system operating limit construction outage study automation best practices final 20150407

13
Transmission Planning Construction Outage Study Automation By Stew Nunn and Bill Robertson Transmission Planning, Planning and Engineering

Upload: stewart-nunn

Post on 11-Apr-2017

104 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: System Operating Limit Construction Outage Study Automation Best Practices Final 20150407

Transmission Planning Construction Outage Study Automation

By Stew Nunn and Bill RobertsonTransmission Planning,

Planning and Engineering

Page 2: System Operating Limit Construction Outage Study Automation Best Practices Final 20150407

4.8.15 Best Practices Workshop Stew Nunn and Bill Robertson 2

Western Interconnection• A gigantic electrical machine• Serves electricity to 78 million

people• Peak power use 152,000 MW

Page 3: System Operating Limit Construction Outage Study Automation Best Practices Final 20150407

Southwest Outage 9/8/20116 Million Customers Without Power

Page 4: System Operating Limit Construction Outage Study Automation Best Practices Final 20150407

Work BackwardsUnderstand WECC

Requirements

Identify Alternatives

Hire and Train 10 new engineers

Automate Processes

Decision

Describe Desired Outcome

Page 5: System Operating Limit Construction Outage Study Automation Best Practices Final 20150407
Page 6: System Operating Limit Construction Outage Study Automation Best Practices Final 20150407

DeriveBetter Practices

EnhanceCurrent Practices

CreateNew Practices

UsePotential Practices

Innovate

Paths to Innovation

Page 7: System Operating Limit Construction Outage Study Automation Best Practices Final 20150407
Page 8: System Operating Limit Construction Outage Study Automation Best Practices Final 20150407

High Performance Computing

User Input

Multiple Scenarios

Program to Split Up Inputs

CPU 1

CPU 2

CPU 80

Program to Reassemble

Outputs

Page 9: System Operating Limit Construction Outage Study Automation Best Practices Final 20150407

50X Performance Increase

Page 10: System Operating Limit Construction Outage Study Automation Best Practices Final 20150407

Development Best Practices

• Work Backwards!• Define Application Boundaries• Eat Your Own Dog Food!

Page 11: System Operating Limit Construction Outage Study Automation Best Practices Final 20150407

Desired Outcome

Unfinished Features

Daily Comunication

Working Software

Real-Time Programming

Page 12: System Operating Limit Construction Outage Study Automation Best Practices Final 20150407

Summary

• Collaboration fuels successful innovation• Operational Excellence is transformational• Management’s trust makes it possible

Page 13: System Operating Limit Construction Outage Study Automation Best Practices Final 20150407

Questions?