Post WeldHeat Treatment
PROCEDURE MANUAL
-
ISO 9001 : 2000 EDITION
HEAT TREATMENT PROCEDURE HEAT TREATMENT PROCEDURE
ISSUE JUN 13, 2003
REVISION DEC 20, 2003
REV. NO. A
PERFORM DEC 20, 2003
DOC. NO. SW-HTP-01
PREPARED BY T. M. LEE
REVIEWED & APPROVED BY
Y. P. CHO
SWI Valve Co.,Ltd.
HEAD OFFICE & PLANT 1023-2, Kwanyang-dong, Anyang, Kyungki-do, Korea Tel : 82-31-422-7495 7 Fax : 82-31-422-7498 Home page : www.swivalve.com
-
QUALITY ASSURANCE DOC NO. SW-HTP-01 HEAT TREATMENT PROCEDURE PAGE 1 3
1.0 SCOPE 1.1 This procedure defines the heat treatment required by the material specification and
postweld heat treatment(PWHT) of pressure rating parts of the valve of SWI Valve Co.,Ltd.(SWI)
1.2 This procedure shall be applied to the manufacturing process. 2.0 APPLICABLE SPECIFICATIONS STANDARDS & CODES 2.1 ASME B31.3 "CHEMICAL PLANT AND PETROLEUM REFINERY PIPING" 2.2 Applicable material Specification. (ASTM) 3.0 HEAT TREATMENT & POSTWELDED HEAT TREATMENT(PWHT) PROCEDURE 3.1 Preparation 1) The forging & Cast steel shall be free of the scales, oil, grease, rust and other foreign adherents. 2) Loading 3.2 Heating After loading, temperature and time shall be prepared in according to the rules. 3.3 Holding 3.4 Cooling 4.0 INSPECTION The inspection after heat treatment and PWHT shall be performed on below test. 1) Visual 2) Heating Rate 3) Holding Time
4) Cooling Rate 5) Hardness Test
-
QUALITY ASSURANCE DOC NO. SW-HTP-01 HEAT TREATMENT PROCEDURE PAGE 2 3
5.0 GENERAL SKETCH OF HEAT TREATMENT CURVE
FORGING STEEL HEAT TREATMRNT TEMPERATURE STANDARD Method
Material NORMALIZING STRESS RELIEVING / PWHT
ASTM A105 A350-LF2
Temp. 88025
Air Max. Cooling 150/Hr 300 Holding Time : 1 Hr/in
Temp. 65025
Max. Max. 100/Hr 150/Hr 300
Holding Time : 1 Hr/inch
Method Material NORMALIZING TEMPERING / P.W.H.T
ASTM A182-F5 A182-F9
Temp. 98025
Air Max. Cooling 150/Hr 300 Holding Time : 1 Hr/inch
Temp. 73025
Max. Max. 100/Hr 150/Hr 300
Holding Time : 1 Hr/in P.W.H.T Holding Time : 2 Hr
Method Material NORMALIZING TEMPERING / P.W.H.T
ASTM A182-F11 A182-F22
Temp. 93025
Air Max. Cooling 150/Hr 300 Holding Time : 1 Hr/inch
Temp. 73025
Max. Max. 100/Hr 150/Hr 300
Holding Time : 1 Hr/in P.W.H.T Holding Time : 2 Hr
-
QUALITY ASSURANCE DOC NO. SW-HTP-01 HEAT TREATMENT PROCEDURE PAGE 3 3
FORGING STEEL HEAT TREATMRNT TEMPERATURE STANDARD Method
Material SOLUTION STRESS RELIEVING / PWHT
ASTM A182-F304 A182-F304L A182-F316 A182-F316L A182-F347 A351-CF3 A351-CF3M A351-CF8 A351-CF8C A351-CF8M
Temp. Min. 1040
Water Max. Cooling 150/Hr 300 Holding Time : 1 Hr/inch
Temp. Min. 1040
Water Max. Cooling 150/Hr 300 Holding Time : 1 Hr/inch
Method Material
NORMALIZING STRESS RELIEVING
ASTM A216-WCB A352-LCB
Temp. 91025
Air Max. Cooling 150/Hr 300 Holding Time : 1 Hr/in
Temp. 65025
Max. Max. 100/Hr 150/Hr 300
Holding Time : 1 Hr/inch
Method Material
NORMALIZING TEMPERING/STRESS RELIEVING
ASTM A217-C5 A217-C12 A217-WC6 A217-WC9
Temp. 95025
Air Max. Cooling 150/Hr 300 Holding Time : 1 Hr/inch
Temp. 73025
Max. Max. 100/Hr 150/Hr 300
Holding Time : 1 Hr/in