technical risk factors in building construction.doc
TRANSCRIPT
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
1/97
Declaration
I hereby declared that this report submission is my own work and to the best of my
knowledge. It does not contain any material previously published or written by any
other person or any material which substantial extent has been accepted for the award
of any degree or diploma of a university or other institution of higher education,
except where referenced are mentioned.
Rathnayake R.M.R.S.B
Department of Building Economics,
Faculty of Architecture,
University of Moratuwa,
Sri Lanka,
April 2009
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
2/97
Acknowledgement
This research study embraces much dedication and ready assistance received from many
people, who contributed in ample ways to complete this study. Consequently, I take this
opportunity to convey my sincere gratefulness to every one of them.
It is my foremost duty to pay my gratitude to the Department of Building Economics,
University of Moratuwa, and all the academic as well as non academic staff of the department
for the tremendous service rendered. I extend my gratitude to Mr. Indunil Senevirathna, Head
of the Department of Building Economics, for his keen interest, encouragement and the
guidance to the achievement of producing this dissertation.
Furthermore, I am grateful to my supervisor, Mrs. Kanchana Perera, Senior lecturer,
Department of Building Economics, for her outstanding supervision, her guidance,
encouragement, and constructive criticisms significantly contributed towards the successful
completion of this research. I extend my gratefulness to Dr. Sepani Senarathna, the
dissertation coordinator, for her interest and dedication throughout the year. I should express
my appreciation to senior lectures of the Department of Building Economics Prof. R.
Rameezdeen, Mr. Suranga Jayasena, Mrs. Yasangika Sandanayaka and Mr. Sandun Fernando
for their valuable guidance throughout the research process.
I convey my special thanks to Mr. Lalith Rathnayaka (VForm consultants), Mr Thilak
kolonne (VForm consultant),Mr. Elmo Fernando (Havelock city project) Mr. Pieris
(Department of Mathematics, University of Moratuwa) for their special guidance, assistance
and encouragement provided to clarify the problems of this research.
I would like to convey my utmost gratitude to all the professionals of organizations who gave
me a great support in many ways for the success of this research.
Finally I express my heartfelt thanks for my family members, relations, colleagues and my
seniors and juniors for giving me an outstanding company to make this dissertation possible.
Rathnayake R.M.R.S.B.
24th April 2009
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
3/97
T a b l e o f C o n t e n t
Table of Contents
Acknowledgement ...................................................................................ii
Table of Contents......................................................................................I
List of Figures.........................................................................................II
List of Tables.........................................................................................III
List of Appendix.....................................................................................IV
Abbreviations ..........................................................................................V
Abstract...................................................................................................VI
Chapter 01................................................................................................1
Chapter 02................................................................................................7
Chapter 03..............................................................................................36
Chapter 04..............................................................................................47
Chapter 05..............................................................................................76
References .............................................................................................82
Appendix ................................................................................................89
C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k I
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
4/97
L i s t o f F i g u r e s
List of Figures
Figure 3.1: Research Process................................................................37
Figure 3.2: Nested reseach methodology..............................................38
Figure3.3: Research methodology illustration.....................................39
C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k II
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
5/97
L i s t o f T a b l e s
List of Tables
Table.2. 1: Risk identification process..................................................19
Table.2. 2: Risk identification................................................................19
C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k III
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
6/97
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
7/97
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
8/97
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
9/97
I n t r o d u c t i o n
Chapter 01
1 INTRODUCTION
1.1 BACKGROUND
The concept of risk can be applied to nearly every human decision making action of
where, the consequences are uncertain (Flanagan and Norman 1993). The word of
risk has entered in to the English language in the mid 17 th century, coming from the
French word risqu (Covello and Mumpower 1985 cited Thilakarathne 2007).
Cooper and Chapman (1987 cited Dent 1997, p. 1)define risk as exposure to the
possibility of economic or financial loss or gain physical damage or injury or delay
as a consequence of the uncertainty associated with pursuing a particular course of
action.
Construction industry is one of the most dynamic and challenging industries
(Woodward 1997) and it is subjected to more risk and uncertainty than many otherindustries (Flanagan and Norman 1993). Furthermore, according to Patrick et al.
(2007), Kangari (1995), Uher and Toakley (1999), and Thevendran and Mawdesley
(2004),risk relates to construction industry and obviously it is related to construction
projects.Hence, construction projects consistently expose to various sources of risks
(Poh and Tah 2006). Those risks can effect to productivity, performance, quality, and
budget of a construction project (Kangari 1995). However, risks cannot be eliminated
(Patricket al. 2007), but it can be minimized or transferred from one stakeholder to
other stakeholder in the construction process (Kangari 1995). Thus, formal and
efficient risk management process is needed to manage all types of risks in
construction projects (El-Sayegh 2008).
Consequently, management of risks has turned into a main part of the organizational
activities (Flanagan and Norman 1993). The risk management is a tool which
control risks in construction projects(Hamshayini 2007, p. 1). The main aim of risk
management is to assist all construction project aims (Mills 2001) by mitigating the
risk, transferring the risk to other parties, or sharing the risk among the parties
C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k 1
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
10/97
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
11/97
I n t r o d u c t i o n
the management of risk is significantly influenced by the uniqueness of the
construction industry of that particular country. As such as, it emphasizes a need of
in depth investigation to the overall consequences and uncertainties in construction
risk management for a variety of project participants in Sri Lankan context.
Besides, according to the empirical study by Kangari (1995) revealed that
management practices are mainly focused on construction risk allocation towards
perception of the typical large contractors and owners. Further, the same study
emphasized the identification of strategies or usage of risk management techniques to
add value to project delivery and improve the effectiveness of the construction
industry throughout of the process of construction.
To handle risks in construction projects appropriately, it is required to assign them
scientifically among parties (El-Sayegh 2007). Thus, scientific assignment of risk
among project parties can be achieved by only if it analytically investigates the
overall consequences and uncertainties in construction risks and risk supervision
(Andi 2006). More importantly, this can only be achieved if all parties do understand
their risk responsibilities properly (Perera 2006).
Identification of sources of risk is vital aspect in risk management process
(Tchankova 2002).Edward and Browen (1998)supported the same argument stating
that for a proper risk management process, it has to first identify source of risks.
Further, the same study classified the sources of risks in to nine categories: financial;
legal; management; market; policy; health; cultural; social and political risks.
However, among all these risks sources/ factors, the technical risk sources/ factors
are not well-represented or not evident in risk management literature (Edwards and
Broun 1998).
According to above mentioned findings and facts, to trounce them and fill the gap,
which had already figured out. Thus, this emphasized a need of research in risk
management area with orientation to identify and analyze possible risk factors
associated with building construction process and further to assess their
consequences and uncertainties towards project parties/stakeholders; specially
towards contractors and owners.
C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k 3
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
12/97
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
13/97
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
14/97
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
15/97
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
16/97
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
17/97
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
18/97
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
19/97
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
20/97
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
21/97
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
22/97
L i t e r a t u r e R e v i e w o n R i s k M a n a g e m e n t
However, when consider above-mentioned definitions with compare to Nummedal et
al. (1996 cited Ahamad and Azar 2004) definition of risk management such as a
process to control the level of risk and to mitigate its effects and it is a systematic
approach for identifying, evaluating, and responding to risks encountered in a
project. It is convinced that that the risk management is a systematic process to
identify, evaluate and responding to risks encountered in a project. Nummedal et al.
(1996 cited Ahamad and Azar 2004) definition takes for this research as the
definition for the risk management.
The application of systematic risk management in construction projects has long
been recognized as an effective approach to minimizing risk impacts(Flanagan and
Norman 1993) and it will aims to identify and assess risk in order to enable them to
be understood clearly and managed effectively(Hillson 2003).
2.4.2.1 SYSTEMATIC RISK MANAGEMENT PROCEDURE
Systematic approach of risk management will be given assurance to the risk
management process by minimizing the missing of risk factors and there affect.
Basically, a systematic risk management process consist with three steps
Figure 2.3: Risk Management Umbrella
C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k 14
(Source- Dent 1997)
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
23/97
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
24/97
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
25/97
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
26/97
ExistenceUncertainty
PreliminaryChecklist
Risk Events/
ConsequenceScenarios
RiskMapping
Logical RiskClassification
Scheme
Risk CategorySummary Sheet
Risk Identification ProcessRisk Identification Process
L i t e r a t u r e R e v i e w o n R i s k M a n a g e m e n t
Controllable
Uncontrollable
Types
Severity
The objective of risk identification is to identify all possible risks (Highways agency
2001), categorize risks that could affect the project (Kangari 1995), and document
these risks (Flanagan and Norman 1993), not to eliminate risks from consideration or
to develop solutions for mitigating risks and those functions are carried out during
the risk assessment and risk mitigation steps. Some of the documentation and
materials should use in risk identification as they become available include these.
Risk identification process
Moreover, the degree, to which the identification process will influence the
effectiveness of risk management and its contribution to the overall project
management of any particular project, is dependent on the way the steps of the
process are implemented (Chapman 2001, p. 147).
Furthermore, proper implementation of these steps will ensure better effectiveness of
identification process and it will guide to better understanding of risk. Moreover, the
key factors involved in each step of the risk identification process demonstrate in
following figure and table. There are six steps involved in the risk identification
process. The following sections will discuss each step separately (Al-Bahar 1988
cited Al-Bahar 1990).
C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k 18
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
27/97
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
28/97
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
29/97
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
30/97
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
31/97
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
32/97
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
33/97
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
34/97
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
35/97
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
36/97
L i t e r a t u r e R e v i e w o n R i s k M a n a g e m e n t
2.7 THE ROLES OF THE PROJECTS DIFFERENT PHASES IN
RISK MANAGEMENT
According to Osipova (2007), construction process is traditionally divided into four
main phases:
Programme (Inception):- client has an idea about the project and analyses
conditions for its execution
Planning: - architects produce construction drawings according to the
clients requirements
Procurement (Tendering):- parties sign the contract.
Production: - contractor executes the job
Since, foreseen all risk at the inception stage is impossible and due to tendency of
identified risk in the programme stage to change during project implementation, joint
and consistent risk management is required throughout all projects (Rahman and
Kumaraswamy 2005). Furthermore, occurrence and effect of construction project
risk in different phases to the project participants difficult to foresee all risk only can
predict to some extend based on the available information in the early stages of the
construction project (Osipova 2007). Moreover, several authors highlighted the
importance of identification of project risk in the early stage of the construction
project life cycle ( Uher and Toakley 1999), (Rahman and Kumaraswamy 2005),
(Flanagan and Norman 1993), (Andi 2006).
Aforementioned facts create the need of developing a risk management framework
within construction project to identify the performance of risk in the construction life
cycle.
C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k 28
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
37/97
L i t e r a t u r e R e v i e w o n R i s k M a n a g e m e n t
2.6 PROJECT RISK CLASSIFICATION AND TECHNICAL RISK
IDENTIFICATION REGARDING TO SYSTEMATIC RISK
MANAGEMENT
2.6.1 PROJECT RISK CLASSIFICATION
Project risk classification is an important step in risk assessment process, because it
attempts to structure the various risks that may affect a project. There is various
classification of project risk with respect to deferent purposes (Edwards and Browen
1998), (Al-Bahar 1990 cited Ahmed and Azhar 2004), (Wong and Hui 2006), (Stoner
et al. 1997). Specially the construction risk is generally perceived as events that
influence project objectives of cost, time and quality and some of the project risks
can be predictable or foreseen (identifiable) while other may totally unforeseen. Due
to that, also it is very much important to classify project risks (Al-Bahar 1990 cited
Ahmed and Azhar 2004).
According to Edwards and Browen (1998), project risk classifies using the risk
source as the basis; primary classification would be human and natural. Natural risks
occur outside the human agencies, while human risk arise the humanly organizedsystem and this classification is illustrated following figure. Human risks relating to
construction project classifies further as social, political, economic, financial, legal,
managerial, technical, and cultural risks.
C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k 29
(Source- Edwards and Brown 1998)
Risk
Natural Human
PoliticalWeather
systemEconomic
Financial
Legal
Health
Managerial
Technical
Social
Cultural
Geological
system
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
38/97
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
39/97
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
40/97
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
41/97
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
42/97
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
43/97
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
44/97
R e s e a r c h M e t h o d o l o g y
Chapter 03
3. RESEARCH METHODOLOGY
3.1 INTRODUCTION
Main aim of this chapter is to outline the research methodology for this research and
specially illustrate the research design, which was followed throughout this research.
Initially, it is describing the research Process of this particular research and it
illustrates completely the Process of this research in a systematic manner using
figures.
Further, it is illustrating the research design together with the steps of the research
design and applicability of research design steps also illustrate.
3.2RESEARCH PROCESS
This research carried out mainly to identify the prevailing technical risk factors and
thereafter to analyze the allocation of risk among contraction parties, figure out
consequences of above risk of contracting parties, moreover to identify the
performance of technical risk in construction life cycle. Thus, it was essential to
think off an appropriate research Process, which is competent of identification risk
factors, which is paramount.
Further, by using a proper research process can be minimized the errors that can be
occurred during our research and can be reduced the mistakes done by the researcher.
Research process for this particular research illustrates using following figure,
C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k 36
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
45/97
R e s e a r c h M e t h o d o l o g y
Figure 3.1: Research Process
C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k 37
Further
Research
Research Question
Establish Aim & objective
Data Collection
Preliminary Survey
Structured Interview Questioner Survey
Data Analysis
Conclusion & Recommendation
Literature Review
Interviewing Literature Review
Guide to
Sampling and
Factor Selection
Background study
Sample
Collect
ion
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
46/97
R e s e a r c h M e t h o d o l o g y
3.3 RESEARCH DESIGN
Research design is complying with three key steps; in sequent, identifying researchphilosophy, identifying research approach, identifying research technique (Kagioglou
et al. 2000 cited Senarathne 2005) Where the selection of research techniques for
data collection and data analysis is based on research approach and the selection of
research approach is based on the research philosophy.
Figure 3.2: Nested reseach methodology
Further, research methodology illustrated by the Saunders et al. (2003) as shown in
the following figure,
C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k 38
(Source- Kagioglou et al. 2000 cited Senarathne 2005)
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
47/97
R e s e a r c h M e t h o d o l o g y
Figure3.3: Research methodology illustration
3.3.1 RESEARCH PHILOSOPHY
Research philosophy selection is the initial step of research designing and it is
depend on the way researcher think about to develop the knowledge. Further, it
directs to the researcher to select appropriate research strategy among one offollowings,
Positivism: - are the natural science researchers. In positivism,
working with an observable social actuality and the finished product
of the research can be generalized (Remenyi et al. 1998 cited saunders
et al. 2003)
Interpretivism: - try to discover the details of the situation to
understand the reality or perhaps reality is working behind them
(Remenyi et al. 1998 cited Saunders et al. 2003).
Realism: - believe that the reality is subjective and interior to the
people and it shares the both view of positivism and interpretivism.
By considering the nature of this research problem it is obvious that this piece of
research needs a vigilant observations and identification about the construction
project risk to manage the to overcome problems created by the construction project
C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k 39
(Source- Saunders et al. 2003)
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
48/97
R e s e a r c h M e t h o d o l o g y
risk to the construction parties throughout the construction project life cycle. Due to
that reason interpretivism select as the research philosophy for this research.
3.3.2 RESEARCH APPROACH
Appropriate research approach should select to deal with the research question
according with the research philosophy. Research approach approaches are about to
organise research activities, especially including the collection of data from the
population in a way that meet the reach problems aims and objectives. According to
Saunders et al. (2003), research approach can be divided in to two categories,
Deductive:- first develop a theory and hypothesis, and design research
strategy to test the hypothesis and moreover this is owes to positivism,
Inductive:- first collect data and develop a theory as a result of the data
analysis, and moreover this is owes to interpretivism,
When considering circumstance of the this research problem, it is important to
identify the technical risk factors , consequences of them and their performance inthe construction life cycle. Therefore as the research approach to this research
deductive approach is selected.
According to the study of, Kagioglou et al. (2000 cited Senarathne 2008);following
approaches are the most popular and widely used research approaches in the world.
Experiments laboratory, quasi-experiments
Surveys
Case study research
Ethnography
Action research
Grounded theory
C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k 40
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
49/97
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
50/97
R e s e a r c h M e t h o d o l o g y
Consequently, very large samples are feasible, making the results statistically
significant even when analyzing multiple variables.
Many questions can be asked about a given topic giving considerable flexibility
to the analysis. There is flexibility at the creation phase in deciding how the questions will be
administered: as face-to-face interviews, by telephone, as group administered
written or oral survey, or by electronic means.
Standardized questions make measurement more precise by enforcing uniform
definitions upon the participants.
Standardization ensures that similar data can be collected from groups then
interpreted comparatively (between-group study).
3.3.3 RESEARCH TECHNIQUE
3.3.3.1 DATA COLLECTION TECHNIQUE
By considering the circumstances of this of this particular research, especially
neediness of the identification and perceptions of construction industry practitioners
about the allocation of technical risk factors among contract parties, questioner
survey selected as the basic technique to collect data. Furthermore, for fill the gap
creating by the questioner survey, semi structured interview was used for thecritically identify the actual scenario.
Preliminary Survey
Preliminary survey carried out to find out, current prevailing condition of the risk in
building construction industry and to identify the significance technical risk factors
relate to building construction industry. Moreover, it was conducted in two ways,
C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k 42
http://var/www/apps/conversion/tmp/scratch_4/com2d4.cfmhttp://var/www/apps/conversion/tmp/scratch_4/com2d4.cfmhttp://var/www/apps/conversion/tmp/scratch_4/com2d4.cfmhttp://var/www/apps/conversion/tmp/scratch_4/com2d4.cfmhttp://var/www/apps/conversion/tmp/scratch_4/com2d4.cfmhttp://var/www/apps/conversion/tmp/scratch_4/com2d4.cfmhttp://var/www/apps/conversion/tmp/scratch_4/com2d4.cfmhttp://var/www/apps/conversion/tmp/scratch_4/com2d4.cfmhttp://var/www/apps/conversion/tmp/scratch_4/com2d4.cfmhttp://var/www/apps/conversion/tmp/scratch_4/com2d4.cfmhttp://var/www/apps/conversion/tmp/scratch_4/com2d4.cfmhttp://var/www/apps/conversion/tmp/scratch_4/com2d4.cfmhttp://var/www/apps/conversion/tmp/scratch_4/com2d4.cfmhttp://var/www/apps/conversion/tmp/scratch_4/com2d4.cfmhttp://var/www/apps/conversion/tmp/scratch_4/com2d4.cfmhttp://var/www/apps/conversion/tmp/scratch_4/com2d4.cfmhttp://var/www/apps/conversion/tmp/scratch_4/com2d4.cfmhttp://var/www/apps/conversion/tmp/scratch_4/com2d4.cfmhttp://var/www/apps/conversion/tmp/scratch_4/com2d4.cfmhttp://var/www/apps/conversion/tmp/scratch_4/com2d4.cfmhttp://var/www/apps/conversion/tmp/scratch_4/com2d4.cfmhttp://var/www/apps/conversion/tmp/scratch_4/com2d4.cfmhttp://var/www/apps/conversion/tmp/scratch_4/com2d4.cfm -
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
51/97
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
52/97
R e s e a r c h M e t h o d o l o g y
construction life cycle. Ultimatly, in the forth question relates to the proper allocation
of the risk among construction parties namely cotractor, client and consultant.
The questionnaire survey forms were distributed to construction professionals
associated with the Sri Lankan construction industry. The completed responses
collected personally.
Structured Interviews
With the guidance of the preliminary survey, structure for the structured interview
was prepared and moreover allocation of risk, consequence, and occurrence of that
particular risk factors within the construction lifecycle was try to figure out. This wasconducted together with the questioners and interviewed the construction
practitioners. In most of the cases interviewed Project manager, Project Engineer,
Site Engineers, and specially quantity surveyor to ensure the monitory terms relate to
technical risk.
3.3.3.2 DATA ANALYSIS TECHNIQUE
Collected data from above three methods evaluate systematically to achieve proper
answer to the research question.
For analyze the allocation of risk to the contracting parties, figure out the
consequences of above risk of contracting parties, and identify performance of risk in
construction life cycle from the collected data. Likert Scale was used in questioner
survey.
Likert Scale
Likert scale can be recognized as the technique of measuring the different attitudes
towards a statement by asking the respondent to indicate their preference in a series
of short statement on a given range of responses. It can be analyzed the general
C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k 44
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
53/97
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
54/97
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
55/97
D a t a A n a l y s i s a n d i n t e r v i e w
a n a l y s i s
Chapter 04
4 DATA ANALYSIS AND INTERVIEW ANALYSIS
4.1 INTRODUCTION
With the aim of upgrading the knowledge in realm of risk management, the research
had first conducted a board literature review in the risk management field with
particular prominence in building construction projects in Sri Lankan perspective.
Prime intention of this chapter is to analysis the degree of risk management aspects
using in technical risk management in construction projects in Sri Lanka. Chapter 2
provided the rigid knowledge of risk management and risk management measures
concerning the technical risk management. Besides, the behavior of the contraction
projects and construction project partys behavior regarding risk management. This
chapter completely based on information collected from construction industry
practitioners through questioner survey and interviews.
Within this chapter consists of the results, after analyzing the data, collected from
questionnaire survey and interview. Moreover, ultimately, discussion carried out with
the intention of approaching the conclusion of this study.
C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k 47
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
56/97
D a t a A n a l y s i s a n d i n t e r v i e w
a n a l y s i s
4.2 PRELIMINARY SURVEY
4.2.1 RISK FACTOR IDENTIFICATION
Various risks were identified in the first stage of this research and they were
illustrated broadly in the chapter 02. This was accomplished mainly through
literature review. Twenty four technical risk factors were identified through the
literature review.
For the fulfillment of aim and objective of the research respondents were asked to
state availability of the listed risk factors which were found out though the literature
review. That was asked to do considering respondents knowledge and experience
about listed technical risk factors. This was done with the intention of removing risk
factors where none of respondent stated as; a particular risk factor could not be seen
in Sri Lankan construction industry. However, according to finding of the
preliminary survey, technical risk identification can be illustrated by following figure
4.1.
According to figure 4.1, all the risk events identified were there in Sri Lankan
construction industry. Based on the survey result, thirty-four respondents out of forty
stated that they have faced to estimation errors considering their experience. Eighty
five percent of the total projects were having estimation errors. Moreover, design
failures/ design variation by client is the second highest technical risk factor. Thirty
three out of forty respondents mentioned that they faced that.
Thirty two out of forty respondents had faced to shortage in skillful workers within
their projects. It means there is an 80% probability of having shortage in skillful
workers for a project. Apart from above mention three technical risk factors,
according to respondents identification there were 6 risk factors having more than
50% probability of occurrence in a particular project.
C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k 48
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
57/97
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
58/97
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
59/97
D a t a A n a l y s i s a n d i n t e r v i e w
a n a l y s i s
Figure 4. 2: Respondents Profile
4.3.1 RSEARCH FINDINGS
4.3.1.1 SIGNIFICANCE OF TECHNICAL RISK FACTORS
Based on the survey results, the relative importance index (RII) was calculated for
each risk based on probability, impact and rating. These risks were then ranked
according to their RII. The results are presented in tables and figures for easy
illustration.
Significance of technical risk was measured considering the project perspectives
independently such as,
Impact to the cost of the project
Impact to the time of the project
C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k 51
SubjectNo of Respondents
Client Contractor Consultant Total
Number of Respondents 11 14 15 40
Less Than 5 Years 1 5 6 12
5-10 Years 1 4 0 5
Above 10 Years 9 5 9 23
Project Scale
less than 500
million1 2 6 9
500-1000
million
5 7 5 17
Above 1000
million5 4 5 14
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
60/97
D a t a A n a l y s i s a n d i n t e r v i e w
a n a l y s i s
Impact to the quality of the project
Reliability of data
Considering the data set gain from the questionnaire survey for the probability,
Cronbach's Alpha was calculated for the data set. The alpha is 0.743. According to
Nunnally and Bernstein (1978), in a reliable data set the alpha should be above 0.7. It
means the data set collected to calculate RII for each risk based on probability is
reliable.
Moreover, considering the data set collected to calculate RII for each risk based on
cost impact, Cronbachs alpha was calculated. The alpha is 0.840. It denoted that the
data set collected through questionnaire to calculate RII for each risk factor based on
cost impact is reliable.
Furthermore, for data sets collected for the time impact and quality impact also
Cronbachs alphas were calculated. Alphas are consequently 0.794 and 0.829.
According to Nunnally (1978), those are reliable data sets.
4.3.1.1.1 SIGNIFICANT TECHNICAL RISK FACTORS CONSIDERING
COST OF THE PROJECT
Cost of the project is one of the most important project perspectives when
considering the budget of the project, which is allocated by the employer, or the
owner of the project. Therefore, it is more important to consider impact to the cost of
the project by the technical risk factors.
Based on the survey, the results are presented in table 4.3. Table 4.4 presents the top
10 technical risks in the Sri Lankan construction industry based on the risk rating
considering impact to the cost of the project. According to risk rating values, most
significant technical risk is estimation errors. The RII is 11.970. Estimation errors are
the key technical risk when considering the cost perspective of the project in Sri
C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k 52
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
61/97
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
62/97
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
63/97
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
64/97
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
65/97
D a t a A n a l y s i s a n d i n t e r v i e w
a n a l y s i s
4.3.1.1.2 SIGNIFICANCE CONSIDERING TIME OF THE PROJECT
Time of the project is one of the most important project perspectives. When
considering time limitation that is given by the owner. That could be due to demand
to the project at market. Therefore, it is more important to consider impact to the
time of the project by the technical risk factors.
Table 4. 5: Significance of Risk Considering Time of the Project
C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k 57
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
66/97
D a t a A n a l y s i s a n d i n t e r v i e w
a n a l y s i s
Based on the survey, the results are presented in table 4.5. Table 4.6 presents the top
10 technical risks in the Sri Lankan construction industry based on the risk rating
considering impact to the time of the project. According to risk rating values, most
C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k 58
No. RISK FACTORS
Impact-
TimeProbability Rating
RII-
(1)
RankRII-
(2)
RankRII-
(3)
Rank
1 Design failures 3.100 7 2.050 20 6.355 15
2 Equipment and system failures 2.675 17 2.150 19 5.751 20
3 New technology failures 2.875 11 2.200 18 6.325 16
4 Estimation errors 2.881 10 3.325 3 9.579 6
5 Accident/ Collision 2.400 22 2.500 12 6.000 19
6 Site Location and access 2.550 21 2.500 12 6.375 14
7Inadequate program scheduling
and tight program scheduling3.825 1 2.975 5 11.379 4
8Design changes / Design
variations by client 3.300 6 3.475 2 11.468 3
9Hazards of environmental
regulations2.825 12 2.525 11 7.133 11
10Incompetence of transportation
facilities2.800 14 2.200 16 6.160 17
11 Increase in site overheads 2.900 9 2.725 8 7.903 8
12 Industrial disputes 3.425 5 2.200 16 7.535 10
13Local firms incompetence and
low credibility2.775 15 2.325 14 6.452 13
14 Materials shortage 3.675 3 3.150 4 11.576 2
15Obsoleteness of building
equipment2.675 17 2.000 22 5.350 22
16Poor quality of procured
accessory facilities2.675 17 2.025 21 5.417 21
17Poor quality of procured
materials2.650 20 2.300 15 6.095 18
18Problems due to partners
different practice2.825 12 2.700 9 7.628 9
19 Shortage in accessory facilities 2.225 24 1.975 23 4.394 24
20 Shortage in skillful workers 3.450 4 3.500 1 12.075 1
21Shortage in supply of water, gas,and electricity
2.325 23 1.925 24 4.476 23
22 Subcontractors low credibility 2.750 16 2.550 10 7.013 12
23 Unknown site physical conditions 3.100 7 2.750 7 8.525 7
24Unusual weather and force
majeure3.700 2 2.925 6 10.823 5
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
67/97
D a t a A n a l y s i s a n d i n t e r v i e w
a n a l y s i s
significant technical risk is Shortage in skillful workers. The RII is 12.075. As
illustrated in 4.3.1.1.1, construction industry is not having permanent labour force.
Therefore, shortage in skillful workers might be a key risk to the project significance
considering the time impact of the project.
Table 4.6: Top Ten Ranked Risk Factors Considering Significance Risk
The fourth risk is owners often impose tight construction schedule (RII=11.379) that
might be difficult and impractical to achieve. This might be caused by the
importance of time to market but often is caused by political reasons. Due to difficultand impracticality this will definitely influence time of the project.
Unusual weather and force majeure is ranked fifth (RII=10.823). This is a risk, which
cannot be easily predicted but effect to time of the project is considerably high. Most
importantly estimation errors which ranked 6 th (RII= 9.579) will also be an impact to
the project as described in section 4.2.1.2.1. Unknown site physical condition is
ranked 7th (RII =8.525). This is also impulsive risk at the planning stage and
occurring of this technical risk event will influence time of the project. The eighth
risk event is contractor related. Increasing site overhead is the ranked eighth (RII=
7.903). Problems arising out of partners deferent practice also create impact to time
of the project. It is ranked ninth (RII= 7.628). Tenth risk is the industrial disputes.
C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k 59
No RISK FACTORS RII Rank
a Shortage in skillful workers 12.075 1b Materials shortage 11.576 2
c Design changes / Design variations by client 11.468 3
dInadequate program scheduling and tight
program scheduling11.379 4
e Unusual weather and force majeure 10.823 5
f Estimation errors 9.579 6
g Unknown site physical conditions 8.525 7
h Increase in site overheads 7.903 8
i Problems due to partners different practice 7.628 9
j Industrial disputes 7.535 10
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
68/97
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
69/97
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
70/97
D a t a A n a l y s i s a n d i n t e r v i e w
a n a l y s i s
C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k 62
NO. RISK FACTORSQuality Probability Rating
RII-
(1)Rank
RII-
(2)Rank
RII-
(3)Rank
1 Design failures3.02
52 2.050 20 6.201 10
2 Equipment and system failures2.30
013 2.150 19 4.945 15
3 New technology failures2.32
512 2.200 18 5.115 13
4 Estimation errors2.10
017 3.325 3 6.983 6
5 Accident/ Collision1.52
523 2.500 12 3.813 23
6 Site Location and access1.75
021 2.500 12 4.375 20
7 Inadequate program schedulingand tight program scheduling
2.875
3 2.975 5 8.553 2
8Design changes / Design
variations by client
2.45
09 3.475 2 8.514 3
9Hazards of environmental
regulations
1.55
022 2.525 11 3.914 22
10Incompetence of transportation
facilities
1.52
523 2.200 16 3.355 24
11 Increase in site overheads1.85
020 2.725 8 5.041 14
12 Industrial disputes 2.050 18 2.200 16 4.510 17
13Local firms incompetence and
low credibility
1.92
519 2.325 14 4.476 18
14 Materials shortage2.70
05 3.150 4 8.505 4
15Obsoleteness of building
equipment
2.35
010 2.000 22 4.700 16
16Poor quality of procured
accessory facilities
2.72
54 2.025 21 5.518 12
17 Poor quality of procured materials 2.700 5 2.300 15 6.210 9
18Problems due to partnersdifferent practice
2.350 10 2.700 9 6.345 8
19 Shortage in accessory facilities2.25
015 1.975 23 4.444 19
20 Shortage in skillful workers3.65
01 3.500 1
12.77
51
21Shortage in supply of water, gas,
and electricity
2.17
516 1.925 24 4.187 21
22 Subcontractors low credibility2.27
514 2.550 10 5.801 11
23 Unknown site physical conditions 2.475
8 2.750 7 6.806 7
24Unusual weather and force
majeure
2.50
07 2.925 6 7.313 5
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
71/97
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
72/97
D a t a A n a l y s i s a n d i n t e r v i e w
a n a l y s i s
planning stage. That will automatically lead owner to reduce quality to do his job
within his budget. Unknown site physical condition is ranked seventh (RII =6.806).
This is also impulsive risk at the planning stage occurring of this technical risk event
will influence quality of the project. Problems arising out of partners differentpractice also create impact to quality of the project. It is eighth ranked (RII= 6.345).
Poor quality of procured material is the 9 th ranked (RII= 6.201) risk event that could
impact on quality of the output. Tenth risk is the design failures. Failures due to
design will lead to impact on quality of output.
Based on the argument mentioned in section 4.2.1.2.1, multiplying the probability
and impact values might be misleading. This is achieved best by plotting the risk
probability- cost impact matrix (figure 4.5).
Figure 4. 5: Quality Significance of Technical Risk Factors
The matrix shows five of the risks to be high (probability >3 and cost impact>3). It
shows that the majority of the risks are medium (probability 2-3 and Cost impact
>2.5). There are two technical risks that have probability of less than two and risks
with cost impact less than 2.5. These are considered low.
4.3.1.2 PERFORMANCE IN CONSTRUCTION LIFE CYCLE
C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k 64
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
73/97
D a t a A n a l y s i s a n d i n t e r v i e w
a n a l y s i s
The performance in construction project life cycle analysis in figure 4.6 and table 4.9
illustrates the performance in each stage of the construction life cycle simply.
According to figure 4.6, construction stage of the construction life cycle is having
highest performance of technical risk.
Considering data set collected through the questionnaire survey to measure the
magnitude of performance level of risk events in construction life cycle, Cronbachs
alpha was calculated for each data set. The alpha values for data set using for the
analysis of performance of risk events in programming stage is = 0.959, planning
stage is 0.755, tendering stage is 0.777 and for the production stage data set = 0.949.
According to Nunnally and Bernstein (1978) as described in 4.2.1.2, they are reliable
data sets.
A careful look at Figure 4.6 confirms the argument that the highest magnitude or the
performance of technical risk in the construction life cycle is in the construction
stage. When comes to construction stage to the inception or the programming stage,
it is reducing.
Unusual weather and force majeure and shortage in skillful workers are having
highest magnitude at the construction stage (RII= 4.000). Second highest are
unknown site physical conditions and local firms incompetence and low credibility.
That is because such kind of technical risk events are having more probability of
occurrence at that stage. Moreover, third highest is design changes/ design variation
by client. Clients tend to do design changes and variation at this stage as they realize
the actual design requirements only at this stage.
According to table 4.9 and figure 6, it is clear that there are only several risk events
in the tendering stage, which are having high performance. Estimation errors, design
failures, inadequate program scheduling and tight program scheduling, design
changes, / design variations by client are that risk events.
Table 4. 9: Performance of risk events in construction life cycle
C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k 65
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
74/97
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
75/97
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
76/97
D a t a A n a l y s i s a n d i n t e r v i e w
a n a l y s i s
construction contracts as owners can place any risks to the contractor. Contractors
usually respond to these risks by increasing their contingency and markup, which
ultimately increase the contract price to the owner. Interviewed respondents indicatedthat risks are not allocated appropriately in the Sri Lankan construction industry.
The analysis of actual and expected risk allocations based on the questionnaire
survey results are presented in table 4.10 and figure 4.7. The table and figure denote
subjective analysis.
Moreover, considering the data set gained from the questionnaire survey for the
allocation of risk events among contracting parties, Cronbach's Alpha was
calculated for the data set. The alpha values for data sets taken for the analysis
(Annexure 05) are above than the value stated in section 4.3.1.1. Therefore, data
taken for the analysis are reliable.
In accordance with figure 4.7, the majority of the technical risk events allocated to
contractors. This is probably due to the culture and widespread use of traditional
contracts that places most of the risk on the contractor. Allocation of risk among
parties in the event of design failure is too high to the consultant. Even though figure
is showing that, most of the interviewed respondent pointed out that, the risk
allocation to consultant is not properly practiced in Sri Lanka. In the event of
consultant failure, there is no a remedial action. In such kind of situation usage of
personal indemnity assurance is very much low (less than 17%). It is clearly shown
by following figure 8. It is almost zero, where the consultant and client both are Sri
Lankan companies.
Risk allocation to the client is very much low according to findings of interviews. In
practical situation consultant, risk also has to be endured by the client in Sri Lanka.
Because contractor always try to price the risk, but there is a limitation. If he or she
price every risk, in the event of competitive tendering there is a probability of losing
it. Therefore, he may price most important risk events only.
C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k 68
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
77/97
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
78/97
D a t a A n a l y s i s a n d i n t e r v i e w
a n a l y s i s
Figure 4. 7: Risk allocation of technical risk factors
Figure 4. 8: usage of PIA
Most significant risk factor is the Accident/ collision to contractor, where majority ofrespondents are considered that the in the event of accident /collision, risk allocation
to the contractor is considerably high. According to table 4.10, it is high.
According to questionnaire survey findings and interviews findings consultant is the
person, who is having lesser allocation of technical risk.
Based on the questionnaire findings, design changes / design variations by client is
the technical risk having higher allocation to the client (RII= 3.700).
C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k 70
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
79/97
D a t a A n a l y s i s a n d i n t e r v i e w
a n a l y s i s
4.3.1.3.1 PROPER ALLOCATION OF TECHNICAL RISK IN CONTRACT
Proper contractual arrangements determine who is more capable of controlling
various specific risks. Generally, the local construction contracts mainly use
condition of contract to do it. Usage of condition of contract type is shown in figure
4.9. Considering the findings of the structured interviews, ICTAD is the most using
document as the condition of contract for the building projects, but interviewed
respondents pointed out that the usage of the type of document will depend on the
type of the client. Usage of ICTAD is 67% percentage. For the government project
they most of the time use ICTAD. However, for the foreign Clients have to use
FIDIC condition of contract.
Figure 4. 9: Type of condition of contract use in Sri Lankan building construction industry
However, interviewed respondents indicated that, allocation of technical risk
between consultant and client in a contract is very much low in Sri Lanka. In most of
the cases client has to suffer them. Because usage of condition of contract between
consultant and client does not much consider about the risk allocation. In addition,
they have argued that, effective allocation of technical risk among parties is a good
risk mitigation strategy.
4.4 REVIEW OF FINDINGS
Any construction work will be subject to some technical risks, such as changes in
design, equipment failure, shortage in skillful workers, material shortage, accident/
collision, etc. However, through this research it was attempted to forecast typical
C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k 71
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
80/97
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
81/97
D a t a A n a l y s i s a n d i n t e r v i e w
a n a l y s i s
Figure 4.11: Most Significant Risk factors performance in life cycle
Furthermore, figure 11 illustrates the performance of most significant technical risk
factors within the life cycle of construction project in Sri Lankan construction
industry. According to above argument, most significant risk factor is shortage in
skillful workers. It is regularly in the production stage. Moreover, according to figure
12, shortage of skillful workers is risk to contractor than other parties in the
construction industry. However, it is not much affecting to consultant but to some
extent affect to the client.
C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k 73
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
82/97
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
83/97
D a t a A n a l y s i s a n d i n t e r v i e w
a n a l y s i s
C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k 75
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
84/97
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
85/97
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
86/97
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
87/97
C o n c l u s i o n a n d R e c o m m e n d a t i o n
Apart from that there were seventeen other technical risk factors such as design
failures, accident/ collision, site location and access, etc. which were not as severe as
aforesaid factors, but when concerning risk managing approaches, these factors
should also be considered in total risk management strategy.
Based on the interview findings, it was able to figure out usage of type of condition
of contract and usage of PIA in Sri Lankan building construction industry. According
to interviewed respondents, risks were allocated more to the client ultimately.
Because, contractors risk is capable to be priced and consultant risk automatically
comes to client according to Sri Lankan practice.
This study is important as it sheds the light on the risks in a booming Sri Lankan
construction industry. Technical risk identification and assessment is an important
step in project risk management and shows the significance of several risks that are
present in the industry. This study lays the foundation to assists local companies in
negotiating their contracts as to the proper allocation of risks. This study also helps in
decision making regarding risk response planning and control.
Moreover, all of this mentioned critical technical risk factors more relevant to
quantity surveyor than other professionals in the building construction industry. That
is because, client quantity surveyor, consultant quantity surveyor or contractor
quantity surveyor most of the time try to give a monitory value for that particular risk
by predicting them at the initial stage. That would be the most efficient method of
mitigation of risk and minimizing the effect of the risk to the building construction
project. Therefore, the quantity surveyor needs to be more concerned about
especially critical risk factors.
5.2 RECOMMENDATION
Considering all facts above discussed and identified, the cost, time and quality
achievement of the building construction projects are effected by several critical
technical risk factors, which are uncontrollable or unforeseeable by the parties to the
C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k 79
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
88/97
C o n c l u s i o n a n d R e c o m m e n d a t i o n
contract at the initial stage. All those risk factors cannot be eliminated completely
and the best would be to minimize the occurrence and impact to the project
objectives by implementing proper mitigation process from initial stage with proper
coordination among parties. Moreover, using proper condition of contract among
parties can also manage the risk.
Through considering project perspectives, risk mitigation process can be decided
along these lines;
Whenever a project needs to consider more about the time then time
significant technical risk factors has to be taking in to account.
If quality is the most considerable project perspective, then quality significant
risk factors have to be taking in to account.
Where, the project having a limited budget cost. Cost significant technical
risk factors have to be taken into consideration.
Besides, commonly for any type of building construction project most criticaltechnical risk factors have to be taken into consideration.
It will lead to complete the building construction project by achieving all project
goals namely; within the time limit, within the budget limit, and with quality
achievement.
Further, it recommends, improving the knowledge on risk management
techniques and its applications; there should be a proper training or learning of
the risk management field which is important to practitioners in the industry
5.3 FURTHER RESEARCH
The research was carried out within building construction project, and same
research can be done to the civil construction projects.
C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k 80
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
89/97
C o n c l u s i o n a n d R e c o m m e n d a t i o n
The effectiveness of contingency in covering unforeseeable risk involvement in
building projects.
Suitability of risk handling tools in better recovery of risk, in the contractors
perspective.
Proper usage of condition of contact to handle construction risk.
C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k 81
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
90/97
R e f e r e n c e s
References
1) Adams, A.K., 2006. Expert elicitation and Bayesian analysis of construction
contract risk: an investigation. Construction management and economics, 24,
81-96.
2) Ahmed, S.M. and Azhar, S.A., 2004. Risk management in the Florida
Construction Industry. Challenge and opportunities for engineering
education, research and development 2-4 June 2004, Miami, Florida, USA.
Sustainable Environment, Track-Paper No. 077, 25(3), 601614.
3) Akintoye, A.S. and Macleod, M.J., 1997. Risk analysis and management in
construction.International journal of project management, 15(1), 31-38.
4) Akintoye, A.S. and Macleod, M.J., 1997. Risk analysis and management in
the construction.International journal of project management, 15(1), 31-38.
5) Al-Bahar, J.F., 1990.Systematic risk management approach for construction
projects. Journal of construction engineering and management, 116(3), 530-
538.
6) Andi, 2006. The importance and allocation of risks in Indonesian
construction projects. Construction management and economics, 24(1), 69
80.
7) Archbold, A.C., 2005. Managing the bottom line: risk management in
policing.International journal of police strategies & management, 28(1), 30-
48.
8) Bajaj, D., Oluwoye, J. And Lenard, D., 1997. An analysis of contractors
approaches to risk identification in new south wales, Australia. Construction
management and economics, 15, 363-369.
C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k 82
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
91/97
R e f e r e n c e s
9) Baker, S., Ponniah, D. and Smith, S., 1999. Risk response techniques
employed currently for major projects, Construction management and
economics, 17, 205-213.
10)Barber, R., 2005. Understanding internally generated risks in projects.
International journal of project management, 23(8), 58490.
11)Carter, R.L. and Doherty, N.A., 1974. Handbook of Risk Management,
Kluwer-Harrap Handbooks: London.
12) Chapman, R.J., 2001. The controlling influences on effective risk
identification.International Journal of project management, 19, 147160.
13) Chicken, J.C. and Posner, T., 1998. The philosophy of risk. Thomas Telford.
14) Cronbach, L. J., 1951. Coefficient alpha and the internal structure of tests.
Psychometrika, 16(3), 297-334
15) Dallas, M., 2006. Value and risk management. Blackwell: UK
16) Dhanasinghe, I., 2007. Risk allocation and risk handling of road project in
sri lanka . Unpublished Dissertations (BSc). University of Moratuwa, Sri
Lanka.
17) Edwards, R.J. and Browen, P.A., 1998. Risk and risk management in
construction: a review and further directions for research. Construction and
architectural management, 5(4), 339-349.
18) El-Sayegh, S.M., 2008. Risk assessment and allocation in the UAE
construction industry. International journal of project management, 26(1),
431-438.
19)Flanagan, R. and Norman, G., 1993, Risk Management and Construction,
Blackwell Science Ltd: Oxford.
20) Fong, S. W., 1987. Risk management. The Cost Engineer, 2, 12-16.
C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k 83
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
92/97
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
93/97
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
94/97
R e f e r e n c e s
41) Perera, K.B.D., 2006. Simulation modeling for time and cost overruns in
road rehabilitation projects in Sri Lanka. Unpublished Dissertations (BSc).
University of Moratuwa, Sri Lank.
42) Perry J.G. and Hayes, R.W., 1985. Risk and its management in
construction projects. Proceedings of institute of civil engineers, 78(1), 499
521.
[
43)Peter, D., (1997). Risk analysis and management for major construction
projects. Cobra 1997 [online], Available from: http://www. Rics-
foundationorg/aboutus.html
44) Poh, Y.P. and Tah, J.H.M., 2006. Integrated durationcost influence network
for-modeling risk impacts on construction tasks. Construction management
and economics, 24(8), 861868.
45) Pushpakumara, P.A.D., 1997. Managing the pricing risks and uncertainties
on below ground construction works in buildings. Unpublished Dissertations
(BSc). University of Moratuwa, Sri Lank.
46)Rahman, M.M. and Kumaraswamy, M.M., 2005. Assembling integrated
project teams for joint risk. Journal of construction engineering and
management, 23(4), 365375.
47) Rowe, W.D., 1977. An anatomy of risk. New York: Wiley.
48)Saunders, M., Lewis, P. and Thornhill, A., 2004, Research Methods for
Business Students, 3rd
ed, Singapore: Pearson Education Pte Ltd.
49)Senarathne, S., 2005. A knowledge-based approach to managing project
change in the construction phase within collaborative ream settings.
Unpublished Thesis (PhD). University of Salford: UK
50) Shen, L.Y., 1997. Project risk management in Hong Kong. International
Journal of project management, 15(2), 101105.
C o n s t r u c t i o n R i s k : F u r t h e r C o n s i d e r a t i o n o f T e c h n i c a l R i s k 86
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
95/97
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
96/97
-
7/29/2019 TECHNICAL RISK FACTORS IN BUILDING CONSTRUCTION.doc
97/97
A p p e n d i x
Appendix