T D S UNIT DISCRIPTION 34.5 m 31.4 m CL girth of wall foundation 65.9 m 11.73 Site vegetaion, clearing & top soil removal 8.83 103.47 m2 -1.00 3.00 ddt 2.00 -6.00 m2 97.47 m2 Total area Excavation Excavation for coumn foundation 11.00 0.60 0.60 0.76 3.01 m3 Excavation for wall foundation 65.90 0.49 0.57 18.42 m3 21.43 m3 Total excavation work Filling 4.38 Under floor slab 3.78 24.77 m2 3.78 3.78 21.38 m2 3.78 3.18 17.98 m2 5.28 2.78 21.96 m2 5.38 3.28 26.40 m2 112.49 m2 112.49 Total filling under floor slab

Upload: indrajith-jeewan-kumara-perera

Post on 05-Jan-2016

212 views

Category:

Documents


0 download

DESCRIPTION

Times Dimension Sum

TRANSCRIPT

Page 1: Tds

T D S UNIT DISCRIPTION

34.5 m

31.4 m

CL girth of wall foundation

65.9 m

11.73 Site vegetaion, clearing & top soil removal

8.83 103.47 m2

-1.00 3.00 ddt

2.00 -6.00 m2

97.47 m2 Total area

Excavation

Excavation for coumn foundation

11.00 0.60

0.60

0.76 3.01 m3

Excavation for wall foundation

65.90

0.49

0.57 18.42 m3

21.43 m3 Total excavation work

Filling

4.38 Under floor slab

3.78 24.77 m2

3.78

3.78 21.38 m2

3.78

3.18 17.98 m2

5.28

2.78 21.96 m2

5.38

3.28 26.40 m2

112.49 m2

112.49 Total filling under floor slab

Page 2: Tds

0.08

1.00

8.44 m3

2.00 65.90 To wall foundation

0.23

0.05

2.31 m3

2.00 65.90

0.06

0.08

0.86 m3

3.17 m3 Total filling to wall foundation

11.00 0.60 To column foundation

0.60

0.46 2.73 m3

Ddt

-11.00 0.23 Column shafts

0.23

0.46 -0.38 m3

2.35 m3 Total filling to coulmn foundation

13.96 m3 Total Filling work

11.73 Termite treatment

8.83 103.47 m2

-1.00 3.00

2.00 -6.00 m2

-1.00 65.90

0.23 -14.83 m2

82.65 m2

Concrete Work

Up to ground floor level

11.00 0.60 75mm tk lean concrete in coulmn base

0.60

0.08 0.30 m3

65.90 75mm tk lean concrte in wall foundation

0.38

0.08 1.86 m3

11.00 0.60 RCC concrete in coulmn base

0.60

Page 3: Tds

0.23 0.89 m3

11.00 0.23 RCC concrete in coulmn shafts

0.23

0.46 0.26 m3

65.90 RCC concrete in plinth beam

0.23

0.23 3.34 m3

Ground floor level to roof ridge level

82.65 75 tk mass concrete in ground floor slab

0.08 6.20 m3

11.00 0.23 In columns

0.23

2.45 1.36 m3

In beams

16.80 225 x 400 mm beam

0.23

0.40 1.51 m3

41.20 225 x 375 mm beam

0.23

0.38 3.48 m3

3.00 225 x 300 mm beam

0.23

0.30 0.20 m3

5.19 Total in beams

Reinforcment

Up to ground floor level

88.00 0.55 In column base

0.63 30.49 kg y10 @ 730mm c/c

cover 25 mm

44.00 0.75 In column shafts

0.89 29.37 kg 4y12, R6 @150mm c/c

cover 30mm

42.46 0.70

0.22 6.60 kg

4.00 65.90 In plinth beam

0.89 234.60 kg cover 25mm

433.33 0.35

0.22 33.67 kg

Ground floor level to roof ridge level

44.00 2.45 In columns

Page 4: Tds

0.89 95.94 kg

179.67 0.70

0.22 27.92 kg

In beams

4.00 16.80 225 x 400 mm beam

0.89 59.81 kg

4.00 41.20 225 x 375 mm beam

0.89 146.67 kg

4.00 3.00 225 x 300 mm beam

0.89 10.68 kg

112.00 1.25 225 x 400 mm beam

0.22 31.08 kg

274.67 1.20 225 x 375 mm beam

0.22 72.51 kg

20.00 1.05 225 x 300 mm beam

0.22 4.62 kg

Form work

44.00 0.30 Sides of coulmn bases

0.60 7.92 m2

44.00 0.23 Column up to gf level

0.39 3.81 m2

2.00 65.90 In plinth beam

0.23 29.66 m2

44.00 0.23 In Columns above ground floor level

2.45 24.26 m2

In Beams

16.80 225 x 400 mm beam

1.25 21.00 m2

41.20 225 x 375 mm beam

1.20 49.44 m2

3.00 225 x 300 mm beam

1.05 3.15 m2

73.59 Total in beams

139.23 m2 Total Form work

65.90 Brick Masonry Work

3.05 201.00

Page 5: Tds

1.50 8.60

1.46 18.85

1.00 5.60

1.46 8.18

1.00 9.50

3.05 28.98

1.00 5.50

4.07 22.39

1.00 4.00

4.21 16.82

1.00 4.00

4.41 17.64

Ddt

-2.00 1.00 Doors

2.45 -4.90

-1.00 1.50

2.45 -3.68

-3.00 2.50 windows

2.45 -18.38

-3.00 3.00

2.45 -22.05

-1.00 4.00

2.45 -9.80

-1.00 1.00

0.85 -0.85

-1.00 1.00 Openings

2.45 -2.45

251.75 m2 Total Brick Masonry work

65.90 RRM

0.28

0.49 11.83

65.90

0.15

0.38 4.84

16.67 m3 Total RRM

Floor Finishes

82.65 Floor Tilling

1.00 82.65

Page 6: Tds

ddt

-1.00 3.78 bathroom area

1.98 -7.46

75.19 Total tilling area

3.78 Bathroom floor tilling

1.98 7.46

Wall Finishes

11.50 Bathroom wall tilling

2.05 23.58

wall plastering

2.00 11.50 External wall

8.60 197.80

2.00 8.60

1.46 25.13

ddt

-3.00 3.00

2.45 -22.05

-3.00 2.50

2.45 -18.38

4.00

2.45 -9.80

2.00

2.45 -4.90

-1.00 1.00

0.85 -0.85

-2.00 1.00

2.45 -4.90

162.05 Total Ext. Plastering

2.00 251.75 Internal Plastering

1.00 503.50 m2

Ddt

162.05 Ext.plastering

1.00 -162.05

341.44 Total Internal plastering

Painting

Page 7: Tds

162.05 External

1.00 162.05

341.44 Inetrnal

1.00 341.44

Ddt

11.50 Bathroom wall tilling area

2.05 -23.58

317.87 Total internal painting