Page 1: Successful construction with PERI

Successful construction with PERI

Page 2: Successful construction with PERI

Building Rehabilitation, LisbonAdvanced Seminar 26-10-2009

Alexandre Jacinto

PERI Portugal, Queijas

Page 3: Successful construction with PERI

Building Rehabilitation, Lisbon

CITY MAP

3

Page 4: Successful construction with PERI

4

Building Rehabilitation, Lisbon

JOBSITE Location: Av. da Republica ( Main Street ) Height: 59 m High pedestrian flow

Page 5: Successful construction with PERI

5

Building Rehabilitation, Lisbon

SOLUTION PLAN Top View

Page 6: Successful construction with PERI

6

Building Rehabilitation, Lisbon

SOLUTION PLAN Av. da Republica

Page 7: Successful construction with PERI

7

Building Rehabilitation, Lisbon

GENERAL DATA Scaffold Maximum Height = 59 m

Scaffold Total Area = 3342 m²

Scaffold Total Weight = 63091 Kg Scaffold = 18.878 Kg/m²

Assembly Team = 12 PERI workers

Assembly Time = 3 weeks (15 work days) Scaffold moved ≈ 350.50 Kg/day/worker

Scaffold assembled ≈ 18.56 m²/day/worker

Page 8: Successful construction with PERI

Building Rehabilitation, Lisbon

JOBSITE PICTURES

8

Page 9: Successful construction with PERI

Building Rehabilitation, Lisbon

FINAL RESULT

9

Page 10: Successful construction with PERI

Building Rehabilitation, Lisbon

THANK YOU FOR YOUR ATTENTION.

10

Page 11: Successful construction with PERI

Formwork Scaffolding Engineering | www.peri.pt