table of contentsnews.cypresscollege.edu/documents/2017... · commonly-used seismic hazard...
TRANSCRIPT
![Page 1: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/1.jpg)
![Page 2: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/2.jpg)
TABLE OF CONTENTS
Project Overview
Executive Summary
Architectural
Architectural Assessment. ..................................................................................................................... 1
Observations
Roof ......................................................................................................................................... 2
Roofing System .............................................................................................................................. 4 Building Enclosure ......................................................................................................................... 6
Interior Observations .... . ......... .............. ............. ................... 1O Accessible Parking .. ....................... ....... ....... . ......... .12
Accessible Path of Travel to East Building Entry ............. .......... ........... 14
General Interior Accessible Path of Travel .................. . ......... 15 Accessible Restrooms.......... .............. ..... .................. ... ............ .......20
Stair ........................................................................................................................................ 33
E r .. . ...... ....... . ... .......... .. . ................ ... ..
Analysis and Recommendations
Roof ........................................................................................................................................38
Roofing System ..................................................................................................................... 38
Building Enclosure ................................................................................................................. 39
Interior Observations .............................................................................................................. 39
Accessible Parking ................................................................................................................40
Accessible Path of Travel to East Building Entry ................................................................... 40
General Interior Accessible Path of Travel. ..................................................................... 40
Accessible Restrooms. ................................................................................................................ 41 Stair .................................................................................................................................. 43
Elevator ............................................................................................................................ 43
Warranty and Limitations of this Report.............................................................................................. 43
Structural
1. Project Overview and Scope of Work .. ............ ..............
1.1. Project Overview ............... ........................... 1.2.
Scope of Work .............. ............ ..............
2. Existing Conditions and Observations ..................
2.1. Existing Structural Drawings ....................
2.2. Building Systems Description ..
..... .. ........... ...... ··············· ... 1
. .......................... 2
····· ..... . ............. ..2
··················· ....4
................... 5
.......... 5
2.2.1. General .................................... .............. .............. .
2.2.2. Gravity System............... ................ .. .......... ........
2.2.3. Lateral Force Resisting System ........................ ...................... .
....................... 4
....... . .......... 8
......... 13
2.2.4. Foundations...................................... ............... ... .............. ....... 14
![Page 3: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/3.jpg)
illDLR Group Science/Engineertng/Math Building
Cypress College, Cypress, California
2.3. Site Visit and Observations .............................................................................................. 14
2.3.1. General. ........................................................................................................................ 14
2.3.2. Skylights ....................................................................................................................... 16
3. Building Systems Evaluation (ASCE/SEI 31-03 Tier 1) ...................................................................................... 18
3.1. General. ................................................................................................................................. 19
3.2. Performance Objective ......................................................................................................... 19
3.3. Site Seismicity ............................................................................................................................ 19
3.4. Required Checklists ......................................................................................................... 21
3.5. Noncompliant Items ......................................................................................................... 21
3.5.1. Basic Structural (Type C2) ......................................................................................... 21
3.5.2. Supplementary Structural (Type C2) ......................................................................... 22
3.5.3. Geologic Site Hazards and Foundations ................................................................ 23
3.5.4. Basic Nonstructural ................................................................................................. 23
3.5.5. Intermediate Nonstructural ......................................................................................... 24
4. Recommendations and Next Steps ............................................................................................. 25
5. References ................................................................................................................................... 26
Appendix A - Completed ASCE/SEI 31-03 Checklists
Appendix B - Seismic Design Parameters
Appendix C - Selected Site Photos
Mechanical
Mechanical Overview ............................................................................................................................ 1
Mechanical Equipment .................................................................................................................... 2
Electrical
Electrical Assessment ...................................................................................................................... 1
Electrical Systems ........................................................................................................................... 1
Electrical Recommendations ..................................................................................................................... 4
Lighting Systems ......................................................................................................................................... 5
Lighting Recommendations ................................................................................................................. 6
Power and Other Miscellaneous Systems ........................................................................................... 7
Power and Other Miscellaneous Systems Recommendations ........................................................... 8
Cost Estimate
Building Efficiency
Building Options
![Page 4: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/4.jpg)
PROJECT OVERVIEW
"Cypress College is the American Dream." Students can start with nothing and leave with all the skills
necessary to thrive. The College has proudly earned a reputation for academic excellence and for the
variety and depth of the educational programs offered. With the support from the local community many
programs are housed in state-of-the-art facilities.
As Cypress College continues to look forward and plan for the future, the College recognized the need to
assess some of the existing facilities. Can they be retrofitted to meet tomorrow's needs, can they be
repurposed for other uses, should they be replaced? These and many more questions need to be fully
understood, discussed and answered to determine the best path forward.
In an effort to begin to answer one of the questions for one of the buildings, Cypress College has
requested to have a due diligence study performed on the Science, Engineering and Mathematics (SEM)
Building. The SEM building is a three story, approximately 100,000 square foot building constructed in
1970-71 on the Cypress College campus. The building program consists primarily of classrooms,
laboratories and offices and also includes mechanical/electrical rooms, a two-story entrance lobby, a
greenhouse and two central lecture halls that slope from the second level to ground level. The building is
currently still used for instruction with the exception of some classroom spaces which are inactive.
The study was to determine the condition of the building enclosure, structural, mechanical, plumbing and
electrical systems as it currently stands and what is necessary or recommended to maintain the facility for
current uses. The study also addressed accessibility issues as it relates to existing buildings, as well as a
cost analysis comparing renovation of the existing building to the costs associated with constructing a
new building at an adjacent location.
The site investigation and study was completed in August and September of 2015 and consisted of visual
site observations and review of plans furnished by the College. No destructive or non-destructive testing
or investigation was conducted.
![Page 5: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/5.jpg)
Group Science/Engineering/Math Building Cypress College, Cypress, California
EXECUTIVE SUMMARY
ARCHITECTURAL
The goal of the architectural assessment was to visually review the building envelope consisting of the
roof and exterior building walls and windows of its current condition and deficiencies and provide any
recommendations for the future. Building compliance with the 2013 California Building Code accessibility
requirements were also reviewed. When the building was designed, no Code for accessibility existed but
since then some provisions had been made, primarily on the first floor.
Compared to the State of California Department of General Services, Office of Architecture and
Construction approved drawings dated February 13, 1970, the building has undergone very few plan
altering renovations. Maintenance has been deferred on some items while some systems or parts thereof
have been updated.
The roofing system has served its useful life and should be removed and replaced. When the roofing
system is replaced, the various components that are connected and impacted by the roofing should be (;JV addressed. The skylights should be replaced, roof access door and frame replaced, metal copings
installed, roof overfow drains installed, sheet metal equipment pad covers installed, cracks in the
concrete equipment screen walls filled, the concrete equipment screen walls sealed and utility supports
installed.
The concrete and aluminum window system building enclosure is in good condition. To maintain and
increase the useful life, a concrete sealer should be applied to the exterior concrete walls to minimize
moisture penetration. Cracks in the concrete wall or adjacent bridge structure should be filled and sealed.
All the window gaskets should be removed and replaced as they have shrunk with age. Window weep
holes should be drilled into the window sill for moisture evacuation. Landscaping irrigation should be
checked, adjusted and redirected to avoid spraying the windows.
An attempt to address exterior accessibility such as parking and path of travel to an entry has been made
but does not comply with the current 2013 California Building Code or even back to the 2007 California
Building Code. Code compliant accessible parking and an accessible path of travel to an entry should be
provided as any work to the building requiring a building permit will require this.
Accessibility issues have generally not been addressed within the building with the exception of the first
floor restrooms. The first floor restrooms have been modified to comply with most, but not all the
accessibility requirements, and require additional work.
When additions or alteration work is executed in an existing building, the cost of compliance shall be
limited to 20 percent of the adjusted construction cost of alterations when the adjusted construction cost
is less than or equal to the current valuation threshold as defined in the Code. If the adjusted
construction cost exceeds the threshold, full compliance is required unless full compliance exceeds 20
percent of the construction cost. At that situation, compliance shall be provided to the greatest extent
possible without exceeding 20 percent. In general the accessible parking and the path of travel to the
area of work are priority and must comply with accessibility requirements. Then the restrooms and
drinking fountains serving the area must comply with accessibility requirements.
The building complies with current exiting requirements with the current uses and corresponding area or
square feet related to the use. If uses are changed or current uses are expanded or decreased, an
exiting calculation should be made to ensure Code compliance.
r
![Page 6: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/6.jpg)
STRUCTURAL
The purpose of the structural report is to identify structural and nonstructural elements of the existing
Structural, Engineering and Mathematics (SEM) building that may require replacement and/or upgrades.
The ultimate objective is to estimate the costs associated with continued operation of the existing SEM
building to compare to the cost of a new replacement building. The ASCE/SEI Tier 1 procedure detailed
in this report is a "first step" screening procedure that identifies "noncompliant" items, or items requiring
further investigation/evaluation (Tier 2 analysis). Once the Tier 2 analysis is complete, required upgrades
are determined (if applicable) and costs can be estimated for these specific upgrades.
Nonstructural components identified as "noncompliant" per Tier 1 will need to be replaced to current
building code standards (no Tier 2 required). Structural and nonstructural components that are identified
as "compliant" per Tier 1 are acceptable as-is.
Mandatory vs Voluntary Seismic Upgrades
The California Administrative Code (CAC), Chapter 4 determines the requirements for seismic upgrades
to community college buildings in California. A seismic rehabilitation is required for the Community
College building if any of the following apply:
Mandatory Seismic Rehabilitation
Triaaer
CAC Ch. 4 Section Applicability to Cypress SEM Building
Existing "nonconforming" building is
converted for use as a school building*
CAC Section 4-307 Does not apply to the SEM building
which is already a DSA Certified
school buildino.
Cost of reconstruction, alteration or
addition exceeds $25,000 and 50% of
the replacement value of the existing
building**
CAC Section 4-309(c) It is anticipated that the alterations
will exceed 50% of the replacement
value; however, this will need to be
confirmed by the cost consultant for
the alterations versus new building
construction costs.
Cost of reconstruction, alteration or
addition exceeds $25,000 but does not
exceed 50% of the replacement value of
the existing building and the proposed
modifications either**
• Increase the effective seismic weight or wind force in any story by more than 10%
! • Decrease the design capacity of
CAC Section 4-309(c) This will need to be confirmed once
the specific proposed alterations to
the SEM building have been
identified.
It is not anticipated that structural
alterations to the building in its
current form to achieve the Life
Safety performance objective will
result in weight increases or capacity
decreases beyond the above
thresholds; however, this will need to
be confirmed after a Tier 2 analysis
is performed on the identified items
in this report.
any existing structural
component by more than 5%,
unless the component has the
capacity to resist the retrofit
desiqn forces
* A "nonconforming" building is defined by CAC as any building that has not been certified by DSA as a
school building.
** Cost excludes maintenance, HVAC, insulation materials, any voluntary seismic upgrades.
![Page 7: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/7.jpg)
Ill DLR Grou p Science/Engineering/Math Building
Cypress College, Cypress, California
If none of the above conditions applied, a seismic rehabilitation would not be required but may be
performed on a voluntary basis at the school's discretion. All structural deficiencies need not be
addressed if voluntary upgrades are performed, whereas all structural deficiencies must be addressed if
seismic upgrades are required by CAC. Voluntary seismic upgrades should not make the building perform
at a lesser seismic capacity. ---
At this time the estimated cost of the replacement building 61.83 million. e alterations to the
existing SEM building exceed 50% of the replacement valu; c1fic alterations/additions to the
existing SEM building have not yet been proposed, seismic rehabilitation will be required per the CAC.
Once the specific alterations are identified, the changes in seismic weight and/or member capacities can
be estimated by the Structural Engineer.
Any seismic upgrades are supervised by and approved by the Division of the State Architect (DSA).
The seismic hazard value referenced in this report is established by the USGS. The USGS Design Maps
summary report is used to generate acceleration parameters Sos & S01 for the site. These values are
commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a
certain site for a given seismic hazard (in this case, ASCE/SEI 31-03 Tier 1 uses the mapped 2%
probability of exceedance in 50 year values). These values then determine whether the site is classified
as "Low", "Medium" or "High" seismicity per ASCE/SEI 31-03 Tier 1 (see page 20 of the structural report).
MECHANICAL
The existing mechanical systems in the building were installed in 2009 and are in very good condition.
No work on these systems is needed or recommended at this time. The rooftop mechanical equipment,
consisting of fans and other equipment are not in good condition. These units, however, can be replaced
by maintenance as the need arises as the units are still functioning.
ELECTRICAL
The SEM building was built in the 1970's. The electrical power distribution is 45 years old and in good
condition. There are several code violations on the required clearances for electrical equipment which are
the most problematic, and should be addressed in either the proposed renovation or within any
repurposing effort planned for this building in the future. The other issues are simpler which are related to
mounting heights of devices and lighting control functionality. The code violations regarding the
clearances will require relocation of electrical equipment which is complicated and requires further
planning since it will impact the electrical service and power distribution. Correction of the lighting controls
should be implemented with Title 24 regulations which utilizes dimming controls and LED energy efficient
fixtures. The simplest corrections are the relocation of outlets and devices to be accessible since the
impacts are localized and isolated. The extent of the renovation is dependent of the future plans and shall
require a separate in-depth study.
![Page 8: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/8.jpg)
COST ESTIMATE
Cost estimates for three scenarios were developed. The first was to renovate the existing building as it
currently exists irrespective of the Final Project Proposal (FPP) impacts. The second was to renovate the
existing building considering both existing conditions and impacts of the FPP. The third was to construct a
completely new building adjacent to the location where the existing building stands. In today's costs, the
existing renovation work without FPP work will cost approximately $17.6 million, the inclusion of the FPP
work to the renovation scope will add approximately $31.7 million ($49.4 million total), and a new building
will cost approximately $71.03 million. The new building estimate includes a 3,500 SF modern
Planetarium, in lieu of a separate building, at a cost of approximately $9.2 million.
The renovation work would address the findings of this report including deferred maintenance items, such
as the roofing system, skylights and windows. Code issues such as general accessibility and fully
accessible restrooms on each floor would be addressed. Code issues involving electrical requirements
and clearances would be addressed. Additionally, electrical revisions required to comply with energy
conservation requirements will be implemented such as providing all new energy compliant LED light
fixtures. Since renovation work exceeds $30.8 million - or half the replacement value - of the building is
anticipated, structural upgrades would be triggered. Changes to the layout of the classrooms, offices and
lecture halls are not included with the exception of modifications required to accommodate accessible
restrooms. This number was to simply identify the costs associated with code or maintenance items not
necessarily associated with the FPP.
The inclusion of FPP scope to the renovation project will result in fully refurbished and modernized
classroom and laboratory spaces, faculty offices, support spaces, toilet rooms and preparatory spaces.
This work would also include ceiling replacement, lighting replacement, reconfiguration of network and
electrical services, replacement/reconfigurati on of the mechanical systems, space reconfiguration to
alleviate efficiency issues and to create more effective instructional environments.
A new building (3,500 SF larger than existing for Planetarium) would comply with all current Codes and
standards including seismic requirements. The cost includes the demolition ($800k) of the existing
building but does not include addressing the displacement of the current programs housed in the building.
An option to this scenario would be to use the existing building as swing space for the bond program
since the building is already DSA approved and field act compliant.
In all cases, the estimated cost is only for the hard cost sometimes referred to as the "brick and mortar
cost" involving the actual physical construction such as site work, building materials and labor. Soft costs
which include design, permits, insurance, testing and furnishings is not included. Soft costs vary from
project to project but can range from 15% to 25% of the hard costs.
BUILDING EFFICIENCY
Efficiencies of the existing building need to be factored as part of the due diligence study summary.
While energy efficiency is discussed within the mechanical section of this report, the purpose of this is to
provide instances for discussion of the pragmatic building efficiencies. These pragmatic inefficiencies are
difficult to quantify in monetary terms.
The building's concrete structure, relative to the provisions of the Capital Outlay Program Final Project
Proposal (FPP) approval for this building, is inherently inefficient due to the difficulty in being able to
"right-size" particular spaces locked within the building's envelope or structure. The push within spaces
requiring accessible upgrades (toilet rooms, elevators, stairs for egress/circulation, etc.), can result in
spaces that are inherently compromised, and ultimately the programming suffers as it attempts
accommodate the specific curriculum and academic needs. For example, the restrictions of the existing
Group Science/Engineering/Math Building
Cypress College, Cypr-ess, CaHfornia
![Page 9: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/9.jpg)
Cypress College, Cypress, California
building make it impossible to increase the number of specific laboratory sections that can be offered or
accommodated.
Inefficiency can also be a result of the specific requirements of the educational specification that cannot
be accommodated within the parameters of the building structure, or as a result of the inability to provide
additional space required by the physical sciences - a planetarium, for example - due to the State Capital
Outlay Program limitations on space additions for modernization projects. The desired addition of a
planetarium is not possible to add under the currently approved Final Project Proposal. Additionally, the
space push mentioned above can adversely affect the ability to construct an addition in an effective
manner as well.
Finally, efficiency of one building needs to be reviewed in the context of the campus. The S.EM Building,
even with an inability to become more efficient than its potential, can still be beneficial to the campus for
short term use. The existing SEM Building is efficient in terms of swing space use to alleviate space
needs for capital construction or for secondary effect projects, without consuming valuable parking or
another site on campus. The aggregate savings by alleviating both parking and available swing space
concerns could exceed $10 million.
BUILDING OPTIONS
As part of the summary of this assessment, three (3) options of approach are presented below with
recognized advantages and disadvantages for consideration. Option 1 is a "maintain the course" action
that may require waiting for a statewide bond for renovation funding, Option 2 is a utilization of local
Measure J funds to move forward with the renovation, and Option 3 is a utilization of local Measure J funds to construct a new SEM Building.
OPTION 1 - Renovation of the Existing SEM Building with State Funds (FPP).
Advantages:
1. State Funds will potentially cover approximately 51% of the project cost ($24 million).
Disadvantages:
1. Delay project approximately one (1) year for funding.
2. Project will be limited to what the State has approved.
3. There is no room for growth.
4. Swing Space cost of approximately $10 million will be spent in modular labs that will later need to be removed and disposed of. This may also impact parking on campus.
5. The project will not allow the opportunity of building a viewing platform, crematorium, nor a
planetarium. The cost of building these new facilities at a later time will be approximately $1O
million.
6. Delaying the project after the community has approved the local bond for the renovation of the
Science building does not seem appropriate.
7. The State Bond needs to be on the 2016 ballot for possible approval.
OPTION 2 - Renovate the Existing SEM Building using Local Bond funds.
Advantages:
1. The renovation Project can start a year sooner.
2. Planetarium, viewing platform and other improvements could be added to the project.
3. There will be more flexibility on the applied modification to meet the ever changing needs of the
instructional programs.
lloLR Group Science/Engineering/Math Building
![Page 10: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/10.jpg)
Disadvantages:
1. The existing SEM Building structure will limit the opportunities for program growth.
2. District would forfeit the $24 million from the State Bond.
3. Swing Space cost of approximately $10 million will spent in modular labs that will later need to be
removed and disposed of. This may impact parking on campus as well.
4. A Planetarium building will still be needed according to the Educational Master Plan
5. The cost of building the Planetarium is approximately $10 million.
OPTION 3 - Build a New SEM Building using Local Bond at New Proposed Location.
Advantages:
1. The new building could be built to meet the current needs and plans for future growth. 2. The existing SEM Building will be used to avoid the expenses of swing space (estimated at $10
million).
3. The new Planetarium and viewing platform could be included in the design of the new SEM
Building.
4. The cost of building these facilities in the future would be saved (approximately $10 million).
5. The existing SEM Building could also be used for swing space for the many future building
modifications planned in the local bond. This would also save a significant amount over the 20
years of the bond.
6. The Educational Master Plan projects the need for a new instructional building in the next 20
years. The existing SEM Building could be re-purposed and re-programmed to be that building.
Disadvantages:
1. Would forfeit the $24 million from the State Bond.
2. Parking will be impacted by the placement of the new SEM Building.
3. College may need to build a new parking structure.
The District's Board of Trustees will need to weigh the options and provide direction to the College on the
desired option and/or course of action relative to the SEM Building.
DLR Group Science/Engineering/Math Building
![Page 11: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/11.jpg)
ARCHITECTURAL
![Page 12: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/12.jpg)
![Page 13: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/13.jpg)
Cypress College, Cypress, California
1
ARCHITECUTRAL ASSESSMENT
Introduction
Cypress College is located at 9200 Valley View Street, south of the intersection of Valley View Street and
Lincoln Avenue, The Science/Engineering/Math (SEM) building is located at the north end of the campus
off of College Circle Drive and west of Parking Lot 7,
The three story, concrete building houses classrooms, laboratories, offices and two lecture halls, One
elevator is provided to serve all floors, At the west elevation of the building, at the second floor, a bridge
system is present connecting the SEM building to the Humanities building to the north and the Fine Arts
building to the west On grade faculty and student parking is located east of the building in Parking Lot 7,
The following report is a based on a visual review of the roof, exterior building envelope, accessible
components, structural, mechanical, plumbing and electrical systems relative to the 2013 California
Building Code, The accessible components reviewed consisted of the parking, path of travel from the
parking to the entry, review of the restrooms and review of the general accessible components, All
accessible requirements for each accessible component were not checked, Since the review was only
cursory in nature, it is recommended that a complete field investigation to determine the full scope of work
to correct any deficient items be conducted,
The following existing drawings were available for review in the preparation of this report,
• TS, SD1, SD2, SD3, SD4, C1, C2, C3, C4, 1A, 2A, 3A, 4A, 5A, 6A, 7A, SA, 9A, 10A, 11A, 12A,
13A, 14A, 15A, 16A, 17A, 18A, 19A, 20A, 21A, 22A, 23A, 24A, 25A, 26A, 27A, 28A, 29A, 30A,
31A, 32A, 33A, 34A and 35A,
• M-2A, M-3A, M-4A, M-1B, M-2B, M-3B, P-1A, E-5A, E-6A, E-7A, E-SA, E-9A, E-10A, E-11A, E-
12A, E-1B, E-2B, E-3B, E-48, E-58, E-68, E-78, C-3(?, Business building) C-4(?, Business
building)
• E-1T, E-2T, E-2A, E-3A, E-4A, and E-5A
Photographs included in the report were taken to illustrate the conditions documented in the report and are for general reierence,
DLR Ciroup Science/Engineering/Math Building
![Page 14: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/14.jpg)
ffti; DLR (Jroup Science/Engineering/Math Building
Cypress College, Cypress, California
2
I. OBSERVATIONS
A. Roof
1. Stair No. 1 located at the south side of the building provided roof access.
2. Four skylights were located in a north-south alignment near the center of the building.
a. The northern skylight was broken and mastic was applied onto the crack.
b. Skylight gasketing was dried and weathered. Caulking was applied over most of
the gasketing but the caulking was also dried and cracking.
![Page 15: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/15.jpg)
Cypress College, Cypress, California
3
3. Concrete equipment screen walls were located along the east and west elevations.
a. The concrete screen walls had no visible water repellant applied to the surface.
b. The top surface of the wall was sloped to prevent moisture build up on the wall.
c. Vertical cracks in the wall were observed at two locations.
4. Most of the mechanical equipment was positioned within the equipment screen walls.
a. Equipment pads and curbs of various types were observed.
b. The top horizontal surface of the concrete equipment pads were not protected from the weather.
c. Rooftop conduit and piping was supported on wood blocks which were set on the
traffic pads.
ii£i DLR {foup Science/Engineering/Math Building
![Page 16: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/16.jpg)
Cypress College, Cypress, California
4
5. A total of eight (8) roof drains were observed on the roof.
a. No overflow roof drains or scuppers were observed.
b. The roof was sloped down away from the roofs perimeter edges.
6. The roof access door and frame were rusted and holes in the frame were observed.
B. Roofing System
1. The roofing system of the building consisted of a built-up asphalt roofing system with a
granule-surfaced cap sheet.
![Page 17: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/17.jpg)
(Jroup Science/Engineering/Math Building
Cypress College, Cypress, California
4
a. Surface cracking or "alligatoring" of the cap sheet was observed throughout the
roof.
b. Cracked and dried mastic was observed throughout the roof.
2. Foil faced flashing was installed at base of wall and parapet top conditions.
3. At the parapet tops, the foil flashing terminated on the horizontal surface.
4. Parapet coping was not observed.
5. At the base of the wall conditions. a sheet metal reglet and counterflashing was set into the wall with the roofing system tucked under the counterflashing.
a. Loose reglets were observed in some locations.
![Page 18: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/18.jpg)
DLR (rouµ Science/Engineering/Math Building Cypress College, Cypress, California
6
6. Lead flashing at vent pipe penetrations were observed.
a. The lead flashing was wrapped into the pipe at the top.
b. At one observed condition, a sheet metal sleeve flashing was installed and
caulked where the sleeve terminated on the pipe.
C. Building Enclosure
1. The exterior walls of the building were constructed of cast-in-place structural concrete and aluminum storefront window system.
![Page 19: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/19.jpg)
5_: DLR (:Jroup Science/Engineering/Math Building Cypress College, Cypress, California
6
2. The east and west exterior walls of the stair shafts were finished with ceramic tile applied over the concrete wall, red tile at the east elevation and blue tile at the west
elevation.
3. At the second floor of the west elevation, the building was connected to an exterior
bridge system which connected with some of surrounding buildings.
4. At the third floor of the south elevation, a slope glass roof enclosed a greenhouse.
5. No significant cracks in the structural concrete walls were observed.
6. The concrete walls appeared to be in good condition.
![Page 20: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/20.jpg)
DLR CJroup Science/Engineering/Math Building Cypress College, Cypress, California
8
7. At the north, east and west elevations, in ground planters abutted the building wall.
a. The planters abutted both the concrete walls and storefront windows of the
building.
b. Water from the landscape sprinklers was observed hitting the lower panes of the storefront window system.
![Page 21: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/21.jpg)
;, DLR (roup Science/Engineering/Math Building
Cypress College, Cypress, California
8
8. At the aluminum window system. water intrusion was observed in various locations at
the window sill.
a. Weep holes along the exterior of the window sill were not observed.
b. The rubber window gaskets had shrunk and large gaps were observed in the
corners of some of the windows.
c. Water intrusion was evidenced by the stains and efflorescence on the window
system and floor.
![Page 22: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/22.jpg)
l!isoLR Science/Engineering/Math BuHding Cypress College, Cypress, California
10
9, On the first floor, at the west elevation, just south of the center entry, evidence of water
intrusion through a crack at the second floor exterior bridge was observed,
a, Water stains were observed on the vertical mullion adjacent to the crack in
addition to the discoloration of the stained wood railing at the window,
0, Interior Observations
1, At the first and second floors, a few areas with stained ceiling tiles were observed,
![Page 23: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/23.jpg)
Science/Engineering/Math Building Cypress College, Cypress, California
11
2. At the second floor, overlooking the west lobby, a guardrail with vertical pickets
bordered the two story space.
a. The top of the guardrail was 42 1/2-inches above the finish floor.
b. Along the bottom of the rail was a 4-inch high by 3-inch wide curb.
c. The 1/2-inch wide pickets were spaced 6-inches on center.
LDLR: (roup Science/Engineering/Math Building
![Page 24: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/24.jpg)
Science/Engineering/Math Building Cypress College, Cypress, California
12
E. Accessible Parking
1. Four parking stalls identified with the International Symbol of Accessibility were located
in Lot 7, the parking lot directly across from the east entry.
2. These stalls each measured 9'-0" wide by 14'-6" deep to the interior or front curb.
3 The northern loading/unloading area was 5'-0" wide and the remaining two were 9'-0"
wide.
a. The stripped area of these loading/unloading areas were 16'-0" deep.
b. 1'-6" of this area was located in the drive aisle.
c. "No Parking" in 12-inch high lettering was marked in the striped
loading/unloading area.
5. The International Symbol of Accessibility was 3'-3" square.
6. The post mounted sign in the grass area at the front end of the stall stated "Reserved"
with the International Symbol of Accessibility.
a. The signs were 18 inches high by 12-inches wide.
b. The height to the bottom of the sign was 6'-5".
c. Van accessible parking was not identified.
LoLR Science/Engineering/Math Building
![Page 25: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/25.jpg)
Science/Engineering/Math Building Cypress College, Cypress, California
13
7. A striped path was marked from the loading/unloading areas to the curb ramp.
a. The striped path was routed behind parked cars others than the stall that it was
serving.
b. The slope of the striped path was measured at 4.9% near the curb ramp.
c. The slope of the striped path was measured at 3.0% parallel to the path of travel.
d. The cross slope was measure at 3.6% along the drive aisle.
e. Depressions and dips in the striped path were observed.
![Page 26: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/26.jpg)
Science/Engineering/Math Building Cypress College, Cypress, California
14
8. Curb ramp
a. The center portion of the curb ramp was measured at 10.2%.
b. The side slopes were measured at 20.9%.
F. Accessible Path of Travel to East Building Entry
1. The slope of the walk at the top of the curb ramp parallel to the ramp (running slope)
was measured at 3.3%.
2. Parallel to the curb in front of the east entry. the cross slope of the walk was measured
at 4.1%.
![Page 27: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/27.jpg)
Science/Engineering/Math Building Cypress College, Cypress, California
15
3. At other areas of the walk leading to the east entry, the slope was measured at 2.0% or
less.
4. The surface mounted emergency telephone enclosure projected out 7 3/4-inches from
the face of the wall.
5. Automatic sliding double doors were observed at the east building entry.
a. The same type of doors were observed at the center entries located at the south
and west elevations.
G. General Interior Accessible Path of Travel
1. The corridors of the building were less than 2% slope in all directions.
a. On the first floor, at the west side near the stairs, a depression around a cleanout
in the hallway was observed. Also a raised door catch was observed.
![Page 28: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/28.jpg)
Science/Engineering/Math Building Cypress College, Cypress, California
16
2. At the majority of the doors, round door knobs were observed.
a. The center of the knobs were measured at 38-inches above the finish floor.
3. Electrical receptacles and other low mounted devices and controls were generally
measured at 10-inches to the bottom of the box.
4. Switches, thermostats and other high mounted devices and controls were generally measured at 53-inches to the top of the box.
![Page 29: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/29.jpg)
(roup Science/Engineering/Math Building
Cypress College, Cypress, California
17
5. In various random locations, wall mounted pencil sharpeners were observed. The
sharpeners projected out 5-inches from the wall.
6. Surface mounted fire alarm pulls with protective covers were observed. The protective
covers projected 5-inches from the wall.
7. Surface mounted fire extinguisher cabinets project out 5 3/4-inches from the wall.
lliK DLR Coup Science/Engineering/Math Building
![Page 30: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/30.jpg)
Cypress College, Cypress, California
17
8. At the west lobby, the clear height under the central concrete stair mid-landing was 81
112-inches.
9) On the south side of the second floor, at the study cubicles, a television mounted was suspended from the ceiling. The bottom edge of the television was measured at 78
314-inches.
10) The fire alarm strobes were mounted at various heights with some less than 80-inches
above the finish floor.
![Page 31: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/31.jpg)
,,,DLR Group Science/Engineering/Math Building Cypress College, Cypress, California
19
11) At the first floor, a wall mounted telephone projects out 5 1/2-inches from the wall.
12) In the classrooms, pull strings or handles for suspended maps, charts projection
screens were higher than 48-inches above the finish floor.
13) Classrooms with raised platforms for the instructor's desks or stations were not accessible. The platforms were measured at 7-inches high.
![Page 32: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/32.jpg)
DLR Croop Science/Engineering/Math Building Cypress College, Cypress, California
19
14) In the two lecture halls, the instructor's raised platform was only accessible by steps,
H, Accessible Restrooms
1, At the first floor, one Women's and one Men's restroom were observed,
a, The Women's restroom was not fully compliant with accessibility Codes although
some modifications had been made in an attempt to comply,
1) The number of water closets in the restroom was reduced to one to provide
a larger water closet stalL
2) At the entry door, on the pull side of the door, a 12 1/2-inch clear space on
the strike side was provided,
![Page 33: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/33.jpg)
DLR (rour Science/Engineering/Math Building Cypress College, Cypress, Callfornia
21
3) On the push side of the door, a 9-inch clear space was provided at the
strike side.
4) The door signage was mounted 65 1/2-inches above the finish floor. No
wall signage was provided.
5) The stall dimensions were 79-inches wide by 98-inches long with a 34 1/4-
inch clear opening door.
![Page 34: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/34.jpg)
(.roup Science/Engineering/Math Building Cypress College, Cypress, California
21
6) The stall door did not self-close.
7) The stall door latching mechanism required grabbing to operate.
8) The coat hook was 68-inches above the finish floor.
![Page 35: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/35.jpg)
23
9) The water closet was centered 18-inches from the wall.
10) The flush handle was located on the narrow side of the stall.
11) The height of the seat was 18-inches above the finish floor.
![Page 36: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/36.jpg)
!h_DLR (iroup Science/Engineering/Math Building
Cypress College, Cypress, California
23
12) The rear grab bar was 36-inches long, 34-inches from the floor to the top of the bar and 6-inches from the corner,
13) The side grab bar was 52-inches long, 33 314-inches from the floor to the top of the bar, started at the rear wall and extended 2'-2" past the front of the water closet
14) The toilet paper dispenser was 19-inches above the finish floor and 2-
inches in front of the water closet
) DLR (;roup Science/Engineering/Math Building
Cypress College, Cypress, California
![Page 37: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/37.jpg)
25
15) The seat cover dispenser was 45-inches above the finish floor.
16) A 36-inch long by 12-inch deep shelf was positioned on the wall opposite
the water closet.
17) The top of the lavatory was 30 3/4-inches above the finish floor and the
bottom 27 1/2-inches.
18) The soap dispenser was 36-inches above the finish floor.
![Page 38: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/38.jpg)
,t--· DLR (Jroup Science/Engineerlng! Math Building
Cypress College, Cypress, California
25
19) The air hand dryer was 34 1/2-inches above the finish floor and projected 6 3/4-inches from the wall.
20) The mirror was 48 1/4-inches above the finish floor to the reflective
surface.
b. The Men's restroom was not fully compliant with accessibility Codes although some modifications had been made in an attempt to comply.
1) The number of water closets in the restroom was reduced to one to provide
a larger water closet stall.
2) On the push side of the door, an 8 1/2-inch clear space was provided at the
strike side.
Croup Science/Engineering/Math Building Cypress College, Cypress. California
![Page 39: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/39.jpg)
Cypress College, Cypress, California
27
3) The door signage was mounted 65 1/2-inches above the finish floor. No wall signage was provided.
4) The stall dimensions were 66 3/4-inches wide by 114-inches long with a 34
1/2-inch clear opening door.
5) The stall door did not self-close.
6) The stall door latching mechanism required grabbing to operate.
7) The coat hook was 65-inches above the finish floor.
![Page 40: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/40.jpg)
DLR (Jroup Science/Engineering/Math Building
Cypress College, Cypress, California
27
8) The water closet was centered 17 3/8-inches from the wall.
9) The flush valve was located on the wide side of the stall.
10) The height of the seat was 17 1/4-inches above the finish floor.
11) The rear grab bar was 36-inches long. 34-inches from the floor to the top of
the bar and 6-inches from the corner.
\c/; DlR (roup Science/Engineering/Math Building
![Page 41: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/41.jpg)
DLR Croup Science/Engineering/Math Building
Cypress College, Cypress, California
29
12) The side grab bar was 52-inches long, 33 3/4-inches from the floor to the
top of the bar, started at the rear wall and extended 2'-2" past the front of
the water closet.
13) The toilet paper dispenser was 19-inches above the finish floor and 2- inches in front of the water closet.
14) The seat cover dispenser was 56-inches above the finish floor.
15) Two urinals were provided mounted in the same position.
17) The urinal rim was 24 1/2-inches above the finish floor.
18) The urinal rim projected out 15-inches from the wall.
![Page 42: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/42.jpg)
Cypress College, Cypress, California
30
19) The urinal flush handle was mounted 52-inches above the finish floor.
20) The top of the lavatory was 30-inches above the finish floor and the bottom 26 3/4-inches.
21) The soap dispenser was 36-inches above the finish floor.
22) The air hand dryer was 36-inches above the finish floor and projected 6
3/4-inches from the wall.
Science/Engineering/Math Building
![Page 43: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/43.jpg)
31
23) The mirror was 55 1/4-inches above the finish floor to the reflective surface.
24) The top of the electrical receptacle was 43 1/2-inches above the finish floor.
c. The drinking fountain located in the hallway did not comply with accessibility
requirements.
2. At the second floor. one Women's and one Men's restroom were observed.
a. In the Women's restroom, no significant modifications had been made in an
attempt to comply with accessibility requirements.
DLR' (.Jroup Science/Engineering/Math Building
Cypress College, Cypress, California
![Page 44: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/44.jpg)
;;DLR (roup Science/Engineering/Math Building
Cypress College, Cypress, California
32
b. In the Men's restroom, no significant modifications had been made in an attempt
to comply with accessibility requirements.
c. The drinking fountain located in the hallway did not comply with accessibility requirements.
3. At the third floor, one Women's restroom and one Men's restroom were observed.
a. Jn the Women's restroom, no significant modifications had been made in an
attempt to comply with accessibility requirements.
![Page 45: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/45.jpg)
33
1) The floor of the restroom vestibule sloped up to the restroom floor.
2) The slope was measured at 4.1%.
b. In the Men·s restroom, no significant modifications had been made in an attempt
to comply with accessibility requirements.
1) The slope of the restroom vestibule sloped up to the restroom floor.
2) The slope was measured at 4.2%.
c. The drinking fountain located in the hallway did not comply with accessibility
requirements.
I. Stairs
1. The west, east and south stairs in the stairways were similarly designed and
constructed.
Science/Engineering/Math Building
Cypress College, Cypress. California
![Page 46: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/46.jpg)
'DLR Science/Engineering/Math Building
Cypress College, Cypress, California
34
a. The stair treads and risers are cast-in-place concrete with rubber flooring on the treads and risers.
b. Contrasting striping was not observed at the upper approach or lower tread of
any stair run.
c. The top of the handrail was measured to be 34-inches at the stair runs and 33-
inches at the landing.
d. A clear space of 2 7/8-inches was measured between the handrail and wall.
e. The wooden handrail was 2-inches wide by 8-inches high.
f. Handrail extensions of 24-inches at the bottom and 12-inches at the top were
measure.
g. At the south stair, at the run from the third floor to the roof, steel pipe handrails
and bare concrete treads and risers were observed.
![Page 47: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/47.jpg)
Cypress College, Cypress, California
35
2. The west stair in the two story lobby was a concrete floating stair.
a. The stair treads and risers were cast-in-place concrete with rubber flooring on the
treads and risers.
b. Contrasting striping was not observed at the upper approach or lower tread of
any stair run.
c. The top of the handrail was measured to be 32-inches at the stair runs and 41-
inches at the landing and handrail extensions.
J. Elevator
1. The building was served by one elevator located near the center of the building.
2. The cab was 80-inches in width and 51-inches in depth at the side panel and 55-inches
in depth at the door.
3. A 36-inch wide clear side opening door provided access to the cab.
l!G.DLR Croup Science/Engineering/Math Building
![Page 48: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/48.jpg)
36
4. Handrails installed at 37 1/2-inches to the top, were provide on back and side walls of
the elevator cab.
5. The elevator control panel was mounted less than 48-inches above the finish floor to
the top button.
6. Hall lanterns were measured to be centered 60 1/2-inches above the finish floor.
Science/Engineering/Math Building
Cypress College, Cypress, California
![Page 49: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/49.jpg)
Cypress College, Cypress, California
37
7. Foor landing numbers were measured to be centered 60-inches above the finish floor.
7. Call buttons were centered 42-inches above the finish floor.
8. An audible signal sounded for each floor.
DLR Croup
Science/Engineering/Math Building
![Page 50: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/50.jpg)
38
II. ANALYSIS AND RECOMMENDATIONS
A. Roof
1. The roof access door and frame is rusted and holes in the frame will allow moisture
intrusion into the building.
2. The skylight gasketing had deteriorated and caulking was applied to seal the skylight
assembly. However, the caulking has also dried out.
3. Cracks in the concrete equipment screen walls will allow moisture intrusion and
promote concrete degradation and rusting of concrete reinforcing.
4. At the equipment pads, the exposed horizontal concrete surface can allow moisture
intrusion into the concrete and building.
5. The lack of roof overflow drains will result in ponding water until the drainage area of
the drain reaches a depth to spill to the adjacent drain or over the roof edge.
6. Recommendations:
a. Remove and replace the roof access door and frame.
b. Replace the skylights.
c. Seal cracks in the concrete equipment screen walls with
d. Apply clear liquid waterproofing to the concrete screen walls to minimize water
absorption.
c. Provide sheet metal equipment pad covers.
d. Fix al/ leaking valves and equipment.
f. Replace the wood supports under the piping and conduit runs with metal support
trapezes or rubberized blocks compatible with the roofing system.
g. Add roof overflow drains.
B. Roofing System
1. The roofing system has reached the end of its useful life as evidenced by the cracking
in the roof membrane and deterioration of the roof flashing details.
2. The lack of a coping depends upon the adhesion of the roofing system to the concrete
parapet wall to prevent water intrusion.
3. A coping will also help protect the top surface of the concrete parapet walls from
absorbing moisture.
4. Recommendations:
a. Remove and replace the roofing system.
liffiDLR Science/Engineering/Math Building
![Page 51: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/51.jpg)
Cypress College, Cypress, California
39
Cypress Col!ege, Cypress, California
![Page 52: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/52.jpg)
![Page 53: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/53.jpg)
<rour Science/Engineering/Math Building
Cypress College, Cypress, California
39
b. Provide sheet metal coping at the top of the parapets.
c. At the pipe penetrations, provide new flashings compatible with the roofing
system.
d. Remove and reinstall reglets and counterflashings if the design and locations are
compatible with the new roofing system.
C. Building Enclosure
1. The exterior concrete walls appeared to be in good condition.
2. The storefront window system gasketing has shrunk and deteriorated and is beyond its
useful life.
3. Recommendations:
a. Apply a clear liquid waterproofing to the concrete surface to minimize moisture
absorption.
b. Remove and replace all window gasketing or provide a combination of gasketing
and wet sealing the glass.
c. Provide weep holes in the window system sill.
d. Adjust the direction of the landscape irrigation away from the windows.
e. Adjust the strength of the sprinkler irrigation spray to stop short of the windows.
D. Interior Observations
1. The stains observed at the first and second floor ceilings were most likely the result of dripping or leaking plumbing pipes and not from water intrusion from the exterior of the building.
2. The top of the guardrails were in compliance with current Code.
a. The presence of the 4-inch high curb has been argued to provide a step thereby
reducing the effective height of the guardrail.
3. The clear space of the guardrail pickets does not comply with Code requirement of less than 4-inches.
4. Recommendations:
a. Confirm that the leaking above the ceiling was the result of a leaking pipe or
valve and that the condition was corrected.
b. Add a decorative sloped cap to the top of the curb to prevent the appearance of
step and make it more difficult to stand on.
c. Add an additional picket or infill panel between the prickets to comply with the
clear space requirement.
![Page 54: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/54.jpg)
40
E. Accessible Parking
1. The accessible parking depth does not comply with the Code requirement of 18'-0".
2. The length of the loading and unloading area does not comply with the Code of 18'-0".
3. Code compliant accessibility parking signage is missing.
4. Additional signage addressing unauthorized parking in accessible spaces is missing.
5. Signage identifying van parking is missing.
5. Directional signage to the accessible entry is missing.
6. Recommendation:
a. Redesign the parking layout to comply with Code.
b. Provide Code compliant parking signage and directional signage.
c. Grade the accessible path to the sidewalk to comply with Code allowed slopes
and cross slopes.
F. Accessible Path of Travel to East Building Entry
1. At the curb ramp, the flared sides exceeded the maximum Code allowed slope of 1:1O
or 10%.
2. For the path of travel, the maximum running slope or slope in the direction of travel is
1:20 or 5%.
3. For the path of travel, the maximum cross slope is 1:50 or 2%.
4. Recommendation:
a. Reconstruct the perpendicular curb ramp to comply with Code.
b. Identify an accessible path to the building entry or regrade the walkway for the
slopes to comply with Code.
G. General Interior Accessibility
1. The general items observed to be not compliant with Codes were throughout the
building.
2. Recommendation:
a. Correct the items that are noncompliant along the accessible path of travel and in
the area or space of work.
b. Replace door knobs with levers or other hardware that does not require grasping
or twisting.
Croup Science/Engineering/Math Building
Cypress College. Cypress, California
![Page 55: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/55.jpg)
42
c. Electrical receptacles and other low mounted devices and controls should be relocated so that the bottom of the box is a minimum of 15-inches above the
finish floor.
d. Switches. thermostats and other high mounted devices and controls should be relocated so that the top of the box is a maximum of 48-inches above the finish floor.
e. Remove the projecting wall pencil sharpeners or provide barriers to comply with
Code to alert someone of the projection.
f. Relocate projecting wall mounted fire alarm pulls or provide barriers to comply
with Code to alert someone of the projection.
g. Relocate projecting fire extinguishers and cabinets or provide barriers to comply
with Code to alert someone of the projection.
h. At the west lobby, under the first run from the first floor to the mid-landing,
provide barriers to comply with Code to alert someone of the reduced overhead clearance.
i. On the south side of the second floor, at the study cubicles, raise the suspended TV to provide a minimum of 80-inches vertical clearance.
j. Adjust the height of the fire alarm strobes so that the entire lens is a minimum 80-
inhces and a maximum of 96-inches above the finish floor.
k. If the scope of work is in a classroom, provide pull strings and handles for
suspended maps, charts and projection screens within the accessible reach
range.
I. If the scope of work is in a classroom or lecture halls, provide access to the
raised platforms.
H. Restrooms
1. The first floor restrooms. where some modifications have been made, may be able to
be fully comply with accessibility Codes.
a. Some relocation and/or removal of walls are necessary to make the entry
comply.
b. Total fixture count required for the building should also be analyzed as required
by the Plumbing Code.
2. In the first floor Women's restroom:
a. Relocate the door signage.
b. Provide and locate proper wall signage.
c. Correct the water closet stall door to self-close.
d. Replace the latching mechanism.
![Page 56: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/56.jpg)
Science/Engineering/Math Building
Cypress College, Cypress, Callfornia
41
e. Relocate the coat hook.
f. Reverse the location of the flush handle to the wide side of the stall.
g. Relocate the toilet paper dispenser.
h. Relocate the seat cover dispenser.
i. Relocate one lavatory.
j. Relocate the mirror.
3. In the first floor Men's restroom:
a. Relocate the door signage.
b. Provide and locate proper wall signage.
c. Correct the water closet stall door to self-close.
d. Replace the latching mechanism.
e. Relocate the coat hook.
f. Relocate the toilet paper dispenser.
g. Relocate the seat cover dispenser.
h. Relocate one urinal.
h. Relocate one lavatory.
j. Relocate the mirror.
4. The second and third floor restrooms do not comply with the accessibility Codes.
a. Full compliance will require a complete renovation involving removal of some
fixtures and relocation and/or removal of some walls.
b. At the third floor restroom vestibule, the sloped floor of the vestibule does not
comply with accessibility Codes for a level landing on either side of a door.
5. Recommendation - restrooms:
a. Complete the renovation of the first floor restrooms and entries to comply with
accessibility Codes.
b. Completely renovate the second and third floor restroom entries and restrooms to
comply with Code.
6. Recommendation - drinking fountains:
a. Provide dual height accessible drinking fountains.
Science/Engineering/Math Building
Cypress College, Cypress, California
![Page 57: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/57.jpg)
42
b. Provide pedestrian protection at the drinking fountains to comply with Code.
I. Stair
1. The stair tread and risers dimensions are in compliance with Code.
2. Contrasting striping was missing from the stairs.
3. Handrail grip size was not in compliance with Code.
4. Recommendations:
a. Provide contrasting striping at the upper landing and lower tread of each stair
run.
b. Depending upon the total scope of work of a future project or projects.
compliance may be required.
J. Elevator
1. The elevator is generally in compliance with Code.
a. Some isolated components are not in strict compliance with Code such as the
cab handrail height and hall lantern height.
b. Use and time may have affected the timing and sound of the elevator.
2. Recommendation:
a. Contract with an elevator contractor to provide a full review of the elevator
mechanics and make adjustments and timing to bring the elevator into full
compliance.
Ill. Warranty and Limitations of this Report
The findings and conclusions in this report were prepared in accordance with general accepted
professional principles and practice in the field of architecture. This warrant is in lieu of all other
warranties, either expressed or implied.
![Page 58: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/58.jpg)
: DLR Ciroup Science/Engineering/Math Building
Cypress College, Cypress, California
43
STRUCTURAL
![Page 59: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/59.jpg)
Cypress College SEM Building
Preliminary Structural Evaluation (ASCE/SEI 31-03 Tier 1)
September 28, 2015
Table of Contents
1. Project Overview and Scope of Work ..................................................................................................... 1
1.1. Project Overview ............................................................................................................................. 2
1.2. Scope of Work ................................................................................................................................. 2
2. Existing Conditions and Observations .................................................................................................... 4
2.1. Existing Structural Drawings ........................................................................................................... 5
2.2. Building Systems Description .......................................................................................................... 5
2.2.1. General ................................................................................................................................... 4
2.2.2. Gravity System ....................................................................................................................... 8
2.2.3. Lateral Force Resisting System ........................................................................................... 13
2.2.4. Foundations .......................................................................................................................... 14
2.3. Site Visit and Observations ........................................................................................................... 14
2.3.1. General ................................................................................................................................. 14
2.3.2. Skylights. .............................................................................................................................. 16
3. Building Systems Evaluation (ASCE/SEI 31-03 Tier 1) ....................................................................... 18
3.1. General .......................................................................................................................................... 19
3.2. Performance Objective .................................................................................................................. 19
3.3. Site Seismicity ............................................................................................................................... 19
3.4. Required Checklists ...................................................................................................................... 21
3.5. Noncompliant Items ...................................................................................................................... 21
3.5.1. Basic Structural (Type C2) ................................................................................................... 21
3.5.2. Supplementary Structural (Type C2) ................................................................................... 22
3.5.3. Geologic Site Hazards and Foundations ............................................................................. 23
3.5.4. Basic Nonstructural .............................................................................................................. 23
3.5.5. Intermediate Nonstructural. .................................................................................................. 24
4. Recommendations and Next Steps ...................................................................................................... 25
5. References ............................................................................................................................................ 26
Appendix A - Completed ASCE/SEI 31-03 Checklists
Appendix B - Seismic Design Parameters Appendix C - Selected Site Photos
![Page 60: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/60.jpg)
75-15618-00 46
1. Project Overview and Scope of Work
![Page 61: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/61.jpg)
75-15618-00
PROJECT OVERVIEW
Cypress College has expressed the desire to evaluate the existing Science, Engineering and Mathematics (SEM) building to determine if the building structural systems require upgrades. Ultimately, the objective of the preliminary structural study is to identify what upgrades are required and to estimate costs for the required upgrades.
The SEM building is a three story building constructed in 1970-71 on the Cypress College campus in Cypress, California. The building is approximately 100,000 square feet. The building program consists primarily of classrooms, laboratories and offices and also includes mechanical/electrical rooms. a two-story entrance lobby, a greenhouse and a central lecture hall that slopes from the second level to ground level. The SEM building is currently still used for instruction with the exception of some classroom spaces which are vacant.
Figure 1: Building South Elevation Exterior as seen from South Elevation
SCOPE OF WORK
This report details the preliminary structural seismic study conducted for the SEM building according to American Society of Civil Engineers/Structural Engineering Institute (ASCE/SEI) Seismic Evaluation of Existing Buildings (31-03) Tier 1 criteria. A Tier 1 evaluation is a preliminary screening which determines whether or not the building requires seismic upgrades. It should be noted that the preliminary structural study does not identify what specific upgrades are required for the building and does not include a comprehensive analysis to determine the structural deficiencies in each member of the building. The Tier 1 study identifies only if
![Page 62: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/62.jpg)
75-15618-00 48
structural upgrades are required based on an initial screening. If upgrades are recommended as a result of the Tier 1 evaluation, a Tier 2 evaluation should be performed to identify exactly what upgrades are required. A Tier 2 study is not included in the scope of this report.
ASCE/SEI 31-03 defines two levels of performance objectives for buildings being evaluated: Life Safety (LS) and Immediate Occupancy (10). The Tier 1 assessment detailed in this report assumes the Life Safety performance objective for the SEM building. This is consistent with guidelines recommended in ASCE/SEI 31-03 since the building is not an essential facility such as a fire station or hospital. An evaluation assuming Immediate Occupancy performance objective per ASCEISEI 31-03 is outside the scope of this report.
The Tier 1 evaluation was performed for the SEM building only and does not include an evaluation of the surrounding buildings. The attached elevated pedestrian bridge/piazza is not included in the Tier 1 evaluation detailed in this report.
The following tasks were performed as part of the preliminary structural Tier 1 study:
• Review of existing structural drawings (provided by Owner)
• Site visit by DLR Group structural engineer to visually inspect the existing building
structure (Note: Destructive and non-destructive testing of the existing structure was not
performed as part of the site visit; visual inspection only)
• Identify code mandated structure upgrades, if any, that apply to the building
• Perform a structural evaluation of the building in accordance with ASCE/SEI 31-03
including applicable structural checklists
• Summarize findings of ASCEISEI 31-03 Tier 1 evaluation and evaluate any non
compliant items
• Provide recommendations to Owner based on Tier 1 evaluation and information
gathered
![Page 63: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/63.jpg)
75-15618-00
2. Existing Conditions and Observations
![Page 64: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/64.jpg)
![Page 65: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/65.jpg)
75-15618-00 5
EXISTING STRUCTURAL DRAWINGS
A set of structural drawings was provided by the Owner. The structural engineering firm listed
on the drawings is Martin & Associates of Los Angeles, California and the drawings are signed
by John A. Martin, the structural engineer of record, (Note: This firm is currently still practicing
as John A. Martin & Associates (JAMA) based in Los Angeles.) The Architect is listed as William
Blurock & Partners/Caudill, Rowlett, Scott Associated Architects. The drawings include a State
of California - Department of General Services Office of Architecture and Construction stamp
marked "Approved" and dated February 13, 1970.
The set appears to be an approved set of final construction drawings and does not indicate "as
built" anywhere on the set. No revision numbers or dates are listed on the set. The drawing set
includes two buildings: the SEM building (Building A), the Business building (Building B) and the
elevated pedestrian walkway piazza structure. Some structural details (e.g. joists, slabs and
foundations) apply to all buildings, as indicated on the sheets. The scope of this report is limited
to Building A.
The drawings provided are a partial set, missing the following sheets for Building A:
• General notes sheet(s)
• Sheet S-1T (slab-on-grade and foundation details)
• Sheet S-2T (foundation details)
• Sheet S-6A (stem walls under auditorium details)
Where information cannot be determined from the existing drawings (e.g. concrete strength not
available since the general notes not included in set), design assumptions will be made per
ASCE/SEI 31-03 recommendations.
BUILDING SYSTEMS DESCRIPTION
General
The SEM building is a three-story reinforced concrete (RC) building. The overall dimensions of
the building are approximately 150 feet in the East-West direction by 240 feet in the North-South
direction. The building footprint is rectangular at the roof and third floor with the exception of
some minor "notches" in the floorplate near the locations stairwell locations, and the stairwell
enclosures.
At the second floor, the east and west portions of the floorplate are stepped inward by
approximately 20 feet to create exterior double-height spaces. Exterior fin walls are provided at
these locations that span from the foundation to the third floor, oriented in the East-West
direction. The unbraced height of these exterior walls is approximately 24 feet. These walls are
exposed on the East and West exterior elevations and are a prominent architectural design
feature.
There are three main staircases located on the east, west and south sides of the building that
are enclosed by concrete walls. The stairwells are approximately 15 feet wide and 30 feet long
in plan. The outward facing ends of each stair are semi-circular in plan along the height of the
staircase structure and are a prominent design feature, visible from the building exterior.
![Page 66: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/66.jpg)
75-15618-00 6
A balcony is located on the second floor of the south elevation of the building. The balcony is approximately 20 feet by 30 feet. At the second floor, the west side of the building connects to the piazza structure.
Figure 2:
![Page 67: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/67.jpg)
75-15618-00 7
f.)!_F;....
if;;;:
Figure 3:
'"JV("
;-,h,JP
Figure 4: Roof Plan
![Page 68: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/68.jpg)
75-15618-00 8
Gravity System
Waffle Slab Floor System
The gravity system consists of a waffle slab floor system supported by RC cruciform gravity columns and RC walls. Columns are spaced at approximately 30 feet on center in each direction, typical.
The waffle slab floor system consists of 4 W' thick concrete slab with 1O" thick, 2'-0" deep joists spaced at 5'-0" on center typical throughout the floor each way (2'-4 %" total structural floor depth). At column locations, the recessed voids between joists are infilled to create solid column drop caps. These solid drop caps extend for one bay in each direction typical at interior columns, centered on the column. The infilled bays around the columns are 2'-2 W' thick, typical (the drop caps include a 2" reveal at the bottom between joists).
Slab reinforcement consists of #3 bars at 12" on center (OC) each way (EW) at slab midheight. Joist reinforcement varies depending on location in the building. Typical joist reinforcement is as follows:
• Typical Middle Strip Joists (M-61):
o Bot Bars: (2)-#7 continuous
o Top Bars @ supports: (2)-#7
o Top Bars @ midspan: (2)-#5
o Ties @ support (5' bay closest to support): #3 @ 1O" OC
o Ties @ midspan: #3 @ 12" OC (2"' floor), #3 @ 18" OC (3''& Roof)
• Typical Column Strip Joists (C-61):
o Bot Bars: (2)-#8 continuous
o Top Bars @ supports: (4)-#7
o Top Bars @ midspan: (2)-#5
o Ties @ support (5' bay closest to support): #3 @ 1O" OC
o Ties @ midspan: #3 @ 12" OC (2"' floor), #3 @ 18" OC (3''& Roof)
• Column Drop Caps:
o Top & Bot Bars: (6)-#5 EW
![Page 69: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/69.jpg)
75-15618-00 9
! t
! i i ' '--" -; L -
Figure 5: Typical Waffle Slab Plan
Figure 6: Typical Waffle Slab Floor Section
2ae £ il ,;;v,c
_
![Page 70: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/70.jpg)
75-15618-00 10
i 4 '
l:.' r:.:7;
a/hX!::f, e t/C'l'-
. r·,·--"_J
r!!:J'.''
Figure 7: Typical Waffle Slab Joist Section
bor·.s .c.-'J/'' i'.'.
Figure 8: Typical Column Drop Cap Section
![Page 71: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/71.jpg)
75-15618-00 11
Columns
Interior gravity columns are 30"x30" (outer dimension) cruciform sections, typical, The web thicknesses of the cruciform columns are 10" in each direction, typical, Columns around the building perimeter are either rectangular or L-shaped depending on the location, The perimeter columns are typically 1O" wide to match the perimeter wall thickness, Reinforcement for the columns varies depending on the location within the building, Typical reinforcement for the interior columns is as follows:
• Typical Interior Column (11E-14N):
o Longitudinal bars (Outer): (8)-#9 (2nd Floor), (8)-#8 (3"' & Roof)
o Longitudinal bars (Center): (4)-#5
o Ties: #3 @ 10" OC
9: Typical Drop Cap at Column
![Page 72: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/72.jpg)
75-15618-00 12
·;
Figure 10: Typical Cruciform Gravity Column Section
![Page 73: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/73.jpg)
75-15618-00 13
Bearing Walls
Bearing walls exist throughout the building, including the building perimeter, stairwells, elevator shaft and auditorium. These perimeter walls are typically 1O" thick. Reinforcement for all walls could not be determined based on the information provided since the typical wall reinforcing schedule (9/S-1T) was not provided in the existing drawing set. However, reinforcement configurations and attachments to floors is indicated for some of the perimeter walls as shown on sheets S-5A and S-9A
Lateral Force Resisting System
The lateral system consists of RC shear walls in both directions. The perimeter walls, stairwell walls, elevator core walls and auditorium walls will act as shear walls since they are tied directly into the floorplates at each level.
Due to the change in building floorplan at the second floor, the East and West perimeter shear walls are discontinuous at the second floor. The two shear walls in the North-South direction at each side of the auditorium extend from the foundation to the third floor (do not extend to roof)
Figure 11: Cruciform Gravity Column at Entrance Lobby Area
![Page 74: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/74.jpg)
75-15618-00 14
creating partial-height shear walls. Drag steel is indicated on the existing plans, extending from the auditorium walls into the waffle slab floor system on either side of the walls. Drag steel extending into the floorplate is also indicated at various stairwell walls at each level.
Foundations
The building foundation consists of RC piles with RC pile caps and tie beams. Continuous footings are provided below the interior and exterior walls spanning between pile cap locations. Slab-on-grade (SOG) is 4" thick.
Exact sizes of the foundation elements were not indicated on the drawings since the foundation sheets were not included in the existing set. Scaled from the existing drawings, the sizes of the rectangular pile caps range from approximately 3'x5'-6" to 10'x12'. The sizes of the hexagonal shaped pile caps range from approximately 4'x5' to 8'x9' outer dimensions. Axial load values for the pile groups are indicated at each pile cap on the foundation plan. These axial loads range from 11O kip to 1070 kip.
Reinforcement for the main foundation elements such as the piles, pile caps, tie grade beams and slab-on-grade could not be determined based on the drawings provided since the foundation detail sheets were missing from the set.
SITE VISIT & OBSERVATIONS
A site visit was conducted on September 2, 2015 to visually inspect the existing building structure and verify conditions indicated on the existing structural drawings.
General
Overall, the building closely resembles the structure indicated on the construction drawings provided with the exception of the skylights (see below). Much of the building structure (columns, walls, waffle slab floor system) is exposed at hallways and main circulation areas which allowed the direct measurement of some structural elements at various locations throughout the building, including:
• Column-to-column dimensions
• Wall dimensions
• Member thicknesses (columns, walls, exposed waffle slab floor system)
Spot measurements were taken at various locations throughout the building to verify the building dimensions and member sizes listed on plan. The sizes and dimensions measured match the design drawings for the areas surveyed. Certain portions of the structure were concealed by ceilings and/or flooring and could not be verified, such as the roof to wall connections within the classrooms. Based on the observed exposed structural components, there is no indication that the classroom areas differ from the design drawings.
The general condition of the concrete elements observed was very good with little to no visible cracking and/or damage. Some minor cracks were observed in a select number of elements; however, these were deemed to be cosmetic and probably caused by incremental shrinkage of the concrete over the life of the building. The observed cracks do not indicate any structural
![Page 75: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/75.jpg)
75-15618-00 15
damage. Very minor damage to column concrete surfaces was observed at the bases of some
gravity columns.
Figure 13: Minor Scratching on Concrete Surface at Base of Gravity Column
![Page 76: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/76.jpg)
75-15618-00 16
Skylights
The original structural and architectural construction drawings indicate a skylight design feature on the roof of the building consisting of skewed 6" RC walls, approximately 10 feet square in plan, approximately 9 feet tall. The existing condition does not match the construction drawings for the skylights: the existing skylights are low-profile domed plastic or polyethylene skylights attached directly to the roof (no other structure is provided above the roof). It is not known whether the existing skylights were originally installed in place of the skylights indicated on the construction drawings or if the original skylights were installed and have been replaced since installation.
Figure 14: Skylight Locations at Roof
![Page 77: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/77.jpg)
75-15618-00 17
f'i9ure ·15, originaTsi< 10 n per Exisiiri
Ii Drawin9s- -- - - ----
.YlT9h!Besi9 9
![Page 78: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/78.jpg)
1-- - 3. Building Systems Evaluation (ASCE/SEI 31- 03 Tier 1)
75-15618-00
![Page 79: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/79.jpg)
75-15618-00 19
TIER 1 ASSESSMENT
General
A preliminary seismic structural evaluation was performed according to ASCE/SEI 31-03 based
on building type, seismicity, and performance objective.
The Tier 1 assessment is based on information observed at the site during the site visit, the
existing structural plans provided by the Owner and other readily available resources, such as
building codes and seismic hazard maps. Where information could not be determined from any
of these sources, the checklist items are marked as "Noncompliant" indicating that further
investigation is required to determine whether these items meet the desired performance
objective. For example, wall reinforcement schedules were not provided in the existing structural
drawing set Since the reinforcement within the wall could not be observed in site, further
investigation is required to determine the bar sizes and spacing within the walls. Many non
structural items, such as ceiling attachments and light fixtures could not be determined since
they were not readily accessible during the site visit Further investigation is required for these
items to determine whether or not they are compliant per the Tier 1 analysis.
Performance Objective
A Life Safety (LS) performance objective was used for the SEM building Tier 1 assessment of
the structural and nonstructural components. This is consistent with ASCE/SEI 31-03
recommendations since the building is not deemed a critical/essential facility (e.g. fire station,
hospital). A Life Safety performance objective is defined by FEMA 356 as a post-earthquake
damage state that ensures partial or total structural collapse does not occur under the design
earthquake, and that damage to nonstructural items is not life-threatening. It should be noted
that the building is expected to sustain significant structural damage under a Life Safety
performance objective.
The SEM Building is classified as Type 9: Concrete Shear Walls with Stiff Diaphragms (C2) per
ASCE/SEI 31-03.
(With Stiff
Diaphragms)
Building Type 9: CONCRETE SHEAR WALLS
These buildings have floor and roof framing that consists of cast-in-place
concrete slabs, concrete beams, one-way joists, two-way waffle joists, or flat slabs. Floors are supported on concrete columns or bearing walls. Lateral forces are resisted by cast-in-place concrete shear walls. In older construction, shear walls are lightly reinforced but often extend throughout the building. In more recent construction, shear walls occur In isolated locations, are more heavily reinforced with concrete slabs, and are stiff relative to the wails. Foundations consist of concrete spread footings, mat foundations, or deep foundations.
Site Seismicity
No existing site-specific geotechnical design information was available for the building site. Therefore, mapped spectral acceleration parameters were used to determine the design
spectral acceleration parameters per ASCE/SEI 31-03.
I
![Page 80: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/80.jpg)
75-15618-00 20
Seismic acceleration parameters Sos and S01 were determined using the 2% probability of
exceedance mapped parameter values from American Society of Civil Engineers/Structural
Engineering Institute (ASCEISEI) Minimum Design Loads for Buildings and Other Structures (7-
05), consistent with ASCEISEI 31-03 methodology. Since no existing geotechnical information
was provided for the site, Site Class D was assumed per ASCE/SEI 31-03 guidelines.
ASCEISEI 31-03 categorizes the site as Low, Medium or High seismicity based on the design
spectral response values:
Table 2-1. Levels of Seismicity Definitions
Moderate <:0.167g
<0.500g
"'...-...-.J
;o0.067g ,
<0.200g
High <:0.500g i <:0.200g i
The Cypress SEM building site is classified as High seismicity. The seismic design parameters
for the SEM Building Tier 1 assessment are summarized below:
!
i I !
!
I
I
i, , I
Table 1: Se1sm1c Design Parameters per ASCEISEI 31-03 & 7-05
! Seismic Parameter Value
I Site Latitude 33.8289
! Site Longitude -118.0244
Occupancy Category 111
Site Class D
· Short-Period Mapped MCE Response Acceleration (Ss), g 1.422
1-Second Mapped MCE Response Acceleration (S1), g 0.513
Short-Period Site Coefficient (F,) 1.0
1-Second Site Coeff1c1ent (Fv) ! 1 5
I Adjusted Short-Period Mapped MCE Response Acceleration (SMs), g 1.422
j Adjusted 1-Second Mapped MCE Response Acceleration (SM1), g 0.770
Design Short-Period Response Acceleration (Sos), g 0.948
Design 1-Second Response Acceleration (S01), g 0.513
Seismic Design Category D
Level of Seismicity per ASCEISEI 31-03 High
Level of Seismici ty1
Sos So1
Low <0.167g <0.067g i
![Page 81: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/81.jpg)
'-- ,..
! Low I LS I i
I
I
!
Required Checklists
ASCE/SEI 31-03 requires the following checklists for the building based on seismicity and
performance level (High Seismicity, Life Safety performance objective):
• Basic Structural
• Supplemental Structural
• Geologic Site Hazard and Foundation
• Basic Nonstructural
• Intermediate Nonstructural
Table 3-2. Checklists Required for a Tier 1Evaluation 1
I I i Required Checkllsts
j Leve! I I I ' of Geologic Site
Leve! Level l Low j Basic Supplemental Hazard and Basic Intermediate Supplemental of of Seisrnicity Structunil Structural Foundation Nonstructural Nonstructural . Nonstructural
Seismtcity Periormancil 'I (Sec. 3.6) I {Sec. 3.7) (Sec. 3.7} {Sec. 3..S) (Sec. 3.9.1) (Sec, 3.9.2} (Soc. 3.9.3)
10 i ,.. ,.. i ,.. Moderate LS
10
,.. ,.. ",.". i ,.. ,.. ,.. ...
High LS I ,.. i ,.. ,.. ,.. ,..
' 10 ,.. I ,.. ,.. ,.. ,.. ,.. '
1A checkmark ( ) des'1gnates the checklist that must he completed for a Tier 1 Evaluatmn as a function of the level of seismrclty and level
of performance.
'ts = Ufe Safety;. 10 = Immediate Ot.-cupancy fdefined rn Section 2-4}. 3 Defmed in Section 2.5.
NoncompliantItems
Based on the Tier 1 evaluation, the following items were found to be noncompl'lant. These items
do not meet the required Life Safety performance objective and require further
investigation/action.
Basic Structural Checklist (Type C2)
Building System - Weak Story
• The shear wall strength of the North-South walls below the 3'' Floor is less than 80% of
the North-South walls below the Roof
• The shear wall strength in the East-West walls below the Roof is less than 80% of the
East-West walls below the 3'' Floor
o Recommendation: A Tier 2 dynamic analysis should be performed to evaluate
the capacity of the shear walls at locations of strength discontinuities.
Building System - Soft Story
• The shear wall stiffness of the North-South walls below the 3'' Floor is approximately
70% of the North-South walls below the Roof
o Recommendation: A Tier 2 dynamic analysis should be performed to evaluate
the potential for soft-story failure of the shear walls below the 3'' Floor.
75-15618-00
![Page 82: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/82.jpg)
75-15618-00 22
Building System - Geometry
• The horizontal dimension of the East-West shear walls below the 3'd Floor is greater
than 30% of the East-West walls below the Roof
o Recommendation: A Tier 2 dynamic analysis should be performed to evaluate
any uneven distributions of seismic forces which may lead to unexpected higher
mode effects and demand concentrations.
Building System - Vertical Discontinuities
• Portions of the North-South shear walls at gridlines SE and 13E are discontinuous at the
3'd Floor
o Recommendation: A Tier 2 analysis should be performed to check the 3"' Floor
diaphragm for the transfer of shear forces from the walls below the Roof to the
adjacent North-South auditorium walls below the 3'd Floor. Drags/collectors at
wall elements should also be checked for adequate embedment into diaphragms.
Lateral-Force-Resisting System - Reinforcing Steel
• Wall reinforcement could not be determined based on the existing drawings
o Recommendation: Wall reinforcement should be determined using destructive or
non-destructive testing on the walls in order to verify size and spacing of bars.
Supplemental Structural Checklist (Type C2)
Diaphragms - Diaphragm Continuity
• Internal expansion joints occur at the 2nd Floor diaphragm on the West side of the
building near the attached piazza structure
o Recommendation: A Tier 2 analysis should be performed to ensure a lateral load
path is provided around the expansion joints at the 2nd Floor.
Diaphragms - Openings at Shear Waifs
• Openings greater than 25% of the wall length occur immediately adjacent to many shear
walls throughout the building
o Recommendation: Shear transfer from diaphragms to walls (and walls to
diaphragms at transfer levels). including embedment of drags/collectors into
diaphragms should be checked via a Tier 2 analysis.
Connections - Uplift at Pile Caps
• Pile cap reinforcement could not be determined based on the existing drawings
o Recommendation: Pile cap reinforcement should be determined using
destructive or non-destructive testing in order to verify top bars and anchorage to
pile caps.
![Page 83: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/83.jpg)
75-15618-00 23
Geologic Site Hazards and Foundations Checklist
Geologic Site Hazards - Liquefaction
• The site is located in a potential liquefaction zone as defined by the State of California
Seismic Hazard Zones maps (see Reference 5)
o Recommendation: A geotechnical evaluation should be performed to identify
liquefaction potential at site and building susceptibility to liquefaction, if
applicable.
Geologic Site Hazards - Surface Fault Rupture
• The site is located within a mile of the Anaheim fault (Fl D: 363) as documented by
Caltrans (Reference 6)
o Recommendation: A geotechnical/seismicity evaluation should be performed to
determine the seismic hazard including near-fault effects and site conditions. A
Tier 2 analysis of the structure should be performed including the updated
geotechnical/seismic study.
Basic Nonstructural Component Checklist
The following nonstructural items were found to be noncompliant based on the Tier 1
assessment. Some of the following items could not be observed during the initial site visit. For
these ·items, assumptions are made based on building age.
The ceiling was removed at one location to observe attachments for the ceiling system and any
exposed ducts, piping and lighting. The observed conditions were assumed to apply at all
ceiling locations.
Light Fixtures - Emergency Lighting
• Light fixtures are not braced
o Recommendation: Braces for the light fixtures should be installed.
Building Contents & Furnishing - Tall Narrow Contents
• Not all contents over 4 feet tall are anchored to slabs or adjacent walls
o Recommendation: Anchors/straps should be installed on items such as file
cabinets and storage racks to affix these items to floors and walls to prevent
overturning during the Life Safety design earthquake.
Mechanical and Electrical Components - Deterioration
• Indoor equipment is compliant; outdoor equipment is rusted
o Recommendation: Replace/retrofit equipment per Mechanical recommendations.
Piping - Fire Suppression Piping
• Bracing/anchorage for fire suppression piping was not observed
o Recommendation: Replace/retrofit piping with compliant anchorage per
Mechanical recommendations.
![Page 84: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/84.jpg)
75-15618-00 24
Piping - Flexible Couplings
• Flexible couplings were not observed
o Recommendation: Provide flexible couplings capable of undergoing expected
building movement/drift based on a Tier 2 analysis. If required, retrofit or replace
existing piping to include flexible couplings.
Hazardous Materials and Storage Distribution - Toxic Substances
• Toxic substances were not observed
o Recommendation: Provide additional restraints for storage of toxic substances as
required using latched doors, shelf lips, wires or other methods to achieve Life
Safety performance objective. Follow manufacturer/supplier recommendations
for safe storage and restraint.
Intermediate Nonstructural Component Checklist
Ceiling Systems - Lay-In Tiles
• Clips were not observed
o Recommendation: Lay-in tile ceilings should be retrofitted with clips or replaced
with a new system that is compliant.
Ceiling Systems - Suspended Lath and Plaster
• Existing suspended plaster ceiling supports and anchorage could not be determined
o Recommendation: A Tier 2 analysis should be conducted to determine the
capacity of the ceiling system under the required nonstructural seismic forces for
Life Safety.
Light Fixtures - Independent Support
• Attachment of light fixtures to structure and/or ceiling could not be determined
o Recommendation: If lights are connected to ceilings only, the light system should
be retrofitted or replaced with compliant support/anchorage that attaches directly
to the building structure.
Cladding and Glazing - Glazing
• Based on the age of the structure, it is unlikely safety glazing is provided
o Recommendation: The glazing should be replaced with a compliant glazing
system per architectural recommendations.
![Page 85: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/85.jpg)
75-15618-00 25
. 4. Recommendations and Next Steps
![Page 86: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/86.jpg)
75-15618-00 26
RECOMMENDATIONS AND NEXT STEPS
Based on the ASCE/SEI 31-03 Tier 1 assessment the building in its current condition is not
compliant for the Life Safety performance objective. Further investigation and analysis is
required to ensure the building will perform as desired in the event of an earthquake.
Recommendations are listed for each noncompliant item in Section 3: "Building Systems
Evaluation (ASCE/SEI 31-03 Tier 1)" in this report. These recommendations should be pursued
by the building Owner if it is desired to maintain the building for future use. It should be noted
that the Tier 2 analysis may indicate that no upgrades/retrofits are required for some items;
however, the Tier 1 screening evaluation requires a Tier 2 analysis be conducted in order to
determine which items require upgrades/retrofits.
The following items are required for the existing SEM Building:
• Further investigation including destructive and/or non-destructive testing of structural
elements, including walls and foundations as noted in this report
• A geotechnical investigation and report should be prepared for the existing structure that
includes site-specific seismic hazards, near-source fault effects and liquefaction potential
• Tier 2 dynamic analysis of existing building including explicit modeling of lateral force
resisting system (walls, diaphragms) and incorporating seismic hazard from geotechnical
report
• Further investigation and/or upgrades to nonstructural systems including light fixtures,
suspended ceilings, furniture and glazing as noted in this report
REFERENCES
1) "Cypress Junior College, North Orange County Junior College District, Science Building"
Structural Drawings, Martin & Associates (Los Angeles, California), 1970. (Existing SEM
Building Structural Drawings)
2) "Cypress Junior College, North Orange County Junior College District, Science Building"
Architectural Drawings, William Blurock & Partners/Caudill, Rowlett, Scott (Corona del
Mar, California), 1970. (Existing SEM Building Architectural Drawings)
3) American Society of Civil Engineers/Structural Engineering Institute (ASCE/SEI),
Seismic Evaluation of Existing Buildings (31-03) , 2003.
4) American Society of Civil Engineers/Structural Engineering Institute (ASCE/SEI),
Minimum Design Loads for Buildings and Other Structures (7-05), 2005.
5) "Seismic Hazard Zones Map - Los Alamitos Quadrangle," State of California
Department of Conservation, Division of Mines and Geology, 1999,
htto:/lgmw.consrv.ca.govl shmpldownload/pdf/ozn ialmLpdf. (Liquefaction Maps)
6) "Caltrans Fault Database (V2a) for ARS Online," Excel and KML files, California
Department of Transportation (Caltrans), October 13, 2012,
htto: l dap3.dotca.gov/ARS Online/technical.php. (Caltrans Fault Maps)
![Page 87: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/87.jpg)
75-15618-00 27
1--- - Appendix A: Completed ASCE/SEI 31-03 Checklists
![Page 88: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/88.jpg)
3 - 62 Seismic Evaluation of Existing Buildings ASCE 31-03 28
Screening Phase (Tier 1)
3.7.9 Basic Structural Checklist for Building Type C2: Concrete Shear Walls with
Stiff Diaphragms
This Basic Structural Checklist shall be completed where required by Table 3-2.
Each of the evaluation statements on this checklist shall be marked Compliant (C), Non-compliant
(NC), or Not Applicable (N/A) for a Tier l Evaluation. Compliant statements identify issues that are
acceptable according to the criteria of this standard, while non-compliant statements identify issues
that require further investigation. Certain statements may not apply to the buildings being evaluated.
For non-compliant evaluation statements, the design professional may choose to conduct further
investigation using the corresponding Tier 2 Evaluation procedure; corresponding section numbers
are in parentheses following each evaluation statement.
Building System
NC NIA LOAD PATH: The structure shall contain a 1nlnl1nu1n of one complete load path for Life Safety
and hnmediate Occupancy for seismic force effects fro1n any horizontal direction that serves to
transfer the inertial forces from the 1nass to the foundati on. (Tier 2: Sec. 4.3.1.I )
NC NIA MEZZAN INES: Interior mezzan ine levels shall be braced independently fro1n the main structure,
or shall be anchored to the lateral-force-resisting elements of the main structure. (Tier 2: Sec. 4.3. 1.3)
WEAK STORY: The strength of the lateral-force-resisti ng system in any story shall not be less
than 80 percent of the strength in an adjacent story, above or below, for Life Safety and Immediate
Occupancy. (Tier 2: Sec. 4.3.2.l )
SOFT STORY: The stiffness of the lateral-force-resisting system in any story shall not be less than
70 percent of th e lateral-force-resisting systen1 stiffness in an adjacent story above or below, or less
than 80 percent of the average lateral-force-resisting system stiffness of the three stories above or
below for Life Safety and Immediate Occupancy. (Tier 2: Sec. 4.3.2.2)
NC NIA GEOM ETRY: There shall be no changes in horizontal dimension of the lateral-force-resisting
system of more than 30 percent in a story relative to adjacent stories for Life Safety and lmmediate
Occupancy, excluding one-story penthouses and 1nezzanines. (Tier 2: Sec. 4.3.2.3)
C NIA VERTICAL DISCONTINUITIES: AH vertical elements in the lateral-force-resisting syste1n shall
be continuous to the foundation. (Tier 2: Sec. 4.3.2.4)
NC NIA MASS: There sha!I be no change in effective mass more than 50 percent fro1n one story to the next
for Life Safety and Immediate Occupancy. Light roots, penthouses, and mezzanines need not be
considered. (Tier 2: Sec. 4.3.2.5)
C3.7.9 Basic Structural _Checklist for Building Type C2
These buildings have floor and roof framing that consists of cast-in-place concrete slabs, concrete
beams, one-wayjo,ists, tocway waffle joists, or flat slabs. Floors are supported on concrete columns
or bearing walls. Later.ilforces are resisted by cast-in-place concrete shear walls. Inolder
construction, shear walls are lightly reinforced but often extend throughout the building. Inmore
recent construction, shelll' walls occur in i_solated locations and are more heavily reinforced with
boundary elements anddosely spaced ties to provide ductile perfonnance. The diaphragms consist of
concrete slabs and are stiff relative to the walls. Foundations consist of concrete spread footings, mat
foundations, or deep foundations. . .· ...
![Page 89: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/89.jpg)
ASCE 31-03 Seismic Evaluation of Existing Buildings 3 - 63 29
Screening Phase (Tier 1)
NC NIA
NC NIA
C NC
NC NIA
NC NIA
NC NIA
NC NIA
c NIA
NC NIA
NC NIA
TORSION: The estimated distance between the story center of 1nass and the stol)' center of rigidity shall be l ess than 20 percent of the building width in either plan di1nension for Life Safety
and Immediate Occupancy. (Tier 2: Sec. 4.3.2.6)
DETERI ORATJ ON OF CONCRETE: There shall be no visible deterioration of concrete or
reinforcing steel in any of the vertical- or lateral-force-resisting elements. (Tier 2: Sec. 4.3.3.4)
POST-TENSIONING ANCHORS: There shall be no evidence of corrosion or spalling in the vicinity of post-tensioning or end fittings. Coil anchors shall not have been used. (Tier 2: Sec. 433.5 )
CONCRETE WALL CRACKS: All existing diagonal cracks in wall elements shall be Jess than 1/8 inch for Life Safety and 1116 inch for Immediate Occu pancy, shall not be concentrated in one
location, and shall not fonn an X pattern. (Tier 2: Sec. 4.3.3.9)
Lateral-Force-Resisting System
COMPLETE FRAMES: Steel or concrete frames classified as secondary components shall form a complete vertical-load-carrying systein. (Tier 2: Sec. 4.4.1 .6.l )
REDUNDANCY: The number of lines of shear walls in each principal direction shall be greater
than or equal to 2 for Life Safety and lm1nediate Occu pancy. (Tier 2: Sec. 4.4.2. l .J )
SHEAR STRESS CHECK: The shear stress in the concrete shear walls, calculated using the Quick
Check procedure of Section 3.5.3.3, shall be less than the greater of I 00 psi or 2 ,{i; for Life
Safety and Immediate Occupancy. (Tier 2: Sec. 4.4.2.2. l )
REINFORCI NG STEEL: The ratio of reinforcing steel area to gross concrete area shall be not iess than 0.0015 in the vertical direction and 0.0025 in the horizontal direction for Life Safety and I mmediate Occupancy. The spacing of reinforcing steel shall be equal to or less than l 8 inches for Life Safety and Immediate Occu pancy. (Tier 2: Sec. 4.4.2.2.2}
Connections
TRANSFER TO SHEAR WALLS: Diaphragms shall be connected for transfer of l oads to the
shear walls for Life Safety and the connections shall be able to develop the l esser of the shear strength of the walls or diaphragms for l mmediate Occupancy. (Tier 2: Sec. 4.6.2.1 )
FOUNDATI ON DOWELS Wal l reinforcement shall be doweled into the foundation for Life Safety, and the dowels shall be able to develop the lesser of the strength of the walls or the uplift capacity of the foundation for Immediate Occupancy. (Tier 2: Sec. 4.6.3.5)
![Page 90: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/90.jpg)
3 - 64 Seismic Evaluation of Existing Buildings ASCE 31-03 30
Screening Phase (Tier 1)
3.7.9S
Supplemental Structural Checklist for Building Type C2: Concrete Shear
Walls with Stiff Diaphragms
This Supplemental Structural Checklist shall be completed where required by Table 3-2. The Basic
Structural Checklist shall be completed prior to completing this Supplemental Structural Checklist.
Lateral-Force-Resisting System
NC N/A
C NC
C NC
C NC
C NC
C NC
C NC
C N/A
C NC
C NC
DEFLECTION COM PATIBILI1Y: Secondary components shall have the shear capacity to develop the flexural strength of the co1nponents for Life Safety and shall meet the requirements of
Sections 4.4.1.4.9, 4.4. l .4.I 0, 4.4.1.4.1 1, 4.4.1.4.1 2 and 4.4.1.4.1 5 for Immediate Occupancy.
(Tier 2: Sec. 4.4.l.6.2)
FLAT SLABS: Flat slabs/plates not part of lateral-force-resisting system shall have continuous botto1n steel through the column joints for Life Safety and Immediate Occupancy. (Tier 2:
Sec. 4.4.1.6.3)
COUPLING BEAMS: The stirrups in coupling beams over means of egress shall be spaced at or
less than d/2 and shall be anchored into the confined core of the bun with hooks of I 35° or more
for Life Safety. AJI coupling beams shall comply with the requirements above and shall have the
capacity in shear to develop the uplift capacity of the adjacent wall for Immediate Occupancy.
(Tier 2: Sec. 4.4.2.2.3)
OVERTURNING: All shear wal ls shall have aspect ratios less than 4-to-1 . Wall piers need not be considered. This statement shall apply to the lmmediate Occupancy Perfom1ancc Level only. (Tier 2: Sec. 4.4.2.2.4)
CONFINEMENT REINFORCING: For shear walls with aspect ratios greater than 2-to-- l , the boundary elements shall be confined with spirals or ties with spacing less than 8d1r This statement
shall apply to the Immediate Occupancy Performance Level only. (Tier 2: Sec. 4.4.2.2.5)
REINFORCING AT OPENINGS: There shall be added tri1n reinforcement around all wall openings with a dimension greater than three times the thickness of the wan. This statement shall apply to the Immediate Occupancy Perfonnance Level only. (Tier 2: Sec. 4.4.2.2.6)
WALL THICKNESS: Thickness of bearing walls shall not be less than l /25 the unsupported height or length, whichever is shorter, nor less than 4 inches. This state1nent shall apply to the Immediate Occupancy Performance Level only. {Tier 2: Sec. 4.4.2.2.7)
Diaphragms
DIAPHRAGM CONTINUITY: The diaphragms shall not be composed of split-level floors and shall not have expansion joints. (Tier 2: Sec. 4.5.l.l )
OPENJNGS AT SHEAR WALLS: Diaphragm openings immediately adjacent to the shear walls sha11 be less than 25 percent of the wa11 1ength for Life Safety and 15 percent of the wall length for Immediate Occupancy. (Tier 2: Sec. 4.5.1 .4)
PLAN IRREGULARITIES: There shall be tensile capacity to develop the strength of the diaphragm at re-entrant comers or other locations of plan irregularities. This stateinent shall apply to the lmmediate Occupancy Performance Level only. (Tier 2: Sec. 4.5. I .7)
DIAPHRAGM REINFORCEM ENT AT OPENINGS: There shall be reinforcing around all
diaphragm openings larger than 50 percent of the building width in either major plan dimension.
This statement shall apply to the Immediate Occupancy Performance Level only. (Tier 2:
Sec. 4.5.1.8)
![Page 91: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/91.jpg)
3 - 65 ASCE 31-03 Seismic Evaluation of Existing Buildings 31
Screening Phase (Tier 1)
Connections
c NIA UPLIFT AT PI LE CAPS: Pile caps shall have top reinforcement and piles shall be anchored to the
pile caps for Life Safety, and the pile cap reinforcement and pile anchorage shall be able to develop
the tensile capacity of the piles for Immediate Occupancy. (Tier 2: Sec. 4.6.3. l 0)
![Page 92: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/92.jpg)
Seismic Evaluation of Existing Buildings ASCE 31-03 32
,
Screening Phase (Tier 1)
3.8 Geologic Site Hazards and Foundations Checklist
This Geologic Site Hazards and Foundations Checklist shall be completed where required by
Table 3-2.
Each of the evaluation statements on this checklist shall be marked Compliant (C), Non-compliant
(NC), or Not Applicable (N/A) for a Tier l Evaluation. Compliant statements identify issues that are
acceptable according to the criteria of this standard, while non-compliant statements identify issues
that require further investigation. Certain statements may not apply to the buildings being evaluated.
For non-compliant evaluation statements, the design professional may choose to conduct further
investigation using the corresponding Tier 2 Evaluation procedure; corresponding section numbers
are in parentheses following each evaluation statement.
Geologic Site Hazards
The foll_owing statements shall be completed for buildings in levels of high or 1noderate seismicity.
C ( NC; NIA LlQUEFACTION: Liquefaction-susceptible, saturated, loose granular soils that could jeopardize
iffe· the building's seismic peifonnance shall not exist in the foundation soils at depths within 50 feet
under the building for Life Safety and Immediate Occupancy. (Tier 2: Sec. 4.7.L l )
NC NIA SLOPE FAl LURE: The building site shall be sufficiently remote from potential earthquake
induced slope failures or rockfalls to be unaffected by such failures or shaH be capable of
accommodating any predicted movements without failure. (Tier 2: Sec. 4.7.1 .2)
C NIA SURFACE FA ULT RUPTURE: Surface fault rupture and surface displace1nent at the building site
is not anticipated. (Tier 2: Sec. 4.7.1.3)
Condition of Foundations
following statement shall be completed for all Tier 1 bu i1ding evaluations.
NC NIA FOUNDATION PERFORMANCE: There shall be no evidence of excessi ve foundation movement
such as settlement or heave that would affect the integrity or strength of the structure. (Tier 2:
Sec. 4.7.2.1)
The following statement shall be completed for buildings in levels of high or 1noderate seis1nicity being evaluated to the
Immediate 0 upancy Perfonnance Level.
C NC DETER10RATION: There shall not be evidence that foundation elements have deteriorated due to
corrosion, sulfate attack, material breakdown, or other reasons in a manner that would affect the
integrity or strength of the structure. (Tier 2: Sec. 4.7.2.2)
C NC
Capacity of Foundations
statement shall be completed for all Tier 1 bu ilding evaluations.
POLE FOUNDATIONS: Pole foundations shall have a minimum embedment depth of 4 feet for
Life Safety and Immediate Occupancy. (Tier 2: Sec. 4.7.3. 1)
The following statements shall be completed for buildings in levels of moderate seismicity being eval uated to the
!mediate Occupancy Perfonnance Level and for buildings in levels of high seismicity.
t_ C l NC NIA OVERTURNING: The ratio of the horizontal dimension of the lateral forceresisting sysrem at the
foundation level to the building height (base/height) shall be greater than 0.6S0 • (Tier 2:
Sec. 4.7.3.2)
![Page 93: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/93.jpg)
3 - 120 Seismic Evaluation of Existing Buildings ASCE 31-03 33
Screening Phase (Tier 1)
NC NIA TIES BETWEEN FOUNDATION ELEM ENTS: The foundation shall have ties adequate to resist
seismic forces where footings, piles, and piers are not restrained by beams, slabs, or soils classified
as Class A, B, or C. (Section 3.5.2.3. J , Tier 2: Sec. 4.7.3.3)
C NC DEEP FOUNDATI ONS: Piles and piers shall be capable of transferring the lateral forces between
the structure and the soil. This statement shall apply to the Immedi ate Occupancy Performance
Level only. (Tier 2: Sec. 4.7.3.4)
C NC SLOPING SITES: The difference in foundation embedment depth from one side of the building to
another shall not exceed one story in height. This state1nent shall apply to the lmmediate Occupancy Performance Level only. (Tier 2: Sec. 4. 7.3.5)
![Page 94: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/94.jpg)
3 - 122 Seismic Evaluation Standard ASCE 31-02 34
Screening Phase (Tier 1)
3.9.l Basic Nonstructural Component Checklist
This Basic Nonstructural Component Checklist shall be completed where required by Table 3-2.
Each of the evaluation statements on this checklist shall be marked Compliant (C), Non-compliant
(NC), or Not Applicable (N/A) for a Tier IEvaluation. Compliant statements identify issues that are
acceptable according to the criteria of this standard, while non-compliant statements identify issues
that require further investigation. Certain statements may not apply to the buildings being evaluated.
For non-compliant evaluation statements, the design professional may choose to conduct further
investigation using the corresponding Tier 2 Evaluation procedure; corresponding section numbers
are in parentheses following each evaluation statement.
Partitions
C NC UNREI NFORCED MASONRY: Unreinforced masonry or hollow clay tile partitions shall be
braced at a spacing equal to or less than I 0 feet in levels of low or moderate seismicity and 6 feet in
levels of high seismicity. (Tier 2: Sec. 4.8.l .l )
Ceiling Systems
NC NIA SUPPORT: The integrated suspended ceiling system shall not be used to laterally support the tops
of gypsum board, masonry, or hollow clay tile partitions. Gypsorn board partitions need not be
evaluated where oniy the Basic Nonstructural Component Checklist is required by Table 3-2. (Tier
2: Sec. 4.8.2.1 )
Light Fixtures
c NIA EMERGENCY LIGHTING: Emergency lighting shall be anchored or braced to prevent falling
during an earthquake. (Tier 2: Sec. 4.8.3.1 )
Cladding and Glazing
C NC CLADDING ANCHORS: Cladding components weighing more than J 0 psf shall be mechanically
anchored to the exterior wall framing at a spacing equal to or less than 4 feet. A spacing of u p to 6
feet is pennitted where only the Basic Nonstructural Component Checklist is required by Table 3-2.
(Tier 2: Sec. 4.8.4.1 )
NC NIA DETERJORA TJON: There shall be no evidence of deterioration, damage or corrosion in any of
the connection elements. (Tier 2: Sec. 4.8.4.2)
C NC CLADDING lSOLATION: For moment frame buildings of steel or concrete, panel connections
shall be detailed to accommodate a story drift ratio of 0.02. Panel connection detail ing for a story
drift ratio of 0.0 l is permi tted where only the Basic Nonstructural Component Checklist is required
by Table 3-2. (Tier 2: Sec. 4.8.4.3)
C NC M ULTI-STORY PANELS: For multi-story panels attached at each floor level, panel connections
shall be detail ed to accommodate a story drift ratio of 0.02. Panel connection detailing for a story
drift ratio of O.Ol is pennitted where only the Basic Nonstructural Component Checklist is required
by Table 3-2. (Tier 2: Sec. 4.8.4.4)
C NC BEARI NG CONNECTIONS: Where bearing connections are required, there shall be a minimum
of two bearing connections for each wall panel. (Tier 2: Sec. 4.8.4.5)
![Page 95: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/95.jpg)
ASCE 31-03 3 - 123 Seismic Evaluation of Ex'1sting Buildings 35
Screening Phase (Tier 1)
C NC
C NC
C NC
C NC
C NC
C NC
C NC
C NC
C NC
C NC
C NC i
INSERTS: Where inserts are used in concrete connections, the inserts shall be anchored to
reinforcing steel or other posi tive anchorage. (Tier 2; Sec. 4.8.4.6)
PANEL CONNECTIONS: Exterior cladding panels shall be anchored out-of-plane with a
minimum of 4 connections for each wall panel. Two connections per wall panel are permitted
where only the Basic Nonstructural Component Checklist is required by Table 3-2. (Tier 2:
Sec. 4.8.4.7)
Masonry Veneer
SHELF ANG LES: Masonry veneer shall be supported by shelf angles or other ele1nents at each
floor 30 feet or more above ground for Life Safety and at each floor above the first floor for
Immediate Occupancy. (Tier 2: Sec. 4.8.5. l )
TI ES: Masonry veneer shall be connected to the back-up with corrosion-resistant tics. The ties
shall have a spacing equal to or less than 24 inches with a minimum of one tie for every 2-2/3
square feet. A spacing of up to 36 inches is permitted where only the Basic Nonstructural
Component Checklist is required by Table 3-2. (Tier 2: Sec. 4.8.5.2)
WEAKENED PLANES; Masonry veneer shall be anchored to the back-up adjacent to weakened
planes, such as at the locations of flashing. (Tier 2: Sec. 4.8.5.3)
DETERJORA TION: There shall be no evidence of deterioration, damage, or corrosion in any of
the connection elements. (Tier 2: Sec. 4.8.5.4)
Parapets, Cornices, Ornamentation, and Appendages
URM PARAPETS: There shall be no laterally unsupported unreinforced masonry parapets or
cornices with height-to-thickness ratios greater than 1 .5. A height-to-thickness ratio of up to 2.5 is
pennitted where only the Basic Nonstructural Component Checklist is required by Table 3-2. (Tier
2: Sec. 4.8.8.I )
CANOPIES: Canopies located at building exits shall be anchored to the structural framing at a
spacing of 6 feet or less. An anchorage spacing of up to l 0 feet is pennitted where only the Basic
Nonstructural Co1nponent Checkl ist is required by Table 3-2. (Tier 2: Sec. 4.8.8.2)
Masonry Chimneys
URM CHJMNEYS: No unreinforced masonry chimney shall extend above the roof surface more
than twice the least dimension of the chimney. A height above the roof surface of up to three times
the least dimension of the chimney is permitted where only the Basic Nonstructural Component
Checklist is required by Table 3-2. (Tier 2: Sec. 4.8.9.1)
Stairs
URM WALLS: Walls around stair enclosures shall not consist of unbraced hollow clay tile or
unreinforced masonry with a height-to thickness ratio greater than 12-to- l. A height-to-th ickness
ratio of up to l 5-to-J is permitted where only the Basic Nonstructural Component Checklist is
required by Table 3-2. (Tier 2; Sec. 4.8.10.1 )
STAIR DETAI LS: I n moment frame structures, the connection between the stairs and the stru cture
shall not rely on shallow anchors in concrete. Alternatively, the stair details shall be capa ble of
accommodating the drift calculated using the Quick Check procedure of Section 3.5.3.I without
including tension in the anchors. (Tier 2: Sec. 4.8.10.2)
![Page 96: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/96.jpg)
3 -124 Seismic Evaluation of Existing Buildings ASCE 31-03 36
Screening Phase (Tier i)
c
C NC
NIA
Building Contents and Furnishing
TALL NARROW CONTENTS: Contents over 4 feet in height with a height-to-depth or height-to
width ratio greater than 3-to-l shall be anchored to the floor slab or adjacent structural walls. A
height-to-depth or height-to-width ratio of up to 4-to- I is pennitted where only the Basic Nonstructural Component Checklist is required by Table 3-2. (Tier 2: Sec. 4.8. l l. l )
Mechanical and Electrical Equipment
EMERGENCY POWER: Equipment used as part of an emergency power system shall be mounted
to maintain continued operation after an earthquake. (Tier 2: Sec. 4.8. l 2. l )
NC NIA HAZARDOUS MATERIAL EQUIPMENT: HVAC or other equipment containing hazardous
material shall not have damaged supply lines or unbraced isolation supports. (Tier 2:
Sec. 4.8.12.2)
C NC
c
c
c
NIA
NIA
NIA
NIA
DETERlORATION: There shall be no evidence of deterioration, dmnage, or corrosion in any of
the anchorage or supports of mechanical or electrical equipment (Tier 2: Sec. 4.8.1 2.3)
indoor outdoor
ATTACHED EQUIPMENT: Equipment weighing over 20 lb that is attached to ceilings, walls, or
other supports 4 feet above the floor level shal l be braced. (Tier 2: Sec. 4.8.12.4)
Piping
FI RE SUPPRESSION PIPING: Fire suppression p1p1ng shall be anchored and braced in
accordance with NFPA- l 3 (NFPA, 1 996). (Tier 2: Sec. 4.8.1 3. I )
FLEXIBLE COUPLI NGS: Fluid, gas, and fire suppression piping shall have flexible couplings.
(Tier 2: Sec. 4.8.13.2)
Hazardous Materials Storage and Distribution
TOXIC SUBSTANCES: Toxic and hazardous substances stored in breakable containers shall be
restrained from falling by latched doors, shelf lips, wires, or other methods. (Tier 2: Sec. 4.8.15. l )
![Page 97: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/97.jpg)
ASCE 31-03 Seismic Evaluation of Existing Buildings 3 -125 37
Screening Phase (Tier 1)
3.9.2 Intermediate Nonstructural Component Checklist
This Intermediate Nonstructural Component Checklist shall be completed where required by
Table 3-2. The Basic Nonstructural Component Checklist shall be completed prior to completing
this Intermediate Nonstructural Component Checklist.
Ceiling Systems
LAY-I N TILES: Lay-in tiles used in ceiling panels located at exits and corridors shall be secured
with clips. (Tier 2: See. 4.8.2.2)
l NTEGRATED CEI LINGS: Integrated suspended ceilings at exits and conidors or weighing 1nore
than 2 pounds per square foot shall be laterally restrained with a minimum of four diagonal wires or
rigid 1nembers attached to the structure above at a spacing equal to or less than 12 feet. (Tier 2:
Sec. 4.8.2.3)
C NIA SUSPENDED LATH AND PLASTER: Ceilings consisting of suspended lath and plaster or
gypsum board shall be attached to resist seismic forces for every l 2 square feet of area. (Tier 2:
Sec. 4.8.2.4)
c
c
C NC
C NC
C NC
NIA
NIA
Light Fixtures
INDEPENDENT SUPPORT: Light fixtures in suspended grid ceilings shall be supported
independently of the ceiling suspension system by a minimum of two wires at diagona11y opposite
comers of the fixtures. (Tier 2: Sec. 4.8.3.2)
Cladding and Glazing
GLAZlNG: Glazing in curtain walls and individual panes over 16 square feet in area, located up to
a height of l 0 feet above an exterior walking surface, shall have safety glazing. Such glazing
located over 1 0 feet above an exterior walking surface shall be laminated annealed or laminated
heat-strengthened safety glass or other glazing system that wiH remain in the frame when glass is
cracked. (Tier 2: See. 4.8.4.8)
Parapets, Cornices, Ornamentation, and Appendages
CONCRETE PARAPETS: Concrete parapets with height-to-thickness ratios greater than 2.5 shall
have vertical reinforcement. (Tier 2: Sec. 4.8.8.3)
APPENDAGES: Cornices, parapets, signs, and other appendages that extend above the highest
point of anchorage to the structure or cantilever from exterior wall faces and other exterior wall
ornamentation shall be reinforced and anchored to the structural system at a spacing equal to or less
than 10 feet for Life Safety and 6 feet for Immediate Occupancy. This requirement need not apply
to parapets or cornices compliant with Section 4.8.8.l or 4.8.8.3. (Tier 2: Sec, 4.8.8.4)
Masonry Chimneys
ANCHORAGE: Masonry chimneys shall be anchored at each floor level and the roof. (Tier 2: Sec.
4.8.9.2)
![Page 98: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/98.jpg)
3· 126 Seismic Evaluation of Existing Buildings ASCE 31-03 38
Screening Phase (Tier 1)
NC NIA
C NC
Mechanical and Electrical Eqnipment
VIBRATION ISOLATORS: Equipment mounted on vibration isolators shall be equipped with
restraints or snubbers. (Tier 2: Sec. 4.8.12.5)
Ducts
STAIR AND SMOKE DUCTS: Stair pressurization and smoke control ducts shall be braced and
shal l have flexible connections at seis1nic joints. (Tier 2: Sec. 4.8. 14.l )
![Page 99: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/99.jpg)
75-15618-00 39
![Page 100: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/100.jpg)
40
![Page 101: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/101.jpg)
-
9/23/2015 Design Maps Summary Report
USGS Design Maps Summary Report
User-Specified nput
LVtlre;;s LOll<,ge SEM
Classifh ation Site Cass - "Stiff Soi!"
:·zoorned Vlevv Area Location
USGS-Provided Output
g :::: 1 = 0.948 g
" 0 13 g = (I g = 0 ,513 g
°!Ji'
l.50
l.?5
1.20
1.. 05
0.7S
0.i (;
MCE Response Spectrum Design Response Spectrum 1.10 -;-
!:ti D.C0
0.SG
OAO
<:1.20 r G.10
Q_ QC -r---+--+--, -+--+-4- + --- i 1.2() ?,1)G t.00 O..?i> ()_ 4( 0.GO D.90 L(,0
41
http://ehp1-earthquake.cr. usgs.gov/des ignmaps/us/sum mary.php?tem plate= minimal&Iatitude= 33.8289&1ongitude=- i18.0244&sitec!ass= 3&riskcategory= O&edit.. 1/i
![Page 102: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/102.jpg)
9/23/2015 Design Maps Detailed Report
ilUSGS Design Maps Detailed Report
ASCE 7-05 Standard (33.8289°N, 118.0244°W)
Site Cl21ss D - "Stiff Soil",
Section 11.4.1 - Mapped Accelera tion Pa rameters
Classes are as rieeo,ea, in Section 11.4,3 .
Section 11.4.2 - Site Class
L 422
SITE
CLASS PROFILE
NAME
Standa rd oenetn•foo11 Soil 1mdrained shear
f\ Hard rock vs > 5,ooo N/A ..................••.......•
N/A
6 Rock 2,soo < vs :<; s,ooo N/A N/A ······ ··· ··· ·· · ··········
dense
soi! and soft
rock
1,200 < -;'.'> :$ 2,500 N > 50
E Stiff soil Ti < 15
1. Plasticity index Pl > 201
2. Moisture content vv 2: 40°10 , and
3. Undrained shear S ,, < soc psf
the characterlstics.
F t'\ny profile containing soHs having one or rr1ore of the
1. SoHs vulnerable to potential failure or
soils,. qutck and highly sensit\\re
characteristics:
such as
cemented
soils.
2, Peats and/01 highly organic c!ays
clay vvhere ::: thickness of
> 10 f eet of peat and/or
Very ( f-f > 25 feet with plasticlty index PI >
thick soft/medium stiff
42
http://ehp1-earthquake.cr. usgs.gov/des ignm aps/us/report.php?ternplate=minimal&!atitude= 33.8289&1ongi tude=-118.0244&si tec!ass= 3&riskcategory= O&edition.. 1/5
![Page 103: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/103.jpg)
912312015 Design Maps Detailed Report
Section 11.4.3 - Site Coefficients and Adjusted Maximum Considered Earthquake Cl".1.<:::S:.l
Spectra l Response Accelera tion Parameters
Tab!e 1.4- : Site Coefficient F,,
Class Ma: pped Met= Soectra l Reso'"";c• Acceleratron Pa ra m eter· Short Penod
.s 0.25 0.50 = 0.75 = 1.00 2:'. 1.25
f\ 0.8
0.8 0.8
s LO
1.0 1.0 1.0
c i.2.
1.2 1,1 LO
D .6 1.4 1.2 1.
E 2,'.) 0.9 0.9
F See Seci:ion 1l.4.7 of /\SCE 7
Note: Use
For Site Class = D and
Tabie 11.1.1 2. Site Coefficient F
0.8
1.0 1.0
----
0.8 0.8 () .8
LO 1.0 .0
• 7
""'
1.5 "• ·4 :i".3
D 2.4 2.0 1.8
•·'
1.5
35 3.2
2.8 2.4 2.4
See Section 11,4 .7 of P,SCE 7
Note: Use stra1c1hr -line 111te1·c,oir1tic:n for" interrr:edate va!ues
IPor Site Cass :::: D and ::;; 0.513 !fll r Pv :=:.· 1,,500
43
1.6 c
![Page 104: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/104.jpg)
http://ehp1-earthquake.cr .usgs.gov/desi gnm aps/us/r eport.php?ternplate= minimal&Iatitude:::: 33.8289&1ongi tude=-i18.0244&si tedass= 3&riskcategory= O&edition.., 215
![Page 105: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/105.jpg)
9/23/2015 Design Maps Detailed Report
L OOO x L 422 g - 1.422 g
1 = = LSOO x 0.513 = 0.770
Section 11.4.4 - Design Spectral Acceleration Parameters
( = % % x 1.422 g - 0.948 g
{ x. 0.770 g 0.513
Section 11.4.5 - Design Response Spectrum
T, = 8 seconds
Figure 11,4-1: Design Response Spectrum ID.4 i· 0.6 T lT,, )
!T
44
http://ehp1-earthquake.cr .usgs.gov/designm aps/us/r eport.php?tem plate= minimal&Iatitude= 33.8289&1ongi tude=- 118.0244&sitecl ass= 3&riskcategory= O&edition. . 3/5
![Page 106: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/106.jpg)
912312015 Design Maps Detailed Report
Section 11.4.6 - Maximum Considered Earthquake (MCE) Response Spectrum
The MCE Resp onse Spectrurn is determined by rnuitipiying the design response spectrurn by 1.5.
-
T0 = 0.108
Period, T {sec}
45
http://ehp1-earthquake.cr .usgs.gov/designmaps/us/report.php ?tern plate=minimal&Iatitude= 33.8289&1ongltude= -i18.0244&sitedass= 3&riskcategory= O&edition. . 415
l_,QQ(;
![Page 107: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/107.jpg)
1
912312015 Design Maps Detailed Report
Section 11.6 - Seismic Design Category
Tab e. 11. .6-1 Seisrnic Design Category Based on Short Period Response Acceleration Paramete1·
OCCUPANCY CATEGORY VALUE OF
Ior I! III IV
B c
c c D
For Occu pancy Category = I and
D D D
= 0948 g, Seismic Design = D
Note: When S J. is rm0n!"PC or
to the Seismic Design Catet1orv
for
buildings in
irrctsp,2ctive of the above,
and III and f fo1· those in Category IV,
Seismic - \\the rn ore severe in accordance with
Ta b!e 11.6-1 or 11.6-2fl = D
Nole: See Section 11.6 for alternative to calculating Seisrnic Desfgn Cate<iory
References
1 22 -1 : http://earthquake,usgs,gov/hazards/design maps/downloads/pdfs/ ASCE7 .,zoo 2, 22-2:
3, 22-15 :
46
http://ehp1earthquake.er .usgs.gov/desl gnmaps/us/report.php?tern plate=minimal&latitude= 33.8289&1ongitude=-118.0244&siteclass= 3&rlskcategory= O&edition. . 515
= Category = D
B B c
c c D
D D D
![Page 108: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/108.jpg)
''""'""ML'oOLJOLOG>OO£Dm"""·"''
''''·"" MAeOXPLANAf'<)N
2Dhe,of!leqdn<l i"""'' "°"
STATE OF CALIFORNIA
SEISMIC HAZARD ZONES
LOS ALAMITOS QUADRANGLE
OFFICIAL MAP
Released: March 25, 1999
Tt<l\'10'""'''"'"''''"n<['°''""''''"
'"=.c'•'l"m'"m"o'w''""'""""·o°'<'''"o"!""'"'''"'°""'""'"''""m"'""''°"''"""''''"""'''-''·"'""'''°''°"""''"'"'"'"'"'•'""'
,_,,. ,...""'"°"""""" ·"''"''""'""'""'"'- '""""'''"'"""""""''''""'"'""'"'
![Page 109: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/109.jpg)
Anahein1 FJD:363.
LlaQ •3 .1 T:re p.,.-,- Cir: r 1
r>:redic·n !l'? T·)r. ·Jf Rue ., 8
Ee,\ c:f r•J p- 1 J ;: "1'? H
Source "Caltrans Fault Database (V2a) for ARS Online," California Department of Transportation (Caltrans), October 13, 2012,
http://dap3.dotca.govIARS_Online/technical. php 48
![Page 110: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/110.jpg)
75-15618-00 84
![Page 111: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/111.jpg)
75-15618-00 49
South 2na Floor Balcony Exterior
![Page 112: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/112.jpg)
75-15618-00 86
![Page 113: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/113.jpg)
75-15618-00 51
Entrance Lobby interior
![Page 114: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/114.jpg)
75-15618-00 88
East Interior Hallway
![Page 115: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/115.jpg)
75-15618-00 53
MECHANICAL
![Page 116: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/116.jpg)
![Page 117: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/117.jpg)
Science/Engineering/Math Building
Cypress College, Cypress, California
1
1. Mechanical Overview
California Climate Zone CZ-08
latitude 33.8°
lon.gitude 118.0°
Elevation 75 ft
92°F 70°F
38"F
Air Distribution System
The building is served by six air handling units, two per floor located in opposing corners of the building. The Air Handling Units will handle all cooling/heating and ventilation needs of each space. Each air handling unit has a direct exhaust connection and utilizes the Mechanical Room as an OSA plenum.
The building is divided into thermal control zones, and zone temperature control appears to be via a constant-temperature/variable-volume method. Air volume to individual thermal control will be modulated via a bank of Belimo actuated valves located in the Mechanical room located directly on top of each air handling unit.
Hydronic System
The chilled water system is connected to the campus Chilled Water loop. The point of connection is located adjacent to the chiller room in the south western corner of the first floor, and the connection pipe runs to the campus central plant via underground piping. The building has a redundant chiller and chilled water pumping system.
The building has in independent Heating Hot Water system, the heating hot water plant is located on the
Third Floor South West Mechanical room. There are two boilers with two primary circulation pumps and a
single Heating Hot Water pump for building distribution. The heating hot water system operation was not
observed.
Building Management System
The Building Management System is provided by Automated Logic Corporation.
![Page 118: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/118.jpg)
Science/Engineering/Math Building
Cypress College, Cypress, California
2
2. Mechanical Equipment
A Air Handling Units:
Tag Number: AH-5
Manufacturer: Model Number: Nominal Airflow: Initial Startup Date: Estimated Life Span:
Remarks:
Alliance 4NN-33,4-MB-AF-PF-HW-CW-AS
16,480 cfm 6/19/2009 15-20 years
Air Handling Unit is in good operational
condition. Mechanical room containing AH-5 also contains the Main Natural Gas Valve and an Electrical Switchboard in the same room.
Tag Number: AH-6
Manufacturer: Model Number: Nominal Airflow: Initial Startup Date:
Estimated Life Span: Remarks:
Alliance 4NN-11.6-20.8-AF-PF-HW-CW
10,120 cfm 6/19/2009 15-20 years
Air Handling Unit is in good operational condition.
![Page 119: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/119.jpg)
Science/Engineering/Math Building
Cypress College, Cypress, California
3
_I _ag Number: Manufacturer: Model Number: Initial Startup Date: Nominal Airflow: Estimated Life Span:
Remarks:
AH-7
Alliance 4NN-33.2- MB-PF-FF-HW-CW-AS 6/19/2009 18,440 cfm 15-20 years
Air Handling Unit is in good operational condition_
OSA Louver is rusty_
Ducting in the mechanical room shows signs of rust
![Page 120: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/120.jpg)
Science/Engineering/Math Building
Cypress College, Cypress, California
4
Tag Number: AH-8
Manufacturer: Model Number: Initial Startup Date: Estimated Life Span: Nominal Airflow: Remarks:
Alliance 4NN-31.2-MB-PF-FF-HW-CW-AS 6/19/2009 15-20 years
16.480 cfm
Air Handling Unit is in good operational condition. Crack in Mechanical Room wall with air leakage due to the negative pressurization of the Mechanical Room.
![Page 121: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/121.jpg)
Cypress College, Cypress, Callfornia
5
Tag Number: AH-9
Manufacturer:
Model Number:
Initial Startup Date:
Estimated Life Span:
Nominal Airflow:
Remarks:
Alliance
4NN-37.9-AF-PF-HW-CW-AS
6/19/2009
15-20 years
20.540 cfm
Air Handling Unit is in good operational
condition; however there appears to be a
leak of condensation water in the
Mechanical Room.
Electrical Switchgear located in this
room.
Noted that AHU switches are 'hand'
mode as opposed to 'auto' mode.
Tag Number: AH-10
Manufacturer:
Model Number:
Initial Startup Date:
Estimated Life Span:
Nominal Airflow:
Remarks:
Alliance
4NN-20.8-38.2-AF-PF-HW-CW
6/19/2009
15-20 years
20.090 elm
Air Handling Unit is in good operational
condition.
DLR Croup Science/Engineering/Math Building
![Page 122: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/122.jpg)
Science/Engineering/Math Building
Cypress College, Cypress, California
6
B. Chiller:
Tag Number: CH-1
Manufacturer: Model Number: Initial Startup Date:
Estimated Life Span: Nominal Tonnage: Remarks:
Carrier 19XL4142465CN 8/22/1994 15-20 years 20,090 elm Chiller appears to be in Standby mode. Building Service CHW appears to be
coming from the campus central plant located outside the scope of this project. Operation not verified.
![Page 123: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/123.jpg)
Science/Engineering/Math Building
Cypress College, Cypress, California
7
C. Chilled Water Pump
Tag Number: P-2
Manufacturer:
Model Number:
Initial Startup Date:
Estimated Life Span:
Nominal Capacity:
Remarks:
Tag Number:
Manufacturer:
Model Number:
Initial Startup Date:
Estimated Life Span:
Nominal Capacity:
Fuel:
Remarks:
Weinman
4"LI - 665GPM
Unknown
Motor replaced 9/3/1997
5-1O years
665 gpm
Chilled Water Pump appears to be in
Standby mode. Building Service CHW
appears to be coming from the campus
central plant located outside the scope of
this project. Operation not verified.
B1 & B2
Patterson Kelly
N2000-MFD
Unknown
15-20 years
1,700.000 btu/hr
Natural Gas
Boiler appears to be in normal operating
condition. Operation not verified.
![Page 124: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/124.jpg)
DLR Group Science/Engineering/Math Building Cypress College, Cypress, California
8
B. Heating Hot Water Pump:
Ta Number: P-1
Manufacturer: Model Number: Initial Startup Date: Estimated Life Span: Nominal Capacity: Remarks:
Bell & Gossett
1510 BF 8.75BF Unknown 15-20 years
180 gpm Heating Hot Water Pump appears to be
in normal operating condition. Operation not verified.
![Page 125: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/125.jpg)
Science/Engineering/Math Building
Cypress College, Cypress, California
9
C. Boiler Circulation Pump:
Manufacturer: Model Number:
Initial Startup Date: Estimated Life Span:
Remarks:
Patterson Kelly
5882-95
Unknown 15-20 years Boiler Circulation Pump appears to be in normal operating condition. Operation not verified.
![Page 126: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/126.jpg)
Science/Engineering/Math Building Cypress College, Cypress, California
10
D. Exhaust Fans
Manufacturer:
Model Number:
Initial Startup Date:
Estimated Life Span:
Remarks:
ILG Industries
Various
Unknown
0-2 years
Significant rust build up on fan casing
and fan wheels (where visible and not
operating).
![Page 127: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/127.jpg)
Science/Engineering/Math BuHding
Cypress College, Cypress, California
11
E. Make Up Air Units
Manufacturer: Model Number: Initial Startup Date: Estimated Life Span:
Remarks:
Trane Various
Unknown
0-2 years Significant rust build up on fan casing.
![Page 128: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/128.jpg)
::.. DLR Clroup Science/Engineering/Math Building Cypress College, Cypress, California
12
F. Misc. Items
• Rooftop exposed ducting is in serviceable condition. There is only minor rusting on the
surface.
• Rooftop exposed piping insulation requires replacement. It has show significant weathering and damage.
![Page 129: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/129.jpg)
Cypress College, Cypress, California
13
• Louvers show significant rusting and is close to the end of service life.
lilli_Dl.R Ciroup Science/Engineering/Math Building
![Page 130: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/130.jpg)
ELECTRICAL
![Page 131: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/131.jpg)
Science/Engineering/Math Building Cypress College, Cypress, California
1
ELECTRICAL ASSESSMENT
1. ELECTRICAL SITE DISTRI BUTION SYSTEM
The campus has 4.16KV electrical power loop distribution with medium voltage feeders #3 and #4. The
service is routed thru manhole #9 and into the Main Electrical Room at the south east corner of the
building.
2. ELECTRICAL BUILDING DISTRIBUTION SYSTEM
The building has two transformers, 1000KVA, 4160V-480/277V and 300KVA, 4160V-208/120V. The
1000KVA transformer supply power to a 1600A Main Switchboard "MSB-1''. The 300KVA transformer
supply power to a 2500A Main Switchboard "MSB-2''. The transformer and main switchboards are in good
condition. There is no emergency generator to serve this building.
t ·.DLR (ffoup Science/Engineering/Math Building
![Page 132: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/132.jpg)
DLR Croup Science/Engineering/Math Building Cypress College, Cypress, California
2
A. FINDINGS
The Main Electrical room houses the two transformers, two main switchboards, and a fire alarm paneL
The room is congested has multiple working clearance violations, There are other code violations and
installation issues seen in other rooms,
![Page 133: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/133.jpg)
Science/Engineering/Math Building Cypress College, Cypress, California
3
There is a cabinet behind the transformer with 28"
clearance only, it should be 48". Provide clearance to meet NEC 110.26 (A)(1) table - typical to all
clearance non-compliance.
The ductwork is within electrical dedicated space. Provide clearance to meet NEC 110.26 (E)(1)
section.
The clearance of the fire alarm panel behind the 300KVA transformer is 28", it should be 36".
The switchboard cover panels are not installed or missing. Wires are exposed to damage.
![Page 134: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/134.jpg)
f: - , DLR Ciroup Science/Engineering/Math Building
Cypress College, Cypress, California
4
B. RECOMMENDATIONS
i. There are code violations on working clearances related to the medium voltage transformers in the Main Electrical room. Removing these transformers and install new outdoor transformers.
ii. There are ductwork and water pipes above electrical switchboard which are code violations on dedicated clearance spaces. Remove and re-route ductwork and pipes to clear up dedicated space above the electrical switchboards. Providing a pan underneath the pipe only should be verified with local inspector.
iii. Install new cover panels on electrical switchboard and distribution boards to protect the live parts of the equipment and reduce the risk of foreign objects to make contact with the live parts. Provide guard to live parts to meet NEC 110.27 (A) & (B).
Piping over switchboard is in dedicated electricalspace also blocking front clearance. Provide
clearance to meet NEC 110.26 (E)(1) section.
![Page 135: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/135.jpg)
Science/Engineering/Math Building Cypress College, Cypress, California
5
3. LIGHTING SYSTEMS
The interior lighting system in the building uses fluorescent and incandescent lights, controlled with
manual switching. The condition of the light fixtures are good, however there are some controls that are
not operational. In the classroom, we noticed the lights above the projector screen is not separately
switched, therefore, the teachers had to place some plastic on the light fixture lens.
A. FINDINGS
![Page 136: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/136.jpg)
DLR Ciroup Science/Engineering/Math Building Cypress College, Cypress, California
6
Exit sign
Time clock and lighting relay controls
Skylight with a crack.
B. RECOMMENDATIONS
i. The lighting controls in the Lecture Hall do not seem to work. Replace existing controls with new. The cellular screen on the ceiling should be removed to eliminate the shadow pattern.
ii. Replace incandescent lights with LED to comply with Title 24 requirements.
iii. Repair skylights to enable more daylighting to pass thru. Utilize photocells to turn off light fixtures while there are sufficient daylights in the space and reconfigure switching controls accordingly.
iv. Re-wire lights in the classrooms to provide separate switchleg for lights above the projector screen to provide the correct controls that will turn off the lights in front of the classroom while leaving the back of the classroom lights turned on.
![Page 137: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/137.jpg)
L.oLR Science/Engineering/Math Building
Cypress College, Cypress, California
7
4. POWER AND OTHER MISCELLANEOUS SYSTEMS
Power panels are distributed within Mechanical rooms and Electrical/Janitorial closets. The panels are in
good condition. The power outlets are also in good condition.
The fire alarm panel is in good condition as well as the devices.
A. FINDINGS
Mounting heights of the devices are not consistent Below are the listed mounting heights that are not
compliant with ADA requirements
• Power outlets - 12" above finished floor on center.
• Light switches - 54" above finished floor on center.
Working clearances m front of
![Page 138: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/138.jpg)
L" DtR Ciroup Science/Engineering/Math Building
Cypress College, Cypress, California
8
B. RECOMMENDATIONS
L There are code violations on working clearances related to the panels in the Electrical rooms. Keep the clearance in front of panels clear of any obstacles. Provide 36" working clearance depth to meet NEC 110.26 (A)(1) table.
ii. Re-install devices at proper mounting heights to meet ADA requirements. Mount convenience outlets minimum at +15'" at bottom of device and light switches and pull sections maximum at +48" at top of device. Provide proper mounting height to meet CBC 11B-308 section.
Ill. Re-work telecom wiring installation to meet proper cable management set-up.
Fire alarm horn/strobe and pull station Wall mounted occupancy sensor/light switch combo
![Page 139: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/139.jpg)
DLR Group Architecture
Engineering
Planning
Interiors
1 650 Spruce Sireet Suite 308
F"ive1-side, CA 92507
![Page 140: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/140.jpg)
![Page 141: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/141.jpg)
DLR Group Science/Engineering/Math Building
Cypress College, Cypress, California
TABLE OF CONTENTS
Project Overview
Executive Summary
Architectural
Architectural Assessment .. ···················........... 1
Observations
Roof..
Roofing System Building Enclosure .. ............
Interior Observations .............. ............. .................... ..............
Accessible Parking ...
Accessible Path of Travel to East Building Entry
General Interior Accessible Path of Travel ....
Accessible Restrooms ..
Stair
Elevator........ ........ ............
.......2
....................... .4
......6
..... 10
..... .. .. . ..... 12
.. 14
.. ............... 15 .................20
. ................ 33
.......35
Analysis and Recommendations Roof .. ................ .................. ..
Roofing System .... ...................... .............
Building Enclosure .................. .
Interior Observations ....... ................................ ..
.38
.38
.39
.39
Accessible Parking .... ............. ......
Accessible Path of Travel to East Building Entry .. ..................... ..
General Interior Accessible Path of Travel.. .....................
Accessible Restrooms.. .......................... ............................ ..
Stair ...... ........................ ............................ .........
Elevator.. ............. .............. .............................. ..
.. ........ ..... ... .40
...................... .40
..................... .40 ........41
........................ 43 .43
Warranty and Limitations of this Report ................................................................................................... 43
Structural
1. Project Overview and Scope of Work ...............
1.1. Project Overview .. ...............
1.2. Scope of Work ............. . ... . ....... . ......... ............. ....................
2. Existing Conditions and Observations .. ...............
2.1. Existing Structural Drawings ... .............. ....... ..... ........................... .
2.2. Building Systems Description........... . ......... . .... ............
2.2.1. General ...... . . ..................... . .......... . ... ......
2.2.2. Gravity System ................
..... ...1
..... . ....2
............ 2
...4
..5
......5
..4
............8
2.2.3. Lateral Force Resisting System .
2.2.4. Foundations.... .................. ..
... . .. . ........ 13
··············· . . ... .... 14
![Page 142: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/142.jpg)
![Page 143: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/143.jpg)
DLR Group Science/Engineering/Math Building
Cypress College, Cypress, California
2.3. Site Visit and Observations .... .................... ........ .... . ........ ....................
2.3.1. General ............ .............. ....................
.14
......14
2.3.2. Skylights ................................ ..
3. Building Systems Evaluation (ASCE/SEI 31-03 Tier 1) ..
3. 1. General. ... .... ....... ............. ................................ .
3.2. Performance Objective... ... .. . ....
3.3. Site Seismicity ...
3.4. Required Checklists ..
3.5. Noncompliant Items..
3.5.1. Basic Structural (Type C2) . . .......... ..
3.5.2. Supplementary Structural (Type C2)
3.5.3. Geologic Site Hazards and Foundations .............
3.5.4. Basic Nonstructural .................. ...... .....
3.5.5. Intermediate Nonstructural ... ........................ ..............
4. Recommendations and Next Steps ..
5. References .. ................................... ........ ........
.......... .... . ....... 16
. . . ....... 18
............ 19
. ......... 19
..19
····· ..........21
...........21
.........21
.....22
................. .....23
..........23
.... . . . ... .....................24
..25
..26
Appendix A - Completed ASCE/SEI 31-03 Checklists
Appendix B - Seismic Design Parameters
Appendix C - Selected Site Photos
Mechanical
Mechanical Overview ....................................................................................................................... 1
Mechanical Equipment ................................................................................................................................ 2
Electrical
Electrical Assessment ...................................................................................................................... 1
Electrical Systems ....................................................................................................................... 1
Electrical Recommendations ...4
Lighting Systems ....................................................................................................................... 5
Lighting Recommendations .... ........... .. .... ..........6
Power and Other Miscellaneous Systems .............................................................................................. 7
Power and Other Miscellaneous Systems Recommendations ...................................................... 8
Cost Estimate
![Page 144: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/144.jpg)
![Page 145: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/145.jpg)
Group Science/Engineering/Math Building Cypress College, Cypress, California
PROJECT OVERVIEW
"Cypress College is the American Dream." Students can start with nothing and leave with all the skills
necessary to thrive. The College has proudly earned a reputation for academic excellence and for the
variety and depth of the educational programs offered. With the support from the local community many
programs are housed in state-of-the-art facilities.
As Cypress College continues to look forward and plan for the future, the College recognized the need to
access some of the existing facilities. Can they be retrofitted to meet tomorrow's needs, can they be
repurposed for other uses, should they be replaced? These and many more questions need to be fully
understood, discussed and answered to determine the best path forward.
In an effort to begin to answer one of the questions for one of the buildings, Cypress College has
requested to have a due diligence study performed on the Science, Engineering and Mathematics (SEM)
Building. The SEM building is a three story, approximately 100,000 square foot building constructed in
1970-71 on the Cypress College campus. The building program consists primarily of classrooms,
laboratories and offices and also includes mechanical/electrical rooms, a two-story entrance lobby, a
greenhouse and two central lecture halls that slope from the second level to ground level. The building is / currently still used for instruction with the exception of some classroom spaces which are veeant" t""U.AR ,,
'.,,. l c!:}fu:- The study was to determine the condition of the building enclosure, structural, mechanical, plumbing and
electrical systems as it currently stands and what is necessary or recommended to _r:paintainJQe facility for
current uses. The study also addressed accessibility issues as it relates to existing'
The site investigation and study was completed in August and September of 2015 and consisted of visual
site observations and review of plans furnished by the College. No destructive or non-destructive testing
or investigation was conducted.
![Page 146: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/146.jpg)
![Page 147: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/147.jpg)
DLR Group Science/Engineering/Math Building Cypress College, Cypress, California
EXECUTIVE SUMMARY
ARCHITECTURAL
The goal of the architectural assessment was to visually review the building envelope consisting of the
roof and exterior building walls and windows of its current condition and deficiencies and provide any
recommendations for the future. Building compliance with the 2013 California Building Code accessibility
requirements were also reviewed. When the building was designed, no Code for accessibility existed but
since then some provisions had been made, primarily on the first floor.
Compared to the State of California Department of General Services, Office of Architecture and
Construction approved drawings dated February 13, 1970, the building has undergone very few plan
altering renovations. Maintenance has been deferred on some items while some systems or parts thereof
have been updated.
The roofing system has served it's useful life and should be removed and replaced. When the roofing
system is replaced, the various components that are connected and impacted by the roofing should be
addressed. The skylights should be replaced, roof access door and frame replaced, metal copings
installed, roof overflow drains installed, sheet metal equipment pad covers installed, cracks in the
concrete equipment screen walls filled, the concrete equipment screen walls sealed and utility supports
installed.
The concrete and aluminum window system building enclosure is in good condition. To maintain and
increase the useful life, a concrete sealer should be applied to the exterior concrete walls to minimize
moisture penetration. Cracks in the concrete wall or adjacent bridge structure should be filled and sealed.
All the window gasketing should be removed and replaced as it has shrunk with age. Window weep
holes should be drilled into the window sill. Landscaping irrigation should be checked, adjusted and
redirected to avoid spraying the windows.
An attempt to address exterior accessibility such as parking and path of travel to an entry has been made
but does not comply with the current 2013 California Building Code or even back to the 2007 California
Building Code. Code compliant accessible p rk· Q-aFlys·. Sible path of travel to an entry should be provided as any work to the building requirin a building permi)wi ill require this.
'- 7 Accessibility issues have generally not been addressedwithin th§ building with the exception of the first
floor restrooms. The first floor restrooms have been modified to comply with most but not all the
accessibility requirements and require additional work.
When additions or alteration work is executed in an existing building, the cost of compliance shall be
limited to 20 percent of the adjusted construction cost of alterations when the adjusted construction cost
is less than or equal to the current valuation threshold as defined in the Code. If the adjusted
construction cost exceeds the threshold, full compliance is required unless full compliance exceeds 20
percent of the construction cost. At that situation, compliance shall be provided to the greatest extent
possible without exceeding 20 percent. In general the accessible parking and the path of travel to the
area of work are priority and must comply with accessibility requirements. Then the restrooms and
drinking fountains serving the area must comply with accessibility requirements.
The building complies with current exiting requirements with the current uses and corresponding area or
square feet related to the use. If uses are changed or current uses are expanded or decreased, an
exiting calculation should be made to ensure Code compliance.
![Page 148: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/148.jpg)
![Page 149: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/149.jpg)
Group Science/Engineering/Math Building
Cypress College, Cypress, California
STRUCTURAL
The purpose of the structural report is to identify structural and nonstructural elements of the existing
Structural, Engineering and Mathematics (SEM) building that may require replacement and/or upgrades.
The ultimate objective is to estimate the costs associated with continued operation of the existing SEM
building to compare to the cost of a new replacement building. The ASCE/SEI Tier 1 procedure detailed
in this report is a "first step" screening procedure that identifies "noncompliant" items, or items requiring
further investigation/evaluation (Tier 2 analysis). Once the Tier 2 analysis is complete, required upgrades
are determined (if applicable) and costs can be estimated for these specific upgrades.
Nonstructural components identified as "noncompliant" per Tier 1 will need to be replaced to current
building code standards (no Tier 2 required). Structural and nonstructural components that are identified
as "compliant" per Tier 1 are acceptable as-is.
Mandatory vs Voluntary Seismic Upgrades
The California Administrative Code (CAC), Chapter 4 determines the requirements for seismic upgrades
to community college buildings in California. A seismic rehabilitation is required for the Community
College building if any of the following apply:
I
I:
* A "nonconforming" building is defined by CAC as any building that has not been certified by DSA as a school building.
** Cost excludes maintenance, HVAC, insulation materials, any voluntary seismic upgrades.
Mandatory Seismic Rehabilitation
Trinner
CAC Ch. 4 Section Applicability to Cypress SEM
Building
Existing "nonconforming" building is
converted for use as a school building* CAC Section 4-307 Does not apply to the SEM building
which is already a DSA Certified school building.
Cost of reconstruction, alteration or
addition exceeds $25,000 and 50% of
the replacement value of the existing
building**
CAC Section 4-309(c) ft is not anticipated that the
alterations will exceed 50% of the
replacement value; however, this will
need to be confirmed by the cost .
COnSUiiant for the a/terotions versus new buildinq construction costs.
Cost of reconstruction, alteration or
addition exceeds $25,000 but does not
exceed 50% of the replacement value of
the existing building and the proposed
modifications either**
• Increase the effective seismic weight or wind force in any story by more than 10%
• Decrease the design capacity of any existing structural
component by more than 5%,
unless the component has the
capacity to resist the retrofit
CAC Section 4-309(c) This will need to be confirmed once / the specific proposed alterations tc/ the SEM building have been / /
identified. /
It is not anticipated that structural
alterations to the building in its
current form to achieve the Life
Safety performance objective will
result in weight increases or capacity
decreases beyond the above
thresholds; however, this will need to
be confirmed after a Tier 2 analysis
is performed on the identified items
in this report. desian forces
![Page 150: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/150.jpg)
![Page 151: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/151.jpg)
Group Science/Engineering/Math Building Cypress College, Cypress, California
If none of the above conditions apply, a seismic rehabilitation is not required but may be performed on a
voluntary basis at the school's discretion. All structural deficiencies need not be addressed if voluntary
upgrades are performed, whereas all structural deficiencies must be addressed if seismic upgrades are
required by CAC. Voluntary seismic upgrades should not make the building worse.
At this time the estimated cost of the replacement building is not known; however, the alterations to the
existing SEM building are not anticipated to exceed 50% of the replacement value. Specific
alterations/additions to the existing SEM building have not yet been proposed, so it cannot be said
definitively at this time whether seismic rehabilitation will be required per CAC. Once the specific
alterations are identified, the changes in seismic weight and/or member capacities can be estimated by
the Structural Engineer.
Any seismic upgrades are supervised by and approved by the Division of the State Architect (DSA).
The seismic hazard value referenced in this report is established by the USGS. The USGS Design Maps
summary report is used to generate acceleration parameters Sos & S01 for the site. These values are
commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a
certain site for a given seismic hazard (in this case, ASCE/SEI 31-03 Tier 1 uses the mapped 2%
probability of exceedance in 50 year values). These values then determine whether the site is classified
as "Low", "Medium" or "High" seismicity per ASCE/SEI 31-03 Tier 1 (see page 20 of the structural report).
MECHANICAL
The existing mechanical systems in the building were installed in 2009 and are in very good condition.
No work on these systems is needed or recommended at this time. The rooftop mechanical equipment,
consisting of fans and other equipment are not in good condition. These units, however, can be replaced
by maintenance as the need arises as the units are still functioning.
ELECTRICAL
The SEM building was built in the 1970's. The electrical power distribution is 45 years old and in good
condition. There are_§§lyfilQJ codE?.,JLiQlations Q!JJb.e...regJJJf Dces for electrical equipment which are
the most problematic. The other issues are simpler which are related to mounting heights of devices and
lighting control functionality. The code violations regarding the clearances will require relocation of
electrical equipment which is complicated and requires further planning since it will impact the electrical
service and power distribution. Correction of the lighting controls should be implemented with Title 24
regulations which utilizes dimming controls and LED energy efficient fixtures. The simplest corrections are
the relocation of outlets and devices to be accessible since the impacts are localized and isolated. The
extent of the renovation is dependent of the future plans and shall require a separate in-depth study.
![Page 152: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/152.jpg)
COST ESTIMATE ()c&f;, Cost estimatesf9f two scenarios were developed. The first was to renovat xisting building as it
currently existS)\Jhe second was to construct a completely new building es! e location where the
existing building stands. In today's costs, the renovation work will cost approximately $19.4 million dollars
while a new building will cost approximately $46.5 million dollars.
The renovation work would address the findings of this report including deferred maintenance items, such
as the roofing system, skylights and windows. Code issues such as general accessibility and fully
accessible restrooms on each fioor would be addressed. Code issues involving electrical requirerrients
and clearances would be addressed. Additionally, electrical revisions required to comply wjtl:l-en-et1J)·..•... •.
conservation requirements will be implemented such as providing all new energy compliaflt LED light )
fixtures. Since renovation work exceeding $23.3 million - or half the replacement value - oMhe'1lU11aTilgTs
not anticipated, structural upgrades would not be triggered. Changes to the layout of the classrooms,
offices and lecture halls are not included with the exception of modifications required to accommodate
accessible restrooms. .)/!'l'Cd. UJlt;"
A new building of the same size would comply with all current Codes and standards including seismic
requirements. The cost includes the demolition of the existing building but does not include addressing
the displacement of the current programs housed in the building.
In both cases, the estimated cost is only for the hard cost sometimes referred to as the "brick and mortar
cost" involving the actual physical construction such as site work, building materials and labor. Soft costs
which include design, permits, insurance, testing and furnishings is not included. Soft costs vary from
project to project but can range from 15% to 25% of the hard costs.
BUILDING EFFICIENCY
Efficiencies of the existing building need to be factored as part of the due diligence study summary.
While energy efficiency is discussed within the mechanical section of this report, the purpose of this is to
provide instances for discussion of the pragmatic building efficiencies. These pragmatic inefficiencies are
difficult to quantify in monetary terms.
The building's concrete structure, relative to the provisions of the Capital Outlay Program Final Project
Proposal Approval for this building, is inherently inefficient due to the difficulty in being able to "right-size"
particular spaces locked within the building's envelope or structure. The push within spaces requiring
accessible upgrades (toilet rooms, elevators, stairs for egress/circulation, etc.), can result in spaces that
are inherently compromised, and ultimately the programming suffers as it attempts accommodate the
specific curriculum and academic needs. For example, the restrictions of the existing building make it
impossible to increase the number of specific laboratory sections that can be offered or accommodated.
Inefficiency can also be a result of the specific requirements of the educational specification that cannot r!il 5 ·' be accommodated within the parameters of the building structure, or as a result of the inability to provide ., .• 1vJ I additional space required by the physical sciences - a planetarium, for example - due to the State Capital ';;JV' Outlay Program limitations on space additions for modernization projects. The desired addition of a
planetarium is not possible to add under the currently approved Final Project Proposal. Additionally, the
space push mentioned above can adversely affect the ability to construct an addition in an effective
manner as well.
Finally, efficiency. uilding needs to be reviewed in the context of the campus. The SEM Building,
even with an inability to beCOiiiem" ore efficient than its potential, can still be beneficial to the campus for
short term use. The existing SEM Building is efficient in terms of swing space use to alleviate space
![Page 153: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/153.jpg)
DLR Group Science/Engineering/Math Building
Cypress College, Cypress, California
needs for capital construction or for secondary effect projects, without consuming valuable parking or
another site on campus. The aggregate savings by alleviating both parking and available swing space
concerns could exceed $10 million.
![Page 154: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/154.jpg)
TABLE OF CONTENTS
Project Overview
Executive Summary
Architectural
Architectural Assessment ............ ····················· ················· ............ 1
Observations
Roof ............. ................. .............. .............. .. ............. ....
Roofing System .................. .
Building Enclosure .... ................
Interior Observations .. ...................... .
Accessible Parking ............ .. . .......
Accessible Path of Travel to East Building Entry ............... ..
General Interior Accessible Path of Travel .. ........... .............
..2
..4
.....6 ............... ... 10
. ....... 12
.. .. ' ... ...... 14 .... ....... .. 15
Accessible Restrooms .. ....................... ..... . .................... .
Stair .......... ........................ .. .. ............ ..................... ............
Elevator... ................ .... ................ ......................... .
..........20
. ...33 ...35
Analysis and Recommendations
Roof.. ............ ............ ...... ............. .38
Roofing System .. ................ ........ . .. .... ............... ............ .38
Building Enclosure.... ................ ............ ............. ....39
Interior Observations ................... ............... .39
Accessible Parking ................... ....... .............. ............................. .............. ........40
Accessible Path of Travel to East Building Entry ............. ...................... .40
General Interior Accessible Path of Travel... .................. ...................... .40
Accessible Restrooms .... ................. ................... .......41
Stair . ........... ...................... .... ... ............ ....................... .........43
Elevator. ........................................................................................................................... 43
Warranty and Limitations of this Report ··············· ············ ... 43
Structural
1. Project Overview and Scope of Work ................. .
1.1. Project Overview ..... ........... .......................... ................. .
1.2. Scope of Work..... ........... ............
2. Existing Conditions and Observations .. ............................ .
2.1. Existing Structural Drawings ...
2.2. Building Systems Description
2.2.1. General ... .................... .
2.2.2. Gravity System ..
2.2.3. Lateral Force Resisting System
2.2.4. Foundations ......... ...............
............. ' 1
....... .......2
.....2
...............4
' . ..............5
.. . ....5
...4
... ... .. ....... . ......8
. ....13
....... ......... .... 14
![Page 155: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/155.jpg)
Group Science/Engineering/Math Building Cypress College, Cypress, California
2.3. Site Visit and Observations
2.3.1. General . .............. .. ... .. . ....
2.3.2. Skylights ... .............. .............
3. Building Systems Evaluation (ASCE/SEI 31-03 Tier 1) ..... ............. .
3.1. General. ................ ...................... ...................... .....................
3.2. Performance Objective ..... . ...... .. . ......... ..
3.3. Site Seismicity ..
3.4. Required Checklists .... .............
3.5. Noncompliant Items........... . . ........... ...............
3.5. 1. Basic Structural (Type C2) ............ ..
3.5.2. Supplementary Structural (Type C2) ...
3.5.3. Geologic Site Hazards and Foundations
3.5.4. Basic Nonstructural ..............
3.5.5. Intermediate Nonstructural
4. Recommendations and Next Steps
5. References .. .............
. ........... 14
. .....14
. ..... 16
. ........... 18
............ 19
.....19
......19
.21
.....21
............21
.......22
............23
.23
' ..24
. ....25
............26
Appendix A - Completed ASCE/SEI 31-03 Checklists
Appendix B - Seismic Design Parameters
Appendix C - Selected Site Photos
Mechanical
Mechanical Overview ....................................................................................................................... 1
Mechanical Equipment ............................................................................................................................... 2
Electrical
Electrical Assessment .. . 1
Electrical Systems ..
Electrical Recommendations ...... .................. . .... " ....... 4
Lighting Systems ............................................................................................................................. 5
Lighting Recommendations .................................................................................................................. 6
Power and Other Miscellaneous Systems .................... . ....... ..?
Power and Other Miscellaneous Systems Recommendations....................................................... 8
Cost Estimate
![Page 156: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/156.jpg)
PROJECT OVERVIEW
"Cypress College is the American Dream." Students can start with nothing and leave with all the skills
necessary to thrive. The College has proudly earned a reputation for academic excellence and for the
variety and depth of the educational programs offered. With the support from the local community many
programs are housed in state-of-the-art facilities.
As Cypress College continues to look forward and plan for the future, the College recognized the need to
access some of the existing facilities. Can they be retrofitted to meet tomorrow's needs, can they be
repurposed for other uses, should they be replaced? These and many more questions need to be fully
understood, discussed and answered to determine the best path forward.
In an effort to begin to answer one of the questions for one of the buildings, Cypress College has
requested to have a due diligence study performed on the Science, Engineering and Mathematics (SEM)
Building. The SEM building is a three story, approximately 100,000 square foot building constructed in
1970-71 on the Cypress College campus. The building program consists primarily of classrooms,
laboratories and offices and also includes mechanical/electrical rooms, a two-story entrance lobby, a
greenhouse and two central lecture halls that slope from the second level to ground level. The building is
currently still used for instruction with the exception of some classroom spaces which are vacant.
The study was to determine the condition of the building enclosure, structural, mechanical, plumbing and
electrical systems as it currently stands and what is necessary or recommended to maintain the facility for
current uses. The study also addressed accessibility issues as it relates to existing buildings.
The site investigation and study was completed in August and September of 2015 and consisted of visual
site observations and review of plans furnished by the College. No destructive or non-destructive testing
or investigation was conducted.
![Page 157: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/157.jpg)
Group Science/Engineering/Math BuHding
Cypress College, Cypress, California
EXECUTIVE SUMMARY
ARCHITECTURAL
The goal of the architectural assessment was to visually review the building envelope consisting of the
roof and exterior building walls and windows of its current condition and deficiencies and provide any
recommendations for the future. Building compliance with the 2013 California Building Code accessibility
requirements were also reviewed. When the building was designed, no Code for accessibility existed but
since then some provisions had been made, primarily on the first floor
Compared to the State of California Department of General Services, Office of Architecture and
Construction approved drawings dated February 13, 1970, the building has undergone very few plan
altering renovations. Maintenance has been deferred on some items while some systems or parts thereof
have been updated.
The roofing system has served it's useful life and should be removed and replaced. When the roofing
system is replaced, the various components that are connected and impacted by the roofing should be
addressed. The skylights should be replaced, roof access door and frame replaced, metal copings
installed, roof overflow drains installed, sheet metal equipment pad covers installed, cracks in the
concrete equipment screen walls filled, the concrete equipment screen walls sealed and utility supports
installed.
The concrete and aluminum window system building enclosure is in good condition. To maintain and
increase the useful life, a concrete sealer should be applied to the exterior concrete walls to minimize
moisture penetration. Cracks in the concrete wall or adjacent bridge structure should be filled and sealed.
All the window gasketing should be removed and replaced as it has shrunk with age. Window weep
holes should be drilled into the window sill. Landscaping irrigation should be checked, adjusted and
redirected to avoid spraying the windows.
An attempt to address exterior accessibility such as parking and path of travel to an entry has been made
but does not comply with the current 2013 California Building Code or even back to the 2007 California
Building Code. Code compliant accessible parking and an accessible path of travel to an entry should be
provided as any work to the building requiring a building permit will require this.
Accessibility issues have generally not been addressed within the building with the exception of the first
floor restrooms. The first floor restrooms have been modified to comply with most but not all the
accessibility requirements and require additional work.
When additions or alteration work is executed in an existing building, the cost of compliance shall be
limited to 20 percent of the adjusted construction cost of alterations when the adjusted construction cost
is less than or equal to the current valuation threshold as defined in the Code. If the adjusted
construction cost exceeds the threshold, full compliance is required unless full compliance exceeds 20
percent of the construction cost At that situation, compliance shall be provided to the greatest extent
possible without exceeding 20 percent In general the accessible parking and the path of travel to the
area of work are priority and must comply with accessibility requirements. Then the restrooms and
drinking fountains serving the area must comply with accessibility requirements.
The building complies with current exiting requirements with the current uses and corresponding area or
square feet related to the use. If uses are changed or current uses are expanded or decreased, an
exiting calculation should be made to ensure Code compliance.
![Page 158: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/158.jpg)
STRUCTURAL
The purpose of the structural report is to identify structural and nonstructural elements of the existing
Structural, Engineering and Mathematics (SEM) building that may require replacement and/or upgrades.
The ultimate objective is to estimate the costs associated with continued operation of the existing SEM
building to compare to the cost of a new replacement building. The ASCE/SEI Tier 1 procedure detailed
in this report is a "first step" screening procedure that identifies "noncompliant" items, or items requiring
further investigation/evaluation (Tier 2 analysis). Once the Tier 2 analysis is complete, required upgrades
are determined (if applicable) and costs can be estimated for these specific upgrades.
Nonstructural components identified as "noncompliant" per Tier 1 will need to be replaced to current
building code standards (no Tier 2 required). Structural and nonstructural components that are identified
as "compliant" per Tier 1 are acceptable as-is.
Mandatory vs Voluntary Seismic Upgrades
The California Administrative Code (CAC), Chapter 4 determines the requirements for seismic upgrades
to community college buildings in California. A seismic rehabilitation is required for the Community
College building if any of the following apply:
Mandatory Seismic Rehabilitation
Triaoer CAC Ch. 4 Section Applicability to Cypress SEM
Buildin11
Existing "nonconforming" building is
converted for use as a school building* CAC Section 4-307 Does not apply to the SEM building
whichis already a OSA Certified
school building.
Cost of reconstruction, alteration or
addition exceeds $25,000 and 50% of
the replacement value of the existing
building** -·
CAC Section 4-309(c) It is not anticipated that the
alterations will exceed 50% of the
replacement value; however, this will
need to be confirmed by the cost
consultant for the alterations versus
new building construction costs.
This will need to be confirmed once
the specific proposed alterations to
the SEM building have been
identified.
Itis not anticipated that structural
alterations to the building in its
current form to achieve the Life
Safety performance objective will
result in weight increases or capacity
decreases beyond the above
thresholds; however, this will need to
be confirmed after a Tier 2 analysis
is performed on the identified items
in this report.
Cost of reconstruction, alteration or
addition exceeds $25,000 but does not
exceed 50% of the replacement value of
the existing building and the proposed
modifications either**
• Increase the effective seismic weight or wind force in any story
by more than 10%
• Decrease the design capacity of any existing structural
component by more than 5%,
unless the component has the
capacity to resist the retrofit
desiQn forces
CAC Section 4-309(c)
* A "nonconforming" building is defined by CAC as any building that has not been certified by OSA as a
school building.
** Cost excludes maintenance, HVAC, insulation materials, any voluntary seismic upgrades.
![Page 159: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/159.jpg)
DLR Group Science/Engineering/Math Building Cypress College, Cypress, California
If none of the above conditions apply, a seismic rehabilitation is not required but may be performed on a
voluntary basis at the school's discretion. All structural deficiencies need not be addressed if voluntary
upgrades are performed, whereas all structural deficiencies must be addressed if seismic upgrades are
required by CAC. Voluntary seismic upgrades should not make the building worse.
At this time the estimated cost of the replacement building is not known; however, the alterations to the
existing SEM building are not anticipated to exceed 50% of the replacement value. Specific
alterations/additions to the existing SEM building have not yet been proposed, so it cannot be said
definitively at this time whether seismic rehabilitation will be required per CAC. Once the specific
alterations are identified, the changes in seismic weight and/or member capacities can be estimated by
the Structural Engineer.
Any seismic upgrades are supervised by and approved by the Division of the State Architect (DSA).
The seismic hazard value referenced ·rn this report is established by the USGS. The USGS Design Maps
summary report is used to generate acceleration parameters Sos & S01 for the site. These values are
commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a
certain site for a given seismic hazard (in this case, ASCE/SEI 31-03 Tier 1 uses the mapped 2%
probability of exceedance in 50 year values). These values then determine whether the site is classified
as "Low", "Medium" or "High" seismicity per ASCE/SEI 31-03 Tier 1 (see page 20 of the structural report).
MECHANICAL
The existing mechanical systems in the building were installed in 2009 and are in very good condition.
No work on these systems is needed or recommended at this time. The rooftop mechanical equipment,
consisting of fans and other equipment are not in good condition. These units, however, can be replaced
by maintenance as the need arises as the units are still functioning.
ELECTRICAL
The SEM building was built in the 1970's. The electrical power distribution is 45 years old and in good
condition. There are several code violations on the required clearances for electrical equipment which are
the most problematic. The other issues are simpler which are related to mounting heights of devices and
lighting control functionality. The code violations regarding the clearances will require relocation of
electrical equipment which is complicated and requires further planning since it will impact the electrical
service and power distribution. Correction of the lighting controls should be implemented with Title 24
regulations which utilizes dimming controls and LED energy efficient fixtures. The simplest corrections are
the relocation of outlets and devices to be accessible since the impacts are localized and isolated. The
extent of the renovation is dependent of the future plans and shall require a separate in-depth study.
![Page 160: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/160.jpg)
COST ESTIMATE
Cost estimates for two scenarios were developed. The first was to renovate the existing building as it
currently exists. The second was to construct a completely new building in the same location where the
existing building stands. In today's costs, the renovation work will cost approximately $19.4 million dollars
while a new building will cost approximately $46.5 million dollars.
The renovation work would address the findings of this report including deferred maintenance items, such
as the roofing system, skylights and windows. Code issues such as general accessibility and fully
accessible restrooms on each floor would be addressed. Code issues involving electrical requirements
and clearances would be addressed. Additionally, electrical revisions required to comply with energy
conservation requirements will be implemented such as providing all new energy compliant LED light
fixtures. Since renovation work exceeding $23.3 million - or half the replacement value - of the building is
not anticipated, structural upgrades would not be triggered. Changes to the layout of the classrooms,
offices and lecture halls are not included with the exception of modifications required to accommodate
accessible restrooms.
A new building of the same size would comply with all current Codes and standards including seismic
requirements. The cost includes the demolition of the existing building but does not include addressing
the displacement of the current programs housed in the building.
In both cases, the estimated cost is only for the hard cost sometimes referred to as the "brick and mortar
cost" involving the actual physical construction such as site work, building materials and labor. Soft costs
which include design, permits, insurance, testing and furnishings is not included. Soft costs vary from
project to project but can range from 15% to 25% of the hard costs.
BUILDING EFFICIENCY
Efficiencies of the existing building need to be factored as part of the due diligence study summary.
While energy efficiency is discussed within the mechanical section of this report, the purpose of this is to
provide instances for discussion of the pragmatic building efficiencies. These pragmatic inefficiencies are
difficult to quantify in monetary terms.
The building's concrete structure, relative to the provisions of the Capital Outlay Program Final Project
Proposal Approval for this building, is inherently inefficient due to the difficulty in being able to "right-size"
particular spaces locked within the building's envelope or structure. The push within spaces requiring
accessible upgrades (toilet rooms, elevators, stairs for egress/drculation, etc.), can result in spaces that
are inherently compromised, and ultimately the programming suffers as it attempts accommodate the
specific curriculum and academic needs. For example, the restrictions of the existing building make it
impossible to increase the number of specific laboratory sections that can be offered or accommodated.
Inefficiency can also be a result of the specific requirements of the educational specification that cannot
be accommodated within the parameters of the building structure, or as a result of the inability to provide
additional space required by the physical sciences - a planetarium, for example - due to the State Capital
Outlay Program limitations on space additions for modernization projects. The desired addition of a
planetarium is not possible to add under the currently approved Final Project Proposal. Additionally, the
space push mentioned above can adversely affect the ability to construct an addition in an effective
manner as well.
Finally, efficiency of one building needs to be reviewed in the context of the campus. The SEM Building,
even with an inability to become more efficient than its potential, can still be beneficial to the campus for
short term use. The existing SEM Building is efficient in terms of swing space use to alleviate space
![Page 161: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/161.jpg)
Group Science/Engineering/Math Building Cypress College, Cypress, California
needs for capital construction or for secondary effect projects, without consuming valuable parking or
another site on campus. The aggregate savings by alleviating both parking and available swing space
concerns could exceed $10 million.
![Page 162: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/162.jpg)
l N N S IR Ii N S T A A E M E N T
FEASIBILITY STUDY
CONSTRUCTION ESTIMATE
for
Science I Engineering I Math Building
Cypress College
Prepared for :
DLR Group
1650 Spruce Street, Suite 300
Riverside, CA 92507
November 9, 2015
# 14-2382
30423 CANWOOD STREET, SUITE 133 ·AGOURA IIILLS, CA 91301-4315 ·T 805-494-3703 ·F 805-497-7721 ·WWW.CPOHALLORAN.COM
![Page 163: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/163.jpg)
Science I Engineering I Math Building
Cypress College
# 14-2382
9-Nov-15
Feasibility Study Construction Estimate
Basis of Estimate
The estimate is based on feasibility study report dated September 2015 and existing plans. Estimated unit costs
include average union labor rates with prevailing wages and competitive bid conditions. Competitive bid
conditions generally occur when bids are received from a minimum of four general contractors and three
subcontractors for each trade. The estimate includes allowances and assumptions for materials, building
systems, specifications and construction schedule, these assumptions should be confirmed at the next design
stage and prior to completion of bid documents. The estimate includes general contractor markups for general
conditions, bonds, insurances, profit, estimate contingency and cost escalation to mid-point of construction.
Project soft costs are not included.
The estimated construction cost represents our best judgment as a professional consultant familiar with the
construction industry. We have no control over the cost or supply of labor, materials and equipment, a
contractor's methods of determining bid prices and market conditions. We cannot and do not warranty or
represent that bids or negotiated prices will not vary from the estimated construction cost.
Estimate Exclusions
Professional design, testing, inspection and management fees.
Fire and all risk insurance.
Legal and financing costs.
Building permits and fees.
Construction, project or staging contingencies.
Furnishings and movable equipment.
Independent commissioning.
Commtmications, technology and security equipment.
Construction phasing.
( I)
C. P. ()'Halloran Associates Inc.
Construction Cost Management
![Page 164: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/164.jpg)
Science I Engineering J 1\lath Building
Cypress College
Renovated Building
Feasibility Study Con:slruction Estimate
Feasibility Study Final PrQject Tota!
Remediation Scope Progranuning (PPP) Scope
# 14-2382
9-Nov-15
I
!Interiors (6 - ?) 30.31 2,997,232 34.50 3,411,774 64.81 6,409,006 I
8. Fixed Equiprnent, Casework, Specialties 4.53 448,175 20.00 1,977,840 24,53 2,426,015
9. Stairs and Elevators uo 128,880 4,00 395,568 5.30 524,448
! Equipment, Stairs and Elevators (8 - 9) 5.84 577,055 -------z4.-0o- 2,373,408 29.84 2,950,463 l
10. Plu1nbing 2.18 215,218 28,00 2,768,976 30.18 2,984,194
11. Heating, Ventilation, Air Conditioning 15,93 1,575,755 49.00 4,845,708 64,93 6,421,463
12. Electrical 1[,33 1,120,759 45,00 4,450,140 56.33 5,570,899
13. Fire Protection 2.32 229,627 2.00 197,784 4.32 427,411
jJ Jechanical and Electrical (Jfi:-]3) --- -- -3,141,360 124.00 12,262,608 155.77 15,403,968 I
14. Site Preparation and Selective Demolition 15.93 l,575,116 6.00 593,352 21.93 2,168,468
15. Site Development 0.45 44,250 0.45 44,250
16. Site Utilities [Sitework (l 4 - 16) 16.38 1,619,366 6.00 593,352 22.38 ----2,2i2:718--]
!SUBTOTAL 118.86 ll,753,982 214.50 21,212,334 333.36 32,966,316 I
General Conditions and General Requirements 9.0% 10,70 1,057,858 19,31 1,909,110 30.00 2,966,968
Bonds and Insurances 2.2% 2.85 281,860 5,[4 508,672 7.99 790,532
Overhead and Profit 4.0% 5.30 523,748 9.56 945,205 14.85 1,468,953
!SUBTOTAL ---- 137.70 13,617,449 248.51 24,575,320 386.21 38,192,770 I
Design I Estimate Contingency 15.0% 20.66 2,042,61 7 37.28 3,686,298 57.93 5,728,915
[TOTAL CONSTRUCTION 1 1/2015 !58.36 $15,660,067 285.78 $28,261,619 444, 14 $43,921,6851
Cost Escalation to Mid Point of Construction 04/2018 @ 5% Per Year l2.5o/o
19.79 1,957,508 35.72 3,532,702 55.52 5,490,211
ITOTAL CONSTRUCTKiN ESC/\ l.ATED 178. 1 5 $17,617.575 321 .51 $31,794,321 499.66 - $49,41 1,8961
( 2 _) C. P. O'Hallor1111 Associates lac.
Cou;trucliou Cost '.\Ian:1ge111e11t
COMPONENT SUMMARY
I. Foundations
98,892 SF
$ / GSF
98,892 SF
$ $ / GSF
98,892 SF
$ $ / GSF
$
2. Vertical Structure 3. Floor and Roof Structure 20.96 2,073,242 6.00 593,352 26,96 2,666,594
4. Exterior Cladding 4,62 457,336 18.00 1,780,056 22.62 2,237,392
5. Roofing and \Vaterproofing 8.98 888,391 2,00 197,784 10,98 1,086,175
ls1' 11 ;f :si- 34.57 3,418,969 26.00 2,511,1n 60.51 5,990,161
6. Interior Partitions and Doors 9.70 959,658 28.00 2,768,976 37.70 3,728,634
7. Interior Finishes - Floors, Walls, Ceilings 20.60 2,037 ,574 6.50 642,798 27.10 2,680,372
![Page 165: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/165.jpg)
Science I Engineering I ;\lath Building
Cypress College
# 14-2382
9-Nov-15
New Constr uction
Final Project Programming
Feasibility Study Construction Estimate (FPP) Replace1nent Planetarium Tota!
Building
98,892 SF 3,500 SF 102,392 SF
COMPONENT SUMMARY $ / GSF $ $ / GSF $ $ / GSF $
1. Foundations 9.00 890,028 35.00 122,500 9.89 1,012,528
2. Vertical Structure 22.00 2,175,624 65 00 227,500 23.47 2,403,124
3. Floor and Roof Structure 48.00 4,746,816 125.00 437,500 50.63 5,184,316
4. Exterior Cladding 63.00 6,230,196 175.00 612,500 66.83 6,842,696
5. Roofing and Waterproofing 8.00 791,136 65.00 227,500 9.95 l,018,636
1s11eili1 - s) 150.00 14,833,800 465.oo T,627,500· 160.n 16,461,300 1
6. Interior Partitions and Doors 36.00 3,560,112 70.00 245,000 37.16 3,805,112
7. Interior Finishes - Floors, Walls, Ceilings 28.00 2,768,976 65.00 227,500 29.26 2,996,476
! Interiors (6 - 7) 64.00 6,329,088 135.00 472,500 66.43 6,801,588 1
8. Fixed Equipment, Casework, Specialties 25.00 2,472,300 750.00 2,625,000 49.78 5,097,300
9. Stairs and Elevators 6.00 593,352 25.00 87,500 6.65 680,852
[Eq;p; ient, Stairs and EieVGtOrS cB - 9) 31.00 3,065,652 775.00 2,712,500 56.43 5,778,152 I
10. Pluinbing 32.00 3,164,544 30.00 105,000 31.93 3,269,544 11. Heating, Ventilalion, Air Conditioning 65.00 6,427,980 85.00 297,500 65.68 6,725,480
12. Electrical 56.00 5,537,952 70.00 245,000 56.48 5,782,952
13. Fire Protection 4.50 445,014 15 00 52,500 4.86 497,514
fMidianical and ElectriC T?Tii- -13) 157.50 ls,5·?"5;490 200.00 700,000 158.95 16,275,490 I
14. Site Preparation and Selective Demolition 1.50 148,338 20.00 70,000 2.13 218,338
15. Sile Development 18.00 1,780,056 150.00 525,000 22.51 2,305,056
16. Site Utilities 4.00 395,568 60.00 210,000 5.91 605,568
ls;tework (14 - 16) 23.50 2,323,962 230.00 805,000 30.56 3,128,962 I lSUBTOTAL 426.00 42,127,992 1,805.00 6,317,500 473.14 48,445,492 l
General Conditions and General Requirements 9.0% 38.34 3,791,519 5.75 568,575 42.58 4,360,094
Bonds and Insurances 2.2% 10.22 l ,010,229 43.28 151,494 1135 1,161,723
Overhead and Profit 4.0% 18.98 l,877,190 2.85 281,503 21.08 2,158,692
lsiJBTiJTAL 493.s4 4s:s06; --2,09[16 1,319,011 548.15 56,126,oo:z 1
Design I Estimate Contingency 12.5% 61.69 6,100,866 925 914,884 68.52 7,015,750
!TOTAL CONSTRUCTION ! t!20_i_5," 555_2]-- $54,907,796 2352_56 $8,233,955 616:67 $63T4I752J
Cost Escalation to Mid Point of Construction 04/2018 @ 5% Per Year 12.So/o 69.40 6,863,475 1041 l,029,244 7708 7,892,719
!T()TAJ ·coN-ITRlJCi·10N"ESCALA·rT:D 624.63 $6!,77!,2-'il 2,646.63 $9,263)00 693.75 $71Jij4,47 ij
Additional Cost:
Building Demolition $800,000
( 3 )
C. P. O'llalloran Assudate Inc.
Comtruction Cost l'-iauagcmenl
![Page 166: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/166.jpg)
Science I Engineering I Math Building
Cypress College
# 14-2382
9-Nov-15
Feasibility Study Remediation Scope
Component Description Quantity Unit Cost $
1. Foundations
$
2. Vertical Structnre
$
3. Floor aud Roof Structure
Allowance for structural upgrades 98,892 SF 18.20 1,800,000
Provide ADA access to raised platfonns, classrooms I
lecture halls 30 EA 6,600.00 198,000
Core and repair roof slab for new roof drains 10 EA 816.00 8,160
Replace all roof wood support under piping and conduit
runs with metal support trapezes or rubberized blocks
compatible with the roofing system 300 LF 45.60 13,680
Miscellaneous metals, concrete and anchorage 98,892 SF 0.54 53,402
$ 2,073,242
4. Exterior Cladding
Exterior concrete wall, apply clear liquid waterproofing 39,012 SF 5.10 198,961
Concrete equipment screen wall at roof
Seal vertical cracks, 2 locations LS 1,800.00 1,800
Apply clear liquid waterproofing, 2 sides 4,918 SF 5.10 25,082
![Page 167: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/167.jpg)
( 5 ) C. P. O'Halloran Associates Inc.
Construction Cost Management
Science I Engineering I Math Building
Cypress College
# 14-2382
9-Nov-15
Feasibility Study Remediation Scope
Component Description Quantity
Unit Cost $
4. Exterior Cladding
Provide new door hardware to existing exterior doors
Glazed doors 12 EA 1 ,020.00 12,240
Hollow metal door EA 870.00 870
Aluminum framed glazing
Remove and replace all window gasketing or provide a combination of gasketing and wet sealing glass 7,103 SF 24.00 170,472
Provide weep holes in the window system sill 50 EA 264.00 13,200
Soffit - patch, repair and paint 6,428 SF 5.40 34,711
$ 457,336
5. Roofing and Waterproofing
Built-up asphalt roofing system with granule-surfaced
including insulation 36,696 SF 17.40 638,510
Skylight, 1O' x 10' 4 EA 18,000.00 72,000
Roof hatch and access
EA 5,040.00 5,040
Roofi ng upstands and sheet metal
Cants and upstands 1,012 LF 14.76 14,937
Flashing 1,012 LF 23.46 23,742
Parapet metal coping 934 LF 91.20 85,181
Metal flashing at pipe penetration, allowance 20 EA 336.00 6,720
Sheet metal equipment pad covers, allowance 300 SF 22.20 6,660
Caulking and sealants 98,892 SF 0.36 35,601
$ 888,391
![Page 168: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/168.jpg)
Science I Engineering I Math Building
Cypress College
# 14-2382
9-Nov-15
Feasibility Study Remediation Scope
Component Description Quantity
Unit Cost $
6. Interior Partitions and Doors
New partition wall, allowance 1,200 LF 319.20 383,040
Patch, repair and paint partition surfacing 112,000 SF 3.30 369,600
Provide new door hardware 147 EA 750.00 110,250
Repair and paint door and frame 147 EA 420.00 61,740
Patch, repair and stain wood railing at glass wall 20 LF 75.60 1,512
Guardrail, second floor
Add decorative sloped cap to the top of curb to prevent the appearance of step and make it more difficult to stand on.
Add an additional picket fence or infill panel between
105 LF 67.20 7,056
tbe pickets, 42-1/2" high to comply with the clear space req uirement of 4", Existing space is 6". 105 LF 252.00 26,460
$ 959,658
7. Interior Finishes - Floors, Walls, Ceilings
Flooring
95,678
SF
l l.40
1,090,729
Base 12,61 1 LF 4.50 56,750
Walls, ceramic tile - allow 8' high 1,328 SF 27.60 36,653
Ceiling
Suspended acoustic ceiling tile 90,178 SF 7.98 719,620
Gypsum board, painted 3,500 SF 19.80 69,300
Gypsum board soffits and details, painted 875 SF 25.74 22,523
Exposed concrete coffer structure, painted 2,000 SF 3.00 6,000
![Page 169: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/169.jpg)
( 7 ) C. P. O'Halloran Associates Inc.
Construction Cost Management
Science I Engineering I Math Building
Cypress College
# 14-2382
9-Nov-15
Feasibility Study Remediation Scope
Component Description Quantity Unit Cost $
7. Interior Finishes - Floors, Walls, Ceilings
Accessibility - correct finished at area I items tbat are non
compliant along the accessible path of travel and in the
area or space of work 1 LS 36,000.00 36,000
$ 2,037,574
8. Function Eq uipment, Casework and Specialties
Casework, allowance
Relocate or protect equipment and furniture, allowance
Code signage
Accessi bil ity
General interior accessible path of travel
Remove projecting wall sharpeners or provide barrier
to comply with Code to alert someone of the
projection, allowance
20
EA
1 44.00
2,880
Remove projecting fire extinguisher and cabinet or
provide barrier to comply with Code to alert someone
of the projection, allowance
15
EA
180.00
2,700
Provide barriers to comply with Code to alert someone of the reduced overhead clearance at Stair #4 first floor mid-landing EA 960.00 960
Raise suspended television to provide minimum vertical clearance, second floor study cubicles EA 720.00 720
Provide pull strings and handles for suspended maps, charts and projection screen within the accessible reach range - classrooms 50 EA 90.00 4,500
400 LF 540.00 21 6,000
95,678 SF 0.30 28,703
98,892 SF 0.54 53,402
![Page 170: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/170.jpg)
Science I Engineering I Math Building
Cypress College
# 14-2382
9-Nov-15
Feasibility Study Remediation Scoee
Component Description Quantity Unit Cost $
8. Function Egnipment, Casework and Specialties
Accessibility
Restrooms
Men and women's restroom, first floor (303 SF total) 2 EA 7,800.00 15,600
Relocate door signage
Provide and locate proper wall signage
Correct water closet stall door to self-close
Replace latching mechanism
Relocate coat hook
Reverse location of flush handle to the wide side of
the stall
Relocate toilet paper dispenser
Relocate seat cover dispenser
Relocate lavatory
Men and women's restroom, 2nd and 3rd floor (606 SF
total) 4 EA 9,150.00 36,600
Toilet partitions
Relocate door signage
Provide and locate proper wall signage
Correct water closet stall door to self-close
Replace latching mechanism
Relocate coat hook
Reverse location of flush handle to the wide side of
the stall
Relocate toilet paper dispenser
Relocate seat cover dispenser
Relocate lavatory
Seismic bracing of existing casework, equipment and
storage of toxic substances 95,678 SF 0.90 86,110
$ 448,1 75
![Page 171: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/171.jpg)
( 9 ) C. P. ()'Halloran Associates Inc.
Construction Cost Management
Science I Engineering I Math Building
Cypress College
Feasibility Study Remediation Scope
Component Description Quantity Unit Cost
9. Stairs and Elevators
# 14-2382
9-Nov-15
$
Stair upgrades - Existing handrails and guardrails to be
modified. Provide contrasting strips of each stair run.
Stair No. 1, 2 and 3 - 2 floor flights each
Stair No. 4 - 1 floor flight
Elevator, 3 stops 3 opening - allowance
3 EA
EA
EA
19,200.00
21 ,600.00
49,680.00
57,600
21,600
49,680
$ 128,880
JO. Plumbing
Provide new ADA compliant restrooms, 2 EA - 2nd and
3rd floors 4 EA 23,400.00 93,600
Provide new ADA compliant drinking fountain 3 EA 9,000.00 27,000
Provide flexible coupling and fix all leaking valves and
equipment 1 LS 24,000.00 24,000
Rainwater drainage
Add roof and overflow drains, allow
J O
EA
891.00
8,910
Piping 210 LF 47.82 10,042
Seismic bracing of existing equipment and piping 95,678 SF 0.54 51,666
$ 215,218
U. Heating, Ventilating and Air Conditioning
Replace I retrofit roof mounted equipment
Make-up air units
Exhaust fans
1 LS 210,000.00 210,000
Piping insulation 50 LF 33.60 1,680
![Page 172: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/172.jpg)
Science I Engineering I Math Building
Cypress College
# 14-2382
9-Nov-15
Feasibility Study Remediation Scope
Component Description Quantity
Unit Cost $
11. Heating, Ventilating and Air Conditioning
Provide flexible coupling and fix all leaking valves and
equipment
LS
24,000.00
24,000
Air distribution and return, reconfigure existing 95,678 SF 9.60 918,509
Diffusers, registers and grilles 95,678 SF 2.70 258,331
Exterior louver, allow 8' x 4'
EA 4,200.00 4,200
Relocate thermostats at proper mounting height, allow 50 EA 540.00 27,000
Testing and balancing 95,678 SF 0.78 74,629
Seismic bracing of existing equipment and piping 95,678 SF 0.60 57,407
$ 1,575,755
12. Electrical
New outdoor transfonner, 300 KVA I EA 78,000.00 78,000
Install new cover panels on electrical switchboards and
distribution boards to protect l ive parts of the equipment
and reduce the risk of foreign objects to make contact with
live parts. Provide guard to live parts.
95,678
SF
0.30
28,703
Provide working clearances to electrical equipment 95,678 SF 0.18 17,222
Lighting system
Lighting control at Lecture Hall (3,737 SF) 1 LS 9,000.00 9,000
Re-wire lights to provide separate switch legs for lights above projector screen to provide correct controls, classrooms 33, 120 SF 3.60 I I 9,232
Replace incandescent lights, mechanical room (2,017 SF) 10 EA 750.00 7,500
Relocate switches at proper mounting hei ght 95,678 SF 0.78 74,629
![Page 173: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/173.jpg)
( 11 ) C. P. 01Halloran Associates Inc.
Construction Cost Management
Science I Engineering I Math Building
Cypress College
# 14-2382
9-Nov-15
Feasibility Study Remediation Scope
Component Description Quantity
Unit Cost $
12. Electrical
Communications conduit and outlets
Relocate outlets at proper mounting height
95,678
SF
2.40
229,627
Re-work telecom wiring installation to meet proper
cable management set-up
95,678
SF
4.20
401,848
Relocate fire alarm devices at proper mounting height 95,678 SF 0.90 86,1 10
Seismic bracing of existing equipment and lighting fixtures 95,678 SF 0.72 68,888
$ 1,120,759
13. Fire Protection
Automatic fire sprinkler wet pipe system, reconfigure
existing
Enclosed area 95,678 SF 2.40 229,627
Covered area - existing
$ 229,627
14. Site Preparation and Selective Demolition
Site protective construction, dust and noise control
95,678
SF
0.54
51,666
Selective interior demolition
Structural demolition 95,678 SF 1.80 172,220
Roofing and skylight demolition 36,696 SF 1.44 52,842
Architectural demolition 95,678 SF 6.00 574,068
Plumbing demolition 95,678 SF 0.42 40,185
HVAC demolition 95,678 SF 0.72 68,888
Electrical demol ition 95,678 SF 0.60 57,407
Fire sprinkler demolition 95,678 SF 0.24 22,963
Debris removal 1 LS 118,628.77 118,629
Selective site demolition I LS 14,400.00 14,400
![Page 174: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/174.jpg)
Science I Engineering I Math Building
Cypress College
# 14-2382
9-Nov-15
Feasibility Study Remediation Scope
Component Description Quantity Unit Cost $
14. Site Preparation and Selective Demolition
Hazardous material abatement - allowance 95.678 SF 4.20 401,848
$ 1,575,1 16
15. Site Development
Accessible parking
Redesign parking layout
Revised accessible parking stall depth from 14' 6" to
1 8' deep
4
EA
90.00
360
Revised northern loading I unloading striping depth from 16' to 18' deep 3 EA 150.00 450
Provide code compliant parking signage and directional signage
Grade accessible path to sidewalk to comply with Code
LS 6,000.00 6,000
allowed sloped and cross slopes LS 14,400.00 14,400
Accessible path of travel to East Building entry
Reconstruct perpendicular curb ramp to comply with
Code EA 9,000.00 9,000
Identify an accessible path to the building entry or
regrade wal kway for the slopes to comply with Code l LS 7,200.00 7,200
Adjust direction oflandscape irrigation away from
building exterior windows LS 5,400.00 5,400
Adjust strength of sprinkler irrigation spray LS 1,440.00 1,440
$ 44,250
16. Site Utilities
$
![Page 175: TABLE OF CONTENTSnews.cypresscollege.edu/Documents/2017... · commonly-used seismic hazard parameters that indicate how much ground acceleration is expected at a certain site for](https://reader034.vdocument.in/reader034/viewer/2022042108/5e88aa21f8cb0162024696df/html5/thumbnails/175.jpg)
( 12 ) C. P. O'HaJloran Associates Inc.
Construction Cost Management