technical risk factors in building construction.doc

Upload: rathnayaker

Post on 14-Apr-2018

212 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    1/97

    Declaration

    I hereby declared that this report submission is my own work and to the best of my

    knowledge. It does not contain any material previously published or written by any

    other person or any material which substantial extent has been accepted for the award

    of any degree or diploma of a university or other institution of higher education,

    except where referenced are mentioned.

    Rathnayake R.M.R.S.B

    Department of Building Economics,

    Faculty of Architecture,

    University of Moratuwa,

    Sri Lanka,

    April 2009

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    2/97

    Acknowledgement

    This research study embraces much dedication and ready assistance received from many

    people, who contributed in ample ways to complete this study. Consequently, I take this

    opportunity to convey my sincere gratefulness to every one of them.

    It is my foremost duty to pay my gratitude to the Department of Building Economics,

    University of Moratuwa, and all the academic as well as non academic staff of the department

    for the tremendous service rendered. I extend my gratitude to Mr. Indunil Senevirathna, Head

    of the Department of Building Economics, for his keen interest, encouragement and the

    guidance to the achievement of producing this dissertation.

    Furthermore, I am grateful to my supervisor, Mrs. Kanchana Perera, Senior lecturer,

    Department of Building Economics, for her outstanding supervision, her guidance,

    encouragement, and constructive criticisms significantly contributed towards the successful

    completion of this research. I extend my gratefulness to Dr. Sepani Senarathna, the

    dissertation coordinator, for her interest and dedication throughout the year. I should express

    my appreciation to senior lectures of the Department of Building Economics Prof. R.

    Rameezdeen, Mr. Suranga Jayasena, Mrs. Yasangika Sandanayaka and Mr. Sandun Fernando

    for their valuable guidance throughout the research process.

    I convey my special thanks to Mr. Lalith Rathnayaka (VForm consultants), Mr Thilak

    kolonne (VForm consultant),Mr. Elmo Fernando (Havelock city project) Mr. Pieris

    (Department of Mathematics, University of Moratuwa) for their special guidance, assistance

    and encouragement provided to clarify the problems of this research.

    I would like to convey my utmost gratitude to all the professionals of organizations who gave

    me a great support in many ways for the success of this research.

    Finally I express my heartfelt thanks for my family members, relations, colleagues and my

    seniors and juniors for giving me an outstanding company to make this dissertation possible.

    Rathnayake R.M.R.S.B.

    24th April 2009

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    3/97

    T a b l e o f C o n t e n t

    Table of Contents

    Acknowledgement ...................................................................................ii

    Table of Contents......................................................................................I

    List of Figures.........................................................................................II

    List of Tables.........................................................................................III

    List of Appendix.....................................................................................IV

    Abbreviations ..........................................................................................V

    Abstract...................................................................................................VI

    Chapter 01................................................................................................1

    Chapter 02................................................................................................7

    Chapter 03..............................................................................................36

    Chapter 04..............................................................................................47

    Chapter 05..............................................................................................76

    References .............................................................................................82

    Appendix ................................................................................................89

    C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k I

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    4/97

    L i s t o f F i g u r e s

    List of Figures

    Figure 3.1: Research Process................................................................37

    Figure 3.2: Nested reseach methodology..............................................38

    Figure3.3: Research methodology illustration.....................................39

    C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k II

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    5/97

    L i s t o f T a b l e s

    List of Tables

    Table.2. 1: Risk identification process..................................................19

    Table.2. 2: Risk identification................................................................19

    C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k III

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    6/97

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    7/97

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    8/97

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    9/97

    I n t r o d u c t i o n

    Chapter 01

    1 INTRODUCTION

    1.1 BACKGROUND

    The concept of risk can be applied to nearly every human decision making action of

    where, the consequences are uncertain (Flanagan and Norman 1993). The word of

    risk has entered in to the English language in the mid 17 th century, coming from the

    French word risqu (Covello and Mumpower 1985 cited Thilakarathne 2007).

    Cooper and Chapman (1987 cited Dent 1997, p. 1)define risk as exposure to the

    possibility of economic or financial loss or gain physical damage or injury or delay

    as a consequence of the uncertainty associated with pursuing a particular course of

    action.

    Construction industry is one of the most dynamic and challenging industries

    (Woodward 1997) and it is subjected to more risk and uncertainty than many otherindustries (Flanagan and Norman 1993). Furthermore, according to Patrick et al.

    (2007), Kangari (1995), Uher and Toakley (1999), and Thevendran and Mawdesley

    (2004),risk relates to construction industry and obviously it is related to construction

    projects.Hence, construction projects consistently expose to various sources of risks

    (Poh and Tah 2006). Those risks can effect to productivity, performance, quality, and

    budget of a construction project (Kangari 1995). However, risks cannot be eliminated

    (Patricket al. 2007), but it can be minimized or transferred from one stakeholder to

    other stakeholder in the construction process (Kangari 1995). Thus, formal and

    efficient risk management process is needed to manage all types of risks in

    construction projects (El-Sayegh 2008).

    Consequently, management of risks has turned into a main part of the organizational

    activities (Flanagan and Norman 1993). The risk management is a tool which

    control risks in construction projects(Hamshayini 2007, p. 1). The main aim of risk

    management is to assist all construction project aims (Mills 2001) by mitigating the

    risk, transferring the risk to other parties, or sharing the risk among the parties

    C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k 1

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    10/97

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    11/97

    I n t r o d u c t i o n

    the management of risk is significantly influenced by the uniqueness of the

    construction industry of that particular country. As such as, it emphasizes a need of

    in depth investigation to the overall consequences and uncertainties in construction

    risk management for a variety of project participants in Sri Lankan context.

    Besides, according to the empirical study by Kangari (1995) revealed that

    management practices are mainly focused on construction risk allocation towards

    perception of the typical large contractors and owners. Further, the same study

    emphasized the identification of strategies or usage of risk management techniques to

    add value to project delivery and improve the effectiveness of the construction

    industry throughout of the process of construction.

    To handle risks in construction projects appropriately, it is required to assign them

    scientifically among parties (El-Sayegh 2007). Thus, scientific assignment of risk

    among project parties can be achieved by only if it analytically investigates the

    overall consequences and uncertainties in construction risks and risk supervision

    (Andi 2006). More importantly, this can only be achieved if all parties do understand

    their risk responsibilities properly (Perera 2006).

    Identification of sources of risk is vital aspect in risk management process

    (Tchankova 2002).Edward and Browen (1998)supported the same argument stating

    that for a proper risk management process, it has to first identify source of risks.

    Further, the same study classified the sources of risks in to nine categories: financial;

    legal; management; market; policy; health; cultural; social and political risks.

    However, among all these risks sources/ factors, the technical risk sources/ factors

    are not well-represented or not evident in risk management literature (Edwards and

    Broun 1998).

    According to above mentioned findings and facts, to trounce them and fill the gap,

    which had already figured out. Thus, this emphasized a need of research in risk

    management area with orientation to identify and analyze possible risk factors

    associated with building construction process and further to assess their

    consequences and uncertainties towards project parties/stakeholders; specially

    towards contractors and owners.

    C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k 3

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    12/97

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    13/97

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    14/97

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    15/97

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    16/97

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    17/97

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    18/97

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    19/97

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    20/97

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    21/97

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    22/97

    L i t e r a t u r e R e v i e w o n R i s k M a n a g e m e n t

    However, when consider above-mentioned definitions with compare to Nummedal et

    al. (1996 cited Ahamad and Azar 2004) definition of risk management such as a

    process to control the level of risk and to mitigate its effects and it is a systematic

    approach for identifying, evaluating, and responding to risks encountered in a

    project. It is convinced that that the risk management is a systematic process to

    identify, evaluate and responding to risks encountered in a project. Nummedal et al.

    (1996 cited Ahamad and Azar 2004) definition takes for this research as the

    definition for the risk management.

    The application of systematic risk management in construction projects has long

    been recognized as an effective approach to minimizing risk impacts(Flanagan and

    Norman 1993) and it will aims to identify and assess risk in order to enable them to

    be understood clearly and managed effectively(Hillson 2003).

    2.4.2.1 SYSTEMATIC RISK MANAGEMENT PROCEDURE

    Systematic approach of risk management will be given assurance to the risk

    management process by minimizing the missing of risk factors and there affect.

    Basically, a systematic risk management process consist with three steps

    Figure 2.3: Risk Management Umbrella

    C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k 14

    (Source- Dent 1997)

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    23/97

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    24/97

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    25/97

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    26/97

    ExistenceUncertainty

    PreliminaryChecklist

    Risk Events/

    ConsequenceScenarios

    RiskMapping

    Logical RiskClassification

    Scheme

    Risk CategorySummary Sheet

    Risk Identification ProcessRisk Identification Process

    L i t e r a t u r e R e v i e w o n R i s k M a n a g e m e n t

    Controllable

    Uncontrollable

    Types

    Severity

    The objective of risk identification is to identify all possible risks (Highways agency

    2001), categorize risks that could affect the project (Kangari 1995), and document

    these risks (Flanagan and Norman 1993), not to eliminate risks from consideration or

    to develop solutions for mitigating risks and those functions are carried out during

    the risk assessment and risk mitigation steps. Some of the documentation and

    materials should use in risk identification as they become available include these.

    Risk identification process

    Moreover, the degree, to which the identification process will influence the

    effectiveness of risk management and its contribution to the overall project

    management of any particular project, is dependent on the way the steps of the

    process are implemented (Chapman 2001, p. 147).

    Furthermore, proper implementation of these steps will ensure better effectiveness of

    identification process and it will guide to better understanding of risk. Moreover, the

    key factors involved in each step of the risk identification process demonstrate in

    following figure and table. There are six steps involved in the risk identification

    process. The following sections will discuss each step separately (Al-Bahar 1988

    cited Al-Bahar 1990).

    C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k 18

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    27/97

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    28/97

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    29/97

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    30/97

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    31/97

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    32/97

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    33/97

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    34/97

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    35/97

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    36/97

    L i t e r a t u r e R e v i e w o n R i s k M a n a g e m e n t

    2.7 THE ROLES OF THE PROJECTS DIFFERENT PHASES IN

    RISK MANAGEMENT

    According to Osipova (2007), construction process is traditionally divided into four

    main phases:

    Programme (Inception):- client has an idea about the project and analyses

    conditions for its execution

    Planning: - architects produce construction drawings according to the

    clients requirements

    Procurement (Tendering):- parties sign the contract.

    Production: - contractor executes the job

    Since, foreseen all risk at the inception stage is impossible and due to tendency of

    identified risk in the programme stage to change during project implementation, joint

    and consistent risk management is required throughout all projects (Rahman and

    Kumaraswamy 2005). Furthermore, occurrence and effect of construction project

    risk in different phases to the project participants difficult to foresee all risk only can

    predict to some extend based on the available information in the early stages of the

    construction project (Osipova 2007). Moreover, several authors highlighted the

    importance of identification of project risk in the early stage of the construction

    project life cycle ( Uher and Toakley 1999), (Rahman and Kumaraswamy 2005),

    (Flanagan and Norman 1993), (Andi 2006).

    Aforementioned facts create the need of developing a risk management framework

    within construction project to identify the performance of risk in the construction life

    cycle.

    C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k 28

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    37/97

    L i t e r a t u r e R e v i e w o n R i s k M a n a g e m e n t

    2.6 PROJECT RISK CLASSIFICATION AND TECHNICAL RISK

    IDENTIFICATION REGARDING TO SYSTEMATIC RISK

    MANAGEMENT

    2.6.1 PROJECT RISK CLASSIFICATION

    Project risk classification is an important step in risk assessment process, because it

    attempts to structure the various risks that may affect a project. There is various

    classification of project risk with respect to deferent purposes (Edwards and Browen

    1998), (Al-Bahar 1990 cited Ahmed and Azhar 2004), (Wong and Hui 2006), (Stoner

    et al. 1997). Specially the construction risk is generally perceived as events that

    influence project objectives of cost, time and quality and some of the project risks

    can be predictable or foreseen (identifiable) while other may totally unforeseen. Due

    to that, also it is very much important to classify project risks (Al-Bahar 1990 cited

    Ahmed and Azhar 2004).

    According to Edwards and Browen (1998), project risk classifies using the risk

    source as the basis; primary classification would be human and natural. Natural risks

    occur outside the human agencies, while human risk arise the humanly organizedsystem and this classification is illustrated following figure. Human risks relating to

    construction project classifies further as social, political, economic, financial, legal,

    managerial, technical, and cultural risks.

    C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k 29

    (Source- Edwards and Brown 1998)

    Risk

    Natural Human

    PoliticalWeather

    systemEconomic

    Financial

    Legal

    Health

    Managerial

    Technical

    Social

    Cultural

    Geological

    system

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    38/97

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    39/97

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    40/97

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    41/97

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    42/97

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    43/97

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    44/97

    R e s e a r c h M e t h o d o l o g y

    Chapter 03

    3. RESEARCH METHODOLOGY

    3.1 INTRODUCTION

    Main aim of this chapter is to outline the research methodology for this research and

    specially illustrate the research design, which was followed throughout this research.

    Initially, it is describing the research Process of this particular research and it

    illustrates completely the Process of this research in a systematic manner using

    figures.

    Further, it is illustrating the research design together with the steps of the research

    design and applicability of research design steps also illustrate.

    3.2RESEARCH PROCESS

    This research carried out mainly to identify the prevailing technical risk factors and

    thereafter to analyze the allocation of risk among contraction parties, figure out

    consequences of above risk of contracting parties, moreover to identify the

    performance of technical risk in construction life cycle. Thus, it was essential to

    think off an appropriate research Process, which is competent of identification risk

    factors, which is paramount.

    Further, by using a proper research process can be minimized the errors that can be

    occurred during our research and can be reduced the mistakes done by the researcher.

    Research process for this particular research illustrates using following figure,

    C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k 36

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    45/97

    R e s e a r c h M e t h o d o l o g y

    Figure 3.1: Research Process

    C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k 37

    Further

    Research

    Research Question

    Establish Aim & objective

    Data Collection

    Preliminary Survey

    Structured Interview Questioner Survey

    Data Analysis

    Conclusion & Recommendation

    Literature Review

    Interviewing Literature Review

    Guide to

    Sampling and

    Factor Selection

    Background study

    Sample

    Collect

    ion

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    46/97

    R e s e a r c h M e t h o d o l o g y

    3.3 RESEARCH DESIGN

    Research design is complying with three key steps; in sequent, identifying researchphilosophy, identifying research approach, identifying research technique (Kagioglou

    et al. 2000 cited Senarathne 2005) Where the selection of research techniques for

    data collection and data analysis is based on research approach and the selection of

    research approach is based on the research philosophy.

    Figure 3.2: Nested reseach methodology

    Further, research methodology illustrated by the Saunders et al. (2003) as shown in

    the following figure,

    C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k 38

    (Source- Kagioglou et al. 2000 cited Senarathne 2005)

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    47/97

    R e s e a r c h M e t h o d o l o g y

    Figure3.3: Research methodology illustration

    3.3.1 RESEARCH PHILOSOPHY

    Research philosophy selection is the initial step of research designing and it is

    depend on the way researcher think about to develop the knowledge. Further, it

    directs to the researcher to select appropriate research strategy among one offollowings,

    Positivism: - are the natural science researchers. In positivism,

    working with an observable social actuality and the finished product

    of the research can be generalized (Remenyi et al. 1998 cited saunders

    et al. 2003)

    Interpretivism: - try to discover the details of the situation to

    understand the reality or perhaps reality is working behind them

    (Remenyi et al. 1998 cited Saunders et al. 2003).

    Realism: - believe that the reality is subjective and interior to the

    people and it shares the both view of positivism and interpretivism.

    By considering the nature of this research problem it is obvious that this piece of

    research needs a vigilant observations and identification about the construction

    project risk to manage the to overcome problems created by the construction project

    C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k 39

    (Source- Saunders et al. 2003)

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    48/97

    R e s e a r c h M e t h o d o l o g y

    risk to the construction parties throughout the construction project life cycle. Due to

    that reason interpretivism select as the research philosophy for this research.

    3.3.2 RESEARCH APPROACH

    Appropriate research approach should select to deal with the research question

    according with the research philosophy. Research approach approaches are about to

    organise research activities, especially including the collection of data from the

    population in a way that meet the reach problems aims and objectives. According to

    Saunders et al. (2003), research approach can be divided in to two categories,

    Deductive:- first develop a theory and hypothesis, and design research

    strategy to test the hypothesis and moreover this is owes to positivism,

    Inductive:- first collect data and develop a theory as a result of the data

    analysis, and moreover this is owes to interpretivism,

    When considering circumstance of the this research problem, it is important to

    identify the technical risk factors , consequences of them and their performance inthe construction life cycle. Therefore as the research approach to this research

    deductive approach is selected.

    According to the study of, Kagioglou et al. (2000 cited Senarathne 2008);following

    approaches are the most popular and widely used research approaches in the world.

    Experiments laboratory, quasi-experiments

    Surveys

    Case study research

    Ethnography

    Action research

    Grounded theory

    C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k 40

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    49/97

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    50/97

    R e s e a r c h M e t h o d o l o g y

    Consequently, very large samples are feasible, making the results statistically

    significant even when analyzing multiple variables.

    Many questions can be asked about a given topic giving considerable flexibility

    to the analysis. There is flexibility at the creation phase in deciding how the questions will be

    administered: as face-to-face interviews, by telephone, as group administered

    written or oral survey, or by electronic means.

    Standardized questions make measurement more precise by enforcing uniform

    definitions upon the participants.

    Standardization ensures that similar data can be collected from groups then

    interpreted comparatively (between-group study).

    3.3.3 RESEARCH TECHNIQUE

    3.3.3.1 DATA COLLECTION TECHNIQUE

    By considering the circumstances of this of this particular research, especially

    neediness of the identification and perceptions of construction industry practitioners

    about the allocation of technical risk factors among contract parties, questioner

    survey selected as the basic technique to collect data. Furthermore, for fill the gap

    creating by the questioner survey, semi structured interview was used for thecritically identify the actual scenario.

    Preliminary Survey

    Preliminary survey carried out to find out, current prevailing condition of the risk in

    building construction industry and to identify the significance technical risk factors

    relate to building construction industry. Moreover, it was conducted in two ways,

    C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k 42

    http://var/www/apps/conversion/tmp/scratch_4/com2d4.cfmhttp://var/www/apps/conversion/tmp/scratch_4/com2d4.cfmhttp://var/www/apps/conversion/tmp/scratch_4/com2d4.cfmhttp://var/www/apps/conversion/tmp/scratch_4/com2d4.cfmhttp://var/www/apps/conversion/tmp/scratch_4/com2d4.cfmhttp://var/www/apps/conversion/tmp/scratch_4/com2d4.cfmhttp://var/www/apps/conversion/tmp/scratch_4/com2d4.cfmhttp://var/www/apps/conversion/tmp/scratch_4/com2d4.cfmhttp://var/www/apps/conversion/tmp/scratch_4/com2d4.cfmhttp://var/www/apps/conversion/tmp/scratch_4/com2d4.cfmhttp://var/www/apps/conversion/tmp/scratch_4/com2d4.cfmhttp://var/www/apps/conversion/tmp/scratch_4/com2d4.cfmhttp://var/www/apps/conversion/tmp/scratch_4/com2d4.cfmhttp://var/www/apps/conversion/tmp/scratch_4/com2d4.cfmhttp://var/www/apps/conversion/tmp/scratch_4/com2d4.cfmhttp://var/www/apps/conversion/tmp/scratch_4/com2d4.cfmhttp://var/www/apps/conversion/tmp/scratch_4/com2d4.cfmhttp://var/www/apps/conversion/tmp/scratch_4/com2d4.cfmhttp://var/www/apps/conversion/tmp/scratch_4/com2d4.cfmhttp://var/www/apps/conversion/tmp/scratch_4/com2d4.cfmhttp://var/www/apps/conversion/tmp/scratch_4/com2d4.cfmhttp://var/www/apps/conversion/tmp/scratch_4/com2d4.cfmhttp://var/www/apps/conversion/tmp/scratch_4/com2d4.cfm
  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    51/97

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    52/97

    R e s e a r c h M e t h o d o l o g y

    construction life cycle. Ultimatly, in the forth question relates to the proper allocation

    of the risk among construction parties namely cotractor, client and consultant.

    The questionnaire survey forms were distributed to construction professionals

    associated with the Sri Lankan construction industry. The completed responses

    collected personally.

    Structured Interviews

    With the guidance of the preliminary survey, structure for the structured interview

    was prepared and moreover allocation of risk, consequence, and occurrence of that

    particular risk factors within the construction lifecycle was try to figure out. This wasconducted together with the questioners and interviewed the construction

    practitioners. In most of the cases interviewed Project manager, Project Engineer,

    Site Engineers, and specially quantity surveyor to ensure the monitory terms relate to

    technical risk.

    3.3.3.2 DATA ANALYSIS TECHNIQUE

    Collected data from above three methods evaluate systematically to achieve proper

    answer to the research question.

    For analyze the allocation of risk to the contracting parties, figure out the

    consequences of above risk of contracting parties, and identify performance of risk in

    construction life cycle from the collected data. Likert Scale was used in questioner

    survey.

    Likert Scale

    Likert scale can be recognized as the technique of measuring the different attitudes

    towards a statement by asking the respondent to indicate their preference in a series

    of short statement on a given range of responses. It can be analyzed the general

    C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k 44

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    53/97

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    54/97

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    55/97

    D a t a A n a l y s i s a n d i n t e r v i e w

    a n a l y s i s

    Chapter 04

    4 DATA ANALYSIS AND INTERVIEW ANALYSIS

    4.1 INTRODUCTION

    With the aim of upgrading the knowledge in realm of risk management, the research

    had first conducted a board literature review in the risk management field with

    particular prominence in building construction projects in Sri Lankan perspective.

    Prime intention of this chapter is to analysis the degree of risk management aspects

    using in technical risk management in construction projects in Sri Lanka. Chapter 2

    provided the rigid knowledge of risk management and risk management measures

    concerning the technical risk management. Besides, the behavior of the contraction

    projects and construction project partys behavior regarding risk management. This

    chapter completely based on information collected from construction industry

    practitioners through questioner survey and interviews.

    Within this chapter consists of the results, after analyzing the data, collected from

    questionnaire survey and interview. Moreover, ultimately, discussion carried out with

    the intention of approaching the conclusion of this study.

    C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k 47

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    56/97

    D a t a A n a l y s i s a n d i n t e r v i e w

    a n a l y s i s

    4.2 PRELIMINARY SURVEY

    4.2.1 RISK FACTOR IDENTIFICATION

    Various risks were identified in the first stage of this research and they were

    illustrated broadly in the chapter 02. This was accomplished mainly through

    literature review. Twenty four technical risk factors were identified through the

    literature review.

    For the fulfillment of aim and objective of the research respondents were asked to

    state availability of the listed risk factors which were found out though the literature

    review. That was asked to do considering respondents knowledge and experience

    about listed technical risk factors. This was done with the intention of removing risk

    factors where none of respondent stated as; a particular risk factor could not be seen

    in Sri Lankan construction industry. However, according to finding of the

    preliminary survey, technical risk identification can be illustrated by following figure

    4.1.

    According to figure 4.1, all the risk events identified were there in Sri Lankan

    construction industry. Based on the survey result, thirty-four respondents out of forty

    stated that they have faced to estimation errors considering their experience. Eighty

    five percent of the total projects were having estimation errors. Moreover, design

    failures/ design variation by client is the second highest technical risk factor. Thirty

    three out of forty respondents mentioned that they faced that.

    Thirty two out of forty respondents had faced to shortage in skillful workers within

    their projects. It means there is an 80% probability of having shortage in skillful

    workers for a project. Apart from above mention three technical risk factors,

    according to respondents identification there were 6 risk factors having more than

    50% probability of occurrence in a particular project.

    C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k 48

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    57/97

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    58/97

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    59/97

    D a t a A n a l y s i s a n d i n t e r v i e w

    a n a l y s i s

    Figure 4. 2: Respondents Profile

    4.3.1 RSEARCH FINDINGS

    4.3.1.1 SIGNIFICANCE OF TECHNICAL RISK FACTORS

    Based on the survey results, the relative importance index (RII) was calculated for

    each risk based on probability, impact and rating. These risks were then ranked

    according to their RII. The results are presented in tables and figures for easy

    illustration.

    Significance of technical risk was measured considering the project perspectives

    independently such as,

    Impact to the cost of the project

    Impact to the time of the project

    C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k 51

    SubjectNo of Respondents

    Client Contractor Consultant Total

    Number of Respondents 11 14 15 40

    Less Than 5 Years 1 5 6 12

    5-10 Years 1 4 0 5

    Above 10 Years 9 5 9 23

    Project Scale

    less than 500

    million1 2 6 9

    500-1000

    million

    5 7 5 17

    Above 1000

    million5 4 5 14

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    60/97

    D a t a A n a l y s i s a n d i n t e r v i e w

    a n a l y s i s

    Impact to the quality of the project

    Reliability of data

    Considering the data set gain from the questionnaire survey for the probability,

    Cronbach's Alpha was calculated for the data set. The alpha is 0.743. According to

    Nunnally and Bernstein (1978), in a reliable data set the alpha should be above 0.7. It

    means the data set collected to calculate RII for each risk based on probability is

    reliable.

    Moreover, considering the data set collected to calculate RII for each risk based on

    cost impact, Cronbachs alpha was calculated. The alpha is 0.840. It denoted that the

    data set collected through questionnaire to calculate RII for each risk factor based on

    cost impact is reliable.

    Furthermore, for data sets collected for the time impact and quality impact also

    Cronbachs alphas were calculated. Alphas are consequently 0.794 and 0.829.

    According to Nunnally (1978), those are reliable data sets.

    4.3.1.1.1 SIGNIFICANT TECHNICAL RISK FACTORS CONSIDERING

    COST OF THE PROJECT

    Cost of the project is one of the most important project perspectives when

    considering the budget of the project, which is allocated by the employer, or the

    owner of the project. Therefore, it is more important to consider impact to the cost of

    the project by the technical risk factors.

    Based on the survey, the results are presented in table 4.3. Table 4.4 presents the top

    10 technical risks in the Sri Lankan construction industry based on the risk rating

    considering impact to the cost of the project. According to risk rating values, most

    significant technical risk is estimation errors. The RII is 11.970. Estimation errors are

    the key technical risk when considering the cost perspective of the project in Sri

    C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k 52

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    61/97

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    62/97

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    63/97

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    64/97

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    65/97

    D a t a A n a l y s i s a n d i n t e r v i e w

    a n a l y s i s

    4.3.1.1.2 SIGNIFICANCE CONSIDERING TIME OF THE PROJECT

    Time of the project is one of the most important project perspectives. When

    considering time limitation that is given by the owner. That could be due to demand

    to the project at market. Therefore, it is more important to consider impact to the

    time of the project by the technical risk factors.

    Table 4. 5: Significance of Risk Considering Time of the Project

    C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k 57

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    66/97

    D a t a A n a l y s i s a n d i n t e r v i e w

    a n a l y s i s

    Based on the survey, the results are presented in table 4.5. Table 4.6 presents the top

    10 technical risks in the Sri Lankan construction industry based on the risk rating

    considering impact to the time of the project. According to risk rating values, most

    C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k 58

    No. RISK FACTORS

    Impact-

    TimeProbability Rating

    RII-

    (1)

    RankRII-

    (2)

    RankRII-

    (3)

    Rank

    1 Design failures 3.100 7 2.050 20 6.355 15

    2 Equipment and system failures 2.675 17 2.150 19 5.751 20

    3 New technology failures 2.875 11 2.200 18 6.325 16

    4 Estimation errors 2.881 10 3.325 3 9.579 6

    5 Accident/ Collision 2.400 22 2.500 12 6.000 19

    6 Site Location and access 2.550 21 2.500 12 6.375 14

    7Inadequate program scheduling

    and tight program scheduling3.825 1 2.975 5 11.379 4

    8Design changes / Design

    variations by client 3.300 6 3.475 2 11.468 3

    9Hazards of environmental

    regulations2.825 12 2.525 11 7.133 11

    10Incompetence of transportation

    facilities2.800 14 2.200 16 6.160 17

    11 Increase in site overheads 2.900 9 2.725 8 7.903 8

    12 Industrial disputes 3.425 5 2.200 16 7.535 10

    13Local firms incompetence and

    low credibility2.775 15 2.325 14 6.452 13

    14 Materials shortage 3.675 3 3.150 4 11.576 2

    15Obsoleteness of building

    equipment2.675 17 2.000 22 5.350 22

    16Poor quality of procured

    accessory facilities2.675 17 2.025 21 5.417 21

    17Poor quality of procured

    materials2.650 20 2.300 15 6.095 18

    18Problems due to partners

    different practice2.825 12 2.700 9 7.628 9

    19 Shortage in accessory facilities 2.225 24 1.975 23 4.394 24

    20 Shortage in skillful workers 3.450 4 3.500 1 12.075 1

    21Shortage in supply of water, gas,and electricity

    2.325 23 1.925 24 4.476 23

    22 Subcontractors low credibility 2.750 16 2.550 10 7.013 12

    23 Unknown site physical conditions 3.100 7 2.750 7 8.525 7

    24Unusual weather and force

    majeure3.700 2 2.925 6 10.823 5

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    67/97

    D a t a A n a l y s i s a n d i n t e r v i e w

    a n a l y s i s

    significant technical risk is Shortage in skillful workers. The RII is 12.075. As

    illustrated in 4.3.1.1.1, construction industry is not having permanent labour force.

    Therefore, shortage in skillful workers might be a key risk to the project significance

    considering the time impact of the project.

    Table 4.6: Top Ten Ranked Risk Factors Considering Significance Risk

    The fourth risk is owners often impose tight construction schedule (RII=11.379) that

    might be difficult and impractical to achieve. This might be caused by the

    importance of time to market but often is caused by political reasons. Due to difficultand impracticality this will definitely influence time of the project.

    Unusual weather and force majeure is ranked fifth (RII=10.823). This is a risk, which

    cannot be easily predicted but effect to time of the project is considerably high. Most

    importantly estimation errors which ranked 6 th (RII= 9.579) will also be an impact to

    the project as described in section 4.2.1.2.1. Unknown site physical condition is

    ranked 7th (RII =8.525). This is also impulsive risk at the planning stage and

    occurring of this technical risk event will influence time of the project. The eighth

    risk event is contractor related. Increasing site overhead is the ranked eighth (RII=

    7.903). Problems arising out of partners deferent practice also create impact to time

    of the project. It is ranked ninth (RII= 7.628). Tenth risk is the industrial disputes.

    C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k 59

    No RISK FACTORS RII Rank

    a Shortage in skillful workers 12.075 1b Materials shortage 11.576 2

    c Design changes / Design variations by client 11.468 3

    dInadequate program scheduling and tight

    program scheduling11.379 4

    e Unusual weather and force majeure 10.823 5

    f Estimation errors 9.579 6

    g Unknown site physical conditions 8.525 7

    h Increase in site overheads 7.903 8

    i Problems due to partners different practice 7.628 9

    j Industrial disputes 7.535 10

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    68/97

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    69/97

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    70/97

    D a t a A n a l y s i s a n d i n t e r v i e w

    a n a l y s i s

    C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k 62

    NO. RISK FACTORSQuality Probability Rating

    RII-

    (1)Rank

    RII-

    (2)Rank

    RII-

    (3)Rank

    1 Design failures3.02

    52 2.050 20 6.201 10

    2 Equipment and system failures2.30

    013 2.150 19 4.945 15

    3 New technology failures2.32

    512 2.200 18 5.115 13

    4 Estimation errors2.10

    017 3.325 3 6.983 6

    5 Accident/ Collision1.52

    523 2.500 12 3.813 23

    6 Site Location and access1.75

    021 2.500 12 4.375 20

    7 Inadequate program schedulingand tight program scheduling

    2.875

    3 2.975 5 8.553 2

    8Design changes / Design

    variations by client

    2.45

    09 3.475 2 8.514 3

    9Hazards of environmental

    regulations

    1.55

    022 2.525 11 3.914 22

    10Incompetence of transportation

    facilities

    1.52

    523 2.200 16 3.355 24

    11 Increase in site overheads1.85

    020 2.725 8 5.041 14

    12 Industrial disputes 2.050 18 2.200 16 4.510 17

    13Local firms incompetence and

    low credibility

    1.92

    519 2.325 14 4.476 18

    14 Materials shortage2.70

    05 3.150 4 8.505 4

    15Obsoleteness of building

    equipment

    2.35

    010 2.000 22 4.700 16

    16Poor quality of procured

    accessory facilities

    2.72

    54 2.025 21 5.518 12

    17 Poor quality of procured materials 2.700 5 2.300 15 6.210 9

    18Problems due to partnersdifferent practice

    2.350 10 2.700 9 6.345 8

    19 Shortage in accessory facilities2.25

    015 1.975 23 4.444 19

    20 Shortage in skillful workers3.65

    01 3.500 1

    12.77

    51

    21Shortage in supply of water, gas,

    and electricity

    2.17

    516 1.925 24 4.187 21

    22 Subcontractors low credibility2.27

    514 2.550 10 5.801 11

    23 Unknown site physical conditions 2.475

    8 2.750 7 6.806 7

    24Unusual weather and force

    majeure

    2.50

    07 2.925 6 7.313 5

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    71/97

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    72/97

    D a t a A n a l y s i s a n d i n t e r v i e w

    a n a l y s i s

    planning stage. That will automatically lead owner to reduce quality to do his job

    within his budget. Unknown site physical condition is ranked seventh (RII =6.806).

    This is also impulsive risk at the planning stage occurring of this technical risk event

    will influence quality of the project. Problems arising out of partners differentpractice also create impact to quality of the project. It is eighth ranked (RII= 6.345).

    Poor quality of procured material is the 9 th ranked (RII= 6.201) risk event that could

    impact on quality of the output. Tenth risk is the design failures. Failures due to

    design will lead to impact on quality of output.

    Based on the argument mentioned in section 4.2.1.2.1, multiplying the probability

    and impact values might be misleading. This is achieved best by plotting the risk

    probability- cost impact matrix (figure 4.5).

    Figure 4. 5: Quality Significance of Technical Risk Factors

    The matrix shows five of the risks to be high (probability >3 and cost impact>3). It

    shows that the majority of the risks are medium (probability 2-3 and Cost impact

    >2.5). There are two technical risks that have probability of less than two and risks

    with cost impact less than 2.5. These are considered low.

    4.3.1.2 PERFORMANCE IN CONSTRUCTION LIFE CYCLE

    C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k 64

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    73/97

    D a t a A n a l y s i s a n d i n t e r v i e w

    a n a l y s i s

    The performance in construction project life cycle analysis in figure 4.6 and table 4.9

    illustrates the performance in each stage of the construction life cycle simply.

    According to figure 4.6, construction stage of the construction life cycle is having

    highest performance of technical risk.

    Considering data set collected through the questionnaire survey to measure the

    magnitude of performance level of risk events in construction life cycle, Cronbachs

    alpha was calculated for each data set. The alpha values for data set using for the

    analysis of performance of risk events in programming stage is = 0.959, planning

    stage is 0.755, tendering stage is 0.777 and for the production stage data set = 0.949.

    According to Nunnally and Bernstein (1978) as described in 4.2.1.2, they are reliable

    data sets.

    A careful look at Figure 4.6 confirms the argument that the highest magnitude or the

    performance of technical risk in the construction life cycle is in the construction

    stage. When comes to construction stage to the inception or the programming stage,

    it is reducing.

    Unusual weather and force majeure and shortage in skillful workers are having

    highest magnitude at the construction stage (RII= 4.000). Second highest are

    unknown site physical conditions and local firms incompetence and low credibility.

    That is because such kind of technical risk events are having more probability of

    occurrence at that stage. Moreover, third highest is design changes/ design variation

    by client. Clients tend to do design changes and variation at this stage as they realize

    the actual design requirements only at this stage.

    According to table 4.9 and figure 6, it is clear that there are only several risk events

    in the tendering stage, which are having high performance. Estimation errors, design

    failures, inadequate program scheduling and tight program scheduling, design

    changes, / design variations by client are that risk events.

    Table 4. 9: Performance of risk events in construction life cycle

    C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k 65

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    74/97

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    75/97

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    76/97

    D a t a A n a l y s i s a n d i n t e r v i e w

    a n a l y s i s

    construction contracts as owners can place any risks to the contractor. Contractors

    usually respond to these risks by increasing their contingency and markup, which

    ultimately increase the contract price to the owner. Interviewed respondents indicatedthat risks are not allocated appropriately in the Sri Lankan construction industry.

    The analysis of actual and expected risk allocations based on the questionnaire

    survey results are presented in table 4.10 and figure 4.7. The table and figure denote

    subjective analysis.

    Moreover, considering the data set gained from the questionnaire survey for the

    allocation of risk events among contracting parties, Cronbach's Alpha was

    calculated for the data set. The alpha values for data sets taken for the analysis

    (Annexure 05) are above than the value stated in section 4.3.1.1. Therefore, data

    taken for the analysis are reliable.

    In accordance with figure 4.7, the majority of the technical risk events allocated to

    contractors. This is probably due to the culture and widespread use of traditional

    contracts that places most of the risk on the contractor. Allocation of risk among

    parties in the event of design failure is too high to the consultant. Even though figure

    is showing that, most of the interviewed respondent pointed out that, the risk

    allocation to consultant is not properly practiced in Sri Lanka. In the event of

    consultant failure, there is no a remedial action. In such kind of situation usage of

    personal indemnity assurance is very much low (less than 17%). It is clearly shown

    by following figure 8. It is almost zero, where the consultant and client both are Sri

    Lankan companies.

    Risk allocation to the client is very much low according to findings of interviews. In

    practical situation consultant, risk also has to be endured by the client in Sri Lanka.

    Because contractor always try to price the risk, but there is a limitation. If he or she

    price every risk, in the event of competitive tendering there is a probability of losing

    it. Therefore, he may price most important risk events only.

    C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k 68

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    77/97

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    78/97

    D a t a A n a l y s i s a n d i n t e r v i e w

    a n a l y s i s

    Figure 4. 7: Risk allocation of technical risk factors

    Figure 4. 8: usage of PIA

    Most significant risk factor is the Accident/ collision to contractor, where majority ofrespondents are considered that the in the event of accident /collision, risk allocation

    to the contractor is considerably high. According to table 4.10, it is high.

    According to questionnaire survey findings and interviews findings consultant is the

    person, who is having lesser allocation of technical risk.

    Based on the questionnaire findings, design changes / design variations by client is

    the technical risk having higher allocation to the client (RII= 3.700).

    C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k 70

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    79/97

    D a t a A n a l y s i s a n d i n t e r v i e w

    a n a l y s i s

    4.3.1.3.1 PROPER ALLOCATION OF TECHNICAL RISK IN CONTRACT

    Proper contractual arrangements determine who is more capable of controlling

    various specific risks. Generally, the local construction contracts mainly use

    condition of contract to do it. Usage of condition of contract type is shown in figure

    4.9. Considering the findings of the structured interviews, ICTAD is the most using

    document as the condition of contract for the building projects, but interviewed

    respondents pointed out that the usage of the type of document will depend on the

    type of the client. Usage of ICTAD is 67% percentage. For the government project

    they most of the time use ICTAD. However, for the foreign Clients have to use

    FIDIC condition of contract.

    Figure 4. 9: Type of condition of contract use in Sri Lankan building construction industry

    However, interviewed respondents indicated that, allocation of technical risk

    between consultant and client in a contract is very much low in Sri Lanka. In most of

    the cases client has to suffer them. Because usage of condition of contract between

    consultant and client does not much consider about the risk allocation. In addition,

    they have argued that, effective allocation of technical risk among parties is a good

    risk mitigation strategy.

    4.4 REVIEW OF FINDINGS

    Any construction work will be subject to some technical risks, such as changes in

    design, equipment failure, shortage in skillful workers, material shortage, accident/

    collision, etc. However, through this research it was attempted to forecast typical

    C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k 71

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    80/97

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    81/97

    D a t a A n a l y s i s a n d i n t e r v i e w

    a n a l y s i s

    Figure 4.11: Most Significant Risk factors performance in life cycle

    Furthermore, figure 11 illustrates the performance of most significant technical risk

    factors within the life cycle of construction project in Sri Lankan construction

    industry. According to above argument, most significant risk factor is shortage in

    skillful workers. It is regularly in the production stage. Moreover, according to figure

    12, shortage of skillful workers is risk to contractor than other parties in the

    construction industry. However, it is not much affecting to consultant but to some

    extent affect to the client.

    C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k 73

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    82/97

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    83/97

    D a t a A n a l y s i s a n d i n t e r v i e w

    a n a l y s i s

    C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k 75

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    84/97

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    85/97

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    86/97

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    87/97

    C o n c l u s i o n a n d R e c o m m e n d a t i o n

    Apart from that there were seventeen other technical risk factors such as design

    failures, accident/ collision, site location and access, etc. which were not as severe as

    aforesaid factors, but when concerning risk managing approaches, these factors

    should also be considered in total risk management strategy.

    Based on the interview findings, it was able to figure out usage of type of condition

    of contract and usage of PIA in Sri Lankan building construction industry. According

    to interviewed respondents, risks were allocated more to the client ultimately.

    Because, contractors risk is capable to be priced and consultant risk automatically

    comes to client according to Sri Lankan practice.

    This study is important as it sheds the light on the risks in a booming Sri Lankan

    construction industry. Technical risk identification and assessment is an important

    step in project risk management and shows the significance of several risks that are

    present in the industry. This study lays the foundation to assists local companies in

    negotiating their contracts as to the proper allocation of risks. This study also helps in

    decision making regarding risk response planning and control.

    Moreover, all of this mentioned critical technical risk factors more relevant to

    quantity surveyor than other professionals in the building construction industry. That

    is because, client quantity surveyor, consultant quantity surveyor or contractor

    quantity surveyor most of the time try to give a monitory value for that particular risk

    by predicting them at the initial stage. That would be the most efficient method of

    mitigation of risk and minimizing the effect of the risk to the building construction

    project. Therefore, the quantity surveyor needs to be more concerned about

    especially critical risk factors.

    5.2 RECOMMENDATION

    Considering all facts above discussed and identified, the cost, time and quality

    achievement of the building construction projects are effected by several critical

    technical risk factors, which are uncontrollable or unforeseeable by the parties to the

    C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k 79

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    88/97

    C o n c l u s i o n a n d R e c o m m e n d a t i o n

    contract at the initial stage. All those risk factors cannot be eliminated completely

    and the best would be to minimize the occurrence and impact to the project

    objectives by implementing proper mitigation process from initial stage with proper

    coordination among parties. Moreover, using proper condition of contract among

    parties can also manage the risk.

    Through considering project perspectives, risk mitigation process can be decided

    along these lines;

    Whenever a project needs to consider more about the time then time

    significant technical risk factors has to be taking in to account.

    If quality is the most considerable project perspective, then quality significant

    risk factors have to be taking in to account.

    Where, the project having a limited budget cost. Cost significant technical

    risk factors have to be taken into consideration.

    Besides, commonly for any type of building construction project most criticaltechnical risk factors have to be taken into consideration.

    It will lead to complete the building construction project by achieving all project

    goals namely; within the time limit, within the budget limit, and with quality

    achievement.

    Further, it recommends, improving the knowledge on risk management

    techniques and its applications; there should be a proper training or learning of

    the risk management field which is important to practitioners in the industry

    5.3 FURTHER RESEARCH

    The research was carried out within building construction project, and same

    research can be done to the civil construction projects.

    C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k 80

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    89/97

    C o n c l u s i o n a n d R e c o m m e n d a t i o n

    The effectiveness of contingency in covering unforeseeable risk involvement in

    building projects.

    Suitability of risk handling tools in better recovery of risk, in the contractors

    perspective.

    Proper usage of condition of contact to handle construction risk.

    C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k 81

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    90/97

    R e f e r e n c e s

    References

    1) Adams, A.K., 2006. Expert elicitation and Bayesian analysis of construction

    contract risk: an investigation. Construction management and economics, 24,

    81-96.

    2) Ahmed, S.M. and Azhar, S.A., 2004. Risk management in the Florida

    Construction Industry. Challenge and opportunities for engineering

    education, research and development 2-4 June 2004, Miami, Florida, USA.

    Sustainable Environment, Track-Paper No. 077, 25(3), 601614.

    3) Akintoye, A.S. and Macleod, M.J., 1997. Risk analysis and management in

    construction.International journal of project management, 15(1), 31-38.

    4) Akintoye, A.S. and Macleod, M.J., 1997. Risk analysis and management in

    the construction.International journal of project management, 15(1), 31-38.

    5) Al-Bahar, J.F., 1990.Systematic risk management approach for construction

    projects. Journal of construction engineering and management, 116(3), 530-

    538.

    6) Andi, 2006. The importance and allocation of risks in Indonesian

    construction projects. Construction management and economics, 24(1), 69

    80.

    7) Archbold, A.C., 2005. Managing the bottom line: risk management in

    policing.International journal of police strategies & management, 28(1), 30-

    48.

    8) Bajaj, D., Oluwoye, J. And Lenard, D., 1997. An analysis of contractors

    approaches to risk identification in new south wales, Australia. Construction

    management and economics, 15, 363-369.

    C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k 82

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    91/97

    R e f e r e n c e s

    9) Baker, S., Ponniah, D. and Smith, S., 1999. Risk response techniques

    employed currently for major projects, Construction management and

    economics, 17, 205-213.

    10)Barber, R., 2005. Understanding internally generated risks in projects.

    International journal of project management, 23(8), 58490.

    11)Carter, R.L. and Doherty, N.A., 1974. Handbook of Risk Management,

    Kluwer-Harrap Handbooks: London.

    12) Chapman, R.J., 2001. The controlling influences on effective risk

    identification.International Journal of project management, 19, 147160.

    13) Chicken, J.C. and Posner, T., 1998. The philosophy of risk. Thomas Telford.

    14) Cronbach, L. J., 1951. Coefficient alpha and the internal structure of tests.

    Psychometrika, 16(3), 297-334

    15) Dallas, M., 2006. Value and risk management. Blackwell: UK

    16) Dhanasinghe, I., 2007. Risk allocation and risk handling of road project in

    sri lanka . Unpublished Dissertations (BSc). University of Moratuwa, Sri

    Lanka.

    17) Edwards, R.J. and Browen, P.A., 1998. Risk and risk management in

    construction: a review and further directions for research. Construction and

    architectural management, 5(4), 339-349.

    18) El-Sayegh, S.M., 2008. Risk assessment and allocation in the UAE

    construction industry. International journal of project management, 26(1),

    431-438.

    19)Flanagan, R. and Norman, G., 1993, Risk Management and Construction,

    Blackwell Science Ltd: Oxford.

    20) Fong, S. W., 1987. Risk management. The Cost Engineer, 2, 12-16.

    C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k 83

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    92/97

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    93/97

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    94/97

    R e f e r e n c e s

    41) Perera, K.B.D., 2006. Simulation modeling for time and cost overruns in

    road rehabilitation projects in Sri Lanka. Unpublished Dissertations (BSc).

    University of Moratuwa, Sri Lank.

    42) Perry J.G. and Hayes, R.W., 1985. Risk and its management in

    construction projects. Proceedings of institute of civil engineers, 78(1), 499

    521.

    [

    43)Peter, D., (1997). Risk analysis and management for major construction

    projects. Cobra 1997 [online], Available from: http://www. Rics-

    foundationorg/aboutus.html

    44) Poh, Y.P. and Tah, J.H.M., 2006. Integrated durationcost influence network

    for-modeling risk impacts on construction tasks. Construction management

    and economics, 24(8), 861868.

    45) Pushpakumara, P.A.D., 1997. Managing the pricing risks and uncertainties

    on below ground construction works in buildings. Unpublished Dissertations

    (BSc). University of Moratuwa, Sri Lank.

    46)Rahman, M.M. and Kumaraswamy, M.M., 2005. Assembling integrated

    project teams for joint risk. Journal of construction engineering and

    management, 23(4), 365375.

    47) Rowe, W.D., 1977. An anatomy of risk. New York: Wiley.

    48)Saunders, M., Lewis, P. and Thornhill, A., 2004, Research Methods for

    Business Students, 3rd

    ed, Singapore: Pearson Education Pte Ltd.

    49)Senarathne, S., 2005. A knowledge-based approach to managing project

    change in the construction phase within collaborative ream settings.

    Unpublished Thesis (PhD). University of Salford: UK

    50) Shen, L.Y., 1997. Project risk management in Hong Kong. International

    Journal of project management, 15(2), 101105.

    C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k 86

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    95/97

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    96/97

  • 7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc

    97/97

    A p p e n d i x

    Appendix