Successful Project Management

Justice, E-Government, & the Internet

June 28, 2000 – Dallas, Texas

Lawrence P. Webster

Page 2: Successful Project Management Justice, E-Government, & the Internet June 28, 2000 – Dallas, Texas Lawrence P. Webster

Project:A temporary endeavor undertaken to create a unique product or service.

Page 3: Successful Project Management Justice, E-Government, & the Internet June 28, 2000 – Dallas, Texas Lawrence P. Webster

Project Management:

The application of knowledge, skills, tools, and techniques to project objectives to meet stakeholder needs and expectations.

Page 4: Successful Project Management Justice, E-Government, & the Internet June 28, 2000 – Dallas, Texas Lawrence P. Webster

Knowledge Areas: Scope Management Time Management Cost Management Quality Management Human Resources Management Communications Management Risk Management Procurement Management Integration Management

Page 5: Successful Project Management Justice, E-Government, & the Internet June 28, 2000 – Dallas, Texas Lawrence P. Webster

Disclaimers:Substantive DifferencesSize DifferencesComponents are IntegratedOver-simplified Examples

Page 6: Successful Project Management Justice, E-Government, & the Internet June 28, 2000 – Dallas, Texas Lawrence P. Webster

Project Management Context:Project Phases and Life CycleStakeholdersLeadership SkillsGeneral Management SkillsCommunications Skills

Page 7: Successful Project Management Justice, E-Government, & the Internet June 28, 2000 – Dallas, Texas Lawrence P. Webster

Project Phases and Life Cycle:Divide Project into PhasesBetter Management ControlReview Deliverables and PerformanceFast-tracking

Page 8: Successful Project Management Justice, E-Government, & the Internet June 28, 2000 – Dallas, Texas Lawrence P. Webster

Example of Project Phases:Conceptual DesignDetailed DesignCoding and TestingTraining and DocumentationDeployment

Page 9: Successful Project Management Justice, E-Government, & the Internet June 28, 2000 – Dallas, Texas Lawrence P. Webster

Stakeholders: Individuals and OrganizationsActively Involved in Project Interests Affected by Project

Page 10: Successful Project Management Justice, E-Government, & the Internet June 28, 2000 – Dallas, Texas Lawrence P. Webster

Leadership Skills:Vision and StrategyEstablishing DirectionAligning PeopleCommunicatingNegotiatingMotivating and Inspiring Influencing OrganizationsOvercoming Barriers to Change

Page 11: Successful Project Management Justice, E-Government, & the Internet June 28, 2000 – Dallas, Texas Lawrence P. Webster

General Management Skills:PlanningFinance and AccountingPersonnel AdministrationTechnologyOrganizational DevelopmentDelegationTeam BuildingConflict ManagementSolving Problems

Page 12: Successful Project Management Justice, E-Government, & the Internet June 28, 2000 – Dallas, Texas Lawrence P. Webster

Communications Skills:WritingListeningSpeakingPresentingMedia RelationsMeeting Management

Page 13: Successful Project Management Justice, E-Government, & the Internet June 28, 2000 – Dallas, Texas Lawrence P. Webster

Scope Management: InitiationScope PlanningScope DefinitionScope VerificationScope Change Control

Page 14: Successful Project Management Justice, E-Government, & the Internet June 28, 2000 – Dallas, Texas Lawrence P. Webster

Key Inputs, Tools & Techniques, and Outputs:Product DescriptionProject CharterScope StatementWork Breakdown Structure (Microsoft

Project)Formal AcceptanceScope Management Plan

Page 15: Successful Project Management Justice, E-Government, & the Internet June 28, 2000 – Dallas, Texas Lawrence P. Webster

Time Management:Activity Definition (Microsoft Project)Activity Sequencing (Microsoft Project)Activity Duration EstimatingSchedule DevelopmentSchedule Control

Page 16: Successful Project Management Justice, E-Government, & the Internet June 28, 2000 – Dallas, Texas Lawrence P. Webster

Key Inputs, Tools & Techniques, and Outputs:Activity ListNetwork DiagramProject ScheduleSchedule Management Plan

Page 17: Successful Project Management Justice, E-Government, & the Internet June 28, 2000 – Dallas, Texas Lawrence P. Webster

Cost Management:Resource PlanningCost EstimatingCost BudgetingCost Control

Page 18: Successful Project Management Justice, E-Government, & the Internet June 28, 2000 – Dallas, Texas Lawrence P. Webster

Key Inputs, Tools & Techniques, and Outputs:Resource RequirementsCost EstimateCost Baseline or Spending Plan

(Microsoft Excel Documents)Cost Management Plan

Page 19: Successful Project Management Justice, E-Government, & the Internet June 28, 2000 – Dallas, Texas Lawrence P. Webster

Quality Management:Quality PlanningQuality AssuranceQuality Control

Page 20: Successful Project Management Justice, E-Government, & the Internet June 28, 2000 – Dallas, Texas Lawrence P. Webster

Key Inputs, Tools & Techniques, and Outputs:Quality Management Plan

Page 21: Successful Project Management Justice, E-Government, & the Internet June 28, 2000 – Dallas, Texas Lawrence P. Webster

Human Resource ManagementOrganizational PlanningStaff AcquisitionTeam Development

Page 22: Successful Project Management Justice, E-Government, & the Internet June 28, 2000 – Dallas, Texas Lawrence P. Webster

Key Inputs, Tools & Techniques, and Outputs:Role Assignment Matrix (Microsoft

Word)Staffing Management PlanOrganizational ChartProject Team Directory

Page 23: Successful Project Management Justice, E-Government, & the Internet June 28, 2000 – Dallas, Texas Lawrence P. Webster

Communications Management:Communications Planning Information DistributionPerformance ReportingAdministrative Closure

Page 24: Successful Project Management Justice, E-Government, & the Internet June 28, 2000 – Dallas, Texas Lawrence P. Webster

Key Inputs, Tools & Techniques, and Outputs:Communications Management PlanProject RecordsPerformance ReportsChange RequestsProject ArchivesFormal AcceptanceLessons Learned

Page 25: Successful Project Management Justice, E-Government, & the Internet June 28, 2000 – Dallas, Texas Lawrence P. Webster

Risk Management:Risk IdentificationRisk QuantificationRisk Response DevelopmentRisk Response Control

Page 26: Successful Project Management Justice, E-Government, & the Internet June 28, 2000 – Dallas, Texas Lawrence P. Webster

Key Inputs, Tools & Techniques, and Outputs:Risk Management PlanChecklistsContingency PlansReservesContractual Terms

Page 27: Successful Project Management Justice, E-Government, & the Internet June 28, 2000 – Dallas, Texas Lawrence P. Webster

Procurement Management:Procurement PlanningSolicitation PlanningSolicitationSource SelectionContract AdministrationContract Close-out

Page 28: Successful Project Management Justice, E-Government, & the Internet June 28, 2000 – Dallas, Texas Lawrence P. Webster

Key Inputs, Tools & Techniques, and Outputs:Procurement Management PlanProcurement DocumentsProposalsContractContract FileFormal Acceptance and Closure

Page 29: Successful Project Management Justice, E-Government, & the Internet June 28, 2000 – Dallas, Texas Lawrence P. Webster

Integration Management:Project Plan DevelopmentProject Plan ExecutionOverall Change Control

Page 30: Successful Project Management Justice, E-Government, & the Internet June 28, 2000 – Dallas, Texas Lawrence P. Webster

Key Inputs, Tools & Techniques, and Outputs:Project PlanLessons Learned

Page 31: Successful Project Management Justice, E-Government, & the Internet June 28, 2000 – Dallas, Texas Lawrence P. Webster

Management Processes: Initiating ProcessesPlanning ProcessesExecuting ProcessesControlling ProcessesClosing Processes

Page 32: Successful Project Management Justice, E-Government, & the Internet June 28, 2000 – Dallas, Texas Lawrence P. Webster

ScopePlanning

ScopeDefinition

ActivityDefinition

ResourcePlanning

ActivitySequencing

DurationEstimating

CostEstimating

ScheduleDevelopment

CostBudgeting

PlanDevelopment

Page 33: Successful Project Management Justice, E-Government, & the Internet June 28, 2000 – Dallas, Texas Lawrence P. Webster

QualityPlanning

CommunicationsPlanning

RiskIdentification

RiskQuantification

ResponseDevelopment

OrganizationalPlanning

StaffAcquisition

ProcurementPlanning

SolicitationPlanning

Page 34: Successful Project Management Justice, E-Government, & the Internet June 28, 2000 – Dallas, Texas Lawrence P. Webster

For More Information: Search Group, Incorporated

www.search.org National Center for State Courts

www.ncsc.dni.us Project Management Institute

www.pmi.org International Standards Organization

www.iso.org Software Engineering Institute

www.sei.cmu.edu Center for Technology in Government

www.ctg.albany.edu

Page 35: Successful Project Management Justice, E-Government, & the Internet June 28, 2000 – Dallas, Texas Lawrence P. Webster

Successful Project Management

Or How to Ruin the Lives of Others

for Fun and Profit!