table of content - miga...eurasia subway group joint venture kadıköy-kartal subway completion...
TRANSCRIPT
Eurasia Subway Group Joint Venture
Kadıköy-Kartal Subway Completion Construction, Electro Mechanic Systems Supply, Montage and Operation Project
1
TABLE OF CONTENT
1. Specifications of the Project ........................................................................................5 1 a) The flow chart, capacity, total area, used technology, the number of
personnel that will work at the planned facility, ................................................................6 Excavation ........................................................................................................8 Construction Works.........................................................................................12
b) Usage of natural sources (land, water, the type of energy to be used etc.) ...14 Land Use:........................................................................................................14 Water Use: ......................................................................................................14 Energy Use: ....................................................................................................14
c) Amounts of wastes that will be produced (solid, liquid, gas) and their chemical, physical and biological features. ....................................................................15
Solid Waste.....................................................................................................15 Liquid Waste: ..................................................................................................16 Gas Waste: .....................................................................................................16
d) The risk of accident that may be growth out of the technology and the materials used................................................................................................................19
e) The precautions that will be taken against the probable environmental impacts of the project ..................................................................................................................24
Construction Phase.........................................................................................24 Solid Waste.....................................................................................................24 Liquid Waste ...................................................................................................24 Gas Waste ......................................................................................................24 Noise and Vibration.........................................................................................24 Operation Phase .............................................................................................25 Solid Waste Generation and Disposal During Operation ................................25 Wastewater Generation During Operation......................................................25 Noise Pollution During Operation....................................................................26
2. Project Location ..........................................................................................................28 a) Existing land use and its quality (agricultural land, forest area, planned area,
water surface etc.)..........................................................................................................28 2.b) Evaluation of the project site considering the wetlands, sea sides,
mountainous districts and forest regions, agricultural areas, national parks, specially protected areas, dense areas in terms of population, historical, cultural, archaeological and similar important areas, erosion districts, landslide districts, forestation fields, potential erosion and forestation fields, with taking into consideration of the list of Sensitive Districts that takes place at Appendix V and aquifers that should be protected in accordance with the Law About Ground Water numbered 167..................................31 3. The alternatives of the Project and Its Place (the reasons of why that project
technology and that project place are chosen) ............................................................35 Results..............................................................................................................................36 Annexes: ..........................................................................................................................40 References: ......................................................................................................................41 The Group That prepared The Project Identification File ............................................42
Eurasia Subway Group Joint Venture
Kadıköy-Kartal Subway Completion Construction, Electro Mechanic Systems Supply, Montage and Operation Project
2
Figure 1: Location of the line....................................................................................7 Figure 2: TBM Picture ..............................................................................................9 Figure 3: Placed Segments......................................................................................9 Figure 4:Dispersion of the equivalent noise level...................................................19 Figure 5 :Noise Dispersion During Operation ........................................................27 Figure 6: Geological Specifications of Istanbul ......................................................29 Figure 7: Earthquake Map of Istanbul ....................................................................30
Table 1 Excavation Amount ...................................................................................15 Table 2: Mass Flow of the Dust..............................................................................16 Table 3 :List of equipments that will work above the ground .................................18 Table 4: Noise Dispersion During Operation..........................................................26
Eurasia Subway Group Joint Venture
Kadıköy-Kartal Subway Completion Construction, Electro Mechanic Systems Supply, Montage and Operation Project
3
ANNEX-IV SELECTION AND ELIMINATION CRITERIA
BASED FOR PREPARING THE PROJECT INTRODUCTION FILE
Heading Page:
Name, address, telephone and fax numbers of the project owner:
Istanbul Greater Metropolitan Municipality
Division of Transportation
Department of Railroad System
M. Nezih Özmen Mah. Kasım Sok
MERTER/ GÜNGÖREN/ İSTANBUL
Tel : +90 212 449 41 75-76
Fax :+90 212 449 41 80
Contractor Firm:
Avrasya Metro Grubu (Eurasia Subway Group Joint Venture )
(ASTALDİ S.p.A – MAKYOL – GÜLERMAK)
Tepecik Cad. Melodi Sk. İ.T.Ü Blokları E- Blok 34337
Etiler/İstanbul
Beşiktaş Tax Office
Tax Number: 1050562403
Project Name:
Kadıköy-Kartal Subway Completion Construction, Electro Mechanic Systems Supply,
Montage and Operation Project
Name of the Location of the site selected for the project:
The City of Istanbul, Kadıköy, Maltepe and Kartal Provinces
Eurasia Subway Group Joint Venture
Kadıköy-Kartal Subway Completion Construction, Electro Mechanic Systems Supply, Montage and Operation Project
4
Description and Objectives of the Project:
In Istanbul, after removal of the tram voyages in 1966, land transportation became
insufficient due to the rapid growth of the population, caused by the immigration.
In metropolitan cities all over the world, generally, efficiency of the railway systems are
measured and monitored considering the percentage of the railway transportation to total
transportation. According to the data of the last couple of years, these rates were; 60% for
Tokyo, 31% for New York, 22% for London, %25 for Paris while it was 3,6% in Istanbul
(Ref.:i). These numbers clearly shows that, in Istanbul, considering the opportunities that
are supplied to the public in utilization of railways in daily transportation, there is a sharp
work load.
Since railway transportation is fast, economic, safe, environmental-friendly and
contemporary systems, for Istanbul as well as the other metropolitan cities are the firstly
thought solutions for in-city transportation problems.
The subject of this Project description folder is construction and operation of the railway
public transportation including 43,447 km tunnel alignment respectively divided as right
alignment 21,694 km, left alignment 21,753 km as well as 16 subway station buildings
construction 3 layover place and 5 turnout structure, starting from Kadıköy and following
the D-100 motorway ending in Kartal in Anatolian side of İstanbul.
Name, Address, Telephone and Fax Numbers of the Working Group / Institution That Prepared the Report:
Report Coordinator Environmental Engineer Emir Salman
Engin Salman
Gülşah Kazanç
F.Çakmak Mh. C.Gürsel Cd. 115/16 Pendik İstanbul
Tel: 0-216-596-0618
Fax: 0-216-397-9052
i http://www.marmaray.com.tr/genel_yolculuk_talepleri.htm
Eurasia Subway Group Joint Venture
Kadıköy-Kartal Subway Completion Construction, Electro Mechanic Systems Supply, Montage and Operation Project
5
1. Specifications of the Project Istanbul Greater Metropolitan Municipality (IBB), decided to construct a railway
transportation system inline with the D-100 motorway, which is one of the most important
arterials. This direction is currently utilized for daily in-city traffic between Gebze - Kartal -
Maltepe - Göztepe – Harem instead of intercity transport.
For this purpose, IBB, Transportation Division, Railway System Directorate is tendered the
construction works to Eurasia Metro Group Joint Venture (ii) which proposed the most
appropriate proposal.
In the scope of construction tender, construction of all of the tunnels, direction structures,
basic construction works of the station buildings, rail placement works, construction of
storage area and workshops. The subject of this project is construction and operation of
the railway public transportation including 43,447 km tunnel alignment respectively divided
as right alignment 21,694 km, left alignment 21,753 km as well as 16 subway station
buildings construction 3 layover place and 5 turnout structure.
This project description folder which is prepared according to the Environmental Impact
Assessment (EIA) Regulation (OG Date: 16.12.2003 Nr: 25318) aimed to determine the
specifications and potential environmental impacts of the project.
ii This project, preliminary granted to Yapı Merkezi· Doğuş - Yüksel - Yenigün inşaat Joint Venture by
İETT (İstanbul Electric Trams and Tunnel Operations General Directorate that owns the project in those days. The Project Desvription Folder which is prepared by the mentioned group is approved by Istanbul Provincial Office of the Ministry of Environment and Forestry (MoEF) on 22 July 2005.
Although there is no differences on the described “Kadıköy-Kartal Subway Completion, Electro Mechanical Systems Supply, Montage and Operation”, the project description folder is revised considering the following justifications:
1. The project’s ownership is transferred from İETT to IBB Division of Transportation, Railway System Directorate.
2. The contractor group is decided to be Eurasia Subway Group Joint Venture by IBB. 3. Small amendments in the project: In first phase a total of 17 stations was planned. Yet, during this
process the station which was planned to be built on the ground, as a viaduct is excluded and the plan is revised to include 16 stations, all underground.
There is no difference in technical details of the project, direction, construction technology, materials and equipments to be used.
Eurasia Subway Group Joint Venture
Kadıköy-Kartal Subway Completion Construction, Electro Mechanic Systems Supply, Montage and Operation Project
6
1 a) The flow chart, capacity, total area, used technology, the number of
personnel that will work at the planned facility,
The work flow chart of the Kadıköy-Kartal Soft Railway Transportation system is
represented in Annex-1 of the report. As it is seen in the chart, the project is planned to be
operated in 30 months. This plan is prepared by the Eurasia Metro Group Joint Venture
which is the new contractor of the work.
Project, forms the most important part of the Istanbul Anatolian side Subway system.
The project covers construction and operation works of the Kadıköy-Kartal Subway Line. It
is planned to be a total of 16 station and 1 storage facility in this line which is
approximately 21.4 km length.
Technical Specifications of the alignment:
The alignment which is 43,447 km tunnel alignment respectively divided as right alignment
21,694 km, left alignment 21,753 km as well as 16 subway station buildings construction 3
layover place and 5 turnout structure.
The alignment between Kadıköy and Kartal will cross the following station structures:
Kadıköy, İbrahimağa, Acıbadem, Ünalan, Göztepe, Yenisahra, Kozyatağı, Bostancı,
Küçükyalı, Altayçeşme, Maltepe, Gülsuyu, Cevizli, Hastahane, Soğanlık, Kartal.
Layover over the alignment
• Göztepe (Between ch: 4+706 and 5+287),
• Bostancı (Between ch: 9+652 and 10+406) and
• Altayçeşme (between ch: 13+575 and 14040);
Turnout Tunnels;
• Kadıköy (Between Ch: 0+444 and 0+818),
• Acıbadem (Between Ch: 2+509 and 2+623),
• Kozyatağı (Between Ch: 8+040 and 8153),
• Maltepe (Between Ch: 15+679 and 15+799) and
Eurasia Subway Group Joint Venture
Kadıköy-Kartal Subway Completion Construction, Electro Mechanic Systems Supply, Montage and Operation Project
7
• Kartal (Between Ch: 20+574 and +20+833).
Location of the project in the city of Istanbul is given in the Figure 1, line cross section and plans are given in Annex-2.
Figure 1: Location of the line
The list of the stations is given below: 1. Kadıköy station
2. İbrahimağa station
3. Acıbadem station
4. Ünalan station
5. Göztepe station
6. Yenisahra station
7. Kozyatağı station
8. Bostancı station
9. Küçükyalı station
10. Altayçeşme station
11. Maltepe station
12. Gülsuyu station
13. Cevizli station
14. Hastane station
15. Soğanlık station
16. Kartal station
Maximum capacity of the system is 65,000 (passenger/direction/hour). This shows that,
this project will considerably contribute to the traffic and air pollution problems of Istanbul.
Eurasia Subway Group Joint Venture
Kadıköy-Kartal Subway Completion Construction, Electro Mechanic Systems Supply, Montage and Operation Project
8
Excavation
Excavations for all layover, turnouts and connection tunnel work related to the above
section will be carried out in conventional method prior to the arrival of the Tunnel Boring
Machine (TBM). Between Altayçeşme – Kartal stations, between km 14+004 - 20+530 in
right alignment and between km 14+076 - 20+607 in left alignment TBM will be used.
Between Kozyatağı – Altayçeşme, between km 14+004 - 8+887 in left alignment and
between km 14+076 - 8+955 in right alignment will be excavated in conventional method.
At the alignment ending point, between km 20+833 - 21+694 in right tube and km 20+872
- 21+753 in left tube planned extension towards Pendik direction will be made by TBMs.
Tunnel boring from the beginning (km 0+000) to km 8+887 (in right), and to km 8+955 (in
left) (Kadıköy-Kozyatağı) will be made by Anadoluray consortium. Yet, final concreting,
and electromechanically works will be left for our consortium. All layover, turnouts,
connection tunnels between some of the stations, elegators will be caried out by
ourselves. open excavation and cut&cover of 16 stations and ticketing halls are in our
scope.
Tunnel Excavations
Tunnel Boring Machines (TBM) will be used during tunneling. These machined are the
group of hydraulic machines which are produced suitable to the ground conditions. TBM
excavates the ground via the special equipments placed in its in front, and in meantime
pushes itself forward. In below figure, a sample picture of a TBM that is used in an other
project.
Eurasia Subway Group Joint Venture
Kadıköy-Kartal Subway Completion Construction, Electro Mechanic Systems Supply, Montage and Operation Project
9
Figure 2: TBM Picture
In TBM there is a control room and lifting and montage equipments that allow the place
the concrete elements (segments) to tunnel surface. In below figure, a view of the placed
concrete segments in an other project. Figure 3: Placed Segments
TBM pushes itself forward resisting on the placed concrete segments. After the placement
of the concrete segments cement solution is applied to ensure the stability of the tunnel.
Eurasia Subway Group Joint Venture
Kadıköy-Kartal Subway Completion Construction, Electro Mechanic Systems Supply, Montage and Operation Project
10
In tail section of the TBM necessary supporting equipments and other systems take place.
There is also a completion system which is called ‘Back up’ system. This system coveres
the removal of the excavation material, completion of necessary materials for cement
solution and arrival of the concrete segments to the montage area. As a necessity of the
system temporary rails are placed in the tunnel and excavation materials are removed by
wagons. Tail and middle sections of the TBM are designed to let the wagons in to remove
the excavation materials.
Thanking to the technology used, it will be possible to progress without any problem about
water layer. TBM machine is designed as a steel tube which is called ‘protective shield’.
The shield is water proof and It is not possible the water in. While the TBM progressing
underground, it covers the tunnel façade with a prefabricated material and injects cement
between the ground and the covering material. Water resistant gasket is placed between
the concrete tunnel covering materials. Thus, water flood risk during tunnel boring is
almost zero.
Cross sections of the excavation works for the Kadıköy-Kartal Subway Line is given in the
Annex-2.
Cut & Cover Excavations
Among the tunnel direction there will be 16 underground stations. Deeper excavation will
be operated for this purpose and excavation supporting system will be used. In this
system, preliminary stakes will be placed to the construction area. After that, excavation
work will be done step by step in conventional manner with anchorages in determined
altitudes.
Before starting excavations, it will be determined if there is point that the traffic has to be
interrupted. Plans for re-arrangement of the traffic flow will be developed. Following the
approval of the plans mitigating measures will be taken. Necessary permits from
Highways Regional Directorates and Provincial Traffic Commission will be obtained.
Apparently, existing infrastructures at project site will be identified consulting to relevant
administrations. When necessary, infrastructure replacements will be realized.
Eurasia Subway Group Joint Venture
Kadıköy-Kartal Subway Completion Construction, Electro Mechanic Systems Supply, Montage and Operation Project
11
In deeper stations, construction works will be managed in two segments. In this phase,
stakes will be placed and together with anchorages it will be ensured to progress into the
desired depth.
After completion of the station constructions, back-filling works will start. The ground will
be filled until it reaches its actual altitude. At this stage, if it is necessary, infrastructures
which are de-placed, will also be taken to their actual positions.
Excavation Equipments
Tunnel excavations will be done via TBM. As it is explained above, the excavation
materials will be removed via wagons and transferred to licensed excavation material
disposing areas via special trucks.
During Open/Close and surface excavations, conventional excavations materials
Backhoe, Loader and excavation transporting trucks will be used.
During transporting of excavation materials, existing traffic and environmental rules will be
obeyed. The trucks will not carry materials more than allowed, and the materials will be
covered.
Duration
Tunnel excavations planned to be completed in 30 months. Station excavations will be
completed in 6 month periods following the land delivery.
Direction Specification
Technical information of the subway line such as km, excavation depth and station depth
are represented in Annex-2. All of the stations are designed to be underground.
Eurasia Subway Group J.V. confirms that if any historical monument is encountered
during excavation, the operation will be immediately stopped and the Ministry of Culture
and Tourism will be informed. Excavations will go on if only necessary permits are
obtained.
Eurasia Subway Group Joint Venture
Kadıköy-Kartal Subway Completion Construction, Electro Mechanic Systems Supply, Montage and Operation Project
12
Construction Works
In tunnels construction and excavation works will be proceed simultaneously.
Explanations of construction of tunnels can be found excavation section. Thus, it is not re-
iterated here.
In stations, after the excavations, construction works will be proceed in conventional
manner in two stages: rough and delicate works. Electro-magnetic equipments will be
installed during delicate works.
All of the underground stations are designed to allow receiving the subway 185 m length.
In stations, all necessary safety measures as well as air conditioning and fire control
measures will be taken.
Total construction duration is planned to be 30 months. General framework of the project
contract is given below:
• All of the 16 stations will be underground. One of the stations is will be on the
ground as a viaduct because of the topographical conditions.
• The first station (placed in Kadıköy) together with the line between this station and
the starting point will be constructed with open/close method. 12 of the rest will be
constructed as tunnel. 3 of the rest will be constructed as tunnel, yet its
components such as ticket halls and entrance&exits will be built with open/close
method.
• Storage area and workshop are still under discussion and planned to be in the
same level with the ground.
According to the technical report which is prepared by Istanbul Technical University (ITU)
Transportation Main Field of Study on on 12.04.2005 the following articles are targeted
and expected:
• The top voyage requirement is 65.000 passenger / hour / one way for 2025. This
exceeds 60.000 passenger / hour / one way, which is the limit for subway system.
Apparently, the stations has to be designed responding to the value of 2025 which
is top hour / one way 11.000 passengers.
• All of the line will be operated with tunnel-boring-system. Thus, D100 motorway
will be effected in minimum level.
Eurasia Subway Group Joint Venture
Kadıköy-Kartal Subway Completion Construction, Electro Mechanic Systems Supply, Montage and Operation Project
13
• During operation TBM and EPB TBM machines will be used. Thus, time
requirement will be kept in optimum levels. Also, safety will be ensured for both
workers and general environment as well as for third parties.
In stations, air conditioning shafts are planned to be used for equipment transfer during
construction when possible.
The storage and maintenance area is planed to be located on 19+000 km between Cevizli
and Soğanlık stations.
One of the most important system which will be established in the scope of the project is
the communication system that allows voice and data conduction including mobilize trains.
The sub systems under the communication system are:
• Communication system
• Telephone system
• Wireless communication system
• Public announcement system
• Closed loop TV system
• Hour system
• Fire Alarm System
• Train Display Info System
The equipment which are planned to be used in this project are mentioned below:
• TBM / EPB TBM tunell boring machines and health kit, bentonite unit,
excavation wagons, locomotive, injection unit, pre-cast transporting
vehicles, rail vb. Other supporting equipments.
• Portable winches
• Forklifts
• Excavators
• Loader
• Roadheader
• Jumbo
• Trucks
• Concrete mixers
• Shof-crefe units
Eurasia Subway Group Joint Venture
Kadıköy-Kartal Subway Completion Construction, Electro Mechanic Systems Supply, Montage and Operation Project
14
• Water pumps and pressure tanks
• Emergency energy generators
• Compressors
Most of the above mentioned equipments will be used underground. Thus it is not
expected that they will effect the existing noise level.
b) Usage of natural sources (land, water, the type of energy to be used etc.)
Land Use:
This project will be constructed underground. Depths between 25 and 50m are belong to
the Treasury and thus there is no ownership document for that. Also, the stations will be
constructed to the points which are generally used by the public. In existing situation in-
city roads are publicized roads and they are belonging to the Treasury. During
construction phase, it is intending to design without nationalization. Yet, if necessary, IBB
will proceed with the necessary steps.
Water Use:
Drinking water of construction will be supplied with demijohns.
During tunnel construction 1 m3/day water will be used to prevent dust.
Energy Use:
Electricity need of the project will be supplied by the city works. Currently, transformer
allocation studies are in progress. A diesel generator will be used incase of any
interruption of the city works.
During operation subways will work with electricity.
Eurasia Subway Group Joint Venture
Kadıköy-Kartal Subway Completion Construction, Electro Mechanic Systems Supply, Montage and Operation Project
15
c) Amounts of wastes that will be produced (solid, liquid, gas) and their
chemical, physical and biological features.
Solid Waste
Solid waste from the staff
During different stages of the construction, different number of staff will be assigned.
During the peak period, there will be a total of 600 personnel. All of the calculations are
made considering the maximum value.
Water generation from one person 1,34 kg (iii). Total daily waste amount will be 804 kg.
All of these waste will be disposed in line with the Solid Waste Control Regulation (14
March 1991 / 20814). They will be collected in containers and delivered to the Municipal
waste disposal system.
Solid waste from constructional activities
Cross cuttings of the excavations which will be made in this project is given in the Annex-
2. Amount of the excavations are given in Table 1.
Table 1 Excavation Amount
Operation Excavation Amount (m3)
Tunnel excavation 950.000
Station excavation 550.000
Total Excavation 1.500.000
Disposal of these waste will be managed in line with the Excavation Soil and Construction
Waste Regulation (18 March 2004 / 25406) and will be disposed to the licensed disposal
area, given in the Annex-3. This is under the responsibility of the J.V.
iii State Statistical Institute, 2005 Environmental Statics
Eurasia Subway Group Joint Venture
Kadıköy-Kartal Subway Completion Construction, Electro Mechanic Systems Supply, Montage and Operation Project
16
Liquid Waste:
During different stages of the construction, different number of staff will be assigned.
During the peak period, there will be a total of 600 personnel. All of the calculations are
made considering the maximum value.
Daily water consumption per person is assumed to be 60 liters (iv)
600 person X 60 l/day = 36.000 l/day
It is assumed that 100 % of this water is disposed as wastewater. Thus, 36 m3 / day
wastewater is expected. This wastewater totally will be given to the sewage system.
During construction ready-mixed concrete will be used. Thus, no water will be used for
this purpose.
Gas Waste:
During excavations there will be four main dust source.
a) During excavations
b) During loading of the excavation material
c) During transportation
d) During unloading of the excavation material
There will be dust generation during tunnel excavation. Yet, these, will stay underground.
But, dust generation from transportation and unloading to the disposal area is calculated
below.
500.000 m3 of the total excavated materials which is 1.500.000 m3 will be used as filling
material. Thus, only 1.000.000 m3 excavation material will be transported and disposed.
Thus, mass flow of the generated dust is calculated considering the below parameters. Table 2: Mass Flow of the Dust
Monthly production (28 months) 35714 Ton
Daily Production (30 day/month) 1190 Ton
Hourly Production (24 hour /day) 50 Ton
iv Regulation on Preparation of the projects regarding to drinking water systems of cities and towns
(22 April 1985 / 19733)
Eurasia Subway Group Joint Venture
Kadıköy-Kartal Subway Completion Construction, Electro Mechanic Systems Supply, Montage and Operation Project
17
a) Dust generation during loading
Dust emission factor is assumed to be 0,01 kg/ton
50 ton/hour x 0,01kg/ton= 0,50 kg/hour. b) Dust generation during movement of the vehicles in the site:
In the tunnels transportation will be done via wagons. Thus, the dust will stay
underground. Below mentioned measures will be undertaken during transportation.
• During transportation all the trucks will be covered.
• The trucks will cross the water pools entering and exiting the project site and dust
transportation via the wheels will be prevented.
Transportation will be realized on asphalt ways. Trucks will be covered. Thus it is
assumed that a minimum amount of dust will be generated.
c) Dust generation during unloading
Dust emission factor is assumed to be 0,01 kg/ton.
47 ton/hour x 0,01kg/ton= 0,50 kg/hour.
Thus, mass flow of the dust generation is calculated to be 1 kg/hour which does not
exceeds the limit value given in the Table 40.1 of the Industrial Sourced Air Pollution
Control Regulation that is 1,5 kg/hour.
Eurasia Subway Group J.V. confirms and approves that it will act complying the
requirements of the Industrial Sources Air Pollution Control Regulation. For this purpose, it
confirms the followings during excavation and transportation of excavation material:
- loading and unloading without fling,
- Covering the trucks with calash or bulky materials which has over 10mm diameter.
Noise
During the excavations the noise will be underground and it is not expected it will effect
the environment.
Eurasia Subway Group Joint Venture
Kadıköy-Kartal Subway Completion Construction, Electro Mechanic Systems Supply, Montage and Operation Project
18
Yet, during the construction of the stations and open excavations noise can be occurred.
Thus, during noise calculation only equipments which will work above the ground are
taken into consideration.
Table 3 :List of equipments that will work above the ground
Unit Equipment Noise Level (dBA)
1 Excavator 105
2 Excavator + Cracker 105
1 Loader 110
2 Truck Dump 85
1 Driller 100
12 Vibrator 100
1 Mobil Winch 95
1 Fuel-oil tank 85
1 Truck 85
4 Pick-Up 85
2 Small lorry 85
It is not possible to say that all of the equipments mentioned in the
will work simultaneously. Yet, in order to calculate the maximum noise level it is assumed
that all of the equipments worked at the same time.
Using the below formula:
10110
110 LiinLogLeq=∑
=
Equivalent noise level is calculated to be 129,8 dBA. Dispersion of this noise level:
2410 rQLogLwLpt π+=
Here:
Lw= Noise level of the machine (Here, equivalent noise level is used)
Q= Reduction factor (assumed to be 1)
r= Distance
Eurasia Subway Group Joint Venture
Kadıköy-Kartal Subway Completion Construction, Electro Mechanic Systems Supply, Montage and Operation Project
19
Figure 4:Dispersion of the equivalent noise level
0
20
40
60
80
100
120
140
Mesafe (m)
Gür
ültü
Düz
eyi (
dBA
)
Gürültü Düzeyi 129,7 84,7 78,7 75,2 72,7 70,8 69,2 67,8 66,7 65,6 64,7
0 50 100 150 200 250 300 350 400 450 500
As it is seen in the Figure 4, even in case all the equipments works at the same time the
equivalent noise level reaches to the limit value which is determined to be 70 dBA
according to the Assessment and Management of environmental Noise Regulation
(01.07.2005/25862) in 300 m.
Beside this, Eurasia Subway Group J.V. confirms and approves that it will measure the
environmental noise which will occur during construction and operation phases and report
them within the “Environmental Status Monitoring” Reports comparing with the
Regulation’s requirements. These reports are planned to be prepared in 3 month periods.
d) The risk of accident that may be growth out of the technology and
the materials used
During excavation phase the main part of the direction is located in 20 m under the
surface or deeper. Thus, no significant affect above the ground is expected. Yet, in
vulnerable areas that the ground conditions change in close distance, a monitoring system
will be installed. In this monitoring system ground movements will be monitored via
sensors and stable points. Ground measurements will be realized in determined periods
and land slides will be monitored. Also, in critical points, works will be proceed carefully
and slowly. For this purpose, studies for “Ground consolidation Control System” are in
Eurasia Subway Group Joint Venture
Kadıköy-Kartal Subway Completion Construction, Electro Mechanic Systems Supply, Montage and Operation Project
20
progress. Main principle of the system is to determine the consolidation of the ground via
specific and sensitive sensors. For this purpose the following equipments
Surface Monitoring Points (SMP)
These points are used for controlling horizontal and vertical deformation and covers the
followings:
• Various types of SMPs to control deformation depending on the structures to be
monitored.
• Measurements on surface monitoring points via conventional vertical control
topographic equipments.
Convergence Measurement Equipments (CG)
These are used to control deformation in certain points during open excavation and
tunneling.
• There will be 2 convergence points at open excavation area. In tunneling areas
there would be more points, up to 7. These points will be installed where the
relevant engineer approved.
• These measurements will be realized via strip extensometer.
Probe - Extensometer (PEX)
• It is used to control ground consolidation
• Extensometer points are installed to the open well holes tied to soil or rock on the
monitoring area together with magnetic scanner.
• Controlling issues, are realized according to the values obtained from the reading
units in the central guide tubes -Inclinometer
• These are used to control the horizontal deformation from the surface to
excavation bottom.
• These equipments are installed in the vertical well holes.
• During control, the probe is taken down among the tube.
Eurasia Subway Group Joint Venture
Kadıköy-Kartal Subway Completion Construction, Electro Mechanic Systems Supply, Montage and Operation Project
21
Vibrating Strand Pressure Measuring Equipment (VSG)
This is used to measure the pressure on steel reinforcements and buttres.
• These equipments are installed to the steel tendinous.
Seismograph
This is used to measure the vibrations during construction works.
• Portable seismographs are used for vibration control. These record 3 octagonal
vibrations including peak particulate rate, half wave frequency, peak accelerate,
peak de-placement Vibrations will be monitored from the points which are
determined by the Engineer.
• Necessary vibration measurements will be monitored to control of the work.
Tilt meter
Tilt meters are used to measure the structural slope and they are tied to structures
(buildings) with a chassis.
Stressing Measurement Equipment With Electric Resistance
It is used to measure the deformation of anchorage and ancestry metal elements. These
equipments generally installed on a clear metallic surface via cement, fulfilling the
producers requirements.
Survey Triangulation Points
Survey triangulation points will be formed on the points that are determined by the
engineer for inspecting deep consolidation.
If any collapse / consolidation is determined in the data provided by above equipments,
excavation operation will be stopped immediately and necessary engineering measures
will be taken. These measures are generally the followings:
• Slowing down the excavation
• Using concrete nail
• Reinforcement the ground
Eurasia Subway Group Joint Venture
Kadıköy-Kartal Subway Completion Construction, Electro Mechanic Systems Supply, Montage and Operation Project
22
Eurasia Subway Group J.V. undertakes and confirms that it will set up above mentioned
equipments in order to avoid land slide, collapsing and consolidation etc. and it will take
engineering measures inline with the data received from these equipments.
Eurasia Subway Group J.V. undertakes and confirms that it will comply with the Labour
Law (4857) and other related Regulations during both the construction and operation.
Thus, occupational health and safety procedures have been prepared. These procedures
will cover below mentioned main headings:
These procedures describe the main framework for the actions to be taken during
emergencies about the environment and occupational health and safety.
Environment:
• Prohibit releases of hazardous substances
• Minimize the negative effects of these substances,
• Remove the effect totally where possible
OH&S
• Save the human life,
• Save people from dangerous areas,
• Save the working area, materials, the product and the equipments,
• Ensure the safety of the working place,
• Ensure the normal working conditions,
• Clean the waste materials in working area
Responsible people are determined in order to ensure fast action during emergency.
Emergency team shares these responsibilities. People in this team, carry responsibilities
in line with their background and education beside their main work.
• Communication team
• Fire fighting team
• Rescue team
• Protection team
Eurasia Subway Group Joint Venture
Kadıköy-Kartal Subway Completion Construction, Electro Mechanic Systems Supply, Montage and Operation Project
23
• First aid team
Accoutrements and equipments that will be used during emergency cover the followings:
• Siren
• Emergency exits
• Fire fighting tubes
• Fire masks
• Fire hose and water tanks (construction site plan in line with the OH&S requirements)
• Signs
• First aid kit, ambulances
• First aid supplier
• Hazardous chemicals receptors (construction site plan in line with the OH&S
requirements)
• Fire pump (construction site plan in line with the OH&S requirements)
• Communication systems (walkie & talkie, telephone, etc.)
Emergency procedure and related documents such as:
• Emergency plan,
• Communication instruction,
• Action instruction for fire,
• First aid guide
Connection tunnels will be constructed between twin tunnels in every 300 meters in case
fire, flood, earthquake etc. These will be used for evacuation and intervention purposes.
In stations, more than one emergency exits are designed to ensure fast evacuation.
Scada system will be set up in order to minimize the hazard of the gases of fire case. In
stations fire warnings and fire fighting systems will exist. Fire fighting equipments will be
set up at intervals.
Drainage systems are in place in order to prevent flood. In case of flood, water will be
collected in pumping wells and removed from the tunnels via the pumps.
Eurasia Subway Group Joint Venture
Kadıköy-Kartal Subway Completion Construction, Electro Mechanic Systems Supply, Montage and Operation Project
24
e) The precautions that will be taken against the probable environmental
impacts of the project
Construction Phase
Solid Waste
Amount of expected waste from the personnel during construction is calculated in Chapter
1.C (pg. 15). This waste is municipal waste and they will be collected in containers and
disposed by the Municipality in line with Solid Waste Management Regulation (14.03.
1991 / 20814).
In construction site no maintenance for the equipments will be done. These works totally
be realized out of the project area.
Liquid Waste
Waste water occurred at the project will be disposed via the sewage system.
Gas Waste
It is possible that dust will be occurred during construction. Since construction works will
be proceed underground the dust will not get out of the project site. In order to ensure that
the staff does not effected from the dust, protective equipment will be used.
Noise and Vibration
During the excavations the noise will be underground and it is not possible that the people
living around will be effected from the noise and vibration.
Yet, during open station excavations noise will be occurred. According to the calculations
expected level of noise will ensure the limit values of Assessment and Management of
Environmental Noise in 300 m. Below measures will be undertaken in order to mitigate
noise level.
• Maintenance of noise sources will be done periodically,
• These sources will be insulated where possible
• The construction area will be covered
Eurasia Subway Group Joint Venture
Kadıköy-Kartal Subway Completion Construction, Electro Mechanic Systems Supply, Montage and Operation Project
25
Noise will be occurred only in construction phase. During construction the workers will use
protective equipment in line with the Labour Law (4857)
Operation Phase
The voyages starts everyday at 06:00 am and end at 00:20 am. At peak hours voyages
will be one in every 5 minutes. In rare hours the voyages will also be sparse, one in every
8 minutes. (v).
During the operation of the project 65000 passengers are expected to be transported. The
system will serve 12 hours / day. Considering the full capacity, the system will transport
780.000 in one way.
Solid Waste Generation and Disposal During Operation
Stations will serve to 780.000 in maximum. Daily wate generation per person is assumed
to be 1,34 kg. considering the waste generation per minute, total amount for 780.000
people will be 1046 ton / day.
Passengers will use the stations maximum 5 minutes.
daypassengerton
daypassengerutesX
uteshourX
hourdayX
dayton
−=−
63,3min5min60
124
11046
This amount is the total amount for all of the stations. For only one station is calculated to
be around 0,21 ton/day.
All of the solid waste from the operation will be collected by private cleansing companies
and will be delivered to IBB solid waste management system in line with the Solid Waste
Control Regulation (14.03.1991 / 20814)
Wastewater Generation During Operation
v http://www.istanbul-ulasim.com.tr/default.asp?menu_id=5&sayfa_id=1
Eurasia Subway Group Joint Venture
Kadıköy-Kartal Subway Completion Construction, Electro Mechanic Systems Supply, Montage and Operation Project
26
The stations will serve to 780.000 people in a day maximum. Daily wastewater amount
per person is assumed to be 60 l. Thus, considering wastewater amount per person – per
minute total amount for 780.000 is calculated to be 46800 m3 /day.
Passengers will use the stations maximum 5 minutes.
daypassengerm
daypassengerutesX
uteshoursX
hoursdayX
daym
−=−
33
5,162min5min60
124
146800
This amount is the total amount for all of the stations. Mean amount for only one station is
around 9,6m3/day. These domestical wastewater will be discharged to the sewage
system.
Noise Pollution During Operation
The main noise source during operation is the operating subway. In subway stations the
maximum noise level is measured to be 85 dBA by IBB in similar lines. The noise level is
planned to be the same in this line. Thus the dispersion of the noise is calculated using
below formula:
2410 rQLogLwLpt π+=
Here:
Lw= Noise level of the machine (Here, equivalent noise level is used)
Q= Reduction factor (assumed to be 1)
r= Distance
Gathered results are given in Table 4.
Table 4: Noise Dispersion During Operation
Distance (m) Noise Level (dBA)
0 85
1 71
2 65
3 61
4 59
5 57
6 55
7 54
Eurasia Subway Group Joint Venture
Kadıköy-Kartal Subway Completion Construction, Electro Mechanic Systems Supply, Montage and Operation Project
27
8 53
9 52
10 51
Figure 5 :Noise Dispersion During Operation
0
10
20
30
40
50
60
70
80
90
0 1 2 3 4 5 6 7 8 9 10
Mesafe (Metre)
Gür
ültü
Düz
eyi (
dBA
)
Gürültü DüzeyiSınır Değer
As it is seen from Figure-2, noise level stays under the limit value in 2 m. This model is
worked for open areas. Thus in closed areas such as stations the distance will be
shortened.
Apparently, in the scope of a study which is executed by IBB for customer satisfaction
noise measurement is realized at one of the buildings near the subway tunnel when the
subway is crossing and the noise level is determined to be 44 dBA. Comparing the limit
values given in the Assessment and Management of Environmental Noise Regulation it is
clear that this values comply with them.
Living rooms (in city) 55 dBA During Day-evening Residential
Areas Serving areas (kitchen) (in-inter
city)
60 dBA During the Activity
Eurasia Subway Group Joint Venture
Kadıköy-Kartal Subway Completion Construction, Electro Mechanic Systems Supply, Montage and Operation Project
28
2. Project Location
a) Existing land use and its quality (agricultural land, forest area,
planned area, water surface etc.)
The area which is allocated for Kadıköy-Kartal Railed Public Transport System project
stays in the boundaries of Kadıköy, Maltepe and Kartal provinces of Istanbul.
City of Istanbul stays between, 280° 01 '-290° 55' east longitudes and 410° 33'.400° 28'
north latitudes. The Bosphorus connects the Marmara and Black Sea and divides the city
in two parts and apart Asia and the Europe. At north Black Sea, at east Kocaeli
Mountains, at south the Sea of Marmara and at west Ergene Basin surrounds the city. At
east and south east Karamürsel, Gebze, Merkez and Kandıra provinces of Kocaeli, at
south Gemlik and Orhangazi provşnces of Bursa, at west and northwest Çorlu Çerkezköy
and Saray provinces of Tekirdağ and Vize province of Kırklareli are the neighbors of
İstanbul. (www.ibb.gov.tr).
At project site, structuring is seen mostly. Üsküdar, Kadıköy, Maltepe regions are
generally residential, Kartal, Pendik, Tuzla regions are generally industrial area. Mainly
the buildings have with 6-7 floors. For the region many plans were prepared with various
scales. These studies are still in progress. City plans of the project site showing the public
works is represented in Annex-4.
In Istanbul generally Mediterranean climates are affective. As it is known, in this climate
the summers are hot and dry and winters are warmish and rainy. Istanbul climate, raises
specific characteristics, effected by Black Sea, Balkans and Anatolian continental
climates. According to the data kept at the Kandilli Observatory, the mean teprature of
Istanbul is 13oC, mean temperature for January is -5oC, for July is 22,7°C. Annual rain fall
is 789 mm. 38% of the total rain falls in winter, 18% in spring, 13% in summer and 31% in
autumn. Anatolian side is somehow warmer than European side. In Florya the hottest
temperature is 27°C, while it is 31°C in Göztepe. Annual temperature mean in Florya is
13,6°C, in Göztepe it is 13,9oC. General seasonal profile of the area is given in Annex-5.
Istanbul Group forms the bottom part of the regional sediment stacking. It generally covers
a passive continental sediments which are formed in between Ordovisiyen-Karbonifer
Eurasia Subway Group Joint Venture
Kadıköy-Kartal Subway Completion Construction, Electro Mechanic Systems Supply, Montage and Operation Project
29
times. It is locally covered by Triyas, top Kretase- low Eosen, Middle Eosen-low Oligosen,
Oligosen – low Miyosen, top Miyosen and Kuvaterner sediments. Older parts generally
slide towards to eastern part of Bosphorus while younger parts generally slide towards to
west.
Istanbul Group is divided into many Iitostratigraphic in formation level.
Geological Cross Cutting of the project site is given in Annex-6 Figure 6: Geological Specifications of Istanbul
Eurasia Subway Group Joint Venture
Kadıköy-Kartal Subway Completion Construction, Electro Mechanic Systems Supply, Montage and Operation Project
30
Earthquake Situation
According to the study that is executed by the General Directorate of Natural the project
site which is covered by Üsküdar – Kadıköy – Maltepe – Kartal – Pendik - Tuzla reagions
designated to cary earthquake risk 1st degree due to its close distance to North Anatolian
Zone. In this area requirement of earthquake regulation is applied.
Figure 7: Earthquake Map of Istanbul
Eurasia Subway Group Joint Venture
Kadıköy-Kartal Subway Completion Construction, Electro Mechanic Systems Supply, Montage and Operation Project
31
2.b) Evaluation of the project site considering the wetlands, sea sides, mountainous districts and forest regions, agricultural areas, national parks, specially protected areas, dense areas in terms of population, historical, cultural, archaeological and similar important areas, erosion districts, landslide districts, forestation fields, potential erosion and forestation fields, with taking into consideration of the list of Sensitive Districts that takes place at Appendix V and aquifers that should be protected in accordance with the Law About Ground Water numbered 167.
The project site does not stay in any of the special areas identified below:
1. The areas that should be protected in accordance with legislation of Turkey
a) ‘National Parks’, ‘Natural Parks’, ‘Nature Monuments’ and ‘Nature Protection
Zones’ which are identified at the article numbered 2 of the Natural Parks Law
numbered 2873.
b) `The Wildlife Protection Areas’ and ‘The Wild Animals Naturalization Areas’
those are determined by Ministry of Forestry in accordance with the Land Hunting
Law numbered 3167,
c) The areas defined as ‘Cultural Heritages’, ‘Natural Heritages’ and ‘Protected
Areas’ at the sub-paragraphs numbered 1, 2, 3 and 5 of ‘a- Definitions’ paragraph
of 2. article of the Law on the Protection of Cultural and Natural Heritage
numbered 2863 and the areas whose ascertainment and registration are
performed in accordance with relevant articles of the same law and of the law
numbered 3386 (The Law on Change of Certain Articles of the Law on the
Protection of Cultural and Natural Heritage numbered 2863)
d) The Areas of Fishery Products Production and Reproduction those are
within the scope of the Fishery Products Law numbered 1380,
e) The areas which are defined at the article numbered 17 of the Regulation of
Check of Water Pollution that has been published at the Official Journal numbered
Eurasia Subway Group Joint Venture
Kadıköy-Kartal Subway Completion Construction, Electro Mechanic Systems Supply, Montage and Operation Project
32
19919 and bear the date of 4/8/1988 and different articles numbered 18, 19 and
20 of the regulation that has been published at the Official Journal numbered
23742 and bear the date of 1/7/1999,
f) The ‘Sensitive Pollution Districts’ those are defined at the article numbered
49 of the Protection of Air Quality Regulation that has been published at the
Official Journal numbered 19269 and bear the date of 2/11/1986,
g) The areas those are ascertained and promulgated as ‘Specially Protected
Environment Areas’ in accordance with the article numbered 9 of the Environment
Law numbered 2872 by the Council of Ministers,
h) The areas those are protected in accordance with the Boğaziçi Law
numbered 2960,
i) The areas promulgated as forest areas in accordance with the Forest Law
numbered 6831,
j) The areas those are restricted districts in accordance with Coast Law
numbered 3621,
k) The areas those are indicated at the Law about Improvement of Growing of
Oils and Inoculation of Wilds numbered 3573,
l) The areas those are stated Pasture Law numbered 4342,
m) The areas those are stated at ‘Regulation of Protection of Wetlands’ which
came into force after published at the Official Journal numbered 24656 and bear
the date of 0/01/2002.
2. The areas that should be protected in accordance with international
agreements those we become a party to
Eurasia Subway Group Joint Venture
Kadıköy-Kartal Subway Completion Construction, Electro Mechanic Systems Supply, Montage and Operation Project
33
a) The I. and II. Protection Areas, ‘The Habitats and Reproduction Areas of
The Mediterranean Seals’ those are stated at ‘Important Reproduction Areas of
Sea Turtles’ which are from the areas those are protected in accordance with ‘The
Agreement of Europe Wildlife and Habitat Protection’ (BERN Agreement) which
came into force after published at the Official Journal numbered 18318 and bear
the date of 20/2/1984.
b) The areas those are protected in accordance with the ‘Agreement of
Protection of Mediterranean Sea Against Pollution’ (Barcelona Agreement) which
came into force after published at the Official Journal numbered 17368 and bear
the date of 12/6/1981,
i) The areas those are determined as ‘Specially Protected Areas’ as required
by ‘Protocol Relating to Protection of Specially Protected Areas at Mediterranean’
which has been published at the Official Journal numbered 19968 and bear the
date of 23/10/1988,
ii) The areas those take place at the list of ‘100 Coastal Historical Protected
Area of Common Significance at Mediterranean’ that has been published by
United Nations Environment Program chosen as required by Genoa Declaration
bear the date of 13/9/1985,
iii) The coastal areas those are habitats and nutrition environment of the ‘Sea
Species, Endemic For Mediterranean, Whose Generation are Under the Risk of
Vanishing’ that takes place at the article numbered 17 of the Genoa Declaration,
c) The cultural, historical and natural areas those are protected as being given
the status of ‘Cultural Heritage’ and ‘Natural Heritage’ by the Ministry of Culture in
accordance with the articles numbered 1 and 2 of the ‘Protection of World Culture
and Natural Heritage Agreement’ which came into force after published at the
Official Journal numbered 17959 bear the date of 14/2/1983,
Eurasia Subway Group Joint Venture
Kadıköy-Kartal Subway Completion Construction, Electro Mechanic Systems Supply, Montage and Operation Project
34
d) The areas those are protected in accordance with the ‘Agreement of
Protection of the Wetlands Those Especially Have International Importance As
Habitats of Waterfowls’ (RAMSAR Agreement) which came into force after
published at the Official Journal numbered 21937 bear the date of 17/05/1994.
3. The areas those should be protected
a) The areas those have been ascertained as restricted districts as the areas
whose present characteristics will be protected at the Environmental Condition
Plans those is approved ( the areas whose natural character will be protected,
biogenetic reserve areas, geothermal areas etc. )
b) Agricultural Areas: The areas of agricultural development, irrigation areas,
the areas that it is possible to irrigate and the areas whose land use ability classes
are I, II, III and IV, the whole areas of I. and II. class and the areas of special crop
plantation where are used in agriculture depends on rain,
c) Wetlands: All of the waters, swamps, rushy those are natural or artificial,
permanent or temporary, whose waters are quiet or streamy, fresh, briny or salt,
those contain depths not exceeding 6 meters during the reflux period of ebb and
flood, those are important as being habitats of living creatures in the first instance
waterfowls, and the areas of well-watered marshy from these areas to black and
dry land as from the trend of the coastline ecologically,
d) Lakes, rivers, the areas of operating underground waters,
e) The areas those are important for scientific researches and/or habitats for
the species that are vanishing or likely to vanish and are endemic for our country,
the areas of biosphere reserves, biotypes, biogenetics reserve areas, the areas of
the geological and geomorphologic formations those have unique characteristics.
Eurasia Subway Group Joint Venture
Kadıköy-Kartal Subway Completion Construction, Electro Mechanic Systems Supply, Montage and Operation Project
35
3. The alternatives of the Project and Its Place (the reasons of why that project technology and that project place are chosen) In recent years, in Istanbul and its surroundings within the scope of the several projects
towards to be metropolitan, projects aiming mitigating effects to environment, reducing
pollutions, and protect the ecological balance carry high importance. Thus, it is targeted to
develop the transportation infrastructure of Istanbul.
Since the project direction forms a part of a whole system no alternatives assessed during
site selection.
Eurasia Subway Group Joint Venture
Kadıköy-Kartal Subway Completion Construction, Electro Mechanic Systems Supply, Montage and Operation Project
36
Results
In metropolitan cities all over the world, generally, efficiency of the railway systems are
measured and monitored considering the percentage of the railway transportation to total
transportation. According to the data of the last couple of years, these rates were; 60% for
Tokyo, 31% for New York, 22% for London, %25 for Paris while it was 3,6% in Istanbul
(Ref.:vi). These numbers clearly shows that, in Istanbul, considering the opportunities that
are supplied to the public in utilization of railways in daily transportation, there is a sharp
work load.
The work flow chart of the Kadıköy-Kartal Soft Railway Transportation system is
represented in Annex-7 of the report. As it is seen in the chart, the project is planned to be
operated in 28 months. This plan is prepared by the Eurasia Metro Group Joint Venture
which is the new contractor of the work.
This project, preliminary granted to Yapı Merkezi· Doğuş - Yüksel - Yenigün inşaat Joint
Venture by İETT (İstanbul Electric Trams and Tunnel Operations General Directorate that
owns the project in those days. The Project Desvription Folder which is prepared by the
mentioned group is approved by Istanbul Provincial Office of the Ministry of Environment
and Forestry (MoEF) on 22 July 2005.
Although there is no differences on the described “Kadıköy-Kartal Subway Completion,
Electro Mechanical Systems Supply, Montage and Operation”, the project description
folder is revised considering the following justifications:
1. The project’s ownership is transferred from İETT to IBB Division of
Transportation, Railway System Directorate.
2. The contractor group is decided to be Eurasia Subway Group Joint Venture by
IBB.
3. Small amendments in the project: In first phase a total of 17 stations was
planned. Yet, during this process the station which was planned to be built on the
ground, as a viaduct is excluded and the plan is revised to include 16 stations, all
underground.
vi http://www.marmaray.com.tr/genel_yolculuk_talepleri.htm
Eurasia Subway Group Joint Venture
Kadıköy-Kartal Subway Completion Construction, Electro Mechanic Systems Supply, Montage and Operation Project
37
There is no difference in technical details of the project, direction, construction
technology, materials and equipments to be used.
The project is tendered to be parallel subway construction totally 21573 length. The
alignment which is 43,447 km tunnel alignment respectively divided as right alignment
21,694 km, left alignment 21,753 km as well as 16 subway station buildings construction 3
layover place and 5 turnout structure.
Tunnel Boring Machines (TBM) will be used during tunneling. These machined are the
group of hydraulic machines which are produced suitable to the ground conditions. TBM
excavates the ground via the special equipments placed in its in front, and in meantime
pushes itself forward.
All of the 16 stations will be underground. One of the stations is will be on the ground as a
viaduct because of the topographical conditions. Deeper excavation will be operated for
this purpose and excavation supporting system will be used. In this system, preliminary
stakes will be placed to the construction area. After that, excavation work will be done
step by step in conventional manner with anchorages in determined altitudes.
The construction will be completed in 30 months
Excavation amount is 950.000 m3 for tunnels, 550.000 m3 for stations and in total it will be
1.500.000 m3. 500.000 m3 of the total excavated materials which is 1.500.000 m3 will be
used as filling material. Thus, only 1.000.000 m3 excavation material will be transported
and disposed.
This project will be constructed underground. Depths between 25 and 50m are belong to
the Treasury and thus there is no ownership document for that. Also, the stations will be
constructed to the points which are generally used by the public. In existing situation in-
city roads are publicized roads and they are belonging to the Treasury. During
construction phase, it is intending to design without nationalization. Yet, if necessary, IBB
will proceed with the necessary steps.
Drinking water of construction will be supplied with demijohns.
During tunnel construction 1 m3/day water will be used to prevent dust.
Eurasia Subway Group Joint Venture
Kadıköy-Kartal Subway Completion Construction, Electro Mechanic Systems Supply, Montage and Operation Project
38
All of the waste will be disposed in line with the Solid Waste Control Regulation (14 March
1991 / 20814). They will be collected in containers and delivered to the Municipal waste
disposal system.
Waste water occurred at the project will be disposed via the sewage system.
During excavations there will be four main dust source.
e) During excavations
f) During loading of the excavation material
g) During transportation
h) During unloading of the excavation material
There will be dust generation during tunnel excavation. Yet, these, will stay underground.
But, dust generation from transportation and unloading to the disposal area is calculated
to be 1 kg/hours. This stays under the limit value determined by the Industrial Sourced Air
Pollution Control Regulation
During the excavations the noise will be underground and it is not possible that the people
living around will be effected from the noise and vibration.
Yet, during open station excavations noise will be occurred. According to the calculations
expected level of noise will ensure the limit values of Assessment and Management of
Environmental Noise in 300 m. Below measures will be undertaken in order to mitigate
noise level.
Eurasia Subway Group J.V. undertakes and confirms that it will comply with the Labour
Law (4857) and other related Regulations during both the construction and operation.
Thus, occupational health and safety procedures have been prepared.
The Project site and its surroundings does not stay in any of the special areas
identified in the Annex-5 of the Environmental Impact Assessment Regulation of 16 December 2003 / 25318.
Since the project direction forms a part of a whole system no alternatives assessed during
site selection.
Eurasia Subway Group Joint Venture
Kadıköy-Kartal Subway Completion Construction, Electro Mechanic Systems Supply, Montage and Operation Project
39
Eurasia Subway Group J.V. undertakes that it will act in compliance with the
following regulations in both construction and operation phases for this project:
• Control of Solid Waste (OJ Date: 14.3.1991 ; nr: 20814)
• Control of Medical Waste (OJ Date: 20.5.1993 ; nr: 21586)
• Environmental Inspection (OJ Date: 5.1.2002 ; nr: 24631)
• Environmental Impact Assessment (OJ Date: 16.12.2003 ; nr: 25318)
• Excavation Soil and Construction Waste (OJ Date: 18.3.2004 ; nr: 25406)
• Control of Vegetable Waste Oil (OJ Date: 19.4.2005 ; nr: 25791)
• Controlling Packaging and Packaging Waste (OJ Date: 30.7.2004 ; nr: 25538)
• Control of Used Batteries and Accumulators (OJ Date: 31.8.2004 ; nr: 25569)
• Control of Water Pollution (OJ Date: 31.12.2004 ; nr: 25687)
• Control of Air Pollution Resulting From Heating Activities (OJ Date: 13.1.2005 ;nr:
25699)
• Control of Soil Pollution (OJ Date: 31.5.2005 ; nr: 25831)
• Management and Assessment of Environmental Noise (OJ Date: 1.7.2005 ; nr:
25862)
• Water Products (OJ Date: 10.03.1995 ; nr: 22223)
• Control of Waste Oil (OJ Date: 21.01.2004 ; nr: 25353)
Considering the facts represented in this report, it is decided that the environmental
impacts of the project will not be significant if only Eurasia Subway Group J.V. complies to
its undertakings mentioned in this report.
Eurasia Subway Group Joint Venture
Kadıköy-Kartal Subway Completion Construction, Electro Mechanic Systems Supply, Montage and Operation Project
40
Annexes: Annex-1 Flow Chart
Annex-2 Direction and cross cuttings of the line
Annex-3 Areas which are allowed to receive excavation wastes
Annex-4 City Plans
Annex-5 Seasonal Specifications
Annex-6 General Geological Specifications
Eurasia Subway Group Joint Venture
Kadıköy-Kartal Subway Completion Construction, Electro Mechanic Systems Supply, Montage and Operation Project
41
References: /1/ The Ministry of Environment and Forestry Official Web Site www.cevreorman.gov.tr
/2/ ISTANBUL SUBWAY AND LIGHT RAILWAY TRASNPORTATIN SYSTEM OTOGAR-
BAĞCILAR HRS CONSTRUCTION AND ELECTRO-MECHANIC PROJECT Economic
and financial feasibility report,
/3/ Dust Constant İ.T.Ü. Air Pollution and control Symposium 15-16 March 1993.
/4/ Doç. Dr. Nevzat ÖZGÜVEN, Industrial Noise Control, The Chamber of Mechanical Engineers Publication
Eurasia Subway Group Joint Venture
Kadıköy-Kartal Subway Completion Construction, Electro Mechanic Systems Supply, Montage and Operation Project
42
The Group That prepared The Project Identification File
Name Surname Emir Salman
Occupation Environmental Engineer
Cv Attached
Signature
Name Surname Gülşah Kazanç
Occupation Chemist
Cv Attached
Signature
Name Surname Engin Salman
Occupation Civil Engineer
Cv Attached
Signature
Eurasia Subway Group Joint Venture
Kadıköy-Kartal Subway Completion Construction, Electro Mechanic Systems Supply, Montage and Operation Project
43
1 İş Planı 2 Hattın Güzergâhı ve Kesiti 3 Döküm İzinli Sahalar 4 İmar Planları 5 Mevsimsel Özellikler 6 Geological Cross Cuttings 7 İş Planı