Operational Environmental Management Plan Revision I.0 Clyde Transfer Terminal February 2010 CONTENTS i TABLE OF CONTENTS 1. INTRODUCTION ................................................................................... 1-1 1.1. Introduction ............................................................................................. 1-1 1.2. Related Documents ................................................................................ 1-2 1.3. Conditions of Consent............................................................................. 1-3 1.4. Objectives ............................................................................................... 1-4 2. SITE OVERVIEW .................................................................................. 2-1 2.1. Property Description ............................................................................... 2-1 2.2. Transfer Terminal Description ................................................................. 2-1 2.2.1. Transfer Building .......................................................................................... 2-1 2.2.2. Office and Amenities .................................................................................... 2-2 2.2.3. Entrance/Exit Road....................................................................................... 2-2 2.2.4. Weighbridge Office and Weighbridge ........................................................... 2-2 2.2.5. Stormwater Oil/Silt Separator and Retention Pond ...................................... 2-2 2.2.6. Car Parking Area .......................................................................................... 2-2 2.3. Bio Physical Environmental Characteristics ............................................ 2-2 2.3.1. Soils .............................................................................................................. 2-2 2.3.2. Flooding and Drainage ................................................................................. 2-3 2.3.3. Flora and Fauna ........................................................................................... 2-4 2.4. Socio Economic Environmental Characteristics ...................................... 2-4 2.4.1. Non-Indigenous Heritage.............................................................................. 2-4 2.4.2. Noise............................................................................................................. 2-4 2.4.3. Air Quality ..................................................................................................... 2-5 2.4.4. Traffic and Transport .................................................................................... 2-6 2.4.5. Visual Assessment ....................................................................................... 2-6 3. REGULATORY AND REPORTING REQUIREMENTS ......................... 3-1 3.1. Consent Conditions................................................................................. 3-1 3.2. Legislative Requirements ........................................................................ 3-1 3.3. Reporting Requirements ......................................................................... 3-2 3.3.1. Environmental Monitoring ............................................................................. 3-2 3.3.2. Development Consent .................................................................................. 3-2 3.3.3. Environment Protection Licence ................................................................... 3-3 3.3.4. Reporting Summary...................................................................................... 3-4 3.3.5. Identification of Potential Adverse Environmental Impacts .......................... 3-4 3.3.6. National Integrated Management System .................................................... 3-5 3.4. Community Liaison and Complaints Handling ......................................... 3-6 3.4.1. Community Consultative Committee ............................................................ 3-6 3.4.2. Additional Community Liaison ...................................................................... 3-7 3.4.3. Complaints Handling Procedure ................................................................... 3-7 3.4.4. Corrective Action .......................................................................................... 3-8 4. IMPLEMENTATION OF THE OEMP ..................................................... 4-1 4.1. Roles and Responsibilities ...................................................................... 4-1 4.2. Induction and Training ............................................................................ 4-3 4.2.1. General Induction ......................................................................................... 4-3 4.2.2. Site Training ................................................................................................. 4-4 4.3. Communication ....................................................................................... 4-5 4.4. Review of OEMP .................................................................................... 4-6 5. SUPPORTING MANAGEMENT PLANS ............................................... 5-1 5.1. Waste Management Plan ........................................................................ 5-1 5.2. Odour Management Plan ........................................................................ 5-1 5.3. Dust Management Plan .......................................................................... 5-1 5.4. Traffic Management Plan ........................................................................ 5-1 5.5. Vermin and Pest Control Plan ................................................................. 5-1 5.6. Stormwater Management Plan................................................................ 5-2 5.7. Site Contamination Management Plan .................................................... 5-2

Upload: doandiep

Post on 09-Mar-2018

222 views

Category:

Documents


3 download

TRANSCRIPT

  • Operational Environmental Management Plan Revision I.0 Clyde Transfer Terminal February 2010 CONTENTS i

    TABLE OF CONTENTS 1. INTRODUCTION ................................................................................... 1-1

    1.1. Introduction ............................................................................................. 1-1 1.2. Related Documents ................................................................................ 1-2 1.3. Conditions of Consent ............................................................................. 1-3 1.4. Objectives ............................................................................................... 1-4

    2. SITE OVERVIEW .................................................................................. 2-1 2.1. Property Description ............................................................................... 2-1 2.2. Transfer Terminal Description ................................................................. 2-1

    2.2.1. Transfer Building .......................................................................................... 2-1 2.2.2. Office and Amenities .................................................................................... 2-2 2.2.3. Entrance/Exit Road ....................................................................................... 2-2 2.2.4. Weighbridge Office and Weighbridge ........................................................... 2-2 2.2.5. Stormwater Oil/Silt Separator and Retention Pond ...................................... 2-2 2.2.6. Car Parking Area .......................................................................................... 2-2

    2.3. Bio Physical Environmental Characteristics ............................................ 2-2 2.3.1. Soils .............................................................................................................. 2-2 2.3.2. Flooding and Drainage ................................................................................. 2-3 2.3.3. Flora and Fauna ........................................................................................... 2-4

    2.4. Socio Economic Environmental Characteristics ...................................... 2-4 2.4.1. Non-Indigenous Heritage.............................................................................. 2-4 2.4.2. Noise ............................................................................................................. 2-4 2.4.3. Air Quality ..................................................................................................... 2-5 2.4.4. Traffic and Transport .................................................................................... 2-6 2.4.5. Visual Assessment ....................................................................................... 2-6

    3. REGULATORY AND REPORTING REQUIREMENTS ......................... 3-1 3.1. Consent Conditions................................................................................. 3-1 3.2. Legislative Requirements ........................................................................ 3-1 3.3. Reporting Requirements ......................................................................... 3-2

    3.3.1. Environmental Monitoring ............................................................................. 3-2 3.3.2. Development Consent .................................................................................. 3-2 3.3.3. Environment Protection Licence ................................................................... 3-3 3.3.4. Reporting Summary ...................................................................................... 3-4 3.3.5. Identification of Potential Adverse Environmental Impacts .......................... 3-4 3.3.6. National Integrated Management System .................................................... 3-5

    3.4. Community Liaison and Complaints Handling ......................................... 3-6 3.4.1. Community Consultative Committee ............................................................ 3-6 3.4.2. Additional Community Liaison ...................................................................... 3-7 3.4.3. Complaints Handling Procedure ................................................................... 3-7 3.4.4. Corrective Action .......................................................................................... 3-8

    4. IMPLEMENTATION OF THE OEMP ..................................................... 4-1 4.1. Roles and Responsibilities ...................................................................... 4-1 4.2. Induction and Training ............................................................................ 4-3

    4.2.1. General Induction ......................................................................................... 4-3 4.2.2. Site Training ................................................................................................. 4-4

    4.3. Communication ....................................................................................... 4-5 4.4. Review of OEMP .................................................................................... 4-6

    5. SUPPORTING MANAGEMENT PLANS ............................................... 5-1 5.1. Waste Management Plan ........................................................................ 5-1 5.2. Odour Management Plan ........................................................................ 5-1 5.3. Dust Management Plan .......................................................................... 5-1 5.4. Traffic Management Plan ........................................................................ 5-1 5.5. Vermin and Pest Control Plan ................................................................. 5-1 5.6. Stormwater Management Plan ................................................................ 5-2 5.7. Site Contamination Management Plan .................................................... 5-2

  • Operational Environmental Management Plan Revision I.0 Clyde Transfer Terminal February 2010 CONTENTS ii

    5.8. Incident Response Plan .......................................................................... 5-2 5.9. Noise Management Plan ......................................................................... 5-2

  • Operational Environmental Management Plan Revision I.0 Clyde Transfer Terminal February 2010 SECTION 1 INTRODUCTION 1-1

    1. INTRODUCTION

    1.1. Introduction

    The Clyde Waste Transfer Terminal (Special Provisions) Act 2003 (the Clyde Act)

    grants Development Consent with 128 Conditions of Consent (COCs) stipulating the

    requirements for the operation of the Clyde Transfer Terminal (the Terminal) at the

    Clyde Marshalling Yards in Auburn. A site location plan is provided in Appendix A.

    In accordance with Section 78A of the Environmental Planning and Assessment Act

    (EP&A), a Development Application (DA) was submitted to the Department of

    Planning (DOP), supported with an Environmental Impact Statement (EIS) prepared

    for public exhibition (between 30 August 2001 and 22 October 2001) allowing

    members of the community, interest groups and government agencies to view and

    make written submissions on the proposed development. Following the exhibition

    period, the issues raised by the public and stakeholders were considered and a

    number of improvements to the design were made. The modifications to the design

    and associated improvements were outlined in the Supplementary Environmental

    Impact Statement (SEIS) (exhibited between 04 February 2002 and 01 March 2002).

    Under section 91 of the EP&A Amendment Act the Terminal is also classified as an

    Integrated Development because operational licensing is required under the

    Protection of the Environment Operations Act, 1997 (POEO) and the Roads Act,

    1993. The licensing requirements are detailed in Section 3 of this report. The

    operation of the Terminal includes:

    Seven (7) days a week, 24 hour operation, entry to the site will be via a left turn

    only for both in and out movements at Parramatta Road, including the use of

    weighbridges;

    Receiving of 400,000 tonnes per annum of putrescible waste onto the floor of the

    Transfer Terminal building; and

    Loading of waste into the compactors via a chute, to form a slug of compacted

    waste. The slug will be pushed into a modified 40 foot shipping container;

  • Operational Environmental Management Plan Revision I.0 Clyde Transfer Terminal February 2010 SECTION 1 INTRODUCTION 1-2

    Other activities related to, but not operated as part of the Terminal include:

    Loading of containers onto trains for transport to the Woodlawn Intermodal

    Facility;

    Unloading of containers at the Intermodal Facility and transporting them by road to

    the Woodlawn Bioreactor site, for disposal; and

    Loading of empty containers back onto the train to return to the Terminal for

    reloading.

    This Operation Environmental Management Plan (OEMP) has been prepared in

    conjunction with the Environmental Protection Licence (EPL) to fulfil the requirements

    of the COCs relating to the operation of the Terminal. The EPL and COCs are

    provided in this OEMP as Appendix B and Appendix C respectively. In accordance

    with Condition 17 of the COCs a Pre-Operation Compliance Report that details the

    compliance with each COC relating to the operational activities of the Terminal is

    provided in Appendix D. Environmental monitoring at the Terminal is conducted in

    accordance with the Environmental Monitoring Program, which has been prepared to