technical aspects of interconnection of the power system of ukraine 28 th of february, 2006 brussels...

17
Technical Aspects of Interconnection of the Power System of Ukraine 28 th of February, 2006 Brussels Electricity Sector of Ukraine: Status and Plans Ahead

Upload: shania-dunford

Post on 31-Mar-2015

222 views

Category:

Documents


6 download

TRANSCRIPT

Page 1: Technical Aspects of Interconnection of the Power System of Ukraine 28 th of February, 2006 Brussels Electricity Sector of Ukraine: Status and Plans Ahead

Technical Aspects of Interconnection

of the Power System of Ukraine

28th of February, 2006 Brussels

Electricity Sector of Ukraine:

Status and Plans Ahead

Page 2: Technical Aspects of Interconnection of the Power System of Ukraine 28 th of February, 2006 Brussels Electricity Sector of Ukraine: Status and Plans Ahead

Ukraine Briefly

Total area is 603,700 sq. km

Total length of the borders is 7,590 km

Population is about 48,5 mln.

The capital is Kyiv

Border countries are:Belarus, Hungary, Moldova, Poland, Romania, Russia Slovakia,

Page 3: Technical Aspects of Interconnection of the Power System of Ukraine 28 th of February, 2006 Brussels Electricity Sector of Ukraine: Status and Plans Ahead

Number of step-up substations 35-750 kV – 5 360 Total installed capacity of transformers – 157 600 MVATotal number of circuit breakers – above 113 000

Total length of electrical lines – above 1 000 000 kmTotal number of transformer substations – above 200 000

Page 4: Technical Aspects of Interconnection of the Power System of Ukraine 28 th of February, 2006 Brussels Electricity Sector of Ukraine: Status and Plans Ahead

Installed Capacity of Generation Equipment

HPP 4784.7 MW9%

NPP 13835 MW27%

TPP 27150 MW52%

Industrial & CC TPP 6374.4 MW

12%

WMPP 59 MW0,11%

Energy Production for 2005

NPP 88756 mln.kW*h

48%

Industrial & CC TPP 22578 mln.kW*h

12%

TPP 61544 mln.kW*h

33%

HPP 12320 mln.kW*h

7%

WMPP 38 mln.kW*h

0,02%

Installed capacity of power plants is above 52 mln. kW

Total annual production is above 185 mln. MW*h

Generation Capacity of Ukraine

5 TPP Generation Companies- 14 TPPs, 97 units (800-150 MW) 1 NPP Generation Company - 4 NPPs, 15 units (1000- 440 MW)1 HPP Generation Company - 8 HPPs, 90 units (117 - 19 MW) 3 big CHP - 9 units (250 – 100 MW)

Page 5: Technical Aspects of Interconnection of the Power System of Ukraine 28 th of February, 2006 Brussels Electricity Sector of Ukraine: Status and Plans Ahead

SE NPC “UKRENERGO”. Main Tasks

- provision of integrity of Ukrainian IPS;

- provision of operative-technological control of Ukrainian IPS with a provision of optimal modes for operation within Wholesale Electricity Market;

- provision of synchronous operation of the IPS of Ukraine with power systems of neighboring countries as well as implementation of special schemes for power transmission to these countries;

- prevention and liquidation of network disturbances and system accidents;

- provision of operation and maintenance of the backbone network and means for IPS of Ukraine control.

Page 6: Technical Aspects of Interconnection of the Power System of Ukraine 28 th of February, 2006 Brussels Electricity Sector of Ukraine: Status and Plans Ahead

220 kV19%

500 kV2%

750 kV19%

800 kV0,4%

400 kV2%

330 kV58%

SE NPC “UKRENERGO”. Transmission Network

-132 substations with voltage level 750-220 kV-total capacity of transformer substations – 75.000 MVA-total length of transmission lines more than 22.000 km

-750 kV lines – 4115 km-500 kV lines – 375 km-400 kV lines – 340 km-330 kV lines – 13000 km-220 kV lines – 4170 km

Page 7: Technical Aspects of Interconnection of the Power System of Ukraine 28 th of February, 2006 Brussels Electricity Sector of Ukraine: Status and Plans Ahead

SE NPC “UKRENERGO”. Dispatch Control

NPC “Ukrenergo”

Distributioncompanies(networks 150 kV and less)

DonbassPS

________

transmission

network

NorthPS

________

transmission

network

CrimeaPS

________

transmission

network

SouthPS

________

transmission

network

CenterPS

________

transmission

network

South-WestPS

________

transmission

network

WestPS

________

transmission

network

Hydro company“Ukrgidroenergo”

Generationcompanies

(TPP, NPP, CoTPP)

HPP

DneprPS

________

transmission

network

Page 8: Technical Aspects of Interconnection of the Power System of Ukraine 28 th of February, 2006 Brussels Electricity Sector of Ukraine: Status and Plans Ahead

CountriesInterconnectin

g Lines 220-750kV

Russia 14

Moldova 7

Belarus 2

Poland 2

Slovakia 2

Hungary 4

Romania 2

Total 33

CountriesIntercon. lines 220-750kV

Russia 14

Moldova 7

Belarus 2

Poland 2

Slovakia 2

Hungary 4

Romania 2

Total 33

Page 9: Technical Aspects of Interconnection of the Power System of Ukraine 28 th of February, 2006 Brussels Electricity Sector of Ukraine: Status and Plans Ahead

“Burshtyn TPP Island”

• Territory – 27 000 km 2

• Population – 3 millions• Export potential – up to 550 MW• Internal consumption – 1000-1050 MW• Power plants – Burshtyn TPP (2300

MW), Kalush TPP (200 MW) and Tereblia-Rikskaya HPP (27 MW)

Page 10: Technical Aspects of Interconnection of the Power System of Ukraine 28 th of February, 2006 Brussels Electricity Sector of Ukraine: Status and Plans Ahead

Establishment of the «Burshtyn TPP Island»

Chronology of Events

• November 1-3, 1995 – initial meeting of UCTE experts with Ukrainian specialists in Lviv.

• January 1996 – first meeting of the Technical Committee UCTE/CENTREL/Ukraine.

• 1995–1997 - elaboration and approval of the Catalogue of Measures on integration of the «Burshtyn TPP Island» to UCTE/CENTREL.

• 1999 – Agreement on long-term physical delimitation of Burshtyn TPP Island from IPS of Ukraine was signed.

• April 6-20, 2002 – tests and 2 weeks trial operation of the «Burshtyn TPP Island» before connection to UCTE power system.

• July 1, 2002 – «Burshtyn TPP Island» was switched on one year trial parallel operation with UCTE.

• July 1, 2003 – Constant operation of «Burshtyn TPP Island» with UCTE.• October10, 2004 – Resynchronization of II synchronous zone of UCTE.

Switching on OHL 400 kV Mukachevo-Roshior (Romania)

Page 11: Technical Aspects of Interconnection of the Power System of Ukraine 28 th of February, 2006 Brussels Electricity Sector of Ukraine: Status and Plans Ahead

1. Increasing of capacity of existing units of Burshtyn TPP

2. Modernization of switching equipment and relay systems

3. Increasing of power export up to 600 – 650 MW

4. Development of fiber-optical communication lines

“Burshtyn TPP Island”. Plans for Development

Page 12: Technical Aspects of Interconnection of the Power System of Ukraine 28 th of February, 2006 Brussels Electricity Sector of Ukraine: Status and Plans Ahead

On the Way to Meet UCTE Requirements. Studies

-Studies of the adequacy of Ukrainian normative documentation to the OH standards;

-Studies of the adequacy of the Ukrainian IPS for synchronous operation with European Power System (N-1, stability, voltage regulation, power reserve control, emergency procedures, information exchange, etc.);

-Studies of generation units to participate in primary and secondary regulation;

-Studies of the electrical substations;

-Development of the Ukrainian Grid Code.

Page 13: Technical Aspects of Interconnection of the Power System of Ukraine 28 th of February, 2006 Brussels Electricity Sector of Ukraine: Status and Plans Ahead

On the Way to Meet UCTE Requirements. Studies to Be Finished 2006

- Development of plan-schedule for II stage of HPP rehabilitation;

- Harmonization of Ukrainian energy industry legislation in accordance with European requirements;

- Development of project documentation for modernization of electrical substations;

- Development of plan-schedule for modernization of TPP units to participate in primary and secondary regulation;

- Development of plan-schedule for voltage control modernization.

Page 14: Technical Aspects of Interconnection of the Power System of Ukraine 28 th of February, 2006 Brussels Electricity Sector of Ukraine: Status and Plans Ahead

Hydro Power Plant Exist / Reconstructed

Units

Units under AGC

Installed capacity

under AGC, MW

Regulation Zones

Kievskaya 20 / 8 1 22,4 Emergency only

Kremenchyckaya 12 / 6 1 57 All zones

Dneprodzerginskaya 8 / 6 1 48 All zones

Dneprovskaya 18 / 9 6 6*72=432 All zones

Kahovskaya 6 / 4 1 52 All zones

Dnestrovskaya 6 / 6 1 117 Emergency only

Total 70 / 39 12 728,4

On the Way to Meet UCTE Requirements. Secondary Control

- Installation of SCADA\EMS\AGC system - 400 MW of HPP is permanently under AGC control

Page 15: Technical Aspects of Interconnection of the Power System of Ukraine 28 th of February, 2006 Brussels Electricity Sector of Ukraine: Status and Plans Ahead

On the Way to Meet UCTE Requirements. Network Construction

-Construction of OHL 330 kV HAES-Hmelnitska-Construction of OHL 330 kV RAES-Lutsk Pivnichna-Construction of N.Donbaska 500 kV substation-Construction of OHL 500 kV Donbaska-N.Donbaska-Increasing of voltage level of OHL RAES-Zahidnoukrainska to 750 kV- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -Modernization of relay protection-Installation of SCADA\EMS\AGC system -Construction of 1160 km of fiber cable communication link-Installation of WAMS system

Page 16: Technical Aspects of Interconnection of the Power System of Ukraine 28 th of February, 2006 Brussels Electricity Sector of Ukraine: Status and Plans Ahead

750 kV Lines:

•Rivnenska NPP - Kyivska 750

330 kV Lines:

•N.Odeska – Artsyz

•Adgalyk – Usatovo

•Zahidnoukrainska – Bogorodchani

•Construction of connections of Dnestr PSPP to OHL Dnestr HPP-Ladygyn TPP

•Dnestr PSPP – Bar

Network modernization:

•Increasing of voltage level of line 220 kV Sevastopol – Simferopol up to 330 kV

•Construction of connections to line 330 kV Melitopol - Simferopol from Dgankoj substation

•Installation of series capacitor on Dgankoj substation

Generation

•Construction of Dnestr Pumped – Storage Power Plant

•Construction of Tashlyk Pumped – Storage Power Plant

On the Way to Meet UCTE Requirements. Network Construction till 2008

Page 17: Technical Aspects of Interconnection of the Power System of Ukraine 28 th of February, 2006 Brussels Electricity Sector of Ukraine: Status and Plans Ahead

Technical Aspects of Interconnection

of the Power System of Ukraine

Volodymyr Luchnikov

Electricity Sector of Ukraine:

Status and Plans Ahead

Thank you for attention !