swpf process and liquid waste interface overview team... · design phase – conceptual thru final...

28
December 9, 2015 SWPF Process and Liquid Waste Interface Overview Salt Waste Processing Facility Pamela Marks – Federal Project Director Bob Leugemors – Chief Engineer

Upload: others

Post on 25-Aug-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: SWPF Process and Liquid Waste Interface Overview Team... · design phase – conceptual thru final construction 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 today –december

December 9, 2015

SWPF Process and Liquid Waste Interface Overview

Salt Waste Processing Facility

Pamela Marks – Federal Project DirectorBob Leugemors – Chief Engineer

Page 2: SWPF Process and Liquid Waste Interface Overview Team... · design phase – conceptual thru final construction 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 today –december

Salt Waste Processing Facility

This essential facility will:

– Reduce radioactive waste volume requiring vitrification

– Utilize the same actinide and cesium removal unit processes as Interim Salt Processing Facilities (ARP/MCU)

– Process over 90% of Tank Farm liquid radioactive waste (97 Mgal. after dissolution)

– Have a nominal capacity of6 – 9 million gallons per year

Parsons is the contractor for the SWPF project (design, construct, commission and operate for one year)

Page 2

Page 3: SWPF Process and Liquid Waste Interface Overview Team... · design phase – conceptual thru final construction 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 today –december

Liquid Waste System Today

Legend:ARP Actinide Removal ProcessDWPF Defense Waste Processing FacilityMCU Modular Caustic Side Solvent Extraction UnitSWPF Salt Waste Processing Facility

SWPF Designed to Process more than 6

millions gallons per year

Cs Decontamination factor > 40,000

Technology is very mature

No open DNFSB issues

DWPFDWPF

Sludge Waste

Tanks Cleaned and

ClosedRadionuclides

Inert chemicals

Salt Waste

DWPF

Glass Waste Storage

ARP

MCU

SWPF(under construction)

Saltstone Disposal Facility

Recycle

H-Canyon Receipts

Page 4: SWPF Process and Liquid Waste Interface Overview Team... · design phase – conceptual thru final construction 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 today –december

Waste Transfers

4

Page 5: SWPF Process and Liquid Waste Interface Overview Team... · design phase – conceptual thru final construction 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 today –december

SWPFF and H AreaTank Farms

Alpha Strike

Process

Alpha FinishingProcess

CesiumRemovalProcess

SaltstoneFacility

DWPF

QualifiedWasteBatch

ConcentratedSr-90/Actinides

Sludge

ConcentratedSr-90/Actinides

Sludge

DecontaminatedSalt Solution

Cs EnrichedStrip Effluent

SWPF Process

Page 5

Page 6: SWPF Process and Liquid Waste Interface Overview Team... · design phase – conceptual thru final construction 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 today –december

Alpha Finishing Facility (AFF)

Cold Chemicals Area

CSSX Room(below)

Truck Bay

Maintenance Area

Facility Support

Area

Process Building Ventilation Systems

Process Vessel Cells

AnalyticalLab

6

SWPF Process Building Layout

Page 7: SWPF Process and Liquid Waste Interface Overview Team... · design phase – conceptual thru final construction 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 today –december

DESIGN PHASE –CONCEPTUAL THRU FINAL

CONSTRUCTION

2002 2004 2006 2008 2010 2012 2014 2016 2018 2020

TODAY – December 2015

TARGET FACILITY OPERATION (CD-4)12/03/2018

CONSTRUCTION COMPLETE

12/31/2016

CD-3B1/2/2009

CD-2/3A9/24/2007

CD-1, MAR 20043/31/2004

CD-0, SEP 20029/2/2002

CONTINUED OPERATIONS

ONE YEAR OPERATIONS

HOT COMMISSIONING

COLD COMMISSIONING

10-15 Years

• 92.8% construction complete

• Construction is ahead of December 2016 completion

• Construction is under running the $530M cost cap

• 19.5% Complete commissioning

• Commissioning Plans and Procedures are in progress

SWPF Project Milestones

7

Page 8: SWPF Process and Liquid Waste Interface Overview Team... · design phase – conceptual thru final construction 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 today –december

SWPF Construction Progress

Basemat Installed

• Performance Category 3 (PC-3) • 8-feet thick • 32,943 square feet • 10,032 cubic yards

First Story Under Construction

• Walls to 100 ft. elev. Completed• Began installation of process piping • Wall placement to 139 ft. elev. in progress • Successful installation of contactor modules• Dark cells fabricated

Vessel Placement

• Successful installation of • 10 large ASME Vessels • 150,000 gal. of tank volume in CPA• PC-1 support structures underway

June 2012

• Roof completed• HVAC 92% complete• Ventilation stack completed• Fire coatings complete• Transformers and switchgear in place• All major process equipment in place• Waste transfer line installation

complete

• 100,000+ LF of piping installed (87% complete)

• 83,000 welds made (93% complete)• 120,000 LF of conduit installed (85%

complete)• 380,000 LF of wire and cable installed

(60% complete)

TODAYTODAY – 92.8% Physical Completion

Projected Construction Completion Date – April 2016

August 2009

April 2011

8

Page 9: SWPF Process and Liquid Waste Interface Overview Team... · design phase – conceptual thru final construction 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 today –december

Cesium Removal Contactors Arrival and Installation (December 2010)

Page 9

Page 10: SWPF Process and Liquid Waste Interface Overview Team... · design phase – conceptual thru final construction 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 today –december

Large ASME Vessels Delivered (June/July 2012)

10

Page 11: SWPF Process and Liquid Waste Interface Overview Team... · design phase – conceptual thru final construction 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 today –december

Alpha Finishing Tanks (December 2013)

Page 11

Page 12: SWPF Process and Liquid Waste Interface Overview Team... · design phase – conceptual thru final construction 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 today –december

Waste Transfer Line Installation (April 2014)

12

Page 13: SWPF Process and Liquid Waste Interface Overview Team... · design phase – conceptual thru final construction 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 today –december

• Extensive Test Program - Demonstrated Process Met or Exceeded 100% Capacity

• Robust Operating Envelope Developed to Provide Flexibility of Operations

• On-going Tests – Reliability/Maintainability – Increase Throughput

SWPF Test Program

Page 13

Page 14: SWPF Process and Liquid Waste Interface Overview Team... · design phase – conceptual thru final construction 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 today –december

SWPF Testing Activities

14

Page 15: SWPF Process and Liquid Waste Interface Overview Team... · design phase – conceptual thru final construction 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 today –december

Liquid Waste Interface Lines

15

From Tank Farm

Low Point Pump Pit

SWPF

Saltstone

DWPF

Page 16: SWPF Process and Liquid Waste Interface Overview Team... · design phase – conceptual thru final construction 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 today –december

SWPF Main Process

ASP

Adsorbed Srand actinides

onto MST.

MST concentrated

by CFFs

Concentrated sludge is washed to remove [Na+]prior to transfer

to the DWPF.

CSSX

Extracts and concentrate Cs

from the aqueous CFF filtrate

(CSS).

The resulting aqueous solution

(DSS) is transferred to the

SPF.

Concentrated Cs is transferred to

the DWPF.

AFP

Similar to the ASP, the MST is

used to sorb selected

actinides and Sr.

This process will be used on

waste batches when a further

reduction in the radionuclide

concentrations in the DSS is

required.

16

Page 17: SWPF Process and Liquid Waste Interface Overview Team... · design phase – conceptual thru final construction 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 today –december

Summary Flow Diagram

17

Page 18: SWPF Process and Liquid Waste Interface Overview Team... · design phase – conceptual thru final construction 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 today –december

Suspended Solids Samples (Cross Flow Filtration)

18

Page 19: SWPF Process and Liquid Waste Interface Overview Team... · design phase – conceptual thru final construction 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 today –december

Solvent Components

ExtractantCalix[4]arene-bis(tert-octylbenzo-crown-6)

"BoBCalixC6"0.007 M

O

O

OO

O

O

O

O

OO

O O O OH

OCH2CF2CF2H

Modifier: 1-(2,2,3,3-tetrafluoropropoxy)-

3-(4-sec-butylphenoxy)-2-propanol "Cs-7SB"

0.75 M

SuppressorTri-n-octylamine

"TOA"0.003 M

N Diluent

Isopar® L

(a blend of C10-C12 branched

alkanes)

Page 19

Page 20: SWPF Process and Liquid Waste Interface Overview Team... · design phase – conceptual thru final construction 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 today –december

Aqueous

ON

O

O

ON

O

O

ON

O

O

Na+

Organic

-O

NO

O

-

-

ON

O

O

K+

Cs+

O

OO

O

O

O

OO

O

OO O

-

Cs+

Na+

-

O

OO

O

O

O

OO

O

OO O

BOBCalixC6 Selectively Extracts Cs+ Ion

A major reaction involves extraction of CsNO3 as an ion pair.Modeling shows that actual mechanism also involves other reactions.

20

Page 21: SWPF Process and Liquid Waste Interface Overview Team... · design phase – conceptual thru final construction 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 today –december

ON

O

O

Cs+

-O

NO

O

O

OO

O

O

O

OO O

OO O

Organic

-

Aqueous

Cs+

O

OO

O

O

O

OO O

OO O

Produces a highly purified productExcellent feed for vitrification in the DWPF

Water Stripping is Key to the CSSX Process

21

Page 22: SWPF Process and Liquid Waste Interface Overview Team... · design phase – conceptual thru final construction 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 today –december

CINC Standard Contactor

22

Page 23: SWPF Process and Liquid Waste Interface Overview Team... · design phase – conceptual thru final construction 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 today –december

Stilling Tank/Decanter

23

Page 24: SWPF Process and Liquid Waste Interface Overview Team... · design phase – conceptual thru final construction 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 today –december

Coalescer

24

Page 25: SWPF Process and Liquid Waste Interface Overview Team... · design phase – conceptual thru final construction 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 today –december

• High degree of technical confidence

• Maintain safety, cost and schedule performance

• Integrate NGS and High Sodium processing to enhance throughput

• Optimize facility operability

• Maintain integration with the Liquid Waste Program

• Minimize Liquid Waste lifecycle costs – Full Solution to SRS Tank Closure

Looking to the Future

25

Page 26: SWPF Process and Liquid Waste Interface Overview Team... · design phase – conceptual thru final construction 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 today –december

26

Page 27: SWPF Process and Liquid Waste Interface Overview Team... · design phase – conceptual thru final construction 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 today –december

Backup

27

Page 28: SWPF Process and Liquid Waste Interface Overview Team... · design phase – conceptual thru final construction 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 today –december

Target ion [ ]’s for the Salt Solution Simulant and Chemical Reconstitution

Chemical Reconstitution Options

– Full reconstitution to the target concentrations for 5.6M [Na+] - (table 5-1)

– Reconstitution of major components only (NaOH, Sodium Nitrate, Sodium Nitrite)

– Reuse of a simulant batch without reconstitution

– A combination of the previous options

28