swpf process and liquid waste interface overview team... · design phase – conceptual thru final...
TRANSCRIPT
![Page 1: SWPF Process and Liquid Waste Interface Overview Team... · design phase – conceptual thru final construction 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 today –december](https://reader035.vdocument.in/reader035/viewer/2022081523/5fd7f7d4d950da5d3c63c88d/html5/thumbnails/1.jpg)
December 9, 2015
SWPF Process and Liquid Waste Interface Overview
Salt Waste Processing Facility
Pamela Marks – Federal Project DirectorBob Leugemors – Chief Engineer
![Page 2: SWPF Process and Liquid Waste Interface Overview Team... · design phase – conceptual thru final construction 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 today –december](https://reader035.vdocument.in/reader035/viewer/2022081523/5fd7f7d4d950da5d3c63c88d/html5/thumbnails/2.jpg)
Salt Waste Processing Facility
This essential facility will:
– Reduce radioactive waste volume requiring vitrification
– Utilize the same actinide and cesium removal unit processes as Interim Salt Processing Facilities (ARP/MCU)
– Process over 90% of Tank Farm liquid radioactive waste (97 Mgal. after dissolution)
– Have a nominal capacity of6 – 9 million gallons per year
Parsons is the contractor for the SWPF project (design, construct, commission and operate for one year)
Page 2
![Page 3: SWPF Process and Liquid Waste Interface Overview Team... · design phase – conceptual thru final construction 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 today –december](https://reader035.vdocument.in/reader035/viewer/2022081523/5fd7f7d4d950da5d3c63c88d/html5/thumbnails/3.jpg)
Liquid Waste System Today
Legend:ARP Actinide Removal ProcessDWPF Defense Waste Processing FacilityMCU Modular Caustic Side Solvent Extraction UnitSWPF Salt Waste Processing Facility
SWPF Designed to Process more than 6
millions gallons per year
Cs Decontamination factor > 40,000
Technology is very mature
No open DNFSB issues
DWPFDWPF
Sludge Waste
Tanks Cleaned and
ClosedRadionuclides
Inert chemicals
Salt Waste
DWPF
Glass Waste Storage
ARP
MCU
SWPF(under construction)
Saltstone Disposal Facility
Recycle
H-Canyon Receipts
![Page 4: SWPF Process and Liquid Waste Interface Overview Team... · design phase – conceptual thru final construction 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 today –december](https://reader035.vdocument.in/reader035/viewer/2022081523/5fd7f7d4d950da5d3c63c88d/html5/thumbnails/4.jpg)
Waste Transfers
4
![Page 5: SWPF Process and Liquid Waste Interface Overview Team... · design phase – conceptual thru final construction 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 today –december](https://reader035.vdocument.in/reader035/viewer/2022081523/5fd7f7d4d950da5d3c63c88d/html5/thumbnails/5.jpg)
SWPFF and H AreaTank Farms
Alpha Strike
Process
Alpha FinishingProcess
CesiumRemovalProcess
SaltstoneFacility
DWPF
QualifiedWasteBatch
ConcentratedSr-90/Actinides
Sludge
ConcentratedSr-90/Actinides
Sludge
DecontaminatedSalt Solution
Cs EnrichedStrip Effluent
SWPF Process
Page 5
![Page 6: SWPF Process and Liquid Waste Interface Overview Team... · design phase – conceptual thru final construction 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 today –december](https://reader035.vdocument.in/reader035/viewer/2022081523/5fd7f7d4d950da5d3c63c88d/html5/thumbnails/6.jpg)
Alpha Finishing Facility (AFF)
Cold Chemicals Area
CSSX Room(below)
Truck Bay
Maintenance Area
Facility Support
Area
Process Building Ventilation Systems
Process Vessel Cells
AnalyticalLab
6
SWPF Process Building Layout
![Page 7: SWPF Process and Liquid Waste Interface Overview Team... · design phase – conceptual thru final construction 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 today –december](https://reader035.vdocument.in/reader035/viewer/2022081523/5fd7f7d4d950da5d3c63c88d/html5/thumbnails/7.jpg)
DESIGN PHASE –CONCEPTUAL THRU FINAL
CONSTRUCTION
2002 2004 2006 2008 2010 2012 2014 2016 2018 2020
TODAY – December 2015
TARGET FACILITY OPERATION (CD-4)12/03/2018
CONSTRUCTION COMPLETE
12/31/2016
CD-3B1/2/2009
CD-2/3A9/24/2007
CD-1, MAR 20043/31/2004
CD-0, SEP 20029/2/2002
CONTINUED OPERATIONS
ONE YEAR OPERATIONS
HOT COMMISSIONING
COLD COMMISSIONING
10-15 Years
• 92.8% construction complete
• Construction is ahead of December 2016 completion
• Construction is under running the $530M cost cap
• 19.5% Complete commissioning
• Commissioning Plans and Procedures are in progress
SWPF Project Milestones
7
![Page 8: SWPF Process and Liquid Waste Interface Overview Team... · design phase – conceptual thru final construction 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 today –december](https://reader035.vdocument.in/reader035/viewer/2022081523/5fd7f7d4d950da5d3c63c88d/html5/thumbnails/8.jpg)
SWPF Construction Progress
Basemat Installed
• Performance Category 3 (PC-3) • 8-feet thick • 32,943 square feet • 10,032 cubic yards
First Story Under Construction
• Walls to 100 ft. elev. Completed• Began installation of process piping • Wall placement to 139 ft. elev. in progress • Successful installation of contactor modules• Dark cells fabricated
Vessel Placement
• Successful installation of • 10 large ASME Vessels • 150,000 gal. of tank volume in CPA• PC-1 support structures underway
June 2012
• Roof completed• HVAC 92% complete• Ventilation stack completed• Fire coatings complete• Transformers and switchgear in place• All major process equipment in place• Waste transfer line installation
complete
• 100,000+ LF of piping installed (87% complete)
• 83,000 welds made (93% complete)• 120,000 LF of conduit installed (85%
complete)• 380,000 LF of wire and cable installed
(60% complete)
TODAYTODAY – 92.8% Physical Completion
Projected Construction Completion Date – April 2016
August 2009
April 2011
8
![Page 9: SWPF Process and Liquid Waste Interface Overview Team... · design phase – conceptual thru final construction 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 today –december](https://reader035.vdocument.in/reader035/viewer/2022081523/5fd7f7d4d950da5d3c63c88d/html5/thumbnails/9.jpg)
Cesium Removal Contactors Arrival and Installation (December 2010)
Page 9
![Page 10: SWPF Process and Liquid Waste Interface Overview Team... · design phase – conceptual thru final construction 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 today –december](https://reader035.vdocument.in/reader035/viewer/2022081523/5fd7f7d4d950da5d3c63c88d/html5/thumbnails/10.jpg)
Large ASME Vessels Delivered (June/July 2012)
10
![Page 11: SWPF Process and Liquid Waste Interface Overview Team... · design phase – conceptual thru final construction 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 today –december](https://reader035.vdocument.in/reader035/viewer/2022081523/5fd7f7d4d950da5d3c63c88d/html5/thumbnails/11.jpg)
Alpha Finishing Tanks (December 2013)
Page 11
![Page 12: SWPF Process and Liquid Waste Interface Overview Team... · design phase – conceptual thru final construction 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 today –december](https://reader035.vdocument.in/reader035/viewer/2022081523/5fd7f7d4d950da5d3c63c88d/html5/thumbnails/12.jpg)
Waste Transfer Line Installation (April 2014)
12
![Page 13: SWPF Process and Liquid Waste Interface Overview Team... · design phase – conceptual thru final construction 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 today –december](https://reader035.vdocument.in/reader035/viewer/2022081523/5fd7f7d4d950da5d3c63c88d/html5/thumbnails/13.jpg)
• Extensive Test Program - Demonstrated Process Met or Exceeded 100% Capacity
• Robust Operating Envelope Developed to Provide Flexibility of Operations
• On-going Tests – Reliability/Maintainability – Increase Throughput
SWPF Test Program
Page 13
![Page 14: SWPF Process and Liquid Waste Interface Overview Team... · design phase – conceptual thru final construction 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 today –december](https://reader035.vdocument.in/reader035/viewer/2022081523/5fd7f7d4d950da5d3c63c88d/html5/thumbnails/14.jpg)
SWPF Testing Activities
14
![Page 15: SWPF Process and Liquid Waste Interface Overview Team... · design phase – conceptual thru final construction 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 today –december](https://reader035.vdocument.in/reader035/viewer/2022081523/5fd7f7d4d950da5d3c63c88d/html5/thumbnails/15.jpg)
Liquid Waste Interface Lines
15
From Tank Farm
Low Point Pump Pit
SWPF
Saltstone
DWPF
![Page 16: SWPF Process and Liquid Waste Interface Overview Team... · design phase – conceptual thru final construction 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 today –december](https://reader035.vdocument.in/reader035/viewer/2022081523/5fd7f7d4d950da5d3c63c88d/html5/thumbnails/16.jpg)
SWPF Main Process
ASP
Adsorbed Srand actinides
onto MST.
MST concentrated
by CFFs
Concentrated sludge is washed to remove [Na+]prior to transfer
to the DWPF.
CSSX
Extracts and concentrate Cs
from the aqueous CFF filtrate
(CSS).
The resulting aqueous solution
(DSS) is transferred to the
SPF.
Concentrated Cs is transferred to
the DWPF.
AFP
Similar to the ASP, the MST is
used to sorb selected
actinides and Sr.
This process will be used on
waste batches when a further
reduction in the radionuclide
concentrations in the DSS is
required.
16
![Page 17: SWPF Process and Liquid Waste Interface Overview Team... · design phase – conceptual thru final construction 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 today –december](https://reader035.vdocument.in/reader035/viewer/2022081523/5fd7f7d4d950da5d3c63c88d/html5/thumbnails/17.jpg)
Summary Flow Diagram
17
![Page 18: SWPF Process and Liquid Waste Interface Overview Team... · design phase – conceptual thru final construction 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 today –december](https://reader035.vdocument.in/reader035/viewer/2022081523/5fd7f7d4d950da5d3c63c88d/html5/thumbnails/18.jpg)
Suspended Solids Samples (Cross Flow Filtration)
18
![Page 19: SWPF Process and Liquid Waste Interface Overview Team... · design phase – conceptual thru final construction 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 today –december](https://reader035.vdocument.in/reader035/viewer/2022081523/5fd7f7d4d950da5d3c63c88d/html5/thumbnails/19.jpg)
Solvent Components
ExtractantCalix[4]arene-bis(tert-octylbenzo-crown-6)
"BoBCalixC6"0.007 M
O
O
OO
O
O
O
O
OO
O O O OH
OCH2CF2CF2H
Modifier: 1-(2,2,3,3-tetrafluoropropoxy)-
3-(4-sec-butylphenoxy)-2-propanol "Cs-7SB"
0.75 M
SuppressorTri-n-octylamine
"TOA"0.003 M
N Diluent
Isopar® L
(a blend of C10-C12 branched
alkanes)
Page 19
![Page 20: SWPF Process and Liquid Waste Interface Overview Team... · design phase – conceptual thru final construction 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 today –december](https://reader035.vdocument.in/reader035/viewer/2022081523/5fd7f7d4d950da5d3c63c88d/html5/thumbnails/20.jpg)
Aqueous
ON
O
O
ON
O
O
ON
O
O
Na+
Organic
-O
NO
O
-
-
ON
O
O
K+
Cs+
O
OO
O
O
O
OO
O
OO O
-
Cs+
Na+
-
O
OO
O
O
O
OO
O
OO O
BOBCalixC6 Selectively Extracts Cs+ Ion
A major reaction involves extraction of CsNO3 as an ion pair.Modeling shows that actual mechanism also involves other reactions.
20
![Page 21: SWPF Process and Liquid Waste Interface Overview Team... · design phase – conceptual thru final construction 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 today –december](https://reader035.vdocument.in/reader035/viewer/2022081523/5fd7f7d4d950da5d3c63c88d/html5/thumbnails/21.jpg)
ON
O
O
Cs+
-O
NO
O
O
OO
O
O
O
OO O
OO O
Organic
-
Aqueous
Cs+
O
OO
O
O
O
OO O
OO O
Produces a highly purified productExcellent feed for vitrification in the DWPF
Water Stripping is Key to the CSSX Process
21
![Page 22: SWPF Process and Liquid Waste Interface Overview Team... · design phase – conceptual thru final construction 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 today –december](https://reader035.vdocument.in/reader035/viewer/2022081523/5fd7f7d4d950da5d3c63c88d/html5/thumbnails/22.jpg)
CINC Standard Contactor
22
![Page 23: SWPF Process and Liquid Waste Interface Overview Team... · design phase – conceptual thru final construction 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 today –december](https://reader035.vdocument.in/reader035/viewer/2022081523/5fd7f7d4d950da5d3c63c88d/html5/thumbnails/23.jpg)
Stilling Tank/Decanter
23
![Page 24: SWPF Process and Liquid Waste Interface Overview Team... · design phase – conceptual thru final construction 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 today –december](https://reader035.vdocument.in/reader035/viewer/2022081523/5fd7f7d4d950da5d3c63c88d/html5/thumbnails/24.jpg)
Coalescer
24
![Page 25: SWPF Process and Liquid Waste Interface Overview Team... · design phase – conceptual thru final construction 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 today –december](https://reader035.vdocument.in/reader035/viewer/2022081523/5fd7f7d4d950da5d3c63c88d/html5/thumbnails/25.jpg)
• High degree of technical confidence
• Maintain safety, cost and schedule performance
• Integrate NGS and High Sodium processing to enhance throughput
• Optimize facility operability
• Maintain integration with the Liquid Waste Program
• Minimize Liquid Waste lifecycle costs – Full Solution to SRS Tank Closure
Looking to the Future
25
![Page 26: SWPF Process and Liquid Waste Interface Overview Team... · design phase – conceptual thru final construction 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 today –december](https://reader035.vdocument.in/reader035/viewer/2022081523/5fd7f7d4d950da5d3c63c88d/html5/thumbnails/26.jpg)
26
![Page 27: SWPF Process and Liquid Waste Interface Overview Team... · design phase – conceptual thru final construction 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 today –december](https://reader035.vdocument.in/reader035/viewer/2022081523/5fd7f7d4d950da5d3c63c88d/html5/thumbnails/27.jpg)
Backup
27
![Page 28: SWPF Process and Liquid Waste Interface Overview Team... · design phase – conceptual thru final construction 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 today –december](https://reader035.vdocument.in/reader035/viewer/2022081523/5fd7f7d4d950da5d3c63c88d/html5/thumbnails/28.jpg)
Target ion [ ]’s for the Salt Solution Simulant and Chemical Reconstitution
Chemical Reconstitution Options
– Full reconstitution to the target concentrations for 5.6M [Na+] - (table 5-1)
– Reconstitution of major components only (NaOH, Sodium Nitrate, Sodium Nitrite)
– Reuse of a simulant batch without reconstitution
– A combination of the previous options
28