table of contents · 2013-12-27 · i table of contents page executive summary ..... 1 introduction...

75

Upload: others

Post on 04-Apr-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1
Page 2: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1

i

TABLE OF CONTENTS

Page

EXECUTIVE SUMMARY ...................................................................................................... 1

Introduction ................................................................................................................................ 1

Environmental Monitoring and Audit Works ............................................................................ 1

Environmental Licenses and Permits ......................................................................................... 1

Key Information in the Reporting Month ................................................................................... 2

Future Key Issues ....................................................................................................................... 3

1 INTRODUCTION ............................................................................................................ 4

Background ................................................................................................................................ 4

Construction Programme ............................................................................................................ 6

Summary of EM&A Requirements ............................................................................................ 6

2 AIR QUALITY MONITORING .................................................................................... 8

Monitoring Requirements ........................................................................................................... 8

Monitoring Locations ................................................................................................................. 8

Monitoring Equipment ............................................................................................................... 8

Monitoring Parameters, Frequency and Duration ...................................................................... 8

Monitoring Methodology and QA/QC Procedure ...................................................................... 9

Results and Observations ......................................................................................................... 10

3 NOISE MONITORING ................................................................................................. 12

Monitoring Requirements ......................................................................................................... 12

Monitoring Locations ............................................................................................................... 12

Monitoring Equipment ............................................................................................................. 12

Monitoring Parameters, Frequency and Duration .................................................................... 12

Monitoring Methodology and QA/QC Procedures .................................................................. 13

Results and Observations ......................................................................................................... 14

4 ENVIRONMENTAL AUDIT ........................................................................................ 15

Site Audits ................................................................................................................................ 15

Review of Environmental Monitoring Procedures ................................................................... 15

Status of Environmental Licensing and Permitting .................................................................. 15

Status of Waste Management ................................................................................................... 16

Implementation Status of Environmental Mitigation Measures ............................................... 16

Summary of Exceedances ........................................................................................................ 17

Implementation Status of Event Action Plans .......................................................................... 17

Summary of Complaint and Prosecution .................................................................................. 17

5 FUTURE KEY ISSUES ................................................................................................. 18

Monitoring Schedule for the Next Month ................................................................................ 18

Construction Program for the Next Month ............................................................................... 18

6 CONCLUSIONS AND RECOMMENDATIONS ....................................................... 18

Conclusions .............................................................................................................................. 19

Recommendations .................................................................................................................... 19

Page 3: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1

ii

LIST OF TABLES

Table I Summary Table for Events Recorded in the Reporting Month

Table II Summary Table for Key Information in the Reporting Month

Table 1.1 Key Project Contacts

Table 2.1 Locations for Air Quality Monitoring

Table 2.2 Air Quality Monitoring Equipment

Table 2.3 Impact Dust Monitoring Parameters, Frequency and Duration

Table 2.4 Summary Table of Air Quality Monitoring Results during the reporting month

Table 3.1 Location of Noise Monitoring Station

Table 3.2 Noise Monitoring Equipment

Table 3.3 Noise Monitoring Parameters, Frequency and Duration

Table 3.4 Summary Table of Noise Monitoring Results during the Reporting Month

Table 4.1 Summary of Environmental Licensing and Permit Status

Table 4.2 Observations and Recommendations of Site Audit

LIST OF FIGURE

Figure 1.1 Site Layout Plan

Figure 1.2 Locations of Air Quality and Noise Monitoring Stations

LIST OF APPENDICES

Appendix A Action and Limit Levels

Appendix B Copies of Calibration Certificates

Appendix C Environmental Monitoring Schedules

Appendix D 1-hour TSP Monitoring Results and Graphical Presentations

Appendix E 24-hour TSP Monitoring Results and Graphical Presentations

Appendix F Noise Monitoring Results and Graphical Presentations

Appendix G Summary of Exceedance

Appendix H Site Audit Summary

Appendix I Event Action Plans

Appendix J Updated Environmental Mitigation Implementation Schedule

Appendix K Waste Generation in the Reporting Month

Appendix L Complaint Log

Appendix M Construction Programme

Page 4: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1

Jardine Engineering Corporation Ltd. Contract No. DE/2009/09

Supply and Installation of Electrical and Mechanical Equipment

for Tai Po Sewage Treatment Works Stage 5 Phase 2B

Monthly EM&A Report – September 2013

MA10069\1309\1309_E&M_kl131021_v1 Cinotech 1

EXECUTIVE SUMMARY

Introduction

1. This is the 27th

monthly Environmental Monitoring and Audit (EM&A) Report

prepared by Cinotech Consultants Limited for DSD Contract no. DE/2009/09 “Supply

and Installation of Electrical and Mechanical Equipment for Tai Po Sewage Treatment

Works Stage 5 Phase 2B”. This report documents the findings of EM&A Works

conducted in September 2013.

2. The major site activities undertaken in the reporting month included:

E&M installation of FC No.8B and 10B; Installation of E&M equipment in Aeration Tank No. 5, 6 & 7; RAS pipework installation at Pipe Gallery for new Aeration Tanks No.5 to 7; E&M installation of Primary Sedimentation Tank No. 5; Pipework installation at Pipe Gallery for new PST No.5; E&M installation of new Air Blower No.5; Electrical load diversion work for replacement of existing MCC5 at Stage IV PST

Pipe Gallery; Demolition of existing cooling water system at CBC; Installation of new E&M equipment at Filtrate Treatment Plant (SBR); Fabrication of bio-gas holder on site; E&M installation for new Sludge Digestion Tank No.3; BS & FS installation in new Gas Transfer Station; and BS & FS installation in new Chemical and Oil Store

Environmental Monitoring and Audit Works

3. Environmental monitoring and audit works for the Project were performed regularly as

stipulated in the Final EM&A Manual and the results were checked and reviewed. The

implementation of the environmental mitigation measures, Event Action Plans and

environmental complaint handling procedures were also checked.

4. Summary of the events and action taken in the reporting month is tabulated in Table I.

Table I Summary Table for Events Recorded in the Reporting Month

Parameter No. of Exceedance No. of Events

Due to this Project Action Taken

Action Level Limit Level

1-hr TSP 0 0 0 N/A

24-hr TSP 0 0 0 N/A

Noise 0 0 0 N/A

Environmental Licenses and Permits

5. Environmental related licenses/permits granted to the Project include the Environmental

Permit (EP) for the Project.

Page 5: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1

Jardine Engineering Corporation Ltd. Contract No. DE/2009/09

Supply and Installation of Electrical and Mechanical Equipment

for Tai Po Sewage Treatment Works Stage 5 Phase 2B

Monthly EM&A Report – September 2013

MA10069\1309\1309_E&M_kl131021_v1 Cinotech 2

Key Information in the Reporting Month

6. Summary of key information in this reporting month is tabulated in Table II.

Table II Summary Table for Key Information in the Reporting Month

Event Event Details

Action Taken Status Remark Number Nature

Complaint received 0 --- N/A N/A ---

Changes to the

assumptions and key

construction / operation

activities recorded

0 --- N/A N/A ---

Status of submissions

under EP 1

Monthly EM&A

Report

(August 2013)

Submitted to EPD on

30th September 2013

(EP condition 6.6)

N/A

---

---

Notifications of any

summons &

prosecutions

0 --- N/A N/A ---

Page 6: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1

Jardine Engineering Corporation Ltd. Contract No. DE/2009/09

Supply and Installation of Electrical and Mechanical Equipment

for Tai Po Sewage Treatment Works Stage 5 Phase 2B

Monthly EM&A Report – September 2013

MA10069\1309\1309_E&M_kl131021_v1 Cinotech 3

Future Key Issues

7. Major site activities for the coming two months will include:

E&M installation of FC No.8B and 10B; Installation of E&M equipment in Aeration Tank No. 5, 6 & 7; RAS pipework installation at Pipe Gallery for new Aeration Tanks No.5 to 7; E&M installation of Primary Sedimentation Tank No. 5; Pipework installation at Pipe Gallery for new PST No.5; E&M installation of new Air Blower No.5; Installation of MCC5 at Stage IV PST Pipe Galley; Demolition of existing cooling water system at CBC; Installation of mechanical screen and shaftless conveyor at Stage IV Screening

House; Fabrication of bio-gas holder on site; Installation of new E&M equipment at Filtrate Treatment Plant (SBR); Installation of new screw pumps (for Stage IV Inlet Works); E&M installation for new Sludge Digestion Tank No.3; Installation of MCC at CBC G/F Switchroom; and Installation of MCC1 at CBC 1/F Switchroom.

8. The future environmental concerns are air quality, noise impacts and waste

management from construction works.

Page 7: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1

Jardine Engineering Corporation Ltd. Contract No. DE/2009/09

Supply and Installation of Electrical and Mechanical Equipment

for Tai Po Sewage Treatment Works Stage 5 Phase 2B

Monthly EM&A Report – September 2013

MA10069\1309\1309_E&M_kl131021_v1 Cinotech 4

1 INTRODUCTION

Background

1.1 Tai Po Sewage Treatment Works (TPSTW) is located within the Tai Po Industrial

Estate. It currently comprises four Stages: I, II, IVA and IVB works. The TPSTW -

Stage V aims to upgrade the existing STW to provide additional sewage treatment

capacity from the present design flow of 88,000 m3/day to 130,000 m

3/day to meet the

demands of both the existing and future developments, and to meet the revised

discharge license requirements.

1.2 The TPSTW Stage V, Phase I and Phase II are Designated Projects under the

Environmental Impact Assessment Ordinance (Cap. 449) with the same EIAO Register

No. AEIAR – 081/2004. A study of environmental impact assessment (EIA) was

undertaken to evaluate various environmental impacts associated with the works within

these two Designed Projects. An EIA Report as well as an Environmental Monitoring

and Audit (EM&A) Manual were approved by the Environmental Protection

Department (EPD) on 28 October 2004.

1.3 The Stage V works will be implemented in 2 phases. The design capacities of Phase I

and Phase II works are 100,000 m3/d and 130,000 m

3/d respectively. An Environmental

Permit (EP) No. EP-265/2007 was issued on 22 March 2007 for the TPSTW Stage V

Phase II to the Drainage Services Department (DSD) as the Permit Holder. The project

“Tai Po Sewage Treatment Works – Stage V Phase IIB” formed part of the Phase II

works, includes additional secondary treatment process units ( 1 primary clarifier; 3

bioreactors and 2 final clarifiers) in TPSTW for its future extended plant design capacity

of 120,000 m3/day. A master construction programme of the Project is provided in

Appendix M. A site layout plan is provided in Figure 1.1. The construction activities

of the Project commenced on 16 May 2011.

1.4 Cinotech Consultants Ltd. was commissioned by the Contractor as the Environmental

Team (ET) to undertake the EM&A works for the Project. Dr. Priscilla CHOY of

Cinotech Consultants Ltd. was appointed as the ET Leader as per the Condition 2.1 of

the EP. Ove Arup and Partners Hong Kong Limited was appointed as the IEC under

Condition 2.2 of the EP. This is the 27th

monthly EM&A report summarizing the

EM&A works for the Project in September 2013.

Page 8: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1

Jardine Engineering Corporation Ltd. Contract No. DE/2009/09

Supply and Installation of Electrical and Mechanical Equipment

for Tai Po Sewage Treatment Works Stage 5 Phase 2B

Monthly EM&A Report – September 2013

MA10069\1309\1309_E&M_kl131021_v1 Cinotech 5

Project Organizations

1.5 Different parties with different levels of involvement in the project organization include:

Project Proponent / Engineer’s Representative (ER) – Drainage Services Department

Environmental Team (ET) – Cinotech Consultants Ltd.

Independent Environmental Checker (IEC) – Ove Arup and Partners Hong Kong

Limited

Contractor – Jardine Engineering Corporation Ltd.

1.6 The responsibilities of respective parties are detailed in Section 1.10 of the Final EM&A

Manual of the Project.

1.7 The Project Organization during Construction Phase

1.8 The key contacts of the Project are shown in Table 1.1.

Table 1.1 Key Project Contacts

Party Role Name Position Phone No. Fax No.

DSD E&M Branch Mr. TONG Sau Kit Senior Engineer 2594 7304

2827 8532 Mr. TSE Ho Engineer 2660 7638

Cinotech Environmental

Team

Dr. Priscilla CHOY ET Leader 2151 2089

3107 1388 Mr. Kevin LAM Project Coordinator and

Audit Team Leader 2151 2099

Mr. Henry LEUNG Monitoring Team Leader 2151 2087

Arup

Independent

Environmental

Checker

Mr. Coleman NG Independent

Environmental Checker 2268 3097

2865 6493

Mr. Ken LEE Assistant to Independent

Environmental Checker 2268 3573

JEC E&M

Contractor

Mr. Alex LAW Project Manager 9312 8659

2887 9090 Mr. Kent MAK Site Agent 6391 2499

Mr. Brendan CHAN Environmental Officer 6892 0956

Page 9: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1

Jardine Engineering Corporation Ltd. Contract No. DE/2009/09

Supply and Installation of Electrical and Mechanical Equipment

for Tai Po Sewage Treatment Works Stage 5 Phase 2B

Monthly EM&A Report – September 2013

MA10069\1309\1309_E&M_kl131021_v1 Cinotech 6

Construction Programme

1.9 The site activities undertaken in the reporting month were:

E&M installation of FC No.8B and 10B; Installation of E&M equipment in Aeration Tank No. 5, 6 & 7; RAS pipework installation at Pipe Gallery for new Aeration Tanks No.5 to 7; E&M installation of Primary Sedimentation Tank No. 5; Pipework installation at Pipe Gallery for new PST No.5; E&M installation of new Air Blower No.5; Electrical load diversion work for replacement of existing MCC5 at Stage IV PST

Pipe Gallery; Demolition of existing cooling water system at CBC; Installation of new E&M equipment at Filtrate Treatment Plant (SBR); Fabrication of bio-gas holder on site; E&M installation for new Sludge Digestion Tank No.3; BS & FS installation in new Gas Transfer Station; and BS & FS installation in new Chemical and Oil Store

Page 10: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1

Jardine Engineering Corporation Ltd. Contract No. DE/2009/09

Supply and Installation of Electrical and Mechanical Equipment

for Tai Po Sewage Treatment Works Stage 5 Phase 2B

Monthly EM&A Report – September 2013

MA10069\1309\1309_E&M_kl131021_v1 Cinotech 7

Summary of EM&A Requirements

1.10 The EM&A programme requires construction phase air quality and noise monitoring as

well as environmental site audits. The EM&A requirements are described in the

following sections, including:

All monitoring parameters;

Action and Limit levels for all environmental parameters;

Event / Action Plans;

Environmental mitigation measures, as recommended in the project EIA study final

report; and

Environmental requirements in contract documents.

1.11 The advice on the implementation status of environmental protection and pollution

control/mitigation measures is summarized in Section 6 of this report.

1.12 This report presents the monitoring results, observations, locations, equipment, period,

methodology and QA/QC procedures of the required monitoring parameters, namely air

quality and noise as well as audit works for the Project in the reporting month.

Page 11: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1

Jardine Engineering Corporation Ltd. Contract No. DE/2009/09

Supply and Installation of Electrical and Mechanical Equipment

for Tai Po Sewage Treatment Works Stage 5 Phase 2B

Monthly EM&A Report – September 2013

MA10069\1309\1309_E&M_kl131021_v1 Cinotech 8

2 AIR QUALITY MONITORING

Monitoring Requirements

2.1 Monitoring of 1-hour and 24-hour Total Suspended Particulates (TSP) was conducted to

monitor the air quality during construction phase. Appendix A shows the established

Action/Limit Levels for the environmental monitoring works.

2.2 In accordance with Section 2.30 of the EM&A Manual, a baseline checking of ambient

TSP levels shall be carried out every six months at each monitoring station, when no

dusty works activities are in operation. The number and location of monitoring stations

and parameters shall be reviewed by ET Leader every three months according to section

8.8 of EM&A Manual.

Monitoring Locations

2.3 Impact air quality monitoring was conducted at the 3 monitoring stations, as shown in

Figure 1.2. Table 2.1 describes the locations of the air quality monitoring stations.

Table 2.1 Locations for Air Quality Monitoring

Monitoring Stations Description Location of Measurement

CAM1 Government Staff Quarters Rooftop

CAM2 Hung Hing Printing Centre On the site boundary just next to the

Hung Hing Printing Centre

CAM3 Talcon Industrial Ltd. On the site boundary just next to

Talcon Industrial Ltd.

Monitoring Equipment

2.4 Table 2.2 summarizes the equipment used for the air quality monitoring.

Table 2.2 Air Quality Monitoring Equipment

Equipment Model and Make Qty.

HVS

Graseby GMW 2310 HVS, Model GS-2310105-1,

Serial no. 10239 and 0810 2

Tisch Environmental, Inc.; Model no. TE-5170,

Serial no. 1704 1

Calibrator Thermo Andersen.; Model no. G25A

Serial no. 1536 1

Monitoring Parameters, Frequency and Duration

2.5 Table 2.3 summarizes the monitoring parameters and frequencies of impact dust

monitoring for the whole construction period.

Page 12: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1

Jardine Engineering Corporation Ltd. Contract No. DE/2009/09

Supply and Installation of Electrical and Mechanical Equipment

for Tai Po Sewage Treatment Works Stage 5 Phase 2B

Monthly EM&A Report – September 2013

MA10069\1309\1309_E&M_kl131021_v1 Cinotech 9

Table 2.3 Impact Dust Monitoring Parameters, Frequency and Duration

Monitoring Stations Parameter Duration Period Frequency

CAM1, CAM2 and

CAM3

1-hour TSP 1 hour During daytime period 3 times / 6-day

24-hour TSP 24 hours 24 hours Once / 6-day

Monitoring Methodology and QA/QC Procedure

Instrumentation

2.6 High Volume Samplers (HVS) connected with appropriate sampling inlets were

employed for air quality monitoring. Each sampler was composed of a motor, a filter

holder, a flow controller and a sampling inlet and its performance specification complies

with that required by USEPA Standard Title 40, Code of Federation Regulations

Chapter 1 (Part 50).

HVS Installation

2.7 The following guidelines were adopted during the installation of HVS:

Sufficient support was provided to secure the samplers against gusty wind.

No two samplers were placed less than 2 meters apart.

The distance between the sampler and an obstacle, such as buildings, was at least

twice the height that the obstacle protrudes above the sampler.

A minimum of 2 meters of separation from walls, parapets and penthouses was

required for rooftop samples.

A minimum of 2 meters separation from any supporting structure, measured

horizontally was required.

No furnaces or incineration flues were nearby.

Airflow around the sampler was unrestricted.

The samplers were more than 20 meters from the drip line.

Any wire fence and gate, to protect the sampler, should not cause any obstruction

during monitoring.

Filters Preparation

2.8 Fiberglass filters were used which have a collection efficiency of larger than 99% for

particles of 0.3 μm diameter. A HOKLAS accredited laboratory, Wellab Ltd., was

responsible for the preparation of pre-weighed filter papers for Cinotech’s monitoring

team.

2.9 All filters, which were prepared by Wellab Ltd., were equilibrated in the conditioning

environment for 24 hours before weighing. The conditioning environment temperature

was around 25 °C and not variable by more than ±3 °C; the relative humidity (RH) was

< 50% and not variable by more than ±5%. A convenient working RH was 40%.

2.10 Wellab Ltd. has a comprehensive quality assurance and quality control programmes.

Page 13: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1

Jardine Engineering Corporation Ltd. Contract No. DE/2009/09

Supply and Installation of Electrical and Mechanical Equipment

for Tai Po Sewage Treatment Works Stage 5 Phase 2B

Monthly EM&A Report – September 2013

MA10069\1309\1309_E&M_kl131021_v1 Cinotech 10

Operating/Analytical Procedures

2.11 Operating/analytical procedures for the TSP monitoring were highlighted as follows:

Prior to the commencement of the dust sampling, the flow rate of the HVS was

properly set (between 1.1 and 1.4 m3/min.) in accordance with the manufacturer's

instruction to within the range recommended in USEPA Standard.

The power supply was checked to ensure the sampler worked properly.

On sampling, the sampler was operated for 5 minutes to establish thermal

equilibrium before placing any filter media at the air quality monitoring station.

The filter holding frame was then removed by loosening the four nuts and carefully a

weighted and conditioned filter was centered with the stamped number upwards, on a

supporting screen.

The filter was aligned on the screen so that the gasket formed an airtight seal on the

outer edges of the filter. Then the filter holding frame was tightened to the filter

holder with swing bolts to avoid air leakage at the edges.

The shelter lid was closed and secured with the aluminum strip.

The timer was then programmed. Information was recorded on the record sheet,

which included the starting time, the weather condition and the filter number (the

initial weight of the filter paper can be found out by using the filter number).

The flow rate of the HVS sampler would be verified to be constant and recorded on

the data sheet after sampling.

After sampling, the filter was removed and sent to the Wellab Ltd. for weighing. The

elapsed time was also recorded.

Before weighing, all filters were equilibrated in a conditioning environment for 24

hours. The conditioning environment should be between 25°C and 30°C and not vary

by more than ±3°C; the relative humidity (RH) should be < 50% and not vary by

more than ±5%. A convenient working RH is 40%. Weighing results were returned

to Cinotech for further analysis of TSP concentrations collected by each filter.

Maintenance/Calibration

2.12 The following maintenance/calibration was required for the HVS:

The high volume motors and their accessories were properly maintained. Appropriate

maintenance such as routine motor brushes replacement and electrical wiring

checking were made to ensure that the equipment and necessary power supply are in

good working condition.

Calibration of the HVS (five point calibration) using Calibration Kit was carried out

every two months. Copies of calibration certificates are attached in Appendix B.

The HVS calibration orifice will be calibrated annually.

Results and Observations

2.13 In the reporting month, 1-hr TSP monitoring was carried out as schedule at each

designated monitoring station on 13 occasions. 24-hr TSP monitoring was carried out

as scheduled at each designated monitoring station on 5 occasions. The monitoring

schedule was updated and is shown in Appendix C. The weather during the monitoring

sessions was mainly sunny and fine.

Page 14: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1

Jardine Engineering Corporation Ltd. Contract No. DE/2009/09

Supply and Installation of Electrical and Mechanical Equipment

for Tai Po Sewage Treatment Works Stage 5 Phase 2B

Monthly EM&A Report – September 2013

MA10069\1309\1309_E&M_kl131021_v1 Cinotech 11

2.14 All measured 1-hr and 24-hr TSP levels were below the Action/Limit Levels. No

exceedance was recorded in the reporting month.

2.15 The monitoring data and graphical presentations of 1-hour and 24-hour TSP monitoring

results are shown in Appendices D and E, respectively.

Table 2.4 Summary Table of Air Quality Monitoring Results during the

reporting month

Paramete

r

Minimum

µg/m3

Maximum

µg/m3

Average

µg/m3

Action Level,

µg/m3

Limit Level,

µg/m3

1-hr TSP

(CAM1) 55 204 108 315 500

24-hr TSP

(CAM1) 31 103 60 171 260

1-hr TSP

(CAM2) 74 236 133 336 500

24-hr TSP

(CAM2) 42 110 69 177 260

1-hr TSP

(CAM3) 91 244 140 344 500

24-hr TSP

(CAM3) 51 122 77 192 260

2.16 According to our field observations, the major dust source identified at the designated

air quality monitoring stations are as follows:

Station Major Pollution Source CAM1 – Government Staff Quarters Road Traffic Dust

CAM2 – Hung Hing Printing Centre Road Traffic Dust and Excavation

CAM3 – Talcon Industrial Ltd. Road Traffic Dust and Excavation

Page 15: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1

Jardine Engineering Corporation Ltd. Contract No. DE/2009/09

Supply and Installation of Electrical and Mechanical Equipment

for Tai Po Sewage Treatment Works Stage 5 Phase 2B

Monthly EM&A Report – September 2013

MA10069\1309\1309_E&M_kl131021_v1 Cinotech 12

3 NOISE MONITORING

Monitoring Requirements

3.1 Noise monitoring was conducted in accordance with the EM&A Manual. Appendix A

shows the established Action and Limit Levels for the environmental monitoring works.

3.2 The number and location of monitoring stations and parameters shall be reviewed by ET

Leader every three months according to section 8.8 of EM&A Manual.

Monitoring Locations

3.3 Noise monitoring was conducted at one designated monitoring station as presented in

Table 3.1. Figure 1.2 shows the locations of the monitoring station.

Table 3.1 Location of Noise Monitoring Station

Monitoring Station Description Location of Measurement

NM1 Government Staff Quarters The corridor at the first floor.

Monitoring Equipment

3.4 Table 3.2 summarizes the noise monitoring equipment model being used.

Table 3.2 Noise Monitoring Equipment

Equipment Model and Make Quantity

Integrating Sound Level Meter SVANTEK - SVAN 955 1

Calibrator SVANTEK – SV30A 1

Wind Speed Anemometer Vane Anemometer, Model AZ8904

(Serial no. 974835) 1

Monitoring Parameters, Frequency and Duration

3.5 Table 3.3 summarizes the monitoring parameters, frequency and total duration of

monitoring.

Table 3.3 Noise Monitoring Parameters, Frequency and Duration

Station Parameter Period Frequency

NM1

Leq(30 min.)

(L10 and L90 were also recorded as

supplementary information)

0700-1900 hrs. on

normal weekdays Once a week

3.6 If construction works are extended to include works during the hours of 1900 - 0700,

additional weekly impact monitoring would be carried out during evening and night-

time works. Applicable permits under NCO have been obtained by the Contractor. The

details of the Construction Noise Permit can be referred to Table 5.1.

Page 16: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1

Jardine Engineering Corporation Ltd. Contract No. DE/2009/09

Supply and Installation of Electrical and Mechanical Equipment

for Tai Po Sewage Treatment Works Stage 5 Phase 2B

Monthly EM&A Report – September 2013

MA10069\1309\1309_E&M_kl131021_v1 Cinotech 13

Monitoring Methodology and QA/QC Procedures

Field Monitoring

3.7 The monitoring procedures are as follows:

The microphone head of the sound level meter was positioned 1m exterior of the

noise sensitive facade and lowered sufficiently so that the building’s external wall acts as a reflecting surface.

The battery condition was checked to ensure good functioning of the meter.

Parameters such as frequency weighting, the time weighting and the measurement

time were set as follows:

- frequency weighting : A

- time weighting : Fast

- measurement time : 30 minutes

Prior to and after noise measurement, the meter was calibrated using the calibrator

for 94.0 dB at 1000 Hz. If the difference in the calibration level before and after

measurement is more than 1.0 dB, the measurement was considered invalid and

repeat of noise measurement was required after re-calibration or repair of the

equipment.

The wind speed at the monitoring station was checked with the portable wind meter.

Noise monitoring was cancelled in the presence of fog, rain, and wind with a steady

speed exceeding 5 m/s, or wind with gusts exceeding 10 m/s.

Noise measurement was paused during periods of high intrusive noise if possible and

observation was recorded when intrusive noise was not avoided.

At the end of the monitoring period, the Leq, L10 and L90 were recorded. In addition,

site conditions and noise sources were recorded on a standard record sheet.

Maintenance and Calibration

3.8 Maintenance and Calibration procedures were as follows:

The microphone head of the sound level meter and calibrator were cleaned with a

soft cloth at quarterly intervals.

The sound level meter and calibrator were checked and calibrated at yearly intervals.

Copies of calibration certificates are attached in Appendix B.

Page 17: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1

Jardine Engineering Corporation Ltd. Contract No. DE/2009/09

Supply and Installation of Electrical and Mechanical Equipment

for Tai Po Sewage Treatment Works Stage 5 Phase 2B

Monthly EM&A Report – September 2013

MA10069\1309\1309_E&M_kl131021_v1 Cinotech 14

Results and Observations

3.9 In the reporting month, noise monitoring during non-restricted hours was conducted as

scheduled at the designated location on 5 occasions. As advised by the Contractor, no

construction activities will be undertaken during restricted hours as such noise

monitoring during restricted hours was omitted. The noise monitoring schedule is

provided in Appendix C.

3.10 The details of the monitoring results and graphical presentations are shown in

Appendix F. The weather during the monitoring sessions was mainly sunny and fine.

3.11 No Action/Limit Level exceedance for construction noise monitoring was recorded in

the reporting month.

Table 3.4 Summary Table of Noise Monitoring Results during the Reporting Month

Parameter

Minimum

Leq(30min)

dB(A)

Maximum

Leq(30min)

dB(A)

Average

Leq(30min) dB

(A)

Action Level Limit Level

NM1 54.9 61.1 59.4

When one

documented

complaint is

received

75dB(A)

3.12 According to our field observations, the major noise source identified at the designated

air quality monitoring stations are as follows:

Station Major Noise Source

NM1 – Government Staff Quarters Road Traffic

Construction of Main Site

Page 18: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1

Jardine Engineering Corporation Ltd. Contract No. DE/2009/09

Supply and Installation of Electrical and Mechanical Equipment

for Tai Po Sewage Treatment Works Stage 5 Phase 2B

Monthly EM&A Report – September 2013

MA10069\1309\1309_E&M_kl131021_v1 Cinotech 15

4 ENVIRONMENTAL AUDIT

Site Audits

4.1 Site audits were carried out by ET on weekly basis to monitor the timely

implementation of proper environmental management practices and mitigation measures

in the Project site. The summaries of site audits are attached in Appendix H.

4.2 Site audits were conducted on 5th

, 13th

, 18th

and 24th

September 2013 by ET. A joint site

audit with the representative with ER, IEC, the Contractor and the ET was carried out

on 13th

September 2013. No site inspection was conducted by EPD during the reporting

month. The details of observations during site audit can refer to Table 4.2.

Review of Environmental Monitoring Procedures

4.3 The monitoring works conducted by the monitoring team were inspected regularly. The

following observations have been recorded for the monitoring works:

Air Quality Monitoring

The monitoring team recorded all observations around the monitoring stations within

and outside the construction site.

The monitoring team recorded the temperature and weather conditions on the

monitoring days.

Noise Monitoring

The monitoring team recorded all observations around the monitoring stations, which

might affect the monitoring result.

Major noise sources were identified and recorded. Other intrusive noise attributing

to the result was trimmed off by pausing the monitoring temporarily.

Status of Environmental Licensing and Permitting

4.4 All permits/licenses obtained for the Project are summarized in Table 4.1.

Page 19: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1

Jardine Engineering Corporation Ltd. Contract No. DE/2009/09

Supply and Installation of Electrical and Mechanical Equipment

for Tai Po Sewage Treatment Works Stage 5 Phase 2B

Monthly EM&A Report – September 2013

MA10069\1309\1309_E&M_kl131021_v1 Cinotech 16

Table 4.1 Summary of Environmental Licensing and Permit Status

Permit / License No. Valid Period

Details Status From To

Environmental Permit (EP)

EP-265/2007

22/3/2007

N/A

Expansion and upgrading of existing

Tai Po Sewage Treatment Works from

100,000 m3/day to 130,000 m

3/day:

(a) additional secondary treatment

process units(1 primary clarified; 3

bioreactors and 2 final clarifiers);

(b) reconstruction of 4 existing final

clarified;

(c) provision of ultraviolet disinfection

facilities;

(d) additional sludge treatment

facilities; and

(e) ancillary works to existing

treatment facilities.

Valid

Registration of Chemical Waste Producer

5517-727-T3270-01 -- N/A Major chemical waste types:

Spent lubricating oil, spend hydraulic

oil, spend cooling oil, surplus paint,

spent alkaline electrolyte, spent battery

and battery parts containing heavy

metals, scrap battery cell containing

heavy metals, Nickel and its

compounds, spent flammable liquid,

spent copper etchant (Ferric chloride),

Sodium hypochlorite, polymer, electric

and torch bulbs and tubes, alkaline

cleaner (spent alkaline solution)

Valid

Status of Waste Management

4.5 The Construction and Demolition (C&D) materials generated in the reporting month

were mainly general refuse. The quantities of waste generated in this reporting month

are summarized in Appendix K.

Implementation Status of Environmental Mitigation Measures

4.6 According to the EIA Study Report, Environmental Permit and the EM&A Manual of

the Project, the mitigation measures detailed in the documents are recommended to be

implemented during the construction phase. An updated summary of the EMIS is

provided in Appendix J.

4.7 During site inspections in the reporting month, non-conformance was identified. In

addition, there was no major environmental deficiency being identified on the site audit

session on 24th

September 2013. The observations and recommendations made during

the audit sessions are summarized in Table 4.2.

Page 20: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1

Jardine Engineering Corporation Ltd. Contract No. DE/2009/09

Supply and Installation of Electrical and Mechanical Equipment

for Tai Po Sewage Treatment Works Stage 5 Phase 2B

Monthly EM&A Report – September 2013

MA10069\1309\1309_E&M_kl131021_v1 Cinotech 17

Table 4.2 Observations and Recommendations of Site Audit

Parameters Date Observations and

Recommendations

Follow-up

Water

Quality N/A N/A N/A

Air Quality N/A N/A N/A

Noise N/A N/A N/A

Waste/

Chemical

Management

5 September

2013

Reminder:

Properly clear the construction

materials near JEC site office.

The observation was observed

improved/rectified by the Contractor

during the audit session on 13

September 2013.

13 September

2013

Reminder:

Provide sorting for the waste

storage in the temporary waste

storage area to sort out general

refuse from construction waste.

The observation was observed

improved/rectified by the Contractor

during the audit session on 18

September 2013.

18 September

2013

Reminder:

Clear the construction material in

the sorting area to keep the area

tidy.

The observation was observed

improved/rectified by the Contractor

during the audit session on 24

September 2013.

Summary of Exceedances

4.8 No exceedance of monitoring results was recorded in the reporting month. Summary of

exceedance is provided in Appendix G.

Implementation Status of Event Action Plans

4.9 The Event Action Plans for air quality and construction noise monitoring are presented

in Appendix I. No exceedance was recorded and thus no action was required to be

implemented.

Summary of Complaint and Prosecution

4.10 No environmental related complaint, prosecution or notification of summons was

received in the reporting month.

4.11 There was no environmental complaint, prosecution or notification of summons

received since the Project commencement. The Complaint Log is attached in Appendix

L.

Page 21: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1

Jardine Engineering Corporation Ltd. Contract No. DE/2009/09

Supply and Installation of Electrical and Mechanical Equipment

for Tai Po Sewage Treatment Works Stage 5 Phase 2B

Monthly EM&A Report – September 2013

MA10069\1309\1309_E&M_kl131021_v1 Cinotech 18

5 FUTURE KEY ISSUES

5.1 Key issues to be considered in the coming month include:

C&D wastes generated from installation of E&M equipment;

Apply good site practice during rainy season; and

Accumulation of C&D waste and general waste on site.

Monitoring Schedule for the Next Month

5.2 The tentative environmental monitoring schedule for the next month is shown in

Appendix C.

Construction Program for the Next Month

5.3 A tentative construction programme is provided in Appendix M. The major

construction activities in the coming month will include:

E&M installation of FC No.8B and 10B; Installation of E&M equipment in Aeration Tank No. 5, 6 & 7; RAS pipework installation at Pipe Gallery for new Aeration Tanks No.5 to 7; E&M installation of Primary Sedimentation Tank No. 5; Pipework installation at Pipe Gallery for new PST No.5; E&M installation of new Air Blower No.5; Installation of MCC5 at Stage IV PST Pipe Galley; Demolition of existing cooling water system at CBC; Installation of mechanical screen and shaftless conveyor at Stage IV Screening

House; Fabrication of bio-gas holder on site; Installation of new E&M equipment at Filtrate Treatment Plant (SBR); Installation of new screw pumps (for Stage IV Inlet Works); E&M installation for new Sludge Digestion Tank No.3; Installation of MCC at CBC G/F Switchroom; and Installation of MCC1 at CBC 1/F Switchroom.

Page 22: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1

Jardine Engineering Corporation Ltd. Contract No. DE/2009/09

Supply and Installation of Electrical and Mechanical Equipment

for Tai Po Sewage Treatment Works Stage 5 Phase 2B

Monthly EM&A Report – September 2013

MA10069\1309\1309_E&M_kl131021_v1 Cinotech 19

6 CONCLUSIONS AND RECOMMENDATIONS

Conclusions

6.1 Environmental monitoring and audit works were conducted in the reporting month. Site

inspections were conducted on a weekly basis. The results were reviewed and checked.

6.2 No exceedance of monitoring results was recorded in the reporting month.

6.3 There was no environmental complaint, prosecution or notification of summons

received.

Recommendations

6.4 According to the environmental audit performed in the reporting month, the following

recommendations were made:

Waste / Chemical Management

Good site practices should be adopted to check for any accumulation of waste

materials on site and dispose waste materials at designated areas.

Segregate and store different types of waste in different containers, skips or

stockpiles to enhance reuse or recycling of materials and their proper disposal.

Page 23: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1

���������

Page 24: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1

Scale Proposa

No.

Date Figure

Mar-11 1.1PROJECT SITE LAYOUT PLAN

N.T.S MA10069TAI PO SEWAGE TREATMENT WORKS, STAGE V, PHASE IIB

Page 25: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1
Page 26: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1

���� ��

����������������������

Page 27: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1

Jardine Engineering Corporation Ltd. DSD Contract No. DE/2009/09

Supply and Installation of Electrical and Mechanical Equipment

for Tai Po Sewage Treatment Works Stage 5 Phase 2B

Monthly EM&A Report

MA10069\App A - AL Level A-1 Cinotech

APPENDIX A – Action and Limit Levels

1-Hour TSP

Location Action Level, μg/m3 Limit Level, μg/m3

CAM1 315

500 CAM2 336

CAM3 344

24-Hour TSP

Location Action Level, μg/m3 Limit Level, μg/m3

CAM1 171

260 CAM2 177

CAM3 192

Construction Noise

Time Period Action Level Limit Level

0700-1900 hrs on normal weekdays

When one

documented

complaint is received

75 dB(A)

0700-2300 hrs on holidays; and 1900-

2300 hrs on all other days 70* dB(A)

2300-0700 hrs of next day 55* dB(A)

Notes:

* The Area Sensitivity Rating for Station NM1 is taken as C, due to the nearby industrial area, according to Table 1 of

EPD’s Technical Memorandum on Noise from Construction Work other than Percussive Piling.

Page 28: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1

���� ���

�������������������

�����������

Page 29: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1
Page 30: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1
Page 31: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1
Page 32: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1
Page 33: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1
Page 34: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1
Page 35: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1
Page 36: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1
Page 37: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1

���� ���

������������������������

���������

Page 38: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1

1-Sep 2-Sep 3-Sep 4-Sep 5-Sep 6-Sep 7-Sep

8-Sep 9-Sep 10-Sep 11-Sep 12-Sep 13-Sep 14-Sep

15-Sep 16-Sep 17-Sep 18-Sep 19-Sep 20-Sep 21-Sep

22-Sep 23-Sep 24-Sep 25-Sep 26-Sep 27-Sep 28-Sep

29-Sep 30-Sep

The schedule may be changed due to unforeseen circumstances (adverse weather, etc)

1 hr TSP

1 hr TSP

1 hr TSP

24 hr TSP

1 hr TSP

Noise

1 hr TSP

1 hr TSP 1 hr TSP

Noise

24 hr TSP

1 hr TSP

24 hr TSP

Wednesday

1 hr TSP

Contract No. DE/2009/09 - Construction of Tai Po Sewage Treatment Works - Stage 5 Phase 2B

Tentative Impact Air Quality and Noise Monitoring Schedule for September 2013

Thursday FridayTuesday SaturdaySunday Monday

Noise

1 hr TSP

24 hr TSP

1 hr TSP

Noise

1 hr TSP

24 hr TSP

1 hr TSP

Noise

Page 39: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1

1-Oct 2-Oct 3-Oct 4-Oct 5-Oct

6-Oct 7-Oct 8-Oct 9-Oct 10-Oct 11-Oct 12-Oct

13-Oct 14-Oct 15-Oct 16-Oct 17-Oct 18-Oct 19-Oct

20-Oct 21-Oct 22-Oct 23-Oct 24-Oct 25-Oct 26-Oct

27-Oct 28-Oct 29-Oct 30-Oct 31-Oct

The schedule may be changed due to unforeseen circumstances (adverse weather, etc)

Noise

1 hr TSP 1 hr TSP 1 hr TSP

24 hr TSP24 hr TSP

24 hr TSP

Noise

Noise

1 hr TSP

24 hr TSP

Contract No. DE/2009/09 - Construction of Tai Po Sewage Treatment Works - Stage 5 Phase 2B

Tentative Impact Air Quality and Noise Monitoring Schedule for October 2013

Thursday FridayTuesday SaturdaySunday Monday

1 hr TSP

Wednesday

1 hr TSP1 hr TSP

1 hr TSP

24 hr TSP

1 hr TSP

Noise

1 hr TSP

1 hr TSP

1 hr TSP

1 hr TSP

1 hr TSP

Page 40: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1

���� ���

�����������������������������

���������������������

Page 41: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1

Appendix D - 1-hour TSP Monitoring Results

Station CAM1 Government Staff Quarters

Sampling Weather Air Atmospheric Filter Weight (g) Particulate Elapse Time Sampling Flow Rate (m3/min.) Av. flow Total vol. Conc.

Time Condition Temp. (K) Pressure (Pa) Initial Final weight (g) Initial Final Time(hrs.) Initial Final (m3/min) (m

3) (µg/m

3)

2-Sep-13 9:00 Sunny 301.3 760.9 3.7520 3.7560 0.0040 19750.1 19751.1 1.0 1.21 1.21 1.21 72.9 55

3-Sep-13 9:00 Cloudy 300.7 759.4 3.7704 3.7841 0.0137 19751.1 19752.1 1.0 1.21 1.21 1.21 72.9 188

6-Sep-13 10:00 Sunny 299.1 763.0 3.0763 3.0818 0.0055 19776.1 19777.1 1.0 1.22 1.22 1.22 73.2 75

9-Sep-13 9:00 Sunny 301.4 762.7 3.0826 3.0891 0.0065 19777.1 19778.1 1.0 1.22 1.22 1.22 72.9 89

12-Sep-13 9:00 Sunny 301.9 761.3 3.6078 3.6150 0.0072 19802.1 19803.1 1.0 1.21 1.21 1.21 72.8 99

13-Sep-13 9:00 Sunny 301.8 760.6 3.5640 3.5693 0.0053 19803.1 19804.1 1.0 1.21 1.21 1.21 72.8 73

16-Sep-13 9:00 Sunny 301.5 758.5 3.5800 3.5861 0.0061 19804.1 19805.1 1.0 1.21 1.21 1.21 72.7 84

17-Sep-13 15:25 Sunny 302.0 757.4 3.6968 3.7105 0.0137 19829.1 19830.1 1.0 1.21 1.21 1.21 72.6 189

19-Sep-13 9:00 Sunny 298.9 758.4 3.6956 3.7105 0.0149 19830.1 19831.1 1.0 1.22 1.22 1.22 73.0 204

23-Sep-13 13:00 Cloudy 298.3 751.2 3.5812 3.5882 0.0070 19855.1 19856.1 1.0 1.21 1.21 1.21 72.8 96

26-Sep-13 9:00 Sunny 300.2 762.2 3.5957 3.6040 0.0083 19856.1 19857.1 1.0 1.22 1.22 1.22 73.0 114

27-Sep-13 9:00 Sunny 299.1 761.8 3.6105 3.6150 0.0045 19857.1 19858.1 1.0 1.22 1.22 1.22 73.2 62

30-Sep-13 16:55 Cloudy 300.1 759.9 3.6117 3.6171 0.0054 19882.1 19883.1 1.0 1.22 1.22 1.22 73.0 74

Min 55

Max 204

Average 108

Station CAM2 Heng Hing Printing Centre

Sampling Weather Air Atmospheric Filter Weight (g) Particulate Elapse Time Sampling Flow Rate (m3/min.) Av. flow Total vol. Conc.

Time Condition Temp. (K) Pressure (Pa) Initial Final weight (g) Initial Final Time(hrs.) Initial Final (m3/min) (m

3) (µg/m

3)

2-Sep-13 9:00 Sunny 301.3 760.9 3.7447 3.7501 0.0054 28924.3 28925.3 1.0 1.22 1.22 1.22 73.2 74

3-Sep-13 9:00 Cloudy 300.7 759.4 3.7089 3.7262 0.0173 28925.3 28926.3 1.0 1.22 1.22 1.22 73.2 236

6-Sep-13 10:00 Sunny 299.1 763.0 3.7574 3.7645 0.0071 28950.3 28951.3 1.0 1.23 1.23 1.23 73.6 96

9-Sep-13 9:00 Sunny 301.4 762.7 3.6384 3.6456 0.0072 28951.3 28952.3 1.0 1.22 1.22 1.22 73.3 98

12-Sep-13 9:00 Sunny 301.9 761.3 3.0619 3.0704 0.0085 28977.3 28978.3 1.0 1.22 1.22 1.22 73.2 116

13-Sep-13 9:00 Sunny 301.8 760.6 3.5986 3.6065 0.0079 28978.3 28979.3 1.0 1.22 1.22 1.22 73.2 108

16-Sep-13 9:00 Sunny 301.5 758.5 3.5924 3.6002 0.0078 28979.3 28980.3 1.0 1.22 1.22 1.22 73.1 107

17-Sep-13 15:30 Sunny 302.0 757.4 3.6175 3.6324 0.0149 29004.3 29005.3 1.0 1.22 1.22 1.22 73.0 204

19-Sep-13 9:00 Sunny 298.9 758.4 3.6610 3.6778 0.0168 29005.3 29006.3 1.0 1.22 1.22 1.22 73.4 229

23-Sep-13 13:00 Cloudy 298.3 751.2 3.6413 3.6477 0.0064 29030.3 29031.3 1.0 1.22 1.22 1.22 73.1 87

26-Sep-13 9:00 Sunny 300.2 762.2 3.7341 3.7466 0.0125 29031.3 29032.3 1.0 1.22 1.22 1.22 73.4 170

27-Sep-13 9:00 Sunny 299.1 761.8 3.7577 3.7642 0.0065 29032.3 29033.3 1.0 1.23 1.23 1.23 73.5 88

30-Sep-13 16:30 Cloudy 300.1 759.9 3.5618 3.5699 0.0081 29057.3 29058.3 1.0 1.22 1.22 1.22 73.3 110

Min 74

Max 236

Average 133

Date

Date

MA10069/Monthly_Dust_201309.xls Cinotech

Page 42: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1

Appendix D - 1-hour TSP Monitoring Results

Station CAM3 Talcon Industrial Ltd

Sampling Weather Air Atmospheric Filter Weight (g) Particulate Elapse Time Sampling Flow Rate (m3/min.) Av. flow Total vol. Conc.

Time Condition Temp. (K) Pressure (Pa) Initial Final weight (g) Initial Final Time(hrs.) Initial Final (m3/min) (m

3) (µg/m

3)

2-Sep-13 9:00 Sunny 301.3 760.9 3.7680 3.7752 0.0072 22159.9 22160.9 1.0 1.22 1.22 1.22 73.2 98

3-Sep-13 9:00 Cloudy 300.7 759.4 3.7555 3.7734 0.0179 22160.9 22161.9 1.0 1.22 1.22 1.22 73.2 244

6-Sep-13 10:00 Sunny 299.1 763.0 3.7464 3.7531 0.0067 22185.9 22186.9 1.0 1.23 1.23 1.23 73.6 91

6-Sep-13 9:00 Sunny 301.4 762.7 3.6152 3.6223 0.0071 22186.9 22187.9 1.0 1.22 1.22 1.22 73.3 97

12-Sep-13 9:00 Sunny 301.9 761.3 3.2163 3.2261 0.0098 22211.9 22212.9 1.0 1.22 1.22 1.22 73.2 134

13-Sep-13 9:00 Sunny 301.8 760.6 3.6070 3.6140 0.0070 22212.9 22213.9 1.0 1.22 1.22 1.22 73.2 96

16-Sep-13 9:00 Sunny 301.5 758.5 3.6018 3.6100 0.0082 22213.9 22214.9 1.0 1.22 1.22 1.22 73.1 112

17-Sep-13 15:30 Sunny 302.0 757.4 3.6193 3.6360 0.0167 22238.9 22239.9 1.0 1.22 1.22 1.22 73.0 229

19-Sep-13 9:00 Sunny 298.9 758.4 3.6421 3.6573 0.0152 22239.9 22240.9 1.0 1.22 1.22 1.22 73.4 207

23-Sep-13 13:00 Cloudy 298.3 751.2 3.6484 3.6568 0.0084 22264.9 22265.9 1.0 1.22 1.22 1.22 73.1 115

26-Sep-13 9:00 Sunny 300.2 762.2 3.7210 3.7326 0.0116 22265.9 22266.9 1.0 1.22 1.22 1.22 73.4 158

27-Sep-13 9:00 Sunny 299.1 761.8 3.7407 3.7490 0.0083 22266.9 22267.9 1.0 1.23 1.23 1.23 73.6 113

30-Sep-13 16:00 Cloudy 300.1 759.9 3.5608 3.5702 0.0094 22291.9 22292.9 1.0 1.22 1.22 1.22 73.3 128

Min 91

Max 244

Average 140

Date

MA10069/Monthly_Dust_201309.xls Cinotech

Page 43: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1

1-hr TSP Concentration Levels

0

100

200

300

400

500

600

Co

nc

en

tra

tio

n, µ

g/m

3

Date

Government Staff Quarters (CAM1) 1-hour TSP Conc.

Action Level: 315 µg/m3

Limit Level: 500 µg/m3

200

300

400

500

600

ce

ntr

ati

on

, µg

/m3

Heng Hing Printing Centre (CAM2) 1-hour TSP Conc.

Action Level: 336 µg/m3

Limit Level: 500 µg/m3

Title Scale Project

N.T.S No. MA10069

Date Appendix

Sep 13 D

Contract No. DE/2009/09

Construction of Tai Po Sewage Treatment Works - Stage V Phase II B

Graphical Presentation of 1-hour TSP Impact Monitoring

Results

0

100

200

300

400

500

600

Co

nc

en

tra

tio

n, µ

g/m

3

Date

Talcon Industrial Ltd (CAM3)1-hour TSP Conc.

Action Level: 344 µg/m3

Limit Level: 500 µg/m3

0

100

200

Co

nc

Date

Page 44: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1

���� ���

������������������������������

���������������������

Page 45: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1

Appendix E - 24-hour TSP Monitoring Results

Station CAM1 Government Staff Quarters

Weather Air Atmospheric Filter Weight (g) Particulate Elapse Time Sampling Flow Rate (m3/min.) Av. flow Total vol. Conc.

Condition Temp. (K) Pressure (Pa) Initial Final weight (g) Initial Final Time(hrs.) Initial Final (m3/min) (m

3) (µg/m

3)

4-Sep-13 Cloudy 297.7 759.2 3.0595 3.1146 0.0551 19752.1 19776.1 24.0 1.22 1.22 1.22 1756.8 31

10-Sep-13 Sunny 301.3 761.1 3.6191 3.6969 0.0778 19778.1 19802.1 24.0 1.21 1.21 1.21 1749.0 44

16-Sep-13 Sunny 302.9 757.1 3.5717 3.6623 0.0906 19805.1 19829.1 24.0 1.21 1.21 1.21 1740.4 52

21-Sep-13 Sunny 302.9 753.9 3.6218 3.8011 0.1793 19831.1 19855.1 24.0 1.21 1.21 1.21 1737.0 103

27-Sep-13 Sunny 299.9 761.3 3.5678 3.6904 0.1226 19858.1 19882.1 24.0 1.22 1.22 1.22 1753.1 70

Min 31

Max 103

Average 60

Station CAM2 Heng Hing Printing Centre

Weather Air Atmospheric Filter Weight (g) Particulate Elapse Time Sampling Flow Rate (m3/min.) Av. flow Total vol. Conc.

Condition Temp. (K) Pressure (Pa) Initial Final weight (g) Initial Final Time(hrs.) Initial Final (m3/min) (m

3) (µg/m

3)

4-Sep-13 Cloudy 297.7 759.2 3.7341 3.8081 0.0740 28926.3 28950.3 24.0 1.23 1.23 1.23 1765.8 42

10-Sep-13 Sunny 301.3 761.1 3.2674 3.3745 0.1071 28952.3 28976.3 24.0 1.22 1.22 1.22 1758.0 61

16-Sep-13 Sunny 302.9 757.1 3.6190 3.7091 0.0901 28980.3 29004.3 24.0 1.22 1.21 1.21 1749.5 52

21-Sep-13 Sunny 302.9 753.9 3.6542 3.8462 0.1920 29006.3 29030.3 24.0 1.21 1.21 1.21 1746.1 110

27-Sep-13 Sunny 299.9 761.3 3.2229 3.3654 0.1425 29033.3 29057.3 24.0 1.22 1.22 1.22 1762.1 81

Min 42

Max 110

Average 69

Station CAM3 Talcon Industrial Ltd

Weather Air Atmospheric Filter Weight (g) Particulate Elapse Time Sampling Flow Rate (m3/min.) Av. flow Total vol. Conc.

Condition Temp. (K) Pressure (Pa) Initial Final weight (g) Initial Final Time(hrs.) Initial Final (m3/min) (m

3) (µg/m

3)

4-Sep-13 Cloudy 297.7 759.2 3.7495 3.8395 0.0900 22161.9 22185.9 24.0 1.23 1.23 1.23 1766.4 51

10-Sep-13 Sunny 301.3 761.1 3.0870 3.2017 0.1147 22187.9 22211.9 24.0 1.22 1.22 1.22 1758.0 65

16-Sep-13 Sunny 302.9 757.1 3.6202 3.7213 0.1011 22214.9 22238.9 24.0 1.21 1.21 1.21 1748.8 58

21-Sep-13 Sunny 302.9 753.9 3.6274 3.8401 0.2127 22240.9 22264.9 24.0 1.21 1.21 1.21 1745.1 122

27-Sep-13 Sunny 299.9 761.3 3.7367 3.8953 0.1586 22267.9 22291.9 24.0 1.22 1.22 1.22 1762.4 90

Min 51

Max 122

Average 77

Start Date

Start Date

Start Date

MA10069/Monthly_Dust_201309.xls Cinotech

Page 46: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1

24-hr TSP Concentration Levels

0

50

100

150

200

250

300

Co

ncen

trati

on

, µ

g/m

3

Date

Government Staff Quarters (CAM1)24-hour TSP Conc.

Action Level: 171 µg/m3

Limit Level: 260 µg/m3

100

150

200

250

300

on

cen

trati

on

, µ

g/m

3

Heng Hing Printing Centre (CAM2) 24-hour TSP Conc.

Action Level: 177 µg/m3

Limit Level: 260 µg/m3

Title Scale Project

N.T.S No. MA10069

Date Appendix

Sep 13 E

Contract No. DE/2009/09

Construction of Tai Po Sewage Treatment Works - Stage V Phase II B

Graphical Presentation of 24-hour TSP Impact Monitoring

Results

0

50

100

Co

Date

0

50

100

150

200

250

300

Co

ncen

trati

on

, µ

g/m

3

Date

Talcon Industrial Ltd (CAM3) 24-hour TSP Conc.

Action Level: 192 µg/m3

Limit Level: 260 µg/m3

Page 47: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1

���� ���

����������������������������

������������������

Page 48: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1

Appendix F - Noise Monitoring Results

Location NM1 - Government Staff Quarters

L eq L10 L 90

2-Sep-13 14:00 Sunny 60.8 62.2 57.1

9-Sep-13 13:20 Sunny 58.8 61.4 56.2

16-Sep-13 13:00 Sunny 61.1 62.8 58.3

23-Sep-13 13:00 Cloudy 58.9 60.4 55.4

30-Sep-13 17:00 Cloudy 54.9 56.2 50.6

Average 59.4 60.6 55.5

Minimum 54.9 56.2 50.6

Maximum 61.1 62.8 58.3

Date Time WeatherdB (A) (30-min)

MA10069/Monthly_Noise_201309.xls Cinotech

Page 49: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1

Noise Levels

50.0

55.0

60.0

65.0

70.0

75.0

80.0

dB

(A)

Date

Government Staff Quarters (NM1)NM1

Limit Level, 75dB(A)

Title Scale Project

N.T.SNo.

MA10069

Date Appendix

Sep 13 F

Contract No. DE/2009/09

Construction of Tai Po Sewage Treatment Works - Stage V Phase II B

Graphical Presentation of Construction Noise Monitoring

Results

Page 50: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1

���� ���

����������� ��������

Page 51: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1

Jardine Engineering Corporation Ltd. DSD Contract No. DE/2009/09

Supply and Installation of Electrical and Mechanical Equipment

for Tai Po Sewage Treatment Works Stage 5 Phase 2B

Monthly EM&A Report

MA10069\App G - Exceedance G-1 Cinotech

APPENIDX G – SUMMARY OF EXCEEDANCE

Reporting Month: September 2013

a) Exceedance Report for 1-hr TSP (NIL)

b) Exceedance Report for 24-hr TSP (NIL)

c) Exceedance Report for Construction Noise (NIL)

Page 52: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1

���� ���

�����������������

Page 53: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1
Page 54: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1
Page 55: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1
Page 56: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1
Page 57: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1

���� ���

����������������

Page 58: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1

Jardine Engineering Corporation Ltd. Contract No. DE/2009/09

Supply and Installation of Electrical and Mechanical Equipment

for Tai Po Sewage Treatment Works Stage 5 Phase 2B

Monthly EM&A Report

MA10069\App I - EA Plans.doc I - 1 Cinotech

APPENDIX I (1) – Event Action Plan for Air Quality Monitoring (Construction Phase)

EVENT ACTION

ET IEC ER CONTRACTOR

ACTION LEVEL

1. Exceedance for one sample

1. Identify source, investigate the causes of exceedance and propose remedial measures;

2. Inform IEC and ER; 3. Repeat measurement to confirm finding; 4. Increase monitoring frequency to daily.

1. Check monitoring data submitted by ET; 2. Check Contractor’s working method.

1. Notify Contractor.

1. Rectify any unacceptable practice; 2. Amend working methods if appropriate.

2. Exceedance for two or more consecutive samples

1. Identify source; 2. Inform IC(E) and ER; 3. Advise the ER on the effectiveness of the

proposed remedial measures; 4. Repeat measurements to confirm findings; 5. Increase monitoring frequency to daily; 6. Discuss with IEC and Contractor on remedial

actions required; 7. If exceedance continues, arrange meeting with

IEC and ER; 8. If exceedance stops, cease additional

monitoring.

1. Check monitoring data submitted by ET; 2. Check Contractor’s working method; 3. Discuss with ET and Contractor on possible

remedial measures; 4. Advise the ET on the effectiveness of the

proposed remedial measures; 5. Supervise Implementation of remedial

measures.

1. Confirm receipt of notification of exceedance in writing;

2. Ensure remedial measures properly implemented.

1. Submit proposals for remedial actions to IEC within three working days of notification;

2. Implement the agreed proposals; 3. Amend proposal if appropriate.

LIMIT LEVEL

1. Exceedance for one sample

1. Identify source, investigate the causes of exceedance and propose remedial measures;

2. Inform Contractor, IEC, ER, and EPD; 3. Repeat measurement to confirm finding; 4. Increase monitoring frequency to daily; 5. Assess effectiveness of Contractor’s remedial

actions and keep IEC, EPD and ER informed of the results.

1. Check monitoring data submitted by ET; 2. Check Contractor’s working method; 3. Discuss with ET and Contractor on possible

remedial measures; 4. Advise the ER on the effectiveness of the

proposed remedial measures; 5. Supervise implementation of remedial

measures.

1. Confirm receipt of notification of exceedance in writing;

2. Notify Contractor; 3. Ensure remedial measures properly

implemented.

1. Take immediate action to avoid further exceedance;

2. Submit proposals for remedial actions to IEC within three working days of notification;

3. Implement the agreed proposals; 4. Amend proposal if appropriate.

2. Exceedance for two or more consecutive samples

1. Notify IEC, ER, Contractor and EPD; 2. Identify source; 3. Repeat measurement to confirm findings; 4. Increase monitoring frequency to daily; 5. Carry out analysis of Contractor’s working

procedures to determine possible mitigation to be implemented;

6. Arrange meeting with IEC and ER to discuss the remedial actions to be taken;

7. Assess effectiveness of Contractor’s remedial actions and keep IC(E), EPD and ER informed of the results;

8. If exceedance stops, cease additional monitoring.

1. Discuss amongst ER, ET, and Contractor on the potential remedial actions;

2. Review Contractor’s remedial actions whenever necessary to assure their effectiveness and advise the ER accordingly;

3. Supervise the implementation of remedial measures.

1. Confirm receipt of notification of exceedance in writing;

2. Notify Contractor; 3. In consolidation with the IEC, agree with

the Contractor on the remedial measures to be implemented;

4. Ensure remedial measures properly implemented;

5. If exceedance continues, consider what portion of the work is responsible and instruct the Contractor to stop that portion of work until the exceedance is abated.

1. Take immediate action to avoid further exceedance;

2. Submit proposals for remedial actions to IEC within three working days of notification;

3. Implement the agreed proposals; 4. Resubmit proposals if problem still not

under control; 5. Stop the relevant portion of works as

determined by the ER until the exceedance is abated.

Page 59: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1

Jardine Engineering Corporation Ltd. Contract No. DE/2009/09

Supply and Installation of Electrical and Mechanical Equipment

for Tai Po Sewage Treatment Works Stage 5 Phase 2B

Monthly EM&A Report

MA10069\App I - EA Plans.doc I - 2 Cinotech

APPENDIX I (2) – Event Action Plan for Construction Noise Monitoring (Construction Phase)

EVENT ACTION

ET IEC ER CONTRACTOR

ACTION LEVEL

1. Notify IEC and Contractor;

2. Carry out investigation;

3. Report the results of investigation to

the IEC, ER and Contractor;

4. Discuss with the Contractor and

formulate remedial measures;

5. Increase monitoring frequency to

check mitigation effectiveness.

1. Review the analyzed results submitted

by the ET;

2. Review the propose d remedial

measures by the Contractor and advise

the ER accordingly;

3. Supervise the implementation of

remedial measures.

1. Confirm receipt of notification of failure

in writing;

2. Notify Contractor;

3. Require Contractor to propose remedial

measures for the analyzed noise

problem;

4. Ensure remedial measures are properly

implemented.

1. Submit noise mitigation proposals to

IEC;

2. Implement noise mitigation proposals.

LIMIT LEVEL

1. Identify source;

2. Inform IEC, ER, EPD and Contractor;

3. Repeat measurements to confirm

findings;

4. Increase monitoring frequency;

5. Carry out analysis of Contractor’s working procedures to determine

possible mitigation to be implemented;

6. Inform IEC, ER and EPD the causes

and actions taken for the exceedances;

7. Assess effectiveness of Contractor’s remedial actions and keep IEC, EPD

and ER informed of the results;

8. If exceedance stops, cease additional

monitoring.

1. Discuss amongst ER, ET, and

Contractor on the potential remedial

actions;

2. Review Contractors remedial actions

whenever necessary to assure their

effectiveness and advise the ER

accordingly;

3. Supervise the implementation of

remedial measures.

1. Confirm receipt of notification of failure

in writing;

2. Notify Contractor;

3. Require Contractor to propose remedial

measures for the analysed noise

problem;

4. Ensure remedial measures properly

implemented;

5. If exceedance continues, consider what

portion of the work is responsible and

instruct the Contractor to stop that

portion of work until the exceedance is

abated.

1. Take immediate action to avoid

further exceedance;

2. Submit proposals for remedial actions

to IEC within 3 working days of

notification;

3. Implement the agreed proposals;

4. Resubmit proposals if problem still

not under control;

5. Stop the relevant portion of works as

determined by the ER until the

exceedance is abated.

Page 60: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1

���� ���

�������������������

�����������������������

����������

Page 61: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1

Jardine Engineering Corporation Ltd. DSD Contract No. DE/2009/09

Supply and Installation of Electrical and Mechanical Equipment

for Tai Po Sewage Treatment Works Stage 5 Phase 2B

Monthly EM&A Report

MA10069\App J- EMIS.doc J-1 Cinotech

APPENDIX J – Updated Environmental Mitigation Implementation Schedule

(During Construction Phase)

Type of Impact Recommended Mitigation Measures Status

Air Quality Dust mitigation measures stipulated in the Air Pollution Control (Construction Dust) Regulation

shall be incorporated to control dust emission. Notice shall be given to authority prior to

commencing of work

Noise Use of quiet PME

N/A

Good Site Practice

Only well-maintained plant should be operated on-site and plant should be serviced regularly

during the construction program;

Silencers or mufflers on construction equipment should be utilized and should be properly

maintained during the construction program;

Mobile plant, if any, should be sited as far from NSRs as possible;

Machines and plant (such as trucks) that may be in intermittent use should be shut down between

work periods or should be throttled down to a minimum;

Plant known to emit noise strongly in one direction should, wherever possible, be orientated so

that the noise is directed away from the nearby NSRs; and

Material stockpiles and other structures should be effectively utilised, wherever practicable, in

screening noise from on-site construction activities.

Water Quality The practices outlined in ProPECC PN 1/94 Construction Site Drainage should be adopted to

minimize the potential water quality impacts from construction site runoff and various construction

activities. The recommendation to install perimeter drains to collect site runoff and to properly treat

the runoff by settlement tank/treatment system shall apply to all sites including those for mainlaying

works. Minimum distances of 100 m should be maintained between the discharge points of

construction site runoff and the existing WSD saltwater intake at Tai Po.

A discharge licence needs to be applied from EPD for discharging effluent from the construction site.

The discharge quality is required to meet the requirements specified in the discharge licence. All the

runoff and wastewater generated from the works areas should be treated so that it satisfies with all

the standards listed in the TM. Reuse and recycling of the treated effluent can minimize water

consumption and reduce the effluent discharge volume. The beneficial uses of the treated effluent

may include dust suppression, wheel washing and general cleaning. Monitoring of the discharge

quality of treated effluent should be part of the Environmental Monitoring and Audit (EM&A)

programme. Detailed effluent sampling programme for water quality control during construction

phase should be submitted to EPD, AFCD and WSD for approval prior to commencement of the

construction works.

N/A

The construction programme should be properly planned to minimize soil excavation, if any, in rainy

seasons. This prevents soil erosion from exposed soil surfaces. Any exposed soil surfaces should also

be properly protected to minimize dust emission. In areas where a large amount of exposed soils

exist, earth bunds or sand bags should be provided. Exposed stockpiles should be covered with

tarpaulin or impervious sheets at all time. The stockpiles of materials should be placed in the

locations away from any stream courses so as to avoid releasing materials into the water bodies.

Final surfaces of earthworks should be compacted and protected by permanent work. It is suggested

that haul roads should be paved with concrete and the temporary access roads are protected using

crushed stone or gravel, wherever practicable. Wheel washing facilities should be provided at all site

exits to ensure that earth, mud and debris would not be carried out of the works areas by vehicles.

Good site practices should be adopted to clean the rubbish and litter on the construction sites so as to

prevent the rubbish and litter from dropping into the nearby environment. It is recommended to clean

the construction sites on a regular basis.

Page 62: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1

Jardine Engineering Corporation Ltd. DSD Contract No. DE/2009/09

Supply and Installation of Electrical and Mechanical Equipment

for Tai Po Sewage Treatment Works Stage 5 Phase 2B

Monthly EM&A Report

MA10069\App J- EMIS.doc J-2 Cinotech

Type of Impact Recommended Mitigation Measures Status

It is recommended to provide sufficient chemical toilets in the works areas. The toilet facilities

should not be less than 30 m from any watercourse. A licensed waste collector should be deployed to

clean the chemical toilets on a regular basis. The construction workers can also make use of the

existing toilet facilities within the TPSTW as necessary.

Notices should be posted at conspicuous locations to remind the workers not to discharge any sewage

or wastewater into the nearby environment during the construction phase of the project.

Implementation of environmental audit on the construction site can provide an effective control of

any malpractices and can achieve continual improvement of environmental performance on site.

It is required to register as a chemical waste producer if chemical wastes would be produced from the

construction activities. The Waste Disposal Ordinance (Cap 354) and its subsidiary regulations in

particular the Waste Disposal (Chemical Waste) (General) Regulation should be observed and

complied with for control of chemical wastes.

Any service shop and minor maintenance facilities should be located on hard standings within a

bunded area, and sumps and oil interceptors should be provided. Maintenance of vehicles and

equipment involving activities with potential for leakage and spillage should only be undertaken with

the areas appropriately equipped to control these discharges.

Disposal of chemical wastes should be carried out in compliance with the Waste Disposal Ordinance.

The Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes published under

the Waste Disposal Ordinance details the requirements to deal with chemical wastes. General

requirements are given as follows:

Suitable containers should be used to hold the chemical wastes to avoid leakage or spillage during

storage, handling and transport

Chemical waste containers should be suitably labelled to notify and warn the personnel who are

handling the wastes to avoid accidents.

Storage area should be selected at a safe location on site and adequate space should be allocated

to the storage area.

Marine water quality monitoring should be carried out under emergency condition or during

maintenance of the THEES tunnel to verify the findings of the water quality modelling. It is

recommended that the maintenance of the THEES tunnel, if unavoidable, should be conducted

during winter season or low flow periods and to avoid the “blooming” season of algae (normally from April to June) if practicable. Details of the monitoring requirements are specified in the EM&A

Manual.

N/A

Page 63: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1

Jardine Engineering Corporation Ltd. DSD Contract No. DE/2009/09

Supply and Installation of Electrical and Mechanical Equipment

for Tai Po Sewage Treatment Works Stage 5 Phase 2B

Monthly EM&A Report

MA10069\App J- EMIS.doc J-3 Cinotech

Type of Impact Recommended Mitigation Measures Status

Waste

Management

Good site

Nomination of approved personnel, such as a site manager, to be responsible for good site

practices, arrangements for collection and effective disposal to an appropriate facility, of all

wastes generated at the site.

Training of site personnel in proper waste management and chemical waste handling procedures.

Provision of sufficient waste disposal points and regular collection for disposal.

Appropriate measures to minimise windblown litter and dust during transportation of waste by

either covering trucks or by transporting wastes in enclosed containers.

Separation of chemical wastes for special handling and appropriate treatment at the Chemical

Waste Treatment Facility.

Regular cleaning and maintenance programme for drainage systems, sumps and oil interceptors.

A Waste Management Plan shall be prepared and this WMP shall be submitted to the Engineer

for approval. One may make reference to ETWB TCW No. 15/2003 for details.

In order to monitor the disposal of C&D materials at landfills and public filling areas, and to

control fly tipping, a trip-ticket system shall be included as one of the contractual requirements

and implemented by an Environmental Team undertaking the Environmental Monitoring and

Audit work. One may make reference to WBTC No. 21/2002 for details.

A recording system for the amount of wastes generated, recycled and disposed (including the

disposal sites) shall be proposed.

Waste reduction is best achieved at the planning and design stage, as well as by ensuring the

implementation of good site practices. Recommendations to achieve waste reduction include:

Segregation and storage of different types of waste in different containers, skips or stockpiles to

enhance reuse or recycling of materials and their proper disposal.

To encourage collection of aluminum cans by individual collectors, separate labelled bins shall be

provided to segregate this waste from other general refuse generated by the work force.

Any unused chemicals or those with remaining functional capacity shall be recycled.

Maximize the use of reusable steel formwork to reduce the amount of C&D material.

Prior to disposal of C&D waste, it is recommended that wood, steel and other metals shall be

separated for re-use and / or recycling to minimize the quantity of waste to be disposed of to

landfill.

Proper storage and site practices to minimize the potential for damage or contamination of

construction materials.

Plan and stock construction materials carefully to minimize amount of waste generated and avoid

unnecessary generation of waste.

Minimize over ordering of concrete, mortars and cement grout by doing careful check before

ordering

General Refuse

General refuse shall be stored in enclosed bins or compaction units separate from C&D material. A

reputable waste collector shall be employed by the contractor to remove general refuse from the site,

separately from C&D material. An enclosed and covered area is preferred to reduce the occurrence

of 'wind blown' light material.

Construction & Demolition (C&D) Material

C&D material generated from the site formation and demolition works shall be sorted on-site into

inert C&D material (i.e. public fill) and C&D waste. In order to minimise the impact resulting from

collection and transportation of C&D material for off-site disposal, the excavated material

comprising fill material shall be reused on-site as backfilling material as far as practicable. C&D

waste, such as wood, plastic, steel and other metals shall be reused or recycled and, as a last resort,

disposed of to landfill. A suitable area shall be designated within the site for temporary stockpiling of

C&D material and to facilitate the sorting process.

Page 64: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1

Jardine Engineering Corporation Ltd. DSD Contract No. DE/2009/09

Supply and Installation of Electrical and Mechanical Equipment

for Tai Po Sewage Treatment Works Stage 5 Phase 2B

Monthly EM&A Report

MA10069\App J- EMIS.doc J-4 Cinotech

Type of Impact Recommended Mitigation Measures Status

Bentonite Slurry

Bentonite slurries used in construction works should be reconditioned and reused wherever

practicable. Residual used bentonite slurry should be disposed of from the site as soon as possible.

The Contractor should explore alternative disposal outlets for the residual used bentonite slurry and

disposal at landfill should be the last resort.

N/A

Note:

√ – Compliance of mitigation measures

X – Non-compliance of mitigation measures

N/A – Not applicable

Page 65: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1

���� ���

����������������������

���������������

Page 66: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1

Jardine Engineering Corporation, Limited

Monthly Summary Waste Flow Table Page 1 of 1

Name of Department: Drainage Services Department Contract No. : DE/2009/09

Monthly Summary - Waste Flow Table for 2013

Month

Annual Quantities of Inert C&D Materials Generated Monthly

Annual Quantities of C&D Materials Generated Monthly

Total Quantity

Generated

Hard Rock & Large Broken

Concrete

Reused in the

Contract

Reused in other

Projects

Disposed as

Public Fill Imported Fill Metals

Paper/

cardboard

packaging

Plastics

(see Note 3)

Chemicals

Waste

Others, e.g.

general refuse

(in m3) (in m

3) (in m

3) (in m

3) (in m

3) (in m

3) (in ‘000 kg) (in ‘000 kg) (in ‘000 kg) (in ‘000 kg) (in tonne)

Jan 0 0 0 0 0 0 0 0 0 0 5.0

Feb 0 0 0 0 0 0 0 0 0 0 1.8

Mar 0 0 0 0 0 0 0 0.13 0 0 2.0

Apr 0 0 0 0 0 0 0 0 0 0 1.2

May 0 0 0 0 0 0 0 0 0 0 1.4

June 0 0 0 0 0 0 0 0.07 0 0 0

July 0 0 0 0 0 0 0 0 0 0 4.4

Aug 0 0 0 0 0 0 0 0 0 600L 3.1

Sept 0 0 0 0 0 0 1.37 0 0 0 3.9

Oct

Nov

Dec

Total 0 0 0 0 0 0 1.37 0.2 0 600L 22.8

Forecast of Total Quantities of C&D Materials to be Generated from the Contractor

Total Quantity

Generated

Hard Rock & Large Broken

Concrete

Reused in the

Contract

Reused in other

Projects

Disposed as

Public Fill Imported Fill Metals

Paper/ cardboard packaging

Plastics (see Note 3)

Chemicals Waste

Others, e.g. general refuse

(in m3) (in m

3) (in m

3) (in m

3) (in m

3) (in m

3) (in ‘000 kg) (in ‘000 kg) (in ‘000 kg) (in ‘000 kg) (in tonne)

0 Nil 0 0 0 0 100 100 50 10 500 Notes: (1) The performance targets are given in PS Clause 1.40.8(14).

(2) The waste flow table shall also include C&D materials that are specified in the Contract to be imported for use at the Site. (3) Plastics refer to plastic bottles/containers, plastic sheets/foam from packaging material. (4) The Contractor shall also submit the latest forecast of the total amount of C&D materials expected to be generated from the Works, together with a breakdown of the nature

where the total amount of C&D materials expected to be generated from the Works is equal to or exceeding 50,000 m3. (PS Clause 1.40.7(4)(b) refers.

Page 67: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1

���� ���

������������

Page 68: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1

Jardine Engineering Corporation Ltd. DSD Contract No. DE/2009/09

Supply and Installation of Electrical and Mechanical Equipment

for Tai Po Sewage Treatment Works Stage 5 Phase 2B

Monthly EM&A Report

MA10069\App L - Complaint L-1 Cinotech

APPENDIX L – COMPLAINT LOG

Reporting Month: September 2013

Log Ref. Location Received

Date

Details of

Complaint

Investigation/Mitigation

Action Status

N/A N/A N/A N/A N/A N/A

Remarks: No environmental complaint was received in the reporting month.

Page 69: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1

���� ���

���������������������

Page 70: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1

ID Task Name Duration Start Finish

1 Section II of the Works 243 days Thu 01/08/13 Mon 31/03/14

2 Modification / Replacement of Existing L.V. Switchboard (RAS MCC3) 203 days Tue 02/07/13 Mon 20/01/14

3 MCC3 Manufacture & Delivery to Site 90 days Thu 01/08/13 Tue 29/10/13

4 Temporary Works Preparation 61 days Tue 02/07/13 Sat 31/08/13

5 Temporary Works Installation 31 days Sun 01/09/13 Tue 01/10/13

6 Migration of Power/Control for Existing E&M Equipment to Temporary Panels 31 days Wed 02/10/13 Fri 01/11/13

7 Removal of Existing MCC1, MCC3 & MCC4 7 days Sat 02/11/13 Fri 08/11/13

8 Civil Modification Works (By Civil Contractor) 21 days Sat 09/11/13 Fri 29/11/13

9 MCC3 Installation, SAT, Cable Installation & Migration 45 days Sat 30/11/13 Mon 13/01/14

10 Removal of Temporary Panels 7 days Tue 14/01/14 Mon 20/01/14

11 Final Clarifier No. 7B to 10B 1105 days Wed 23/03/11 Mon 31/03/14

12 Equipment and Material Delivery to Site 862 days Wed 23/03/11 Thu 01/08/13

13 Tripods, Bridges & Scrapers for FC7B - 10B 0 days Wed 20/02/13 Wed 20/02/13

14 Weir Plates 0 days Wed 20/02/13 Wed 20/02/13

15 Density Current Baffle 0 days Wed 23/03/11 Wed 23/03/11

16 FCW & FEDB 0 days Wed 22/08/12 Wed 22/08/12

17 DI Pipes, Fittings & Accessories 0 days Tue 03/05/11 Tue 03/05/11

18 Water Spray Pumps & Associated Pipework 0 days Fri 13/05/11 Fri 13/05/11

19 Instrumentation (Ultrasonic Level Sensors & Sludge Blanket Sensors) 0 days Fri 29/04/11 Fri 29/04/11

20 LCP for Scraper Bridges 0 days Thu 01/08/13 Thu 01/08/13

21 Cable, Cable Trays and Accessories 0 days Wed 22/08/12 Wed 22/08/12

22 B.S. Equipment & Accessories 0 days Fri 15/07/11 Fri 15/07/11

23 Site Possession / Available 0 days Thu 01/08/13 Thu 01/08/13

24 FC7B - 10B 0 days Thu 01/08/13 Thu 01/08/13

25 Cable drawpit and duct 0 days Thu 01/08/13 Thu 01/08/13

26 Installation 213 days Thu 01/08/13 Sat 01/03/14

27 FC7B 57 days Thu 01/08/13 Thu 26/09/13

28 Site Preparation Works 5 days Thu 01/08/13 Mon 05/08/13

29 Tripods, Bridges & Scrapers 15 days Tue 06/08/13 Tue 20/08/13

30 Weir Plates 10 days Thu 01/08/13 Sat 10/08/13

31 Density Current Baffles 10 days Sun 11/08/13 Tue 20/08/13

32 FCW & FEDB 6 days Wed 21/08/13 Mon 26/08/13

33 Instrumentation 10 days Sun 11/08/13 Tue 20/08/13

34 Final screeding 31 days Tue 27/08/13 Thu 26/09/13

35 FC8B 104 days Tue 06/08/13 Sun 17/11/13

36 Site Preparation Works 5 days Tue 06/08/13 Sat 10/08/13

37 Tripods, Bridges & Scrapers 15 days Fri 27/09/13 Fri 11/10/13

38 Weir Plates 10 days Sun 22/09/13 Tue 01/10/13

39 Density Current Baffles 10 days Wed 02/10/13 Fri 11/10/13

40 FCW & FEDB 6 days Sat 12/10/13 Thu 17/10/13

41 Instrumentation 10 days Wed 02/10/13 Fri 11/10/13

42 Final screeding 31 days Fri 18/10/13 Sun 17/11/13

43 FC9B 151 days Sun 11/08/13 Wed 08/01/14

44 Site Preparation Works 5 days Sun 11/08/13 Thu 15/08/13

45 Tripods, Bridges & Scrapers 15 days Mon 18/11/13 Mon 02/12/13

46 Weir Plates 10 days Wed 13/11/13 Fri 22/11/13

47 Density Current Baffles 10 days Sat 23/11/13 Mon 02/12/13

48 FCW & FEDB 6 days Tue 03/12/13 Sun 08/12/13

49 Instrumentation 10 days Sat 23/11/13 Mon 02/12/13

50 Final screeding 31 days Mon 09/12/13 Wed 08/01/14

51 FC10B 198 days Fri 16/08/13 Sat 01/03/14

52 Site Preparation Works 5 days Fri 16/08/13 Tue 20/08/13

53 Tripods, Bridges & Scrapers 15 days Thu 09/01/14 Thu 23/01/14

54 Weir Plates 10 days Sat 04/01/14 Mon 13/01/14

55 Density Current Baffles 10 days Tue 14/01/14 Thu 23/01/14

56 FCW & FEDB 6 days Fri 24/01/14 Wed 29/01/14

57 Instrumentation 10 days Tue 14/01/14 Thu 23/01/14

58 Final screeding 31 days Thu 30/01/14 Sat 01/03/14

59 Electrical Installation 180 days Mon 26/08/13 Fri 21/02/14

60 Modification of existing PLC system E 120 days Fri 25/10/13 Fri 21/02/14

61 B.S. Installation 31 days Wed 22/01/14 Fri 21/02/14

62 Testing and Commissioning 30 days Sun 02/03/14 Mon 31/03/14

63 Stage IV RAS Pumping Station 730 days Sun 01/04/12 Mon 31/03/14

64 Equipment and Material Delivey to Site 143 days Sun 01/04/12 Wed 22/08/12

65 RAS Pumps 0 days Tue 01/05/12 Tue 01/05/12

66 Pipework & Valves 0 days Sun 01/04/12 Sun 01/04/12

67 VSD Panel for RAS Pumps No.1 & 5 0 days Wed 22/08/12 Wed 22/08/12

68 PLC System H Panel 0 days Wed 22/08/12 Wed 22/08/12

69 Installation 243 days Thu 01/08/13 Mon 31/03/14

70 RAS Pump No.5 31 days Thu 01/08/13 Sat 31/08/13

71 Available of Pump Concrete Plinth (Modified by Civil Contractor) 0 days Thu 01/08/13 Thu 01/08/13

72 Installation of Pump, Gate Valve, Swing Check Valve & DI Pipework 21 days Thu 01/08/13 Wed 21/08/13

73 Electrical Works & SCADA/PLC Works 14 days Thu 08/08/13 Wed 21/08/13

74 Testing & Commissioning 10 days Thu 22/08/13 Sat 31/08/13

75 RAS Pump No.4 53 days Sun 01/09/13 Wed 23/10/13

76 Decommissioning & Removal of Pump 3 days Sun 01/09/13 Tue 03/09/13

77 Pump Concrete Plinth Modification Works (By Civil Contractor) 21 days Wed 04/09/13 Tue 24/09/13

78 Installation of Pump & DI Pipework 19 days Wed 25/09/13 Sun 13/10/13

79 Electrical Works & SCADA/PLC Works 14 days Mon 30/09/13 Sun 13/10/13

80 Testing & Commissioning 10 days Mon 14/10/13 Wed 23/10/13

81 RAS Pump No.3 53 days Thu 24/10/13 Sun 15/12/13

82 Decommissioning & Removal of Pump 3 days Thu 24/10/13 Sat 26/10/13

83 Pump Concrete Plinth Modification Works (By Civil Contractor) 21 days Sun 27/10/13 Sat 16/11/13

84 Installation of Pump & DI Pipework 19 days Sun 17/11/13 Thu 05/12/13

85 Electrical Works & SCADA/PLC Works 14 days Fri 22/11/13 Thu 05/12/13

86 Testing & Commissioning 10 days Fri 06/12/13 Sun 15/12/13

87 RAS Pump No.2 53 days Mon 16/12/13 Thu 06/02/14

88 Decommissioning & Removal of Pump 3 days Mon 16/12/13 Wed 18/12/13

89 Pump Concrete Plinth Modification Works (By Civil Contractor) 21 days Thu 19/12/13 Wed 08/01/14

90 Installation of Pump & DI Pipework 19 days Thu 09/01/14 Mon 27/01/14

91 Electrical Works & SCADA/PLC Works 14 days Tue 14/01/14 Mon 27/01/14

92 Testing & Commissioning 10 days Tue 28/01/14 Thu 06/02/14

93 RAS Pump No.1 53 days Fri 07/02/14 Mon 31/03/14

94 Decommissioning & Removal of Pump 3 days Fri 07/02/14 Sun 09/02/14

95 Pump Concrete Plinth Modification Works (By Civil Contractor) 21 days Mon 10/02/14 Sun 02/03/14

96 Installation of Pump & DI Pipework 19 days Mon 03/03/14 Fri 21/03/14

97 Electrical Works & SCADA/PLC Works 14 days Sat 08/03/14 Fri 21/03/14

98 Testing & Commissioning 10 days Sat 22/03/14 Mon 31/03/14

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

20/02

20/02

23/03

22/08

03/05

13/05

29/04

01/08

22/08

15/07

01/08

01/08

01/08

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

100%

01/05

01/04

22/08

22/08

0%

01/08

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

Mar '11 Apr '11 May '11 Jun '11 Jul '11 Aug '11 Sep '11 Oct '11 Nov '11 Dec '11 Jan '12 Feb '12 Mar '12 Apr '12 May '12 Jun '12 Jul '12 Aug '12 Sep '12 Oct '12 Nov '12 Dec '12 Jan '13 Feb '13 Mar '13 Apr '13 May '13 Jun '13 Jul '13 Aug '13 Sep '13 Oct '13 Nov '13 Dec '13 Jan '14 Feb '14 Mar '14

Q2 '11 Q3 '11 Q4 '11 Q1 '12 Q2 '12 Q3 '12 Q4 '12 Q1 '13 Q2 '13 Q3 '13 Q4 '13 Q1 '14

Critical

Critical Split

Critical Progress

Task

Split

Task Progress

Baseline

Baseline Split

Baseline Milestone

Milestone

Summary Progress

Summary

Project Summary

External Tasks

External Milestone

Deadline

DSD Contract : DE/2009/09Supply and Installation of Electrical and Mechanical Equipment for Tai Po Sewage Treatment Works Stage 5 Phase 2B

Section II Works Programme

Page 1

Rev.2Date: 17 June 2013

Page 71: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1

ID Task Name Duration Start Finish

1 Section III of the Works 425 days Fri 16/03/12 Tue 14/05/13

2 EOT Granted 2 days Wed 15/05/13 Thu 16/05/13

3

4 Modification / Replacement of Existing L.V. Switchboard 733 days Thu 01/03/12 Mon 03/03/14

5 CBC 1/F MCC2A 475 days Thu 01/03/12 Tue 18/06/13

6 MCC2A Manufacture & Delivery to Site 265 days Thu 01/03/12 Tue 20/11/12

7 Relocate Existing Workstation 6 days Wed 16/05/12 Mon 21/05/12

8 Civil Modification Works (By Civil Contractor) 169 days Tue 22/05/12 Tue 06/11/12

9 MCC2A Installation & SAT 59 days Wed 07/11/12 Fri 04/01/13

10 New Power Cable Installation from New CBC G/F Switchboard to MCC2A 77 days Sat 05/01/13 Fri 22/03/13

11 Energization of MCC2A 0 days Fri 22/03/13 Fri 22/03/13

12 Migration of Power/Control for Existing E&M Equipment to MCC2A 88 days Sat 23/03/13 Tue 18/06/13

13 CBC 1/F MCC2 307 days Wed 01/05/13 Mon 03/03/14

14 MCC2 Manufacture & Delivery to Site 150 days Mon 15/07/13 Wed 11/12/13

15 MCC2 Extension Manufacture & Delivery to Site 90 days Tue 02/07/13 Sun 29/09/13

16 Demolition of MCC8 at CBC 1/F 21 days Thu 01/08/13 Wed 21/08/13

17 Temporary Works Preparation 61 days Wed 01/05/13 Sun 30/06/13

18 Temporary Works Installation 21 days Mon 01/07/13 Sun 21/07/13

19 Installation of Permanent Marshalling Boxes & Cable Trays 61 days Wed 22/05/13 Sun 21/07/13

20 Migration of Power/Control for Existing E&M Equipment from existing MCC2 Extension to Temp. MCC 44 days Mon 22/07/13 Tue 03/09/13

21 Removal of Existing MCC2 Extension 7 days Wed 04/09/13 Tue 10/09/13

22 Civil Modification Works for New MCC2 Extension (By Civil Contractor) 21 days Wed 11/09/13 Tue 01/10/13

23 MCC2 Extension Installation & SAT 14 days Wed 02/10/13 Tue 15/10/13

24 Migration of Power/Control for Existing E&M Equipment to New MCC2 Extension & Temp. MCC 31 days Wed 16/10/13 Fri 15/11/13

25 Removal of Existing Switchboard MCC2 7 days Sat 16/11/13 Fri 22/11/13

26 Civil Modification Works for MCC2 (By Civil Contractor) 21 days Sat 23/11/13 Fri 13/12/13

27 MCC2 Installation & SAT 21 days Sat 14/12/13 Fri 03/01/14

28 Migration of Power/Control for Existing E&M Equipment to New MCC2 45 days Sat 04/01/14 Mon 17/02/14

29 Installation of New Cables 14 days Tue 04/02/14 Mon 17/02/14

30 Removal of Temporary Panels 14 days Tue 18/02/14 Mon 03/03/14

31 PST MCC5 & MCC5A 441 days Wed 08/08/12 Tue 22/10/13

32 MCC5 Manufacture & Delivery to Site 368 days Wed 08/08/12 Sat 10/08/13

33 Temporary Works Preparation 36 days Thu 16/05/13 Thu 20/06/13

34 Temporary Works Installation 14 days Fri 21/06/13 Thu 04/07/13

35 Migration of Power/Control for Existing E&M Equipment to Temporary Panels 14 days Fri 05/07/13 Thu 18/07/13

36 Removal of Existing MCC5 & MCC5B 7 days Fri 19/07/13 Thu 25/07/13

37 Civil Modification Works (By Civil Contractor) 21 days Fri 26/07/13 Thu 15/08/13

38 MCC5 Installation, MCC5A Modification, SAT, Cable Installation & Migration 61 days Fri 16/08/13 Tue 15/10/13

39 Removal of Temporary Panels 7 days Wed 16/10/13 Tue 22/10/13

40

41

42 Air Blowers in CBC 825 days Thu 01/12/11 Tue 04/03/14

43 Equipment and Material Delivery to Site 452 days Thu 01/12/11 Mon 25/02/13

44 Air Blowers 0 days Thu 01/12/11 Thu 01/12/11

45 Pipework & Valves 0 days Mon 25/02/13 Mon 25/02/13

46 Air Ductwork 0 days Mon 25/02/13 Mon 25/02/13

47 Vibration Monitoring System 0 days Thu 01/03/12 Thu 01/03/12

48 Modification Works 646 days Mon 28/05/12 Tue 04/03/14

49 Air Blower No.5 646 days Mon 28/05/12 Tue 04/03/14

50 Decommissioning & Dismantle of Existing Air Blower & Accessories 19 days Mon 28/05/12 Fri 15/06/12

51 Civil Modification & GMS Puddle Flange Pipe Installation (By Civil Contractor) 255 days Sat 16/06/12 Mon 25/02/13

52 Installation of New Air Blower & Accessories 180 days Tue 26/02/13 Sat 24/08/13

53 Electrical Installation (with Temporary MCC/Starter Panel) 90 days Tue 16/04/13 Sun 14/07/13

54 Testing and Commissioning 15 days Sun 25/08/13 Sun 08/09/13

55 Migration from Temporary MCC/Starter to MCC2 15 days Tue 18/02/14 Tue 04/03/14

56 Air Blower No.2 81 days Mon 09/09/13 Thu 28/11/13

57 Decommissioning & Dismantle of Existing Air Blower & Accessories 15 days Mon 09/09/13 Mon 23/09/13

58 Civil Modification & GMS Puddle Flange Pipe Installation (By Civil Contractor) 21 days Tue 24/09/13 Mon 14/10/13

59 Installation of New Air Blower & Accessories 30 days Tue 15/10/13 Wed 13/11/13

60 Electrical Installation (with New MCC2) 30 days Tue 15/10/13 Wed 13/11/13

61 Testing and Commissioning 15 days Thu 14/11/13 Thu 28/11/13

62 Air Blower No.1 81 days Fri 29/11/13 Mon 17/02/14

63 Decommissioning & Dismantle of Existing Air Blower & Accessories 15 days Fri 29/11/13 Fri 13/12/13

64 Civil Modification & GMS Puddle Flange Pipe Installation (By Civil Contractor) 21 days Sat 14/12/13 Fri 03/01/14

65 Installation of New Air Blower & Accessories 30 days Sat 04/01/14 Sun 02/02/14

66 Electrical Installation (with New MCC2) 30 days Sat 04/01/14 Sun 02/02/14

67 Testing and Commissioning 15 days Mon 03/02/14 Mon 17/02/14

68

69

70 Primary Sedimentation Tank No.5 934 days Fri 21/10/11 Sun 11/05/14

71 Equipment and Material Delivery to Site 528 days Fri 21/10/11 Mon 01/04/13

72 Sludge & Scum Collection System 0 days Tue 02/10/12 Tue 02/10/12

73 PST Drain-off Pump 0 days Fri 26/10/12 Fri 26/10/12

74 Scum Pump 0 days Tue 06/11/12 Tue 06/11/12

75 Pipework & Valves 0 days Fri 21/10/11 Fri 21/10/11

76 Local Control Panel for Sludge & Scum Collection System 0 days Mon 01/04/13 Mon 01/04/13

77 Site Possession / Available 161 days Mon 04/02/13 Mon 15/07/13

78 PST No.5 0 days Mon 04/02/13 Mon 04/02/13

79 Pipe Gallery for PST No.5 0 days Mon 15/07/13 Mon 15/07/13

80 Cable Drawpit & Duct 0 days Mon 15/07/13 Mon 15/07/13

81 Installation 372 days Mon 04/02/13 Mon 10/02/14

82 Sludge & Scum Scrapers 150 days Mon 04/02/13 Wed 03/07/13

83 Influent Pipework in Pipe Gallery 61 days Mon 15/07/13 Fri 13/09/13

84 PST Drain-off Pump & Associated Pipework 30 days Sat 14/09/13 Sun 13/10/13

85 Water Spray Pipework for Scum Trough 15 days Mon 15/07/13 Mon 29/07/13

86 Scum Pump & Associated Pipework 60 days Sat 14/09/13 Tue 12/11/13

87 Local Control Panel & Electrical Installation 90 days Wed 13/11/13 Mon 10/02/14

88 H2S Detection System Installation 60 days Fri 13/12/13 Mon 10/02/14

89 Testing and Commissioning 90 days Tue 11/02/14 Sun 11/05/14

90

91

92 New Aeration Tanks No.5 to 7 1144 days Fri 29/04/11 Sun 15/06/14

93 Equipment and Material Delivery to Site 825 days Fri 29/04/11 Thu 01/08/13

94 Air Diffusers 0 days Thu 17/05/12 Thu 17/05/12

95 GRP Mixer Bridges 0 days Tue 11/09/12 Tue 11/09/12

96 Bridge Mounted Vertical Mixers 0 days Mon 27/08/12 Mon 27/08/12

97 MLR Pumps 0 days Tue 01/11/11 Tue 01/11/11

98 Submersible Mixers 0 days Tue 01/11/11 Tue 01/11/11

99 Water Spray Pumps 0 days Fri 13/05/11 Fri 13/05/11

100 Penstock & Actuators 0 days Thu 01/03/12 Thu 01/03/12

100%

100%

59%

99%

100%

100%

100%

100%

100%

22/03

99%

12%

0%

0%

0%

79%

0%

44%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

66%

85%

92%

0%

0%

0%

0%

0%

0%

56%

100%

01/12

25/02

25/02

01/03

56%

78%

100%

100%

62%

70%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

24%

100%

02/10

26/10

06/11

21/10

01/04

0%

04/02

15/07

15/07

29%

89%

0%

0%

0%

0%

0%

0%

0%

19%

0%

17/05

11/09

27/08

01/11

01/11

13/05

01/03

Apr '11 May '11 Jun '11 Jul '11 Aug '11 Sep '11 Oct '11 Nov '11 Dec '11 Jan '12 Feb '12 Mar '12 Apr '12 May '12 Jun '12 Jul '12 Aug '12 Sep '12 Oct '12 Nov '12 Dec '12 Jan '13 Feb '13 Mar '13 Apr '13 May '13 Jun '13 Jul '13 Aug '13 Sep '13 Oct '13 Nov '13 Dec '13 Jan '14 Feb '14 Mar '14 Apr '14 May '14 Jun '14 Jul '14 Aug '14 Sep '14 Oct '14

Q2 '11 Q3 '11 Q4 '11 Q1 '12 Q2 '12 Q3 '12 Q4 '12 Q1 '13 Q2 '13 Q3 '13 Q4 '13 Q1 '14 Q2 '14 Q3 '14

Critical

Critical Split

Critical Progress

Task

Split

Task Progress

Baseline

Baseline Split

Baseline Milestone

Milestone

Summary Progress

Summary

Project Summary

External Tasks

External Milestone

Deadline

DSD Contract : DE/2009/09Supply and Installation of Electrical and Mechanical Equipment for Tai Po Sewage Treatment Works Stage 5 Phase 2B

Section III Works Programme

Page 1

Rev. 4Date: 17 Jun 2013

Page 72: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1

ID Task Name Duration Start Finish

101 Instruments (EM Flowmeters, Air Flowmeters & Online Sensors) 0 days Fri 29/04/11 Fri 29/04/11

102 Pipework & Valves 0 days Sat 15/10/11 Sat 15/10/11

103 Lifting Appliance 0 days Thu 01/08/13 Thu 01/08/13

104 GMS Air Mains 0 days Tue 02/07/13 Tue 02/07/13

105 Site Possession / Available 277 days Fri 28/09/12 Tue 02/07/13

106 Interior Part of New Aeration Tank No.5 0 days Fri 28/09/12 Fri 28/09/12

107 Interior Part of New Aeration Tank No.6 0 days Mon 15/10/12 Mon 15/10/12

108 Steel Air Main Platforms, Walkway and Cable Trenches for New Aeration Tanks No.5, 6 & 7 0 days Tue 02/07/13 Tue 02/07/13

109 Interior Part of New Aeration Tank No.7 0 days Mon 22/04/13 Mon 22/04/13

110 Pipe Gallery Extension 0 days Tue 02/07/13 Tue 02/07/13

111 Installation 519 days Mon 15/10/12 Mon 17/03/14

112 New Aeration Tanks No.5 & 6 440 days Mon 15/10/12 Sat 28/12/13

113 GMS Air Mains & FRP Staircase 60 days Tue 02/07/13 Fri 30/08/13

114 Air Diffusers 120 days Mon 15/10/12 Mon 11/02/13

115 Air Pipework, Butterfly Valves & Air Flowmeters 60 days Sat 31/08/13 Tue 29/10/13

116 GRP Mixer Bridges 75 days Wed 02/01/13 Sun 17/03/13

117 Bridge Mounted Vertical Mixers 75 days Mon 18/03/13 Fri 31/05/13

118 Lifting Appliance 60 days Thu 01/08/13 Sun 29/09/13

119 MLR Pumps & Associated Pipework 60 days Mon 15/10/12 Thu 13/12/12

120 Submersible Mixers 30 days Tue 02/07/13 Wed 31/07/13

121 Water Spray Pumps & Associated Pipework 30 days Tue 02/07/13 Wed 31/07/13

122 Penstock & Actuators 45 days Mon 17/12/12 Wed 30/01/13

123 Instruments 30 days Tue 02/07/13 Wed 31/07/13

124 RAS Pipework in Pipe Gallery Extension 120 days Tue 02/07/13 Tue 29/10/13

125 Electrical Works 180 days Tue 02/07/13 Sat 28/12/13

126 SCADA/PLC System 120 days Sat 31/08/13 Sat 28/12/13

127 New Aeration Tanks No.7 330 days Mon 22/04/13 Mon 17/03/14

128 GMS Air Mains & FRP Staircase 60 days Tue 02/07/13 Fri 30/08/13

129 Air Diffusers 120 days Sat 31/08/13 Sat 28/12/13

130 Air Pipework, Butterfly Valves & Air Flowmeters 60 days Sun 29/12/13 Wed 26/02/14

131 GRP Mixer Bridges 120 days Mon 22/04/13 Mon 19/08/13

132 Bridge Mounted Vertical Mixers 45 days Tue 20/08/13 Thu 03/10/13

133 Lifting Appliance 60 days Thu 01/08/13 Sun 29/09/13

134 MLR Pumps & Associated Pipework 60 days Mon 30/09/13 Thu 28/11/13

135 Submersible Mixers 30 days Fri 29/11/13 Sat 28/12/13

136 Water Spray Pumps & Associated Pipework 30 days Sun 29/12/13 Mon 27/01/14

137 Penstock & Actuators 45 days Tue 02/07/13 Thu 15/08/13

138 Instruments 30 days Tue 28/01/14 Wed 26/02/14

139 RAS Pipework in Pipe Gallery Extension 120 days Tue 02/07/13 Tue 29/10/13

140 Electrical Works 180 days Thu 19/09/13 Mon 17/03/14

141 SCADA/PLC System 120 days Mon 18/11/13 Mon 17/03/14

142 MCC3 Ready 0 days Mon 13/01/14 Mon 13/01/14

143 Testing and Commissioning 90 days Tue 18/03/14 Sun 15/06/14

144

145

146 New Mixed Liquor Channels 849 days Tue 01/11/11 Wed 26/02/14

147 Equipment and Material Delivery to Site 639 days Tue 01/11/11 Thu 01/08/13

148 Foam Removal Collector 0 days Wed 01/05/13 Wed 01/05/13

149 Submersible Mixers 0 days Tue 01/11/11 Tue 01/11/11

150 Penstock & Actuator 0 days Thu 01/03/12 Thu 01/03/12

151 Lifting Appliance 0 days Thu 01/08/13 Thu 01/08/13

152 Pipework & Valves 0 days Wed 01/08/12 Wed 01/08/12

153 Local Control Panel 0 days Thu 01/08/13 Thu 01/08/13

154 Site Possession / Available 0 days Thu 01/08/13 Thu 01/08/13

155 Mixed Liquor Channel, Foam Channel & Pillar Box 0 days Thu 01/08/13 Thu 01/08/13

156 Bunded Area & Shelter for NaOCl Dosing System 0 days Thu 01/08/13 Thu 01/08/13

157 Installation 264 days Thu 09/05/13 Mon 27/01/14

158 Penstock & Actuactor in Flow Splitter Box 60 days Thu 01/08/13 Sun 29/09/13

159 Lifting Appliance 30 days Mon 30/09/13 Tue 29/10/13

160 Submersible Mixers 30 days Wed 30/10/13 Thu 28/11/13

161 Foam Removal Collector 26 days Thu 09/05/13 Mon 03/06/13

162 Water Spray System 15 days Fri 29/11/13 Fri 13/12/13

163 Relocation of Foam Transfer Pumps 30 days Fri 29/11/13 Sat 28/12/13

164 Relocation of NaOCl Dosing System 30 days Sun 29/12/13 Mon 27/01/14

165 Local Control Panel & Electrical Installation 90 days Wed 30/10/13 Mon 27/01/14

166 SCADA/PLC System 60 days Fri 29/11/13 Mon 27/01/14

167 Testing and Commissioning 30 days Tue 28/01/14 Wed 26/02/14

168

169

170 Existing Aeration Tanks No.1 to 4 1081 days Sat 15/10/11 Mon 29/09/14

171 Equipment and Material Delivery to Site 656 days Sat 15/10/11 Thu 01/08/13

172 GMS Air Mains 0 days Thu 01/08/13 Thu 01/08/13

173 Pipework & Valves 0 days Sat 15/10/11 Sat 15/10/11

174 Modification Works 425 days Thu 01/08/13 Mon 29/09/14

175 New Air Mains 364 days Thu 01/08/13 Wed 30/07/14

176 Steel Bridges (By Civil Contractor) Available for Air Mains 0 days Thu 01/08/13 Thu 01/08/13

177 GMS Air Mains Installation 61 days Thu 01/08/13 Mon 30/09/13

178 Connection Existing Air Mains beside RAS Pumping Station (By Civil Contractor) 30 days Tue 01/07/14 Wed 30/07/14

179 Aeration Tank No.4 91 days Mon 30/09/13 Mon 30/12/13

180 Tank Available for Modification (Drained Down by DSD/ST1) 0 days Mon 30/09/13 Mon 30/09/13

181 Air Pipework, Butterfly Valves & Air Flowmeters 60 days Tue 01/10/13 Fri 29/11/13

182 Electrical Installation 45 days Wed 16/10/13 Fri 29/11/13

183 Testing and Commissioning 31 days Sat 30/11/13 Mon 30/12/13

184 Aeration Tank No.3 91 days Mon 30/12/13 Mon 31/03/14

185 Tank Available for Modification (Drained Down by DSD/ST1) 0 days Mon 30/12/13 Mon 30/12/13

186 Air Pipework, Butterfly Valves & Air Flowmeters 60 days Tue 31/12/13 Fri 28/02/14

187 Electrical Installation 45 days Wed 15/01/14 Fri 28/02/14

188 Testing and Commissioning 31 days Sat 01/03/14 Mon 31/03/14

189 Aeration Tank No.2 91 days Mon 31/03/14 Mon 30/06/14

190 Tank Available for Modification (Drained Down by DSD/ST1) 0 days Mon 31/03/14 Mon 31/03/14

191 Air Pipework, Butterfly Valves, & Air Flowmeters 60 days Tue 01/04/14 Fri 30/05/14

192 Electrical Installation 45 days Wed 16/04/14 Fri 30/05/14

193 Testing and Commissioning 31 days Sat 31/05/14 Mon 30/06/14

194 Aeration Tank No.1 91 days Mon 30/06/14 Mon 29/09/14

195 Tank Available for Modification (Drained Down by DSD/ST1) 0 days Mon 30/06/14 Mon 30/06/14

196 Air Pipework, Butterfly Valves & Air Flowmeters 60 days Tue 01/07/14 Fri 29/08/14

197 Electrical Installation 45 days Wed 16/07/14 Fri 29/08/14

198 Testing and Commissioning 31 days Sat 30/08/14 Mon 29/09/14

199

200

29/04

15/10

01/08

02/07

0%

28/09

15/10

02/07

22/04

02/07

20%

35%

0%

100%

0%

100%

100%

0%

100%

0%

0%

100%

0%

0%

0%

0%

5%

0%

0%

0%

48%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

13/01

0%

6%

100%

01/05

01/11

01/03

01/08

01/08

01/08

01/08

01/08

01/08

7%

0%

0%

0%

100%

0%

0%

0%

0%

0%

0%

0%

0%

01/08

15/10

0%

0%

01/08

0%

0%

0%

30/09

0%

0%

0%

0%

30/12

0%

0%

0%

0%

31/03

0%

0%

0%

0%

30/06

0%

0%

0%

Apr '11 May '11 Jun '11 Jul '11 Aug '11 Sep '11 Oct '11 Nov '11 Dec '11 Jan '12 Feb '12 Mar '12 Apr '12 May '12 Jun '12 Jul '12 Aug '12 Sep '12 Oct '12 Nov '12 Dec '12 Jan '13 Feb '13 Mar '13 Apr '13 May '13 Jun '13 Jul '13 Aug '13 Sep '13 Oct '13 Nov '13 Dec '13 Jan '14 Feb '14 Mar '14 Apr '14 May '14 Jun '14 Jul '14 Aug '14 Sep '14 Oct '14

Q2 '11 Q3 '11 Q4 '11 Q1 '12 Q2 '12 Q3 '12 Q4 '12 Q1 '13 Q2 '13 Q3 '13 Q4 '13 Q1 '14 Q2 '14 Q3 '14

Critical

Critical Split

Critical Progress

Task

Split

Task Progress

Baseline

Baseline Split

Baseline Milestone

Milestone

Summary Progress

Summary

Project Summary

External Tasks

External Milestone

Deadline

DSD Contract : DE/2009/09Supply and Installation of Electrical and Mechanical Equipment for Tai Po Sewage Treatment Works Stage 5 Phase 2B

Section III Works Programme

Page 2

Rev. 4Date: 17 Jun 2013

Page 73: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1

ID Task Name Duration Start Finish

201 Filtrate Pumping System (Stage I/II Modification) 842 days Thu 25/08/11 Fri 13/12/13

202 Equipment and Material Delivery to Site 311 days Thu 25/08/11 Sun 01/07/12

203 Submersible Pump 0 days Thu 25/08/11 Thu 25/08/11

204 Pipework & Valves 0 days Sun 01/07/12 Sun 01/07/12

205 Site Possession / Available 0 days Thu 01/08/13 Thu 01/08/13

206 Underground Pipework to Stage IV Aeration Tanks (By Civil Contractor) 0 days Thu 01/08/13 Thu 01/08/13

207 Installation 448 days Thu 23/08/12 Wed 13/11/13

208 Pump Replacement & Pipework Modification at Existing Pump Chamber 45 days Thu 01/08/13 Sat 14/09/13

209 Filtrate Pipework Installation at Aeration Tanks 60 days Sun 15/09/13 Wed 13/11/13

210 Existing L.V. Switchboard Modification 6 days Thu 23/08/12 Tue 28/08/12

211 Electrical Installation 45 days Sun 15/09/13 Tue 29/10/13

212 Testing and Commissioning 30 days Thu 14/11/13 Fri 13/12/13

3%

100%

25/08

01/07

01/08

01/08

4%

0%

0%

100%

0%

0%

Apr '11 May '11 Jun '11 Jul '11 Aug '11 Sep '11 Oct '11 Nov '11 Dec '11 Jan '12 Feb '12 Mar '12 Apr '12 May '12 Jun '12 Jul '12 Aug '12 Sep '12 Oct '12 Nov '12 Dec '12 Jan '13 Feb '13 Mar '13 Apr '13 May '13 Jun '13 Jul '13 Aug '13 Sep '13 Oct '13 Nov '13 Dec '13 Jan '14 Feb '14 Mar '14 Apr '14 May '14 Jun '14 Jul '14 Aug '14 Sep '14 Oct '14

Q2 '11 Q3 '11 Q4 '11 Q1 '12 Q2 '12 Q3 '12 Q4 '12 Q1 '13 Q2 '13 Q3 '13 Q4 '13 Q1 '14 Q2 '14 Q3 '14

Critical

Critical Split

Critical Progress

Task

Split

Task Progress

Baseline

Baseline Split

Baseline Milestone

Milestone

Summary Progress

Summary

Project Summary

External Tasks

External Milestone

Deadline

DSD Contract : DE/2009/09Supply and Installation of Electrical and Mechanical Equipment for Tai Po Sewage Treatment Works Stage 5 Phase 2B

Section III Works Programme

Page 3

Rev. 4Date: 17 Jun 2013

Page 74: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1

ID Task Name Duration Start Finish

1 Section V of the Works 821 days Sat 22/01/11 Sun 21/04/13

2 EOT Granted 29.5 days Mon 22/04/13 Tue 21/05/13

3

4 Modification / Replacement of Existing L.V. Switchboard 998 days Sat 22/01/11 Tue 15/10/13

5 CBC G/F MCC 800 days Sat 22/01/11 Sun 31/03/13

6 Drawing Submission for CLP & DSD Approval 287 days Sat 22/01/11 Fri 04/11/11

7 Switchboard Manufacture & Delivery to Site 90 days Mon 02/01/12 Sat 31/03/12

8 Temporary Works Preparation 76 days Mon 16/01/12 Sat 31/03/12

9 Site Setup of Temporary Backup Facilities & Removal of Existing Switchboard 45 days Wed 11/04/12 Fri 25/05/12

10 Civil Modification Works (By Civil Contractor) 124 days Sat 26/05/12 Wed 26/09/12

11 New Switchboard Installation & SAT 76 days Thu 27/09/12 Tue 11/12/12

12 CLP's Tx Upgrading Works & Cable Connection to New Switchboard 43 days Sat 12/05/12 Tue 08/01/13

13 Removal of Existing Cables & Installation of New Cables 51 days Wed 09/01/13 Thu 28/02/13

14 Connect Permanent Power Supply for Existing Small Power D/B 14 days Mon 18/03/13 Sun 31/03/13

15

16 IW 1/F MCC1 508 days Sat 26/05/12 Tue 15/10/13

17 Switchboard Manufacture & Delivery to Site 107 days Sun 02/12/12 Mon 18/03/13

18 Temporary Works Preparation 61 days Sat 26/05/12 Wed 25/07/12

19 Temporary Works Installation 246 days Thu 26/07/12 Thu 28/03/13

20 Migration of Power/Control for Existing E&M Equipment to Temporary Panels 95 days Fri 29/03/13 Mon 01/07/13

21 Relocation of Existing Remote I/O Panel 31 days Sat 01/06/13 Mon 01/07/13

22 Removal of Existing Switchboard 7 days Tue 02/07/13 Mon 08/07/13

23 Civil Modification Works (By Civil Contractor) 21 days Tue 09/07/13 Mon 29/07/13

24 Modification of Exisiting Switchroom Partition 21 days Wed 25/09/13 Tue 15/10/13

25 New Switchboard Installation & SAT 21 days Tue 30/07/13 Mon 19/08/13

26 Migration of Power/Control of Existing E&M Equipment to New Switchboard 40 days Tue 20/08/13 Sat 28/09/13

27 Removal of Existing Cables & Installation of New Cables 14 days Sun 29/09/13 Sat 12/10/13

28

29 IW G/F MCC 987 days Sat 22/01/11 Fri 04/10/13

30 Drawing Submission for CLP & DSD Approval 175 days Sat 22/01/11 Fri 15/07/11

31 Switchboard Manufacture & Delivery to Site 223 days Sat 21/04/12 Thu 29/11/12

32 Completion of Genset Replacement 0 days Mon 15/04/13 Mon 15/04/13

33 Temporary Works Preparation 31 days Sat 25/05/13 Mon 24/06/13

34 Site Setup of Temporary Backup Facilities & Removal of Existing Switchboard 14 days Tue 25/06/13 Mon 08/07/13

35 Civil Modification Works (By Civil Contractor) 21 days Tue 09/07/13 Mon 29/07/13

36 New Switchboard Installation & SAT 60 days Tue 30/07/13 Fri 27/09/13

37 CLP's Tx Upgrading Works & Cable Connection to New Switchboard 45 days Wed 07/08/13 Fri 20/09/13

38 Removal of Existing Cables & Installation of New Cables 7 days Sat 28/09/13 Fri 04/10/13

39 Connect Power Supply for Existing Lighting & Small Power D/B 7 days Sat 28/09/13 Fri 04/10/13

40

41

42 Replacement of Emergency Genset for IW G/F MCC 333 days Fri 18/05/12 Mon 15/04/13

43 New 1500kVA Genset & Accessories Delivery to Site 0 days Mon 26/11/12 Mon 26/11/12

44 Site Setup of Power Backup Facilities by Tempoary Genset 50 days Fri 18/05/12 Fri 06/07/12

45 Removal of Existing 750kVA Genset 7 days Sat 07/07/12 Fri 13/07/12

46 Civil Modification Works (By Civil Contractor) 135 days Sat 14/07/12 Sun 25/11/12

47 Installation of New Genset & SAT 141 days Mon 26/11/12 Mon 15/04/13

48

49

50 Inlet Works 935 days Fri 29/04/11 Mon 18/11/13

51 Equipment and Material Deliver to Site 614 days Fri 29/04/11 Wed 02/01/13

52 Screw Pumps 0 days Wed 02/01/13 Wed 02/01/13

53 Mechanical Bar Screen 0 days Fri 19/10/12 Fri 19/10/12

54 Screw Conveyor 0 days Fri 19/10/12 Fri 19/10/12

55 Actuator for Existing Penstocks 0 days Mon 02/04/12 Mon 02/04/12

56 Ultrasonic Level Sensors 0 days Fri 29/04/11 Fri 29/04/11

57 Installation 336 days Fri 19/10/12 Thu 19/09/13

58 Temporary Flow Diversion for Lower Wet Well 30 days Tue 02/07/13 Wed 31/07/13

59 Screw Pump Installation & Screeding Works at Lower Wet Well 30 days Thu 01/08/13 Fri 30/08/13

60 Screw Pump Installation & Screeding Works at Upper Wet Well 195 days Wed 02/01/13 Mon 15/07/13

61 Installation of Mechanical Bar Screen, Screw Conveyor & Ultrasonic Level Sensors 286 days Fri 19/10/12 Wed 31/07/13

62 Installation of Actuators for Existing Penstocks 7 days Thu 25/07/13 Wed 31/07/13

63 Electrical Installation 60 days Mon 22/07/13 Thu 19/09/13

64 SCADA/PLC System 60 days Mon 22/07/13 Thu 19/09/13

65 Testing and Commissioning 60 days Fri 20/09/13 Mon 18/11/13

66

67

68 Filtrate Treatment Plant (SBR) 862 days Tue 01/11/11 Tue 11/03/14

69 Equipment and Material Delivery to Site 456 days Tue 01/11/11 Wed 30/01/13

70 Air Blower 0 days Wed 30/01/13 Wed 30/01/13

71 Filtrate Transfer Pump 0 days Wed 01/02/12 Wed 01/02/12

72 Filtrate Inlet Sump Pump 0 days Tue 01/11/11 Tue 01/11/11

73 Air Diffusers 0 days Thu 17/05/12 Thu 17/05/12

74 Pipework & Valves 0 days Tue 01/11/11 Tue 01/11/11

75 Site Possession / Available 123 days Sat 01/09/12 Thu 03/01/13

76 SBR Tank 0 days Thu 03/01/13 Thu 03/01/13

77 Civil Works Provision (By Civil Contractor) 0 days Sat 01/09/12 Sat 01/09/12

78 Existing Plant Rooms 0 days Mon 26/11/12 Mon 26/11/12

79 Installation 343 days Thu 03/01/13 Wed 11/12/13

80 Take Down of Existing Decanter 5 days Thu 03/01/13 Mon 07/01/13

81 Modification of Concrete Corbels & Cast-in Puddle Flanged Pipe (By Civil Contractor) 189 days Tue 08/01/13 Mon 15/07/13

82 Off-site Modification of Existing Decanter 28 days Tue 08/01/13 Mon 04/02/13

83 Installation of Modified Decanter 5 days Tue 16/07/13 Sat 20/07/13

84 Modification of Air Diffusers 60 days Tue 16/07/13 Fri 13/09/13

85 Installation of Air Blower, Filtrate Transfer Pump, Filtrate Inlet Sump Pump & Associated Pipework 183 days Wed 30/01/13 Wed 31/07/13

86 Existing L.V. Switchboard Modification 90 days Mon 15/07/13 Sat 12/10/13

87 Electrical Installation 60 days Sun 13/10/13 Wed 11/12/13

88 SCADA/PLC System 60 days Sun 13/10/13 Wed 11/12/13

89 Testing and Commissioning 90 days Thu 12/12/13 Tue 11/03/14

90

91

92 Primary Sludge Gravity Thickener 1016 days Tue 03/05/11 Tue 11/02/14

93 Equipment and Material Delivery to Site 699 days Tue 03/05/11 Mon 01/04/13

94 Knife Gate Valves & Actuators 0 days Tue 03/05/11 Tue 03/05/11

95 Deodorizing Unit, Extraction Fan & Accessories 0 days Fri 01/02/13 Fri 01/02/13

96 Pipework & Valves 0 days Mon 01/04/13 Mon 01/04/13

97 Air Ductwork & Accessories 0 days Mon 01/04/13 Mon 01/04/13

98 Local Control Panel for DO Unit 0 days Mon 01/04/13 Mon 01/04/13

99 CCTV System 0 days Mon 01/04/13 Mon 01/04/13

100 Site Possession / Available 0 days Thu 01/08/13 Thu 01/08/13

101 Decanting Chamber 0 days Thu 01/08/13 Thu 01/08/13

102 Concrete Plinth for DO System 0 days Thu 01/08/13 Thu 01/08/13

103 Civil Works Provision at Existing Valve Chamber (By Civil Contractor) 0 days Thu 01/08/13 Thu 01/08/13

104 Cable Drawpit & Ducts 0 days Thu 01/08/13 Thu 01/08/13

105 Installation 135 days Thu 01/08/13 Fri 13/12/13

106 Knife Gate Valves & Actuators 30 days Thu 01/08/13 Fri 30/08/13

107 Deodorizing Unit, Air Ductwork & Associated Accessories 90 days Sat 31/08/13 Thu 28/11/13

108 Pipework Installation at Existing Valve Chamber 15 days Fri 29/11/13 Fri 13/12/13

109 Electrical Installation 60 days Tue 15/10/13 Fri 13/12/13

110 CCTV Installation 30 days Thu 14/11/13 Fri 13/12/13

111 SCADA/PLC System 60 days Tue 15/10/13 Fri 13/12/13

112 Testing and Commissioning 60 days Sat 14/12/13 Tue 11/02/14

113

114

115 Biogas System 730 days Tue 01/11/11 Wed 30/10/13

116 Equipment and Material Delivery to Site 199 days Tue 01/11/11 Fri 18/05/12

117 Waste Gas Burner for Stage I/II 0 days Tue 03/01/12 Tue 03/01/12

118 Waste Gas Burner for Stage IV 0 days Fri 18/05/12 Fri 18/05/12

119 Biogas Holding Tank Materials 0 days Mon 19/12/11 Mon 19/12/11

120 Flame Arrestor and Condensation Pot 0 days Thu 01/12/11 Thu 01/12/11

121 Biogas Booster 0 days Tue 03/01/12 Tue 03/01/12

122 Pipework & Valves 0 days Tue 01/11/11 Tue 01/11/11

123 Site Possession / Available 347 days Thu 15/03/12 Mon 25/02/13

124 Biogas Holding Tank Concrete Slab 0 days Fri 16/03/12 Fri 16/03/12

125 Biogas Holding Tank Valve Chamber 0 days Fri 01/06/12 Fri 01/06/12

126 Gas Transfer Station 0 days Mon 25/02/13 Mon 25/02/13

127 Concrete Plinth for Waste Gas Burner in Stage I/II 0 days Thu 15/03/12 Thu 15/03/12

128 Concrete Plinth for Waste Gas Burner in Stage IV 0 days Wed 01/08/12 Wed 01/08/12

129 Concrete Plinth for Relocated DO in Stage I/II 0 days Thu 15/03/12 Thu 15/03/12

130 Installation 535 days Thu 15/03/12 Sat 31/08/13

131 Waste Gas Burner Installation in Stage I/II 90 days Thu 15/03/12 Tue 12/06/12

132 Waste Gas Burner Installation in Stage IV 91 days Wed 01/08/12 Tue 30/10/12

133 Dismantle of Existing Waste Gas Burner in Stage I/II 15 days Tue 02/07/13 Tue 16/07/13

134 Dismantle of Existing Waste Gas Burner in Stage IV 15 days Thu 31/05/12 Thu 14/06/12

135 Biogas Holding Tank Installation 482 days Mon 07/05/12 Sat 31/08/13

136 Installation in New Valve Chamber for New Biogas Holding Tank 90 days Sun 14/10/12 Fri 11/01/13

137 Installation in Existing Valve Chamber No.1 & 2 for Existing Biogas Holding Tank 60 days Thu 02/08/12 Sun 30/09/12

138 Installation in Pipe Gallery 60 days Thu 02/08/12 Sun 30/09/12

139 Installation in Gas Transfer Station 150 days Fri 01/03/13 Sun 28/07/13

140 Methane Gas Detection System Installation 60 days Thu 30/05/13 Sun 28/07/13

141 Testing and Commissioning 180 days Sat 04/05/13 Wed 30/10/13

142

143

144 Sludge Digestion Tank No.3 and Hot Water Circulation System 878 days Tue 01/11/11 Thu 27/03/14

145 Equipment and Material Delivery to Site 639 days Tue 01/11/11 Thu 01/08/13

146 Sludge Mixers 0 days Fri 25/01/13 Fri 25/01/13

147 Draft Tube & Cast-in Items 0 days Tue 09/04/13 Tue 09/04/13

148 GRP Platform for Sludge Mixers 0 days Thu 01/08/13 Thu 01/08/13

149 Hot Water Boiler 0 days Thu 02/05/13 Thu 02/05/13

150 Hot Water Recirculation Pump 0 days Mon 10/06/13 Mon 10/06/13

151 Heat Exchanger 0 days Tue 04/06/13 Tue 04/06/13

152 Pipework & Valves 0 days Wed 01/05/13 Wed 01/05/13

153 Flame Arrestor & Condensation Pot 0 days Tue 01/11/11 Tue 01/11/11

154 Inspection Window 0 days Tue 01/11/11 Tue 01/11/11

155 Pressure Vacuum Relief Valve c/w Flame Arrestor 0 days Tue 01/11/11 Tue 01/11/11

156 Site Possession / Available 0 days Thu 15/08/13 Thu 15/08/13

100%

100%

85%

100%

100%

100%

100%

100%

100%

100%

100%

100%

100%

77%

100%

100%

100%

85%

55%

0%

0%

0%

0%

0%

0%

72%

100%

100%

15/04

77%

0%

0%

0%

0%

0%

0%

100%

26/11

100%

100%

100%

100%

56%

100%

02/01

19/10

19/10

02/04

29/04

61%

0%

0%

86%

85%

0%

0%

0%

0%

43%

100%

30/01

01/02

01/11

17/05

01/11

100%

03/01

01/09

26/11

49%

100%

85%

100%

0%

0%

76%

0%

0%

0%

0%

0%

100%

03/05

01/02

01/04

01/04

01/04

01/04

01/08

01/08

01/08

01/08

01/08

0%

0%

0%

0%

0%

0%

0%

0%

76%

100%

03/01

18/05

19/12

01/12

03/01

01/11

100%

16/03

01/06

25/02

15/03

01/08

15/03

85%

100%

100%

0%

100%

84%

100%

100%

100%

73%

32%

25%

0%

0%

25/01

09/04

01/08

02/05

10/06

04/06

01/05

01/11

01/11

01/11

15/08

01 '11 02 '11 03 '11 04 '11 05 '11 06 '11 07 '11 08 '11 09 '11 10 '11 11 '11 12 '11 01 '12 02 '12 03 '12 04 '12 05 '12 06 '12 07 '12 08 '12 09 '12 10 '12 11 '12 12 '12 01 '13 02 '13 03 '13 04 '13 05 '13 06 '13 07 '13 08 '13 09 '13 10 '13 11 '13 12 '13 01 '14 02 '14 03 '14 04 '14

Q1 '11 Q2 '11 Q3 '11 Q4 '11 Q1 '12 Q2 '12 Q3 '12 Q4 '12 Q1 '13 Q2 '13 Q3 '13 Q4 '13 Q1 '14

Critical Critical Split Critical Progress Task Split Task Progress Baseline Baseline Split Baseline Milestone Milestone Summary Progress Summary Project Summary External Tasks External Milestone Deadline

DSD Contract : DE/2009/09Supply and Installation of Electrical and Mechanical Equipment for Tai Po Sewage Treatment Works Stage 5 Phase 2B

Section V Works Programme

Page 1

Rev. 5Date: 17 Jun 2013

Page 75: TABLE OF CONTENTS · 2013-12-27 · i TABLE OF CONTENTS Page EXECUTIVE SUMMARY ..... 1 Introduction ..... 1

ID Task Name Duration Start Finish

157 Sludge Digestion Tank No.3 0 days Thu 15/08/13 Thu 15/08/13

158 Site Works 269 days Tue 02/07/13 Thu 27/03/14

159 Hot Water Circulation System 175 days Tue 02/07/13 Mon 23/12/13

160 Temporary Works to Facilitate Civil Modification Works 30 days Tue 02/07/13 Wed 31/07/13

161 Civil Modification Works (By Civil Contractor) 30 days Thu 01/08/13 Fri 30/08/13

162 Installation of Hot Water Boiler, Recirculation Pump & Associated Pipework 85 days Sat 31/08/13 Sat 23/11/13

163 Electrical Installation (with Temporary MCC) 60 days Wed 25/09/13 Sat 23/11/13

164 SCADA/PLC System 60 days Wed 25/09/13 Sat 23/11/13

165 Testing and Commissioning 30 days Sun 24/11/13 Mon 23/12/13

166 Sludge Digestion Tank No.3 225 days Thu 15/08/13 Thu 27/03/14

167 Installation of Draft Tubes, Sludge Mixers, Heat Exchangers & Inspection Window 60 days Thu 15/08/13 Sun 13/10/13

168 Installation of GRP Platform 30 days Sun 29/09/13 Mon 28/10/13

169 Installation of Sludge, Biogas, Hot Water Recirculation, FeCl3 Dosing Pipework & Instruments 60 days Tue 29/10/13 Fri 27/12/13

170 Electrical Installation 90 days Sun 29/09/13 Fri 27/12/13

171 SCADA/PLC System 60 days Tue 29/10/13 Fri 27/12/13

172 Testing and Commissioning 90 days Sat 28/12/13 Thu 27/03/14

173

174

175 SAS Thickening System 607 days Thu 01/03/12 Mon 28/10/13

176 Equipment & Material Delivery to Site 285 days Thu 01/03/12 Tue 11/12/12

177 Centrifuge 0 days Mon 16/07/12 Mon 16/07/12

178 SAS Feed Pump 0 days Thu 30/08/12 Thu 30/08/12

179 Polyelectrolyte Feed Pump 0 days Thu 30/08/12 Thu 30/08/12

180 Thickened Sludge Storage Tank 0 days Tue 11/12/12 Tue 11/12/12

181 Pipework & Valves 0 days Fri 01/06/12 Fri 01/06/12

182 Vibration Monitoring System 0 days Thu 01/03/12 Thu 01/03/12

183 PLC System M Panel 0 days Fri 01/06/12 Fri 01/06/12

184 Site Possession / Available 0 days Fri 01/06/12 Fri 01/06/12

185 Civil Works Provision (By Civil Contractor) 0 days Fri 01/06/12 Fri 01/06/12

186 Installation 380 days Mon 16/07/12 Tue 30/07/13

187 Centrifuge, Vibration Monitoring System & Associated Accessories 30 days Mon 16/07/12 Tue 14/08/12

188 SAS Feed Pump & Associated Pipework 30 days Thu 30/08/12 Fri 28/09/12

189 Polyelectrolyte Feed Pump & Associated Pipework 16 days Sat 29/09/12 Sun 14/10/12

190 Thickened Sludge Storage Tank & Associated Accessories 30 days Tue 11/12/12 Wed 09/01/13

191 Centrate Pipework 16 days Thu 10/01/13 Fri 25/01/13

192 Existing L.V. Switchboard Modification 90 days Sat 03/11/12 Thu 31/01/13

193 Electrical Installation 90 days Fri 01/02/13 Wed 01/05/13

194 SCADA/PLC System 90 days Thu 02/05/13 Tue 30/07/13

195 Testing & Commissioning 90 days Wed 31/07/13 Mon 28/10/13

196

197

198 Sludge Dewatering System 694 days Thu 08/12/11 Thu 31/10/13

199 Equipment & Material Delivery to Site 115 days Thu 08/12/11 Sun 01/04/12

200 Membrane Filter Press 0 days Mon 20/02/12 Mon 20/02/12

201 Sludge Feed Pump 0 days Thu 08/12/11 Thu 08/12/11

202 Polyelectrolyte Dosing Pump 0 days Sun 01/04/12 Sun 01/04/12

203 Floctronic Sensor c/w Inline Mixer 0 days Fri 20/01/12 Fri 20/01/12

204 Pipework & Valves 0 days Sun 01/04/12 Sun 01/04/12

205 PLC System K Panel 0 days Sun 01/04/12 Sun 01/04/12

206 Site Possession / Available 0 days Sun 01/04/12 Sun 01/04/12

207 Civil Works Provision (By Civil Contractor) 0 days Sun 01/04/12 Sun 01/04/12

208 Installation 275 days Mon 27/02/12 Tue 27/11/12

209 Membrane Filter Press 79 days Mon 27/02/12 Tue 15/05/12

210 Sludge Feed Pump & Associated Pipework 30 days Wed 16/05/12 Thu 14/06/12

211 Polyelectrolyte Dosing Pump & Associated Pipework 30 days Fri 15/06/12 Sat 14/07/12

212 Filtrate Pipework 15 days Sun 15/07/12 Sun 29/07/12

213 Existing L.V. Switchboard Modification & Electrical Installation 90 days Fri 01/06/12 Wed 29/08/12

214 Electrical Installation 90 days Thu 30/08/12 Tue 27/11/12

215 SCADA/PLC System 60 days Sat 29/09/12 Tue 27/11/12

216 Testing and Commissioning 334 days Sun 02/12/12 Thu 31/10/13

217

218

219 Miscellaneous 90 days Thu 01/08/13 Tue 29/10/13

220 Hybrid Street Light Installation, Testing & Commissioning 90 days Thu 01/08/13 Tue 29/10/13

221 Automatic Weather Station Installation, Testing & Commissioning 90 days Thu 01/08/13 Tue 29/10/13

15/08

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

0%

72%

100%

16/07

30/08

30/08

11/12

01/06

01/03

01/06

01/06

01/06

89%

100%

100%

100%

100%

100%

100%

100%

52%

0%

81%

100%

20/02

08/12

01/04

20/01

01/04

01/04

01/04

01/04

100%

100%

100%

100%

100%

100%

100%

100%

59%

0%

0%

0%

01 '11 02 '11 03 '11 04 '11 05 '11 06 '11 07 '11 08 '11 09 '11 10 '11 11 '11 12 '11 01 '12 02 '12 03 '12 04 '12 05 '12 06 '12 07 '12 08 '12 09 '12 10 '12 11 '12 12 '12 01 '13 02 '13 03 '13 04 '13 05 '13 06 '13 07 '13 08 '13 09 '13 10 '13 11 '13 12 '13 01 '14 02 '14 03 '14 04 '14

Q1 '11 Q2 '11 Q3 '11 Q4 '11 Q1 '12 Q2 '12 Q3 '12 Q4 '12 Q1 '13 Q2 '13 Q3 '13 Q4 '13 Q1 '14

Critical Critical Split Critical Progress Task Split Task Progress Baseline Baseline Split Baseline Milestone Milestone Summary Progress Summary Project Summary External Tasks External Milestone Deadline

DSD Contract : DE/2009/09Supply and Installation of Electrical and Mechanical Equipment for Tai Po Sewage Treatment Works Stage 5 Phase 2B

Section V Works Programme

Page 2

Rev. 5Date: 17 Jun 2013