sunset fish passage & energy project · 2014. 4. 4. · 4/10/2014 7:04:41 pm %pdf-1.7 %¡³Å×...

19
SUNSET FISH PASSAGE & ENERGY PROJECT 7 Page 21/162

Upload: others

Post on 21-Feb-2021

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: SUNSET FISH PASSAGE & ENERGY PROJECT · 2014. 4. 4. · 4/10/2014 7:04:41 pm %PDF-1.7 %¡³Å× 15 0 obj  endobj 14 0 obj  endobj 13 0 obj  endobj 12 0 obj

SUNSET FISH PASSAGE &

ENERGY PROJECT

7

Page 21/162

Page 2: SUNSET FISH PASSAGE & ENERGY PROJECT · 2014. 4. 4. · 4/10/2014 7:04:41 pm %PDF-1.7 %¡³Å× 15 0 obj  endobj 14 0 obj  endobj 13 0 obj  endobj 12 0 obj

SFPEP

•Activities to date:

•Design Refinements

•Study Updates

•Next Steps

Action Date

Submitted Revised Study Plan December 31, 2013

FERC issued Study Plan Determination January 30, 2014

Update to Board February 4, 2014

Study Period Commences February 2014

8

Page 22/162

Page 3: SUNSET FISH PASSAGE & ENERGY PROJECT · 2014. 4. 4. · 4/10/2014 7:04:41 pm %PDF-1.7 %¡³Å× 15 0 obj  endobj 14 0 obj  endobj 13 0 obj  endobj 12 0 obj

SFPEP: Design Refinements

•District design process continually evaluating alternatives to reduce cost and impacts as new data collected

•Planned design revisions to following areas:

• Intake / Headrace

• Fish Screens

• Power Tunnel

• Powerhouse

• Bridge

• Turbine Selection

9

Page 23/162

Page 4: SUNSET FISH PASSAGE & ENERGY PROJECT · 2014. 4. 4. · 4/10/2014 7:04:41 pm %PDF-1.7 %¡³Å× 15 0 obj  endobj 14 0 obj  endobj 13 0 obj  endobj 12 0 obj

SFPEP: Intake / Headrace - PAD

•PAD design

included 7-ft

weir structure

spanning

channel

10

Page 24/162

Page 5: SUNSET FISH PASSAGE & ENERGY PROJECT · 2014. 4. 4. · 4/10/2014 7:04:41 pm %PDF-1.7 %¡³Å× 15 0 obj  endobj 14 0 obj  endobj 13 0 obj  endobj 12 0 obj

SFPEP: Intake / Headrace

1938 Pool and

Control Point

2006 Pool and

Control Point

11

Page 25/162

Page 6: SUNSET FISH PASSAGE & ENERGY PROJECT · 2014. 4. 4. · 4/10/2014 7:04:41 pm %PDF-1.7 %¡³Å× 15 0 obj  endobj 14 0 obj  endobj 13 0 obj  endobj 12 0 obj

SFPEP: Intake / Headrace - refined

• Per bathymetry, review of historic aerial imagery and refinement of rating curve, no weir is required

• Flow regulation via powerhouse control

• Natural stable control point downstream maintains deep pool, self-cleaning at high flows

• Saves approx $10M construction cost

• Reduces in-water work and timeline

12

Page 26/162

Page 7: SUNSET FISH PASSAGE & ENERGY PROJECT · 2014. 4. 4. · 4/10/2014 7:04:41 pm %PDF-1.7 %¡³Å× 15 0 obj  endobj 14 0 obj  endobj 13 0 obj  endobj 12 0 obj

SFPEP: Intake / Headrace - refined

13

Page 27/162

Page 8: SUNSET FISH PASSAGE & ENERGY PROJECT · 2014. 4. 4. · 4/10/2014 7:04:41 pm %PDF-1.7 %¡³Å× 15 0 obj  endobj 14 0 obj  endobj 13 0 obj  endobj 12 0 obj

SFPEP: Fish Screens - PAD

•PAD design included large cavern

housing vertical fish screens

•Approx 50% of project excavation identified related to cavern & weir

14

Page 28/162

Page 9: SUNSET FISH PASSAGE & ENERGY PROJECT · 2014. 4. 4. · 4/10/2014 7:04:41 pm %PDF-1.7 %¡³Å× 15 0 obj  endobj 14 0 obj  endobj 13 0 obj  endobj 12 0 obj

SFPEP: Fish Screens - refined

• Move to opposite side of hillside

• Reduces 50% of excavation, simpler constructability

• Fish bypass returns juveniles directly to bypass reach

• Long-term improved access and O&M

• Reduces overall project cost

15

Page 29/162

Page 10: SUNSET FISH PASSAGE & ENERGY PROJECT · 2014. 4. 4. · 4/10/2014 7:04:41 pm %PDF-1.7 %¡³Å× 15 0 obj  endobj 14 0 obj  endobj 13 0 obj  endobj 12 0 obj

SFPEP: Power Tunnel - PAD

16

Page 30/162

Page 11: SUNSET FISH PASSAGE & ENERGY PROJECT · 2014. 4. 4. · 4/10/2014 7:04:41 pm %PDF-1.7 %¡³Å× 15 0 obj  endobj 14 0 obj  endobj 13 0 obj  endobj 12 0 obj

SFPEP: Power Tunnel - refined

• Allows flexibility to construction sequencing, should reduce duration and disperse traffic due to multiple entrance sites

17

Page 31/162

Page 12: SUNSET FISH PASSAGE & ENERGY PROJECT · 2014. 4. 4. · 4/10/2014 7:04:41 pm %PDF-1.7 %¡³Å× 15 0 obj  endobj 14 0 obj  endobj 13 0 obj  endobj 12 0 obj

SFPEP: Powerhouse - PAD

18

Page 32/162

Page 13: SUNSET FISH PASSAGE & ENERGY PROJECT · 2014. 4. 4. · 4/10/2014 7:04:41 pm %PDF-1.7 %¡³Å× 15 0 obj  endobj 14 0 obj  endobj 13 0 obj  endobj 12 0 obj

SFPEP: Powerhouse - refined

• Moving closer to river reduces overall cost, powerhouse height, tailrace length, and removes need to excavate entire rock knob

• Relocation of switchyard reduces rock excavation

19

Page 33/162

Page 14: SUNSET FISH PASSAGE & ENERGY PROJECT · 2014. 4. 4. · 4/10/2014 7:04:41 pm %PDF-1.7 %¡³Å× 15 0 obj  endobj 14 0 obj  endobj 13 0 obj  endobj 12 0 obj

Turbine Selection

• Kaplan or Francis fits head/flow

• Kaplan improves overall energy production, improved overall economics

• Still evaluating unit size and single vs. double

20

Page 34/162

Page 15: SUNSET FISH PASSAGE & ENERGY PROJECT · 2014. 4. 4. · 4/10/2014 7:04:41 pm %PDF-1.7 %¡³Å× 15 0 obj  endobj 14 0 obj  endobj 13 0 obj  endobj 12 0 obj

SFPEP: Study Revisions - HDR

• SP 1, Water Quality: Revisions to study plan including

increased monitoring (additional locations, additional

parameters), $42,057

• SP 17, Mollusks: New study requirement, $36,975

• SP 18, Benthic Macroinvertebrates: Revisions to study

plan, $2,047

• Additional contract cost: $81,079

• New total contract cost: $311,242

21

Page 35/162

Page 16: SUNSET FISH PASSAGE & ENERGY PROJECT · 2014. 4. 4. · 4/10/2014 7:04:41 pm %PDF-1.7 %¡³Å× 15 0 obj  endobj 14 0 obj  endobj 13 0 obj  endobj 12 0 obj

SFPEP: Study Revisions - Anchor • SP 12, Downstream Fish Passage at Falls (Injury

Assessment): Revisions to study plan including more

tests with larger fish

• Additional contract cost: $85,170

• New total contract cost: $302,646

22

Page 36/162

Page 17: SUNSET FISH PASSAGE & ENERGY PROJECT · 2014. 4. 4. · 4/10/2014 7:04:41 pm %PDF-1.7 %¡³Å× 15 0 obj  endobj 14 0 obj  endobj 13 0 obj  endobj 12 0 obj

SFPEP: Study Revisions - ERM

• SP 9, Aesthetic Resource Study: Additions to study plan

as required by the FERC Study Plan Determination, to

include low, medium and high flows for 6 Visual Key

Observation Points (VKOPs), include landscape views

(mountains) at 4 KOPs, and include photomontages for

temporary construction impacts. New Project design

requires new photomontages of intake, powerhouse, and

fish screens.

• Additional contract cost: $77,458

• New total contract cost: $276,058

23

Page 37/162

Page 18: SUNSET FISH PASSAGE & ENERGY PROJECT · 2014. 4. 4. · 4/10/2014 7:04:41 pm %PDF-1.7 %¡³Å× 15 0 obj  endobj 14 0 obj  endobj 13 0 obj  endobj 12 0 obj

SFPEP: Next Steps

• Amend 3 Contracts: additional $243,707

• Complete all field work for 16 required Study Plans and

geotechnical work, and deliver draft reports by year end

• Discuss design revisions with stakeholders – further

refinement may occur

• Announce revisions in project design to FERC service list

• Update to media

• Continue with design development

24

Page 38/162

Page 19: SUNSET FISH PASSAGE & ENERGY PROJECT · 2014. 4. 4. · 4/10/2014 7:04:41 pm %PDF-1.7 %¡³Å× 15 0 obj  endobj 14 0 obj  endobj 13 0 obj  endobj 12 0 obj

QUESTIONS

25

Page 39/162