TBM main beam support design
Alex Vamvakas
31/10/18
Considerations
• Independent girders
• Lower cost
• Easy to assemble and install
• Integrated features
Girder section preliminary design
• Steel
• Standard rectangular hollow section
• 250*150*12mm
• 100kg/2m
• Supported in • 2 points – Gaussian points
• 3 points – extremities and middle
250 mm
150 mm
12 mm
3 points suport
• 3 vertical support points• Minimizing sag
• Combination of movement allows for roll and pitch control
• 2 transversal points• Close to the extremities to maximize
resolution
• 1 longitudinal point• In the middle
• Active or not
Degrees of freedom
2 point support
• 27um max sag
• Eigen frequencies:• 134.71
• 182.73
• 300.03
• 320.13
• 435.15
• 511.12
3 point support
• 5um max sag
• Eigen frequencies:• 199.14
• 300.85
• 477.83
• 495.92
• 523.5
• 555.42
K-module
• New girder and actuators
• Adjustable support for every SAS
• Spiral loads
• New compact loads for RF network
Courtesy Y. Cuvet
Integrated movers
• Movers are integrated on the girder
• Flexure based joints
• WPS are attached directly on the girder
• WPS need to open diagonally or supported slightly differently
Vertical DoF
Horizontal DoF
Vertical installation
• Movers are assembled on the girder beforehand
• Minimizing work in the tunnel
• One single connection for electronics
• One single connection for cooling
Top plate remains attached on the girder
Wires are not disturbed
Ground plate
SAS adjustable support
• 6 DoF support based on flexures and wedges
Courtesy J. Vainola
2 beam module
• Support system is identical
• Adjustable supports on DBQs
• PETS are fixed
• New components are introduced here as well
2 beam module
• Height reduced to 1m from 1.2m
• Waveguides need further layout optimization
Common RF
Common RF girder
• RF unit with pre-assembled SAS, PETS, girder and actuators
• 3 supporting points
• DBQ on active support
• DBQ is supported on the same plate
Common RF girder
• WPS directly on the girder, close to the beam line
• Whole assembly removed vertically