

Percentage of Subsea Production

26 - TEPUK – Subsea Europe 30/10/08

Subsea Developments - Key to Success-Lessons learnt

Dedicated project team

For engineering phase, tenders, project phase

Comprehensive Testing programme treated as key commissioning

activities

Qualification testing for all new components

System testing ( FAT for each item + integration )

External Interface Testing

Operational Testing

Dedicated team of inspectors provided by the operator

Early Involvement of end users

27 - TEPUK – Subsea Europe 30/10/08

Subsea Systems – The Downside – Systems

ObsolescenceParts no longer available

Often for relatively new systems

VendorsFocus on big new projects

Lack of interest in older systems

Lack of personnel to support the systems

Solution to obsolescence is to sell a newsystem whilst withdrawing support to the oldersystems

New Systems

Quality control – reduced.

Systems appear to be in place, but are the

people there?

Corporate Knowledge (Vendor and Operator) –

are we repeating past mistakes?

Leaks due to materials

Correct ones specified

Wrong ones installed

Global efficiency of subsea production below platform production

Problems often appear very early after installation and require long recovery procedures.

28 - TEPUK – Subsea Europe 30/10/08

Subsea Systems – The Downside – Support

DSVs / ROVSVs

Shortage – unable to readily obtain

vessels for rapid intervention

New vessels coming onto the market

Where are the experienced crews /

engineers / divers to man them?

Cost

Competence

Lack of training

Vendor personnel

Operator personnel

Two contradictory assumptions prevalent:

Instrument subsea is the same as an

instrument topsides.

It’s a black box, we need the vendor.

29 - TEPUK – Subsea Europe 30/10/08

Subsea production – Potential improvements

Tie-back to a platform – Primary importance to get first oil in time followed by a

sustainable production

Reliability of systems to be improved

Quality control

Requirements for Routine maintenance to be minimized : difficult and expensive

Unplanned incidents cost huge loss of production

Long term operability of subsea systems must become a major trend for

improvement,

Operability of long subsea tie-backs is field proven but not yet a routine

operation,

Impact of subsea developments on topsides often under estimated,

Standardization : Typical project approach going systematically for tenders is not

compatible with standardization of subsea equipment , what can we do ?

General lack of competency, lack of inspection resources, are we doing enough ?

30 - TEPUK – Subsea Europe 30/10/08

Conclusion – Subsea , significance to the UK

UKCS is a mature production area (38 Billion barrels already produced)

10 to 15 remain to be produced, 5 to 10 yet to be discovered

90 % of new developments mobilize less than 50 MBoe, most below 20.

Existing Infrastructure + Existing Subsea technology available in the

UK are well adapted to this problematic.

However success will be very dependant of the price of oil and

capacity of the industry to keep costs at an acceptable level.

Today, and specially today, such costs are not at a reasonable level in

the UK.

31 - TEPUK – Subsea Europe 30/10/08