successful applications of project visualization
TRANSCRIPT
Title
Successful Applications of Project VisualizationFrom Concept to Implementation
1
Todays AgendaRole and Application of Project VisualizationChris Riale, Deputy Planning / Urban Design Manager WSP | Parsons Brinckerhoff
Case Studies:The Walk Bridge Program: Norwalk, CTJames A. Fallon, Facilities Manager Connecticut Department of Transportation
I-95 New Haven Harbor Crossing Corridor Improvement Program: New Haven, CTMark Rolfe, Construction Administrator Connecticut Department of Transportation
Chris RialeDeputy Planning / Urban Design ManagerWSP | Parsons BrinckerhoffRole and Application of Project Visualization
Don't tell me the moon is shining; show me the glint of light on broken glass.
- Anton Chekhov
#
4
Overview of Project VisualizationVarious applications for planning, design & construction:Concept developmentAlternatives development and refinementAid in design and constructionPublic engagement & supportMethods & output types vary:Hand sketch v. digital2D v. 3D v. AR (Augmented Reality)
#
5
3 Core PrinciplesVisualize design and inform decision-making Convey placemaking / city-building objectives.Generate and sustain community & stakeholder support.
#
6
Route 34 New Haven DowntownCrossing
#
7
Route 34 New Haven DowntownCrossing
#
8
Route 34 New Haven Downtown Crossing
#
9
Route 34 New Haven Downtown Crossing
#
10
Route 34 New Haven Downtown Crossing
#
11
Route 34 New Haven Downtown Crossing
#
12
Route 34 New Haven Downtown Crossing
#
13
Providence Zoning Ordinance
#
14
Providence Zoning Ordinance
#
15
Meadowlands Center Master Plan
#
16
Meadowlands Center Master Plan
#
17
Meadowlands Center Master Plan
#
18
Miami TOD Visioning
#
19
Miami TOD Visioning
#
20
Miami TOD Visioning
#
21
Hartford Rail Alternatives Analysis Overview of six rail alternatives
#
22
The Preferred Alternative
#
23
Step 1: Evaluate Existing Conditions
#
24
Step 2: Consider Highway design
#
25
Step 3: Develop Rail Alternative to work with Highway
#
26
Step 4: Modify Highway to Free Our Station Area
#
27
Step 5: Create Supporting Street Framework
#
28
Step 6: Compress Rail and Highway
#
29
Step 7: Reshape the Urban Fabric
#
30
Preferred Alternative From Study
#
31
Visualization is Critical to Successful Evolution of a ProjectA powerful tool to inform decision-making and problem solvingConveys physical implications of policy and design decisionsHighlights limitations and drawbacks, and allows planners to effectively calibrate policy and design
#
32
Visualizations During DesignWalk Bridge Program: Norwalk, CTJames A. FallonManager of Facilities and TransitConnecticut Department of Transportation
The Northeast Corridor
Metro-North Railroad's New Haven Line, the busiest commuter rail line in AmericaApprox. 200 Trains Daily Approx. 125,000 Passengers Daily
What is the Walk Bridge?
Preliminary Design (30%)Environmental PhaseConstruction on the Walk Bridge Late 20184-5 Year Duration
Construction on Danbury Dockyard Early 20173 Year Duration
Construction on CP243 Interlocking Early 20173 Year Duration
The Walk Bridge Program
Discuss CM/GC Process37
Program Objectives Maintain rail service throughout constructionMaintain navigation and access to the Norwalk RiverMinimize disruption to the surrounding communityComplete the project in a safe and efficient manner
Benefits of Visuals During DesignProvide a common view of design concepts to increase the level of understandingEvaluate Contractors means and methods and constructability Coordination of materials and equipment
Collaboration Owner, Designer, Contractor and Program Manager Risk ReductionValidate design schedule and identify physical constraints
Bridge Replacement Options
Preferred Alternative
Design DevelopmentDetail Design (Public Outreach)
Construction Staging and Refinement (CM/GC)Main Span ConfigurationPiers/Abutments/Walls configurationFinishes and colorsHigh TowersHistoric and Public Input
Main Span ConfigurationTrack Alignment West Approach RebuildHigh TowersConstruction Staging
CHECK CAPITALIZATION OF BULLETS44
Concepts for Bridge Approach Spans
Replicate existing truss configuration on face of exterior girders with non-structural attachments45
West Approach
New bridge girders
Concepts for New Bridge Piers
47
Concepts for New Control House
48
Span Color
Color and finishing based on public feedback 49
Channel Alignment
Potential Construction SequencingStep-by-step implementation of new bridgeBuilding new bridge 2 tracks at a timeImplementation of accelerated bridge techniques
51
High Towers and South Foundations
1234
52
South Two-Track Installation567
8
53
Northern Two-Track Installation
91011
54
Location of Equipment
Visualizations for OutreachDuring Public and Stakeholder MeetingsSpecial EventsWebsite/Social Media Program NoticesDetour/Alternate Routes
Visualizations During ConstructionI-95 New Haven Harbor Crossing Corridor Improvement Program: New Haven, CT
Mark RolfeConstruction AdministratorConnecticut Department of Transportation
57
BostonNew York
58
59
Visualizations During ConstructionDesign, build and simulate projects virtually before executing them in reality.Innovative / expedited project deliveryEnhanced collaboration / cooperation Communication with stakeholders Provides a common viewIncreases safetyIncreases efficiencyReduces risk and costsCTDOT standard practice
60
Visualizations During Construction
OwnerProject Development / PlanningStakeholder Coordination Public Info / OutreachDesign / Construction Reviews Contractor Project Understanding Bidding Staging / SequencingMeans and Methods Designer
OwnerContractor Designer Prepare ModelClash DetectionConstructability ReviewsWorking Drawing Reviews
Digital Model
61
Visualizations During Construction
This video is 48 seconds62
Visualizations During Construction
Out-of-sequence steel erection
New pier construction prior to bridge demolitionPile driving concurrent with steel erection
Identify Scheduling Conflicts
Benefits: Schedule clash detection - steel erection occurring near highway within close proximity to where pile driving work is simultaneously occurring. Reviewed steel erection/vibration specifications for distance and updated schedule logic (shifted resources) so that work would not occur simultaneously.Missing logic - Construction of PS-8 before existing bridge steel demolition. There is enough space to construct all three footings for PS-8. There will likely be enough space to construct Column 3, but it will be difficult to complete construction of columns 1 & 2, and the cap beam cannot be built until that section of the existing bridge (which is span 10) has been completely removed.Simultaneous segment steel erection at abutment, which was on the critical path, identified and schedule was updated.
63
Visualizations During Construction
Temporary shoring towers placed on the trestle prior to construction.
Temporary shoring towers installed prior to demolition of existing bridge.
Contractor Means and Methods
Shoring towers constructed prior to trestle construction.Temporary shoring towers erected prior to existing bridge abutment demolition. This enhanced communication with contractor to revise demolition sequence.64
Cranes moved to positions C1/C2
Workers on boom lifts, girder delivered in median
Girder lifted from delivery vehicle
Crane rigging detachedRight lanes opened to traffic
From the Digital Model, the operators were able to figure out that with the elevation differences, they will not be able to see each other and spotters were needed. The model also helped to figure out what lane the contractor would take on the night of- they were originally going to take the right lane but because of the curve of the girder they needed to take the left lane (median)65
Visualizations for Safety Planning
Typical PlanLaser ScanHot Work Limits
Top Left Revised contractor drawing submittal of existing Bridge No. 03036 demolition sequence.Top Right Laser scan point cloud helped create accurate 3D geometry.Bottom Right Diagram of steel cut method used in field during bridge demolition, the contractor hinged the girder away from building during pick.Bottom Left 4D simulation of contractor demolition sequence showing hot work limit (35) at girder cut near building66
Visualizing Change
Megan is looking for a model photo to demonstrate going from drawing, to model, to actual photo. However, if there isnt a good one we should take this slide out bc it doesnt fit the theme of the presentation.67
Visualizing Change
Model201320152016
68
201720222032Visualizing Change
201720222032Proposed Landscaping at Franklin Street
These renderings show the Wooster Square area along Franklin Street and are used by the Program to show residents how plantings will look 5 and 15 years from planting. 69
Traffic shift alerts, detours, and access routesVisuals in advance of construction completionIllustrates alternatives and design solutionsInforms about roadway conditions
Public and Stakeholder Outreach
70
Public and Stakeholder Outreach
BEFOREAFTER
71
Customized graphics to zoom in on specific locations in detail72
Public and Stakeholder Outreach
TS 20P Ramp S- Video 1:2473
Public and Stakeholder Outreach
(actual field condition) March 2014August 2014October 2014
74
Public and Stakeholder Outreach Weekly Construction News Construction Updates for Traffic Shifts Detour / Alternate Routes Before and After Visualizations Traffic Shift Videos Website Interactive Map Media Content
75
Public and Stakeholder OutreachRepresentation at Community MeetingsParticipation in Community EventsMedia Open HousesPresentations and ToursGrand Opening Celebrations
Discuss visual support during community outreach activities:Use graphics to demonstrate traffic shifts at community meetings and eventsShare video clips with the media to assist in spreading the word on upcoming alignment changesThe digital model is used to demonstrate changes in alignment over time during presentations/open housesThe model is also used to create maps for our events, such as the grand opening celebration76
Thank you!Questions?
77