substantiation and assessment of claims for extensions of time

Upload: egglestona

Post on 15-Oct-2015

27 views

Category:

Documents


1 download

DESCRIPTION

Substantiation and Assessment of Claims for Extensions of Time

TRANSCRIPT

  • 5/25/2018 Substantiation and Assessment of Claims for Extensions of Time

    http:///reader/full/substantiation-and-assessment-of-claims-for-extensions-

    Substantiation and assessment of claims for extensions of time

    M.M. Kumaraswamya,*, K. Yogeswaranb

    aThe University of Hong Kong, Pokfulam, Hong KongbKowloon Canton Railway Corporation, West Rail Project, Hong Kong

    Received 12 January 2001; received in revised form 6 June 2001; accepted 13 July 2001

    Abstract

    Standard forms of contract provide for extensions of time (EOT) due to excusable delays, and EOT claims are common in many

    construction projects. The contractor and the supervising engineer often spend considerable time on substantiating and assessing

    such claims. However, a variety of diverse techniques have been employed for such evaluations. A study was undertaken to analyse

    different EOT evaluation techniques in Hong Kong, which continues to be a hotbed of construction activity attracting international

    organisations. Reasons for delays in the submission and assessment of EOT were also probed. Conclusions on the suitability of

    different techniques are drawn from an analysis of both the literature reviewed and a consolidation of practitioner perceptions, as

    derived from a questionnaire survey and subsequent in-depth interviews. This leads to recommendations for explicit policies, clear

    guidelines, tool-kits and improved contractual procedures that will upgrade the management of this crucial area. # 2002 Elsevier

    Science Ltd and IPMA. All rights reserved.

    Keywords: Claims; Evaluation; Extensions of time; Hong Kong

    1. Background and introduction

    Delays are a major source of claims and disputes inconstruction projects [1] and have even been cited as the

    most common and costly cause of problems [2,3].

    Delays themselves may arise from a wide variety of

    causes. Considerable research efforts have been devoted

    to identifying and categorising the principal factors that

    commonly contribute to delays. For example, Kumar-

    aswamy and Chan [4] compared a cross-section of

    recent findings on major factors causing delays in

    countries ranging from the USA, UK, Turkey, Nigeria,

    Saudi Arabia and Indonesia with Hong Kong. How-

    ever, disagreements on the responsibilities and liabilities

    for such delays continue to trigger hotly contested con-

    tractual claims.

    A study that investigated contractual claims from 67

    completed civil engineering projects in Hong Kong

    revealed that 57 out of the 67 projects were delayed [5].

    In such projects, the contractor submits claims for

    extensions of time using one or more of an assortment

    of techniques available for substantiation, upon which

    the engineer then assesses the claims arising from excu-

    sable delays, also using one or more of a variety of

    approaches.Various common techniques and approaches were

    examined by Alkass et al. [6], who reviewed and com-

    pared the following delay analysis techniques used in

    USA and Canadian contractual regimes, prior to pro-

    posing a new Isolated Delay Type (IDT) technique.

    1.1. Global Impact technique

    All the delays are plotted on a summary bar chart.

    The total delay to the project is rather simplistically

    assumed to be the sum total of all individual activity

    delay durations. This may well over-estimate the actual

    overall delay, as it does not make allowance for con-

    current delays in parallel activities.

    1.2. Net Impact technique

    Only the net effect of all delays including concurrent

    delays are plotted on a bar chart based on the as-built

    schedule. All delays, disruptions, variation orders and

    suspensions are first plotted on the as-built schedule.

    The net effect of all delays is next estimated taking

    concurrent delays into account. The requested time

    extension is then taken as the time difference between

    0263-7863/01/$22.00 # 2002 Elsevier Science Ltd and IPMA. All rights reserved.

    P I I : S 0 2 6 3 - 7 8 6 3 ( 0 1 ) 0 0 0 5 2 - 7

    International Journal of Project Management 21 (2003) 2738

    www.elsevier.com/locate/ijproman

    The views expressed in this paper are those of the authors.

    * Corresponding author. Tel.: +852-2859-1976; fax: +852-2559-

    5337.

    E-mail address: [email protected](M.M. Kumaraswamy).

    mailto:[email protected]:[email protected]
  • 5/25/2018 Substantiation and Assessment of Claims for Extensions of Time

    http:///reader/full/substantiation-and-assessment-of-claims-for-extensions-

    the as-planned and as-built completion dates, the latter

    having been adjusted by the net effect of excusable

    delays. However, this method does not use network

    programmes and may therefore misinterpret the true

    effect of a delayed activity on overall completion.

    1.3. But for technique (or As Built But for techniqueas described by Bordoli and Baldwin [7], Pickavance

    [8] and Adams [9])

    All delays for which one party (the owner according

    to Pickavance [8]) accepts responsibility, are injected

    into the as-built schedule. Using the CPM network

    scheduling format, the updated schedule yields a revised

    project completion date. This is compared against the as-

    planned schedule. It is concluded that the difference

    between the as-planned and the revised project completion

    dates is a result of delays that were beyond that parti-

    cular partys control. For example, if the owners were

    using this technique, they would identify and inject allnon-excusable delays (attributable to the owners fault)

    into the as-built schedule. The adjusted schedule would

    generate a completion date that theoretically could have

    been achieved but for the owner-caused delays. Bordoli

    and Baldwin [7] and Adams [9] go a logical step further

    in suggesting the deduction of all excusable delays,

    including those due to neutral events i.e. neither partys

    responsibility. The difference between the adjusted (but

    for excusable delays) completion date and the as-plan-

    ned completion date is then attributable to the con-

    tractor. However, this technique does not account for

    changing critical paths during the progress of the project.

    1.4. Time Impact technique

    This analysis examines the delay effects during the

    progress of the project. The impact of each delay or

    delaying event on the schedule is determined at the

    relevant construction stage, the intention being to

    obtain a stop action picture of the project before and/

    or after a major delay impact. The difference between

    the projected completion dates at these two stages is

    determined as the delay to the project that occurred

    during the period, with the total delay to the project

    duration being the sum of all delays during the project.

    But this technique neither scrutinises causes of delays

    nor accounts for concurrent delays

    1.5. Snapshot technique

    Like the Time Impact technique, the snapshot

    approach is based on comparing the as-planned and

    revised as-built schedules that have been implemented

    during the execution of the project. But unlike the Time

    Impact technique, this approach does not focus on spe-

    cific delays or delaying events. Instead, the total project

    duration is divided into a number of time periods, or

    snapshots. The dates of these snapshots usually coincide

    with major project milestones, significant changes in

    planning or when a major delay or group of delays is

    known to have occurred. The relationships and dura-

    tions of the as-built schedule within the snapshot period

    are imposed upon the as-planned schedule, while main-taining the relationships and durations of the as-plan-

    ned schedule for the remaining activities after the

    snapshot period. The project completion date of the

    thus extended schedule is compared with the estab-

    lished, as-planned completion date of the project prior

    to this procedure. The difference between the comple-

    tion dates is taken as the amount of delay that occurred

    to the project as a result of delaying events during that

    snapshot period. The more snapshots (number of time

    periods) chosen, the greater the accuracy. Although

    concurrent delays are considered together, the causes of

    delay are not initially investigated, e.g. in order to

    decide whether they are excusable delays or not.

    1.6. Adjusted as-built CPM technique

    The Critical Path Method (CPM) format is used to

    develop an as-built schedule. Delaying events are depic-

    ted as activities and linked to specific work activities.

    The critical path(s) are identified twice, firstly in the as-

    planned schedule and secondly at the end of the project.

    The difference between the as-planned completion date

    and the adjusted as-built completion date is the amount

    of time for which the claimant would request compen-

    sation. This technique is similar to the net impact tech-nique in that both techniques only show the net effect of

    all claimed delays on the projects completion date and

    do not distinguish between different causes of delay.

    Alkass et al. [6] compared and identified the advan-

    tages and disadvantages of these techniques as discussed

    earlier. They then subsequently proposed the IDT tech-

    nique. The latter essentially considers delay types, con-

    current delays and uses real time CPM analysis,

    harnessing the systematic and objective approach of the

    time impact and snapshot techniques while applying the

    scrutinising approach of the But for technique.

    While Mawdesley et al. [10] also found that network

    techniques are often used for evaluating extensions of

    time, they classified these as: addition method, sub-

    traction method, stage addition method and time

    slice method. Despite the differences in terminology,

    similarities can be identified between these methods and

    some of those described by Alkass et al. [6]. The differ-

    ent types (options) of window analyses described by

    Finke [11] also contain similar approaches, his recom-

    mendation being to select the option that compared the

    completion date indicated by the as-planned schedule,

    as extended by adding excusable delays to the as-plan-

    ned completion date.

    28 M.M. Kumaraswamy, K. Yogeswaran / International Journal of Project Management 21 (2003) 2738

  • 5/25/2018 Substantiation and Assessment of Claims for Extensions of Time

    http:///reader/full/substantiation-and-assessment-of-claims-for-extensions-

    The time extension substantiation and assessment

    techniques used in practice in different contractual

    regimes do not always fit exactly into any of the earlier

    classifications. But the approaches include elements of

    the techniques described earlier. For example, Adams

    [9] has referred to what may be termed static analyses,

    based on either the original programme with delaysadded, or the as-built programme with delays sub-

    tracted. He drew attention to their limitations, for

    example in relying on just one programme and therefore

    one (static) critical pathwhich is contrary to reality.

    He then recommended more dynamic window analyses

    by considering several network programmes, taken at

    regular time intervals (windows)similar in these

    respects to the snapshot technique described by Alkass

    et al. [6] and the window analyses recommended by

    Finke [11] and also described in more detail by Pick-

    avance [8].

    The evident uncertainties, apparent confusion and the

    lack of uniformity/standardisation in the earlier techni-ques also leads to protracted disputes on time extension

    entitlements and any related cost implications. These

    factors led the authors to study this sensitive area with a

    view to identifying the more rationalised and better

    methods if not best practice. While this study was

    based in Hong Kong, the need for similar studies in

    other contractual regimes is also apparent. Scott [12]

    reported the use of a variety of approaches in assessing

    the validity of a claim for an extension of time, based on

    a questionnaire survey in the UK. He also reported on

    the increasing use of project management software for

    substantiating claims for extensions of time. Conlin andRetik [3] compared the features of 16 relevant project

    management software packages available in the market,

    while Bordoli and Baldwin [7] confirmed the wide

    variability in the techniques used for assessment of

    claims for extensions of time in UK, based on an ana-

    lysis of the 96 responses received from contractors,

    architectural practices, project management practices

    and quantity surveyors.

    Following on from these findings and a perception of

    increasing difficulties through similar divergence in

    Hong Kong [5], a questionnaire was formulated to

    identify the common techniques adopted by construc-

    tion professionals in evaluating time extension claims in

    civil engineering works in Hong Kong. Delays in sub-

    mission and assessment of claims were also probed. The

    outcomes from the analysis of the survey responses are

    presented in the following sections.

    2. Questionnaire survey in Hong Kong

    Interviews with some experienced practitioners in

    Hong Kong revealed that it was often difficult to con-

    vince relevant parties (including their own team, let

    alone the opposing team) of the reliability of the more

    accurate techniques, given that they appear to be more

    complex. They were therefore often persuaded to resort

    to simplistic and less reliable techniques (e.g. the Net

    Impact Techniques or other static techniques) in order

    to ensure that their claims were understood and dealt

    with speedily. The questionnaire was therefore for-mulated to investigate the following practices applied in

    the Hong Kong civil engineering project scenario:

    1. common techniques used to substantiate and

    assess claims for extension of time;

    2. reasons for delays in submitting and assessing

    claims for extensions of time;

    3. preferred techniques for submitting/assessing

    claims for extensions of time; and

    4. recommended techniques for substantiating/evalu-

    ating extensions of time.

    The questionnaire was sent to 55 potential respon-

    dents, who were carefully selected for their extensivegeneral experience in civil engineering projects in Hong

    Kong and some particular experience with extension-of-

    time evaluations. This selection was mostly based on the

    authors knowledge of their relevant experience/exper-

    tise in many cases, while a few others in the selected

    sample of 55 were recommended by some of the initially

    chosen industry experts themselves. Thirty four respon-

    ses (yielding a 62% response rate) were received. The

    respondents were civil engineers (23), quantity surveyors

    (seven) and construction lawyers (four). They repre-

    sented consulting engineers (13), contractors (seven),

    employers (six) and others (eight academics and law-yers).

    Their principal industry experience pattern, as shown

    in Table 1, indicates a reasonable spread of both general

    and specific experience among the respondents. Apart

    from the experience in specific sectors (of Employers,

    Consultants or Contractors) shown in Table 1, it was

    also found that the 34 respondents had an average of 17

    years experience in civil engineering type projects and

    also an average of 13 years experience in Hong Kong

    projects. The responses received are analysed in the fol-

    lowing sections. It should be noted that brief pre-

    liminary and follow-up interviews with a few of the

    respondents enabled the integration of supplementary

    observations that are also incorporated in the following

    sections.

    3. Submissions of claims for extensions of time

    The respondents were given three optional categories

    in which to classify the usual timing of submissions of

    details of claims for extensions of time. The response

    summary is shown in Table 2. The timing of the

    occurrence of an excusable event is often arguable, and

    M.M. Kumaraswamy, K. Yogeswaran / International Journal of Project Management 21 (2003) 2738 29

  • 5/25/2018 Substantiation and Assessment of Claims for Extensions of Time

    http:///reader/full/substantiation-and-assessment-of-claims-for-extensions-

    this is analysed in the following sections. Assuming that

    agreement exists on the timing of occurrence of excu-

    sable events, most of the respondents state that the

    submissions of the claims for extensions of time are

    made within the construction period but rarely within 4

    weeks of the occurrence of the event giving rise to the

    claim. Although the 1993 Hong Kong General Condi-tions of Contract for Civil Engineering Works stipu-

    lated that a notice of claim should be served within 42

    days of occurrence of an event, this was reduced to a 28

    day period in the 1999 edition. A 28 day period was

    chosen in the questionnaire in any case, to reflect the

    traditional monthly reporting of progress and events.

    Clearly, events such as inclement weather could be

    analysed within a week from the date of cessation of the

    effects of weather on the activities which are weather-

    sensitive (e.g. earthworks). However, it may be noted

    that since extensions of time associated with inclement

    weather are further sub-classified as non-compensable

    excusable events, contractors often prefer to seek other

    openings that may enable alternative claims for compen-

    sable and excusable events. The respondents were

    requested to identify the reasons for delays in submissionsof details of EOT claims, and these are ranked based on

    the number of responses against each of the reasons.

    Reasons for delays in submissions are ranked in Table 3.

    It appears that the principal reasons for delays in

    submissions are often related to the (1) inability to

    identify the full extent of the delay at the beginning of

    the event causing the delay; and (2) contractors desire

    to focus on the progress of the works. This contractor

    focus on the progress of works may be taken to include

    Table 2

    Timing of submission of details of claims for extensions of time

    Timing of submissions Frequently Sometimes Rarely

    Within 28 days of the occurrence of the excusable event giving rise to the possible delay 2 7 25

    At the end of the original construction period for the relevant section 14 17 3

    Others 0 0 0

    Table 1

    Experience pattern of the 34 respondents to the questionnaire survey

    Experience Average No.

    of years worked

    in a specific sectora

    by those^ who are now in that sector

    Average No.

    of years worked

    in a specific sectora

    taking the whole sample (of 34)

    Experience with employers 19 (by the 6^ now in this sector) 6

    Experience with consultants 18 (by the 13^ now in this sector) 10

    Experience with contractors 16 (by the 7^ now in this sector) 7

    a Sector: is taken to refer to either the Employers, Consultants or Contractors sector Note: four construction lawyers and four academics

    (with industry experience) also responded.

    Table 3

    Reasons for delays in submitting the details of claims for extensions of time

    Ranka Description No. of responses

    1 Overall delay cannot be ascertained/actual delay could not be determined until end of delay or construction 14

    2 Focus on progress of work and not on claim/contractors staff too busy on other tasks/lack of staff (in

    contractors organisation) to deal with EOT claims

    12

    3e General lack of details 63e Lack of contractors management resources 6

    5 The effects are not known/could not foresee that an event would cause a delay until the delay occurred 4

    6e Contractor does not want to cause friction or offend the employer 3

    6e Poor paperwork control by the contractor 3

    6e Contractor wants to know exactly the amount of extension of time required such that their risk to liquidated

    damages can be removed

    3

    9e Benefit of hindsight (choose events that attracts money) 2

    9e Engineer requests excessive details 2

    9e Policy to submit global claims can cause delayed submissions 2

    9e Site staff inexperienced in contract procedures and task undertaken by head office expert who needs time to

    understand claim situation

    2

    9e If the claim is related to inclement weather usually prompt action is taken 2

    a e: (e.g. in 6e) signifies that this rank is shared with other items.

    30 M.M. Kumaraswamy, K. Yogeswaran / International Journal of Project Management 21 (2003) 2738

  • 5/25/2018 Substantiation and Assessment of Claims for Extensions of Time

    http:///reader/full/substantiation-and-assessment-of-claims-for-extensions-

    endeavours to recover non-excusable delays and miti-

    gate excusable delays. A preference to delay a claim

    submission, so as not to generate friction with the

    employer/client and consultant/engineer was also noted

    from general observations and comments received in the

    questionnaires and at related discussions.

    4. Assessment of claims for extensions of time

    The Engineer is obliged to assess the submitted claims

    for extensions of time, while the onus of providing ade-

    quate information for this evaluation rests with the

    claimant (contractor). The respondents were requested

    to identify the timing of assessment of claims for exten-

    sions of time and the summary of responses is shown in

    Table 4. It appears that the assessments are carried out

    at the end of the original construction period in most

    cases. Submissions and assessments are inter-related

    and responses to questions on the timing of submissionsand assessment are consistent (Tables 2 and 4) in iden-

    tifying the more frequent timing to be at the end of the

    construction period.

    The respondents were next requested to identify the

    reasons for delays in assessment of claims for extensions

    of time. These reasons are ranked based on the number

    of responses for each of the reasons. The ranked reasons

    are shown in Table 5. Possible actions that may betaken to address the problems causing delays in assess-

    ment as suggested/formulated by the authors are also

    presented in Table 5.

    It appears that the principal reasons for delays in

    assessments are related to lack of details and clarity in

    substantiation, and delays in submissions of details by

    the claimant. There also appear to be deficiencies in

    procedures and approaches/attitudes that may be traced

    to a lack of clear policies and guidelines. There is a need

    to set out common objectives for the claimant and the

    assessor to achieve speedy settlement of the claims for

    extensions of time. It should be appreciated that the

    contractor and the engineer representing the Employerhave a common goal in achieving speedy and successful

    Table 4

    Timing of assessment of claims for extensions of time

    Timing of assessment Frequently Sometimes Rarely

    Within 28 days of the occurrence of the excusable event giving rise to the possible delay 0 4 30

    At the end of the original construction period for the relevant section 16 16 2

    Within reasonable time from the date of submission of details of the claim by the claimant (contractor) 12 14 6

    Table 5

    Reasons for delays in assessing claims for extensions of time

    Ranka Reasons for the delay in assessment No. of responses Possible action to address the problem

    1 Poorly presented submissions/lack of particulars 18 Provide guidelines on presentation of particulars of

    the claims

    2 Late submission of claims by the contractors/engineer

    waits for final information from contractor

    9 Formulate a clear and pragmatic policy on submission

    and assessment of claims

    3 Insufficient personnel to process the assessment/lack

    of resources and experience

    8 Management/recruitment of experienced personnel

    4e Employers attitude/interference/political 6 Clear policy is required

    4e Consultant would rather wait until end of job 6 Clear policy is required

    6e No timetoo busy/ERs staff too busy with other tasks 4 Resources to be better managed

    6e Collection of relevant facts from site records to establishthe principle of the claim and quantification usually

    takes longer than 28 days/time consuming to check records

    4 Formulate a clear and pragmatic policy on submissionand assessment of claims

    8 Delay in approval by employer 3 Standardise procedures in the employers organisation

    10e Global Impact is uncertain 2 Practical problembut guidelines on interim assessment

    may be useful

    10e Absence of EOT may put pressure on contractor to

    perform more efficiently

    2 Genuine attempt to get the job done but using wrong

    management techniqueneeds a change of mind-set

    10e It is nearly always necessary for the engineer to make an

    interim assessment before receipt of any particulars

    from the contractor

    2 Formulate a policy on interim/final assessment of claims

    10e Because of engineers passive position contractor employs

    a delaying tactics in his submissions

    2 Clearly allocate responsibilities

    a e: (e.g. in 6e) signifies that this rank is shared with other items.

    M.M. Kumaraswamy, K. Yogeswaran / International Journal of Project Management 21 (2003) 2738 31

  • 5/25/2018 Substantiation and Assessment of Claims for Extensions of Time

    http:///reader/full/substantiation-and-assessment-of-claims-for-extensions-

    completion of a project, although manifesting conflict-

    ing financial interests in respect of price levels.

    5. Techniques used in substantiation and assessment

    The respondents were asked to identify the commontechniques used in substantiation and assessment of

    claims for extensions of time and the summary of their

    responses is shown in Tables 6 and 7. It appears that the

    contractors frequently use Global Impact and Net

    Impact techniques in substantiation, while the engineers

    often apply Adjusted as-built CPM and Net Impact

    techniques. Such observations may be taken to lead to

    interim hypotheses that need testing: for example, if the

    contractor uses Net Impact technique in substantiating

    the claim, there could be a greater likelihood of early

    settlement since many engineers may accept the conclu-

    sions reached via this technique.

    The respondents were also asked to identify theirpreferred techniques and these are summarised in

    Table 8. The Adjusted as-built CPM technique has

    evoked general preference in both substantiation (from

    the viewpoint of a claimant) and assessment (from the

    perspective of assessor) modes, while Net Impact tech-

    nique also attracted substantial (and almost equal)

    interest in both modes. However, it may be noted that

    each of these techniques: (1) have some shortcomings,

    for example in (a) analysing delay types, (b) dealing

    with concurrent delays or (c) incorporating real time

    CPM [6]; and (2) would lead to different outcomes upon

    quantification. Therefore there is a need for a uniformpolicy and consistent strategies, at least in identifying

    suitable techniques or a mix of techniques for specific

    scenarios.

    In the above context it is useful to track any relevant

    legalistic views on the relative suitability of different

    evaluation techniques, while the body of relevant legal

    precedents is emerging in parallel in different common

    law regimes. Wickwire and Ockman [13] provided some

    examples from the USA. For example, they cited cases

    such as (1) Haney vs. United States where the US Court

    of Claims accepted the comparison of as-planned with

    as-built critical path (CPM) programmes in 1982; (2)

    Utley James Inc. where the General Services Board of

    Contract Appeals provided specific views on various

    aspects of CPM programming, including on resource

    levelling and acceleration; and (3) Weaver Bailey Con-

    tractors Inc. vs. United States in which the Chief Judge

    of the US Court of Claims (in 1990) described float as

    an expiring resource available for use by all parties to

    the contract. Pickavance [8] cited other cases, for exam-

    ple (1)Titan Pacific Construction Corp. vs. United States

    in relation to As Planned vs. As Built Bar Chart meth-

    ods and (2) Cannon Construction Corporation in respect

    of the As Built But for technique. The foregoing indi-

    cate that all such approaches have achieved legal recog-

    nition and the relevant body of developing case law will

    shed further light on the more contractually acceptable

    approaches.

    It is further noted that the type of contract used (and

    any special conditions introduced) may also influence

    the chosen approach. For example, any particular pro-gramming and progress control requirements, such as

    on critical path based submissions may have a bearing

    on readily available project documentation, which may

    in turn facilitate certain evaluation techniques to a

    greater extent than others.

    6. Responsibilities for submissions and assessment of

    claims

    Having reviewed prevalent common perceptions in

    the Hong Kong civil engineering construction industry,

    Table 6

    Techniques used in substantiation of claims for extensions of time

    Technique for substantiation No. of responses

    Frequently Sometimes Rarely

    A Global Impact 15 3 7

    B Net Impact 11 11 2

    C But for 0 10 8

    D Time Impact 5 4 11

    E Snapshot 1 3 16

    F Adjusted as-built CPM 8 3 8

    Table 7

    Techniques used in assessment of claims for extension of time

    Technique for assessment No. of responses

    Frequently Sometimes Rarely

    A Global Impact 7 3 20

    B Net Impact 10 15 4

    C But for 7 10 12

    D Time Impact 8 10 12

    E Snapshot 2 8 18

    F Adjusted as-built CPM 13 10 7

    Table 8

    Preferred techniques in substantiating and assessing claims for exten-

    sion of time

    Technique Substantiation

    (No. of responses)

    Assessment

    (No. of responses)

    A Global Impact 6 1

    B Net Impact 9 8

    C But for 2 6

    D Time Impact 3 7

    E Snapshot 1 2

    F Adjusted as-built CPM 10 11

    32 M.M. Kumaraswamy, K. Yogeswaran / International Journal of Project Management 21 (2003) 2738

  • 5/25/2018 Substantiation and Assessment of Claims for Extensions of Time

    http:///reader/full/substantiation-and-assessment-of-claims-for-extensions-

    based on the earlier questionnaire survey and some

    related preliminary and follow-up interviews, it is

    necessary to relate these to the relevant responsibilities

    for submission and assessment of claims for extensions

    of time. Such contractual obligations are reviewed

    separately under submissions and assessment in the

    following sections, based primarily on the Hong KongGovernment General Conditions of Contract for Civil

    Engineering Works (HKGCC).

    6.1. Submissions

    Where delays are anticipated, the contractor is

    responsible for submitting a notice of claim, followed

    by the detailed particulars of the claims.

    6.1.1. Notice of claim

    The 1999 HKGCC Clause 50 first provides that:

    50 (1) (a) As soon as practicable but in any eventwithin 28 days after the cause of any delay to the

    progress of the Works or any Section thereof has

    arisen, the Contractor shall give notice in writing to

    the Engineer of the cause and probable extent of

    the delay.

    The contractor is also obliged to mitigate the effect of

    any excusable delays and recover the non-excusable

    delays. In practice, contractors may either notify earlier

    than necessary (e.g. the contractor may notify his

    intention to claim an extension as soon as he receives

    any variation order, regardless of whether the variationorder is minor or major), or wait until the delay is

    beyond a recoverable stage (i.e. without incurring addi-

    tional expenses). Some engineers estimate the 28 day

    period from the date of issue of instruction of variation

    and reject a claim for extension of time based on the

    argument that the notice had not been served within this

    28 day period. However, it may be more prudent to take

    a practical approach in considering the claim for exten-

    sion of time if the particulars provided by the contractor

    satisfy the requirements of the above sub-clause 50(1)

    rather than merely disagree on the time of serving the

    notice. Such flexibility is recommended even in other

    contractual regimes, for example in the UK and Sri

    Lanka [14], since giving notice within the designated

    time period is usually not considered to be a condition

    precedent to the claim itself, although it may have other

    contractual implications (e.g. signifying a breach).

    6.1.2. Detailed particulars

    HKGCC Clause 50(3) provides that:

    For the purposes of determining whether or to

    what extent the Contractor may be entitled to an

    extension of time under sub-clause (1)(b) the Engi-

    neer may require the Contractor to submit full and

    detailed particulars of the cause and extent of the

    delay to the progress of the Works. Where such full

    and detailed particulars are required by the Engi-

    neer, they shall be submitted in writing by the

    Contractor to the Engineer as soon as practicable

    in order that the Contractors claim may be inves-tigated at that time by the Engineer. If the Con-

    tractor fails to comply with the provisions of this

    sub-clause, the Engineer shall consider such exten-

    sion only to the extent that the Engineer is able on

    the information available.

    Sub-clause (1)(b) identifies the excusable events that

    entitle the contractor to an extension of time. One of the

    principal reasons for delays in assessment of claims that

    emerged from the aforementioned survey, was poorly

    presented details/lack of particulars/engineer waits for

    contractors information. It is essential to spell out in

    Particular or General Specifications, the type ofdetailed particulars that may be required by the engi-

    neer. Since the engineer is obliged to consider an exten-

    sion of construction period based on the information

    available to him, some contractors wait for the engineer

    to advise his award. Subsequently, the contractor builds

    up his counter claim based on the engineers award. In

    such cases, the engineer tends to be defensive and delays

    in providing his response since the contract does not

    require him to do so. However, it is in the long-term

    interests of both claimant and assessor that the informa-

    tion should be supplied as soon as possible by both par-

    ties in order to achieve a speedy and equitable solution.

    6.2. Assessments

    The HKGCC Clause 50(2) provides that:

    If in accordance with sub-clause (1) of this Clause

    the Engineer considers that the Contractor is fairly

    entitled to an extension of time for the completion

    of the Works or any Section thereof, the Engineer

    shall within a reasonable time determine, grant and

    notify in writing to the Contractor such extension.

    If the Engineer decides that the Contractor is not

    entitled to an extension, the Engineer shall notify

    the Contractor in writing accordingly. Provided

    that the Engineer in determining any such exten-

    sion shall take into account all the circumstances

    known to him at that time, including the effect of

    any omission of work or substantial decrease in the

    quantity of any item of work. Provided further that

    the Engineer shall, if the Contractor shall so

    request in writing, make a subsequent review of the

    circumstances causing delay and determine whether

    any further extension of time for completion

    should be granted.

    M.M. Kumaraswamy, K. Yogeswaran / International Journal of Project Management 21 (2003) 2738 33

  • 5/25/2018 Substantiation and Assessment of Claims for Extensions of Time

    http:///reader/full/substantiation-and-assessment-of-claims-for-extensions-

    The obligation of the engineer to grant an extension

    of time if he considers that the contractor is fairly enti-

    tled to an extension of time, is unequivocal. The term

    fairly appears to suggest that the contractor will not

    receive extensions of time for reasonably avoidable

    delay [15]. It is not practical for the engineer to assess a

    claim for extension of time without any informationsubmitted by the contractor. Generally, the engineer

    requests the contractor to submit detailed particulars of

    the claim while the contractor provides very basic

    details, for example, using a method such as the Global

    technique to substantiate his claim. The clause does not

    specify a time frame within which an award should be

    made. Nevertheless, both the contractor and the

    employer are desirous of knowing the exact extent of

    the revised construction period in the event of delays

    caused by excusable events (given that delays due to

    non-excusable events should be recovered by the con-

    tractor). Lack of a specified time frame does not

    encourage an expeditious settlement, and as seen fromthe responses (in Tables 2 and 4), submissions and

    assessments are frequently made towards the end of

    construction period. Both the contractor and the

    employer are thus denied knowledge of the revised con-

    struction period at intermediate stages in the project.

    6.2.1. Detailed particulars and documents needed for

    assessment

    While the earlier examples are principally from Hong

    Kong, they are indicative of many similar scenarios

    where international construction organisations interact.

    In general, Thomas [16] recommends that the con-tractor, in order to substantiate his claim, is well advised

    to provide details and diagrams indicating:

    1. what ought to have occurred if there had been no

    delaying event, or circumstance;

    2. what actually occurred as a result of the delaying

    event, or circumstance; and

    3. analysis of facts, calculations, explanations and

    arguments to show how the delaying event, or cir-

    cumstance, was responsible for the change in the

    method and/or programme.

    Detailed particulars should include programmes and

    other factual evidence to support the claim. Substantia-

    tion and assessment should use an agreed technique for

    analysing the claim. As seen from the responses to the

    survey in Hong Kong, Net Impact technique and Adjus-

    ted as-built CPM techniques are preferred in comparison

    with other techniques. Since more powerful computers

    and matching project management software have become

    affordable in the context of medium to large scale projects

    it is imperative that more scientific techniques are adop-

    tedfor consistency, reliability, better planning and

    reduced disputes. Network based assessments are more

    realistic and comprehensive in this respect.

    Maintenance of contemporary records from the

    inception of a project is essential for efficient and expe-

    dient substantiation and assessment of construction

    claims. Prudent management policies are also needed,

    for example, to engage sufficient personnel such as a

    programming engineer with relevant experience, and

    equipment such as adequate computer hardware andsoftware to capture and maintain contemporary

    records. Daily progress should be recorded with rele-

    vant links to the programmed activities and where

    necessary new activities/sub-activities may be recorded

    to reflect the delays/variations that were not evident in

    the approved works programme. Activity numbers

    should be used to conveniently record and collate the

    resources (labour and plant) allocated to each activity.

    Works supervisors/inspectors should agree the records

    with contractors foremen on a daily basis and enter the

    data on a spread-sheet format (e.g. Excel), which can be

    easily imported into project management software such

    as PRIMAVERA project planner when updating theprogress periodically (say on a monthly basis). In this

    context, it is recalled that the earlier described ques-

    tionnaire survey revealed that inadequate records and

    focus on progress of the works but not on pursuing a

    claim, due to lack of staff were among the principal

    generic causes, identified as leading to delays in sub-

    stantiation/assessment of claims. An appropriate bal-

    ance is therefore needed between allocating resources

    for monitoring/recording of the progress and in opti-

    mising resources for executing the physical works. Top

    management should formulate appropriate policies that

    will be implemented through clear and realistic guide-lines as indicated, for example, in the last column of

    Table 5.

    Clearly, the agreed scope of works associated with

    each activity at the submission/review stage of the

    works programme would assist the site supervisory

    staff to record the commencement and completion of

    activities without disagreement. It should be noted

    that these actual start/completion dates of activities

    would play an integral role in establishing delays and

    as-built critical path(s). Actual records should reflect

    the sequence of the programmed works in order to

    maintain consistency between as-planned and as-built

    records.

    The type of contract, including general and special

    conditions and particular specifications, may well influ-

    ence the nature of the available project documentation,

    apart from also governing any programming, progress

    control and delay mitigation measures. The size and/or

    complexity of the project may also influence the type

    and quality of documents maintained. These two fac-

    tors, i.e. the type of contract and the size and/or com-

    plexity of the project may therefore have a bearing on

    the final approach to EOT evaluation on a particular

    project.

    34 M.M. Kumaraswamy, K. Yogeswaran / International Journal of Project Management 21 (2003) 2738

  • 5/25/2018 Substantiation and Assessment of Claims for Extensions of Time

    http:///reader/full/substantiation-and-assessment-of-claims-for-extensions-

    6.2.2. Recommended technique(s) under the HKGCC

    The respondents to the Hong Kong based survey were

    invited to recommend suitable technique(s) for submis-

    sion and assessment of claims for extensions of time.

    Most of the respondents recommended the Net Impact

    technique as a simple method while also recommending

    the Adjusted as-built CPM technique. Respondentsrecognised that there is no explicit provision in the

    HKGCC as to which technique should be applied. This

    flexibility was probably necessary when initially framing

    the HKGCC, especially due to there being no guarantee

    of sufficient resources to substantiate/assess the claims.

    This need not be the case in the current environment

    where advanced computing facilities and relevant soft-

    ware are widely available. Suitable inputs from man-

    agement could be used in developing acceptable

    scientific approaches to reach consistent conclusions on

    reasonable claims with less disputes. An Adjusted as-

    built CPM technique may be specified in the contract or

    in guidelines/codes of practice to substantiate the claimsif a policy is adopted to settle the claims at the end of

    the construction period. However, this technique may

    not be suitable for those Employers and Contractors

    who wish to know the implications of adjusted contract

    periods while there is still time for compensatory

    actions. A Time Impact or Snapshot technique may be

    suitable in such cases. Although the former appears to

    be more familiar and preferred in Hong Kong according

    to the surveyed sample, the latter is better equipped to

    analyse concurrent delays [6]. It is essential to maintain

    records that are relevant for substantiating/assessing the

    claims in any of these approaches. For example, Tho-mas [16] stipulated the type of records that should be

    maintained on a general site for such purposes.

    6.2.3. Supplementary expert views from the Hong Kong

    industry

    After analysing the survey results, a series of in-depth

    interviews were recently arranged with seven experts

    who were reputed for their experience in assessing EOT

    in Hong Kong projects. These seven experts consisted of

    four who were presently working for consultants

    (including claims consultants representing contractors

    or clients), two working for large clients and one for a

    contractor. In each case the interviewees were those who

    particularly dealt with EOT claims on behalf of their

    organisations. Given their wide and high level general

    experience and professionalism, it was not surprising

    that no particular differences were observed between

    their views that may have arisen from their present

    work affiliations (i.e. to consultants or a contractor). A

    consolidated cross-section of their responses to two of

    the questions raised are summarised later to further

    illustrate the current approaches and perceived short-

    falls in present practices that need to be addressed with

    suggestions for improvements.

    6.2.3.1. on Evaluation Methods. It was generally

    recommended to use one of the CPMs (Critical Path

    Methods) in comparing the As Built CPM programme

    with the original CPM (As Planned) program, along

    with interim checks of programme vs. progress. It was

    also suggested to check the initial program, method

    statement and resource allocation plan for their suit-ability and viability. There was a suggestion to (1) use

    Window Analysis for logic driven jobs; while (2)

    checking the quantum of work planned vs. quantum of

    work done for resource driven jobs; and (3) using As

    Built Collapsed CPM for quick analysis. Methods of

    valuation were said to depend on the quality and

    amount of information available. In general, it was felt

    that delay causations could be best assessed by using

    regular Window Analysis updates on an ongoing basis.

    6.2.3.2. on Shortcomings in present practice that need to

    be addressed by the present study. It was recommended

    that somewhat theoretical/abstract (or of that matter,unquantified global) EOT claims (that ignore activity

    dependencies and critical paths) should be avoided.

    However, a simple method for EOT evaluation is needed

    and ongoing delay assessments should be encouraged. It

    was suggested that a check-list would help to monitor and

    record changes. It was also recommended to upgrade the

    relevant knowledge of all professionals involved in the

    preparation and assessment of claims.

    6.3. Overall time frames

    It is clear from the responses that in most cases in HongKong, extensions of time were awarded at the completion

    of the project rather than soon after occurrence of an

    event although the contract indicates that an award

    should be made within a reasonable period. For example,

    a claim for extension of time due to inclement weather

    or delay in possession of site can be promptly evaluated

    and awarded, while disruption to progress of works due

    to variations instructed by the engineer may be difficult

    to evaluate without detailed analysis of actual progress

    of the works. A typical cycle for assessment of a claim

    for an extension of time may be summarised as follows:

    Action taken (listed sequentially) Response

    period (weeks)

    Contractor serves Notice of claim 6

    Acknowledgement of notice by the

    Engineer

    1

    Submission of preliminary details 2

    Engineer requests further details 1

    Contractor submits further details

    after the effects of the event are known

    26

    Engineers initial assessment/award 36

    Total 1525

    M.M. Kumaraswamy, K. Yogeswaran / International Journal of Project Management 21 (2003) 2738 35

  • 5/25/2018 Substantiation and Assessment of Claims for Extensions of Time

    http:///reader/full/substantiation-and-assessment-of-claims-for-extensions-

    A brief comparison of advantages (and dis-advantages) of interim award and awarding extension

    at completion has been compiled by the authors on the

    basis of the literature surveyed, their experiences in

    industry and observations derived from the interviews

    and other interactions during the recent survey. These

    are summarised in Table 9.

    In applying the chosen techniques, basic principles

    such as; the contractors obligation to recover non-

    excusable delays and the contractors/employers right

    to use previously programmed float time should be

    taken into account and incorporated in an explicit pol-

    icy and then translated into guidelines/technical notes.The actual durations of activities as compared with the

    planned durations should also take into account:

    1. contractors efficiency/inefficiency;

    2. contractors additional efforts (or otherwise) to

    recover non-excusable delays;

    3. over-estimation of the production rate (for as-

    planned durations);

    4. different production rates for old and new plant;

    5. different output rates from different gangs of

    labour; and

    6. different output rates for similar activities due to

    weather/ climatic influences.

    A pragmatic approach would minimise the disputes

    arising from differing perceptions of the above con-

    siderations, i.e. by providing clear guidelines, flowing

    from the earlier recommended explicit policy.

    7. Conclusions and recommendations

    The survey results indicate that detailed claims for

    extensions of time are often submitted towards the end

    of the construction period. This is one of the con-

    tributory factors to the late assessment of claims. Itwould appear reasonable to adopt a policy decision to

    assess claims for extensions of time at the end of the

    original construction if the project durations are less

    than a specified short period, say, for example, 24

    months, and also if the claims do not appear to be

    large. This is achievable by clearly specifying the

    intentions of the parties to the contract. In cases of

    projects of more than the specified short durations (e.g.

    24 months) or for larger claims, it is prudent to follow

    an interim assessment approach, to achieve greater cer-

    tainty as to revised completion dates, and to encourage

    mitigation measures.The assessment of claims is the responsibility of the

    engineer, as assisted by the site staff. The Contract pro-

    vides that the engineer should assess and award exten-

    sions of timesome argue that (s)he should do so even

    if (s)he had not received detailed particulars from the

    contractor. However, it is prudent to place the onus for

    substantiation squarely on the claimant, while the

    responsibility for evaluating the details provided by the

    claimant should rest with the engineer. As seen from the

    responses to the question soliciting reasons for delays in

    the assessment of claims, the engineers rely on the clai-

    mants submissions. It is suggested that General Condi-

    tions of Contract should be amended to reflect the

    earlier pragmatic considerations with specified time

    frames for submissions of details and assessment. It is

    noted that the time frame specified for submitting noti-

    ces of claims is not sufficient by itself, to achieve the

    desired results. For example, it is desirable that the

    revised construction period for the project should be

    determined as soon as possible, by awarding extensions

    of time in a timely manner in response to reasonable

    claims.

    Agreed records of progress for all activities should be

    maintained which will help in the prompt assessment of

    Table 9

    Comparison of interim award and award at completion approaches

    Interim award Award at completion

    1 Construction period is clear to both the contractor and

    employer at any stage of the contract

    Actual period of construction is known and the award need not be greater

    2 Contractor may not be able to cover his own delays with

    extensions from interim award(s)

    An efficient contractor may be able to cover his delays with excusable delays

    3 If an event occurs when the contractor instituted steps to

    accelerate the works to recover non-excusable delays, it

    may be difficult to take account of the effect of an

    excusable event on the progress of works in an interim

    assessment

    Actual progress could involve both the effects of non-excusable and excusable

    events as well as the contractors effort to recover non-excusable delays.

    Equitable assessment can be reflected on the actual extent of the delay if it

    could be linked to excusable event

    4 Interim assessments of delays due to disruption of works

    due to excusable events require analysis of actual

    progress of the works

    At the completion of project full records may be available and it is easier to

    analyse the implication(s)

    5 It is easier to obtain relevant information before works

    are covered up, documents are misplaced, facts are

    forgotten and/or some key persons involved have

    moved on to other projects

    Further details may be difficult to elicit in relation to covered up works, and

    poorly documented events

    36 M.M. Kumaraswamy, K. Yogeswaran / International Journal of Project Management 21 (2003) 2738

  • 5/25/2018 Substantiation and Assessment of Claims for Extensions of Time

    http:///reader/full/substantiation-and-assessment-of-claims-for-extensions-

    claims. Essential hardware, software and management

    resources should also be provided in order that such

    records can be prepared and up-dated conveniently; and

    ideally feed directly into the formulation, substantiation

    and assessment of claims. The next phase in this ongo-

    ing research project is in progressin formulating the

    framework for an appropriate knowledge-based deci-sion support system for evaluating such claims for

    extensions of time in civil engineering projects in Hong

    Kong [17].

    In cases of medium size projects, management

    resources are limited and the records are usually inade-

    quate for applying sophisticated techniques such as the

    Isolated Delay Technique proposed by Alkass et al. [6].

    Simple techniques such as Net Impact are preferred by

    the respondents to the current survey. However, Net

    Impact is not an accurate technique and would not rea-

    listically apportion responsibility for critical delays. It

    may thus only be used, if at all, for an approximate first-

    order estimate of a possible extension of time. Further-more, large scale projects with sufficient management

    resources warrant more accurate methods and the

    Adjusted as-built CPM technique is preferred by the

    survey respondents.

    The Time Impact technique is preferable where early

    assessments are particularly useful; and the Snapshot

    technique is desirable where concurrent delays need to

    be carefully considered. A hybrid technique, such as the

    Isolated Delay technique may be even better, but it is

    concluded that a scenario-specific technique may be

    chosen from a tool-kit according to preset guidelines.

    The urgent need for such guidelines is underlined bythe evident confusion and shortfalls in the choice of

    EOT evaluation techniques and the disputes arising

    from the applications of different techniques. A degree

    of standardisation is useful in minimising temptations to

    choose the more advantageous and/or the more easily

    applied/understood technique. While no single techni-

    que can be universally applicable, it appears possible to

    identify a battery of best-practice techniques from

    which a scenario-specific one may be selected according

    to some guidelines.

    The literature review of international practice as sur-

    veyed by researchers in other countries, together with

    the present survey in Hong Kong have yielded what

    may be considered the foregoing interim conclusions

    and pointers on preferred approaches to assessments

    of extensions of time. However, given the complexities

    and variables unearthed, more detailed studies with lar-

    ger samples are warranted prior to definitive recom-

    mendations on specific techniques.

    Delays in submissions and assessment of claims may

    be minimised by addressing the causes underlying the

    reasons given by the respondents. An initial attempt has

    been made to recommend measures to address such

    causes (as in Table 5). It is useful to extract common/

    recurring generic causes and corresponding recommen-

    dations from such tabulations in order to formulate

    general strategies for better management of claims for

    extensions of time. Such strategies could be scenario-

    specific as in the case of particular measures related to

    Hong Kong, or more general in the case of a broader

    range of applications.Specific recommendations derived from such strate-

    gies and related realistic assessment methods could

    initially be conveyed through various guides/codes of

    practice; since incorporating detailed assessment meth-

    ods in conditions of contract would impose an onerous

    rigidity, as against the flexibility that may be needed to

    model particular scenarios. These guides could, for

    example be adapted and conveyed through the Techni-

    cal Circulars that are periodically issued by the Works

    Bureau of the Hong Kong Government and applied to

    most civil engineering projects in the territory; or be

    embodied in industry codes of practice or tool-kits, as

    may be developed, for example, by the ConstructionIndustry Institutes in USA or Australia or the European

    Construction Institute. In addition, each construction

    organisation could, and should, develop its own policies

    and organisation-specific strategies and procedures that

    will expedite the efficient and reliable substantiation and

    evaluation of extension of time entitlements on its own

    projects.

    Acknowledgements

    The reported study is supported by a CRCG researchgrant from The University of Hong Kong, which is

    gratefully acknowledged as is the assistance of Mr.

    Ragupathy Nadarajah in conducting and documenting

    the recent interviews. The authors are also thankful for

    the thoughtful and valuable responses from Hong Kong

    construction industry practitioners.

    References

    [1] Barrie DS, Paulson BS. Professional construction management.

    3rd ed. McGraw-Hill, 1992.

    [2] Alkass S, Mazerolle M, Tribaldos E, Harris F. Computer aidedconstruction delay analysis and claims preparation. Construction

    Management and Economics 1995;13:33552.

    [3] Conlin J, Retik A. The applicability of project management soft-

    ware and advanced IT techniques in construction delays mitiga-

    tion. International Journal of Project Management 1997;15(2):

    10720.

    [4] Kumaraswamy MM, Chan DWM. Factors facilitating faster con-

    struction. Journal of Construction Procurement 1999;5(2):8898.

    [5] Yogeswaran K, Kumaraswamy MM, Miller DRA. Claims for

    extensions of time in civil engineering projects. Construction

    Management and Economics 1998;16(3):28393.

    [6] Alkass S, Mazerolle M, Harris F. Construction delay analysis

    techniques. Construction Management and Economics 1996;14:

    37594.

    M.M. Kumaraswamy, K. Yogeswaran / International Journal of Project Management 21 (2003) 2738 37

  • 5/25/2018 Substantiation and Assessment of Claims for Extensions of Time

    http:///reader/full/substantiation-and-assessment-of-claims-for-extensions-

    [7] Bordoli DW, Baldwin AN. A methodology for assessing con-

    struction project delays. Construction Management and Eco-

    nomics 1998;16:32737.

    [8] Pickavance K. Delay and disruption in construction contracts.

    2nd ed. London: LLP Reference Publishing, 2000.

    [9] Adams S. Whats the delay? Asian Architect and Contractor,

    International Federation of Asian & Western Pacific Contractors

    2000;29(7):3941.

    [10] Mawdesley M, Askew W, OReilly M. Planning and controlling

    construction projects. Harlow, England: The Chartered Institute

    of Building and Addison Wesley Longman, 1997.

    [11] Finke MR. Window analyses of compensable delays. Journal

    of Construction Engineering and Management 1999;125(2):96

    100.

    [12] Scott S. Delay claims in UK contracts. Journal of Construction

    Engineering and Management 1997;123(3):23844.

    [13] Wickwire JM, Ockman S. Use of critical path method on contract

    claims2000. The Construction Lawyer, USA 1999;October:1221.

    [14] Kodikara GW. A rational approach to extension of time and

    liquidated damages provisions. Constructor 2000;5(2):712.

    [15] Corbett EC. FIDIC 4tha practical guide, a commentary on the

    international construction contract. London: Sweet and Maxwell,

    1991.

    [16] Thomas R. Construction contract claims. London: Macmillan

    Press, 1993.

    [17] Anumba CJ, Ugwu OO, Ren Z (Eds), Proceedings of the 8th

    International Workshop of the European Group for Structural

    Engineering Applications of Artificial Intelligence (in association

    with ASCE Technical Council on Computing and Information

    Technology), entitled Artificial Intelligence in Construction and

    Structural Engineering at Loughborough, UK. Centre for Inno-

    vative Construction Engineering, Loughborough, pp. 2230.

    38 M.M. Kumaraswamy, K. Yogeswaran / International Journal of Project Management 21 (2003) 2738