system of systems (sosa) update
DESCRIPTION
System of Systems (SoSA) Update. Gary Macomber. Agenda. SoSA Update Use Cases Domain Model UI Summary. SoSA – Use Cases and Domain Model. Use Cases MMS Component level use cases 98% complete EMS Component level use cases 95% complete - PowerPoint PPT PresentationTRANSCRIPT
System of Systems (SoSA) Update
Gary Macomber
2
ERCOT Public
12/18/2007
Agenda
• SoSA Update – Use Cases
– Domain Model
• UI
• Summary
3
ERCOT Public
12/18/2007
SoSA – Use Cases and Domain Model
• Use Cases– MMS Component level use cases 98% complete– EMS Component level use cases 95% complete– Updating System level based on reconciliation with Component
level– NMMS and CMM being updated (Feb)– Planning to republish in early January
• Domain Model– Updated to include EDS 1 and 2 items not previously included– Published 14 December – Complete thru EDS 3 Release 6.1 in early January
4
ERCOT Public
12/18/2007
UI Project
• UI project Manager on board – Gerry Murphy
• Technology limitations impact consistent look and feel
Project Involvement Status Comments
EMS Control Room Prototype completing
MMS External UI – Development
Internal – Control Room
Building Web Service, testing
Prototype completing
Completing phase 1
OS Internal and external UI development
Revisiting prior designs New resource starting in Jan
CRR Review vendor UIs, provide design direction
Complete reviews 1 & 2, completing 3
Limited by technology and level of engagement
MPIM Review vendor UIs, provide design direction
Completed work on Phase 1, starting Phase 1,5
Limited by technology
FT, Reg, Disputes
Review design and test development
Completed design review
CMM Review design, work directly with team
Design review completed Limited by technology
NMMS Reviewed design, provide design direction
Vendor has implemented some changes
Limited by technology, internal development?
MIS Design and direct development Release 1.8 out Continuing work
5
ERCOT Public
12/18/2007
ERCOT Control Room Screen Concept
Dashboard (ERCOT Designed/Developed)
Summary Detail Summary Detail
Detail Detail Detail Detail(Vendor Developed)
6
ERCOT Public
12/18/2007
LMP Contour Map
• Proof of concept complete• Initial working prototype complete• Decided on MIS display method
– Links to .jpgs
– Initially over-write previous version
– Phase 2, see recent
• Target MIS integration early Jan• Available to Market mid Jan
7
ERCOT Public
12/18/2007
Summary
• SoSA– Use Cases: completing Component level, republish in January– Domain Model: entering EDS 1 & 2 entities, republished 14
December• UI Project
– Completing MMS Iteration 1 of 5 projected– Finishing Control Room conceptual designs– Starting revisiting OS design