SUCCESSFUL INSTALLATION AND COMMISSIONING OF THE MOST POWERFUL HYPER COMPRESSOR WORLDWIDE LDPE Webinar, April 2021 Alexandru Roman – Burckhardt Compression Kevin Liao - Formosa Plastic Corporation

Upload: others

Post on 15-Jan-2022

2 views

Category:

Documents


0 download

TRANSCRIPT

SUCCESSFUL INSTALLATION AND COMMISSIONING OF THE MOST POWERFUL HYPER COMPRESSOR WORLDWIDELDPE Webinar, April 2021Alexandru Roman – Burckhardt CompressionKevin Liao - Formosa Plastic Corporation

FilenameDate

Page 2

Outline Project introduction Compressor Package Overview, technical data Formosa Plastic Corporation USA - introduction Construction and installation key milestones Installation highlights, key points K8+8 Hyper compressor pre-commissioning and commissioning

highlights First operation experience with K8+8 Hyper Compressor BC support for Maintenance & Reliability Readiness

FilenameDate

Page 3

FPC, TX, USA LDPE Plant ExxonMobil Tubular License

Projected Production: 400 kTA

PP: BCAG 8B6C, Hyper: K8+K8

Hyper Compressor Rate: 160 T/hr.

5 Reactor Ethylene Feed

6 Injection points

FilenameDate

Page 4

PP Compressor Overview – 8B6C-2.108_1

FilenameDate

Page 5

K8+8 Overview

FilenameDate

Page 6

K8+8 – Technical Data Motor power: 34.5 MW 1st Stage discharge pressure – 1530bar 2nd Stage discharge pressure – 3100bar

Motor-Compressor coupling spec:- Rigid coupling - 2nd Stage- Torsionally rigid coupling - 1st Stage

FilenameDate

Page 7

Formosa Plastics Corporation, U.S.A. Founded in 1978 Headquarter: Livingston, New Jersey. Manufacturing complex:

Baton rouge, LouisianaPoint Comfort, Texas

Annual revenue: ~USD$ 5 billions US Employee: 2,900

Point Comfort, Texas: now including LDPE

FilenameDate

Page 8

FPC Taiwan Mailiao Plant

FilenameDate

Page 9

Formosa and BCAG Hyper

(1) K6

(1) K8, (1) K6(2) K8, (1) 8B6C

Mailiao EVA plant: (1) K8 on 160kTA tubular line, (1) K6 on 72kTA autoclave line Ningbo EVA plant: (1) K6 on 72kTA autoclave line Point Comfort LDPE: (2) K8 (K8+K8) on 400kTA tubular

FilenameDate

Page 10

Purge/Primary TimelineHyper Timeline

PP/Hyper Construction Milestones

2020/11 C2 runs to 44,000psig, making polymer

2016/7 Site construction break-ground

2017/4

2018/8

2018/10

2018/11

2020/1

2020/9

Hyper frames arrived for humidity controlled storage.

Motor assembly begins, 2nd stage frame and foundation bolts installed.

Motor rotor and 1st stage frame rough set. Roof over. Leveling and grouting in progress.

Hyper oil mist system operational. Oil piping flushing scope proposed. On-site installations continues

Hyper 5-minute mechanical run (5 minutes)

Hyper nitrogen run, commissioning

2018/7

2019/72019/10

2020/6

Motors assembly begins

Motor and frame rough set. On-site installation begins

PP pre-commissioning begins

PP Nitrogen run; HP blowing

Compressor overhaul

FilenameDate

Page 11

Hyper Compressor Installation Highlights Foundation base plate alignment Oil mist system 1st stg frame - motor – 2nd stg frame alignments

FilenameDate

Page 12

Hyper Foundation Highlight Upper base plate alignment precision: 0.05mm across 1m

FilenameDate

Page 13

Oil Mist System (On-site preservation) Corrosion prevention by low pressure, atomized (2 micron) oil droplets inside of compressor frame

and cylinders , creates lubricant film on internal surfaces

While installation and alignments in progress

(48) mist points on PP/Hyper

FilenameDate

Page 14

Hyper compressor alignment highlights Centerline misalignment: ±5.8mm / ±2.0mm

Flange face parallel: ± 0.9mm

FilenameDate

Page 15

Picture gallery

FilenameDate

Page 16

K8+8 Hyper compressor pre-commissioning and commissioning highlights Mechanical Test Run Nitrogen test run Ethylene test run - Operation experience with K8+8 Hyper Compressor Prognost data

FilenameDate

Page 17

Nitrogen Test Run – operating range

FilenameDate

Page 18

First start up with Ethylene - a correct approach

4.5 hours – Ramp up3h@ 3000barMTR

FilenameDate

Page 19

Prognost System data – operation experienceTroubleshoot

FilenameDate

Page 20

Prognost System data – 1st Stage Plungers Run-out

FilenameDate

Page 21

Prognost System data – 2nd Stage Plungers Run-out

FilenameDate

Page 22

All intermediate CRS Vibrations

FilenameDate

Page 23

BC support for Maintenance & OperationReliability Readiness On site operation and maintenance training:▪ cylinder lubrication adjustment before and during operation:

➢ cylinder lubrication corrective measures based on plungers behavior

➢ cylinder lubrication delivery rate

▪ maintenance training - general practice and documentation

▪ specific maintenance procedures for PP and Hyper compressor

▪ workshop (clean room) maintenance procedures for compressor parts, special storage condition

Spare part management training Prognost system training

FilenameDate

Page 24

BC support for Maintenance & OperationReliability Readiness