synergy - pmi north india chapter · synergy collaborating project management for high performance...
TRANSCRIPT
Synergy
Collaborating Project Management for High Performance Business Insight
PMI North India Chapter
April-June 2012 Newsletter
Issue 5
Work life balance, critically yours…
this issue
Managing Complex Business… P2
Cash Flow Management…P3
Organizational Change… P7
Quiz…P9
Rigidity to Agility...P12
Project Management Office…P16
Best Practice Quality Assurance…P18
Past Events…P21
Authors… P22
Editorial Team…P23
From the Editor’s Desk
First Anniversary Issue
It is a proud moment for entire community as our SYNERGY turns 1 year old. I, along with my entire Editorial
team, take pride in releasing the fifth edition as a First “Anniversary Issue”. Successful and timely releases
of SYNERGY reflect the involvement and commitment of entire Project Management fraternity. Timely
releases of SYNERGY would not have been possible without your support. I, on behalf of Chapter board,
eulogize all the authors in the last 1 year who have devoted their valuable time for nurturing SYNERGY
P1
21st June is longest day of the year since sunlight is for longer duration of the day in Northern Hemisphere. We aim to take
this cue from nature and spread the light of knowledge and experience using SYNERGY as a medium for many more years.
We have symbolically chosen 21st June to release our SYNERGY Anniversary Issue as a source of inspiration towards
continuous growth and awareness of Project Management.
I am also grateful for Editorial team's efforts comprising of committed individuals who have zealously worked as a team in
reviewing all inputs and feedback to ensure that a well packaged SYNERGY is released every quarter. Our entire editorial
team is a classic example of executing project using a virtual team. This is due to the fact that our editorial team has never
had a single face to face meeting since the time SYNERGY was conceived! We take pride that we have released every
edition of SYNERGY on the announced date without any schedule overrun.
I urge fellow professionals to read SYNERGY and we always look forward to your critical review that will help SYNERGY to
become a mature adult.
Happy Reading!
despite their other professional and personal commitments.
Regards
Piyush Govil PMP®
Vice –President – Communications
PMI North India Chapter
Managing Complex Business Deliverables in Projects
business analyst is focused on the risk analysis of the
business vision and project opportunities. The technology is
changing fast, in the times of recession there is a huge
pressure on the margins and the customer wants the best
at the cheapest rates. Further in case of global
opportunities various legal, geographic specific risk,
political risks need to be assessed.
Technical architect and commercial architect of the
business /project opportunity will have to take project
oriented approach.
Analyze the risks and suggest multiple scenarios to the
customer as well as to the management and will have to
create a balance between customers requirement and
organizations goals of profitability before coming up
with an optimum techno-commercial solution.
It is a trend and most of the organizations today are
hence using teams to analyze these risks and suggest
mitigations and come up with scenarios with technical,
commercial and legal background.
Right project management approach in these kinds of
teams is not currently used to an optimum level at least
in Indian companies and a lot can/ needs be done to
introduce the concept and principles of project
management in such teams.
Project management techniques specially those of
analyzing & mitigating risks like creating risks
frameworks, risk registers etc are the essential need of
business managers/analysts/bid managers in today’s
global volatile business environment.
Business Case – Telecom Industry
Key Inherent Risks for Working Project Managers: Inherent risks in markets (systematic risks)
Specific risks (non systematic risks) which can be
classified as: Market Risk (Market price fluctuations, FX
etc)
A business customer has a requirement which can be served
by a global MPLS based VPN but the customer has a limited
budget and also wants the solution to run for seven years
without impacting its real time requirements.
Techno commercial risks are:
Hardware requirement -suggested may become obsolete.
Technical obsolesce and Capex limitations
Geo political risks are:
Regulatory constraints in the different global locations
may impose different challenges like censorship on the
content and risks which needs to be mitigated by
proper contracting.
Case Study – Telecom Industry Managers:
Project management key essentials Managers:
Current telecom market business atmosphere with
uncertainty and project delivery limitations can be best
managed by a balanced careful approach for project
managers/BA’s/Procurement teams to plan and analyze
potential risks event with mitigation plan for seamless
delivery and satisfied end customer expectations.
In today’s dynamic futuristic world the role of a
Take Away Managers:
By – Ritesh Arora
Save Earth, Go Green P2
Mr. Ritesh Arora Senior Manager-Central Bid team, HCL Infosystems Ltd,
Noida
Ritesh has close to 10 years of Management Consulting, and
Industry wide experience across multiple sectors - Telecom, IT,
Oil & Gas, Government ( e-Governance), BFSI . His key
competencies are: Project & program management, Commercial &
bid management, procurement & vendor management, business
development, relationship and stakeholder for transition & change
management and provide thought leadership. He has worked with
various clients in India & Middle East. He is BE in Computers
Science and Engineering from DIT in year 1998-2002 and MBA from
FMS (part-time).
About Author
Cash Flow Management in Large Infrastructure Projects
costs of different packages, predict the timing of cash
outflow, arrange funds, monitor the actual cash outflow,
identify deviations with respect to plan and modify the
baseline plan as the project progresses so that the actual
cash outflow is within permissible deviation limits. This is a
continuous and intricate process as it involves thorough
knowledge of the commercial order conditions for raising
bills, timing of the bills raised, payments cycle, physical
progress made against each package etc. Large
infrastructure projects are capital intensive and require
funds during the project execution. The source of these
funds may be either debt or equity. Managing the funds
and its efficient outflow synchronizing with the actual
progress made is a complicated task due to the fact that a
track of the incremental physical progress is required to be
kept on real time basis. Efficient Management of funds is
essential to optimize the interest cost and at the same
time ensure that sufficient funds are available to release
payments against the bills being received, without
annoying the vendors and contractors.
P roject Cash Flow Management involves estimating
During the project investment approval, costs are allocated
against each item under the cost head based on market
estimates and in-house cost database. Applicable taxes and
duties if any are also indicated. If required, cost of some of
the items under the cost head are estimated in foreign
currency assuming that such items would be imported.
Thereafter the total cost estimate is derived. Tolerance
limit in estimated cost of +/- 20 % at the time of seeking
investment approval is considered accurate.
Estimating cost for each item under the cost head Managers:
Steps in Cash Flow Management Managers:
By – Asim Prasad
Cash flow management is an integral part of Project
Management. It’s a systematic long drawn continuous
process which starts immediately after the project capital
cost estimates has been prepared. Estimating the net cash
flow over the economic life of the project with accuracy is
important as it affects the wealth creation of the
shareholders. Based on my experience of executing cross
country natural gas pipeline projects the steps required to
be followed for efficient cash flow management for large
infrastructure projects are as under:
Identification of cost heads
Cost heads are identified with the decomposition of the
project at the time investment approval. Large
infrastructure projects involves various cost heads
comprising direct and indirect cost, hard and soft costs as
detailed herein. The project cost estimated at the time of
project investment approval forms the basis for ascertaining
the project cost overrun at the time of project completion.
1
2
Sl. Cost head Total Cost
TCi
1. Procurement packages (P1,P2….Pj) TC1
2. Work Packages(W1,W2….Wk) TC2
3. Owners Management Expenses TC3
4. Contingency TC4
5. Inflation TC4
6. Interest on Debt , Margin Money for Working Capital TC5
Project Approved Cost(Baseline-0 at Time T0) TACB0
Table 1
TACB0 = ∑TCi where i=1 to n; n= total number of cost heads
Mathematically,
The total approved cost=TAC, is a function of time and is
dependent on market forces.
Large infrastructure projects are completed in three to five
years time depending on the project complexity and size. At
the time of investment approval, considering the estimated
project schedule, the cash outflows against each cost head
are forecasted based on project schedule, past experience
and market estimates. Thereafter the total outflow against
each month is calculated.
Further the percentage monthly cash outflow is also
calculated based on estimated costs. Refer Table 2
Calculate the Cash Outflow based on estimated cost 3
Save Earth, Go Green P3
Food for thought
Served by – Piyush Govil
Work life balance, are we really serious? or buzz words…
In large infrastructure projects, awarding contracts to
vendors and contractors for procurement and works is a
lengthy process as high value procurement involves several
intricate steps for which standard transparent procedures
and guidelines are followed. This process also involves
different categories of stakeholders who interact with each
other and are influential enough to alter the decision
process. Considering all this, as and when the orders are
placed, the actual order value is recorded. Based on the
execution schedule for the particular order considering the
commercial conditions, the cash flow is determined.
Sl. Cost head Total Cost: TCi Month -1 Month -2 Month-(N-1) Month-N
1 Procurement packages (P1,P2….Pj) TC1 TC11 TC12
2 Work Packages(W1,W2….Wk) TC2 TC21 TC22
3 Owners Management Expenses TC3 TC31 TC32
4 Contingency TC4 TC41 TC42
5 Inflation TC5 TC51 TC52
6 Interest on Debt , Margin Money for Working Capital TC6 TC61 TC62
Total [Basaeline-0] TACB0 TCM1 TCM2 TCM (N-1) TCM-N
% Cash Outflow [Basaeline-0] -
TCM1/ TACB0
TCM2/ TACB0
TCM(N-1)/ TACB0
TCM-N/ TACB0
Table 2
Calculate the Cash Outflow based on actual ordered
cost and scheduled progress [Baseline-1] 4
The cash outflow so calculated is the baseline-0 cost
outflow based on estimated cost.
TACB0=∑TCMm where m=1 to N; N= total number of months for cash outflow
Mathematically,
Sl. Cost head Total
Cost: TCi Total Order
Cost: TCi
Month: Month: Month: Month:N
N-m N-2 (N-1)
1 Procurement packages (P1,P2….Pj) TC1 TOC1
2 Work Packages(W1,W2….Wk) TC2 TOC2
3 Owners Management Expenses TC3 TOC3
4 Contingency TC4 TOC4
5 Inflation TC5 TOC5
6 Interest on Debt , Margin Money for Working Capital TC6 TOC6
Total [Basaeline-1] TACB0 TOCB1
TOCM (N-m)
TOCM (N-2)
TOCM (N-1)
TOCM-(N)
% Cash Outflow [Basaeline-1] - - TOCM(N-
m)/ TOCB1
TOCM(N-2)/
TOCB1
TOCM(N-1)/
TOCB1
TOCM-(N)/
TOCB1
The actual expenditure under cost heads like Owners
Management Expenses, Contingency, Inflation, Interest on
Debt, Margin Money for Working Capital are calculated after
the project completion during capitalization. However,
during execution certain values are estimated based on past
experience and indicated under total cost head. The steps
are repeated till all orders are placed. Refer Table 3
TOCB1 = ∑TOCMm where m=1 to N; N= total number of months for cash outflow
Mathematically,
The cash outflow so calculated is the baseline-1 cost outflow
based on ordered cost.
Further the percentage monthly cash outflow is also
calculated based on ordered costs.
Table 3
Save Earth, Go Green P4
At the time of project execution, recalculate the cash outflow based on balance expenditure to be made and
actual progress made [Baseline-2]
5
Further the percentage monthly cash outflow is also
calculated based on balance expenditure.
The cash outflow so calculated is the baseline-2 cost outflow
based on balance expenditure. As the project progress, on
month to month basis the balance expenditure and revised
cash flow are calculated. This continuous process improves
the accuracy level of prediction w.r.t. anticipated
expenditure required in subsequent months. Refer Table 4
Sl. Cost head X=Total Order
Cost: TCi
Y=Cumulative Expenditure Made till
previous month
Z=X-Y=
Balance Expenditure till previous month
1 Procurement packages (P1,P2….Pj)
TOC1 TCE1 Z1=TOC1-TCE1
2 Work Packages(W1,W2….Wk) TOC2 TCE2 Z2=TOC2-TCE2
3 Owners Management Expenses TOC3 TCE3 Z3=TOC3-TCE3
4 Contingency TOC4 TCE4 Z4=TOC4-TCE4
5 Inflation TOC5 TCE5 Z5=TOC5-TCE5
6 Interest on Debt (Indirect Cost) TOC6 TCE6 Z6=TOC6-TCE6
Total [Basaeline-2] TOCB1 TCE Z=TOCB1 -TCE
% Cash Outflow [Basaeline-2] - TCE/TOCB1 (TOCB1 –TCE)/ TOCB1
Table 4
Identify the deviations with reasons between the
cash outflow derived in step 4 and step 5 6
The project execution involves uncertainties and often it is
difficult to precisely predict the risk and its outcomes. Risk
may be known-known or known-unknown. This affects the
cash flow during actual execution. Mostly it happens that the
actual physical progress is in variance with the planned
progress. Therefore it becomes important to identify the
reasons for deviations and the corresponding variation in
cash outflow. Once such deviations are identified, the
planned cash outflow can be prepared with higher levels of
accuracy. Accuracy levels in prediction of cash flow on
month to month basis of 95 % are considered good. The
periodicity of such a detailed analysis for ascertaining
deviation is one month.
Once the reasons for deviations under different WBS element
are identified, contingency plans are prepared to minimize
deviations. Implementation of the contingency plan in true
spirit ensures that the project is still on the scheduled path.
Some contingency plans may involve usage of resource like
time, cost and heavy equipment. However, due to scarcity in
resources, it is not always possible to implement contingency
plans due to which projects are delayed. This may result in
cost overrun also. The project manager may therefore
conduct a decision tree analysis along with a cost benefit
analysis before proceeding ahead.
Prepare contingency plan to minimize the deviation 7
Monitor the actual cash outflow 8
Cash outflow is required to be monitored on continuous basis
with the release of payments against running bills. This being
a real time process, some system needs to be designed that
will monitor the progress electronically and provide a
snapshot information to the project manager on aspects like
balance payment against each cost head, look ahead plan for
succeeding months, percentage financial progress made in
each cost head along with overall percentage financial
progress. The percentage progress is measured considering
the overall approved project cost in the denominator.
Save Earth, Go Green P5
Overhead by -Kumar Saurabh, PMP®
Project Management – lighter side
The more innocuous the modification appears to be, the further its influence will
extend and the more plans will have to be redrawn.
The above methodology has been applied in execution of
cross country natural gas pipeline projects with high
degree of success in predicting cash outflows with
accuracy within permissible limits. Considering the fact
that debt financing is also involved in large infrastructure
projects, it becomes very important to precisely predict
the future cash outflows on monthly basis for project
completion so that only the portion of amount required for
Take Away Managers:
Save Earth, Go Green P6
expenditure in the successor month is borrowed on month to
month basis. The above exercise also helps to prepare budget
estimates for the financial years during the lifecycle of the
project completion. If the company is executing number of
different infrastructure projects of varying size and
complexity, it helps to ascertain the cash flow of the entire
project portfolio at the organizational level.
Mr. Asim Prasad Chief Manager
GAIL (India) Limited, New Delhi
About Author
Mr. Asim Prasad is a graduate in Mechanical Engineering from IIT
Kanpur and working as Chief Manager at GAIL(India) Limited,
New Delhi. He has varied rich experience of the natural gas value
chain comprising Operation & Maintenance of Cross Country
Natural Gas Pipelines, Project Management of Cross Country
Natural Gas Pipelines and Natural Gas Marketing. During the
course of his professional career he completed Post Graduate
Diploma in Project Management, Advanced Diploma in
Management and Executive Diploma in Project Management. He
is a member of PMI USA, ASME USA; Life Member IIGE Kolkotta
and Member IEI Kolkotta.
Organizational Change – What’s in it for me?
By – Anju Agarwal
accelerating at an increasing rate. Factors, such as
globalization, new technologies, mergers & acquisitions,
shifting markets, structural changes and outsourcing, force
businesses to respond effectively in order to survive. Every
organization must change - not only to survive, but also to
retain its relevance in a world of intense competition,
constant scientific progress, and rapid communication.
Though it is very clear that change is necessary, one
question why change efforts fail to achieve the desired
results, or why employees feel totally lost and frustrated
during and after a change, or why the attrition rate
skyrockets during these organizational changes.
C hange is a necessary part of growth and it is
To embrace change, people need to feel comfortable about
the change; they need to understand and appreciate the
reason for the change. Buy-in is also about personal
benefit, and if employees don’t believe that they shall
receive a certain level of individual benefit from the
change, getting buy-in will always be a challenge.
This paper explores why employees are left unappreciated
and undervalued during corporate change programs and
offers some ideas as to how a corporation can
institutionalize change management to become a
constantly evolving success story.
It is very important that
change is identified by the
employees as a stimulator
of their growth. One
cannot drive and motivate
an employee for long, by
providing figures of future
benefits of organizational
changes. Every change
requires an adjustment
and it is very difficult to
get a buy in from an
employee without framing
the change as a “What’s in
it for me? (WIFM)”.
Employees fail to see the reason for the change. It is natural
for employees to view change, first from the perspective of
their own job security, and then from the needs of the
organization. Employee’s concern zone is limited to their
projects or working teams, and thus they fail to connect to
the big picture that the senior management is able to
envision.
Managers need to define the change for the employee in as
Save Earth, Go Green
Top reasons and remedies for employee
dissatisfaction during an organizational change:
Lack of a shared vision 1
much detail and as
early as possible.
Updates should also be
provided as things
develop and become
clearer. The reason or
rationale for change
must be passed to
every single employee
constantly and
consistently.
Employees should be
able to see the clear
objectives to be
achieved by the
company wide changes.
Along with the change, comes the team alignment shifts.
Employees may have new managers, new leadership, team
members, policies, processes, locations or alterations of
working hours.
Implementing change in an organization forces people to alter
how they relate to one another. Not only do their goals,
processes and equipments change but the way they deal with
others in the organization changes. It causes anxiety, which
leads to resistance to the change.
Lack of support, training and guidance 2
P7
Save Earth, Go Green
One way to counter this is through communication and
education. The top management should instil the need of
change with frequent and early communication to the
employees. Managers should minimize uncertainties by
addressing the employee’s needs and talk about any fears
or concerns with the employees. They should educate their
employees to be “change-ready” as it serves two broad
purposes. First, it enhances employee’s understanding of
the organization’s business so that they comprehend both
where and why change is necessary. Second, education
provides employees with the necessary skills to implement
change.
Loss of direction 3
Often during a change, there is chaos and uncertainty
regarding the to-be policies and new processes. Old
policies may need to be replaced, while the new policies
and process are still not developed. This can cause
confusion in the mind of employees and they feel that
nobody is caring for them with respect to their self growth,
both in monetary and professional terms.
If senior managers can put these processes and new
structures into place early in the change process, the rest
of the change implementation will proceed more smoothly.
As a direct manager, it is important to empathize and
listen to your people so that you understand their fears and
work to address them.
Lack of employee participation 4
Often after the initial announcement of a big
organizational change, the senior management often delays
to present the ancillary plans. They might take a long time
to create a final structure which they think is more
appropriate for sharing with the employees. But a
prolonged roll-out can also exacerbate staff uncertainty
about the future; heighten anxiety, and lower morale. This
leads to a communication gap between them and the
employees, who feel that they do not have any say or
inputs in the supporting decisions. Faced with forced
change, many employees feel threatened and believe that
they will lose power, prestige, competence, and security.
They feel that the situation is beyond their control and
they fear the process.
Here, employee participation is necessary to keep them
engaged with the changes. Employees should be
encouraged to participate, as this will give them a sense of
ownership in the process. Involvement in formulating the
proposals to implement change as well as participation in the
task forces reduces the fear of the unknown and leads to
commitment.
Disengagement 5
Employees need to know what is expected of them. They need
to believe that their needs are important and their value is
acknowledged. They need to know how to contribute and
remain involved in organization.
Organizations cannot afford to lose their skilled employees by
causing them to disengage from the organizational changes.
Managers should do their part in keeping their employees
engaged and they should find projects which justify their skill
set and experience. Employees should not feel that their skills
and abilities have been devalued by the organization and
managers should provide meaningful work to all employees.
Weak leadership 6
To drive organizational change, one needs a very skilled and
matured set of leadership. Often it seems that people are
promoted on a criterion not at all related to the skills needed
to drive this change. This can be a serious mistake and can
jeopardize the organizational change efforts.
Serious consideration and thoughts should be given to the
drivers of these changes – the top management. They should
either have had extensive experience in handling such
changes or must have previously shown their capabilities in
such situations.
Indifference to the change and loss of productivity 7
When people are forced to embrace change or do not see any
benefits for them in the change, the quality of human capital
deteriorates. Highly energized employees start to lose their
passion and stop applying themselves to the process. They
become distracted and lose interest in their current work
responsibilities. Hence a very motivated employee becomes
an indifferent employee. In the worst-case scenario, the
valued employees leave the organization.
A rewards and awards programme is an important binder for
the change drive. An organization should properly
acknowledge and appreciate its people for their support for
change and constantly encourage them for their inputs in the
process and make sure that their voices are heard by the
senior management.
P8
Save Earth, Go Green
It’s not only the change that people resist, but the
method of the organization’s change management.
Leaders need to identify the business imperative,
communicate the vision, establish the parameters, and
create a supportive environment with the employees so
they understand what is coming and what it means for
them.
As an employee, you have a choice. You can lie back and
have it thrust upon you, whether you like it or not, or
you can try to participate in that change and therefore
have an input into its design and outcomes, to move the
organization towards the goal.
Quiz
P9
By – Abhijit Bharatkumar
Answers to quiz – SYNERGY 4th Edition - http://www.pminorthindia.org/Synergy/Issue04/
1-b, 2-b, 3-d, 4-d, 5-d
No winner for fourth edition
To generate interest and increase the readership along with participation of members, Quiz has been
designed based on the articles published in this edition. To attempt and Win a prize, please read all articles
carefully. Do send your entries ([email protected]), support your SNERGY…
First 3
correct entries will
win a prize
References: Joanne Mowat, The Herridge Group – Managing Organizational Change F. John Reh – Managing Change: Managing People’s Fear
As a manager, you also have a choice. You can either be blind
to the various employee-perspective challenges that any form
of change management brings or alienate your employees, or
you may acknowledge and work together these human
components of the corporation to build a healthy and
profitable enterprise that best survives and flourishes in the
ambiguity of change.
Ms. Anju Agarwal Project Manager
Stryker, New Delhi
Anju has 13+ years of experience in IT. She has worked in various domains like Insurance Sector, Media Industry, Fleet Tracking and Medical Industry etc. Currently she is working as a Project Manager, responsible for designing and developing end to end IT solutions. She had worked in the technical role for more than 10 years and still cannot resist the temptation to fix errors in a team member’s code.
She is an MCA and a certified PMP. She is a passionate Project Manager, who would love to see a world where people acknowledge the work of PM's and would fully understand the significance of this role.
About Author
P10
Managing Complex Business Deliverables in Projects
A. I only B. I and II only C. I, II and III D. II and III only
Organizational Change – What’s in it for me?
Project Management Office – An Integrative Approach
Save Earth, Go Green
Question 3 Which of the following is NOT a part of emotional intelligence?
Question 4 According to article, which of the
following is NOT a reason for employee dissatisfaction during
organizational change?
A. I only B. I and II only C. I, II and III D. II and III only
Question6 According to the article, which of the following is NOT a step that helped CDAC, Noida to achieve Capability Maturity Model Integration Level 5
index rating?
Question 5 Which of the following is usually NOT
a function of the Project Management Office (PMO)?
A. Understanding employee emotions B. Facility with words and languages C. Motivating employees and executing employee engagement D. Recognizing emotions in team members
A. Lack of a Shared Vision B. Lack of infrastructure C. Lack of Support, Training and Guidance D. Indifference to the change and Loss of Productivity
Question 1 Which of the following activities can be considered project management? I – Quality control of an automobile manufacturing plant II – Budget setting for the next financial year of a venture capital firm. III – Construction of a new tower for a cellular communications company
Question 2 Which of the following statements are true in regards to Risk Management? I – The risk register is the detail documentation of all risks associated to a particular project II – Risks always have a negative impact and not a positive one III – Risk Management is an active part in overall project management
A. Appointing the chief executive officer for the organization B. Providing expert judgement when required C. Act as a hub of central co-ordination of all projects D. Can also be responsible for direct management of a project
A. Appointing the chief executive officer for the organization B. Providing expert judgement when required C. Act as a hub of central co-ordination of all projects D. Can also be responsible for direct management of a project
5th Edition Quiz
Save Earth, Go Green P11
Cash Flow Management in large Infrastructure Projects
Question 7 Which of the following is NOT an element of Cash
Flow Management
according to the article?
Rigidity to Agility - A Case Study
A. I – II – III – IV – V B. I – II – V – IV – III C. II – I – V – IV – III D. II – I – III – IV – V
Question 9 Which qualities one should imbibe
to adopt Agile?
A. Estimating costs of different packages B. Predicting the timing of cash outflow C. Generate product sales for required cash generation D. Monitor the actual cash outflow
Question 8 Accordingly to the article, some of the processes required for efficient management of funds are listed below. Please suggest the correct order. I - Identification of cost heads II - Calculate the Cash Outflow based on estimated cost III - Calculate the Cash Outflow based on actual ordered cost and scheduled progress IV - Prepare contingency plan to minimize the deviation V - Monitor the actual cash outflow
A. Transparency, Centre of Importance B. Truth, Honesty & Trust C. Being bossy, Me & Myself over team D. Lies, Dishonest & Distrust
A. 357,000 B. 412,000 C. 288,000 D. 734,000
Question 10 How many dollars did we save by saving man-hours in transforming to Agile?
By - Father of Nation -Mahatma Gandhi
Food for Thought
It’s easy to stand in the crowd but it takes courage to stand alone.
Mr. Abhijit Bharatkumar
Siemens, India
Abhijit is trained as a mechanical engineer from NIT, Bhopal
and works as an Executive in Siemens, specializing in Piping
& Plant design for the world's most efficient natural gas
based power-plant projects.
He has worked on projects in Germany, Oman and South
Korea, as well as several standardized power plants for
Siemens and has worked in India and Germany. Apart from
Project Management, his other interests include finance and
travelling.
About Author
Save Earth, Go Green
Rigidity to Agility - A Case Study
By – Prashant Malhotra
technology, which is expanding multi-fold, there is always
a threat from new or existing competitors in the market.
Customer loyalty may start shifting and they would think
twice on buying your products if they get better bargains.
How does one survive in such an environment where you
need to produce better, faster & cheaper products?
Companies till now had formulated strategies to meet at
least one end of this triangle i.e. either by producing
cheaper products through mass production or outsourcing,
producing better products by investing in vendors &
employees etc. or by being ‘The First One’ to market. For
past couple of years, companies have been revisiting their
strategies as they could easily see the scope of meeting at
least two corners of the better-faster-cheaper triangle.
And with this, we saw the emergence of Agile
In IT world, everybody nowadays is talking about Agile. In
current scenario, if you don’t know Agile; people would see
you as if you have just arrived from 18th century. Agile has
many avatars and had been surviving in this world since
1950s. As this was the buzz word, we too wanted to be
AGILE by snapping of our fingers in our organization but
this was not sufficient. In order to transform ourselves into
agile, we first went through white pages, articles & blogs
by Agile Gurus. Then, to get a good grasp of the real
potential & contribution of Agile, we attended multiple
conferences, webinars too.
Our immediate manager showcased the potential of agile
to management and finally our management agreed upon
to do a pilot run. Below is a case study wherein, we would
like to present some facts as how our transformation to
agile improved our results.
A s the world grows leveraging the power of
History
The product roll-out used to happen once a year. Then as
competition grew; there arose a need to deliver the
product frequently and yet meeting the quality. The below
project management triangle always plays a role, no
matter what methodology you follow.
The product team had been working in waterfall methodology
for a century or so. From
application architects,
database administrators to
application developers,
testers & support
engineers; everyone
played a critical role at
various phases of the
project lifecycle.
Journey
The biggest task for anyone in adopting Agile was, is & will be
“Changing of Attitude from I, me & myself to We & Ours”.
Truth, Honesty & Trust are valued very high instead of hiding
key facts to remain center of importance or Mavericks.
With agile coming in, the focus was to equip all team
members with attitude as “Jack of All, Master of Some”.
Resources were encouraged to share the knowledge
overcoming their false loss of importance to product; as
transparency was the most important aspect. Fault
acceptance attitude was given more importance instead of
blame games. Walls were covered with Whiteboards that also
acted as status-boards to give a clear picture to everyone on
the progress & hurdles from letting the team move forward.
Each & every Enhancement Request that spanned across
multiple months was broken down to multiple tasks that could
be covered in least possible time. The bridge of trust was
built from both sides (Management & Team) as being a
product team and estimations were taken from team members
directly. The team members automatically turned personally
responsible & accountable for delivery. There were separate
tasks opened up for R & D which were earlier part of a feature
request. Buffer time which was one big culprit in any project
would now no longer exist either at management’s end or at
team’s end.
P12
Overhead by -Kumar Saurabh, PMP®
Project Management – lighter side
If you perceive that there are four possible ways in which a procedure can go wrong, and
circumvent these, then a fifth way will promptly develop.
Save Earth, Go Green
Below depicting an old work flow using a waterfall method.
With agile coming into practice; the above cycle saw a
change. With newer approach, we broke the big features &
phases to smaller ones. As the deliverables became
smaller, quality team involvement commenced from
understanding the requirement till delivery. Many implicit
requirements that slipped through the cracks during design
& development phase were caught right up front and were
explicitly made part of overall scope.
Below is the diagram that depicts a smaller cycle as
compared to the entire phase.
New work flow
Old work flow
Results & Measure –
Good or excellent are qualitative attributes to a result of
task performed but these can be interpreted in different
scale & style from person to person as each has his or her
own definition or perspective. But if you show numbers
such as 3 out of 5, or let’s say if 4 out 5; people can easily
understand as good or excellent respectively.
So, no matter what you do, how good you do & even if it’s best
for you, your team or company; nothing counts or matters if
the results cannot be quantified. So, in order to measure as
what’s done now versus what’s done earlier; we started
analyzing data from our bug tracking software.
77%
23%
RootCause
Coding Error
Non Coding Error
58%
42%
RootCause
Coding Error
Non Coding Error
Earlier
Current
The above diagram clearly shows that there has been a
noticeable change between ‘Coding’ & ‘Non-Coding’ errors.
Non-Coding errors have increased by about 17%. When we
went deeper, we found that Requirements & Design errors had
increased quite a bit (as seen in the below diagram).
77%
5%
11%
7% RootCause
Coding Error
Enhancement Requests
Design Error
Requirements
58%
4%
21%
17%
Root Cause
Coding Error
Enhancement Request
Design Error
Requirements
Earlier
Current
This made us curious to understand the real root cause of
such a change in numbers.
Results
Results
P13
Save Earth, Go Green
Upon analyzing, we came across that introduction of quality
/quality team member right in the beginning transformed
implicit requirements to explicit ones. Their way of looking
upon the functionality & technicality of a piece with the
entire system in background made the product owners &
designers revisit their work to incorporate every aspect
before handing over to the team to start off construction or
task.
The above results were something that we noticed in our
product delivery cycle in a one year period. The results may
depend & vary from product to product & service to service.
After the results were quantified, transforming these
numbers for management to comprehend was the next big
step. So, we thought of two ways through which we could
collate results in dollar value –
Saving of man hours to deliver workable software 1
We calculated & compared costs incurred in delivering the
software and we saved approximately 24% of man hours on
yearly-product cycle basis. Converting man hours into
dollars were put to management. In our case, we were
around 20 resources across the globe and if average
resource is $30 an hour; we saved approximately $288K for
this year.
Reducing the cost of fixing a bug
2
It is a well known fact that cost of fixing a defect at an
early stage is always lesser than at later stage as depicted
in the below diagram.
For this, we took numbers reported by bug tracking software
and approx cost of fixing a defect in various stages of SDLC.
To ease our calculations, below is the table that we can use
as reference point –
Requirement
Design
Development
Test
Customer
Time
$ d
ollars
500
450
400
350
300
250
200
150
100
0
SDLC Phase Cost of Fixing ($)
Requirements 100
Design 200
Development & Testing 300
Let’s assume that there total 100 bugs (earlier cycle &
newer cycle), so cost of fixing would come out to be –
SDLC Phase # of Bugs Cost ($) Total Cost
($)
Requirements 7 100 700
Design 16 200 3200
Development & Testing
77 300 23100
Grand Total ($) 27000
Old cycle
New cycle
SDLC Phase # of Bugs Cost ($) Total Cost
($)
Requirements 17 100 1700
Design 25 200 5000
Development & Testing
58 300 17400
Grand Total ($) 24100
From above calculations, its turns out that we saved approx
$2900 for every 100 bugs; the real figures would definitely
be on higher side in a highly evolving product cycle.
Time to market
3
Market growth is something we couldn’t really put into
dollar value but was easily accepted by our management.
Turning agile gave advantage to change our direction on
the fly based on market sentiments. We could now easily
maneuver to meet the ongoing changes in expectations of
customers. Customers were happy and ready to shell in
extra dollars as we helped them remain in competition by
using our fast evolving product.
P14
By - Father of Nation -Mahatma Gandhi
Food for Thought
Work is a means of living, it is not life itself.
Save Earth, Go Green
The management saw the benefit and praised us and is
now buying in arguments easily on being agile, but we still
feel we have a long way to go as, still some features of
ours expand over months as partly delivered features
doesn’t add value to base product.
And obviously the other part is Reward. We got rewarded
by another product transformation which is bigger,
complicated.
Project Management Office --- An Integrative Approach
By – Shalu Gupta & R.T. Sundari
nerve of the any organization. Any project starts and ends
with PMO. In projects like infrastructure or product
development the right material used at the right time
constitute 70% of the project execution, where as in IT
projects Human resource utilization is the major that helps
the project delivery in time and within the budget. This
article highlights effective implementation and integrated
approach to PMO in organizations, by taking reference to
such practice adopted in CDAC, Noida.
Control Tower. It is therefore important to consult entire
stakeholders to implement PMO effectively within the
organization.
P roject Management Office (PMO) is the central
Integrative approach of PMO
PMO is constituted to help the project group to plan and
manage the project. The role of PMO should have an
integrated approach based on the nature of projects
running in the organization, be it, Weather Station or
The objective of the restructuring of PMO is to improve project
delivery in terms of schedule, budget and quality. To achieve
the objective we have selected the cross breed of Weather
Station and Control Tower.
Merge QA with PMO: 1
The first step taken was to merge the Quality Assurance (QA)
with PMO. While PMO sets the process and method for project
execution, QA becomes the watch dog in process adherence.
QA has dual responsibility of the project and process audit.
P15
Mr. Prashant Malhotra
Project Manager
Aspire Systems
Prashant has 12+ yrs of work experience in IT, having cross
functional experience in domain of CRM & CEM, HR (401K),
and Consultancy &Membership lifecycle. In addition to an
MBA from IIM Kozhikode in Finance & Operations, he is an
MCA; and currently working as a Project Manager delivering
end to end solutions. Building self propelled effective &
efficient teams is one of his mottos of life.
About Author
This product has more number of centers of development across
the globe as compared to current one.
With customized or hybrid approach, we have achieved such an
improvement; so the bigger question is, should we move
forward to pure agile? If yes, how much scope of improvisation
should we expect? Should we jump onto second product or
should we first transform the first product fully? Any input,
comment or response is more than welcome.
Save Earth, Go Green
Project performance data and reports are collected by QA
using various innovative tools and submitted to PMO, who
manage the resource allocation and priority issues with the
help of data.
Stakeholder in Projects 2
The turf wars between PMO and project manager that
usually arise when the Control Tower PMO is implemented.
To minimize conflicting roles, the Program Managers are
brought into PMO fold to head the different project groups.
PMO become one of the stakeholders in all projects.
The existing structure consisted of groups organized around
technical groups like Health Informatics, e-Governance,
Language Technology and Embedded Systems. Project
teams were formed within these groups, who were
responsible for design, development, testing and
implementation. This resulted in more emphasis on coding
and little importance was given to design, testing and
documentation. A root cause analysis of the above problem
brought out that it can be solved only with the proper
restructuring of the existing system.
How we did it…
Accordingly a restructuring strategy was adopted by which
the existing groups were demolished paving way to creation
of four verticals viz. Implementation, Design, Development
and Testing. Due to this structure, the documentation has
become a MUST. It became a deliverable from one vertical
to the other.
•Code
•Unit Testing
•System Integration Testing
•HLD
•LLD
•SRS
•Client CR
Implementation Design
Development Testing
The Functional Organogram
Centralized Repository 1
The Centralized Repository of all project documents and
codes was created with PMO having an administrative
control. The baseline documents were uploaded in project
repository for the stakeholders to use. This enabled the
project managers to monitor the activity systematically. The
centralized repository helps in reducing the non-availability
of project related documents.
P16
By - Father of Nation -Mahatma Gandhi
Food for Thought
There is more to life than simply increasing its speed.
Implementation Team: Responsible for interaction with
the customers for understanding and freezing the
requirements. They prepare the Software Requirement
Specification (SRS) and submit it to the Design Team for
designing.
Design Team: Responsible for creating High Level Design
(HLD) and Low Level Design (LLD) and their review by the
Review Committee before they are handed over to the
Development Team.
Development Team: Responsible for Coding and Unit
Testing and generating Test Reports.
Testing Team: Responsible for System Integration testing
and generating Test Reports.
Save Earth, Go Green
Coordination and Communication 2
Coordination and Communication between different
functional units were routed through PMO. Based on the
functional area, the new and existing projects got
registered in PMO after filling the project registration form.
Schedule and Cost Estimation 3
The projects schedule and cost were estimated based on
functional area and timeliness. As per estimation of
resources projects cost were segregated among different
functional areas. This helps PMO in monitoring the projects
by each functional area in terms of schedule, cost and
resource utilization.
Monitoring and Control 4
The processes carried out in the organization were
mentored by experts and trainings were provided to
functional area team members leading to effective
implementation of processes in the organization. PMO could
track and control all deliverables of projects.
Benefits achieved
The vertical functional group and horizontal project team of
matrix helped us to speed up our journey towards CMMI Level
5 and finally achieving it..!!
Some of the benefits obtained by restructuring and
implementation of PMO include:
Improvement of project management practices in the
organization.
Reduction in cost and schedule overrun by accurate
evaluation of the schedule and cost estimates.
Improved utilization of resources by centralized allocation
of manpower and resources.
Improved historical data collection for future projects by
better documentation processes.
Increased customer satisfaction through quality and timely
delivery of the projects.
P17
Ms. Shalu Gupta Senior Technical Officer
C-DAC,Noida
Ms. Shalu Gupta, is working as Sr. Technical Officer ’in C-DAC
Noida. She is PMP certified. She has nine years of experience
in software development. She has worked in the field of
NMS, SNMP, Optical comm., DSLAM OCR and Quality
Assurance. She has worked in various companies like C-DoT,
Wipro Technology and Flextronics Software Systems.
Currently she is associated with the Quality Assurance Group.
She has published 9 international and national research
papers. Her area of interest includes Software Quality
Assurance and Software Metrics.
About Author
R.T.Sundari is working as a consultant in C-DAC
Noida. She has a post graduation in management and
more than 30 years of experience in designing,
development, testing and quality assurance. She has
published 5 national research papers. She is currently
heading the PMO and Quality assurance division.
Ms.R. T. Sundari Consultant
C-DAC,Noida
About Author
Save Earth, Go Green
Best Practice – Quality Assurance Maturity
By – Chetan Mathur
but indispensable component of Project Management.
Essentially comprising of three vital components, quality
management flows top-down within an organization’s
hierarchy. This approach helps project managers understand
customer’s requirements precisely and consistently deliver
the key results that stakeholders expect.
Let’s look at the three vital areas of quality management:
Defining the organization’s vision in terms of delivering
quality – Quality Policy.
Q uality Management is often considered an overhead,
Common scenarios in Quality Management
– Defect Seepage
Increased go to production time performing additional
testing to conform to quality standards.
Fewer adherences to quality assurance process, thereby
releasing products with defects in testing / control
stage.
Defect seepage data is neither maintained nor managed.
Increased Cost – Cost of Non Conformance.
Process definition and
implementation to ensure
deliveries meet their
objectives – Quality Assurance
Make sure the results of what
has been developed are what
was expected – Quality
Control.
Clearly visible, the key
differentiator between QA and
QC is that while QA is process
oriented, QC is product oriented.
It is not an uncommon scenario whereby delivery
organizations are recalling their products from the markets
months after they have been delivered, now at a huge cost
incur – The reason - They failed to implement Quality
Management as a matured process in its essence and failed
to capture and correct the defects internally.
Approximate 60-70% of the defects are being captured
at QC stage or even after release.
Only 30-40% of defects are being captured internally.
Common Root Cause Analysis for Defect Seepage
Inadequate base lined standards being followed
Unit / Component Development Standards
Development / Production best practices
Performance Productivity Baselines
Unstructured Change Management Procedure
Unstructured Reviews being performed
Work In Progress Reviews
Document Reviews – Including Requirements Work
plan, Requirements Analysis Documents, Enterprise
Analysis, Design, Test Plan & Logs
Review checklists not base lined across the Enterprise
and made available as Organizational process Assets.
P18
By - Father of Nation -Mahatma Gandhi
Food for Thought
Satisfaction lies in the effort, not in the attainment. Full effort is full victory.
Save Earth, Go Green
Inadequate / Unstructured Testing performed:
Product Level unit testing
Integration testing
Regression / Negative testing
System Level Testing
Black / White Box Testing
Un-available / Un-structured Test Data.
Lack of detailed project planning
Project Reviews not defined / estimated.
Project re-work based upon reviews not defined /
estimated.
Others
Lack of organized team structure
Same resources shared across development &
testing teams.
Other than peer reviews, no cross team /
functional reviews performed
Others
Lack of documentation
Project Plans not being developed, reviewed,
approved and base lined.
Test Plans, Test Cases, Test Logs and Test Data
not developed, reviewed, approved and base
lined.
Configuration Management not implemented
across the projects.
15
12
16
9 10
8
12 10
8
0 2 4 6 8
10 12 14 16 18
Percentage Wise Pareto Analysis
Percentage Wise Pareto Analysis
Defect Level Pareto Chart
Best practices for QA maturity
Development standards to be a derivative of best practices
and industry standards.
Development standards should be base lined either across
enterprise or for a customer or across a vertical. This should
be done in order to.
Avoid conflicts during implementation.
Create synchronization between reviewer and
developer.
Optimum utilization of man-power.
Save duplicate work / repetition cost.
Formalize Change Management Procedure and make the
customer / Delivery teams / Vendor / Partner aware of the
same.
Formally Release Change Management procedure.
Conduct training sessions across stakeholder groups for
change management.
Track and report changes and change parameters.
Do Not Gold-Plate.
Structure & Formalize Reviews
Formally Release Review checklists for Component /
Unit and Document Reviews – Including Requirements
Work plan, Requirements Analysis Documents,
Enterprise Analysis, Design, Test Plan & Logs
Conduct training sessions across stakeholder groups for
necessity and usability of the checklists.
Track and report checklist compliance across projects.
Review teams to be
structured separately
than the development
teams.
Reviews & associated
Re-work to be estimated
and workforce managed
separately from
development.
Stages of reviews to be
planned including Peer,
Functional, Cross
Functional, Quality just
to name a few.
Have a “Review” Center
of Excellence in place.
P19
Save Earth, Go Green
Structure & Formalize Testing
Requirement Traceability across all testing
stages to be maintained.
Test Plans, Test Cases, Test Data and Test Logs
to be reviewed and review logs maintained.
Automation testing tools to be used as far as
possible.
Testing teams to be structured separately than
the development teams.
Testing to be estimated and workforce managed
separately from development.
Have a “Testing” Center of Excellence in place.
Implement Release, Problem and Configuration
Management.
Develop Requirements Work Plan – Make sure no
requirements fall through the cracks. Maintain
Requirement Traceability across the life cycle of the
project.
Conclusion
Quality assurance (QA) consists of a means of monitoring the
engineering processes and methods used to ensure quality.
The purpose of Quality Assurance is to define and implement
the techniques, procedures, and methodologies that will be
used to assure timely delivery of the application / product
that meets specified requirements within project resources.
With a focus on improved Customer Satisfaction and
enhanced business opportunities, a matured QA process aims
at controlling defect seepage and enhancing the percentage
of defects detected internally before being released to
production to close to 80-90%.
An un-matured QA Process
A matured QA Process
35%
65%
Defected detected before being released to Production
Defects detected post Release
85%
15% Defected detected before being released to Production
Defects detected post Release
P20
Mr. Chetan Mathur Asst. Director - IT
Sistema Shyam Teleservices Limited (MTS
India)
Chetan has rich 16 years of experience in End to End Program Delivery. He is a certified PMP and is also certified on ITIL and eTOM best practices and a member of IIBA and is a nominated Champion by PMI India. He has managed and delivered various end to end projects and programs from RFP, Discovery, Due-diligence, Transition (KT, Shadowing, and Reverse Shadowing), Transformation (Analysis, Design, Development, Testing & Implementation) to Application Support & Maintenance phases.
Chetan has been managing large teams and multiple projects, ensuring deliveries are completed on time & within budget and in strict compliance with quality systems/procedures in an onsite offshore model.
About Author
Save Earth, Go Green P21
Past Events:
25th
March’2012
13th
– 15th
April
Chapter Networking / Knowledge Sharing Event at Jaipur, Rajasthan
Rajasthan Chamber of Commerce & Industry Sukhadia Bhawan, M.I. Road, Jaipur
“21”
PDUs
“4”
PDUs
PMI Agile Certification Training Workshop
On 25 March, the chapter held “Project Management:
Infrastructure and IT Projects” in Jaipur, Rajasthan. In an
effort to conduct effective discussions on infrastructure
projects, the chapter invited senior officials of the Rajasthan
government. Mr. Vinod Garg, managing director, PROMAC,
commenced the event, followed by an address by Mr. Manoj
Gupta, president, PMI North India Chapter. Mr. Rakesh Verma,
IAS, principle secretary, Planning Department, Rajasthan
Government, was the chief guest and Mr. Atmaram Gupta,
chairman, Federation of Rajasthan Trade and Industries, was
the guest of honor.
Highly experienced Subject Matter Experts participated in a
panel discussion on “The Importance of Standard Practices for
Efficient and Effective Completion of Infrastructure
Projects.” The panelists were Mr. Mukund Joshi, chief
engineer, Central Public Works Department – North Zone - III;
Brig. Balbir Singh, additional command chief engineer,
Headquarters, South Western Command – Indian Army; Mr.
Puneet Mittal, managing director and CEO, Pratham Software;
Mr. Alok Ranjan, chairman, Indian Institute of Architects,
Jaipur Chapter; Mr. Tushar Sogani, secretary, Indian Institute of
Architects, Jaipur Chapter; and Dr. Vanita Ahuja, assistant
professor, Gautam Buddha University, Greater Noida. Mr
Hemant Seigell shared Risk Management Best Practices.
Panel Discussion
Chief Guest Welcome
The two and a half day training, conducted by Mr. Hiren Doshi, trainer, Practice Agile, served as a primer for those
involved in teams adopting agile techniques or those planning to take the PMI Agile Certified Practitioner (ACP)
examination.
Watch out this space for upcoming events. Be involved
Past One Year, Authors Felicitation
Save Earth, Go Green
http://www.pminorthindia.org/Synergy/Issue04/
http://www.pminorthindia.org/Synergy/Issue03/
http://www.pminorthindia.org/Synergy/Issue02/
http://www.pminorthindia.org/Synergy/Issue01/
P22
SYNERGY First Edition SYNERGY Second Edition
SYNERGY Third Edition SYNERGY Fourth Edition
Mr. G Ravi Mr. Kumar Saurabh Mr. Nirmallya Kar Mr. Amit Tambi Mr. Maneesh Dutt Mr. Navin Das Ms. Archana Sharma Mr. Hemant Seigell Mr. Piyush Govil
We are grateful to you to nurture SYNERGY to 1 year old…
Mr. G Ravi Mr. Kumar Saurabh Mr. Nirmallya Kar Mr. Maneesh Dutt Ms. Pauline Jacqueline Mr. Prabhu Jha Mr. Tathagat Varma Mr. Hemant Seigell
Mr. Piyush Govil
Ms. Vidhi Singh Mr. Vikas Dua Mr. Chetan Mathur Mr. Hemant Seigell Ms. Pauline Jacqueline Mr. Suhail Qadir Mr. Anshul Chetal Mr. Kumar Saurabh
Mr. Piyush Govil
Mr. Prashant Malhotra Mr. Vikas Dua Mr. Chetan Mathur Mr. Asim Prasad Mr. Arun Gupta Mr. Abhijit Bharatkumar Ms. Vanita Ahuja Mr. Kumar Saurabh
Mr. Piyush Govil
Previous Editions
Special thanks to Mr. Pritam Gautam – VP Technology - PMINIC for publishing every edition on Chapter Website.
Save Earth, Go Green
Editorial Team
Piyush Govil Manoj Gupta Kumar Saurabh Nirmallya Kar
Hemant Seigell Abhijit B Kumar Jitin Bindlish
Felix George Pooja Kapoor Nitin M Singh Prashant Malhotra
PMI North India Chapter
http://www.pminorthindia.org
Editorial Team welcomes Articles, Case Studies, White Papers, etc. for their
ongoing endeavor.
We always welcome suggestions or ideas for improvement.
Kindly submit at
Renew your membership today
visit chapter website
http://www.pminorthindia.org