SUNSET FISH PASSAGE &
ENERGY PROJECT
7
Page 21/162
SFPEP
•Activities to date:
•Design Refinements
•Study Updates
•Next Steps
Action Date
Submitted Revised Study Plan December 31, 2013
FERC issued Study Plan Determination January 30, 2014
Update to Board February 4, 2014
Study Period Commences February 2014
8
Page 22/162
SFPEP: Design Refinements
•District design process continually evaluating alternatives to reduce cost and impacts as new data collected
•Planned design revisions to following areas:
• Intake / Headrace
• Fish Screens
• Power Tunnel
• Powerhouse
• Bridge
• Turbine Selection
9
Page 23/162
SFPEP: Intake / Headrace - PAD
•PAD design
included 7-ft
weir structure
spanning
channel
10
Page 24/162
SFPEP: Intake / Headrace
1938 Pool and
Control Point
2006 Pool and
Control Point
11
Page 25/162
SFPEP: Intake / Headrace - refined
• Per bathymetry, review of historic aerial imagery and refinement of rating curve, no weir is required
• Flow regulation via powerhouse control
• Natural stable control point downstream maintains deep pool, self-cleaning at high flows
• Saves approx $10M construction cost
• Reduces in-water work and timeline
12
Page 26/162
SFPEP: Intake / Headrace - refined
13
Page 27/162
SFPEP: Fish Screens - PAD
•PAD design included large cavern
housing vertical fish screens
•Approx 50% of project excavation identified related to cavern & weir
14
Page 28/162
SFPEP: Fish Screens - refined
• Move to opposite side of hillside
• Reduces 50% of excavation, simpler constructability
• Fish bypass returns juveniles directly to bypass reach
• Long-term improved access and O&M
• Reduces overall project cost
15
Page 29/162
SFPEP: Power Tunnel - PAD
16
Page 30/162
SFPEP: Power Tunnel - refined
• Allows flexibility to construction sequencing, should reduce duration and disperse traffic due to multiple entrance sites
17
Page 31/162
SFPEP: Powerhouse - PAD
18
Page 32/162
SFPEP: Powerhouse - refined
• Moving closer to river reduces overall cost, powerhouse height, tailrace length, and removes need to excavate entire rock knob
• Relocation of switchyard reduces rock excavation
19
Page 33/162
Turbine Selection
• Kaplan or Francis fits head/flow
• Kaplan improves overall energy production, improved overall economics
• Still evaluating unit size and single vs. double
20
Page 34/162
SFPEP: Study Revisions - HDR
• SP 1, Water Quality: Revisions to study plan including
increased monitoring (additional locations, additional
parameters), $42,057
• SP 17, Mollusks: New study requirement, $36,975
• SP 18, Benthic Macroinvertebrates: Revisions to study
plan, $2,047
• Additional contract cost: $81,079
• New total contract cost: $311,242
21
Page 35/162
SFPEP: Study Revisions - Anchor • SP 12, Downstream Fish Passage at Falls (Injury
Assessment): Revisions to study plan including more
tests with larger fish
• Additional contract cost: $85,170
• New total contract cost: $302,646
22
Page 36/162
SFPEP: Study Revisions - ERM
• SP 9, Aesthetic Resource Study: Additions to study plan
as required by the FERC Study Plan Determination, to
include low, medium and high flows for 6 Visual Key
Observation Points (VKOPs), include landscape views
(mountains) at 4 KOPs, and include photomontages for
temporary construction impacts. New Project design
requires new photomontages of intake, powerhouse, and
fish screens.
• Additional contract cost: $77,458
• New total contract cost: $276,058
23
Page 37/162
SFPEP: Next Steps
• Amend 3 Contracts: additional $243,707
• Complete all field work for 16 required Study Plans and
geotechnical work, and deliver draft reports by year end
• Discuss design revisions with stakeholders – further
refinement may occur
• Announce revisions in project design to FERC service list
• Update to media
• Continue with design development
24
Page 38/162
QUESTIONS
25