Task Name Duration 4 wks 4 wks 3 wks 4 wks 20 days 12 wks 4 wks Install conduit at ceiling Install duct in ceiling Install Gypsum board ceiling to Toilets & lift lobbies Install Acoustic Metal Panel ceiling to Office & meeting rooms Install Toilet accessories & sanitary fixtures Complete interior and exterior sod and plantings Pave, curb, and stripe parking lot

Upload: smsajjad-haider-naqvi

Post on 16-Jan-2016

214 views

Category:

Documents


0 download

DESCRIPTION

construction task with durations

TRANSCRIPT

Page 1: task with durations

Task Name Duration

Install conduit at ceiling 4 wks

Install duct in ceiling 4 wks

3 wks

4 wks

20 days

12 wks

4 wks

Install Gypsum board ceiling to Toilets & lift lobbies

Install Acoustic Metal Panel ceiling to Office & meeting rooms

Install Toilet accessories & sanitary fixtures

Complete interior and exterior sod and plantings

Pave, curb, and stripe parking lot