task with durations
DESCRIPTION
construction task with durationsTRANSCRIPT
Task Name Duration
Install conduit at ceiling 4 wks
Install duct in ceiling 4 wks
3 wks
4 wks
20 days
12 wks
4 wks
Install Gypsum board ceiling to Toilets & lift lobbies
Install Acoustic Metal Panel ceiling to Office & meeting rooms
Install Toilet accessories & sanitary fixtures
Complete interior and exterior sod and plantings
Pave, curb, and stripe parking lot