    Tender No.: 11000058-HB-11370: VIS Painting for Bharatpur Depot (Annex I,II & III)

    Annexure I

    PROJECT DETAILS & TECHNICAL SPECIFICATIONS :

    It is proposed to paint all facilities, pipelines, structures, equipment, Sheds, buildings etc., as perVisual Identity standard at HPCL, Bharatpur Depot situated at the address given below:

    Address of the site :

    HINDUSTAN PETROLEUM CORPORATION LTD.BHARATPUR POL DepotBHARATPUR MATHURA ROADDHORMUIBHARATPUR 321025Ph: 05644-238407 , 238359

    The contractor shall arrange all materials, equipment, scaffolding, Labour, tools etc required forexecution & completion of the job.

    The tenderers are required to go through the tender document thoroughly and carefully andoffer their most competitive rates for the job. They are also advised to visit the site if requiredbefore offering their quotation.

    NOTE:

    The work has to be carried out in a operating location. The contractor has toobtain all necessary work permits for executing the jobs. The contractor is

    required to strictly follow all the prevailing safety (like safety belts, Helmets,gloves, protection glass etc.) & statutory regulations that are being followed at thelocation.

  • 7/27/2019 Technical Specification PAINTING & Special_Final(1)

    2/13

    Tender No.: 11000058-HB-11370: VIS Painting for Bharatpur Depot (Annex I,II & III)

    TECHNICAL SPECIFICATIONS

    Codes to be followed for painting :

    IS 384 : 1964 - Brushes for painting.IS 1477 : Code of practice for paintingIS 2074 : Specification for ready mixed paint, primer.--------------------

    1.0 SCOPE

    These specifications cover the minimum requirements of all material, paint, equipment,consumables, utilities, application including all labour, supervision, inspection and testsof performance of all operations and incidentals necessary for painting of pipelines, steelstructures, buildings as per detailed specifications given below.

    2.0 SURFACE PREPARATION

    Surface preparation is the core of all painting jobs & hence due importance to be givento surface preparation. The surface preparation shall be done by the party at his cost bymaking full use of all mechanical tools by manual chipping and wire brushing andcleaning with sand paper to remove loose rust and scale to St.2 of Swedish standardSIS 05 5900. All the surface should be thoroughly dusted down before applying primer.The cleaned surface shall not be kept exposed to atmosphere for more than two hours(Particularly at night time when humidity percentage is more in atmosphere).

    3.0 PAINTS:

    a) All primer/paints shall be strictly in accordance with those given in the tender specificationsfor painting & general specifications for painting and no deviations shall be accepted.

    b) When ever necessary, the paints may be tested according to IS specifications (latest editionIS 101 ) for various chemical properties like consistency, spreading rate, time colour fastenersto light hardness, flexibility, adhesion, water resistance etc. at approved laboratory and as perthe directions of the site engineer regarding the frequency of the test etc. Even if the partyprovides manufacturing test certificates of each batch showing all the above details, theEngineer in charge may advise the party get the paints test at his discretion.

    c) The contractor shall adhere to paint manufacturers instruction strictly and all coats shall be ofuniform thickness as specified.

    d) All paints shall be of Ist quality Asian / Berger / Nerolac/Jenson & Nicholson/ICI makeonly. However, final discretion to use a particular brand of paints shall remain with HPCLdepending upon performance, past experience and availability of the same.

    4.0 SCAFFOLDING

    Scaffolding has to be in steel, arranged by the contractor at his own cost for carrying outentire painting jobs at all height and provide all facilities for proper inspection of surface

  • 7/27/2019 Technical Specification PAINTING & Special_Final(1)

    3/13

    Tender No.: 11000058-HB-11370: VIS Painting for Bharatpur Depot (Annex I,II & III)

    at various stages. Material has to be erected as per safe methods. Ropes and guywires shall be used for tying etc. The scaffolding shall be of steel and shall notendanger the painter. Scaffolding shall be sufficiently away from the tank shell/ surfaceto be painted so as to enable the painter to work with ease. The scaffolding shall beremoved by the contractor promptly after completion of the work.

    5.0 PRECAUTION AGAINST FIRE

    Paints and thinners leave vapors which are inflammable. Hence, adequate precautions shallbe taken in the form of screens, covers etc against fire while painting, mixing of paintingwork is in progress.

    6.0 DRYING TIME

    The time gap of 24 hours for each coat of paint is the minimum and if any deviationbecomes necessary due to any reason, paint manufacturers shall be consulted and theirinstructions followed only with the approval of the site-in-charge (HPCL).

    7.0 USE OF THINNER PAINTS

    The use of thinners shall be limited strictly to the paint manufacturers instructions. Eachcoat of primer and finishing coats shall be applied only after ensuring that the paint is freefrom dew or moisture and the surface is hard dry and free from dust.

    8.0 APPLICATION OF PAINT BY AIRLESS SPRAY GUN OR BRUSH

    The contractor shall engage only skilled workmen for painting work. The application of painton Tanks surface shall be made strictly by airless spray gun. The application of paint canbe made by brush in case of inaccessible area or paint application area is small. Thebrushes used shall be of best quality suitable for painting. The paint brush shall not be

    dipped deep into the paint as the bristles get overloaded and the heels gets filled up withpaint and thereby loses flexibility. The brushes shall be dipped to only of the total lengthof the bristles. After the brush is initially dipped, the end shall be wiped against the walls ofthe painting. The brush shall be held at an angle of 45 degree to the vertical surface andseveral light strokes applied in the area to be painted so as to first transfer the paint on bothturned 180 degrees in order to ensure that the paint on both the faces of the bristles isutilized completely. The paint is then to be spread with gentle pressure so as to be ensuredthat the ends and not the sides of the bristles come into contact with the surface duringpainting. The paint shall be applied first using vertical strokes until the surface is coveredand then brushed crosswise for complete coverage with light strokes so as to smooth outlaps and brush marks and finally laid off with vertical strokes.

    9.0 During painting, every time after the paint has been worked out of the brush bristles or afterthe brush is unloaded, the bristles of the brush (which are drawn together due to highsurface tension of the small quantity of paint left in between the bristles) shall be opened upby stroking the brush against a portion of the unpainted surface with the end of the bristlesheld at right angles to the surface so that the bristles thereafter will collect the correctamount of paint when dipped again into the container.

    10.0 A new bristle brush shall be properly conditioned by suspending it in raw linseed oil for aperiod of 24 hours. The oil soaks into the bristles which makes it further impervious to paint

  • 7/27/2019 Technical Specification PAINTING & Special_Final(1)

    4/13

    Tender No.: 11000058-HB-11370: VIS Painting for Bharatpur Depot (Annex I,II & III)

    pigments. Before use, the linseed oil shall be removed from the brush by washing it in athinner compatible with the paint and subsequently used. After each days work the brushshall be cleaned in mineral turpentine oil or any other thinner compatible with paint toremove all paint and pigments from the bristles and the heel of the brush. If the brushes areto be re-used the next day, they shall be hung in a thinner or linseed oil in a container. Thebrushes shall not be allowed to stand on bristles.

    11.0 PAINTING OF PIPELINES

    Brushes : The brushes used in painting shall confirm to IS:384-1964.

    Primer : as mentioned in the tender document.

    Only superior grade paints of approved make, quality and conforming to above specificationsshall be used.

    Surface Preparation :

    Before painting, the surface shall be cleaned thoroughly leaving it free of all scales, rust, grease,oil coating, moisture and other matter. Any protrusions of weld metal etc. shall be ground bygrinding machine to get smooth surface. Heavy deposits of grease and oily material if any shallbe removed by a suitable solvent wash before painting.

    Painting :

    (a) The cleaned surface shall not be kept exposed to atmosphere for more than two hours.(Particularly at night time when humidity percentage is more in atmosphere).(b) The surface shall be applied with the first coat of primer of approved make, as given in the

    tender document, soon after cleaning and before any visible rusting occurs.(c) ) In all one coat of Self priming surface tolerant Epoxy high build coating with

    Polyamido amine catalyst primer of approved make of 100 microns DFT and two coats offirst quality Acrylic Polyurethane of total of 80 microns DFT ( 2 x 40 microns), paint asgiven in the tender document shall be applied. The finish coats of Poly Urethane paint, as givenin the tender document, shall be applied only after the primer coat is dried.

    (d) The paint coats shall be smooth and even and shall not show any trace of brush or unevenmarks. If a uniform shining surface can not be achieved by two coats, contractor shall provideextra coats till the required surface is achieved at no extra cost to HPCL.

    The following colours shall be painted for different pipelines and the fittings :

    a) All above ground decanting product pipelines, the flanges on product pipelines shall be

    painted with first quality paint of shades as described / provided in this tender.

    b) All the tank appurtenances viz. delivery, receipt water drain off etc. will be identified within 4long x 1.5 thick size lettering. The tank No., product, capacity in litres, size etc. will beidentified using approved shade.

    c) The water & foam lines shall be painted with first quality PU paint of approved make.

  • 7/27/2019 Technical Specification PAINTING & Special_Final(1)

    5/13

    Tender No.: 11000058-HB-11370: VIS Painting for Bharatpur Depot (Annex I,II & III)

    d) All above ground product pipelines, the flanges on product pipelines shall be painted with firstquality paint of shades as described / provided. White paint shall be applied on white oillines. Black oil lines shall be painted black. Colour Code bands shall be painted on thepipelines as per Industry Quality Control Manual (IQCM). Rate quoted shall be inclusiveof the same. No separate payment for painting bands.

    Colour code bands :Latest specifications of Colour Bands as per IQCM shall be obtainedfrom HPCL site engineer

    e) Name of the product along with the flow direction arrow mark as per the ICQM standard atspecified places like bends, change of direction and other places as directed by the EIC.

    12. PAINTING OF EQUIPMENTS :

    The job includes painting of all the DG sets, Fire Engines, transformer,pumps, Product/Foam pumps motors loading arms, flowmeters and any other equipment advised byengineer I/c as per the colour codes mentioned in this attachment for each equipment.

    Rate to include the cost of scaffolding, surface preparation to make the surface free from dust ,fungus algae , moss & other foreign matters ,materials and labour, wastages, mixing as permanufacturers specifications.

    13. PAINTING OF STRUCTURES & PANELS :

    The job includes painting of all the structures of sheds like gantry, pump house, structuralpedestals, stair case, railings, pillars, walkway plat farm grills, channels, angles,electricpoles,towers, electrical stuctures, electrical panels etc. as per the colour codesmentioned in this attachment for each equipment.

    Rate to include the cost of scaffolding, surface preparation to make the surface free from dust ,

    fungus algae , moss & other foreign matters ,materials and labour, wastages, mixing as permanufacturers specifications.

    14.0 SPECIFICATION FOR PAINTING OF BUILDINGS, SHEDS & BOUNDARY WALL:

    14.1 INTERIOR PAINTING OF BUILDINGS:

    It includes cleaning the buildings completely in all respects and application of 2 coats ofcement primer of approved colour & approved manufacturer.

    Providing and applying 2 coats of first quality Acrylic emulsion (for interiors of buildings) ofapproved manufacturer and of required shades as approved by HPCL and of required shades

    on all surfaces and heights to give an even shade, surface evenness after thoroughly brushingthe surface free from mortar dropping, etc.. Cost includes all.

    14.2 EXTERIORPAINTING OF ALL BUILDINGS, WALLS, PLATFORMS :

    Cleaning & Painting of Buildings, AC Sheets of Sheds External & Internal , RCC Reservoir,Dyke Wall, Boundary Wall and any other area as advised by the Officer Incharge.

  • 7/27/2019 Technical Specification PAINTING & Special_Final(1)

    6/13

    Tender No.: 11000058-HB-11370: VIS Painting for Bharatpur Depot (Annex I,II & III)

    (a) application of 1 coat of Acrylic exterior primer of approved colour & approvedmanufacturer.(b) Providing and applying 2 coats of first quality 100% Acrylic exterior emulsion of approvedmanufacturer and of required shade.

    15.0 COLOUR SPECIFICATIONS :

    15.1 BUILDINGS, INETERIOR : Off white ( Interior grade acrylic emulsion ) of AsianPaints(APEX) / Paints ( Whether coat)/ ICI/Nerolac.

    15.2 BUILDINGS, EXTERIOR : 100 % acrylic emulsion as per colours mentionedbelow.

    i. Fins & Chajjas : Georgia clay of Asian paints ( APEX )/ Ming red of BergerPaints ( Weather coat )/Equivalent shade in ICI/ Nerolac.

    ii. Main structure : Moon slice of Asian Paints ( APEX )/ Whipped cream of Berger Paints( Weather Coat )/ Equivalent shade in ICI/ Nerolac

    15.3 DYKES WALLS, CONCRETE PEDASTALS EXTERIOR : 100 % acrylic emulsionwhite and border as per VI standard.

    15.4 AC SHEET INTERNAL & EXTERNAL :

    i) Acrylic exterior primer & 100% Acrylic exterior emulsion white of AsianPaints(APEX) / Paints ( Whether coat)/ ICI,Nerolac.

    ii) Blue bands on sides : French Blue Colour 0112 or equivalentmatching with ACM Colour

    15.5 PRODUCT PIPE LINES, LOADING ARMS :

    i) Self priming surface tolerant Epoxy high build coating with Polyamido aminecatalyst & PU White,

    ii) RCC supports : Bottom1/4 Jet Black,upper Acrylic whiteiii)Loading arms, Flow meters, Strainers/ Air eliminators,Valves, colour bands and

    direction arrows as per applicable colours for each product.

    MS :Dark Orange No.591 ( IS-5 ),HSD : Oxford blue No.105 ( IS- 5 ),SKO : Golden Yellow No.356 ( IS-5 )ETHANOL : Dark Violet No.796 ( IS-5)Lettering on Loading arm : Jet Black

    15.6 PRODUCT PUMPS :

    I) Motors of product pumps : French Blue No. 166 ( IS-5 )II) Coupling Guard & pump : Applicable colour code for respective

    productIII) Motor concrete base : Dark Admiralty grey No.632 ( IS-5 )IV) Civil foundation : Jet Black

  • 7/27/2019 Technical Specification PAINTING & Special_Final(1)

    7/13

    Tender No.: 11000058-HB-11370: VIS Painting for Bharatpur Depot (Annex I,II & III)

    15.7 WATER PIPE LINES : Grass green No.218 ( IS-5 )

    15.8 FIRE HYDRANT PIPE LINES/ENGINES :

    i) Pipe Line/Fire engine : Fire red No. 536 ( IS-5 )ii) Fire engine control panels : Fire red No. 536 ( IS-5 )iii) Fire Engine fuel tanks,lines : French Blue No.166 ( IS-5)iv) Structural support : Jet Blackv) RCC supports : Bottom1/4 Jet Black,upper Acrylic whitevi) Monitors, double hydrant points Fire hose boxes :

    Body Fire red No. 536 ( IS-5 ),Valve wheels Jet BlackGate Valves PU whiteStructural support Jet black

    15.9 FOAM PIPE LINE/FOAM TANK

    i) Pipe line , Tank Body : Golden yellow No. 356 (IS-5)ii) Valves : PU whiteiii) Structural support,Handle,Wheels : Jet Black

    iv) RCCsupport : Jet black for bottom of the block and whitewash for the upper portion.

    15.10 DG SETS :

    i) Engines and alternators : Smoke grey No. 692 (IS-5)ii) Coupling guard : satin blue No. 177 (IS-5)

    iii) Electric panel : Silver greyNo. 628 (IS-5)iv) Fuel tank & Pipe lines : French Blue No. 166 (IS-5)v) Radiator : Jet blackvi) Civil foundation : Whitevii) Exhaust pipe : Alluminiumviii) Exhaust piping supports : Smoke grey No. 692 (IS-5)ix) Civil Foundation : White

    15.11 MCC PANELS, TRANSFORMER :

    i) MCC panels, Transformer : Silver Grey No. 628 ( IS-5 )ii) Structural supports for panles and cables : Jet black

    iii) Chequered plates for cable trench : Jet Black

    15.12 STRUCTURES :

    I) Pillars & Angles, light towers, structures : Smoke Grey ( Shade 692 )II) Stair Case, Railings & Walkway grills : Jet BlackIII) Strip on staircase edge, swing lader edges : Reflective Fire red No. 536 ( IS-5 )

    15.13 LETTER PAINTING ON AG TANKS & OTHERS :

  • 7/27/2019 Technical Specification PAINTING & Special_Final(1)

    8/13

    Tender No.: 11000058-HB-11370: VIS Painting for Bharatpur Depot (Annex I,II & III)

    The letters to be painted in black on the second streak from the bottom near the stair case.

    Size of letters to be painted on the shell of A/G storage tanks as below:

    Tank number : 230 mm ht ( 9 )

    Name of product : 150 mm ht ( 6 )Tank capacity : 80 mm ht ( 3 )Size of tank : 80 mm ht ( 3 )Safe filling height : 80 mm ht ( 3 )Date painted : 80 mm ht ( 3 )Date Commissioned. : 80 mm ht ( 3 )Date of Calibration : 80 mm ht ( 3 )Date of Hydro testing : 80 mm ht ( 3 )Due Date of Cleaning : 80 mm ht ( 3 )Asset ID : 80 mm ht. ( 3 )

    Letter painting on other places shall be done as per the advice from officer In charge of HPC.

    Payment shall be made on physical measurement of the area painted in square meters.

    . End of Annexure I ..

  • 7/27/2019 Technical Specification PAINTING & Special_Final(1)

    9/13

    Tender No.: 11000058-HB-11370: VIS Painting for Bharatpur Depot (Annex I,II & III)

    Annexure II

    GENERAL INSTRUCTIONS

    1. Painting shall follow immediately after satisfactory surface preparation /manual cleaning.

    2. No painting shall be carried out when there is a danger of dew or moisture or high humidconditions on the surface to be painted.

    3. Tools used shall be clean and not worn out.

    4. The paint in drum shall be mixed thoroughly and proper mixing shall be done in case oftwo pack systems as per manufacturers specifications before application. The drumshall be inspected for the correct grade and to see that no sediments is left in it.

    5. In case paint is thickened because of evaporation of solvents, its viscosity shall be

    adjusted as recommended by the paint manufacturer.

    6. Each coat shall be inspected and allowed sufficient drying time to make the surface harddry but not excessive before applying the next coat. Manufacturers specifications fordrying time shall be adhered to strictly.

    7. Each individual coat shall be properly applied and shall be free from dust etc.

    8. BASIS OF MEASUREMENT AND PAYMENT

    As per calculation based on physical measurements.

    9. INSPECTION AND APPROVAL OF SURFACE

    After each coat, surface would be inspected by HPCL Engineer and only after obtainingclearance from him, in writing, next coat would be applied. HPCL Engineer at his owndiscretion, can ask the contractor to arrange the visit of authorized representative of paintmanufacture for inspection of the surface and contractor would be required to arrange thesame, at no extra cost, as per the instructions of HPCL Engineer. If contractor fails toarrange the visit of paint manufacturers representative, HPCL may arrange the same at therisk and cost of contractor. If the surface does not meet the specified requirements, thesame shall have to be rectified by the contractor, free of cost.

    The DFT for a particular surface/pipeline length/structural/pipeline fittings/tankappurtenances would be calculated by taking the average of readings as per the solediscretion of HPCL Engineer. If during inspection, DFT specified is not found on paintedsurface, the contractor shall provide additional coat to make up the deficit in DFT, at noextra cost. Only sealed paint tins to be brought at the site. The party is supposed to maintainan inspection book at the site . Job progress to be written on the same & to be broughtevery day before taking out the permit.

  • 7/27/2019 Technical Specification PAINTING & Special_Final(1)

    10/13

    Tender No.: 11000058-HB-11370: VIS Painting for Bharatpur Depot (Annex I,II & III)

    10. OTHER TERMS AND CONDITIONS :

    10.1. The Contractor should provide sufficient manpower for carrying out the job awarded. Theworkmen engaged by the contractor shall be deemed to be under the employment of thecontractor and not that of corporation.

    10.2 Contractor shall comply with all the provisions of labour laws and get the ESI, EPFcoverage for the employee and confirm to all statutory requirements as stipulated by theGovernment. If the company is required to pay any amount to the contractors employees underany law, the same will be recovered from the contractor bills.

    10.3 The Contractor should provide full address and arrange Police verification for thepersonnel/workers employed by him for the job & produce to HPCL.

    10.4. The contractor and his workmen should use PPE like safety shoes, helmets, gloves etcand follow all safety practices at the location. The contractor is fully responsible in all respects.

    10.5. The contractor has to obtain photo Identity cards from the depot for self and all the

    contract workmen engaged by him and wear photo Identity cards while carrying out the jobinside the premises.These passes are only valid for working within the HPCL premises andshould not be used for any other purpose or out side HPCL.

    10.6. The contractor and his workmen shall strictly adhere to the safety practices, rules andregulations prevalent in the corporation, HPCL reserves the right to ask the contractor toremove/ replace any of his employees in case of misbehavior/ non working as desired.

    10.7. Any act of indiscipline misconduct, theft or pilferage by any employee of the contractorshall be viewed very seriously and HPCL have the rights to terminate the contract forth andclaims damages.

    10.8 If the Contractor fails to undertake the work satisfactorily, HPCL reserves the right to re dothe work for which there will be no extra payment.

    10.09 If the party does not follow the given schedules or any delay in carrying out the jobHPCL shall get the job done through any other party and the expenses incurred by thecorporation shall be recovered from the contractor.

    10.10 The contractor is responsible for any negligence, default or failure at any time on the partof the house keeping contractor, to perform, carry out observe any of the terms and conditionshereof/and/or if the Housekeeping contractor shall become insolvent or bankrupt or enters intoany composition or agreement with his creditors, this agreement shall stand terminated at once.

    10.11 The job shall be carried out only during normal working hours of the depot and theworkmen have to leave the depot premises once the day's job is completed and should notloiter inside the depot without the prior permission from HPCL officer.

    10.12 If any accident or damage to property/life etc. arises by reasons of any act of negligenceof contractor or contractor's men/default or noncompliance of any terms and conditions ofstatutory or rules and regulations applicable within HPCL premises, the compensation has tobe paid by the contractor. Contractor shall agree to keep HPCL indemnified and will be liable

  • 7/27/2019 Technical Specification PAINTING & Special_Final(1)

    11/13

    Tender No.: 11000058-HB-11370: VIS Painting for Bharatpur Depot (Annex I,II & III)

    to pay compensation towards all claims whatsoever inclusive of damages / costs or otherwisearising from injuries or alleged injuries or death of a person whosoever ( including HPCL's representatives and employees ) or damages or alleged damages to third party's propertyarising out of any accidents.

    10.13 All terms and conditions as per GTC are applicable in addition to the above.

    . End of Annexure II ..

  • 7/27/2019 Technical Specification PAINTING & Special_Final(1)

    12/13

    Tender No.: 11000058-HB-11370: VIS Painting for Bharatpur Depot (Annex I,II & III)

    Annexure III

    SPECIAL TERMS OF CONTRACT

    (SPECIAL CONDITION OF CONTRACT SHALL BE READ IN CONJUNCTION WITH

    GENERAL TERMS AND CONDITIONS OF CONTRACT)

    1. PRICE :

    The rates offered shall be inclusive of taxes, charges for mobilization ofmen/material, steel pipe scaffolding etc. complete for carrying out the job. In case therates are exclusive of the same, the vendors have to quote all charges specifically.No extra payment shall be made other than the quoted rates.

    The rates shall be firm till completion of supply. No escalation is allowed.

    'C' form will not be given by HPCL, hence rate to be quoted without 'C' form.

    2. COMPLETION PERIOD :

    The entire scope of work should be completed within 3 months from the date of LOI /PO.

    The party has to submit a schedule details of time limits for each of Pipelines,structures, equipment, buildings etc. before beginning of the work and shalladhere to the same.

    3. PAYMENT TERMS:

    Payments will be made against Running Accounts bills certified by the Owner's Engineer-in-Charge/Site-in-

    Charge within 15 days from the date of receipt of the bill. The payment shall be credited to thecontractor's account through electronic mode (e-payment).Payment of final bill shall be made within 30 days from the date of receipt of the certified bill by the DisbursementSection of the owner.Partial payment is allowed.

    4. OFFER VALIDITY :

    Should be 90 days from the due date / extended due date of tender.

    5. DISTRIBUTION OF QUANTITY :

    The entire quantity of the items shall be offered to the L1 bidder.

    6. SECURITY DEPOSIT:

    The contractor who is awarded the contract shall be required to submit a security depositof 1% of the PO value in the form of account payee crossed Demand Draft in favour ofHPCL, payable at Jaipur. The security deposit will be refunded to the contractor withoutinterest 12 months after satisfactory completion of the job.

  • 7/27/2019 Technical Specification PAINTING & Special_Final(1)

    13/13

    Tender No.: 11000058-HB-11370: VIS Painting for Bharatpur Depot (Annex I,II & III)

    7. LIQUIDATED DAMAGES:

    The liquidated damages shall be initially at the rate of 0.5% (half percent) of the totalcontract value for every week of the delay subject to a maximum of 5% of the totalcontract value.

    The final calculation of LD shall be on the value of the unexecutedportion/quantity of material as on the CDD ( Contractual Delivery Date ) /Completion date.Other sub- clauses are applicable as per GTC.

    8. DEFECT LIABILITY PERIOD :

    The job done made against this order shall be fully guaranteed against any defects /poor workmanship / inferior quality etc. for a period of 12 months from the date ofcompletion of the job. During this period the contractor will arrange to rectify/ redo thejob at the places identified In case the contractor fails to do so HPCL reserves the rightget the job done by any other party and the cost towards the same shall be charged tothe contractor.

    9. MANUFACTURERS GUARANTEE :

    Contractor & Paint Manufacturer, whose paint party intend to use, will have to give jointGuaranty for painting of structural paintings like tanks, pipelines, gantry structure etc fora period of 4 years after defect liability period on Rs.100/- Stamp paper inthe prescribed format which shall be filled & submitted on award of contract.

    (Building painting is excluded from this guarantee)10. WATER & POWER :

    Water & Power required for the work and workmen shall be arranged by HPCL.

    11. WATCHING & LIGHTING :

    The contractor shall provide and maintain at his own expense all lights, guards, fencingand watching when and wherever deemed necessary by the Site In charge for protectionof the works or for the safety and convenience of those employees on the works orpublic.

    All the terms and conditions are applicable as per GTC.

    . End of Annexure III ..