system capacity assurance plan - project win > homemsdprojectwin.org/portals/0/library/overflow...

38

Upload: lamnguyet

Post on 18-Jul-2018

212 views

Category:

Documents


0 download

TRANSCRIPT

System Capacity Assurance Plan

Revised January 2010 i

TABLE OF CONTENTS

LIST OF APPENDICES ...................................................................................................................ii

BACKGROUND AND SUMMARY ..................................................................................................1

Organization of Report ............................................................................................................................ 3

SECTION 1 INTRODUCTION AND SYSTEM CAPACITY OVERVIEW .....................................1

1.1 INTRODUCTION .......................................................................................................................... 1

1.2 SCAP PURPOSE ............................................................................................................................ 2

1.3 CAPACITY ASSURANCE INFORMATION MANAGEMENT................................................................ 3

SECTION 2 SYSTEM CAPACITY PROTOCOL .......................................................................1

2.1 SYSTEM CAPACITY MODELING AND MONITORING ...................................................................... 1

2.2 WATER QUALITY TREATMENT CENTERS (WQTC) CAPACITY PROTOCOL ....................................... 2

2.3 WASTEWATER COLLECTION CAPACITY PROTOCOL ...................................................................... 3

2.4 PUMP STATION AND FORCE MAIN CAPACITY PROTOCOL ............................................................ 4

SECTION 3 CAPACITY CERTIFICATION DETERMINATION PROCEDURES ............................1

3.1 CURRENT, COMMITTED, AND REQUESTED CAPACITY .................................................................. 1

3.2 MSD SYSTEM CAPACITY ASSURANCE PROCESS ............................................................................ 2

3.2.1 Step-By-Step System Capacity Assurance Process ....................................................................... 2

3.2.2 Response .................................................................................................................................... 5

3.2.3 Jeffersontown Water Quality Treatment Center.......................................................................... 7

3.2.4 Sanitary Sewers Located in the Combined Sewer System ............................................................ 7

3.3 LOJIC GIS AND HANSEN IMS ........................................................................................................ 7

SECTION 4 APPROVAL THROUGH CREDIT BANKING PROCEDURES ..................................1

4.1 CREDIT BANKING SYSTEM ........................................................................................................... 1

System Capacity Assurance Plan

Revised January 2010 ii

4.2 SPECIAL CONDITIONS .................................................................................................................. 2

4.2.1 Certification Exceptions .............................................................................................................. 2

4.2.2 Redevelopment of Existing Facilities ........................................................................................... 2

4.3 APPROVAL THROUGH CREDITS BANKING PROCESS ..................................................................... 3

4.3.1 Step-by Step Credits Banking Process .......................................................................................... 3

4.3.2 Inflow and Infiltration (I/I) Surcharge .......................................................................................... 4

SECTION 5 – STANDARD PROCEDURES FOR CALCULATING AND TRACKING FLOW CREDITS ......1

5.1 SEWER SYSTEM REHABILITATION AND I/I REMOVAL ................................................................... 1

5.2 ESTIMATED FLOW REDUCTION FROM SYSTEM REHABILITATION ................................................. 2

5.2.1 Manhole Rehabilitation............................................................................................................... 2

5.2.2 Removal of Illicit Connections to the Sanitary Sewer System ....................................................... 3

5.2.3 Rehabilitation of Deteriorated Mainline Sewers and Sewer Service Lateral Corrections............... 4

5.3 CREDITS CALCULATION ............................................................................................................... 4

5.4 ENTERING AND TRACKING CREDITS IN HANSEN IMS ................................................................... 5

LIST OF APPENDICES

Appendix A – Lateral Extension Procedures, Forms, and Process

1. Lateral Extension Just In Time Submittals Process 2. Lateral Extension Procedures Description 3. Downstream Facilities Capacity Request Form 4. Hansen LE Request Data Entry Process

Appendix B – Treatment Center Capacity Reports

1. WQTC Permitted ADFs and Designed Peak Capacities

Appendix C – WQTC Current Capacity, Projected and Pending Flow Reports

Appendix D – Pump Station Capacity Information

1. Master Pump Station Spreadsheet

System Capacity Assurance Plan

Revised January 2010 iii

2. Drawdown Test Form 3. Pump Station Prioritization Report

Appendix E – Pump Station Current Peak User Flow Calculation

Appendix F – Pump Station LE Reports through 12-31-09

Appendix G – List of SSOs and Abatement Projects (as of August 2009)

Appendix H – I/I Removal Capacity Credit Calculation Instructions and Examples

Appendix I – Available Capacity Credits by Catchment Area through 12-31-2009

Appendix J – Hansen Capacity Credit Application Entry Instructions

Appendix K – Credit Balance Report through 12-31-2009

System Capacity Assurance Plan

Revised January 2010 iv

Acronyms & Abbreviations

ADF Average Daily Flow CFR Code of Federal Regulations CIP Capital Improvement Program CMOM Capacity, Management, Operations, and Maintenance CS Collection System CSO Combined Sewer Overflow EPA Environmental Protection Agency FEMA Federal Emergency Management Agency GIS Geographic Information System gpd Gallons Per Day I/I Inflow and Infiltration IMS Information Management System KDOW Kentucky Division of Water KPDES Kentucky Pollutant Discharge Elimination System LOJIC Louisville/Jefferson County Information Consortium MGD Million Gallons Per Day MSD Louisville and Jefferson County Metropolitan Sewer District O&M Operations and Maintenance SCAP System Capacity Assurance Plan SOP Standard Operating Procedure SSES Sanitary Sewer Evaluation Study SSO Sanitary Sewer Overflow Project WIN Waterway Improvements Now WQTC Water Quality Treatment Center WWP Wet Weather Plan

Definitions

Average Daily Flow (ADF) – This is the average daily flow at a water quality treatment center calculated using daily flow records from a 2-year window of water quality treatment center influent flow data.

Credit Catchment – Defined area of the sewer system where capacity assurance credits are tracked for the Credit Banking System.

InfoWorks Collection Systems (CS) – hydraulic modeling software developed by Wallingford Software used by MSD for collection system modeling.

MSD Development Team – The department within MSD’s Engineering Division responsible for reviewing and approving new development plans and requests for sewer system capacity.

System Capacity Assurance Plan

Revised January 2010 v

Peak Wet Weather Flow – The anticipated, calculated, or monitored maximum flow within the sewer system during an actual or synthetic rainfall event.

Surcharge Condition – The condition within the sewer when the water surface level is less than two feet from the manhole rim elevation. If the sewer system is in a residential area with historical capacity-related backup complaints, then a surcharge condition is considered to be a water surface level within five feet of the manhole rim.

Modeling and Flow Monitoring Basins

BB—Buechel Branch CC—Cedar Creek FF—Floyds Fork HC—Hite Creek HP—Hikes Point JT—Jeffersontown MC—Mill Creek MF—Middle Fork Beargrass Creek ND—Northern Ditch ORFM—Ohio River Forman PC—Pond Creek

Regional Water Quality Treatment Center (WQTC)

CCWQTC—Cedar Creek WQTC FFWQTC—Floyds Fork WQTC HCWQTC—Hite Creek WQTC JTWQTC—Jeffersontown WQTC MFWQTC—Morris Forman WQTC WCWQTC—West County WQTC

System Capacity Assurance Plan

Revised January 2010 E-1

BACKGROUND AND SUMMARY

In areas of Louisville Metro with separate sanitary sewers, sanitary sewer overflows (SSOs) occur because of aged pipes that leak when the system is overloaded from rainfall or due to illicit connections to the sanitary sewer system such as sump pumps, roof drains, and foundation drains. Although new connections do not contribute to the root causes identified for sanitary sewer overflows, they do contribute additional flow that utilizes available capacity in the system. Since system capacity deficiencies have been identified as the cause for a significant portion of wet weather overflows, it is important for Louisville and Jefferson County Metropolitan Sewer District (MSD) to have a program to ensure new connections do not cause or contribute to sanitary sewer overflows.

In accordance with U. S. Environmental Protection Agency (EPA) requirements, MSD developed a Capacity, Management, Operations and Maintenance (CMOM) program in May 2006. MSD’s CMOM Self-Assessment was conducted in an approach that exceeds the requirements of Paragraph 23(c) of the Kentucky Division of Water (KDOW) and EPA Region 4 August 12, 2005 Consent Decree.

The overall goal of the CMOM Self-Assessment Report was to determine if there are MSD programs or activities that should be recommended for improvement to enhance service or compliance performance and to recommend specific actions and an implementation schedule to complete the recommended improvements. Paragraph 23c of the Consent Decree listed nine areas to be scrutinized in the CMOM Self-Assessment (one of which being system capacity). CMOM states that the System Capacity Assurance Program (SCAP) should be the basis for applying capacity decision criteria to support each watershed’s community values. The process should include a programmatic approach for items such as: confirming available capacity of water quality treatment centers (WQTC), pump stations, and conveyance system; creating capacity credits; identifying hydraulic constrictions; and proposing capacity improvements that support interim and long-term performance objectives.

Required improvements to the sewer system to accommodate system capacity will take years to implement. While these improvements are being implemented, developers, individual homeowners, and other entities continue making requests for additional flows to the system. The CMOM Self-assessment specifies that MSD must respond to these requests for new

System Capacity Assurance Plan

Revised January 2010 E-2

connections to the sewer system and subsequent increases in flow through this SCAP.

The objective of the SCAP is to enable MSD to authorize new sewer service connections or increases in flow from existing sewer service connections while making system improvements that ensure no existing capacity limitations are exacerbated. As detatiled in the plan, MSD assesses the peak flow capacity of all major system components (collector sewers, interceptor sewers, pump stations and treatment centers) and reviews requests for increased flow to the collection system.

The SCAP is a living, dynamic document and will continue to change due to various components including, modeling improvements, map updates, Consent Decree program implementation, reporting automation, capital improvement projects, capacity requests, and other CMOM and MSD programs.

In addition, the plan outlines MSD’s procedure for authorizing additional flows through capacity-limited areas by removing infiltration and inflow from the system and creating capacity credits. This capacity credit banking through system rehabilitation is similar to approaches in other cities.

System Capacity Assurance Plan

Revised January 2010 E-3

Organization of Report

This SCAP report is organized into five sections as listed below.

Section 1 provides an introduction to the SCAP describing Louisville Metro’s sewer system, the SCAP purpose and goals, and an overview of MSD’s information management system (IMS).

Section 2 provides a description and background of the existing capacity in the collection system using the hydraulic models and monitoring. Section 2 also establishes capacity assessment protocols for all treatment facilities, pump stations, and collection lines. (Table 4.2: M-E-6 - Major Facility Capacity, and M-E-7 - Facility Capacity Protocol of the May 2006 CMOM Report.)

Section 3 details the current, committed, and requested flow methodology for system capacity as well as how LOJIC GIS and Hansen IMS will play a role in storing, tracking, and analyzing data related to system capacity. The main objective of Section 3 is to define the systematic process to determine current capacity limitations and the available capacity for the system to receive new flow. (Table 4.2 M-E-8 Current and Committed Capacity and M-E-9 Build-out Capacity of the May 2006 CMOM Report)

Section 4 describes a step-by-step process for situations where adequate system capacity cannot be certified. The Approval Through Credit Banking Process addresses how new flow can be authorized through a Credit Banking System.

Section 5 documents the standard procedures for calculating and tracking flow credits.. This section outlines procedures for estimating flow reduction from corrective actions, calculating credit, and entering and tracking credits in Hansen IMS. (Table 4.2: M-E-10 - Available Capacity Standard Operations Procedures (SOP) of the May 2006 CMOM Report)

System Capacity Assurance Plan

Revised January 2010 1-1

SECTION 1 INTRODUCTION AND SYSTEM CAPACITY OVERVIEW

1.1 INTRODUCTION

Louisville Metro has over 3,200 miles of sewer, approximately 500 miles being over 100 years old. Currently, MSD serves 220,000 customer accounts and 693,000 people. The collection system operated and maintained by MSD includes:

• 6 regional wastewater treatment facilities • 16 small water quality treatment centers • Approximately 300 pumping stations • Ohio River Flood Protection System, including 16 flood pumping stations and 29 miles of

floodwall

In areas of Louisville Metro with separate sanitary sewers, sanitary sewer overflows (SSO) occur because of aged pipes that leak when the system is overloaded from rainfall or due to illicit connections of sump pumps, roof drains, or foundation drains to the sanitary sewer system.

The Louisville Metro combined sewer system was built from the 1860s to the 1950s. Currently, there are 105 active combined sewer overflow (CSO) locations and on average will overflow 30 times per year. Additionally, during a year with above average rainfall, over 170 locations in the separate sanitary sewer system could overflow.

MSD has been pro-active and initiated a Wet Weather Abatement Program in 1989. The first goal was to identify potential overflow points in the combined sewers and in the fast growing sanitary sewer system. Both CSOs and SSOs occur most often during prolonged rain storms. On the wettest days, millions of gallons of diluted sewage are discharged to local streams.

MSD's Wet Weather Abatement plan included these measures:

• Adding storage basins to the combined sewer system • Cleaning sewers of excess sand, gravel and mud to increase carrying capacity • Removing unnecessary clean-water connections (downspouts and sump pumps) • Repairing sewer leaks that allow groundwater into the sewer system

System capacity assurance is an important component of MSD’s Project WIN (Waterway Improvements Now) initiative. Project WIN was initiated to address the challenges of improving

System Capacity Assurance Plan

Revised January 2010 1-2

Louisville’s water quality. To meet these challenges, MSD has embarked on a comprehensive sewer improvement program that will eliminate major sources of water pollution throughout Louisville Metro. MSD has already completed more than $1.4 billion in capital expansion and upgrades to wastewater and stormwater facilities, some of these accomplishments include:

• Reduced 300 sewer overflow points in the combined and separate systems • Installed solids and floatable controls at nearly all Combined Sewer Overflow (CSO)

locations • Separated 66,000 linear feet of combined sewers • Eliminated 44,000 septic tanks • Eliminated 275 small plants and pumping stations • Built and expanded regional wastewater treatment facilities

1.2 SCAP PURPOSE

The SCAP is the basis for coordinating capacity decision criteria for each sewershed within the separate sanitary system. Providing wastewater collection, conveyance, and treatment that meet the expansion needs of MSD’s customers, while protecting the environment and meeting regulatory requirements, are top priorities of MSD’s facility improvement and sewer capacity review efforts. .

Due to existing wet weather capacity limitations and the time it will take to implement a complete sewer overflow abatement plan, the SCAP is developed to enable MSD to authorize new sewer service connections or increases in flow from existing sewer service connections while making system improvements. These improvements will increase available capacity by removing I/I in accordance with the May 2006 CMOM recommendations, which state:

“Develop a System Capacity Assurance Program that implements the performance objectives that result from the Wet Weather Team and stakeholder group involvement in the development of the WWP. The System Capacity Assurance Program will be the basis for coordinating capacity decision criteria for each watershed. The process should include a programmatic approach for items such as: confirming capacity of plants, pump stations, and conveyance system; identifying hydraulic constrictions; and proposing capacity improvements that support interim and WWP performance objectives. Review current connection protocols with the Metro

System Capacity Assurance Plan

Revised January 2010 1-3

Government and modify, if necessary, plumbing permit process or MSD capacity certification process, to ensure that capacity assurance is incorporated into permitting process. Implement capacity certification process through System Capacity Assurance Program developed and updated under the supervision of a licensed professional engineer. Document and track using existing programs in Hansen.”

The capacity assurance process applies to the separate sanitary system and does not include the combined sewer areas. New development in the combined sewer area is addressed from a surface storm water perspective through periodic updates to MSD’s Design Manual.

The SCAP process includes a programmatic approach for items such as confirming capacity of treatment centers, pump stations, and conveyance systems; generating sewer capacity credits; identifying hydraulic constrictions; and proposing capacity improvements that support interim and WQTC performance objectives. The protocols and procedures for providing adequate average daily flow (ADF) capacity are not covered within this plan.

1.3 CAPACITY ASSURANCE INFORMATION MANAGEMENT

The protocols and procedures described within the SCAP require a significant amount of data management. Tracking this data along with process automation and standardization is vital to the success of the capacity assurance program and will be improved as the program evolves.

The capacity assurance program utilizes MSD’s current information management system (IMS), housed within Hansen, and the Louisville/Jefferson County Information Consortium (LOJIC) Geographical Information System (GIS) to track data and automate the processes outlined within the SCAP. MSD currently uses these systems to track existing, committed, and proposed flows as well as facilities and assets, capital projects, corrective actions (work orders), overflows and system deficiencies, and various other data sets relevant to system capacity.

Hansen IMS is utilized to track system capacity for treatment centers and pump stations, as well as capacity credits. These tools are utilized for a credit banking system as described in Section 4 to track both earned capacity credits from specific rehabilitation and capital improvement projects, and credit expenditures from approved increases or additions in wastewater flows.

System Capacity Assurance Plan

Revised January 2010 1-4

Data from the InfoWorks CS hydraulic modeling results are housed within the GIS displaying current sewer capacity and system deficiencies. The following is a list of the major datasets that are tracked and housed within the Hansen IMS. Staff will develop additional datasets as the SCAP is implemented in combination with the existing databases.

• Hydraulic modeling results – sewer surcharging and deficiencies • Sewer system monitoring data • Designed, measured, and calculated capacities for sanitary sewer system assets • Approved, committed, and pending requests for capacity • Certification and approval documentation • Sewer rehabilitation projects • Capacity credits accounting system

System Capacity Assurance Plan

Revised January 2010 2-1

SECTION 2 SYSTEM CAPACITY PROTOCOL

Although new sewer connections do not contribute to the root causes identified for existing sanitary sewer overflows (SSO), they do contribute additional flow that utilizes available capacity within the system and will make existing overflows worse. MSD must have a program to ensure new connections do not cause or contribute to sanitary sewer overflows, which can be achieved by sewer system rehabilitation and credit generation.

This section outlines the protocol for determining the current peak wet weather capacities for the wastewater collection system, pump stations, and the water quality treatment centers (WQTCs). These protocols, as well as associated data limitations, are discussed for each of the three system elements.

2.1 SYSTEM CAPACITY MODELING AND MONITORING

To analyze sewer system capacity, many complex factors must be evaluated for each type of facility or asset within a collection system under different scenarios. To accomplish this task, MSD has developed hydraulic models for its entire service area using InfoWorks Collection Systems modeling software. The goal of this modeling is to provide a computer model that mimics the function of the actual sewer system, including sanitary flow and I/I sources (as well as stormwater in the combined sewer area). The sewer system models contain pump stations, hydraulic structures, interceptors, and collector sewers1

The hydraulic models were developed using LOJIC GIS data, historical hydraulic models, as-built record drawings, survey data, and field data. The models were calibrated and validated using flow monitoring and rainfall data collected between January and June of 2007. Within the flow monitoring period, dry weather periods were used to develop average daily user flows while wet weather events were used to analyze collection system response to wet weather and to determine the impacts of inflow and infiltration (I/I). Once calibrated to dry and wet weather data, the models are used to assess existing conditions, qualify and quantify deficiencies, and serve as a tool for future planning and capacity assurance reviews.

within the MSD service area.

1 For the separate sanitary sewer system all collector sewers 8-inch in diameter or larger were included in the hydraulic models. For the combined sewer system all sewers 18-inch and larger were included.

System Capacity Assurance Plan

Revised January 2010 2-2

For the purposes of the SCAP, a 1.82-inch cloudburst2

storm event was chosen as the minimum level of protection and applied to the Infoworks hydraulic models to analyze system capacity. These model runs serve as the basis for analyzing current sewer capacity, along with pump station testing, run time monitoring, and flow metering throughout the system. The following sections describe how modeling data will be used to evaluate capacity at MSD’s water quality treatment centers, sanitary pump stations, and throughout MSD’s sanitary sewer collection system.

2.2 WATER QUALITY TREATMENT CENTERS (WQTC) CAPACITY PROTOCOL

Certification of adequate treatment plant capacity is critical because it confirms that at the time the WQTC receives the proposed increased flow, the WQTC will be in compliance for quarterly reporting, and that the new or increased flow will not result in bypasses or diversions prohibited by the National Pollutant Discharge Elimination System (NPDES) permits. Current peak treatment capacities and average daily flow (ADF) limits for MSD’s six regional WQTCs and 15 small WQTCs have been established. Wet weather capacity at each WQTC is determined using design data. ADF limits are established within each WQTC’s current NPDES permit. Appendix B lists the current WQTC capacities, which are reviewed and updated annually to evaluate capacity and report evaluation updates.

The existing wet weather flow at each WQTC is calculated using the hydraulic models with the peak design wet weather capacities coded into the model. For the purposes of the SCAP, a WQTC is determined to be at peak wet weather capacity when the hydraulic model shows a surcharge condition at the influent pump station or at manholes along the main interceptor leading to the treatment plant. A surcharge condition is defined as a water surface level less than two (2) feet from the top of the influent pump station wetwell or at a manhole (MH) rim along the main interceptor leading to the WQTC.

Current ADF is calculated using a 2-year window of WQTC influent flow data. This 2-year window of data is updated annually, every January, in Hansen. Between these updates,

2 A cloudburst event analysis for the Louisville area was developed using a statistical analysis of historical rainfall data using the methods explained in NOAA Atlas 14. This analysis also developed a typical storm distribution and duration (3 hours) for the Louisville area.

System Capacity Assurance Plan

Revised January 2010 2-3

committed and requested capacity from new flow customers are tracked within a database using an estimated flow of 290 gpd per single-family equivalent (see Section 2.2.1 below for further discussion). A WQTC is considered to be at ADF capacity when the calculated ADF plus the committed capacity equals or exceeds the permitted ADF. MSD also uses the ADF data for future flow forecasting and planning of WQTC upgrades.

2.2.1 Average Daily Flow Evaluation

According to the MSD Design Manual, the design of new infrastructure (collector sewers and small pump stations) is based on Ten State Standards at an average daily design flow of 400 gpd per single-family equivalent (100 gpcd X 4 people/house). This figure is highly conservative in that it is based on average household population sizes during the 1960’s and is intended to consider appropriate sizing for future development flows that could potentially enter the system as well as some degree of inflow and infiltration.

For offsetting flows from new capacity requests, MSD determined a flow that more accurately represents single family household discharges given current average household populations. In order to determine a more accurate average daily design flow per single-family equivalent, MSD researched U.S. Census data (Average household size = 2.37 persons, 2000 US Census data) and past studies (Saturation = 2.87 persons /dwelling, 1993 Floyds Fork Action Plan Study

Based on these studies, an average daily design flow of 290 gpd (100 gpcd x 2.9 people/house) has been determined to represent a more accurate, yet still conservative, wastewater production per single-family household. Therefore, to calculate the credits needed to offset new flows upstream of capacity limited areas, this factor of 290 gpd is used to scale the new development flows (see Section 4.1 for example calculation).

) for more accurate household numbers. Additionally, MSD reviewed influent flows at its regional treatment centers to evaluate these flows compared to design flows calculated from the corresponding contributing service area population.

2.3 WASTEWATER COLLECTION CAPACITY PROTOCOL

Certification of adequate collection capacity is critical because it confirms that each gravity sewer through which the proposed additional flow will pass has adequate capacity to convey both the existing and proposed peak wet weather flows from all new or existing service

System Capacity Assurance Plan

Revised January 2010 2-4

connections, without causing a surcharge condition.

The existing wet weather peak flow of the collection system is calculated and evaluated using the 1.82-inch cloudburst storm simulation within the InfoWorks CS hydraulic models. The models will indicate areas of surcharging during the design storm simulation. For the purposes of the SCAP, a wet weather surcharge condition is defined as a water surface level within the sewer that is less than two (2) feet from the manhole rim elevation. If the sewer system is in a residential area with historical capacity-related backup complaints then a surcharge condition is considered to be a water surface level within five (5) feet of the manhole rim. However, if MSD has, pursuant to the SCAP, identified pipe segments or manholes designed to operate under a pressure condition (such as siphons), then the capacity of these pipe segments or manholes shall be evaluated based on their design criteria.

The current design capacity of the collection system is determined using the hydraulic models. Using design standard calculations, if adequate capacity to convey the proposed new flow is not available, the customer requesting capacity and MSD must coordinate and determine the measures needed to provide adequate capacity for the proposed new flow. If the sewers downstream of the capacity request have adequate design capacity, but display wet weather issues, MSD must remove I/I from the system to create capacity credits.

2.4 PUMP STATION AND FORCE MAIN CAPACITY PROTOCOL

Certification of adequate pump station and force main capacity is critical because it confirms that each pump station and associated force main has adequate capacity to transmit the existing peak wet weather flow plus the proposed peak wet weather flow without causing a surcharge condition at the pump station or within the collection system served by the pump station.

The existing peak wet weather flow at each pump station is calculated and evaluated using the 1.82-inch cloudburst storm simulation within the InfoWorks CS hydraulic models. The hydraulic models contain information on all MSD operated pump stations and force mains, which are gathered through a combination of capacity measurements, pump run time analysis, and design data reviews. Using the hydraulic models to simulate pump station and force main capacity provides MSD with a tool to dynamically evaluate all the factors associated with a pump station’s capacity, such as wet well and collection system storage, multiple pump configurations,

System Capacity Assurance Plan

Revised January 2010 2-5

and timing of peak wet weather flows.

Because capacity measurements, also known as pump drawdown tests, are the most accurate and up-to-date information that can be obtained for pump stations, MSD periodically performs capacity measurements at all pump stations. The capacity measurement consists of measuring a pump’s ability to drawdown, or drop, in the pump station wet-well volume and the corresponding time. After accounting for inflow during the test, the average pump discharge is determined. If there are several pumps, each is tested individually and then in combination with each other. The drawdown tests results are compared to design data to note pump stations that are not performing at designed capacity. See Appendix D for a pump station drawdown test form, a master list of drawdown results, and a deficiency prioritization report for pump stations based on capacity reviews.

For the purposes of the SCAP, a wet weather surcharge condition at a pump station is defined as water surface level less than two (2) feet from the top of the pump station wetwell or at any manhole rim within the upstream collection system served by the pump station. If the collection system served by the pump station is in a residential area with historical capacity-related backup complaints, then a surcharge condition is considered a water surface level within five (5) feet of the top of the wetwell or at any manhole rim within the upstream collection system served by the pump station.

Adequate design capacity is determined by comparing the Peak User Flow against the pump station Firm Measured Capacity found in Hansen IMS (see Figure 2.1). If the Peak User Flow is less than the Firm Measured Capacity then the pump station has available capacity for additional proposed peaked flows. If adequate capacity is not available, the developer and MSD’s Development Team must determine the measures needed to provide adequate capacity for the proposed peak flow.3

See Appendix E for the Current Peak User Flow Calculation Method for Pump Stations.

3 For pump stations with unique designs, functions, or setups, such as combination flood and sanitary stations, specific capacity conditions may apply that fall outside of the pump station and force main capacity protocols outlined in this section. Capacity at these facilities will be determined based on factors most applicable to each unique situation.

System Capacity Assurance Plan

Revised January 2010 2-6

Figure 2.1 – Pump Station Capacity Information found in Hansen IMS

Additional design capacity reviews required for pump stations include reviewing the current LE Report for each downstream pump station affected by the new flow. The total flow committed plus the Firm Measured Capacity must not exceed the Firm Design Capacity of the Pump Station. Figure 2.2 represents a Pump Station Report generated from Hansen IMS documenting the pump station design capacity, new customer information, and total requested flow upstream of that pump station. See Appendix F for full LE reports of all applicable pump stations in the sanitary sewer system.

Figure 2.2 – Pump Station Report with LE request data

System Capacity Assurance Plan

Revised January 2010 3-1

SECTION 3 CAPACITY CERTIFICATION DETERMINATION PROCEDURES

The objective of capacity certification is to ensure that system capacity is available starting at the new flow entry point, downstream through the collection system, and ending at the WQTC. In this section, the three levels of system capacity are defined as well as the step-by-step process for assuring the system has capacity for new flow

3.1 CURRENT, COMMITTED, AND REQUESTED CAPACITY

There are three levels of system capacity that must be analyzed in order to certify that capacity for a new flow request in a particular sewershed is available. These levels of system capacity are current capacity, committed capacity, and requested capacity

Current Capacity – The capacity of the existing system. As explained in Section 2, current capacity is determined from the InfoWorks CS hydraulic models and system monitoring data. Current capacity is tracked in the hydraulic models and the Hansen IMS System for use by the Development Team. To ensure the data remains current, current available capacity will be calculated on an annual basis.

. Each of these three capacity levels is defined as follows.

Committed Capacity (Projected Flow) – The sum of new flows from all approved new developments, capital projects, sewer acquisitions, and sewer assessment projects. Committed ADFs are based on 290 gallons per day (gpd) times the number of equivalent single-family dwelling units for ADF. Peak wet weather flows are determined by multiplying the MSD Design Standard peaking factor, which ranges from 2.5 to 5.0, by the calculated ADF. Currently, approved capacity requests are tracked within the Hansen IMS system for use by the Development Team to determine current committed system capacity.

Requested Capacity (Pending Flow) – The sum of all current capacity requests pending MSD’s approval. All capacity requests (or Lateral Extension (LE) requests) are reviewed on a weekly basis by MSD’s Development Team LE review staff. Flows from pending capacity requests are also calculated using 290 gpd as explained for committed capacity. Currently, pending capacity requests are tracked within the Hansen IMS system and are used by the Development Team to determine current requested capacity.

System Capacity Assurance Plan

Revised January 2010 3-2

Current, committed, and requested capacity are tracked within each WQTC sewershed and capacity credit basin for use in reviewing each new capacity request. Appendix C provides current capacity, projected and pending flow reports for each of the six regional WQTCs as of October 2009.

3.2 MSD SYSTEM CAPACITY ASSURANCE PROCESS

A system capacity assurance process ensures and documents that the sanitary sewer system has capacity for new flow without exacerbating an existing overflow or known capacity restriction. MSD has developed a step-by-step approach that ensures that prior to new flow entering a system, the existing capacity of the system has been assessed properly.

3.2.1 Step-By-Step System Capacity Assurance Process

The purpose of the System Capacity Assurance Process is to determine the available capacity of the system to convey average daily flows (ADF) as well as the peak wet weather flows. If the system does not have the capacity to convey the ADF then the new flow customer must coordinate with MSD to remedy the capacity issues. It will be the new flow customer’s responsibility to resolve the ADF capacity deficiency as described in the steps below.

Figure 3-1 depicts the MSD System Capacity Assurance Process. The systematic approach addresses flows from new development and redevelopment, capital projects, sewer assessment projects, sewer acquisitions, and any other project that will increase flow to a WQTC sewershed. Each step outlined below references the numbered steps in Figure 3-1. The capacity assurance process described below applies to the separate sanitary sewer system only and does not apply to the combined sewer areas in this case. The combined sewer areas are addressed from a surface stormwater perspective through updates to the MSD Design Manual.

STEP 1 - New Development Lateral Extensions (LE) & MSD Capital Projects Initial Submittal Review

MSD’s LE process (see Appendix A-1 and A-2) requires the customer to submit capacity calculations for each new development or redevelopment that will add flow to the existing system. MSD must submit its own capacity request for capital projects that will add flow or

System Capacity Assurance Plan

Revised January 2010 3-3

divert flow from one point to another. The standard capacity request form, entitled “Downstream Facility Capacity Request” (see Appendix A-3), is used to ensure all relevant information is submitted to MSD in order to properly evaluate the capacity requirements of the proposed development or capital project. Example information required includes the projected flow based on the size of the proposed development or capital project, where the new flow will tie into the existing system, and which downstream facilities will be affected by the new flow (determined by MSD).

Currently, when the Downstream Facility Capacity Request form is submitted, a member of the Development Team reviews the form for completeness and enters the request data into the Hansen IMS. Refer to Appendix A-4 for example steps of the Hansen LE Request data entry process. All impacted pump stations, WQTCs, SSOs, and planned MSD projects are identified in preparation for the review team meeting. This regularly scheduled weekly review meeting consists of a team of MSD staff members from Engineering, Regulatory Services, and Metro Operations who then proceed through the Asset Capacity Review Process (Steps 2-5).

STEP 2 – Collection System Firm Design Capacity Evaluation for Conveying the Proposed Peaked Flow

The Asset Capacity Review Process is focused on the peak wet weather as well as the firm design capacity issues of the separate sanitary sewer system. This step involves a review of the new flow location’s downstream system and its firm design capacity using the methods described in Section 2.4.

Step 2a

If no downstream sewers are in a surcharge condition or indicate bottlenecks, then proceed to the Pump Station Firm Design Capacity Evaluation in

includes an analysis of surcharging and bottlenecks in the downstream sewer. A critical step in this process is investigating whether surcharging occurs during the 1.82-inch cloudburst storm downstream of the new flow entry point. Surcharging is indicative of a wet weather capacity problem in the sewer system. 2’ and 5’ surcharge levels and sewer deficiencies such as bottlenecks are tracked in the hydraulic models and are also available in the Development Team HARP Viewer and LOJIC MSDDATA.

Step 3. If procedures from Section 2.4 show that the collection system may not be adequate to convey the proposed peaked flow due to surcharging conditions or bottlenecks, Step 2b, Modeling Verification, is required using the

System Capacity Assurance Plan

Revised January 2010 3-4

InfoWorks CS hydraulic models. If modeling results confirm additional downstream capacity deficiencies brought on by the new flow, the request will be denied, but the new flow customer may coordinate with MSD to remedy capacity issues. This coordination process is further described below. If modeling results do not present additional surcharging and/or new SSOs in the downstream collection system, proceed to the Pump Station Firm Design Capacity Evaluation in Step 3

STEP 3 – Pump Station Firm Design Capacity Evaluation for Conveying the Proposed Peaked Flow

.

This step in the Asset Capacity Review Process involves a review of affected downstream pump stations and the firm design capacity using the methods described in Section 2.5. If the pump station’s design capacity, drawdown run times, and committed flows confirm the station is adequate to convey the proposed peaked flow, proceed to the Water Quality Treatment Center Capacity Evaluation in Step 4

STEP 4 – Does The Water Quality Treatment Center Have Adequate Capacity To Treat The Average Daily Flow and the Peak Wet Weather Flow?

. If the system pump stations are not adequate to convey the proposed peaked flow, the request will be denied, but the new flow customer may coordinate with MSD to remedy capacity issues.

In this step, the rated capacity, peak design capacity, and committed flows at the receiving WQTC are analyzed using the WQTC Capacity Data within the Hansen IMS system as described in Section 2.3. If the WQTC does have capacity, proceed to the Sanitary Sewer Overflow Check in Step 5

STEP 5 – Is the New Flow Upstream of a Documented Overflow?

. If the WQTC does not have capacity, the request will be denied.

This step requires the identification of all documented overflow locations downstream of the new flow entry point. Documented overflow data is updated continuously per the Sewer Overflow Response Protocol requirements and is tracked in Hansen IMS. Appendix G presents the list of current documented SSOs. If there are no documented overflow locations downstream from the proposed new flow location, then capacity is certified for the new flow. If there are documented overflow locations downstream, the flow may be approved with the condition that capacity credits are used and documentation performed. The response process is further described

System Capacity Assurance Plan

Revised January 2010 3-5

below.

3.2.2 Response

Certify Capacity (Collection, Pumping & Treatment)

If steps 1 through 5 are satisfied, then capacity is certified, the new flow customer is notified, and the requested capacity is reserved for the proposed new flow. As a result, the committed flow database within Hansen IMS will be updated with the new flow. A capacity assurance fee is required for all new development as discussed in Section 4.3.

Deny Request - New Flow Customer Must Coordinate With MSD to Remedy the Capacity Issues

If MSD finds that the design capacity of the system is insufficient to handle any additional flow, then the new flow request will be denied and the customer will need to coordinate with the appropriate MSD department to determine potential methods to address the system deficiency. This could include pipe replacements, pump station upgrades, or other system upgrades as determined by MSD.

Deny Request Due to Lack of WQTC Capacity

If MSD finds that the WQTC capacity (rated or peak) is not adequate to treat any additional flow, then the new flow request will be denied. Once WQTC capacity becomes available then the new flow customer will be notified and will need to resubmit the capacity request.

Approve With Capacity Credits and Perform Documentation

If adequate capacity cannot be certified due to existing downstream documented overflows, MSD documents the reason capacity certification was not granted and moves the request to the Credits Banking Process described in Section 4. The new flow may be approved if capacity credits are available.

System Capacity Assurance Plan

Revised January 2010 3-6

System Capacity Assurance Plan

Revised January 2010 3-7

3.2.3 Jeffersontown Water Quality Treatment Center

As stated in MSD’s Amended Consent Decree signed April 2009, until the Composite Correction Plan for the Jeffersontown WQTC has been fully implemented and the Jeffersontown WQTC has either been eliminated or achieved full compliance with its KPDES permit, MSD will only certify new flow requests from existing sewer service connections upstream of the Jeffersontown WQTC in the following cases:

1) MSD may certify new flow requests for each of the five new flow customers listed in the Amended Consent Decree provided the new flow request certification process is consistent with MSD’s SCAP procedures and is limited to the remaining gallons per day of sewer flow subject to approval as listed in the Amended Consent Decree.

2) MSD may certify a new flow request only if, as a direct result of the project involving the new flow request, an equal or greater amount of flow from an existing sewer service connection is eliminated prior to certification of the new request with the purpose being to not increase the total flow to the Jeffersontown WQTC. Additionally, the new flow requests certification process should be consistent with MSD’s SCAP procedures.

3.2.4 Sanitary Sewers Located in the Combined Sewer System

As stated previously, combined sewers are not subject to SCAP requirements; however, separate sanitary sewers that flow into the combined system must adhere to SCAP requirements. The procedures for certification and credit banking in these areas will be reviewed and conducted on a case-by-case basis.

3.3 LOJIC GIS AND HANSEN IMS

The System Capacity Assurance Process requires utilization of the LOJIC GIS and the Hansen IMS system to store, track, and analyze data related to system capacity.

MSD has established LOJIC GIS layers and databases for analyzing system capacity that include:

System Capacity Assurance Plan

Revised January 2010 3-8

• Documented SSOs • Sanitary Sewer Collection lines • Pump Station and Transmission Components • Water Quality Treatment Centers • System Monitoring Locations • Sewershed Boundaries • Hydraulic Modeling Results for Surcharging and Deficiencies

As MSD’s Development and Capacity Review Team reviews each new flow request, Hansen IMS is utilized to document the capacity assurance process and record the pertinent information from the review. In addition, databases within Hansen IMS will document the new flow customers’ location, system capacity requirements, as well as the capacity of the WQTCs, pump stations, and the collection system downstream. When the system is incapable of conveying new flows, Hansen IMS will track these deficient areas and the actions necessary to approve future new flow requests.

System Capacity Assurance Plan

Revised January 2010 4-1

SECTION 4 APPROVAL THROUGH CREDIT BANKING PROCEDURES

Under Certification of Capacity protocols, MSD may authorize the contribution of additional flow to the system after it certifies that there is adequate collection system capacity, transmission capacity, and treatment plant capacity as described in Section 3.2.

Based on the evaluations of the collection, transmission, and treatment plant capacity that have taken place to-date, it is anticipated that, initially, many locations within MSD’s system will not meet the SCAP certification requirements due to downstream capacity restrictions. This means that MSD will only authorize those capacity requests via “Approval through Credit Banking Procedures” described in the following sections.

4.1 CREDIT BANKING SYSTEM

MSD may authorize additional flow to the system that could not previously be certified through a credit banking system. As MSD completes capital or infrastructure projects that restore capacity by reducing peak wet weather flows or construct additional capacity, MSD will bank flow credits in the system to be used for authorizing new flow.

MSD will bank these credits upon completion of the capital or infrastructure projects. One gpd of credit will be banked for each gpd of peak flow removed or gallon of capacity added. Credits will be used to approve new capacity requests using a ratio of three capacity credits per one gallon of new flow (3:1). These credits must be in place within the appropriate credit catchment prior to the time the proposed additional flow is introduced to the system.

For example, a manhole rehabilitation project reduces peak flow by approximately 170,000 gpd in a SCAP catchment area; then a credit of 170,000 gpd is banked and added to the total credits within that SCAP catchment area. The estimated flow from a new development of 100 single-family homes is 29,000 gpd (100 SFE x 290 gpd/SFE) introduced upstream of the project, then 87,000 gpd of credits (29,000 x 3:1 offset) will be subtracted from the total available credits within the SCAP catchment area.

MSD has and will perform quarterly reviews of estimated peak flow reductions or peak capacity additions as a result of completed projects and will adjust current available credits and future credits achieved, as appropriate.

System Capacity Assurance Plan

Revised January 2010 4-2

4.2 SPECIAL CONDITIONS

4.2.1 Certification Exceptions

In some cases, MSD may authorize a request for additional flow to the system even if adequate capacity cannot be certified and credits are not available at the anticipated time of flow initiation. These cases include the following:

• Request eliminates illicit discharges of wastewater to the stormwater system. • Request is made for an essential service facility. Essential services are defined as

critical or essential facilities such as, healthcare facilities, public safety facilities, public schools, other government facilities, or in cases where a pollution or sanitary nuisance (as determined by the Louisville Metro Public Health and Wellness Department) will be eliminated in relation to on-site septic systems.

• A request or internal capital project that diverts existing flow from one sewershed provides an environmental benefit.

However, a subtraction shall be made from the credit bank in an amount equal to the average projected flow from the correction of the illicit wastewater discharge, essential service facility, or diversion of flow. Credits for these exceptions will be generated as quickly as possible.

4.2.2 Redevelopment of Existing Facilities

In some instances, a request will be received requesting flow for a new structure replacing an existing structure that previously contributed flow to the separate sanitary sewer system. In these cases, the previous flow will be subtracted from the projected flow and the residual flow will be assessed according to credit banking procedures.

System Capacity Assurance Plan

Revised January 2010 4-3

4.3 APPROVAL THROUGH CREDITS BANKING PROCESS

As discussed in the previous sections, MSD may authorize additional wastewater flow to the system using a credit banking system. As specific projects are completed, MSD will bank flow credits and these credits will be used to offset proposed additional flows.

Figure 4.1 shows the approval through Credit Banking Procedures Step-by-Step diagram. The systematic approach in Figure 4.1 addresses new flows from development whose certification has been declined due to downstream capacity restrictions according to Section 3, Figure 3.1.

4.3.1 Step-by Step Credits Banking Process

The description of the credits banking process outlined below references the numbered steps in Figure 4.1. The numbered steps continue from Steps 1 through 9 in Section 3 (Figure 3.1).

STEP 1 - Confirm Capacity Assurance Process Was Performed

The System Capacity Assurance Process discussed in Section 3 must be completed

1. Location and estimated flows from the proposed development,

prior to the Credit Banking Process. Two important pieces of information from the capacity assurance process are required:

2. Documentation of reason for requiring credits

If this information is not available, return to Section 3 and complete steps per System Capacity Assurance Procedures (Figure 3.1) before proceeding to Step 2 of the Credits Banking Process

STEP 2 – Do Available System Credits Exceed New Flow within the Credits Catchment?

.

MSD will determine if sufficient credits from system rehabilitation projects are available to offset the proposed new flow within the Credits Catchment where the new flow applies. If credits are available, approval of the new flow may be granted as described below. If credits are not available, proceed to Step 3 of the Credits Banking Process

Grant Approval and Deduct Amount of Credit Used to Approve Flow

.

System Capacity Assurance Plan

Revised January 2010 4-4

MSD will approve the new flow request and then deduct the appropriate capacity credits from the Credits Bank using the 3:1 offset calculation process described in Section 4.1.

STEP 3 - Approval with I/I Credits

New flow requests will be approved and MSD will create sufficient credits or capacity to accommodate flows prior to their actual initiation. As MSD is beginning its 2nd year of implementing the SCAP, inspection and rehabilitation efforts are underway to offset new flows with capacity credits.

4.3.2 Inflow and Infiltration (I/I) Surcharge

MSD has enacted an I/I surcharge fee to be paid by new flow request customers in support of rehabilitation of the sewer system or the disconnection of illicit connections. The surcharge fee will partially support the district-wide rehabilitation program to be managed and further financed by MSD and will be used to perform rehabilitation work in areas of the separate sanitary sewer system with limited capacity.

The fee applies as stated in MSD’s Rates, Rentals, and Service Charges policy: $1 per gallon per day of estimated new flow, with a minimum charge of $400 for a single project.

The I/I fee is not applicable in the following cases:

a. Properties located within a catchment subject to “recapture fees” but exempt from fees such as “Non-Subject Properties” pursuant to terms and conditions of the applicable Recapture Agreement between MSD and the Developer.

b. Properties located within a catchment where I/I reduction work has been approved by MSD and performed in accordance with the SCAP.

c. Properties that do not impact documented SSOs as determined by MSD, and for which a Reservation of Capacity Agreement was executed prior to August 1, 2008, and a Lateral Extension Agreement was executed prior to September 1, 2008.

d. Properties that discharge flow directly into the combined sewer and for which a separate sanitary sewer is not available.

System Capacity Assurance Plan

Revised January 2010 4-5

System Capacity Assurance Plan

Revised January 2010 5-1

SECTION 5 – STANDARD PROCEDURES FOR CALCULATING AND TRACKING FLOW CREDITS

The SCAP requires a standard operating procedure to revise and implement processes to determine if capacity is available in the system. Section 5 describes a standard process to document available capacity and create, calculate, track, and expend capacity credits. The following sections explain how MSD will accumulate capacity credits through I/I removal projects and estimated flow reduction from these projects, how credits are calculated from I/I removal, and how credits are tracked and distributed to new flow requests within the Hansen IMS.

5.1 SEWER SYSTEM REHABILITATION AND I/I REMOVAL

As described in Section 4, all new flow requests where system capacity cannot be certified will be required to use capacity credits on a 3:1 ratio. The SCAP goal is to ensure new flows do not exacerbate existing system deficiencies; therefore, the tracking of I/I removal is very important. This goal is achieved by requiring three gallons of I/I removal for every one gallon of new flow added in areas where system capacity cannot be certified.

MSD continues to execute inspection and rehabilitation projects to remove I/I from the sanitary sewer system. MSD’s Continuing Sanitary Sewer Assessment (CSSA) Program is responsible for the inspection, identification, prioritization, and rehabilitation of sewer line defects. Through this program, capacity restoration projects and capital projects are ongoing and include sewer line replacement, pump station upgrades, main line repairs, and remediation of sewer lines, manholes, and service laterals. All of these projects have increased peak wet weather capacity within the sanitary sewer system by removing I/I. With this in mind, the SCAP will serve as a platform to begin tracking and using credits for these flow reductions.4

As MSD continues to repair, replace, and remediate the sanitary sewer system, credits will be accrued on a one capacity credit per one gallon of I/I removal basis. Calculations for estimating I/I removal from various types of repairs and remediation are explained in the following section.

4 MSD has been performing rehabilitation and system improvements associated with the terms of the Consent Decree with KDOW and EPA. To capture the credits earned as a result of these improvements the effective retroactive date for credit claims is August 12, 2005, the date the Consent Decree went into effect.

System Capacity Assurance Plan

Revised January 2010 5-2

5.2 ESTIMATED FLOW REDUCTION FROM SYSTEM REHABILITATION

In order to calculate capacity credits for corrective actions, the flow reduction or added capacity from the corrective actions must be estimated. The following types of corrective actions are anticipated: mainline sewer rehabilitation; manhole rehabilitation, downspout connection removals, foundation drain (sump pump) connection removals, area drain connection removals, and rehabilitation of private sewer service laterals. The estimated flow reduction listed in this section is based on values presented in the SCAP by MSD of Greater Cincinnati. Any alternative methods for estimating flow reduction are accepted and are subject to review by MSD’s capacity review team. The calculation of estimated flow reduction, or capacity increase, from each type of corrective action is discussed below.

5.2.1 Manhole Rehabilitation

Primary repair mechanisms for manholes include chimney seals, full lining, and mechanical or chemical treatment. The estimated peak flow reduction is determined by severity and number of defects identified during inspection, as well as the location of the manhole and its susceptibility to inundation by rainwater during wet weather as defined below.

Paved Areas - Manholes in paved areas that do not meet the along a stream definition.

Non-Paved Areas - Manholes in non-paved areas that do not meet the along a stream definition.

Along a Stream - Manholes will be considered to be along a stream when they are located within 50-feet of a blue-line stream or within the floodway of a FEMA designated 1%-annual-chance (100-year) floodplain. If a 2-year floodplain boundary has been developed for a stream then manholes within the 2-year floodplain are also considered to be along a stream.

(Source: American Society of Civil Engineers

Tables 5.1 through 5.3 provide the typical peak flow reduction for manhole rehabilitation in paved areas, non-paved areas, and along a stream.

, Manual Practice No. 92)

System Capacity Assurance Plan

Revised January 2010 5-3

Table 5.1 – Peak Flow Reduction for Manholes in Paved Areas

Manhole Section

Reduction Values in Gallons Per Day (gpd) Minor I/I Moderate I/I Heavy I/I Severe I/I

Frame Seal 78 156 311 622 Chimney 78 156 311 622 Cone 78 156 311 622 Wall 39 78 156 311 Pipe Seal 39 78 156 311 Bench 39 78 156 311 Channel 39 78 156 311

Table 5.2 – Peak Flow Reduction for Manholes in Non-Paved Areas

Manhole Section

Reduction Values in Gallons Per Day (gpd) Minor I/I Moderate I/I Heavy I/I Severe I/I

Frame Seal 328 656 1,313 2,626 Chimney 328 656 1,313 2,626 Cone 328 656 1,313 2,626 Wall 164 328 656 1,313 Pipe Seal 164 328 656 1,313 Bench 164 328 656 1,313 Channel 164 328 656 1,313

Table 5.3 – Peak Flow Reduction for Manholes Along a Stream

Manhole Section

Reduction Values in Gallons Per Day (gpd) Minor I/I Moderate I/I Heavy I/I Severe I/I

Frame Seal 864 1,728 3,456 6,912 Chimney 864 1,728 3,456 6,912 Cone 864 1,728 3,456 6,912 Wall 432 864 1,728 3,456 Pipe Seal 432 864 1,728 3,456 Bench 432 864 1,728 3,456 Channel 432 864 1,728 3,456

5.2.2 Removal of Illicit Connections to the Sanitary Sewer System

Illicit connections to the sanitary sewer system are direct stormwater inflow sources.

System Capacity Assurance Plan

Revised January 2010 5-4

Disconnection of these sources can provide significant increases in capacity. The following are estimated peak flow reduction due to the removal of typical illicit connections.

Downspout 4,000 gpd

Area Drain 6,000 gpd

Foundation Drain 4,000 gpd

Sump Pump 4,000 gpd

5.2.3 Rehabilitation of Deteriorated Mainline Sewers and Sewer Service Lateral

Corrections

The estimated peak flow reductions for mainline sewer rehabilitation or replacement (including service laterals) are as follows in gpd per inch diameter-mile (IDM) of pipe rehabilitated:

Stream Inundation / High Groundwater 34,000 gpd / IDM

Non- Inundation / Low Groundwater 60 gpd / IDM

5.3 CREDITS CALCULATION

In order to accrue and track capacity credits for corrective actions, the estimated flow reduction or added capacity from the corrective actions must be calculated. Total credits accrued from mainline sewer rehabilitation are based on length of pipe repaired, pipe diameter, and whether the pipe is located along a stream or not. Total credits accrued from manhole rehabilitation are based on location of the manhole, the type of repair, and the severity of the I/I. Appendix H provides detailed instructions for calculating rehab credits.

Figure 5.1 shows an example Rehabilitation Credits Calculation sheet from an actual Interceptor Rehabilitation project. In this example, only rehabilitation of mainline sewers and manholes took place. The Project Total Credits summarized at the bottom of the sheet are the credits applied to the catchment(s) for the credit banking purposes.

System Capacity Assurance Plan

Revised January 2010 5-5

Figure 5.1 – Rehabilitation Credits Calculation Sheet

5.4 ENTERING AND TRACKING CREDITS IN HANSEN IMS

The Hansen IMS will be used to enter credits from I/I removal or capacity restoration projects. As the rehabilitation projects are completed, the associated credits will be made available for use in the Credit Banking process as discussed in Section 4. System rehabilitation performed by MSD IFP will be reviewed on an annual basis and credits will be updated in catchment areas accordingly. Appendix I provides a report of available credits by catchment area as of December 31, 2009.

Figure 5.2 represents an example SCAP credit form where estimated flow reduction is entered into Hansen IMS after an I/I removal project is completed. Appendix J provides detailed instructions for entering SCAP credits into the Hansen IMS.

System Capacity Assurance Plan

Revised January 2010 5-6

Figure 5.2 – Example SCAP Credit Form

The Hansen IMS will also be used to track where each capacity credit is being used, and where the new flow request credits apply. The amount of credit subtracted from the database to offset a proposed new flow addition will be determined based on the Credit Banking criteria discussed in Section 4. Appendix K provides a credit balance report summarizing the number of credits approved in each basin and the available credits created through rehabilitation projects. This report summarizes activity through December 31, 2009.