technical and economic considerations in selection of boiler size and thermal storage capacity for...
TRANSCRIPT
Technical and Economic Considerations In
Selection of Boiler Size and Thermal Storage CapacityFor
Commercial and Small Industrial Wood-fired Boiler Systems
“Small can be beautiful”
Raymond J Albrecht, P.E.
Technical Consultant to Lopper North America
www.LopperNorthAmerica.com
Typical Wood Boiler Oversizing Impacts
Oversizing factor of 2 X or even 3 X peak heating load
Increased space requirements within boiler room
Capital cost premium for boiler, fuel feeding components, multi-cyclones and electrofilters, etc.
Efficiency penalty during start-ups for morning heat during Fall/Spring seasons
Excess hours for low load operating conditions (smoldering) with increased PM 2.5 and UHC/CO emissions due to lower average flame temperature
Tool for sizing of wood boilers: ASHRAE Weather DataAmerican Society of Heating, Refrigerating and Air-conditioning Engineers
Thousands of US/Canada and global locations
Averages and maximum/minimum values
Temperatures
Bin hour temperature data
Humidity
Wind Speed
Solar Radiation
Available at www.ashrae.org website
Heating Bin Hours vs. Outdoor Temperature
Typical northern US location
Design Temp = Minus 5 deg F
4800 hours per year at 55 deg For lower
3900 hours occur between 25oF and 55 deg F
80% of heating hours at 50%or less of peak heating load
Wood-fired boiler sized to provide 100% of peak heating load
Output Analysis - 2 MMBTU/hr wood-fired boiler for entire heating load
Temp bin Annual Heating Wood boiler Oil boiler Total heating Wood boiler Oil boiler(deg F) hours Load output in bin output in bin output in bin output in bin output in bin
in bin Btu/hr BTU/hr BTU/hr MMBTU/yr MMBTU/yr MMBTU/yr
-5/-1 6 1917000 1917000 - 12 12 -
0/4 58 1750000 1750000 - 101 101 - 5/9 66 1583000 1583000 - 104 104 -
10/14 125 1417000 1417000 - 177 177 -
15/19 243 1250000 1250000 - 304 304 -
20/24 354 1083000 1083000 - 383 383 -
25/29 511 917000 917000 - 468 468 -
30/34 957 750000 750000 - 718 718 -
35/39 720 583000 583000 - 420 420 -
40/44 636 417000 417000 - 265 265 -
45/49 577 250000 250000 - 144 144 -
50/54 585 83000 83000 - 48 48 -
Totals 4838 hrs 3144 3144
Wood-fired output = 3144/3144 = 100 percent of total system output
Heating oil savings = Approximately 38,000 gallons
Wood boiler meets 100% of peak heating load
Wood boiler provides 100% of annual heating output
Wood-fired boiler sized to provide 75% of peak heating load
Can meet heating load down to about 10 deg F
Supplemental boiler provides output only for portion of heating load in excess of 1.5 MM Btu/hr at temperatures below 10 deg F
Output Analysis - 1.5 MMBTU/hr wood-fired boiler plus 500,000 Btu/hr Oil-fired Boiler
Temp bin Annual Heating Wood boiler Oil boiler Total heating Wood boiler Oil boiler(deg F) hours Load output in bin output in bin output in bin output in bin output in bin
in bin Btu/hr BTU/hr BTU/hr MMBTU/yr MMBTU/yr MMBTU/yr
-5/-1 6 1917000 1500000 417000 12 9 3
0/4 58 1750000 1500000 250000 101 87 14 5/9 66 1583000 1500000 83000 104 99 5
10/14 125 1417000 1417000 - 177 177 -
15/19 243 1250000 1250000 - 304 304 -
20/24 354 1083000 1083000 - 383 383 -
25/29 511 917000 917000 - 468 468 -
30/34 957 750000 750000 - 718 718 -
35/39 720 583000 583000 - 420 420 -
40/44 636 417000 417000 - 265 265 -
45/49 577 250000 250000 - 144 144 -
50/54 585 83000 83000 - 48 48 -
Totals 4838 hrs 3144 3122 22
Wood-fired output = 3122/3144 = 99 percent of total system output
Wood boiler meets 75% of peak heating load
Wood boiler provides 99% of annual heating output
Can meet heating load down to about 20 deg F
Supplemental boiler provides output only for portion of heating load in excess of 1 MM Btu/hr during temperatures below 20 deg F
Wood-fired boiler sized to provide 50% of peak heating load
Output Analysis - 1 MM BTU/hr wood-fired boiler plus 1 MM Btu/hr oil-fired boiler
Temp bin Annual Heating Wood boiler Oil boiler Total heating Wood boiler Oil boiler(deg F) hours Load output in bin output in bin output in bin output in bin output in bin
in bin Btu/hr BTU/hr BTU/hr MMBTU/yr MMBTU/yr MMBTU/yr
-5/-1 6 1917000 1000000 917000 12 6 6
0/4 58 1750000 1000000 750000 101 58 43 5/9 66 1583000 1000000 583000 104 66 38
10/14 125 1417000 1000000 417000 177 125 52
15/19 243 1250000 1000000 250000 304 243 61
20/24 354 1083000 1000000 83000 383 354 29
25/29 511 917000 917000 - 468 468 -
30/34 957 750000 750000 - 718 718 -
35/39 720 583000 583000 - 420 420 -
40/44 636 417000 417000 - 265 265 -
45/49 577 250000 250000 - 144 144 -
50/54 585 83000 83000 - 48 48 -
Totals 4838 hrs 3144 2915 229
Wood-fired output = 2915/3144 = 93 percent of total system output
Wood boiler meets 50% of peak heating load
Wood boiler provides 93% of annual heating output
Heating Output vs Wood and Oil Boiler Capacity
Horizontal Axis: Wood Boiler Capacity – Percent of Peak Heating Load
Vertical Axis: RED Percent of Annual Wood Heating Output (also percent Oil Savings)
BLUE Percent of Annual Oil Heating Output
Percent PercentOf Peak Of AnnualHeating Heating Output/Load Oil Savings
25% 63%
50% 93%
75% 99%
100% 100%
125% 100%
150% 100%
175% 100%
200% 100%
Eliminating the Smoldering Mode
300 kW wood-fired boiler plus 150 kW wood-fired boiler plus 150 kW oil-fired boiler for Peak and Low Loads
Use oil -fired boiler until heating load reaches at least 20-30 percent of capacity of smaller boiler (i.e., about 50 kW) depending on thermal storage
“On” temperature for wood-fired boiler about 10 deg C
Wood-fired boiler still provides 95% of total annual output
Thermal Storage
1 BTU = 1 lb Water X 1 deg F delta T
Typical practical delta T = Approximately 40 to 60 deg F
One gallon Water = 8.33 lbs
100 gallons Water X delta T of 40 deg F = 33,320 BTU of thermal storage
500 gallons Water X delta T of 60 deg F = 250,000 BTU of thermal storage
20,000 gallons Water X delta T of 40 deg F = 6,650,000 BTU of thermal storage
20,000 gallons Water = 2666 ft3 = Tank dimensions of 18 ft L X 18 ft W x 8 ft H
Case Study: Large Institutional Logwood-fired Boiler System
Abbey of St Benoit du Lac
St Benoit du Lac, QuebecCanada
Twin Commercial Size Logwood-fired Boilers
Ultra-low PM 2.5 emissions (0.01 to 0.02 lb/MMBtu )
Less than 100 ppm NOx
82 – 84 percent efficiency (HHV)
Lambda (air/fuel ratio) control with independent primary and secondary air flow control
Vertical extension to primary gasification chamber to double wood loading capacity up to 16 hours full-capacity burn time
Decoupling of wood loading capacity from firing capacity important factor in meeting user interest in reduced frequency of reloading
Each boiler has 1.1 million BTU/hr (320 kW) thermal capacity
Total thermal capacity of 2.2 million BTU/hr (640 kW)
Peak heating load is about 2.5 million BTU/hr (730 kW)
Approximately 150,000 square feet of heated space
Storage Tank
Benefits include smoother boiler loads plus pre-charging to handle peak heating loads
Approximately 6000 gallons
6000 gal X 8.33 lb/gal X 40 deg F delta T =
2 million Btu storage capacity
Can boost system capacity by 500,000 Btu/hr for 4 hrs during peak morning loads
Storage barns for logwood
350 cords per year
One year drying time
Steel racks for logwood bundles
Boilers can handle up to 48 inch log lengths
Approximately 1/3 cord wood per bundle
One logwood bundle provides for 8 hours of boiler operation under full-load conditions
Boilers can handle two bundles maximum wood loading
Tractor loading of logwood bundles
Tractor with front end loader carries logwood bundles from storage barn to boiler house
System includes small overhead crane
Bundle is lowered into top loading door
Chains are then released and removed with bracket assembly
Economics of Logwood Boiler Installation
Purchase cost of approximately $50,000 per boiler
Installation cost of approximately $50,000 including labor and accessories
Total system installed cost of approximately $150,000
Heating oil savings = 60,000 gallons per year
Heating oil cost savings = about $220,000
Logwood consumption = 350 cords per year
Total logwood fuel cost = $35,000 per year
Labor/equipment cost = $50,000 per year (estimate)
Total cost savings = $130,000 per year
Payback period = Just over one year
Payback period would have been more than two years if boiler oversized by 2 or 3 X factor especially if larger building required
Payback period would be about 9 months if only one boiler had been installed
Abbey of St Benoit du Lac
St Benoit du Lac, QuebecCanada
Craftsbury Outdoor CenterCraftsbury, Vermont
Photos courtesy of WR Boilers of Fairfield, Vermont and Lopper North America
Integrated energy system of industrial-grade logwood-fired boiler (240,000 Btu/hr) with 150 kW biodiesel-fired CHP and solar thermal plus 20,000 gallons thermal storage system
Conclusions
25 % undersizing only 1 % loss of total annual wood heating output and heating oil savings
50 % undersizing only 7 % loss of total annual wood heating output and heating oil savings
Reducing boiler size by 50 % can save 20 to 30 % in capital cost andlength of payback period
Using oil or propane-fired boiler for low load conditions can preventsmoldering conditions with just small increase in oil/propane use
Shorter payback periods More customersHigher efficiency Lower Fuel Costs
Lower emissions Happier neighbors
“Small can be beautiful”
Thank You!